Utility Air Regulatory Group v. EPA ( 2014 )


Menu:
  • (Slip Opinion)              OCTOBER TERM, 2013                                       1
    Syllabus
    NOTE: Where it is feasible, a syllabus (headnote) will be released, as is
    being done in connection with this case, at the time the opinion is issued.
    The syllabus constitutes no part of the opinion of the Court but has been
    prepared by the Reporter of Decisions for the convenience of the reader.
    See United States v. Detroit Timber & Lumber Co., 
    200 U.S. 321
    , 337.
    SUPREME COURT OF THE UNITED STATES
    Syllabus
    UTILITY AIR REGULATORY GROUP v.
    ENVIRONMENTAL PROTECTION AGENCY ET AL.
    CERTIORARI TO THE UNITED STATES COURT OF APPEALS FOR
    THE DISTRICT OF COLUMBIA CIRCUIT
    No. 12–1146. Argued February 24, 2014—Decided June 23, 2014 *
    The Clean Air Act imposes permitting requirements on stationary
    sources, such as factories and powerplants. The Act’s “Prevention of
    Significant Deterioration” (PSD) provisions make it unlawful to con-
    struct or modify a “major emitting facility” in “any area to which [the
    PSD program] applies” without a permit. §§7475(a)(1), 7479(2)(C). A
    “major emitting facility” is a stationary source with the potential to
    emit 250 tons per year of “any air pollutant” (or 100 tons per year for
    certain types of sources). §7479(1). Facilities seeking to qualify for a
    PSD permit must, inter alia, comply with emissions limitations that
    reflect the “best available control technology” (BACT) for “each pollu-
    tant subject to regulation under” the Act. §7475(a)(4). In addition,
    Title V of the Act makes it unlawful to operate any “major source,”
    wherever located, without a permit. §7661a(a). A “major source” is a
    stationary source with the potential to emit 100 tons per year of “any
    air pollutant.” §§7661(2)(B), 7602(j).
    In response to Massachusetts v. EPA, 
    549 U.S. 497
    , EPA promul-
    gated greenhouse-gas emission standards for new motor vehicles, and
    ——————
    * Together with No. 12–1248, American Chemistry Council et al. v.
    Environmental Protection Agency et al., No. 12–1254, Energy-Intensive
    Manufacturers Working Group on Greenhouse Gas Regulation et al. v.
    Environmental Protection Agency et al., No. 12–1268, Southeastern Le-
    gal Foundation, Inc., et al. v. Environmental Protection Agency et al.,
    No. 12–1269, Texas et al. v. Environmental Protection Agency et al., and
    No. 12–1272, Chamber of Commerce of United States States et al. v.
    Environmental Protection Agency et al., also on certiorari to the same
    court.
    2             UTILITY AIR REGULATORY GROUP v. EPA
    Syllabus
    made stationary sources subject to the PSD program and Title V on
    the basis of their potential to emit greenhouse gases. It recognized,
    however, that requiring permits for all sources with greenhouse-gas
    emissions above the statutory thresholds would radically expand
    those programs and render them unadministrable. So EPA purport-
    ed to “tailor” the programs to accommodate greenhouse gases by
    providing, among other things, that sources would not become newly
    subject to PSD or Title V permitting on the basis of their potential to
    emit greenhouse gases in amounts less than 100,000 tons per year.
    Numerous parties, including several States, challenged EPA’s ac-
    tions in the D. C. Circuit, which dismissed some of the petitions for
    lack of jurisdiction and denied the remainder.
    Held: The judgment is affirmed in part and reversed in part.
    
    684 F.3d 102
    , affirmed in part and reversed in part.
    JUSTICE SCALIA delivered the opinion of the Court with respect to
    Parts I and II, concluding:
    1. The Act neither compels nor permits EPA to adopt an interpre-
    tation of the Act requiring a source to obtain a PSD or Title V permit
    on the sole basis of its potential greenhouse-gas emissions. Pp. 10–
    24.
    (a) The Act does not compel EPA’s interpretation. Massachusetts
    held that the Act-wide definition of “air pollutant” includes green-
    house 
    gases, 549 U.S., at 529
    , but where the term “air pollutant” ap-
    pears in the Act’s operative provisions, including the PSD and Title V
    permitting provisions, EPA has routinely given it a narrower, con-
    text-appropriate meaning. Massachusetts did not invalidate those
    longstanding constructions. The Act-wide definition is not a com-
    mand to regulate, but a description of the universe of substances EPA
    may consider regulating under the Act’s operative provisions.
    Though Congress’s profligate use of “air pollutant” is not conducive to
    clarity, the presumption of consistent usage “ ‘readily yields’ ” to con-
    text, and a statutory term “may take on distinct characters from as-
    sociation with distinct statutory objects calling for different imple-
    mentation strategies.” Environmental Defense v. Duke Energy Corp.,
    
    549 U.S. 561
    , 574. Pp. 10–16.
    (b) Nor does the Act permit EPA’s interpretation. Agencies em-
    powered to resolve statutory ambiguities must operate “within the
    bounds of reasonable interpretation,” Arlington v. FCC, 569 U. S. ___,
    ___. EPA has repeatedly acknowledged that applying the PSD and
    Title V permitting requirements to greenhouse gases would be incon-
    sistent with the Act’s structure and design. A review of the relevant
    statutory provisions leaves no doubt that the PSD program and Title
    V are designed to apply to, and cannot rationally be extended beyond,
    a relative handful of large sources capable of shouldering heavy sub-
    Cite as: 573 U. S. ____ (2014)                   3
    Syllabus
    stantive and procedural burdens. EPA’s interpretation would also
    bring about an enormous and transformative expansion in EPA’s
    regulatory authority without clear congressional authorization. FDA
    v. Brown & Williamson Tobacco Corp., 
    529 U.S. 120
    , 160. Pp. 16–20.
    (c) EPA lacked authority to “tailor” the Act’s unambiguous nu-
    merical thresholds of 100 or 250 tons per year to accommodate its
    greenhouse-gas-inclusive interpretation of the permitting triggers.
    Agencies must always “ ‘give effect to the unambiguously expressed
    intent of Congress.’ ” National Assn. of Home Builders v. Defenders
    of Wildlife, 
    551 U.S. 644
    , 665. The power to execute the laws does
    not include a power to revise clear statutory terms that turn out not
    to work in practice. Pp. 20–24.
    2. EPA reasonably interpreted the Act to require sources that
    would need permits based on their emission of conventional pollu-
    tants to comply with BACT for greenhouse gases. Pp. 24–29.
    (a) Concerns that BACT, which has traditionally been about end-
    of-stack controls, is fundamentally unsuited to greenhouse-gas regu-
    lation, which is more about energy use, are not unfounded. But an
    EPA guidance document states that BACT analysis should consider
    options other than energy efficiency, including “carbon capture and
    storage,” which EPA contends is reasonably comparable to more tra-
    ditional, end-of-stack BACT technologies. Moreover, assuming that
    BACT may be used to force improvements in energy efficiency, im-
    portant limitations on BACT may work to mitigate concerns about
    “unbounded” regulatory authority. Pp. 24–27.
    (b) EPA’s decision to require BACT for greenhouse gases emitted
    by sources otherwise subject to PSD review is, as a general matter, a
    permissible interpretation of the statute under Chevron U. S. A. Inc.
    v. Natural Resources Defense Council, Inc., 
    467 U.S. 837
    . The specif-
    ic phrasing of the BACT provision—which requires BACT “for each
    pollutant subject to regulation under” the Act, §7475(a)(4)—does not
    suggest that the provision can bear a narrowing construction. And
    even if the text were not clear, applying BACT to greenhouse gases is
    not so disastrously unworkable, and need not result in such a dra-
    matic expansion of agency authority, as to make EPA’s interpretation
    unreasonable. Pp. 27–29.
    SCALIA, J., announced the judgment of the Court and delivered an
    opinion, Parts I and II of which were for the Court. ROBERTS, C. J., and
    KENNEDY, J., joined that opinion in full; THOMAS and ALITO, JJ., joined
    as to Parts I, II–A, and II–B–1; and GINSBURG, BREYER, SOTOMAYOR,
    and KAGAN, JJ., joined as to Part II–B–2. BREYER J., filed an opinion
    concurring in part and dissenting in part, in which GINSBURG, SO-
    TOMAYOR, and KAGAN, JJ., joined. ALITO, J., filed an opinion concurring
    in part and dissenting in part, in which THOMAS, J., joined.
    Cite as: 573 U. S. ____ (2014)                              1
    Opinion of the Court
    NOTICE: This opinion is subject to formal revision before publication in the
    preliminary print of the United States Reports. Readers are requested to
    notify the Reporter of Decisions, Supreme Court of the United States, Wash-
    ington, D. C. 20543, of any typographical or other formal errors, in order
    that corrections may be made before the preliminary print goes to press.
    SUPREME COURT OF THE UNITED STATES
    _________________
    Nos. 12–1146, 12–1248, 12–1254, 12–1268, 12–1269, and 12–1272
    _________________
    UTILITY AIR REGULATORY GROUP,
    PETITIONER
    12–1146                v.
    ENVIRONMENTAL PROTECTION AGENCY, ET AL.;
    AMERICAN CHEMISTRY COUNCIL, ET AL.,
    PETITIONERS
    12–1248             v.
    ENVIRONMENTAL PROTECTION AGENCY, ET AL.;
    ENERGY-INTENSIVE MANUFACTURERS WORKING
    GROUP ON GREENHOUSE GAS REGULATION,
    ET AL., PETITIONERS
    12–1254                v.
    ENVIRONMENTAL PROTECTION AGENCY, ET AL.;
    SOUTHEASTERN LEGAL FOUNDATION, INC.,
    ET AL., PETITIONERS
    12–1268                v.
    ENVIRONMENTAL PROTECTION AGENCY, ET AL.;
    TEXAS, ET AL., PETITIONERS
    12–1269                v.
    ENVIRONMENTAL PROTECTION AGENCY,
    ET AL.; AND
    2         UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of the Court
    CHAMBER OF COMMERCE OF THE UNITED
    STATES, ET AL., PETITIONERS
    12–1272               v.
    ENVIRONMENTAL PROTECTION AGENCY, ET AL.;
    ON WRITS OF CERTIORARI TO THE UNITED STATES COURT OF
    APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT
    [June 23, 2014]
    JUSTICE SCALIA announced the judgment of the Court
    and delivered the opinion of the Court with respect to
    Parts I and II.
    Acting pursuant to the Clean Air Act, 69 Stat. 322, as
    amended, 
    42 U.S. C
    . §§7401–7671q, the Environmental
    Protection Agency recently set standards for emissions of
    “greenhouse gases” (substances it believes contribute to
    “global climate change”) from new motor vehicles. We
    must decide whether it was permissible for EPA to deter-
    mine that its motor-vehicle greenhouse-gas regulations
    automatically triggered permitting requirements under
    the Act for stationary sources that emit greenhouse gases.
    I. Background
    A. Stationary-Source Permitting
    The Clean Air Act regulates pollution-generating emis-
    sions from both stationary sources, such as factories and
    powerplants, and moving sources, such as cars, trucks,
    and aircraft. This litigation concerns permitting obliga-
    tions imposed on stationary sources under Titles I and V
    of the Act.
    Title I charges EPA with formulating national ambient
    air quality standards (NAAQS) for air pollutants. §§7408–
    7409. To date, EPA has issued NAAQS for six pollutants:
    sulfur dioxide, particulate matter, nitrogen dioxide, carbon
    monoxide, ozone, and lead. Clean Air Act Handbook 125
    (J. Domike & A. Zacaroli eds., 3d ed. 2011); see generally
    40 CFR pt. 50 (2013). States have primary responsibility
    Cite as: 573 U. S. ____ (2014)            3
    Opinion of the Court
    for implementing the NAAQS by developing “State imple-
    mentation plans.” 
    42 U.S. C
    . §7410. A State must desig-
    nate every area within its borders as “attainment,” “non-
    attainment,” or “unclassifiable” with respect to each
    NAAQS, §7407(d), and the State’s implementation plan
    must include permitting programs for stationary sources
    that vary according to the classification of the area where
    the source is or is proposed to be located. §7410(a)(2)(C),
    (I).
    Stationary sources in areas designated attainment or
    unclassifiable are subject to the Act’s provisions relating to
    “Prevention of Significant Deterioration” (PSD). §§7470–
    7492. EPA interprets the PSD provisions to apply to
    sources located in areas that are designated attainment or
    unclassifiable for any NAAQS pollutant, regardless of
    whether the source emits that specific pollutant. Since the
    inception of the PSD program, every area of the country
    has been designated attainment or unclassifiable for at
    least one NAAQS pollutant; thus, on EPA’s view, all sta-
    tionary sources are potentially subject to PSD review.
    It is unlawful to construct or modify a “major emitting
    facility” in “any area to which [the PSD program] applies”
    without first obtaining a permit. §§7475(a)(1), 7479(2)(C).
    To qualify for a permit, the facility must not cause or
    contribute to the violation of any applicable air-quality
    standard, §7475(a)(3), and it must comply with emissions
    limitations that reflect the “best available control technol-
    ogy” (or BACT) for “each pollutant subject to regulation
    under” the Act. §7475(a)(4). The Act defines a “major
    emitting facility” as any stationary source with the poten-
    tial to emit 250 tons per year of “any air pollutant” (or 100
    tons per year for certain types of sources). §7479(1). It
    defines “modification” as a physical or operational change
    that causes the facility to emit more of “any air pollutant.”
    4                UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of the Court
    §7411(a)(4).1
    In addition to the PSD permitting requirements for
    construction and modification, Title V of the Act makes it
    unlawful to operate any “major source,” wherever located,
    without a comprehensive operating permit. §7661a(a).
    Unlike the PSD program, Title V generally does not im-
    pose any substantive pollution-control requirements.
    Instead, it is designed to facilitate compliance and en-
    forcement by consolidating into a single document all of a
    facility’s obligations under the Act. The permit must
    include all “emissions limitations and standards” that
    apply to the source, as well as associated inspection, moni-
    toring, and reporting requirements. §7661c(a)–(c). Title V
    defines a “major source” by reference to the Act-wide
    definition of “major stationary source,” which in turn
    means any stationary source with the potential to emit
    100 tons per year of “any air pollutant.” §§7661(2)(B),
    7602( j).
    B. EPA’s Greenhouse-Gas Regulations
    In 2007, the Court held that Title II of the Act “author-
    ize[d] EPA to regulate greenhouse gas emissions from new
    motor vehicles” if the Agency “form[ed] a ‘judgment’ that
    ——————
    1 Although the statute sets numerical thresholds (100 or 250 tons per
    year) for emissions that will make a facility “major,” it does not specify
    by how much a physical or operational change must increase emissions
    to constitute a permit-requiring “modification.” Nor does it say how
    much of a given regulated pollutant a “major emitting facility” must
    emit before it is subject to BACT for that pollutant. EPA, however, has
    established pollutant-specific numerical thresholds below which a
    facility’s emissions of a pollutant, and increases therein, are considered
    de minimis for those purposes. See 40 CFR §§51.166(b)(2)(i), (23), (39),
    (j)(2)–(3), 52.21(b)(2)(i), (23), (40), (j)(2)–(3); see also Alabama Power Co.
    v. Costle, 
    636 F.2d 323
    , 360–361, 400, 405 (CADC 1979) (recognizing
    this authority in EPA); cf. Wisconsin Dept. of Revenue v. William
    Wrigley, Jr., Co., 
    505 U.S. 214
    , 231 (1992) (“[D]e minimis non curat lex
    . . . is part of the established background of legal principles against
    which all enactments are adopted”).
    Cite as: 573 U. S. ____ (2014)                 5
    Opinion of the Court
    such emissions contribute to climate change.” Massachu­
    setts v. EPA, 
    549 U.S. 497
    , 528 (quoting §7521(a)(1)). In
    response to that decision, EPA embarked on a course of
    regulation resulting in “the single largest expansion in the
    scope of the [Act] in its history.” Clean Air Act Handbook,
    at xxi.
    EPA first asked the public, in a notice of proposed rule-
    making, to comment on how the Agency should respond to
    Massachusetts. In doing so, it explained that regulating
    greenhouse-gas emissions from motor vehicles could have
    far-reaching consequences for stationary sources. Under
    EPA’s view, once greenhouse gases became regulated
    under any part of the Act, the PSD and Title V permitting
    requirements would apply to all stationary sources with
    the potential to emit greenhouse gases in excess of the
    statutory thresholds: 100 tons per year under Title V, and
    100 or 250 tons per year under the PSD program depend-
    ing on the type of source. 73 Fed. Reg. 44420, 44498,
    44511 (2008). Because greenhouse-gas emissions tend to
    be “orders of magnitude greater” than emissions of con-
    ventional pollutants, EPA projected that numerous small
    sources not previously regulated under the Act would be
    swept into the PSD program and Title V, including “smaller
    industrial sources,” “large office and residential build-
    ings, hotels, large retail establishments, and similar facili-
    ties.” 
    Id., at 44498–44499.
    The Agency warned that this
    would constitute an “unprecedented expansion of EPA
    authority that would have a profound effect on virtually
    every sector of the economy and touch every household in
    the land,” yet still be “relatively ineffective at reducing
    greenhouse gas concentrations.” 
    Id., at 44355.2
    ——————
    2 Comments from other Executive Branch agencies reprinted in the
    notice echoed those concerns. See, e.g., 73 Fed. Reg. 44360 (Depart-
    ments of Agriculture, Commerce, Transportation, and Energy noting
    EPA would “exercis[e] de facto zoning authority through control over
    thousands of what formerly were local or private decisions, impacting
    6            UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of the Court
    In 2009, EPA announced its determination regarding
    the danger posed by motor-vehicle greenhouse-gas emis-
    sions. EPA found that greenhouse-gas emissions from
    new motor vehicles contribute to elevated atmospheric
    concentrations of greenhouse gases, which endanger pub-
    lic health and welfare by fostering global “climate change.”
    74 Fed. Reg. 66523, 66537 (hereinafter Endangerment
    Finding). It denominated a “single air pollutant” the
    “combined mix” of six greenhouse gases that it identified
    as “the root cause of human-induced climate change”:
    carbon dioxide, methane, nitrous oxide, hydrofluorocar-
    bons, perfluorocarbons, and sulfur hexafluoride. 
    Id., at 66516,
    66537. A source’s greenhouse-gas emissions would
    be measured in “carbon dioxide equivalent units” (CO2e),
    which would be calculated based on each gas’s “global
    warming potential.” 
    Id., at 66499,
    n. 4.
    Next, EPA issued its “final decision” regarding the
    prospect that motor-vehicle greenhouse-gas standards
    would trigger stationary-source permitting requirements.
    75 Fed. Reg. 17004 (2010) (hereinafter Triggering Rule).
    EPA announced that beginning on the effective date of its
    greenhouse-gas standards for motor vehicles, stationary
    sources would be subject to the PSD program and Title V
    on the basis of their potential to emit greenhouse gases.
    As expected, EPA in short order promulgated greenhouse-
    gas emission standards for passenger cars, light-duty
    ——————
    the construction of schools, hospitals, and commercial and residential
    development”); 
    id., at 44383
    (Council of Economic Advisers and Office
    of Science and Technology Policy stating that “[s]mall manufacturing
    facilities, schools, and shopping centers” would be subject to “full major
    source permitting”); 
    id., at 44385
    (Council on Environmental Quality
    noting “the prospect of essentially automatic and immediate regulation
    over a vast range of community and business activity”); 
    id., at 44391
    (Small Business Administration finding it “difficult to overemphasize
    how potentially disruptive and burdensome such a new regulatory
    regime would be to small entities” such as “office buildings, retail
    establishments, hotels, . . . schools, prisons, and private hospitals”).
    Cite as: 573 U. S. ____ (2014)            7
    Opinion of the Court
    trucks, and medium-duty passenger vehicles to take effect
    on January 2, 2011. 75 Fed. Reg. 25324 (hereinafter
    Tailpipe Rule).
    EPA then announced steps it was taking to “tailor” the
    PSD program and Title V to greenhouse gases. 75 Fed.
    Reg. 31514 (hereinafter Tailoring Rule). Those steps were
    necessary, it said, because the PSD program and Title V
    were designed to regulate “a relatively small number of
    large industrial sources,” and requiring permits for all
    sources with greenhouse-gas emissions above the statu-
    tory thresholds would radically expand those programs,
    making them both unadministrable and “unrecognizable
    to the Congress that designed” them. 
    Id., at 31555,
    31562.
    EPA nonetheless rejected calls to exclude greenhouse
    gases entirely from those programs, asserting that the Act
    is not “ambiguous with respect to the need to cover
    [greenhouse-gas] sources under either the PSD or title V
    program.” 
    Id., at 31548,
    n. 31. Instead, EPA adopted a
    “phase-in approach” that it said would “appl[y] PSD and
    title V at threshold levels that are as close to the statutory
    levels as possible, and do so as quickly as possible, at least
    to a certain point.” 
    Id., at 31523.
       The phase-in, EPA said, would consist of at least three
    steps. During Step 1, from January 2 through June 30,
    2011, no source would become newly subject to the PSD
    program or Title V solely on the basis of its greenhouse-
    gas emissions; however, sources required to obtain permits
    anyway because of their emission of conventional pollu-
    tants (so-called “anyway” sources) would need to comply
    with BACT for greenhouse gases if they emitted those
    gases in significant amounts, defined as at least 75,000
    tons per year CO2e. 
    Ibid. During Step 2,
    from July 1,
    2011, through June 30, 2012, sources with the potential to
    emit at least 100,000 tons per year CO2e of greenhouse
    gases would be subject to PSD and Title V permitting for
    their construction and operation and to PSD permitting
    8           UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of the Court
    for modifications that would increase their greenhouse-gas
    emissions by at least 75,000 tons per year CO2e. 
    Id., at 31523–31524.3
    At Step 3, beginning on July 1, 2013, EPA
    said it might (or might not) further reduce the permitting
    thresholds (though not below 50,000 tons per year CO2e),
    and it might (or might not) establish permanent exemp-
    tions for some sources. 
    Id., at 31524.
    Beyond Step 3, EPA
    promised to complete another round of rulemaking by
    April 30, 2016, in which it would “take further action to
    address small sources,” which might (or might not) include
    establishing permanent exemptions. 
    Id., at 31525.
       EPA codified Steps 1 and 2 at 40 CFR §§51.166(b)(48)
    and 52.21(b)(49) for PSD and at §§70.2 and 71.2 for Title
    V, and it codified its commitments regarding Step 3 and
    beyond at §§52.22, 70.12, and 71.13. See Tailoring Rule
    31606–31608. After the decision below, EPA issued its
    final Step 3 rule, in which it decided not to lower the
    thresholds it had established at Step 2 until at least 2016.
    77 Fed. Reg. 41051 (2012).
    C. Decision Below
    Numerous parties, including several States, filed peti-
    tions for review in the D. C. Circuit under 
    42 U.S. C
    .
    §7607(b), challenging EPA’s greenhouse-gas-related ac-
    tions. The Court of Appeals dismissed some of the peti-
    tions for lack of jurisdiction and denied the remainder.
    Coalition for Responsible Regulation, Inc. v. EPA, 
    684 F.3d 102
    (2012) (per curiam). First, it upheld the Endan-
    germent Finding and Tailpipe Rule. 
    Id., at 119,
    126.
    Next, it held that EPA’s interpretation of the PSD permit-
    ting requirement as applying to “any regulated air pollu-
    ——————
    3 EPA stated that its adoption of a 75,000-tons-per-year threshold for
    emissions requiring BACT and modifications requiring permits was not
    an exercise of its authority to establish de minimis exceptions and that
    a truly de minimis level might be “well below” 75,000 tons per year.
    Tailoring Rule 31560; cf. n. 
    1, supra
    .
    Cite as: 573 U. S. ____ (2014)            9
    Opinion of the Court
    tant,” including greenhouse gases, was “compelled by the
    statute.” 
    Id., at 133–134.
    The court also found it “crystal
    clear that PSD permittees must install BACT for green-
    house gases.” 
    Id., at 137.
    Because it deemed petitioners’
    arguments about the PSD program insufficiently applica-
    ble to Title V, it held they had “forfeited any challenges to
    EPA’s greenhouse gas-inclusive interpretation of Title V.”
    
    Id., at 136.
    Finally, it held that petitioners were without
    Article III standing to challenge EPA’s efforts to limit the
    reach of the PSD program and Title V through the Trig-
    gering and Tailoring Rules. 
    Id., at 146.
    The court denied
    rehearing en banc, with Judges Brown and Kavanaugh
    each dissenting. No. 09–1322 etc. (Dec. 20, 2012), App.
    139, 
    2012 WL 6621785
    .
    We granted six petitions for certiorari but agreed to
    decide only one question: “ ‘Whether EPA permissibly
    determined that its regulation of greenhouse gas emis-
    sions from new motor vehicles triggered permitting re-
    quirements under the Clean Air Act for stationary sources
    that emit greenhouse gases.’ ” 571 U. S. ____ (2013).
    II. Analysis
    This litigation presents two distinct challenges to EPA’s
    stance on greenhouse-gas permitting for stationary
    sources. First, we must decide whether EPA permissibly
    determined that a source may be subject to the PSD and
    Title V permitting requirements on the sole basis of the
    source’s potential to emit greenhouse gases. Second, we
    must decide whether EPA permissibly determined that a
    source already subject to the PSD program because of its
    emission of conventional pollutants (an “anyway” source)
    may be required to limit its greenhouse-gas emissions by
    employing the “best available control technology” for
    greenhouse gases. The Solicitor General joins issue on
    both points but evidently regards the second as more
    important; he informs us that “anyway” sources account
    10          UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of the Court
    for roughly 83% of American stationary-source greenhouse-
    gas emissions, compared to just 3% for the additional, non-
    “anyway” sources EPA sought to regulate at Steps 2 and 3
    of the Tailoring Rule. Tr. of Oral Arg. 52.
    We review EPA’s interpretations of the Clean Air Act
    using the standard set forth in Chevron U. S. A. Inc. v.
    Natural Resources Defense Council, Inc., 
    467 U.S. 837
    ,
    842–843 (1984). Under Chevron, we presume that when
    an agency-administered statute is ambiguous with respect
    to what it prescribes, Congress has empowered the agency
    to resolve the ambiguity. The question for a reviewing
    court is whether in doing so the agency has acted reasona-
    bly and thus has “stayed within the bounds of its statutory
    authority.” Arlington v. FCC, 569 U. S. ___, ___ (2013)
    (slip op., at 5) (emphasis deleted).
    A. The PSD and Title V Triggers
    We first decide whether EPA permissibly interpreted
    the statute to provide that a source may be required to
    obtain a PSD or Title V permit on the sole basis of its
    potential greenhouse-gas emissions.
    1
    EPA thought its conclusion that a source’s greenhouse-
    gas emissions may necessitate a PSD or Title V permit
    followed from the Act’s unambiguous language. The Court
    of Appeals agreed and held that the statute “compelled”
    EPA’s 
    interpretation. 684 F.3d, at 134
    . We disagree.
    The statute compelled EPA’s greenhouse-gas-inclusive
    interpretation with respect to neither the PSD program
    nor Title V.4
    ——————
    4 The Court of Appeals held that petitioners’ arguments applied only
    to the PSD program and that petitioners had therefore “forfeited any
    challenges to EPA’s greenhouse gas-inclusive interpretation of Title 
    V.” 684 F.3d, at 136
    . The Solicitor General does not defend the Court of
    Appeals’ ruling on forfeiture, and he concedes that some of the argu-
    Cite as: 573 U. S. ____ (2014)                   11
    Opinion of the Court
    The Court of Appeals reasoned by way of a flawed syllo-
    gism: Under Massachusetts, the general, Act-wide defini-
    tion of “air pollutant” includes greenhouse gases; the Act
    requires permits for major emitters of “any air pollutant”;
    therefore, the Act requires permits for major emitters of
    greenhouse gases. The conclusion follows from the prem-
    ises only if the air pollutants referred to in the permit-
    requiring provisions (the minor premise) are the same air
    pollutants encompassed by the Act-wide definition as
    interpreted in Massachusetts (the major premise). Yet no
    one—least of all EPA—endorses that proposition, and it is
    obviously untenable.
    The Act-wide definition says that an air pollutant is
    “any air pollution agent or combination of such agents,
    including any physical, chemical, biological, [or] radioac-
    tive . . . substance or matter which is emitted into or oth-
    erwise enters the ambient air.” §7602(g). In Massachu­
    setts, the Court held that the Act-wide definition includes
    greenhouse gases because it is all-encompassing; it “em-
    braces all airborne compounds of whatever 
    stripe.” 549 U.S., at 529
    . But where the term “air pollutant” appears
    in the Act’s operative provisions, EPA has routinely given
    it a narrower, context-appropriate meaning.
    That is certainly true of the provisions that require PSD
    and Title V permitting for major emitters of “any air pollu-
    tant.” Since 1978, EPA’s regulations have interpreted “air
    pollutant” in the PSD permitting trigger as limited to
    regulated air pollutants, 43 Fed. Reg. 26403, codified, as
    amended, 40 CFR §52.21(b)(1)–(2), (50)—a class much
    narrower than Massachusetts’ “all airborne compounds of
    ——————
    ments petitioners have made before this Court apply to Title V as well
    as the PSD program. See Brief for Federal Respondents 56. We agree,
    and we are satisfied that those arguments were also made below. See,
    e.g., Brief for State Petitioners et al. in No. 10–1073 etc. (CADC), pp.
    59–73; Brief for Non-State Petitioners et al. in No. 10–1073 etc.
    (CADC), pp. 46–47.
    12         UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of the Court
    whatever 
    stripe,” 549 U.S., at 529
    . And since 1993 EPA
    has informally taken the same position with regard to the
    Title V permitting trigger, a position the Agency ultimately
    incorporated into some of the regulations at issue here.
    See Memorandum from Lydia N. Wegman, Deputy Direc-
    tor, Office of Air Quality Planning and Standards, to Air
    Division Director, Regions I–X, pp. 4–5 (Apr. 26, 1993);
    Tailoring Rule 31607–31608 (amending 40 CFR §§70.2,
    71.2). Those interpretations were appropriate: It is plain
    as day that the Act does not envision an elaborate, bur-
    densome permitting process for major emitters of steam,
    oxygen, or other harmless airborne substances. It takes
    some cheek for EPA to insist that it cannot possibly give
    “air pollutant” a reasonable, context-appropriate meaning
    in the PSD and Title V contexts when it has been doing
    precisely that for decades.
    Nor are those the only places in the Act where EPA has
    inferred from statutory context that a generic reference to
    air pollutants does not encompass every substance falling
    within the Act-wide definition. Other examples abound:
    	 The Act authorizes EPA to enforce new source per-
    formance standards (NSPS) against a pre-existing
    source if, after promulgation of the standards, the
    source undergoes a physical or operational change
    that increases its emission of “any air pollutant.”
    §7411(a)(2), (4), (b)(1)(B). EPA interprets that pro-
    vision as limited to air pollutants for which EPA
    has promulgated new source performance stand­
    ards. 36 Fed. Reg. 24877 (1971), codified, as
    amended, 40 CFR §60.2; 40 Fed. Reg. 58419 (1975),
    codified, as amended, 40 CFR §60.14(a).
    	 The Act requires a permit for the construction or
    operation in a nonattainment area of a source with
    the potential to emit 100 tons per year of “any air
    Cite as: 573 U. S. ____ (2014)          13
    Opinion of the Court
    pollutant.” §§7502(c)(5), 7602(j). EPA interprets
    that provision as limited to pollutants for which the
    area is designated nonattainment. 45 Fed. Reg.
    52745 (1980), promulgating 40 CFR §51.18(j)(2), as
    amended, §51.165(a)(2).
    	 The Act directs EPA to require “enhanced monitor-
    ing and submission of compliance certifications” for
    any source with the potential to emit 100 tons per
    year of “any air pollutant.” §§7414(a)(3), 7602(j).
    EPA interprets that provision as limited to regulated
    pollutants. 62 Fed. Reg. 54941 (1997), codified
    at 40 CFR §§64.1, 64.2.
    	 The Act requires certain sources of air pollutants
    that interfere with visibility to undergo retrofitting
    if they have the potential to emit 250 tons per year
    of “any pollutant.” §7491(b)(2)(A), (g)(7). EPA in-
    terprets that provision as limited to visibility­
    impairing air pollutants. 70 Fed. Reg. 39160
    (2005), codified at 40 CFR pt. 51, App. Y, §II.A.3.
    Although these limitations are nowhere to be found in the
    Act-wide definition, in each instance EPA has concluded—
    as it has in the PSD and Title V context—that the statute
    is not using “air pollutant” in Massachusetts’ broad sense
    to mean any airborne substance whatsoever.
    Massachusetts did not invalidate all these longstanding
    constructions. That case did not hold that EPA must
    always regulate greenhouse gases as an “air pollutant”
    everywhere that term appears in the statute, but only that
    EPA must “ground its reasons for action or inaction in the
    
    statute,” 549 U.S., at 535
    (emphasis added), rather than
    on “reasoning divorced from the statutory text,” 
    id., at 532.
    EPA’s inaction with regard to Title II was not suffi-
    ciently grounded in the statute, the Court said, in part
    14          UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of the Court
    because nothing in the Act suggested that regulating
    greenhouse gases under that Title would conflict with the
    statutory design. Title II would not compel EPA to regu-
    late in any way that would be “extreme,” “counterintui-
    tive,” or contrary to “ ‘common sense.’ ” 
    Id., at 531.
    At
    most, it would require EPA to take the modest step of
    adding greenhouse-gas standards to the roster of new-
    motor-vehicle emission regulations. 
    Ibid. Massachusetts does not
    strip EPA of authority to ex-
    clude greenhouse gases from the class of regulable air
    pollutants under other parts of the Act where their inclu-
    sion would be inconsistent with the statutory scheme. The
    Act-wide definition to which the Court gave a “sweeping”
    and “capacious” interpretation, 
    id., at 528,
    532, is not a
    command to regulate, but a description of the universe of
    substances EPA may consider regulating under the Act’s
    operative provisions. Massachusetts does not foreclose the
    Agency’s use of statutory context to infer that certain of
    the Act’s provisions use “air pollutant” to denote not every
    conceivable airborne substance, but only those that may
    sensibly be encompassed within the particular regulatory
    program. As certain amici felicitously put it, while Mas­
    sachusetts “rejected EPA’s categorical contention that
    greenhouse gases could not be ‘air pollutants’ for any
    purposes of the Act,” it did not “embrace EPA’s current,
    equally categorical position that greenhouse gases must be
    air pollutants for all purposes” regardless of the statutory
    context. Brief for Administrative Law Professors et al. as
    Amici Curiae 17.5
    ——————
    5 Our decision in American Elec. Power Co. v. Connecticut, 564 U. S.
    ___ (2011), does not suggest otherwise. We there held that the Act’s
    authorization for EPA to establish performance standards for power-
    plant greenhouse-gas emissions displaced any federal-common-law
    right that might otherwise have existed to seek abatement of those
    emissions. Id., at ___ (slip op., at 10). The authorization to which we
    referred was that given in the NSPS program of §7411, a part of the Act
    Cite as: 573 U. S. ____ (2014)               15
    Opinion of the Court
    To be sure, Congress’s profligate use of “air pollutant”
    where what is meant is obviously narrower than the Act-
    wide definition is not conducive to clarity. One ordinarily
    assumes “ ‘that identical words used in different parts of
    the same act are intended to have the same meaning.’ ”
    Environmental Defense v. Duke Energy Corp., 
    549 U.S. 561
    , 574 (2007). In this respect (as in countless others),
    the Act is far from a chef d’oeuvre of legislative draftsman-
    ship. But we, and EPA, must do our best, bearing in mind
    the “ ‘fundamental canon of statutory construction that the
    words of a statute must be read in their context and with a
    view to their place in the overall statutory scheme.’ ” FDA
    v. Brown & Williamson Tobacco Corp., 
    529 U.S. 120
    , 133
    (2000). As we reiterated the same day we decided Massa­
    chusetts, the presumption of consistent usage “ ‘readily
    yields’ ” to context, and a statutory term—even one defined
    in the statute—“may take on distinct characters from
    association with distinct statutory objects calling for dif-
    ferent implementation strategies.” Duke 
    Energy, supra, at 574
    .
    We need not, and do not, pass on the validity of all the
    limiting constructions EPA has given the term “air pollu-
    tant” throughout the Act. We merely observe that taken
    together, they belie EPA’s rigid insistence that when
    interpreting the PSD and Title V permitting requirements
    it is bound by the Act-wide definition’s inclusion of green-
    house gases, no matter how incompatible that inclusion is
    with those programs’ regulatory structure.
    In sum, there is no insuperable textual barrier to EPA’s
    interpreting “any air pollutant” in the permitting triggers
    of PSD and Title V to encompass only pollutants emitted
    in quantities that enable them to be sensibly regulated at
    the statutory thresholds, and to exclude those atypical
    ——————
    not at issue here and one that no party in American Electric Power
    argued was ill suited to accommodating greenhouse gases.
    16           UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of the Court
    pollutants that, like greenhouse gases, are emitted in such
    vast quantities that their inclusion would radically trans-
    form those programs and render them unworkable as
    written.6
    2
    Having determined that EPA was mistaken in thinking
    the Act compelled a greenhouse-gas-inclusive interpreta-
    tion of the PSD and Title V triggers, we next consider the
    Agency’s alternative position that its interpretation was
    justified as an exercise of its “discretion” to adopt “a rea-
    sonable construction of the statute.” Tailoring Rule 31517.
    We conclude that EPA’s interpretation is not permissible.
    Even under Chevron’s deferential framework, agencies
    must operate “within the bounds of reasonable interpreta-
    tion.” Arlington, 569 U. S., at ___ (slip op., at 5). And
    reasonable statutory interpretation must account for both
    “the specific context in which . . . language is used” and
    “the broader context of the statute as a whole.” Robinson
    v. Shell Oil Co., 
    519 U.S. 337
    , 341 (1997). A statutory
    ——————
    6 During  the course of this litigation, several possible limiting con-
    structions for the PSD trigger have been proposed. Judge Kavanaugh
    argued below that it would be plausible for EPA to read “any air pollu-
    tant” in the PSD context as limited to the six NAAQS pollutants. See
    Coalition for Responsible Regulation, Inc. v. EPA, No. 09–1322 etc.
    (CADC, Dec. 20, 2012), App. 171–180, 
    2012 WL 6621785
    , *15–*18
    (opinion dissenting from denial of rehearing en banc). Some petitioners
    make a slightly different argument: that because PSD permitting is
    required only for major emitting facilities “in any area to which [the
    PSD program] applies,” §7475(a), the relevant pollutants are only those
    NAAQS pollutants for which the area in question is designated attain-
    ment or unclassifiable. That approach would bring EPA’s interpreta-
    tion of the PSD trigger in line with its longstanding interpretation of
    the permitting requirements for nonattainment areas. Others main-
    tain that “any air pollutant” in the PSD provision should be limited to
    air pollutants with localized effects on air quality. We do not foreclose
    EPA or the courts from considering those constructions in the future,
    but we need not do so today.
    Cite as: 573 U. S. ____ (2014)          17
    Opinion of the Court
    “provision that may seem ambiguous in isolation is often
    clarified by the remainder of the statutory scheme . . .
    because only one of the permissible meanings produces a
    substantive effect that is compatible with the rest of the
    law.” United Sav. Assn. of Tex. v. Timbers of Inwood
    Forest Associates, Ltd., 
    484 U.S. 365
    , 371 (1988). Thus,
    an agency interpretation that is “inconsisten[t] with the
    design and structure of the statute as a whole,” University
    of Tex. Southwestern Medical Center v. Nassar, 570 U. S.
    ___, ___ (2013) (slip op., at 13), does not merit deference.
    EPA itself has repeatedly acknowledged that applying
    the PSD and Title V permitting requirements to green-
    house gases would be inconsistent with—in fact, would
    overthrow—the Act’s structure and design. In the Tailor-
    ing Rule, EPA described the calamitous consequences of
    interpreting the Act in that way. Under the PSD program,
    annual permit applications would jump from about 800 to
    nearly 82,000; annual administrative costs would swell
    from $12 million to over $1.5 billion; and decade-long
    delays in issuing permits would become common, causing
    construction projects to grind to a halt nationwide. Tailor-
    ing Rule 31557. The picture under Title V was equally
    bleak: The number of sources required to have permits
    would jump from fewer than 15,000 to about 6.1 million;
    annual administrative costs would balloon from $62 mil-
    lion to $21 billion; and collectively the newly covered
    sources would face permitting costs of $147 billion. 
    Id., at 31562–31563.
    Moreover, “the great majority of additional
    sources brought into the PSD and title V programs would
    be small sources that Congress did not expect would need
    to undergo permitting.” 
    Id., at 31533.
    EPA stated that
    these results would be so “contrary to congressional in-
    tent,” and would so “severely undermine what Congress
    sought to accomplish,” that they necessitated as much as a
    1,000-fold increase in the permitting thresholds set forth
    in the statute. 
    Id., at 31554,
    31562.
    18        UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of the Court
    Like EPA, we think it beyond reasonable debate that
    requiring permits for sources based solely on their emis-
    sion of greenhouse gases at the 100- and 250-tons-per-year
    levels set forth in the statute would be “incompatible” with
    “the substance of Congress’ regulatory scheme.” Brown &
    
    Williamson, 529 U.S., at 156
    . A brief review of the rele-
    vant statutory provisions leaves no doubt that the PSD
    program and Title V are designed to apply to, and cannot
    rationally be extended beyond, a relative handful of large
    sources capable of shouldering heavy substantive and
    procedural burdens.
    Start with the PSD program, which imposes numerous
    and costly requirements on those sources that are required
    to apply for permits. Among other things, the applicant
    must make available a detailed scientific analysis of the
    source’s potential pollution-related impacts, demonstrate
    that the source will not contribute to the violation of any
    applicable pollution standard, and identify and use the
    “best available control technology” for each regulated
    pollutant it emits. §7475(a)(3), (4), (6), (e). The permitting
    authority (the State, usually) also bears its share of the
    burden: It must grant or deny a permit within a year,
    during which time it must hold a public hearing on the
    application. §7475(a)(2), (c).      Not surprisingly, EPA
    acknowledges that PSD review is a “complicated, resource-
    intensive, time-consuming, and sometimes contentious
    process” suitable for “hundreds of larger sources,” not
    “tens of thousands of smaller sources.” 74 Fed. Reg.
    55304, 55321–55322.
    Title V contains no comparable substantive require-
    ments but imposes elaborate procedural mandates. It
    requires the applicant to submit, within a year of becom-
    ing subject to Title V, a permit application and a “compli-
    ance plan” describing how it will comply with “all applica-
    ble requirements” under the Act; to certify its compliance
    annually; and to submit to “inspection, entry, monitoring,
    Cite as: 573 U. S. ____ (2014)           19
    Opinion of the Court
    . . . and reporting requirements.”            §§7661b(b)–(c),
    7661c(a)–(c). The procedural burdens on the permitting
    authority and EPA are also significant. The permitting
    authority must hold a public hearing on the application,
    §7661a(b)(6), and it must forward the application and any
    proposed permit to EPA and neighboring States and re-
    spond in writing to their comments, §7661d(a), (b)(1). If it
    fails to issue or deny the permit within 18 months, any
    interested party can sue to require a decision “without
    additional delay.” §§7661a(b)(7), 7661b(c). An interested
    party also can petition EPA to block issuance of the per-
    mit; EPA must grant or deny the petition within 60 days,
    and its decision may be challenged in federal court.
    §7661d(b)(2)–(3). As EPA wrote, Title V is “finely crafted
    for thousands,” not millions, of sources. Tailoring Rule
    31563.
    The fact that EPA’s greenhouse-gas-inclusive interpre-
    tation of the PSD and Title V triggers would place plainly
    excessive demands on limited governmental resources is
    alone a good reason for rejecting it; but that is not the only
    reason. EPA’s interpretation is also unreasonable because
    it would bring about an enormous and transformative
    expansion in EPA’s regulatory authority without clear
    congressional authorization. When an agency claims to
    discover in a long-extant statute an unheralded power to
    regulate “a significant portion of the American economy,”
    Brown & 
    Williamson, 529 U.S., at 159
    , we typically greet
    its announcement with a measure of skepticism. We
    expect Congress to speak clearly if it wishes to assign to
    an agency decisions of vast “economic and political signifi-
    cance.” 
    Id., at 160;
    see also MCI Telecommunications
    Corp. v. American Telephone & Telegraph Co., 
    512 U.S. 218
    , 231 (1994); Industrial Union Dept., AFL–CIO v.
    American Petroleum Institute, 
    448 U.S. 607
    , 645–646
    (1980) (plurality opinion). The power to require permits
    for the construction and modification of tens of thousands,
    20          UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of the Court
    and the operation of millions, of small sources nationwide
    falls comfortably within the class of authorizations that we
    have been reluctant to read into ambiguous statutory text.
    Moreover, in EPA’s assertion of that authority, we con-
    front a singular situation: an agency laying claim to ex-
    travagant statutory power over the national economy
    while at the same time strenuously asserting that the
    authority claimed would render the statute “unrecogniza-
    ble to the Congress that designed” it. Tailoring Rule
    31555. Since, as we hold above, the statute does not com-
    pel EPA’s interpretation, it would be patently unreason-
    able—not to say outrageous—for EPA to insist on seizing
    expansive power that it admits the statute is not designed
    to grant.7
    3
    EPA thought that despite the foregoing problems, it
    could make its interpretation reasonable by adjusting the
    levels at which a source’s greenhouse-gas emissions would
    ——————
    7 A few additional points bear mentioning.      The Solicitor General
    conjectures that EPA might eventually alter its longstanding interpre-
    tation of “potential to emit” in order to reduce the number of sources
    required to have permits at the statutory thresholds. But neither he
    nor the Agency has given us any reason to believe that there exists a
    plausible reading of “potential to emit” that EPA would willingly adopt
    and that would eliminate the unreasonableness of EPA’s interpretation.
    Nor have we been given any information about the ability of other
    possible “streamlining” techniques alluded to by EPA—such as “gen-
    eral” or “electronic” permitting—to reduce the administrability prob-
    lems identified above; and in any event, none of those techniques would
    address the more fundamental problem of EPA’s claiming regulatory
    authority over millions of small entities that it acknowledges the Act
    does not seek to regulate. Finally, the Solicitor General suggests that
    the incompatibility of greenhouse gases with the PSD program and
    Title V results chiefly from the inclusion of carbon dioxide in the
    “aggregate pollutant” defined by EPA. We decide these cases on the
    basis of the pollutant “greenhouse gases” as EPA has defined and
    regulated it, and we express no view on how our analysis might change
    were EPA to define it differently.
    Cite as: 573 U. S. ____ (2014)          21
    Opinion of the Court
    oblige it to undergo PSD and Title V permitting. Although
    the Act, in no uncertain terms, requires permits for
    sources with the potential to emit more than 100 or 250
    tons per year of a relevant pollutant, EPA in its Tailoring
    Rule wrote a new threshold of 100,000 tons per year for
    greenhouse gases. Since the Court of Appeals thought the
    statute unambiguously made greenhouse gases capable of
    triggering PSD and Title V, it held that petitioners lacked
    Article III standing to challenge the Tailoring Rule be-
    cause that rule did not injure petitioners but merely re-
    laxed the pre-existing statutory requirements. Because
    we, however, hold that EPA’s greenhouse-gas-inclusive
    interpretation of the triggers was not compelled, and
    because EPA has essentially admitted that its interpreta-
    tion would be unreasonable without “tailoring,” we consider
    the validity of the Tailoring Rule.
    We conclude that EPA’s rewriting of the statutory
    thresholds was impermissible and therefore could not
    validate the Agency’s interpretation of the triggering
    provisions. An agency has no power to “tailor” legislation
    to bureaucratic policy goals by rewriting unambiguous
    statutory terms. Agencies exercise discretion only in the
    interstices created by statutory silence or ambiguity; they
    must always “ ‘give effect to the unambiguously expressed
    intent of Congress.’ ” National Assn. of Home Builders v.
    Defenders of Wildlife, 
    551 U.S. 644
    , 665 (2007) (quoting
    
    Chevron, 467 U.S., at 843
    ). It is hard to imagine a statu-
    tory term less ambiguous than the precise numerical
    thresholds at which the Act requires PSD and Title V
    permitting. When EPA replaced those numbers with
    others of its own choosing, it went well beyond the “bounds
    of its statutory authority.” Arlington, 569 U. S., at ___
    (slip op., at 5) (emphasis deleted).
    The Solicitor General does not, and cannot, defend the
    Tailoring Rule as an exercise of EPA’s enforcement discre-
    tion. The Tailoring Rule is not just an announcement of
    22        UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of the Court
    EPA’s refusal to enforce the statutory permitting require-
    ments; it purports to alter those requirements and to
    establish with the force of law that otherwise-prohibited
    conduct will not violate the Act. This alteration of the
    statutory requirements was crucial to EPA’s “tailoring”
    efforts. Without it, small entities with the potential to
    emit greenhouse gases in amounts exceeding the statutory
    thresholds would have remained subject to citizen suits—
    authorized by the Act—to enjoin their construction, modi-
    fication, or operation and to impose civil penalties of up to
    $37,500 per day of violation. §§7413(b), 7604(a), (f)(4); 40
    CFR §19.4. EPA itself has recently affirmed that the
    “independent enforcement authority” furnished by the
    citizen-suit provision cannot be displaced by a permitting
    authority’s decision not to pursue enforcement. 78 Fed.
    Reg. 12477, 12486–12487 (2013). The Solicitor General is
    therefore quite right to acknowledge that the availability
    of citizen suits made it necessary for EPA, in seeking
    to mitigate the unreasonableness of its greenhouse-gas-
    inclusive interpretation, to go beyond merely exercising its
    enforcement discretion. See Tr. of Oral Arg. 87–88.
    For similar reasons, Morton v. Ruiz, 
    415 U.S. 199
    (1974)—to which the Solicitor General points as the best
    case supporting the Tailoring Rule, see Tr. of Oral Arg. 71,
    80–81—is irrelevant. In Ruiz, Congress had appropriated
    funds for the Bureau of Indian Affairs to spend on provid-
    ing assistance to “ ‘Indians throughout the United States’ ”
    and had not “impose[d] any geographical limitation on the
    availability of general assistance benefits.” 
    Id., at 206–
    207, and n. 7. Although we held the Bureau could not
    deny benefits to off-reservation Indians because it had not
    published its eligibility criteria, we stated in dictum that
    the Bureau could, if it followed proper administrative
    procedures, “create reasonable classifications and eligibil-
    ity requirements in order to allocate the limited funds
    available.” 
    Id., at 230–231.
    That dictum stands only for
    Cite as: 573 U. S. ____ (2014)          23
    Opinion of the Court
    the unremarkable proposition that an agency may adopt
    policies to prioritize its expenditures within the bounds
    established by Congress. See also Lincoln v. Vigil, 
    508 U.S. 182
    , 192–193 (1993). Nothing in Ruiz remotely
    authorizes an agency to modify unambiguous require-
    ments imposed by a federal statute. An agency confront-
    ing resource constraints may change its own conduct, but
    it cannot change the law.
    Were we to recognize the authority claimed by EPA in
    the Tailoring Rule, we would deal a severe blow to the
    Constitution’s separation of powers. Under our system of
    government, Congress makes laws and the President,
    acting at times through agencies like EPA, “faithfully
    execute[s]” them. U. S. Const., Art. II, §3; see Medellín v.
    Texas, 
    552 U.S. 491
    , 526–527 (2008). The power of exe-
    cuting the laws necessarily includes both authority and
    responsibility to resolve some questions left open by Con-
    gress that arise during the law’s administration. But it
    does not include a power to revise clear statutory terms
    that turn out not to work in practice. See, e.g., Barnhart
    v. Sigmon Coal Co., 
    534 U.S. 438
    , 462 (2002) (agency
    lacked authority “to develop new guidelines or to assign
    liability in a manner inconsistent with” an “unambiguous
    statute”).
    In the Tailoring Rule, EPA asserts newfound authority
    to regulate millions of small sources—including retail
    stores, offices, apartment buildings, shopping centers,
    schools, and churches—and to decide, on an ongoing basis
    and without regard for the thresholds prescribed by Con-
    gress, how many of those sources to regulate. We are not
    willing to stand on the dock and wave goodbye as EPA
    embarks on this multiyear voyage of discovery. We reaf-
    firm the core administrative-law principle that an agency
    may not rewrite clear statutory terms to suit its own sense
    of how the statute should operate. EPA therefore lacked
    authority to “tailor” the Act’s unambiguous numerical
    24            UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of the Court
    thresholds to accommodate its greenhouse-gas-inclusive
    interpretation of the permitting triggers. Instead, the
    need to rewrite clear provisions of the statute should have
    alerted EPA that it had taken a wrong interpretive turn.
    Agencies are not free to “adopt . . . unreasonable interpre-
    tations of statutory provisions and then edit other statu-
    tory provisions to mitigate the unreasonableness.” App. 175,
    
    2012 WL 6621785
    , *16 (Kavanaugh, J., dissenting from
    denial of rehearing en banc). Because the Tailoring Rule
    cannot save EPA’s interpretation of the triggers, that
    interpretation was impermissible under Chevron.8
    B. BACT for “Anyway” Sources
    For the reasons we have given, EPA overstepped its
    statutory authority when it decided that a source could
    ——————
    8 JUSTICE BREYER argues, post, at 10 (opinion concurring in part and
    dissenting in part), that when the statutory permitting thresholds of
    100 or 250 tons per year do not provide a “sensible regulatory line,”
    EPA is entitled to “read an unwritten exception” into “the particular
    number used by the statute”—by which he apparently means that the
    Agency is entitled to substitute a dramatically higher number, such as
    100,000. We are aware of no principle of administrative law that would
    allow an agency to rewrite such a clear statutory term, and we shudder
    to contemplate the effect that such a principle would have on demo-
    cratic governance.
    JUSTICE BREYER, however, claims to perceive no difference between
    (a) reading the statute to exclude greenhouse gases from the term “any
    air pollutant” in the permitting triggers, and (b) reading the statute to
    exclude sources emitting less than 100,000 tons per year from the
    statutory phrase “any . . . source with the potential to emit two hundred
    and fifty tons per year or more.” See post, at 7. The two could scarcely
    be further apart. As we have explained (and as EPA agrees), statutory
    context makes plain that the Act’s operative provisions use “air pollu-
    tant” to denote less than the full range of pollutants covered by the Act-
    wide definition. See Part II–A–
    1, supra
    . It is therefore incumbent on
    EPA to specify the pollutants encompassed by that term in the context
    of a particular program, and to do so reasonably in light of that pro-
    gram’s overall regulatory scheme. But there is no ambiguity whatso-
    ever in the specific, numerical permitting thresholds, and thus no room
    for EPA to exercise discretion in selecting a different threshold.
    Cite as: 573 U. S. ____ (2014)           25
    Opinion of the Court
    become subject to PSD or Title V permitting by reason of
    its greenhouse-gas emissions. But what about “anyway”
    sources, those that would need permits based on their
    emissions of more conventional pollutants (such as partic-
    ulate matter)? We now consider whether EPA reasonably
    interpreted the Act to require those sources to comply with
    “best available control technology” emission standards for
    greenhouse gases.
    1
    To obtain a PSD permit, a source must be “subject to the
    best available control technology” for “each pollutant
    subject to regulation under [the Act]” that it emits.
    §7475(a)(4). The Act defines BACT as “an emission limita-
    tion based on the maximum degree of reduction of each
    pollutant subject to regulation” that is “achievable . . .
    through application of production processes and available
    methods, systems, and techniques, including fuel cleaning,
    clean fuels, or treatment or innovative fuel combustion
    techniques.” §7479(3). BACT is determined “on a case-by-
    case basis, taking into account energy, environmental, and
    economic impacts and other costs.” 
    Ibid. Some petitioners urge
    us to hold that EPA may never
    require BACT for greenhouse gases—even when a source
    must undergo PSD review based on its emissions of con-
    ventional pollutants—because BACT is fundamentally
    unsuited to greenhouse-gas regulation. BACT, they say,
    has traditionally been about end-of-stack controls “such as
    catalytic converters or particle collectors”; but applying it
    to greenhouse gases will make it more about regulating
    energy use, which will enable regulators to control “every
    aspect of a facility’s operation and design,” right down to
    the “light bulbs in the factory cafeteria.” Brief for Peti-
    tioner Energy-Intensive Manufacturers Working Group on
    Greenhouse Gas Regulation et al. in No. 12–1254, p. 7; see
    Joint Reply Brief for Petitioners in No. 12–1248 etc., pp.
    26        UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of the Court
    14–15 (“BACT for [greenhouse gases] becomes an un-
    bounded exercise in command-and-control regulation” of
    everything from “efficient light bulbs” to “basic industrial
    processes”). But see Brief for Calpine Corp. as Amicus
    Curiae 10 (“[I]n Calpine’s experience with ‘anyway’
    sources, the [greenhouse-gas] analysis was only a small
    part of the overall permitting process”).
    EPA has published a guidance document that lends
    some credence to petitioners’ fears. It states that at least
    initially, compulsory improvements in energy efficiency
    will be the “foundation” of greenhouse-gas BACT, with
    more traditional end-of-stack controls either not used or
    “added as they become more available.” PSD and Title V
    Permitting Guidance for Greenhouse Gases 29 (Mar. 2011)
    (hereinafter Guidance); see Peloso & Dobbins, Greenhouse
    Gas PSD Permitting: The Year in Review, 42 Tex. Env.
    L. J. 233, 247 (2012) (“Because [other controls] tend to
    prove infeasible, energy efficiency measures dominate the
    [greenhouse-gas] BACT controls approved by the states
    and EPA”). But EPA’s guidance also states that BACT
    analysis should consider options other than energy effi-
    ciency, such as “carbon capture and storage.” Guidance
    29, 32, 35–36, 42–43. EPA argues that carbon capture is
    reasonably comparable to more traditional, end-of-stack
    BACT technologies, 
    id., at 32,
    n. 86, and petitioners do not
    dispute that.
    Moreover, assuming without deciding that BACT may
    be used to force some improvements in energy efficiency,
    there are important limitations on BACT that may work
    to mitigate petitioners’ concerns about “unbounded” regu-
    latory authority. For one, BACT is based on “control
    technology” for the applicant’s “proposed facility,”
    §7475(a)(4); therefore, it has long been held that BACT
    cannot be used to order a fundamental redesign of the
    facility. See, e.g., Sierra Club v. EPA, 
    499 F.3d 653
    , 654–
    655 (CA7 2007); In re Pennsauken Cty., N. J., Resource
    Cite as: 573 U. S. ____ (2014)           27
    Opinion of the Court
    Recovery Facility, 2 E. A. D. 667, 673 (EAB 1988). For
    another, EPA has long interpreted BACT as required only
    for pollutants that the source itself emits, see 44 Fed. Reg.
    51947 (1979); accordingly, EPA acknowledges that BACT
    may not be used to require “reductions in a facility’s de-
    mand for energy from the electric grid.” Guidance 24.
    Finally, EPA’s guidance suggests that BACT should not
    require every conceivable change that could result in
    minor improvements in energy efficiency, such as the
    aforementioned light bulbs. 
    Id., at 31.
    The guidance
    explains that permitting authorities should instead con-
    sider whether a proposed regulatory burden outweighs
    any reduction in emissions to be achieved, and should
    concentrate on the facility’s equipment that uses the
    largest amounts of energy. 
    Ibid. 2 The question
    before us is whether EPA’s decision to
    require BACT for greenhouse gases emitted by sources
    otherwise subject to PSD review is, as a general matter, a
    permissible interpretation of the statute under Chevron.
    We conclude that it is.
    The text of the BACT provision is far less open-ended
    than the text of the PSD and Title V permitting triggers.
    It states that BACT is required “for each pollutant subject
    to regulation under this chapter” (i.e., the entire Act),
    §7475(a)(4), a phrase that—as the D. C. Circuit wrote 35
    years ago—“would not seem readily susceptible [of] misin-
    terpretation.” Alabama Power Co. v. Costle, 
    636 F.2d 323
    ,
    404 (1979). Whereas the dubious breadth of “any air
    pollutant” in the permitting triggers suggests a role for
    agency judgment in identifying the subset of pollutants
    covered by the particular regulatory program at issue, the
    more specific phrasing of the BACT provision suggests
    that the necessary judgment has already been made by
    Congress. The wider statutory context likewise does not
    28        UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of the Court
    suggest that the BACT provision can bear a narrowing
    construction: There is no indication that the Act elsewhere
    uses, or that EPA has interpreted, “each pollutant subject
    to regulation under this chapter” to mean anything other
    than what it says.
    Even if the text were not clear, applying BACT to
    greenhouse gases is not so disastrously unworkable, and
    need not result in such a dramatic expansion of agency
    authority, as to convince us that EPA’s interpretation is
    unreasonable. We are not talking about extending EPA
    jurisdiction over millions of previously unregulated enti-
    ties, but about moderately increasing the demands EPA
    (or a state permitting authority) can make of entities
    already subject to its regulation. And it is not yet clear
    that EPA’s demands will be of a significantly different
    character from those traditionally associated with PSD
    review. In short, the record before us does not establish
    that the BACT provision as written is incapable of being
    sensibly applied to greenhouse gases.
    We acknowledge the potential for greenhouse-gas BACT
    to lead to an unreasonable and unanticipated degree of
    regulation, and our decision should not be taken as an
    endorsement of all aspects of EPA’s current approach, nor
    as a free rein for any future regulatory application of
    BACT in this distinct context. Our narrow holding is that
    nothing in the statute categorically prohibits EPA from
    interpreting the BACT provision to apply to greenhouse
    gases emitted by “anyway” sources.
    However, EPA may require an “anyway” source to com-
    ply with greenhouse-gas BACT only if the source emits
    more than a de minimis amount of greenhouse gases. As
    noted above, the Tailoring Rule applies BACT only if a
    source emits greenhouse gases in excess of 75,000 tons per
    year CO2e, but the Rule makes clear that EPA did not
    arrive at that number by identifying the de minimis level.
    See nn. 1, 
    3, supra
    . EPA may establish an appropriate de
    Cite as: 573 U. S. ____ (2014)                  29
    Opinion of SCALIA, J.
    minimis threshold below which BACT is not required for a
    source’s greenhouse-gas emissions. We do not hold that
    75,000 tons per year CO2e necessarily exceeds a true de
    minimis level, only that EPA must justify its selection on
    proper grounds. Cf. Alabama 
    Power, supra, at 405
    .9
    *     *    *
    To sum up: We hold that EPA exceeded its statutory
    authority when it interpreted the Clean Air Act to require
    PSD and Title V permitting for stationary sources based
    on their greenhouse-gas emissions. Specifically, the Agency
    may not treat greenhouse gases as a pollutant for pur-
    poses of defining a “major emitting facility” (or a “modifi-
    cation” thereof) in the PSD context or a “major source” in
    the Title V context. To the extent its regulations purport
    to do so, they are invalid. EPA may, however, continue to
    treat greenhouse gases as a “pollutant subject to regula-
    tion under this chapter” for purposes of requiring BACT
    for “anyway” sources. The judgment of the Court of Ap-
    peals is affirmed in part and reversed in part.
    It is so ordered.
    ——————
    9 JUSTICE ALITO argues that BACT is “fundamentally incompatible”
    with greenhouse gases for two reasons. Post, at 4 (opinion concurring
    in part and dissenting in part). First, BACT requires consideration of
    “ambient air quality at the proposed site and in areas which may be
    affected by emissions from [the proposed] facility for each pollutant
    subject to regulation under this chapter,” §7475(e)(1); see also
    §7475(e)(3)(B); and it is not obvious how that requirement should apply,
    or even whether it can apply, to greenhouse gases. Post, at 4–5. But
    the possibility that that requirement may be inoperative as to green-
    house gases does not convince us that they must be categorically
    excluded from BACT even though they are indisputably a “pollutant
    subject to regulation.” Second, JUSTICE ALITO argues that EPA’s
    guidance on how to implement greenhouse-gas BACT is a recipe for
    “arbitrary and inconsistent decisionmaking.” Post, at 8. But we are not
    reviewing EPA’s guidance in these cases, and we cannot say that it is
    impossible for EPA and state permitting authorities to devise rational
    ways of complying with the statute’s directive to determine BACT for
    greenhouse gases “on a case-by-case basis, taking into account energy,
    environmental, and economic impacts and other costs.” §7479(3).
    Cite as: 573 U. S. ____ (2014)                  1
    Opinion of BREYER, J.
    SUPREME COURT OF THE UNITED STATES
    _________________
    Nos. 12–1146, 12–1248, 12–1254, 12–1268, 12–1269, and 12–1272
    _________________
    UTILITY AIR REGULATORY GROUP,
    PETITIONER
    12–1146                v.
    ENVIRONMENTAL PROTECTION AGENCY, ET AL.;
    AMERICAN CHEMISTRY COUNCIL, ET AL.,
    PETITIONERS
    12–1248             v.
    ENVIRONMENTAL PROTECTION AGENCY, ET AL.;
    ENERGY-INTENSIVE MANUFACTURERS WORKING
    GROUP ON GREENHOUSE GAS REGULATION,
    ET AL., PETITIONERS
    12–1254                v.
    ENVIRONMENTAL PROTECTION AGENCY, ET AL.;
    SOUTHEASTERN LEGAL FOUNDATION, INC.,
    ET AL., PETITIONERS
    12–1268                v.
    ENVIRONMENTAL PROTECTION AGENCY, ET AL.;
    TEXAS, ET AL., PETITIONERS
    12–1269                v.
    ENVIRONMENTAL PROTECTION AGENCY,
    ET AL.; AND
    CHAMBER OF COMMERCE OF THE UNITED
    STATES, ET AL., PETITIONERS
    12–1272               v.
    2         UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of BREYER, J.
    ENVIRONMENTAL PROTECTION AGENCY, ET AL.;
    ON WRITS OF CERTIORARI TO THE UNITED STATES COURT OF
    APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT
    [June 23, 2014]
    JUSTICE BREYER, with whom JUSTICE GINSBURG,
    JUSTICE SOTOMAYOR, and JUSTICE KAGAN join, concurring
    in part and dissenting in part.
    In Massachusetts v. EPA, 
    549 U.S. 497
    (2007), we held
    that greenhouse gases fall within the Clean Air Act’s
    general definition of the term “air pollutant,” 
    42 U.S. C
    .
    
    §7602(g). 549 U.S., at 528
    –529. We also held, conse-
    quently, that the Environmental Protection Agency is
    empowered and required by Title II of the Act to regulate
    greenhouse gas emissions from mobile sources (such as
    cars and trucks) if it decides that greenhouse gases “con-
    tribute to . . . air pollution which may reasonably be antic-
    ipated to endanger public health or welfare,” 
    §7521(a)(1). 549 U.S., at 532
    –533. The EPA determined that green-
    house gases endanger human health and welfare, 74 Fed.
    Reg. 66496 (2009) (Endangerment Finding), and so it
    issued regulations for mobile emissions, 75 Fed. Reg.
    25324 (2010) (Tailpipe Rule).
    These cases take as a given our decision in Massachu-
    setts that the Act’s general definition of “air pollutant”
    includes greenhouse gases. One of the questions posed by
    these cases is whether those gases fall within the scope of
    the phrase “any air pollutant” as that phrase is used in the
    more specific provisions of the Act here at issue. The
    Court’s answer is “no.” Ante, at 10–24. I disagree.
    The Clean Air Act provisions at issue here are Title I’s
    Prevention of Significant Deterioration (PSD) program,
    §7470 et seq., and Title V’s permitting regime, §7661 et
    seq. By contrast to Title II, Titles I and V apply to sta-
    tionary sources, such as power plants and factories. Un-
    Cite as: 573 U. S. ____ (2014)            3
    Opinion of BREYER, J.
    der the PSD program, “major emitting facilities” con-
    structed in the United States must meet certain require-
    ments, including obtaining a permit that imposes emis-
    sions limitations, §7475(a)(1), and using “the best
    available control technology for each pollutant subject to
    regulation under [the Act] emitted from” the facility,
    §7475(a)(4). Title V requires each “major source” to obtain
    an operating permit. §7661a(a).
    These cases concern the definitions of “major emitting
    facility” and “major source,” each of which is defined to
    mean any stationary source that emits more than a
    threshold quantity of “any air pollutant.” See §7479(1)
    (“major emitting facility”); §§7602(j), 7661(2)(B) (“major
    source”). To simplify the exposition, I will refer only to the
    PSD program and its definition of “major emitting facility”;
    a parallel analysis applies to Title V.
    As it is used in the PSD provisions,
    “[t]he term ‘major emitting facility’ means any of [a
    list of specific categories of] stationary sources of air
    pollutants which emit, or have the potential to emit,
    one hundred tons per year or more of any air pollutant
    . . . . Such term also includes any other source with
    the potential to emit two hundred and fifty tons per
    year or more of any air pollutant.” §7479(1).
    To simplify further, I will ignore the reference to specific
    types of source that emit at least 100 tons per year (tpy) of
    any air pollutant. In effect, we are dealing with a statute
    that says that the PSD program’s regulatory requirements
    must be applied to
    “any stationary source that has the potential to emit
    two hundred fifty tons per year or more of any air
    pollutant.”
    The interpretive difficulty in these cases arises out of
    the definition’s use of the phrase “two hundred fifty tons
    4         UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of BREYER, J.
    per year or more,” which I will call the “250 tpy threshold.”
    When applied to greenhouse gases, 250 tpy is far too low a
    threshold. As the Court explains, tens of thousands of
    stationary sources emit large quantities of one greenhouse
    gas, carbon dioxide. See ante, at 17–20, and n. 7. To
    apply the programs at issue here to all those sources
    would be extremely expensive and burdensome, counter-
    productive, and perhaps impossible; it would also contra-
    vene Congress’s intent that the programs’ coverage be
    limited to those large sources whose emissions are sub-
    stantial enough to justify the regulatory burdens. 
    Ibid. The EPA recognized
    as much, and it addressed the prob-
    lem by issuing a regulation—the Tailoring Rule—that
    purports to raise the coverage threshold for greenhouse
    gases from the statutory figure of 250 tpy to 100,000 tpy
    in order to keep the programs’ coverage limited to “a rela-
    tively small number of large industrial sources.” 75 Fed.
    Reg. 31514, 31555 (2010); see 
    id., at 31523–31524.
       The Tailoring Rule solves the practical problems that
    would have been caused by the 250 tpy threshold. But
    what are we to do about the statute’s language? The
    statute specifies a definite number—250, not 100,000—
    and it says that facilities that are covered by that number
    must meet the program’s requirements. The statute says
    nothing about agency discretion to change that number.
    What is to be done? How, given the statute’s language,
    can the EPA exempt from regulation sources that emit
    more than 250 but less than 100,000 tpy of greenhouse
    gases (and that also do not emit other regulated pollutants
    at threshold levels)?
    The Court answers by (1) pointing out that regulation at
    the 250 tpy threshold would produce absurd results, (2)
    refusing to read the statute as compelling such results,
    and (3) consequently interpreting the phrase “any air
    pollutant” as containing an implicit exception for green-
    house gases. (Emphasis added.) Put differently, the
    Cite as: 573 U. S. ____ (2014)             5
    Opinion of BREYER, J.
    Court reads the statute as defining “major emitting facility”
    to mean “stationary sources that have the potential to
    emit two hundred fifty tons per year or more of any air
    pollutant except for those air pollutants, such as carbon
    dioxide, with respect to which regulation at that threshold
    would be impractical or absurd or would sweep in smaller
    sources that Congress did not mean to cover.” See ante, at
    15–16 (“[T]here is no insuperable textual barrier to EPA’s
    interpreting ‘any air pollutant’ in the permitting triggers
    of PSD and Title V to encompass only pollutants emitted
    in quantities that enable them to be sensibly regulated at
    the statutory thresholds, and to exclude those atypical
    pollutants that, like greenhouse gases, are emitted in such
    vast quantities that their inclusion would radically trans-
    form those programs and render them unworkable as
    written”).
    I agree with the Court that the word “any,” when used
    in a statute, does not normally mean “any in the uni-
    verse.” Cf. FCC v. NextWave Personal Communications
    Inc., 
    537 U.S. 293
    , 311 (2003) (BREYER, J., dissenting)
    (“ ‘Tell all customers that . . .’ does not refer to every cus-
    tomer of every business in the world”). Rather, “[g]eneral
    terms as used on particular occasions often carry with
    them implied restrictions as to scope,” ibid., and so courts
    must interpret the word “any,” like all other words, in
    context. As Judge Learned Hand pointed out when inter-
    preting another statute many years ago, “[w]e can best
    reach the meaning here, as always, by recourse to the
    underlying purpose, and, with that as a guide, by trying to
    project upon the specific occasion how we think persons,
    actuated by such a purpose, would have dealt with it, if it
    had been presented to them at the time.” Borella v. Bor-
    den Co., 
    145 F.2d 63
    , 64 (CA2 1944). The pursuit of that
    underlying purpose may sometimes require us to “aban-
    don” a “literal interpretation” of a word like “any.” 
    Id., at 64–65.
    6         UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of BREYER, J.
    The law has long recognized that terms such as “any”
    admit of unwritten limitations and exceptions. Legal
    philosophers like to point out that a statute providing that
    “ ‘[w]hoever shall willfully take the life of another shall be
    punished by death’ ” need not encompass a man who kills
    in self-defense; nor must an ordinance imposing fines upon
    those who occupy a public parking spot for more than two
    hours penalize a driver who is unable to move because of a
    parade. See Fuller, The Case of the Speluncean Explorers,
    62 Harv. L. Rev. 616, 619, 624 (1949); see also United
    States v. Kirby, 
    7 Wall. 482
    , 485–487 (1869) (holding that
    a statute forbidding knowing and willful obstruction of the
    mail contains an implicit exception permitting a local
    sheriff to arrest a mail carrier). The maxim cessante
    ratione legis cessat ipse lex—where a law’s rationale ceases
    to apply, so does the law itself—is not of recent origin.
    See, e.g., Zadvydas v. Davis, 
    533 U.S. 678
    , 699 (2001)
    (citing 1 E. Coke, Institutes *70b); Green v. Liter, 8 Cranch
    229, 249 (1814) (Story, J.) (“cessante ratione, cessat ipsa
    lex”).
    I also agree with the Court’s point that “a generic refer-
    ence to air pollutants” in the Clean Air Act need not “en-
    compass every substance falling within the Act-wide
    definition” that we construed in Massachusetts, §7602(g).
    See ante, at 12–13. As the Court notes, the EPA has
    interpreted the phrase “any air pollutant,” which is used
    several times in the Act, as limited to “air pollutants for
    which EPA has promulgated [new source performance
    standards]” in the portion of the Act dealing with those
    standards, as limited to “visibility-impairing air pollu-
    tants” in the part of the Act concerned with deleterious
    effects on visibility, and as limited to “pollutants for which
    the area is designated nonattainment” in the part of the
    Act aimed at regions that fail to attain air quality stand-
    ards. 
    Ibid. But I do
    not agree with the Court that the only way to
    Cite as: 573 U. S. ____ (2014)            7
    Opinion of BREYER, J.
    avoid an absurd or otherwise impermissible result in these
    cases is to create an atextual greenhouse gas exception to
    the phrase “any air pollutant.” After all, the word “any”
    makes an earlier appearance in the definitional provision,
    which defines “major emitting facility” to mean “any . . .
    source with the potential to emit two hundred and fifty
    tons per year or more of any air pollutant.” §7479(1)
    (emphasis added). As a linguistic matter, one can just as
    easily read an implicit exception for small-scale green-
    house gas emissions into the phrase “any source” as into
    the phrase “any air pollutant.” And given the purposes of
    the PSD program and the Act as a whole, as well as the
    specific roles of the different parts of the statutory defini-
    tion, finding flexibility in “any source” is far more sensible
    than the Court’s route of finding it in “any air pollutant.”
    The implicit exception I propose reads almost word for
    word the same as the Court’s, except that the location of
    the exception has shifted. To repeat, the Court reads the
    definition of “major emitting facility” as if it referred to
    “any source with the potential to emit two hundred fifty
    tons per year or more of any air pollutant except for those
    air pollutants, such as carbon dioxide, with respect to
    which regulation at that threshold would be impractical or
    absurd or would sweep in smaller sources that Congress
    did not mean to cover.” I would simply move the implicit
    exception, which I’ve italicized, so that it applies to
    “source” rather than “air pollutant”: “any source with the
    potential to emit two hundred fifty tons per year or more
    of any air pollutant except for those sources, such as those
    emitting unmanageably small amounts of greenhouse
    gases, with respect to which regulation at that threshold
    would be impractical or absurd or would sweep in smaller
    sources that Congress did not mean to cover.”
    From a legal, administrative, and functional perspec-
    tive—that is, from a perspective that assumes that Con-
    gress was not merely trying to arrange words on paper but
    8         UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of BREYER, J.
    was seeking to achieve a real-world purpose—my way of
    reading the statute is the more sensible one. For one
    thing, my reading is consistent with the specific purpose
    underlying the 250 tpy threshold specified by the statute.
    The purpose of that number was not to prevent the regula-
    tion of dangerous air pollutants that cannot be sensibly
    regulated at that particular threshold, though that is the
    effect that the Court’s reading gives the threshold. Ra-
    ther, the purpose was to limit the PSD program’s obliga-
    tions to larger sources while exempting the many small
    sources whose emissions are low enough that imposing
    burdensome regulatory requirements on them would be
    senseless.
    Thus, the accompanying Senate Report explains that
    the PSD program “is reasonable and necessary for very
    large sources, such as new electrical generating plants or
    new steel mills. But the procedure would prove costly and
    potentially unreasonable if imposed on construction of
    storage facilities for a small gasoline jobber or on the
    construction of a new heating plant at a junior college.”
    S. Rep. No. 95–127, p. 96 (1977). And the principal spon-
    sor of the Clean Air Act amendments at issue here, Sena-
    tor Edmund Muskie, told the Senate that the program
    would not cover “houses, dairies, farms, highways, hospi-
    tals, schools, grocery stores, and other such sources.” 123
    Cong. Rec. 18013, 18021 (1977).
    The EPA, exercising the legal authority to which it is
    entitled under Chevron U. S. A. Inc. v. Natural Resources
    Defense Council, Inc., 
    467 U.S. 837
    (1984), understood the
    threshold’s purpose in the same light. It explained that
    Congress’s objective was
    “to limit the PSD program to large industrial sources
    because it was those sources that were the primary
    cause of the pollution problems in question and be-
    cause those sources would have the resources to com-
    Cite as: 573 U. S. ____ (2014)            9
    Opinion of BREYER, J.
    ply with the PSD requirements. Congress’s mecha-
    nism for limiting PSD was the 100/250 tpy threshold
    limitations. Focused as it was primarily on NAAQS
    pollutants [that is, those air pollutants for which the
    EPA has issued a national ambient air quality stand-
    ard under Title I of the Act, see EPA v. EME Homer
    City Generation, L. P., 572 U. S. ___, ___ (2014) (slip
    op., at 4)], Congress considered sources that emit
    NAAQS pollutants in those quantities generally to be
    the large industrial sources to which it intended PSD
    to be limited.” Tailoring Rule, 75 Fed. Reg. 31555.
    The Court similarly acknowledges that “the PSD pro-
    gram and Title V are designed to apply to, and cannot
    rationally be extended beyond, a relative handful of large
    sources capable of shouldering heavy substantive and
    procedural burdens.” Ante, at 18; see also Alabama Power
    Co. v. Costle, 
    636 F.2d 323
    , 353 (CADC 1979) (“Congress’s
    intention was to identify facilities which, due to their size,
    are financially able to bear the substantial regulatory
    costs imposed by the PSD provisions and which, as a
    group, are primarily responsible for emission of the delete-
    rious pollutants that befoul our nation’s air”).
    An implicit source-related exception would serve this
    statutory purpose while going no further. The implicit
    exception that the Court reads into the phrase “any air
    pollutant,” by contrast, goes well beyond the limited con-
    gressional objective. Nothing in the statutory text, the
    legislative history, or common sense suggests that Con-
    gress, when it imposed the 250 tpy threshold, was trying
    to undermine its own deliberate decision to use the broad
    language “any air pollutant” by removing some substances
    (rather than some facilities) from the PSD program’s
    coverage.
    For another thing, a source-related exception serves the
    flexible nature of the Clean Air Act. We observed in Mas-
    10        UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of BREYER, J.
    sachusetts that “[w]hile the Congresses that drafted” the
    Act “might not have appreciated the possibility that burn-
    ing fossil fuels could lead to global warming, they did
    understand that without regulatory flexibility, changing
    circumstances and scientific developments would soon
    render the Clean Air Act 
    obsolete.” 549 U.S., at 532
    . We
    recognized that “[t]he broad language of ” the Act-wide
    definition of “air pollutant” “reflects an intentional effort
    to confer the flexibility necessary to forestall such obsoles-
    cence.” 
    Ibid. The Court’s decision
    to read greenhouse gases out of the
    PSD program drains the Act of its flexibility and chips
    away at our decision in Massachusetts. What sense does it
    make to read the Act as generally granting the EPA the
    authority to regulate greenhouse gas emissions and then
    to read it as denying that power with respect to the pro-
    grams for large stationary sources at issue here? It is
    anomalous to read the Act to require the EPA to regulate
    air pollutants that pose previously unforeseen threats to
    human health and welfare where “250 tons per year” is a
    sensible regulatory line but not where, by chemical or
    regulatory happenstance, a higher line must be drawn.
    And it is anomalous to read an unwritten exception into
    the more important phrase of the statutory definition
    (“any air pollutant”) when a similar unwritten exception to
    less important language (the particular number used by
    the statute) will do just as well. The implicit exception
    preferred by the Court produces all of these anomalies,
    while the source-related exception I propose creates none
    of them.
    In addition, the interpretation I propose leaves the EPA
    with the sort of discretion as to interstitial matters that
    Congress likely intended it to retain. My interpretation
    gives the EPA nothing more than the authority to exempt
    sources from regulation insofar as the Agency reasonably
    determines that applying the PSD program to them would
    Cite as: 573 U. S. ____ (2014)            11
    Opinion of BREYER, J.
    expand the program so much as to contravene Congress’s
    intent. That sort of decision, which involves the Agency’s
    technical expertise and administrative experience, is the
    kind of decision that Congress typically leaves to the
    agencies to make. Cf. Barnhart v. Walton, 
    535 U.S. 212
    ,
    222 (2002) (enumerating factors that we take to indicate
    that Congress intends the agency to exercise the discre-
    tion provided by Chevron). To read the Act to grant that
    discretion here is to read it as furthering Congress’s (and
    the public’s) interest in more effective, less wasteful
    regulation.
    Last, but by no means least, a source-related exception
    advances the Act’s overall purpose. That broad purpose,
    as set forth at the beginning of the statute, is “to protect
    and enhance the quality of the Nation’s air resources so as
    to promote the public health and welfare and the produc-
    tive capacity of its population.” §7401(b)(1); see also
    §7470(1) (A purpose of the PSD program in particular
    is “to protect public health and welfare from any actual
    or potential adverse effect which in the Administra-
    tor’s judgment may reasonably be anticipate[d] to occur
    from air pollution”); §7602(h) (“All language [in the Act]
    referring to effects on welfare includes . . . effects on . . .
    weather . . . and climate”). The expert agency charged
    with administering the Act has determined in its En-
    dangerment Finding that greenhouse gases endanger
    human health and welfare, and so sensible regulation of
    industrial emissions of those pollutants is at the core of
    the purpose behind the Act. The broad “no greenhouse
    gases” exception that the Court reads into the statute
    unnecessarily undercuts that purpose, while my narrow
    source-related exception would leave the Agency with the
    tools it needs to further it.
    *     *     *
    I agree with the Court’s holding that stationary sources
    12        UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of BREYER, J.
    that are subject to the PSD program because they emit
    other (non-greenhouse-gas) pollutants in quantities above
    the statutory threshold—those facilities that the Court
    refers to as “anyway” sources—must meet the “best avail-
    able control technology” requirement of §7475(a)(4) with
    respect to greenhouse gas emissions. I therefore join Part
    II–B–2 of the Court’s opinion. But as for the Court’s hold-
    ing that the EPA cannot interpret the language at issue
    here to cover facilities that emit more than 100,000 tpy of
    greenhouse gases by virtue of those emissions, I respect-
    fully dissent.
    Cite as: 573 U. S. ____ (2014)                  1
    Opinion of ALITO, J.
    SUPREME COURT OF THE UNITED STATES
    _________________
    Nos. 12–1146, 12–1248, 12–1254, 12–1268, 12–1269, and 12–1272
    _________________
    UTILITY AIR REGULATORY GROUP,
    PETITIONER
    12–1146                v.
    ENVIRONMENTAL PROTECTION AGENCY, ET AL.;
    AMERICAN CHEMISTRY COUNCIL, ET AL.,
    PETITIONERS
    12–1248             v.
    ENVIRONMENTAL PROTECTION AGENCY, ET AL.;
    ENERGY-INTENSIVE MANUFACTURERS WORKING
    GROUP ON GREENHOUSE GAS REGULATION,
    ET AL., PETITIONERS
    12–1254                v.
    ENVIRONMENTAL PROTECTION AGENCY, ET AL.;
    SOUTHEASTERN LEGAL FOUNDATION, INC.,
    ET AL., PETITIONERS
    12–1268                v.
    ENVIRONMENTAL PROTECTION AGENCY, ET AL.;
    TEXAS, ET AL., PETITIONERS
    12–1269                v.
    ENVIRONMENTAL PROTECTION AGENCY,
    ET AL.; AND
    CHAMBER OF COMMERCE OF THE UNITED
    STATES, ET AL., PETITIONERS
    12–1272               v.
    2         UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of ALITO, J.
    ENVIRONMENTAL PROTECTION AGENCY, ET AL.;
    ON WRITS OF CERTIORARI TO THE UNITED STATES COURT OF
    APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT
    [June 23, 2014]
    JUSTICE ALITO, with whom JUSTICE THOMAS joins,
    concurring in part and dissenting in part.
    In Massachusetts v. EPA, 
    549 U.S. 497
    (2007), this
    Court considered whether greenhouse gases fall within the
    Clean Air Act’s general definition of an air “pollutant.”
    
    Id., at 528–529.
    The Environmental Protection Agency
    cautioned us that “key provisions of the [Act] cannot co-
    gently be applied to [greenhouse gas] emissions,” Brief for
    Federal Respondent in Massachusetts v. EPA, O. T. 2006,
    No. 05–1120, p. 22, but the Court brushed the warning
    aside and had “little trouble” concluding that the Act’s
    “sweeping definition” of a pollutant encompasses green-
    house 
    gases. 549 U.S., at 528
    –529. I believed Massachu-
    setts v. EPA was wrongly decided at the time, and these
    cases further expose the flaws with that decision.
    I
    As the present cases now show, trying to fit greenhouse
    gases into “key provisions” of the Clean Air Act involves
    more than a “little trouble.” These cases concern the
    provisions of the Act relating to the “Prevention of Signifi-
    cant Deterioration” (PSD), 
    42 U.S. C
    . §§7470–7492, as
    well as Title V of the Act, §7661. And in order to make
    those provisions apply to greenhouse gases in a way that
    does not produce absurd results, the EPA effectively
    amended the Act. The Act contains specific emissions
    thresholds that trigger PSD and Title V coverage, but the
    EPA crossed out the figures enacted by Congress and
    substituted figures of its own.
    I agree with the Court that the EPA is neither required
    nor permitted to take this extraordinary step, and I there-
    Cite as: 573 U. S. ____ (2014)           3
    Opinion of ALITO, J.
    fore join Parts I and II–A of the Court’s opinion.
    II
    I do not agree, however, with the Court’s conclusion that
    what it terms “anyway sources,” i.e., sources that are
    subject to PSD and Title V permitting as the result of the
    emission of conventional pollutants, must install “best
    available control technology” (BACT) for greenhouse gases.
    As is the case with the PSD and Title V thresholds,
    trying to fit greenhouse gases into the BACT analysis
    badly distorts the scheme that Congress adopted.
    The Court gives two main reasons for concluding that
    BACT applies to “anyway” sources, one based on text
    and one based on practical considerations. Neither is
    convincing.
    A
    With respect to the text, it is curious that the Court,
    having departed from a literal interpretation of the term
    “pollutant” in Part II–A, turns on its heels and adopts a
    literal interpretation in Part II–B. The coverage thresh-
    olds at issue in Part II–A apply to any “pollutant.” The
    Act’s general definition of this term is broad, and in Mas-
    sachusetts v. 
    EPA, supra
    , the Court held that this defini-
    tion covers greenhouse gases. The Court does not disturb
    that holding, but it nevertheless concludes that, as used in
    the provision triggering PSD coverage, the term “pollu-
    tant” actually means “pollutant, other than a greenhouse
    gas.”
    In Part II–B, the relevant statutory provision says
    that BACT must be installed for any “pollutant subject
    to regulation under [the Act].” §7475(a)(4). If the term
    “pollutant” means “pollutant, other than a greenhouse
    gas,” as the Court effectively concludes in Part II–A, the
    term “pollutant subject to regulation under [the Act]” in
    §7475(a)(4) should mean “pollutant, other than a green-
    4         UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of ALITO, J.
    house gas, subject to regulation under [the Act], and that
    is subject to regulation under [the Act].” The Court’s
    literalism is selective, and it results in a strange and
    disjointed regulatory scheme.
    Under the Court’s interpretation, a source can emit an
    unlimited quantity of greenhouse gases without triggering
    the need for a PSD permit. Why might Congress have
    wanted to allow this? The most likely explanation is that
    the PSD permitting process is simply not suited for use in
    regulating this particular pollutant. And if that is so, it
    makes little sense to require the installation of BACT for
    greenhouse gases in those instances in which a source
    happens to be required to obtain a permit due to the emis-
    sion of a qualifying quantity of some other pollutant that
    is regulated under the Act.
    B
    The Court’s second reason for holding that BACT ap-
    plies to “anyway” sources is its belief that this can be done
    without disastrous consequences. Only time will tell
    whether this hope is well founded, but it seems clear that
    BACT analysis is fundamentally incompatible with the
    regulation of greenhouse-gas emissions for at least two
    important reasons.
    1
    First, BACT looks to the effects of covered pollutants in
    the area in which a source is located. The PSD program is
    implemented through “emission limitations and such
    other measures” as are “necessary . . . to prevent signifi-
    cant deterioration of air quality in each region.” §7471
    (emphasis added). The Clean Air Act provides that BACT
    must be identified “on a case-by-case basis,” §7479(3), and
    this necessarily means that local conditions must be taken
    into account. For this reason, the Act instructs the EPA to
    issue regulations requiring an analysis of “the ambient air
    Cite as: 573 U. S. ____ (2014)             5
    Opinion of ALITO, J.
    quality . . . at the site of the proposed major emitting facil-
    ity and in the area potentially affected by the emissions
    from such facility for each pollutant regulated under [the
    Act].” §7475(e)(3)(B) (emphasis added). The Act also
    requires a public hearing on “the air quality at the pro-
    posed site and in areas which may be affected by emissions
    from such facility for each pollutant subject to regulation
    under [the Act] which will be emitted from such facility.”
    §§7475(a)(2), (e)(1) (emphasis added). Accordingly, if
    BACT is required for greenhouse gases, the Act demands
    that the impact of these gases in the area surrounding a
    site must be monitored, explored at a public hearing, and
    considered as part of the permitting process. The effects of
    greenhouse gases, however, are global, not local. See PSD
    and Title V Permitting Guidance for Greenhouse Gases
    41–42 (Mar. 2011) (hereinafter Guidance). As a result, the
    EPA has declared that PSD permit applicants and permit-
    ting officials may disregard these provisions of the Act. 75
    Fed. Reg. 31520 (2010).
    2
    Second, as part of the case-by-case analysis required by
    BACT, a permitting authority must balance the environ-
    mental benefit expected to result from the installation of
    an available control measure against adverse consequences
    that may result, including any negative impact on the
    environment, energy conservation, and the economy. And
    the EPA itself has admitted that this cannot be done on a
    case-by-case basis with respect to greenhouse gases.
    The Clean Air Act makes it clear that BACT must be
    determined on a “case-by-case basis, taking into account
    energy, environmental, and economic impacts and other
    costs.” §7479(3). To implement this directive, the EPA
    adopted a five-step framework for making a BACT deter-
    mination. See New Source Review Workshop Manual:
    Prevention of Significant Deterioration and Nonattain-
    6            UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of ALITO, J.
    ment Area Permitting (Oct. 1990).1 Under the fourth step
    of this analysis, potentially applicable and feasible control
    technologies that are candidates for selection as BACT for
    a particular source are eliminated from consideration
    based on their “collateral impacts,” such as any adverse
    environmental effects or adverse effects on energy con-
    sumption or the economy.
    More recently, the EPA provided guidance to permitting
    authorities regarding the treatment of greenhouse-gas
    emissions under this framework, and the EPA’s guidance
    demonstrates the insuperable problem that results when
    an attempt is made to apply this framework to greenhouse
    gas emissions. As noted above, at step 4 of the framework,
    a permitting authority must balance the positive effect
    likely to result from requiring a particular source to install
    a particular technology against a variety of negative ef-
    fects that are likely to occur if that step is taken. But
    in the case of greenhouse gases, how can a permit-
    ting authority make this individualized, source-specific
    determination?
    The EPA instructs permitting authorities to take into
    ——————
    1 The
    EPA describes these steps as follows:
    (1) The applicant must identify all available control options that are
    potentially applicable by consulting EPA’s BACT clearinghouse along
    with other reliable sources.
    (2) The technical feasibility of the control options identified in step 1
    are eliminated based on technical infeasibility.
    (3) The control technologies are ranked based on control effective-
    ness, by considering: the percentage of the pollutant removed; expected
    emission rate for each new source review (NSR) pollutant; expected
    emission reduction for each regulated NSR pollutant; and output based
    emissions limit.
    (4) Control technologies are eliminated based on collateral impacts,
    such as: energy impacts; other environmental impacts; solid or hazard-
    ous waste; water discharge from control device; emissions of air toxics
    and other non-NSR regulated pollutants; and economic impacts.
    (5) The most effective control option not eliminated in step 4 is
    proposed as BACT for the pollutant and emission unit under review.
    Cite as: 573 U. S. ____ (2014)                 7
    Opinion of ALITO, J.
    consideration all the adverse effects that the EPA has
    found to result from the overall increase in greenhouse
    gases in the atmosphere. These include an increased risk
    of dangerous heat waves, hurricanes, floods, wildfires, and
    drought, as well as risks to agriculture, forestry, and
    water resources. Guidance 40–41. But the EPA admits
    that it is simply not possible for a permitting authority to
    calculate in any meaningful way the degree to which any
    potential reduction in greenhouse gas emissions from any
    individual source might reduce these risks. And without
    making such a calculation in even a very rough way, a
    permitting authority cannot do what the Clean Air Act
    and the EPA’s framework demand—compare the benefits
    of some specified reduction in the emission of greenhouse
    gases from a particular source with any adverse environ-
    mental or economic effects that might result from mandat-
    ing such a reduction.
    Suppose, for example, that a permitting authority must
    decide whether to mandate a change that both decreases a
    source’s emission of greenhouse gases and increases its
    emission of a conventional pollutant that has a negative
    effect on public health. How should a permitting authority
    decide whether to require this change? Here is the EPA’s
    advice:
    “[W]hen considering the trade-offs between the envi-
    ronmental impacts of a particular level of GHG
    [greenhouse gas] reduction and a collateral increase in
    another regulated NSR pollutant,[2] rather than at-
    tempting to determine or characterize specific envi-
    ronmental impacts from GHGs emitted at particular
    locations, EPA recommends that permitting authori-
    ties focus on the amount of GHG emission reductions
    ——————
    2 “New source review pollutants” are those pollutants for which a
    National Ambient Air Quality standard has been set and a few others,
    such as sulphur dioxide. See 40 CFR 51.165(a)(1)(xxxvii) (2013).
    8             UTILITY AIR REGULATORY GROUP v. EPA
    Opinion of ALITO, J.
    that may be gained or lost by employing a particular
    control strategy and how that compares to the envi-
    ronmental or other impacts resulting from the collat-
    eral emissions increase of other regulated NSR pollu-
    tants.” Guidance 42.
    As best I can make out, what this means is that permit-
    ting authorities should not even try to assess the net
    impact on public health. Instead of comparing the positive
    and negative public health effects of a particular option,
    permitting authorities are instructed to compare the
    adverse public health effects of increasing the emissions of
    the conventional pollutants with the amount of the reduc-
    tion of the source’s emissions of greenhouse gases. But
    without knowing the positive effects of the latter, this is a
    meaningless comparison.
    The EPA tries to ameliorate this problem by noting that
    permitting authorities are entitled to “a great deal of
    discretion,” Guidance 41, but without a comprehensible
    standard, what this will mean is arbitrary and incon-
    sistent decisionmaking. That is not what the Clean Air
    Act contemplates.3
    *     *    *
    BACT analysis, like the rest of the Clean Air Act, was
    developed for use in regulating the emission of conven-
    tional pollutants and is simply not suited for use with
    respect to greenhouse gases. I therefore respectfully
    dissent from Part II–B–2 of the opinion of the Court.
    ——————
    3 WhileI do not think that BACT applies at all to “anyway sources,” if
    it is to apply, the limitations suggested in Part II–B–1 might lessen the
    inconsistencies highlighted in Part II of this opinion, and on that
    understanding I join Part II–B–1.
    

Document Info

Docket Number: 12-1146

Filed Date: 6/23/2014

Precedential Status: Precedential

Modified Date: 5/7/2020

Cited By (95)

Biodiversity Conservation Alliance v. Jiron ( 2014 )

S. Coast Air Quality Mgmt. Dist. v. Envtl. Prot. Agency ( 2018 )

United States Telecom Ass'n v. Federal Communications ... ( 2016 )

Nucor Steel-Arkansas v. Big River Steel, LLC ( 2016 )

United States v. David Husmann ( 2014 )

United States v. Manuel Soto ( 2015 )

Diller v. Diller ( 2021 )

Joseph Pakootas v. Teck Cominco Metals, Ltd. ( 2016 )

Lawrence + Memorial Hospital v. Burwell ( 2016 )

Boris Khazin v. TD Ameritrade Holding Corp ( 2014 )

Redus Florida Commercial, LLC v. College Station Retail ... ( 2014 )

Norfolk Southern Railway Co. v. Thomas Perez ( 2015 )

Oregon Restaurant and Lodging v. Thomas Perez ( 2016 )

Cumberland County Hospital System, Inc. v. Burwell ( 2016 )

New Mexico v. Department of the Interior ( 2017 )

City & County of San Francisco v. Donald Trump ( 2018 )

Louisiana State v. United States Army Corps of Engineers ( 2016 )

Helping Hand Tools v. U.S. Environmental Protection Agency ( 2016 )

National Biodiesel Board v. Environmental Protection Agency ( 2016 )

Healthalliance Hospitals, Inc. v. Price ( 2018 )

View All Citing Opinions »