Able Demolition, Inc v. City of Pontiac , 275 Mich. App. 577 ( 2007 )


Menu:
  • 739 N.W.2d 696 (2007)
    275 Mich. App. 577

    ABLE DEMOLITION, Inc., Plaintiff-Appellant,
    v.
    City of PONTIAC, Defendant-Appellee.

    Docket No. 273295.

    Court of Appeals of Michigan.

    Submitted March 14, 2007, at Lansing.
    Decided May 17, 2007, at 9:05 a.m.
    Released for Publication September 28, 2007.

    *697 Penzien & Associates, PLLC (by Charles M. Penzien), Mount Clemens, for the plaintiff.

    Bigler, Berry, Johnston, Sztykiel & Hunt, P.C. (by Eric S. Goldstein and Mary Jo Boerman), Zeeland, for the defendant.

    Before: SMOLENSKI, P.J., and SAAD and WILDER, JJ.

    SAAD, J.

    Able Demolition, Inc., appeals the trial court's grant of summary disposition to the city of Pontiac. For the reasons set forth below, we affirm the trial court's ruling.

    I. Facts and Procedural History

    On July 1, 2004, Able Demolition contracted with Pontiac to tear down certain abandoned homes. As the below-quoted *698 provisions of the contract make clear, Able was required to obtain specific written permission to proceed before demolishing any building:

    IV. SCOPE OF SERVICES
    4.01 The Contractor shall diligently perform certain Demolition Services for the City of Pontiac, primarily for the Department of Community Development, as outlined in the attached "Contract Documents." The term "Contract Documents" means and includes the following: 1) Performance Bond; 2) Bid Tally Sheet; 3) Specifications (including any supplemental specifications and special provisions.)
    4.02 The demolition services shall be performed over the course of the one (1) year contract, and shall include, but not be limited to, work as specified on the Purchase Order attached hereto, incorporated hereto marked as Exhibit "A" regarding ________________,
    (address of building)
    4.03 The Contractor is an independent contractor and shall not be subject to the specific direction or supervisions of any representative of the City, except in regard to the determination of the acceptability of the Contractor's work product by the Director of the Community Development Department and the Mayor of the City of Pontiac, and in regard to the mandatory requirements that the Contractor get pre-demolition authorization ("Letter to Proceed" described below) from the Director of Law or their designees prior to performance and/or demolition.
    * * *
    V. PRE-DEMOLITION APPROVAL
    5.01 Prior to any performance of services by the Contractor under the terms of this contract and pursuant to a successful bid, the Contractor must, on the date that the anticipated services will be performed (mandatory), contact the Director of Law or their designee to secure written approval to proceed with said services. Upon request for approval by the Contractor, the Director of Law or their designee will provide said Contractor with a "Letter to Proceed" which will specifically grant the Contractor written approval to proceed with said specified services. Prior to any payment under the terms of this contract (Section VI. Compensation), the Contractor must present the "Letter to Proceed" (Director of Law's — City Attorney's approval documentation) to the Director of Finance of the City verifying that approval to proceed was granted. If the Contractor proceeds without the approval specifically granted in the "Letter to Proceed", the Contractor shall forfeit any payment for unauthorized services performed as a result of his failure to get said pre-approval "Letter to Proceed".
    * * *
    VII. COMPENSATION
    7.01 The City agrees to pay the Contractor for the Demolition Services performed pursuant to Paragraph 4.02 in the amount of ___ Thousand ___ Hundred and ___/100 Dollars ($ ___.___), itemization required), not to exceed a maximum of One Hundred Thousand and 00/100 Dollars ($100,000.00) for the entire one (1) year contract. If the "Letter to Proceed" for each demolished property is not provided, the Contractor forfeits any payment under the terms of this contract.
    * * *
    VIII. METHOD OF PAYMENT
    8.01 Contractor shall submit monthly "Itemization Statements" for services *699 along with the "Letters to Proceed" in accordance with the provisions of this Contract. The original of said "Itemization Statement and "letters [sic] to Proceed" must be sent to the Director of the Community Development Department. Copies must also be provided to the Finance Director and to the Director of Law and the City of Pontiac.

    Able maintains that it demolished numerous buildings under the contract, but that Pontiac refused to pay $42,299 for 11 of the demolitions that Able completed. Able filed a complaint against Pontiac on May 10, 2006, and alleged claims of breach of contract, promissory estoppel, unjust enrichment, and quantum meruit.

    In lieu of an answer, Pontiac filed a motion for summary disposition under MCR 2.116(C)(10), and argued that Able is not entitled to payment because it did not comply with the material terms of the contract. Specifically, Pontiac asserted that Able failed to obtain letters to proceed as required by § 5.01 for 11 of the houses it demolished and that, therefore, Able forfeited its right to payment for those demolitions. In response, Able asserted that it substantially performed under the contract and it did not materially breach the agreement when it failed to obtain letters to proceed. Following oral argument, the trial court ruled that the contract language clearly and explicitly states that a letter to proceed is required before Able performs a demolition and before Able is entitled to payment. For that reason, the trial court granted summary disposition to Pontiac.

    II. Analysis

    A. Standard of Review

    This Court explained in Hamade v. Sunoco Inc. (R & M), 271 Mich.App. 145, 165-166, 721 N.W.2d 233 (2006):

    This Court . . . reviews de novo the proper interpretation of a contract. Clark v. DaimlerChrysler Corp., 268 Mich.App. 138, 141, 706 N.W.2d 471 (2005). Likewise, whether a contract's terms are ambiguous is a question of law this Court reviews de novo. Wilkie v. Auto-Owners Ins. Co., 469 Mich. 41, 47, 664 N.W.2d 776 (2003). When a contract is unambiguous, it must be enforced according to its terms. Daimler-Chrysler Corp. v. G-Tech Professional Staffing, Inc., 260 Mich.App. 183, 185, 678 N.W.2d 647 (2003).[1]

    B. Contract Interpretation

    Section 5.01 of Able's contract with Pontiac unambiguously requires that, on the day of each demolition, Able must obtain written assurance from Pontiac's director of law before Able may go forward with the destruction of a building. Sections 5.01, 7.01, and 8.01 also plainly state that, to be paid, Able must submit the letters to proceed to the city and various city representatives. The contract also provides *700 that, if a contractor fails to submit the letters, the company forfeits its right to payment.

    As our Supreme Court explained in Quality Products Concepts Co. v. Nagel Precision, Inc., 469 Mich. 362, 375, 666 N.W.2d 251 (2003):

    In interpreting a contract, our obligation is to determine the intent of the contracting parties. Sobczak v. Kotwicki, 347 Mich. 242, 249, 79 N.W.2d 471 (1956). If the language of the contract is unambiguous, we construe and enforce the contract as written. Farm Bureau Mut. Ins. Co. of Michigan v. Nikkel, 460 Mich. 558, 570, 596 N.W.2d 915 (1999). Thus, an unambiguous contractual provision is reflective of the parties' intent as a matter of law. Once discerned, the intent of the parties will be enforced unless it is contrary to public policy. Id.

    Here, the language of the contract is clear: the contractor, Able Demolition, must obtain a letter to proceed from the city's legal department before it can proceed.[2] The question here is what is the legal consequence of the contractor's failure to comply with this unambiguous contractual obligation.

    C. Condition Precedent[3]

    Because the contractual language is clear, we need not interpret this contract. Instead, we address the question of the legal consequences of plaintiff's failure to comply with its straightforward obligation. We hold that the contract provision that required Able to obtain letters to proceed is a condition precedent and that Able's failure to comply with this provision means that it was not entitled to performance by Pontiac, i.e., payment for demolition services. A condition precedent ``is a fact or event that the parties intend must take place before there is a right to performance.' Mikonczyk v. Detroit Newspapers, Inc., 238 Mich.App. 347, 350, 605 N.W.2d 360 (1999), quoting Reed v. Citizens Ins. Co. of America, 198 Mich.App. 443, 447, 499 N.W.2d 22 (1993). "Failure to satisfy a condition precedent prevents a cause of action for failure of performance." Berkel Co. Contractors v. Christman Co., 210 Mich.App. 416, 420, 533 N.W.2d 838 (1995).

    *701 "``Courts are not inclined to construe stipulations of a contract as conditions precedent unless compelled by the language in the contract.' Mikonczyk, supra at 350, 605 N.W.2d 360, quoting Reed, supra at 447, 499 N.W.2d 22. The clear and unambiguous language of the disputed provision compels the conclusion that the parties intended that Able must obtain a letter to proceed before each demolition, in order to trigger its right to payment. Section 4.03 of the contract states that prior to performance and/or demolition," Able must "get pre-demolition authorization," and 5.03 specifies that "Prior to any performance of services . . . [Able] must, on the date that the anticipated services will be performed (mandatory), contact the Director of Law or their designees to secure written approval to proceed with said services." (First and second emphasis in original; third emphasis added.) Moreover, § 7.01 unequivocally states that "[i]f the ``Letter to Proceed' for each demolished property is not provided, [Able] forfeits any payment under the terms of this contract." Again, the contract repeatedly states that Able's right to payment is contingent on its acquiring and submitting the letters, and this did not occur. In other words, the contractual language unambiguously sets forth the condition, clarifies its importance, and states the consequences of a failure to comply with the condition. Able acknowledges that it failed to obtain the letters, and, because of this failure, Pontiac is not obligated to perform under the contract. Accordingly, the trial court correctly granted summary disposition to Pontiac.

    D. Substantial Breach

    Were we to conclude that the letter to proceed provision constitutes a duty or a promise rather than a condition precedent, Able would not be entitled to recover under the contract. Again, Able concedes that it failed to comply with the terms of the agreement when it failed to obtain preapproval letters before it demolished the buildings for which it now seeks compensation. ``The rule in Michigan is that one who first breaches a contract cannot maintain an action against the other contracting party for his subsequent breach or failure to perform.' Michaels v. Amway Corp., 206 Mich.App. 644, 650, 522 N.W.2d 703 (1994), quoting Flamm v. Scherer, 40 Mich.App. 1, 8-9, 198 N.W.2d 702 (1972). However, the rule only applies if the initial breach was substantial. Id. To determine whether a substantial breach occurred, a trial court considers "whether the nonbreaching party obtained the benefit which he or she reasonably expected to receive." Holtzlander v. Brownell, 182 Mich.App. 716, 722, 453 N.W.2d 295 (1990). Able maintains that it demolished buildings, which was the central purpose of the agreement, and that, therefore, its failure to obtain and submit the preapproval letters should not excuse Pontiac's obligation to pay for its services.

    We disagree with Able's assertion for several reasons. Though the contract contemplated that Able would perform demolition services for the city, the contract here is more than a mere services contract. Rather, the contract is a "legal protocol," and, as such, the critical aspect of the agreement is that any demolition be accomplished in strict compliance with the procedures designated by Pontiac's legal department to minimize the risk of legal liability and the serious violation of citizens' property rights. A demolition company must ask the city for a letter on the day of each demolition because, in some cases, a property owner may obtain a last-minute temporary restraining order to prevent destruction of a building. Clearly, the city insists on the clause to avoid liability for demolitions that should not, legally, *702 go forward. This intent is clear because the contract language makes the letter to proceed mandatory on the date the demolition is performed, and this preapproval letter must be issued by the city's director of law. Because this step is in the contract to protect property rights and to protect the city from exposure to liability, the letter-to-proceed provision is an essential term of the contract and not a mere technicality. Indeed, the term goes to the heart of the agreement and reflects that the parties understood that the underlying action — the demolition of property — carries with it serious legal implications for all parties. If the parties were not bound by this term, the legal safeguards set forth in the agreement would be rendered meaningless. Thus, we hold that Able's breach was substantial and that Able may not maintain an action for damages against Pontiac as a matter of law.[4]

    Affirmed.

    Smolenski, J., concurred.

    WILDER, J., (concurring).

    I agree with and join in parts I and II(A), (B), and (C) of the majority opinion.

    NOTES

    [1] The trial court granted summary disposition to Pontiac under MCR 2.116(C)(10). "This Court reviews the grant or denial of summary disposition de novo to determine if the moving party is entitled to judgment as a matter of law." Maiden v. Rozwood, 461 Mich. 109, 118, 597 N.W.2d 817 (1999). As the Maiden Court further explained:

    A motion under MCR 2.116(C)(10) tests the factual sufficiency of the complaint. In evaluating a motion for summary disposition brought under this subsection, a trial court considers affidavits, pleadings, depositions, admissions, and other evidence submitted by the parties, MCR 2.116(G)(5), in the light most favorable to the party opposing the motion. Where the proffered evidence fails to establish a genuine issue regarding any material fact, the moving party is entitled to judgment as a matter of law. MCR 2.116(C)(10), (G)(4). Quinto v. Cross Peters Co., 451 Mich. 358, 547 N.W.2d 314 (1996). [Maiden, supra at 120, 597 N.W.2d 817.]

    [2] For the first time on appeal, Able avers that the contract language is ambiguous. Able did not assert in the trial court that the contract is unclear and, therefore, this issue is not preserved for appeal. Fast Air, Inc. v. Knight, 235 Mich.App. 541, 549, 599 N.W.2d 489 (1999). Nonetheless, Able's claim lacks merit. Section 5.01 provides that, if the demolition contractor fails to obtain a letter to proceed, it forfeits any payment for unauthorized services. Able contends that the phrase unauthorized services is ambiguous because, with further discovery, Able may be able to show that Pontiac officials authorized the demolitions and, therefore, the demolitions would not amount to an unauthorized service under the contract. First, that other officials may have authorized Able to demolish certain buildings does not render the contract language ambiguous. Further, the remainder of the section states that the failure to obtain letters to proceed constitutes a forfeiture of payment for unauthorized services performed as a result of his failure to get said pre-approval ``Letter to Proceed.' A plain reading of the section compels the conclusion that unauthorized services refers directly to the failure to obtain letters to proceed. Accordingly, that Able may have obtained permission from another source does not render the contract ambiguous and does not excuse performance under the terms specified in the agreement.

    [3] The Restatement of Contracts now refers to a "condition precedent" simply as a "condition." Restatement Contracts, 2d, § 224, comment e, p. 163. Here, we use the term "condition precedent" because it most aptly describes the precondition at issue and because our courts have continued to use the term since the Restatement's change.

    [4] To the extent Able continues to maintain its unjust enrichment, quantum meruit, and promissory estoppel claims, we affirm their dismissal. A claim of unjust enrichment does not apply if there is an express contract, Martin v. East Lansing School Dist., 193 Mich. App. 166, 177, 483 N.W.2d 656 (1992), and the same is true for a quantum meruit claim. Dykema Gossett PLLC v. Ajluni, 273 Mich. App. 1, 8-9, 730 N.W.2d 29 (2006). Furthermore, the contract contains an integration clause; therefore, it would have been unreasonable as a matter of law for Able to rely on any outside representations to support a promissory estoppel claim. UAW-GM Human Resource Ctr. v. KSL Recreation Corp., 228 Mich.App. 486, 504, 579 N.W.2d 411 (1998).

Document Info

Docket Number: Docket 273295

Citation Numbers: 739 N.W.2d 696, 275 Mich. App. 577

Judges: Smolenski, Saad, Wilder

Filed Date: 9/28/2007

Precedential Status: Precedential

Modified Date: 11/10/2024

Authorities (16)

Farm Bureau Mutual Insurance v. Nikkel , 460 Mich. 558 ( 1999 )

Reed v. Citizens Insurance Co. of America , 198 Mich. App. 443 ( 1993 )

Martin v. East Lansing School District , 193 Mich. App. 166 ( 1992 )

Clark v. DaimlerChrysler Corp. , 268 Mich. App. 138 ( 2005 )

Fast Air, Inc v. Knight , 235 Mich. App. 541 ( 1999 )

Wilkie v. Auto-Owners Insurance , 469 Mich. 41 ( 2003 )

Flamm v. Scherer , 40 Mich. App. 1 ( 1972 )

Quality Products and Concepts Co. v. Nagel Precision, Inc. , 469 Mich. 362 ( 2003 )

Berkel & Co. Contractors v. Christman Co. , 210 Mich. App. 416 ( 1995 )

Quinto v. Cross and Peters Co. , 451 Mich. 358 ( 1996 )

Holtzlander v. Brownell , 182 Mich. App. 716 ( 1990 )

Sobczak v. Kotwicki , 347 Mich. 242 ( 1956 )

UAW-GM Human Resource Center v. KSL Recreation Corp. , 228 Mich. App. 486 ( 1998 )

Hamade v. SUNOCO, INC.(R & M) , 721 N.W.2d 233 ( 2006 )

Michaels v. Amway Corp. , 206 Mich. App. 644 ( 1994 )

Mikonczyk v. Detroit Newspapers, Inc , 238 Mich. App. 347 ( 2000 )

View All Authorities »