Gramatan-Sullivan, Inc. v. Nathan Koslow ( 1957 )


Menu:
  • HAND, Circuit Judge.

    The plaintiff, a New York corporation, appeals from a judgment in its favor, awarding a part only of its claim against the defendant, a citizen of New Jersey: the jurisdiction .depends upon this “diversity” of citizenship. The plaintiff’s claim arises because of an alleged diversion to the defendant of a “trust” fund which a New York, corporation, A. Shaw & Co., Inc., should have held for the payment of the plaintiff's claim against it. The complaint alleged that the “trust” arose under § 36-a of the Lien Law of New York, McK.Consol.Laws, c. 33, because of the following facts. A. Shaw & Co., Inc., is a building contractor, and had entered into a contract to construct the masonry needed for an “improvement” upon real estate in Dobbs Ferry, New York. Although the plaintiff had no contract with the contractor, upon the contractor’s orders it from time to time furnished sand and mortar needed on the job as it went along; so that, when the contractor abandoned performance of the contract at the end of August 1954, it owed the plaintiff more than $33,000. The contract provided for interim payments each month by the owner as the work progressed, two installments of which make up the fund in dispute, which the contractor received in May and June 1954, and which it turned over to the defendant in payment of loans by him for money used to finance the job. At the time of these two payments the contractor owed the plaintiff only $321.60, and it is to that amount that Judge Palmieri limited the plaintiff’s recovery, instead of awarding it the whole of the two installments. He held that, although § 36-a imposed a “trust” upon all payments made to a contractor, it secured subcontractors only to the extent of their claims at the time when the payments were made, and that the contractor was not therefore obliged to retain interim payments intact as a “trust” until the completion of the job. It was from this limitation of its recovery that the plaintiff appeals.

    The first question is whether the contractor was an “indispensable” party, jurisdiction over which was a condition upon the validity of any judgment herein. The plaintiff made it a party defendant in the original complaint but struck it out by amendment, because, like the plaintiff, it was a New *525York corporation and its presence defeated the “diversity” jurisdiction of the court. It is clear that the contractor has no personal interest in the outcome of this action, because if the plaintiff succeeded, the payments made by the defendant would pro tanto reduce its debt to the plaintiff and would at most revive the defendant’s claim against it, thus merely changing one creditor for another. Ordinarily, “indispensable” parties are those whose presence is necessary to protect them from injustice to them that will arise out of the judgment. The defendant does not press that objection here; instead he argues that it is he, and not the contractor, who would have been prejudiced by a full recovery, because although that would revive his debt against the contractor, in an action to collect it, he would not have the benefit of an estoppel upon the issue whether the payments had been made out of interim payments by the owner. It is impossible to take this argument seriously as a basis for holding that the court was without jurisdiction to decide the action at bar. In an action by the defendant to collect his debt against the contractor, it is the contractor which would have the burden of proving the payments, which were in fact made by endorsing to the defendant cheques of the owner. Certainly, as soon as that appeared, it became evident that the defendant could be under no handicap upon meeting a defense that the contractor had paid its debt out of funds not derived from the owner. We agree, therefore, that the court had jurisdiction under Fed.Rules Civ.Proc., Rule 19(b), 28 U.S.C.A., to proceed without the presence of the contractor, and we reach the merits.

    The plaintiff’s position is that § 36-a makes all interim payments on a building job a trust fund, not only for the benefit of existing claims of “subcontractors,” but of future claims that may arise thereafter as the work progresses. The contractor must keep intact all such payments save that he may pay claims of other “subcontractors” as they fall due. If he uses the payments for any other purpose, he is guilty of larceny, and anyone who receives them is liable, at least civilly to “subcontractors,” present and future, if he knows, or is charged with notice, that what he receives is part of an interim payment. For this interpretation the plaintiff especially relies upon a report of the New York Law Revision Commission, submitted to the legislature on December 11, 1941, which presumably resulted in the amendment of § 36-a and which for the first time expressly granted a civil remedy for breaches of the trust. This report did indeed twice say that “it would seem” that the trust was for the benefit of future, as well as existing, claimants; and, although such a guarded statement was not a categorical ruling, but apparently tentative, we will assume arguendo that it is authoritative. The issue at bar does not, however, turn on whether or not the trust is for the benefit of future, as well as of existing, claims; it depends upon whether the contractor has any privilege to use the payments, pending the completion of the work, and the existence of such a privilege is not necessarily a consequence of recognizing future claimants as beneficiaries. The privilege to pay claims as they mature, itself shows that the trust is not of the usual kind, for its exercise may result in giving earlier claimants a preference over later: e. g. if the contractor fails to earn any later payments. However, that privilege would not justify a privilege to use the payments for the contractor’s own purposes, had not the section declared that a contractor is guilty of larceny, if he not only fails to apply the payments to the “claims of subcontractors” but that he also “fails to pay the claims.” In short, if he pays the claims from other resources, he is not guilty of larceny, though he has used the payments for other purposes. It is a necessary condition upon his guilt that he shall be in default in the payment of the claims and it follows that he cannot be guilty as to claims that have not matured — certainly not as to claims not *526yet even in existence. No doubt, that exposes “subcontractors” to the risk of the contractor’s continued solvency before their claims mature, but it does not deny them protection as soon as they do. Moreover, this does not appear to us an unreasonable compromise between the possible necessities of the contractor, and the protection of “subcontractors” considering the fact that a criminal sanction was being imposed.

    At any rate, whether or not as a new proposition that is the correct interpretation of the language, the Court of Appeals adopted it in Raymond Concrete Pile Co. v. Federation Bank, 288 N.Y. 452, 43 N.E.2d 486. When that case was in the Appellate Division, 261 App.Div. 25, 23 N.Y.S.2d 933, the critical issue was that “ [Reasonable inquiry on the part of the bank undoubtedly would have disclosed the fact that L. P. O’Connor, Inc., would be unable to pay its subcontractors on February 20th, if, as was done in this ease, the sum of $78,000 was deducted from the face amount of the cheek” received from the owner, 261 App.Div. at page 28, 23 N.Y.S.2d at page 936. However, in the Court of Appeals, the plaintiff apparently made an added argument, 288 N.Y. at page 458, 43 N.E.2d at page 489: that is, that “irrespective of any denial of actual knowledge, since the bank benefited by the diversion, it is subject to the requirements of the law to restore to the trust the funds which it received for its personal benefit.” To this the court answered: “There is no evidence in the case whether or not the bank made any inquiry to determine if there were in existence any beneficiaries of the fund when the offset was made,” and then went on as follows, 288 N.Y. at page 459, 43 N.E.2d at page 489: “The most that the statute does or was designed to do * * * is to create the possibility of a fiduciary relationship arising between the contractor * * * and a possible subcontractor * * *. The statute does not give rise to a fiduciary relationship * * * or, if once created, continue it under any and all contingencies. Whether the moneys * * are or may be the subject-matter of a trust depends exclusively upon the fact, * * * that the contractor fails to pay the claims mentioned in the section. Nothing in the section bars the contractor from using the moneys received for any purpose he may see fit provided he does not fail to pay all such claims out of other moneys which he may then have or which he may after-wards receive, * * * There is no evidence in the case to indicate that the defendant knew or had any reasonable grounds to suspect prior to February 23, 1939, either that the plaintiff was a subcontractor * * * or that it had any claim at any time * * *. Without such evidence, there was no basis in the record for the judgment requiring defendant to return the moneys * * * ” Finally, 288 N.Y. at page 462, 43 N.E.2d at page 491: “In clear terms those sections were not intended to create a real trust fund to remain such under any and all contingencies from the time the contractor or subcontractor first received payment * *

    Thus the Court of Appeals did not think that the bank was put on notice as to whether there might be outstanding claims; it had no duty to inquire. The defendant’s position in the case at bar is much stronger than the bank’s in that action, for an inquiry would have shown that there were no existing claims whatever except that for which the plaintiff has recovered. If the plaintiff is to recover more, it can only be because it is a breach of trust for the contractor while the work is progressing to use any of the payments for his own purposes before the job is completed. That might have been the meaning but it was never expressed.

    We have hitherto been discussing § 36-a before its amendment in 1942, and we understand that, the defendant argues that this changed the scope of the liability theretofore imposed. However, the section remained as before, word for word, except for the *527addition of two sentences: one, granting a “civil action” to enforce the trust regardless of a “subcontractor’s” failure to file any lien; and the other providing that the trust funds shall include the right of action “upon an obligation for moneys due or to become due to a contractor.” We can find no basis in those changes for supposing that more was intended than to attach the civil sanction to the same liability to which the criminal sanction already attached. It would be an unwarranted construction of the change to suppose that, although the criminal liability remained subject to the former condition that the contractor “fails to pay the claims,” the civil liability was relieved of that condition. Finally, we submit that the validity of a payment by a contractor to a third person must depend upon the situation as it exists when the payment is received: that is, the payee does not hold it subject to a condition subsequent that the contractor shall pay at their maturity upon future claims as they may arise as the work progresses. If invalid, it is invalid at once; any other construction would make the section a trap for those who dealt with the contractor. It is fair in this connection to remember that the Court of Appeals as part of its reasoning for holding that the unamended section imposed no civil sanction said, 288 N.Y. at page 463, 43 N.E.2d at page 491: “Though section 23 requires a liberal construction of the provisions of the Lien Law, it does not authorize judicial amendment so as to enlarge its clearly defined scope and purposes.”

    Judgment affirmed.

Document Info

Docket Number: 24140_1

Judges: Clark, Hand, Swan

Filed Date: 1/7/1957

Precedential Status: Precedential

Modified Date: 10/19/2024