Insurance Co. of North America v. Allgood Electric Co. , 229 Ga. App. 715 ( 1997 )


Menu:
  • Beasley, Judge.

    These two appeals are from portions of the trial court’s judgment on a motion for j.n.o.v.

    Insurance Company of North America, the prime contractor’s surety on a state-owned construction project, appeals from the denial of its j.n.o.v. motion awarding a second-tier electrical subcontractor, Allgood Electric Company, Inc., benefits under the prime contractor’s statutory payment bond. See OCGA § 13-10-1 (b) (2) (A). We affirm the judgment against the surety because there is proof authorizing the jury’s finding that Allgood is entitled to benefits under the payment bond for the unpaid balance of its lump-sum subcontract with the prime contractor’s security system contractor, Micro Manage*716ment Associates, Inc.

    Allgood cross-appeals from that part of the same judgment entered in favor of the surety notwithstanding a jury’s verdict awarding Allgood attorney fees and expenses of litigation under OCGA § 13-6-11.

    We reverse the ruling because Allgood’s proof that the surety refused to negotiate its pre-suit claim under the payment bond authorized the jury’s finding that the surety acted in bad faith in dealing with Allgood and because competent evidence supported the amount of the award.

    The State of Georgia contracted with Ray Bell Construction Company (“Ray Bell”) to build a prison in Wilcox County, Georgia, and Ray Bell contracted with Micro to install the prison’s security system. Micro then subcontracted with Allgood to wire the security system. According to this subcontract’s “FINAL PAYMENT” provision, Micro agreed to pay Allgood $350,500 when the wiring was complete, less any advances paid under the subcontract’s “PROGRESS PAYMENTS” provision giving Allgood the right to apply for monthly progress payments for “the value of the Work completed” during performance.

    After receiving two progress payments from Micro for work performed in June and July 1990, Allgood received three consecutive progress payments in August, September and October 1990. Allgood received these payments via checks from Ray Bell payable to Micro and Allgood for sums exceeding the amount of work performed by Allgood. Allgood endorsed the checks, but retained only proceeds reflecting payment for work it had performed. Allgood paid the residual to Micro.

    Allgood submitted a $65,926.65 progress payment request, dated November 19, 1991, certifying anticipated payment advances, plus retainer, for about 99 percent of the work under its subcontract with Micro. This request was not honored. Allgood instead accepted a joint check from Ray Bell payable to Micro and Allgood for $34,208.60. All-good endorsed this check, kept the proceeds and continued work. About a month later, Allgood executed a document entitled, “SUBCONTRACT/PURCHASE ORDER RECEIPT AFFIDAVIT AND PARTIAL LIEN WAIVER,” certifying payment advances totaling $240,448.88 (about 69 percent of the $350,500 contract price) and releasing “all claims arising out of said subcontract and the project through December 1991 . . . , including but [not] limited to claims representing mechanics liens.”

    Although Allgood submitted progress payment requests for December 1990 and January, February, March and April 1991, All-good did not receive another payment until May 1991. Allgood thereafter continued work, but received only four more progress pay*717ments. Because these payments did not cover Allgood’s outstanding payment requests, Allgood notified the surety of its claim in a letter dated April 30, 1992. The surety responded in a letter dated June 4, 1992, advising Allgood that the matter was under investigation. All-good thereafter continued work and completed the job in July 1992.

    Micro went out of business, and Ray Bell’s attorney posted a letter to Allgood’s president accusing Allgood of shoddy work. This attorney informed Allgood that “[i]t is Ray Bell’s position that All-good has been paid all monies which are due to it at this time.” When the surety failed to respond to Allgood’s claim for almost a year, All-good filed an action against Micro, Ray Bell and the surety in Fulton County Superior Court on April 20, 1994, seeking recovery for the remaining $87,543.80 balance under its contract with Micro. Allgood also sought over $100,000 worth of extra work it allegedly performed for Ray Bell and requested attorney fees and expenses of litigation pursuant to OCGA § 13-6-11.

    Allgood later abandoned its action against Micro and Ray Bell and proceeded solely against the surety. Ray Bell remained in the suit and pressed a counterclaim against Allgood for allegedly performing substandard work. After a trial, a jury awarded Allgood the entire unpaid balance of its contract with Micro, $87,543.80, and granted Allgood $48,276.21 in attorney fees and expenses of litigation under OCGA § 13-6-11. The jury did not accept Allgood’s claim for extra work and rejected Ray Bell’s claim against Allgood for substandard performance.

    Case No. A97A1386

    1. The surety contends the trial court erred in denying its motion for j.n.o.v., arguing that Allgood’s November 19, 1991 progress payment request certifying completion of about ninety-nine percent of the job, along with Allgood’s execution of the partial lien waiver a month later, demands a judgment for Allgood for no more than the subcontract’s ten percent retainer plus one percent of the work which Allgood did not certify as complete in its November 1991 progress payment request, i.e., $37,013.50. The surety also contends the jury should have given it credit for the total balance of the three joint progress payment checks Ray Bell tendered to Micro and Allgood for work which Allgood and Micro completed in August, September and October 1990. These assertions are without merit.

    Nothing in Allgood’s November 1991 payment certification or the December 1991 partial lien waiver diminished Micro’s promise to pay Allgood $350,500 when the wiring job was complete. Further, we find no authority authorizing a subcontractor to unilaterally retain proceeds of a joint check for work which the subcontractor has not per*718formed. Saying so would sanction theft, which we refuse to do. Accordingly, since it is undisputed that Allgood kept only money from the joint checks that it had earned and then gave the rest to Micro, and since there is proof that Allgood competently completed its work in July 1992, the jury’s verdict awarding Allgood the unpaid balance of its lump-sum contract with Micro was authorized. The trial court did not err in denying the surety’s motion for j.n.o.v. with regard to Allgood’s claim for payment under Ray Bell’s payment bond. See Beasley v. Paul, 223 Ga. App. 706 (1) (478 SE2d 899) (1996).

    2. The surety’s second enumeration of error challenging the admission of testimony regarding Allgood’s reason for executing the partial lien waiver in December 1991 provides no basis for reversal. Any such testimony admitted is harmless since the partial lien waiver does not evidence an agreement relinquishing Allgood’s right to recover the full benefit of its lump-sum performance contract with Micro.

    Case No. A97A1387

    3. We agree with Allgood that the trial court erred in granting a judgment in favor of the surety notwithstanding the jury’s verdict awarding Allgood attorney fees and expenses of litigation under OCGA § 13-6-11.

    “ ‘A judgment n.o.v. is properly granted only when there can be only one reasonable conclusion as to the proper judgment; if there is any evidentiary basis for the jury’s verdict, viewing the evidence most favorably to the party who secured the verdict, it is no error to deny the motion. (Cits.)’ Stone v. Cook, 190 Ga. App. 11, 12 (1) (378 SE2d 142) (1989).” Ga. Ports Auth. v. Southeast Atlantic Cargo &c., 202 Ga. App. 318, 324 (3) (414 SE2d 232) (1991).

    “A trial judge cannot grant motions for directed verdict or j.n.o.v. on any issue if ‘any evidence’ exists to support that issue. See Grubb v. Woodglenn Properties, 220 Ga. App. 902, 903 (470 SE2d 455) (1996).” Beasley v. Paul, 223 Ga. App. at 707 (1).

    (a) OCGA § 13-6-11 Liability. The trial court granted the surety’s motion for j.n.o.v. as to Allgood’s claim under OCGA § 13-6-11 because Allgood’s attorney could not testify and segregate, with any degree of certainty, time and expenses attributable to Allgood’s successful breach of contract claim from time and expenses attributable to Allgood’s unsuccessful extra-work claims. (Nor could this attorney say how much time was necessary to defend Ray Bell’s counterclaim.) Quoting Arford v. Blalock, 199 Ga. App. 434, 439 (10) (405 SE2d 698) (1991), the trial court specifically reasoned that such vague testimony defeated the jury’s attorney fees and litigation expenses award *719because “[n]o evidence was presented from which the jury could determine what portion of the total amount of attorney time and litigation expenses incurred in this multi-count, multi-defendant litigation was attributable to the particular claim. ...”

    We find this logic misplaced because, notwithstanding the success or validity of Allgood’s unsuccessful claims or Ray Bell’s counterclaim, Allgood tendered proof that the surety engaged in “wanton and excessive indulgence in litigation” by refusing, in bad faith, to investigate, negotiate or discuss any claim, set-off or defense with Allgood between the time Allgood posted its April 30, 1992 claim letter and the time Allgood initiated suit in Fulton County on April 20, 1994.1 Such circumstances not only distinguish this case from the rule set out in Arford v. Blalock, 199 Ga. App. 434, 439 (10), supra, but also removes it from the rule in Lineberger v. Williams, 195 Ga. App. 186, 188 (3) (393 SE2d 23) (1990) (that recovery is not possible under OCGA § 13-6-11 for attorney fees and expenses incurred for defending a claim). Had the surety aspired to negotiate or simply communicate with Allgood before forcing litigation, alternative dispute resolution would have provided a chance for avoiding this protracted and expensive lawsuit.

    Just as in Buffalo Cab Co. v. Williams, 126 Ga. App. 522 (191 SE2d 317) (1972), and Western &c. R. Co. v. Smith, 15 Ga. App. 289 (82 SE 906) (1914), the surety’s “so sue me” gamble authorized an OCGA § 13-6-11 award for all of Allgood’s attorney fees and expenses of litigation. See Tift v. Towns, 63 Ga. 237, 242 (3) (1879); and Presiding Justice now Chief Justice Robert Benham’s special concurrence in Latham v. Faulk, 265 Ga. 107, 108-109 (454 SE2d 136) (1995). See also Crocker v. Stevens, 210 Ga. App. 231, 238 (8) (435 SE2d 690) (1993).

    (b) Allgood’s Proof of Attorney Fees and Litigation Expenses. Gloria A. Alday, Allgood’s president, testified about work which was billed as performed by Allgood’s trial attorney and at least six other individuals — two named lawyers, an unnamed associate attorney, two or more unnamed paralegals and “Walker Hulbert.” Billing records were used by the witness to refresh her recollection of the invoices received and which she was responsible for reviewing and paying. Allgood’s president knew personally some of the precise bases for the fees because she was involved in the preparation for trial three times and for settlement talks, and she knew of the motions and responses required for the litigation. She considered the fees reasonable and comparable to fees the company incurred from other *720attorneys in the past and in accord with her investigation of fees charged by others.

    Allgood’s trial attorney then testified and expressed opinion that Alday’s account of the attorneys’ billings was necessary and reasonable. The plaintiff’s attorney himself is competent to testify as to his opinion on reasonable fees, which he did. Bankers Health &c. Ins. Co. v. Plumer, 67 Ga. App. 720, 727 (2) (21 SE2d 515) (1942); First Bank of Clayton County v. Dollar, 159 Ga. App. 815, 817 (4) (285 SE2d 203) (1981). He testified as to the rates of the various people who worked on the case, his background and rationale for the rates, his familiarity with the litigation history, the type of work which was done, and the reasonableness of it and of the fees charged. He was cross-examined to the extent defendant desired.

    Both witnesses gave the same figure for the total amount of All-good’s attorney fees and litigation expenses, an amount which mirrors the jury’s $48,276.21 verdict.

    Competent evidence supported that verdict, not only as to the substantive ground but also as to the reasonableness of the amount awarded by the jury.

    Judgment affirmed in Case No. A97A1386. Judgment reversed in Case No. A97A1387.

    Andrews, C. J., Birdsong, P. J., Pope, P. J, and Johnson, J., concur. Smith, J., concurs in the judgment only. McMur-ray, P. J., and Eldridge, J., concur in part and dissent in part. Blackburn and Ruffin, JJ, not participating.

    Allgood originally filed suit in Wilcox County on April 1, 1993, but withdrew this action because the surety contested venue.

Document Info

Docket Number: A97A1386, A97A1387

Citation Numbers: 494 S.E.2d 728, 229 Ga. App. 715, 98 Fulton County D. Rep. 10, 1997 Ga. App. LEXIS 1494, 1997 WL 795275

Judges: Beasley, McMurray, Andrews, Birdsong, Pope, Johnson, Smith, McMur-ray, Eldridge, Blackburn, Ruffin

Filed Date: 12/5/1997

Precedential Status: Precedential

Modified Date: 11/8/2024