Mobile Gas Service Corp. v. Federal Power Commission, United Gas Pipe Line Co., Intervener , 215 F.2d 883 ( 1954 )
Menu:
-
HASTIE, Circuit Judge (dissenting).
The Commission’s order of July 10, 1953 was lawful and proper under the terms and scheme of the Natural Gas Act. This court now is requiring that order to be changed in a way which, in my view, causes the Commission to exceed its authority under the Act. Accordingly, I dissent.
Document Info
Docket Number: 11280_1
Citation Numbers: 215 F.2d 883, 1954 U.S. App. LEXIS 2908
Judges: Hastie, McLaughlin, Staley
Filed Date: 9/7/1954
Precedential Status: Precedential
Modified Date: 10/19/2024