-
Mr. Justice Moore delivered the opinion of the Court.
We will refer to the parties as follows: to The Western Colorado Power Company as Western; the Public Service Company of Colorado as Public Service; the
*265 Public Utilities Commission as the Commission; and the Colorado-Ute Electric Association, Inc. as Colorado-Ute.On May 11, 1962, Colorado-Ute filed an application with the Commission for a “Certificate of Convenience and Necessity.” The object of the application was to permit Colorado-Ute to construct near Hayden, Colorado, a steam electric generating plant with a nominal rating of 150,000 kilowatts, together with associated transmission lines and related facilities necessary to deliver power to certain new customers it sought to serve at wholesale. On June 14, 1962, Colorado-Ute filed a petition for an order of the Commission authorizing it to execute notes payable to the United States of America in an amount not to exceed $22,876,000 and mortgages to secure the notes in order to finance the project.
Public Service and Western filed protests in opposition to Colorado-Ute’s requests and the matters were consolidated for hearing. Protests to those applications which were filed by Public Service and Western generally alleged that each was a public utility subject to the jurisdiction of this Commission engaged, among other things, in the generation, transmission and distribution of electric power and energy at wholesale and otherwise throughout various areas of the State of Colorado; that all or a portion of the lines, plant, and facilities proposed to be constructed by Colorado-Ute would cause physical and uneconomical duplication of the lines, plants, and systems of the companies which had been lawfully constructed and dedicated to the public use; that the companies then, and for many years past, had maintained electric generating facilities and transmission lines and related facilities adequate and sufficient to meet all present and future needs of their customers and service areas, and held themselves out as ready, willing and able to render wholesale electric service to Colorado-Ute or any of its members; that there did not exist any need nor necessity for the con
*266 struction of the proposed plant and facilities of Colorado-Ute and that if such construction was authorized by the Commission it would result in substantial damage to the companies and their electric consumers.Subsequent to hearing, the Commission entered its order authorizing the construction of the Hayden plant and the financing thereof, but denying authority to construct certain of the facilities originally requested. Western and Public Service thereafter commenced certiorari proceedings in the district court, and from the judgment therein entered, affirming the Commission’s decision, they bring writ of error here.
Colorado-Ute is an incorporated rural electric cooperative association engaged in generating and transmitting electric energy as a wholesaler. It proposes to sell electric energy to various customers it denominates “members” as well as to the Bureau of Reclamation, a nonmember. It further proposes to dedicate its facilities to whatever use the public convenience and necessity require, including the wheeling of power to protestants Public Service and Western. It is federally financed by the Rural Electrification Administration under the Rural Electrification Act of 1936 (Title VII, USCA 901). Eleven of its members are “distribution members” and distribute electrical energy directly to their users. Of the two other members, the Arkansas Valley G & T generates and transmits energy for its three “distribution members,” and the Salt River Project Agricultural Improvement and Power District provides both electric and water service in the area surrounding Phoenix, Arizona. Salt River is not a cooperative but is a quasi-governmental organization incorporated under the laws of the State of Arizona.
Both Public Service and Western have been rendering electric service in Colorado since long prior to the time Colorado-Ute was first incorporated or ever constructed any generation and transmission facilities. Western serves in southwestern Colorado in the general area
*267 from Durango to Paonia, Colorado, and Public Service serves in a large area of the eastern slope of Colorado, including Denver, as well as in portions of western Colorado such as the San Luis Valley, Grand Junction, Rifle, and other specific areas within the state.On this writ of error, contentions of Western and Public Service fall into three general categories: (1) That Colorado-Ute did not prove the need, demand, or necessity required by the law of public convenience and necessity for power to be provided by the Hayden Plant; (2) that the financial arrangements of Colorado-Ute with the Rural Electrification Administration are illegal; and (3) that numerous errors of an evidentiary, procedural, and administrative nature were committed by the Commission, all to the prejudice of Western and Public Service.
The first category consisted of six sub-categories, each of which, it is said, points to error because the action of the Commission, and the trial court in affirming the Commission, contravened the fundamental concept of public utility law relating to public convenience and necessity. In this respect it is asserted: (1) That the evidence established that proposed new customers of Colorado-Ute already had an adequate power supply and that these customers would merely change their source and commence taking their power from Colorado-Ute; (2) that the construction of the plant would duplicate service made available by Western and Public Service as well as other electric suppliers presently rendering such service; (3) that the estimates of power costs submitted by Colorado-Ute found no support in the evidence; (4) that the generation and transmission of energy at less cost, assuming the record established such fact, is not a factor in establishing public convenience and necessity where reliance upon cheaper energy as basis for certification would be destructive of the concept of regulated monopoly; (5) that it would not be in the public interest to permit the construction
*268 of the plant where it would put Colorado-Ute in a debt position of more than 100%; (6) that the Commission erred in receiving evidence concerning alleged benefits which would accrue to the Colorado River Basin fund as a result of the construction of the plant where the reception of such evidence was based upon the construction of a 600,000 k.w. plant and basing its decision thereon when the application was for a plant of only 150,000 k.w.The Commission (by a two to one vote) found that public convenience and necessity demanded the construction of the Hayden Plant and its related facilities. This determination is the subject of attack by writ of error in this court. The record consists of some eight thousand pages with over twenty-five hundred pages of testimony. One hundred and twenty-four exhibits were offered. It would unduly lengthen this opinion to discuss in detail each facet of the evidence presented, and it is not necessary to do so.
The record discloses that the Colorado-Ute was organized in 1941 by a group of rural electric distribution associations on the Western Slope, but remained inactive for some years. In 1952 Colorado-Ute was reorganized, and it obtained a loan from the Rural Electrification Administration to construct transmission lines and a generating plant to supply the electric requirements of its then members. Upon the completion of the construction of this plant, known as the Nucía plant, Colorado-Ute commenced serving, on a wholesale basis, four distribution cooperatives located in the southwestern portion of the state. At the time of the hearing before the Commission there was then pending an application by Colorado-Ute to commence serving a fifth member located near Grand Junction, Colorado.
The alleged purpose to be served by the construction of the Hayden plant is to supply the electric requirements not of its five members but of thirteen members. This would have the effect of making Colorado-Ute the
*269 wholesale supplier of electric energy to a large portion of the State of Colorado, as well as to a small portion of the State of Wyoming and the State of Utah, and a large supplier to the Salt River Project in Arizona. Each of these eight potential new customers of Colorado-Ute is now receiving service from other sources, and the existing Nucía Plant of Colorado-Ute is adequate to serve the requirements of the five earlier members. It is thus apparent that Colorado-Ute seeks to commence rendering electric service on an expanded basis in areas it has not heretofore served, to customers it has never before served, and to customers and in areas where electric service is being supplied and is available from other existing sources.Wholesale electric service to many of the proposed new distribution cooperative customers of Colorado-Ute was for many years supplied by other utilities in the area, and later by the Bureau of Reclamation, and all parties to this proceeding are distinctly in the wholesale electric business. Arkansas G & T is an organization similar to Colorado-Ute and supplies wholesale electric service to three distribution cooperatives. Arkansas Valley obtains its power by purchase from municipal electric plants and from its own generating plant located near Canon City. This, in turn, it wholesales. The effect of the Commission’s decision is to substitute Colorado-Ute as the source of supply for all of these proposed new members. For instance, those receiving wholesale service from the Bureau of Reclamation will terminate such purchases; those proposed new customers which have generating plants will dispose of those plants ■by one means or another; and those new customers which purchased from municipalities will no longer do so. Arkansas G & T, which only recently completed the construction of its Canon City generating plant, will no longer obtain any power from its own plant but instead will purchase from Colorado-Ute.
*270 Although there was much conflicting testimony with respect to the ability of the Bureau of Reclamation to continue meeting the wholesale requirements of the proposed new members of Colorado-Ute, all three Commissioners concurred in a finding that Bureau power — the existing source of supply of many of these cooperatives — was adequate for the foreseeable future. In addition the record clearly reflects that the Arkansas G & T plant is more than adequate to meet the anticipated demands of its customers for a considerable period of time. It is also shown by the record that Public Service and Western have adequate generating facilities with which to meet the demands of any wholesale requirements in their respective areas should existing sources prove insufficient.Under these circumstances, it is apparent that the generating capabilities of existing electric suppliers in the State of Colorado are more than adequate to supply increased electrical needs without the addition of the Hayden plant, which was to be constructed only for the purpose of providing service to substitute for that already being rendered.
Confronted with the fact that there was no need for Colorado-Ute to expand its operations to serve customers already being served, the two concurring Commissioners evolved a theory that such new customers could pick and choose between (1) continuing service from existing suppliers, (2) purchasing wholesale requirements from certificated investor-owned utilities, or (3) purchasing from Colorado-Ute if it obtained authority to construct the Hayden plant. This is shown 'by the following statement of Commissioner Horton:
“That Ute, the applicant herein as we interpret the record, has to elect from three sources of power available to take care of their present and future needs:
“1. To purchase power from the investor-owned utilities represented by the Protestants herein;
*271 “2. To avail themselves of Bureau Power from The Colorado River Storage Project; and“3. To construct a steam electric plant at Hayden.”
QUESTION'S TO BE DETERMINED
First. Does public convenience and necessity require the construction and operation of the Hayden plant in view of the acknowledged adequacy of existing service?
We answer this question in the negative. The State of Colorado has long been dedicated to the principle of “regulated monopolies” in the conduct of public utility operations. This principle has been the public policy of this state since the year 1913 when the Public Utilities A'ct of the State of Colorado was first adopted. The concept has never varied in a long line of decisions of this court. We will comment upon some of those decisions later in this opinion, but it is here observed that as recently as September 13, 1965, in the case of Colorado Transportation Company v. The Public Utilities Commission of the State of Colorado, 158 Colo. 136, 405 P.2d 682, this court again reminded the P.U.C. of the concept of regulated monopoly as follows:
“It would seem to us that probably the real reason for the Commission’s falling into error in the instant case is the fact that even at this comparatively late date it professes to be uncertain as to whether utility regulation of motor carriers in Colorado is based upon the theory of ‘regulated competition’ or ‘regulated monopoly.’ As illustrative thereof, during the course of the hearing, one Commissioner opined as follows:
“ ‘We have a peculiar situation here and I hardly know how to rule. Our federal con'cept, as I under (sic) it, has been on the theory of regulated competition. If you can tell me what the Colorado concept is — I don’t know. We have got rulings that indicate both ways.’
“And then in its formal findings and order, the Commission stated as follows:
“ ‘The Colorado [Public Utilities] Commission, for the past twenty years, has regulated motor carriers for hire
*272 under the belief that the theory of regulated competition was in compliance with our law. We will not attempt to resolve this question as it would appear it is a matter of law which we feel is beyond our jurisdiction and should be left to the courts. * * *’“It is too late to debate the merits of the competing principles of ‘regulated competition’ and of ‘regulated monopoly’ in the field of utility regulation. Despite the claimed uncertainty of the Commission, the State of Colorado has long been wedded to the concept of regulated monopoly in the field of public utility regulation. For the benefit of the Commission, a few of the many cases which say so, are: Ephraim Freightways, Inc. v. Public Utilities Commission, 151 Colo. 596, 380 P.2d 228; Donohue v. Public Utilities Commission, 145 Colo. 499, 359 P.2d 1024; Denver & Rio Grande Western Railroad Co. v. Public Utilities Commission, 142 Colo. 400, 351 P.2d 278; and Archibald v. Public Utilities Commission, 115 Colo. 190, 171 P.2d 421. For better or for worse, then, Colorado is quite definitely committed to the principle that public utility regulation is based upon the theory of a ‘regulated monopoly.’ ”
There are a great many other cases adhering to the regulated monopoly principle and no purpose would here be served by reference to all of them. Suffice it to say that these cases clearly show that the regulated monopoly principle is not consistent with the theory of the case upon which the two concurring Commissioners based their decision.
The statute which is determinative of the basic issue in this case is C.R.S. 1963, 115-5-1, which provides as follows:
“115-5-1. New construction — extension.— (1) No public utility shall begin the construction of a new facility, plant, or system, or of any extension of its facility, plant, or system, without first having obtained from the commission a certificate that the present or
*273 future public convenience and necessity require or will require such construction. Sections 115-5-1 to 115-5-4 shall not be construed to require any corporation to secure such certificate for an extension within any city and county or city or town within which it shall have theretofore lawfully commenced operations, or for an extension into territory, either within or without a city and county or city or town, contiguous to its facility, or line, plant, or system, and not theretofore served by a public utility providing the same commodity or service, or for an extension within or to territory already served by it, necessary in the ordinary course of its business. * * *”The above statute makes mandatory proof of public convenience and necessity prior to the construction of any new plant or system, subject to certain exceptions. It is obvious that none of the exceptions are applicable in this case, and Colorado-Ute has never contended to the contrary. This statute is the foundation of the regulated monopoly principle and as this court has observed on many occasions it was designed to prevent duplication of facilities and competition between utilities, and to authorize new utilities in a field only when existing ones are found to be inadequate. Ephraim Freightways, Inc. v. Public Utilities Commission, 151 Colo. 596, 380 P.2d 228; Donohue v. Public Utilities Commission, 145 Colo. 499, 359 P.2d 1024; Public Service Company v. Public Utilities Commission, 142 Colo. 135, 350 P.2d 543; Public Utilities Commission v. Donahue, 138 Colo. 492, 335 P.2d 285; Public Utilities Commission v. Loveland, 87 Colo. 556, 289 Pac. 1090. It is our view that Commissioner Zarlengo correctly understood the force and effect of the statute and its application to the issues in this case as indicated by the following quotation from his dissent:
“It is obvious that the objective of the statute is to avoid duplication of sources of power in the public in
*274 terest. Why should the consuming public pay for, and maintain, two sources of power if one will do, or 3 sources of power if 2 will do, etc., etc.? The law, therefore, subjects proposals for new, or expanded, construction to the judgment of the Commission and in such cases the Applicant must make an affirmative showing that the purpose of the statute will not be defeated.“It is incumbent upon the Applicant ‘to tip the scales’ in the direction that duplication will not result from its proposed action. In doing this it must show that there is a need for the additional construction which necessarily involves showing that the existing sources are, and will, not be reasonably adequate and available.”
It is impossible for this court to reconcile its previous pronouncements with the statement of Commissioner Horton that Colorado-Ute could pick and choose the manner in which it availed itself of public utility service, one important kind of which is the furnishing of wholesale power, a service performed for many years by both protestants, and one as entitled to the protection of its regulated monopoly status as any other. Allowing customers to pick and choose from whom they will obtain any public utility service obviously creates rather then prevents duplication, fosters rather than controls competition, and totally disregards the principle that inadequacy of existing facilities must be shown in order to authorize a new service.
It appears from the record that Colorado-Ute initially recognized that it was required to satisfy these basic principles of public convenience and necessity if it were to prevail. Much evidence was produced in an effort to show that the Bureau of Reclamation did not have sufficient power to meet the requirements of 'Colorado-Ute’s proposed new customers. As indicated, each of the three Commissioners found to the contrary, and to illustrate the complete lack of proof of this essential
*275 ingredient of public convenience and necessity we quote from the Commission’s decision.Commissioner Horton stated:
“* * * However, the Bureau assures Ute that power and energy will be made available to them as preference customers by Act of Congress, from the Colorado River Storage Project.”
Commissioner Bjelland agreed in the following language:
“* * * Even as the record clearly establishes the fact that Ute needs more power, it equally clearly establishes that Ute’s immediate needs and reasonable future needs can be satisfied by purchasing hydroelectric power from the Colorado River Project. Ute and its member cooperatives are preference customers for power from this project, and preference power for the Upper Division States will in all liklihood not be fully utilized until the mid 1970’s. This source of power is stable and the price is reasonable. * * *” (Emphasis supplied.) Commissioner Zarlengo, in his dissent, stated:
“Giving consideration to all of the testimony upon this point, it is obvious that the requirements of Northern Division preference customers which they are entitled to obtain from the Bureau of Reclamation under the preference laws of the United States can be supplied by the Bureau from the Colorado River Storage Project through the year 1970, and perhaps through 1975.” (Emphasis supplied.)
The evidence of the capacity or ability of Arkansas Valley to continue supplying its customers’ requirements was clearly established by the record. Thus, existing sources of supply to the proposed new customers of Colorado-Ute were conclusively shown to be adequate. It should also be noted that the determination of the adequacy of existing sources was made without giving any consideration to other potential suppliers such as plaintiffs in error who were ready, willing and able to render this service in their respective service areas.
We agree with Commissioner Zarlengo when he points
*276 out in his dissenting opinion the lack of evidence of public convenience and necessity:“It appears that the applicant has founded its case, in the main, on the premises that if the Hayden Plant and facilities be authorized, the power and energy produced will find a market, all the while ignoring substantial proof and competent evidence as to the availability (58) or non-availability of power and energy from existing sources and the reasonableness of its cost to the consumers. To say the least, it has glossed over this phase, or, at most, tendered evidence which is vague, indefinite and uncertain.”
To affirm the decision of the Commission authorizing the construction of the Hayden plant where existing service was already adequate, would require a complete departure by this court from its previous decisions. The fundamental misconception of Colorado-Ute is its failure to recognize that, under regulation, existing suppliers are entitled to serve all desiring service, whether they be existing or potential customers. In our early decision in Public Service Company v. Loveland, supra, we protected the right of the existing utility to render electric service to potential customers even though the utility was not then serving them. A recent case in point is the case of Public Utilities Commission v. Verl Harvey, Inc., 150 Colo. 158, 371 P.2d 452, where the Commission had granted a certificate for an expanded motor carrier operation without finding that existing carriers were inadequate or unable to perform the desired service. The existing carriers had protested the expanded authority sought by one Watson because they were ready, willing and able to perform the service even though none of the customers involved were then served by them. The following quotation from that opinion is particularly suited to the issues here:
“Presented to the commission in opposition to granting of any authority to Watson was the contention of protestants, supported by uncontradicted evidence, that
*277 licensed carriers were ready, able and willing to fill the requirements of shippers, including the needs of those who have been using the service of Watson. Instead of making a finding that additional facilities were or were not needed, the commission expressly avoided answering this very important question, and stated:“ ‘That the services which Applicant seeks to provide are necessary for the public convenience and necessity even though there are other carriers who allege (though the Commission does not so find from the record) that they can adequately fill the vacuum which would result from cessation of operations by the Applicant.’ ”
The decision of this court in Donahue v. Public Utilities Commission, supra, is also particularly significant in view of the contentions here raised by 'Colorado-Ute. In that case the Commission had failed to find that service by existing carriers was inadequate but granted the authority requested on the basis that there was sufficient business to support the new carrier. In rejecting that concept of public convenience and necessity, and again adhering to the absolute requirement that the Commission find inadequacy of service before granting a new certificate, we said:
“* * * The finding by the commision that, ‘* * * nor can we say that his [protestant’s] service is adequate at this time,’ falls far short of a finding of failure reasonably to supply the need. There is not sufficient competent evidence in this record to warrant any such finding. The finding which is called the ‘serious question’ confronting the commission, namely, ‘Is there sufficient business to warrant two certificated carriers?’ amounts to a repudiation of the basic concept upon which the structure of Public Utility Commission powers is based, namely, that of regulated monopoly.”
All in all, on review of the record and the two concurring opinions of the majority of the Commission, it is apparent that no real effort was made to decide this case in a manner consistent with the pertinent statute
*278 (C.R.S. 1963, 115-5-1) and our many decisions construing and interpreting it. Instead, an approach of “non-regulation” was employed, as appears from the following statement quoted from the Commission’s findings:“We do not feel that the Commission should assume the burden of speculation on a matter so vital to thousands of consumers when the Colorado-Ute Board has made a management decision to construct the Hayden Plant.”
Our statement in the case of Consolidated Freightways Corporation v. Public Utilities Commission, 158 Colo. 239, 406 P.2d 83, bears repeating:
“Regulation —■ not non-regulation — has been declared to be in the public interest.”
In summarizing the factual situation presented by the record, it is apparent that,
1. adequate electric service is already available in the State of Colorado for the needs and necessities of the proposed new customers of Colorado-Ute; therefore
2. the construction of the Hayden Plant, requiring an investment of approximately thirty million dollars, is not necessary to supply any present or foreseeable future electric requirements, and Colorado ratepayers should not be required to support it; and
3. affirmance of the district court’s judgment and the decisions of the Commission would sanction a duplication of existing electric facilities which are adequate to supply the needs of the public; and
4. the affirmance of the district court and Commission decisions by this court would be inconsistent with the doctrine of regulated monopoly and would, as we stated in Public Utilities Commission v. Verl Harvey, supra, render regulation “wholly ineffective and meaningless.”
Having discussed the Colorado law of Public Convenience and Necessity as a crucial point upon which the decision in this case turns, we must inquire whether there are any other considerations which should, for
*279 reasons special to this case, absolve Colorado-Ute from the necessity of proving that the public convenience and necessity requires construction of the Hayden plant. If such considerations exist it must be admitted at the outset that the result would emasculate the concept of regulated monopoly and the entire Colorado structure of public utility law.SECOND. Does Colo. Sess.Laws 1961, ch. 198, 115-1-3(2), which generally conferred jurisdiction over cooperatives in the Public Utilities Commission, violate the Constitution of Colorado or of the United States?
This question is answered in the negative. At the commencement of its consideration of this case, the court requested and received an additional oral argument from counsel, upon questions concerning the constitutionality of the 1961 amendments (particularly Session Laws of Colorado 1961, ch. 198, 115-1-3(2)) to the Public Utility Law, and the consequent investiture of the Public Utilities Commission with jurisdiction of cooperatives.
Prior to the occasion of this oral argument Colorado-Ute had not questioned the constitutionality of the Act, had filed its application before the Commission and followed the matter through Commission, district court, and briefs in this court without suggesting unconstitutionality.
The power to regulate entities affected with a public interest is a function of the police power of the state, and any business or activity which is affected with a public interest may be so classified and so regulated. Eachus v. People, 124 Colo. 454, 238 P.2d 885; Nebbia v. New York, 291 U.S. 502; Munn v. Illinois, 94 U.S. 113; Idaho Power & Light v. Blomquist, 141 Pac. 1083 (Idaho 1914); Boone County Rural Electric Membership Corporation, et al. v. Public Service Commission of Indiana, et al., 239 Ind. 525, 159 N.E.2d 121; Kentucky Utilities Company v. Public Service Commission, 252 S.W.2d 885 (Ky. 1952); Dairyland Power Cooperative v. Brennan,
*280 248 Minn. 556, 82 N.W.2d 56; Orndoff v. Public Utilities Commission, 135 Ohio State 438, 21 N.E.2d 334.The record shows that Colorado-Ute in wholesaling electric power intends to serve various classes of customers including consuming cooperatives, other wholesaling cooperatives, governmental or quasi-governmental bodies (Salt River), and even an arm of the Federal Government, the Bureau of Reclamation, together with any other applicants for service if approved by the Commission. We hold that its business is affected with a public interest and is subject to regulation under the police power of the State of Colorado, and that such regulation does not violate either the Constitution of the State of Colorado or the Constitution of the United States.
The 1961 amendments to the Public Utilities Law of the State of Colorado are valid, enforceable, and constitutional. C.R.S. 1963, 115-1-3(2) provides:
“Every co-operative electric association, or nonprofit electric corporation or association, and every other supplier of electrical energy, whether supplying electric energy for the use of the public or for the use of its own members, is hereby declared to be affected with a public interest and to be a public utility and to be subject to the jurisdiction, control, and regulation of the commission and to the provisions of articles 1 to 7 of this chapter.”
This statute is couched in clear and cogent terms. It makes no exceptions. “Every co-operative electric association” is a public utility, as well as all other electric suppliers.
No issue has been raised in this case that Colorado-Ute is not a “co-operative electric association.” By the terms of the statute, therefore, it is subject to the “jurisdiction, control and regulation” of the Public Utilities Commission, and we so hold.
Colórado-Ute in its application before the Public Util
*281 ities Commission readily admits that it is a public utility. The application contains the following:“Applicant is a corporation organized and existing under and by virtue of the laws of the ’State of Colorado subject to the jurisdiction of this Commission under the provisions of H.B. No. 245 passed by the Colorado Legislature and signed by the Governor on April 23, 1961. * * *
“The public convenience and necessity requires the construction of said generating plant, transmission lines, and related facilities, and the interconnections herein described.”
These allegations are consistent only with the concept that Colorado-Ute is a public utility, and are inconsistent with any idea that it is concerned only with the needs and requirements of its co-operative members.
Western and Public Service admit that Colorado-Ute is a public utility. The legislature has declared in no uncertain terms that it is a public utility. It furnishes electrical energy which is used by countless consumers in a very large segment of this state. The widespread interest of the public is clearly shown, and this court should not declare the legislative act to be void, especially when the parties themselves admit that it is valid and enforceable.
There is an abundance of authority to support the classification of a wholesaler of energy to distributors as a public utility. North Carolina Public Service Co., et al. v. Southern Power Co., 282 Fed. 837; Boone County Rural Electric Membership Corporation, et al. v. Public Service Company of Indiana, et al., 239 Ind. 525, 159 N.E.2d 121; Orndoff v. Public Utilities Commission, 135 Ohio State 438, 21 N.E.2d 334; Industrial Gas Company v. Public Utilities Commission of Ohio, 135 Ohio St. 408, 21 N.E.2d 166; Wisconsin Traction Company v. Green Bay & Miss. Canal Co., 188 Wise. 54, 205 N.W. 551.
The co-operative form of organization obviously has nothing to do with the question of what constitutes the
*282 public convenience and necessity, or with the obligation of any utility to prove public convenience and necessity in accordance with the theory of regulated monopoly as expressed by the statutes of the State of Colorado and the decisions of this court. These statutes were enacted for the benefit of the public as a whole, and result in the granting of regulated status to a supplier of a commodity essential to the public interest. Under regulation, an electric consumer need not be a member of a co-operative to secure its service. Likewise a consumer located in an area exclusively served by such co-operative must take its service if indeed service is to be received at all. The form of organization delivering service makes no difference whatever to these consumers and the legislature recognizes reality when it specifically places the co-operatives under the regulatory arm of the state.As long ago as 1926 this court, in the case of Davis v. Public Utilities Commission, 79 Colo. 642, 247 Pac. 801, determined that in examining an activity affected with the public interest it would look to substance and ignore form. In that case the court said:
“In determining whether a business is that of a common carrier ‘the important thing is what it does, not what its charter says.’ Terminal Taxicab Co. v. Kutz, et al, 241 U.S. 252, 36 Sup. Ct. 583, 60 L. Ed. 984, Ann. Cas. 1916D, 765. A service may effect (sic) ‘so considerable a fraction of the public that it is public in the same sense in which any other may be called so-. . . The public does not mean everybody all the time.’ ”
That wholesaling of electric power is affected with a public interest is well illustrated by the fact that if it were not so, Public Service or Western could spin off their generation and transmission functions to a subsidiary corporation, and thus evade and defeat the regulation of wholesale power rates, and thereby the rates to the ultimate consumer. Certainly the legislature no
*283 more intended this result in the case of the co-operatives than it did in the case of the investor-owned utilities.THIRD. Does the fact that Colorado-Ute, a co-operative, has but thirteen members who are also co-operatives, warrant treatment of a different kind than that which would be applicable to any other kind of membership?
This question is answered in the negative. We find no merit to the argument that as a co-operative whose members are other co-operatives, Colorado-Ute is merely an extension or adjunct of these member cooperatives so that its act is the act of its members, and for that reason Colorado-Ute is not subject to regulation.
We observe first that Colorado-Ute is in all respects a separate legal entity; it has its own distinct corporate organization, including directors and officers; and it deals with its customers, whether co-operatives or not, by means of long term power supply contracts. It is obvious that the decision to construct the Hayden plant was the decision of Colorado-Ute itself rather than its members as of the time the decision was made to build the Hayden plant. At that time it had no more than five • members. Many of its new members did not become members or agree to power purchase contracts until shortly before the Commission hearing commenced, which was long after the decision to construct the plant was made. It is, therefore, apparent that Colorado-Ute, instead of being the alter ego of its members, is the complete master of its own destiny. Thus the concept of it as a mere extension or adjunct of the distribution co-operative members has no legal or factual basis and is a forced and artificial one. But even if we accepted the artificial idea of the nature of Colorado-Ute as an alter ego, so to speak, of its members, no different application of the legal principles here involved would result. There is no contention in this case that those customers of ■ Colorado-Ute that are themselves co-operatives are
*284 not public utilities and. are not subject to the jurisdiction of the Public Utilities Commission.Any such co-operative, which had not theretofore generated its own electricity, would be required to secure Commission approval if it proposed to construct such a plant (CPUS. 1963, 115-5-1), and of course if it came before the Commission with such purpose it, like any other utility, would be required to prove that the public convenience and necessity demanded such construction because it would then be engaging in a wholly new and distinct type of utility service (generation) theretofore supplied by “a public utility providing the same commodity or service.”
Similarly, Colorado-Ute did not go before the Commission seeking to extend existing facilities to serve existing customers. The record shows clearly it had ample facilities to serve all of its then existing customers and that the purpose of its application was to expand its service from a small area in southwestern Colorado to cover substantially all Western Slope as well as many thousands of square miles in the southeastern portion of the state.
In closing the discussion of the nature of Colorado-Ute, it may be remarked that its suggested status as an adjunct of its individual co-operatives is belied by what occurred. None of the distributive co-operatives were parties to the proceedings and their representatives did not appear before the Commission to give evidence in their own behalf that the public convenience and necessity required construction of the Hayden plant, and this lack cannot be supplied by mere speculation on the part of either Commission or court.
Secondly, Colorado-Ute is not by any means “a cooperative of cooperatives.” As we have already noted, of its thirteen members eleven are distribution cooperatives, one is a wholesale co-operative of a nature similar to that of Colorado-Ute itself, and the thirteenth — and by far the largest of all of its members — Salt
*285 River, is a governmental or quasi-governmental agency of a nature completely different from that of all other members.It is thus clearly apparent that the business of Colorado-Ute is affected with a special interest far beyond that of its eleven distributive co-operatives and therefore is not immune from regulation.
FOURTH. Does the fact that the Hayden plant has already been completed require an affirmance of the judgment of the trial court?
The answer is “No.” The court is aware that the Hayden plant is now constructed. This fact, however, cannot subvert the legal principles upon which our decision is based nor be allowed to defeat the doctrine of regulated monopoly to which Colorado subscribes. It is clear that both Colorado-Ute and the REA, its financing associate (who was not before the Commission) recognized that construction of the Hayden plant during litigation was attended with substantial risk, and they engaged in such activity with full knowledge of the possible consequences.
For good reason, no contention is made that the construction precludes decisions by this court. It is the law that when the interest of the public is concerned it is not only the right but the duty of an appellate court to determine the issues, regardless of interim construction. Bruce v. Leo, 129 Colo. 129, 267 P.2d 1014; Reserve Life Insurance Company, Dallas, Texas v. Frankfather, 123 Colo. 77, 225 P.2d 1035; Golden v. People ex rel., 101 Colo. 381, 74 P.2d 715; Pallas v. Johnson, 100 Colo. 449, 68 P.2d 559; Jackson v. Denver Producing and Refining Company, 96 F.2d 457 (10th Circuit 1938); Southern Pacific Terminal Company v. Interstate Commerce Commission, 219 U.S. 498, 55 L. Ed. 310; Franks v. State Highway Commission, 182 Kan. 131, 319 P.2d 535; Moore v. Smith, 160 Kan. 167, 160 P.2d 675; and Moore v. White, Okla., 323 P.2d 352.
Colorado-Ute solemnly assured the Commission and
*286 district court that in the event of the reversal of the Commission order, Colorado-Ute and its Colorado consumers would escape scatheless from adverse economic consequences because Salt River of Arizona would then assume the obligation for the Hayden plant. The record discloses that counsel for Colorado-Ute wrote the Commission under date of March 21, 1963, specifically stating that Salt River had agreed to take the Hayden plant off the hands of Colorado-Ute at no loss to Ute in the event that “some court” subsequently ruled that the certificate should not be issued.The district court warned applicant and its members and its participating financiers of the possible consequences of proceeding pendente lite, in the following language:
“If the cooperative members are willing to pledge their credit and the United States and the Salt River Project are prepared to spend the money to build this Plant in Colorado upon their expectation that the decision of the Public Utilities Commission will be sustained in the Courts, the progress of the work during the litigation would appear to cause no damage in law to anyone.”
In the unlikely event of loss it will not be borne by ultimate consumers of electricity, but will fall upon those who saw fit to go ahead notwithstanding the manifest uncertainty of their position and the express provisions of Section 4 of the Rural Electrification Act in which the Congress of the United States provided:
“That no loan for the construction, operation, or enlargement of any generating plant shall be made unless the consent of the State authority having jurisdiction in the premises is first obtained. Loans under this section and section 5 shall not be made unless the Administrator finds and certifies that in his judgment the security therefor is reasonably adequate and such loan will be repaid within the time agreed.”
When litigation in accordance with the statutes and
*287 procedures of the state in question is in progress, it needs no citation of authority to establish that consent of the state authority to the construction has not been obtained, ncr could any reasonable person believe that security for the -proposed loan is adequate and that the loan will be repaid in due course when the very right to construct the plant is still in litigation. The Court of Appeals for the 4th Circuit had occasion to examine related questions in the case of Greenwood County v. Duke Power Company, 107 Fed.2d 484, and said at pages 488-489:“The question of law as to whether the Public Works Administrator could lawfully make a loan and grant to a county for the construction of a project such as this was a new one and one upon which the opinion of able lawyers and judges was divided. It was in the interest of all parties concerned that the question be authoritatively settled before monies were advanced and expenditures made * *
“* * * The mere pendency of the suit raising such questions was sufficient to prevent advancement of funds by an officer of the United States, irrespective of the granting of the temporary injunction.”
Before concluding this opinion we desire to make additional comments on the Commission’s decision for the purpose of future reference and guidance. The Commission is primarily a fact finding body and has few, if any, of the attributes of an appellate court. It is required by law to make findings of fact upon which any necessary judicial review of its actions can be predicated. In the instant case, the lack of findings of fact by the Commission and the confusion arising from the separate statements by the respective commissioners as to what, if any, facts were agreed upon by the Commission as a regulatory body, have had grave consequences.
In order to get the matter before this court, the lack of proper findings first required counsel to prepare and
*288 file exceedingly long briefs and appendices and it next caused this court a massive amount of drudgery. Both of these results have contributed to delay in disposing of a case which is affected with great public interest.The judgment of the trial court is reversed and the cause remanded with directions that it vacate its judgment and thereafter direct the Commission to vacate and set aside its decision No. 60156.
Mr. Chief Justice Sutton concurs in the result.
Mr. Justice Frantz dissents.
Document Info
Docket Number: 21136
Citation Numbers: 411 P.2d 785, 159 Colo. 262, 1966 Colo. LEXIS 718
Judges: Frantz, Moore
Filed Date: 2/14/1966
Precedential Status: Precedential
Modified Date: 11/3/2024