State ex rel. Doner v. Zody , 130 Ohio St. 3d 446 ( 2011 )


Menu:
  • [Cite as State ex rel. Doner v. Zody, 
    130 Ohio St.3d 446
    , 
    2011-Ohio-6117
    .]
    THE STATE EX REL. DONER ET AL. v. ZODY, DIR., ET AL.
    [Cite as State ex rel. Doner v. Zody, 
    130 Ohio St.3d 446
    , 
    2011-Ohio-6117
    .]
    Eminent domain—Flooding allegedly caused by government-constructed spillway
    and by government policies for managing lake level—Statute of
    limitations—R.C. 2305.09(E) applies—Running of limitations period is
    tolled when act on government’s land causes continuing damage to
    another’s property and when government retains control over structure or
    condition that causes damage—Burden of proof in mandamus cases is
    clear and convincing evidence—Mandamus is proper vehicle for
    compelling government to institute appropriation proceedings for taking
    of private property—Claimant establishes taking in government-induced
    flooding cases by showing that flooding was either deliberate result of
    government action or natural, direct result thereof and that flooding is
    either permanent invasion or inevitably recurring invasion.
    (No. 2009-1292—Submitted September 20, 2011—Decided December 1, 2011.)
    IN MANDAMUS.
    __________________
    SYLLABUS OF THE COURT
    1. Under R.C. 2305.09(E), an action for relief on the grounds of a physical or
    regulatory taking of real property must generally be brought within four
    years after the cause of action accrued. (State ex rel. Nickoli v. Erie
    MetroParks, 
    124 Ohio St.3d 449
    , 
    2010-Ohio-606
    , 
    923 N.E.2d 588
    ,
    approved and followed.)
    2. When an act carried out on the actor’s own land causes continuing damage to
    another’s property and the actor’s conduct or retention of control is of a
    SUPREME COURT OF OHIO
    continuing nature, the statute of limitations is tolled. (Sexton v. Mason,
    
    117 Ohio St.3d 275
    , 
    2008-Ohio-858
    , 
    883 N.E.2d 1013
    ; State v. Swartz
    (2000), 
    88 Ohio St.3d 131
    , 
    723 N.E.2d 1084
    ; and Valley Ry. Co. v. Franz
    (1885), 
    43 Ohio St. 623
    , 
    4 N.E. 88
    , approved and followed; R.C.
    2305.09(E), construed.)
    3. Relators in mandamus cases must prove their entitlement to the writ by clear
    and convincing evidence. (State ex rel. Pressley v. Indus. Comm. (1967),
    
    11 Ohio St.2d 141
    , 
    40 O.O.2d 141
    , 
    228 N.E.2d 631
    ; and State ex rel.
    Henslee v. Newman (1972), 
    30 Ohio St.2d 324
    , 
    59 O.O.2d 386
    , 
    285 N.E.2d 54
    , approved and followed.)
    4. Mandamus is the appropriate action to compel public authorities to institute
    appropriation proceedings when an involuntary taking of private property
    is alleged. Any direct encroachment upon land that subjects it to a public
    use that excludes or restricts the dominion and control of the owner over it
    is a taking of property, for which the owner is guaranteed a right of
    compensation under Section 19, Article I of the Ohio Constitution. (State
    ex rel. Shemo v. Mayfield Hts. (2002), 
    95 Ohio St.3d 59
    , 63, 
    765 N.E.2d 345
    ; and Norwood v. Sheen (1933), 
    126 Ohio St. 482
    , 
    186 N.E. 102
    ,
    approved and followed.)
    5. In eminent-domain cases involving claims of government-induced flooding,
    the claimant establishes a taking by proving that (1) the flooding is either
    intended by the government or is the direct, natural, or probable result of
    government-authorized activity and (2) the flooding is either a permanent
    invasion or creates a permanent liability because of intermittent, but
    inevitably recurring, overflows.     (Ridge Line, Inc. v. United States
    (Fed.Cir.2003), 
    346 F.3d 1346
    ; and Cary v. United States (Fed.Cir.2009),
    
    552 F.3d 1373
    , approved.)
    __________________
    2
    January Term, 2011
    MCGEE BROWN, J.
    {¶ 1} This is an action by relators, owners of land located downstream
    from the western spillway of Grand Lake St. Marys, for a writ of mandamus to
    compel respondents, the Ohio Department of Natural Resources (“ODNR”) and
    its director, Scott A. Zody,1 to initiate appropriation proceedings for the physical
    taking of their property resulting from flooding caused by a spillway constructed
    by respondents and the state’s lake-level-management practices. We find that
    relators’ claim is not barred by the applicable statute of limitations and that they
    have established a taking; therefore, we grant the writ.
    Facts
    Grand Lake St. Marys
    {¶ 2} Grand Lake St. Marys (“GLSM”) is a man-made lake located in
    Mercer and Auglaize Counties in Ohio. GLSM was created between 1837 and
    1841 as a water source for the Miami-Erie Canal by damming the headwaters of
    the Wabash and St. Marys Rivers and flooding the area in between. By the early
    20th century, the use of the canal had decreased, and the lake’s primary purpose
    changed. In 1949, the state designated GLSM as a state park and placed it under
    ODNR’s authority.
    {¶ 3} GLSM is about 8.2 miles long, covers roughly 13,500 acres, and
    drains an area of about 112 square miles. Without the lake, about 59 percent of
    the GLSM watershed would drain to the west and eventually into the Mississippi
    River, and the remaining 41 percent would drain to the east into the St. Marys
    River and eventually into Lake Erie.
    {¶ 4} The dam at GLSM is an earthen embankment about 5,540 feet long.
    In 1914, a 39.4-foot curved spillway was constructed on the western shoreline of
    1. This case was instituted against then director Sean D. Logan, but he was subsequently replaced
    by David Mustine, who has now been replaced by Scott A. Zody as the director of ODNR. Zody
    is thus automatically substituted as a respondent in this case. S.Ct.Prac.R. 10.2 and Civ.R.
    25(D)(1).
    3
    SUPREME COURT OF OHIO
    the lake that feeds into Beaver Creek. The spillway had a crest elevation of 870
    feet above mean sea level and four gated outlet conduits. Between 1985 and
    1997, only two of the four gates worked. GLSM discharges water from the
    western spillway into Beaver Creek, which in turn discharges water into the
    Wabash River, which flows in a westerly direction from Ohio into Indiana.
    Although a gate also existed at the eastern end of the lake, that gate had limited
    discharge capabilities. ODNR thus used the western spillway for virtually all
    water flow out of the lake.
    {¶ 5} A 1978 inspection showed that the western spillway at GLSM could
    not pass a probable maximum flood2 without overtopping for 48 hours, which
    would result in the eventual failure of the dam and catastrophic flooding. This
    potential for failure presented an unacceptable risk for people and property
    downstream from the western spillway. In 1988, ODNR raised the crest elevation
    of the spillway to 870.6 feet by placing four-inch wooden boards at the crest of
    the old spillway.
    {¶ 6} In 1990, ODNR determined that the 39.4-foot spillway needed to be
    replaced with a 500-foot spillway to pass the probable-maximum-flood test.
    ODNR began construction of the new spillway in 1996 and completed it in 1997.
    The new spillway has a crest elevation of 871.5 feet above mean sea level with a
    50-foot-long notch in its center at 870.6 feet above mean sea level.
    {¶ 7} The redesigned spillway permanently established the four-inch
    increase in the lake level that ODNR had first achieved in 1988 by placing “stop
    logs” across the spillway to increase recreational value to boaters at GLSM.
    ODNR had previously regulated the lake level at GLSM by lowering it through
    the old spillway’s gated outlets by 12 inches almost every winter. However, after
    the new spillway—which has two 60-inch outlets near the bottom of the
    2. A “probable maximum flood” has been described as the flood caused by runoff from a probable
    maximum precipitation.
    4
    January Term, 2011
    structure—was built, ODNR considered the lake to be self-regulating; it has not
    lowered the GLSM lake level since that time, although it has the capability to do
    so. When ODNR finished building the new spillway, it also modified the eastern
    outlet of GLSM with a structure that has no flood-management capacity.
    Concerns about New Spillway
    {¶ 8} From the outset of the spillway-replacement project, public officials
    and private citizens expressed concerns to ODNR and others regarding the
    possibility of greater flooding downstream along Beaver Creek.
    {¶ 9} Keith G. Earley, the Mercer County Engineer at that time, wrote a
    series of letters and met with ODNR and other officials to express his concern that
    the new spillway would cause increased flooding on the western side of GLSM
    that would adversely affect downstream farmers and businesses. Earley later
    concluded that “ODNR chose to serve recreational users of Grand Lake by
    maintaining a constant lake level and to avoid any flooding on the southern end of
    Grand Lake to the detriment of the owners of structures and farmers on the
    western side of Grand Lake.”
    {¶ 10} Similarly, the Mercer County Soil and Water Conservation District
    advised ODNR that it needed to either address or further study the effect of the
    new spillway on croplands and that it believed that ODNR “has forgotten the
    farmer, as the * * * design of the spillway will put 4 feet in Beaver Creek itself.”
    {¶ 11} Finally, the Mercer County Board of Commissioners warned that
    “any possible adverse [effects] that could occur along the Beaver Creek outlet
    should be thoroughly evaluated before proceeding further.”
    State ex rel. Post v. Speck
    {¶ 12} In May 2001, five landowners of property located downstream
    from the western spillway of GLSM along Beaver Creek or the Wabash River
    filed an action for a writ of mandamus against the director of ODNR in the
    Mercer County Court of Common Pleas. The landowners owned farmland whose
    5
    SUPREME COURT OF OHIO
    location ranged from less than one mile from the redesigned western spillway to
    11 miles away. The common pleas court granted the writ after concluding that
    ODNR’s 1997 modification of the western spillway constituted a taking of the
    farmers’ property because of “frequent, severe and persistent flooding.”
    {¶ 13} On appeal, the court of appeals affirmed the judgment of the
    common pleas court after it determined that the court’s factual findings were
    supported by sufficient, credible evidence. State ex rel. Post v. Speck, Mercer
    App. No. 10-2006-001, 
    2006-Ohio-6339
    , 
    2006 WL 3477024
    , ¶ 76-77.
    Case Leasing & Rental, Inc. v. Ohio Dept. of Natural Resources
    {¶ 14} In 2005, an Ohio corporation filed suit against ODNR in the Ohio
    Court of Claims, alleging that flood damage to its property caused by the
    replacement spillway resulted in an unconstitutional taking without just
    compensation. The corporation owned 21 acres of land adjacent to Beaver Creek,
    a few hundred yards downstream from the intersection of Beaver Creek and the
    western shoreline of GLSM. The Court of Claims held that ODNR was liable for
    the negligent construction and maintenance of the replacement spillway. The
    court concluded that “ODNR knew or should have known that the installation of
    the replacement spillway as designed would result in more frequent and more
    severe flooding to downstream landowners” and that ODNR’s “design choice and
    subsequent lake level management were unreasonable.”
    {¶ 15} On appeal, the court of appeals affirmed that part of the judgment
    finding ODNR liable in negligence, but reversed and remanded for further
    determination on the issue of damages. Case Leasing & Rental, Inc. v. Ohio
    Dept. of Natural Resources, Franklin App. No. 09AP-498, 
    2009-Ohio-6573
    , 
    2009 WL 4809639
    .
    6
    January Term, 2011
    Mandamus
    {¶ 16} On July 17, 2009, relators, more than 80 landowners,3 filed this
    action for a writ of mandamus in this court to compel respondents, ODNR and its
    director, to initiate appropriation proceedings for the taking of their property.
    Respondents filed a motion to dismiss, and relators filed a memorandum in
    opposition. We granted an alternative writ and set a schedule for briefing and
    presentation of evidence. 
    123 Ohio St.3d 1404
    , 
    2009-Ohio-5031
    , 
    914 N.E.2d 203
    .
    We later appointed a master commissioner for the limited purpose of receiving
    evidence and making evidentiary rulings. 
    123 Ohio St.3d 1435
    , 
    2009-Ohio-5611
    ,
    
    915 N.E.2d 659
    .          The parties submitted evidence, and we made various
    evidentiary rulings. See, e.g., 
    125 Ohio St.3d 1504
    , 
    2010-Ohio-3268
    , 
    929 N.E.2d 1069
    .
    {¶ 17} Relators presented substantial, credible lay evidence by way of
    affidavits, depositions, photographs, and videos to show that following ODNR’s
    1997 replacement of the western spillway and its concomitant decision to
    abandon lake-level management, their properties flooded more frequently, over a
    larger area, for longer periods of time and with greater resulting damage,
    including crop loss, the deposit of silt, sand, stone, and other debris, drainage-tile
    failure, soil compaction, and the destruction of trees, bushes, and shrubs. Some of
    the relators presented evidence that their properties had never flooded until the
    construction of the new spillway and abandonment of lake-level management.
    {¶ 18} Most of the relators have experienced flooding on a frequent basis
    since the new spillway was built and lake-level management was discontinued,
    3. The original complaint included 86 relators and over 200 parcels that they owned or had an
    interest in. On March 12, 2010, we granted relator Kuhn Farms, Inc.’s application to dismiss its
    claims. State ex rel. Doner v. Logan, 
    124 Ohio St.3d 1512
    , 
    2010-Ohio-919
    , 
    923 N.E.2d 155
    . And
    on March 19, 2010, we granted relators’ motion to substitute the estate of Marilyn M. Kuhn in her
    place. State ex rel. Doner v. Logan, 
    124 Ohio St.3d 1517
    , 
    2010-Ohio-1069
    , 
    923 N.E.2d 618
    .
    7
    SUPREME COURT OF OHIO
    with many experiencing flooding every year and in some years on multiple
    occasions.
    {¶ 19} Relators also presented expert evidence in support of their claims.
    Their primary expert was Pressley L. Campbell, an engineer with education and
    experience in hydrology and hydraulics.4 Based on his previous work as an
    expert for the relators in Case Leasing, as well as his analysis of rainfall records
    and storm-event data from 1913 to 2006 and lake-elevation readings from 1927 to
    2006, Campbell opined that the redesigned spillway caused frequent and severe
    flooding in the Beaver Creek-Wabash River area.
    {¶ 20} Campbell concluded that it was highly unlikely that relators’
    property downstream from the GLSM spillway would have flooded if the old
    spillway had been in place and ODNR had continued the lake-level management
    it had practiced before the 1997 construction of the new spillway. Campbell
    determined that based upon his analysis of lake-elevation data, if the new spillway
    had been in place in 1927, 15 storm events between 1927 and 2006 would have
    resulted in flooding, i.e., an average of one every five years, whereas with the old
    39.4-foot spillway and lake-level-management practices in place, only one storm
    event would have caused flooding.
    {¶ 21} Campbell further calculated that since 1997, 73.3 percent of the
    daily measurements reflected GLSM elevations above 870.6 feet mean sea level,
    the elevation at which water overflows the spillway and enters Beaver Creek. By
    contrast, before 1997, the lake elevation was above 870.6 feet for only 21.4
    percent of the measurements. Campbell found that since 1997, 26.3 percent of the
    daily measurements exhibited lake elevations above 871.5 feet mean sea level, the
    4. Hydrology is “a science dealing with the properties, distribution, and circulation of water,” and
    hydraulics is the “branch of science that deals with practical applications (as the transmission of
    energy or the effects of flow) of water or other liquid in motion.” Webster’s Third New
    International Dictionary (1986) 1109 and 1107.
    8
    January Term, 2011
    elevation at which water overflows the entire 500-foot spillway, whereas before
    1997, the lake elevation was above 871.5 feet for only 2.4 percent of the
    measurements.
    {¶ 22} Relators also relied on the testimony of Keith Earley, the former
    Mercer County Engineer who had warned ODNR that its planned redesign of the
    spillway would result in flooding to downstream farmers on the western side of
    the lake, and James Moir, an engineer who had criticized the analysis performed
    by respondents’ expert. Finally, relators submitted evidence from Post and Case
    Leasing, which involved different properties in the same general area as those at
    issue here.
    {¶ 23} Respondents submitted evidence from ODNR’s expert, the
    consulting firm Stantec. Stantec constructed hydrologic and hydraulic models of
    the pertinent property using computer programs developed by the United States
    Army Corps of Engineers. Stantec’s hydrologic modeling confirmed greater peak
    spillway flow from the new spillway when compared to the old spillway for 24-
    hour 100-year storm events and 96-hour five-year, ten-year, and 100-year storm
    events.
    {¶ 24} For example, the peak spillway flow for a 96-hour five-year rain
    event for the new spillway was 390 cubic feet per second (“cfs”), which exceeds
    the 345 cfs peak spillway flow for a 96-hour 100-year rain event for the old
    spillway. And the 650 cfs peak spillway flow for a 96-hour ten-year rain event
    for the new spillway exceeds the 480 to 500 cfs capacity for Beaver Creek that
    ODNR had stipulated to in Case Leasing, which would cause Beaver Creek to
    overtop its banks.
    {¶ 25} In Stantec’s initial report in March 2010, it concluded that for an
    event expected to occur once every 15 years (7 percent chance of occurring in any
    given year), the new spillway causes an increase in depth of flooding up to 1.6
    feet directly below the spillway, and the increased depth decreases until about two
    9
    SUPREME COURT OF OHIO
    miles downstream, when any increased flooding results from local drainage and
    runoff, not spillway flow. Stantec further found that for an event expected to
    occur once every 100 years (1 percent chance of occurring in any year), the new
    spillway causes an increase in depth of flooding up to three feet directly below the
    spillway, with the depth decreasing until about four miles downstream.
    {¶ 26} In sum, Stantec determined that the new spillway increases the
    duration of out-of-bank flooding for some properties adjacent to Beaver Creek
    and the Wabash River during both the 15-year and 100-year rain events because
    of the new spillway, with some properties having increased duration of flooding
    of up to two days, but that a number of parcels identified in the case are not
    affected by either increased depth or duration of flooding due to the new spillway.
    {¶ 27} In its March 2010 report, Stantec determined that “[b]ecause
    rainfall events that are likely to cause flooding happen over the entire watershed,
    when assessing the impacts of the spillway modification, it is not proper to do so
    without considering the contribution of runoff below the dam; runoff that was
    present and contributed to flooding problems in Beaver Creek well before the
    spillway modification.” For a 96-hour 15-year rain event, the “spillway flow
    makes up well under 10% of the overall flow entering the system for both the new
    and old spillway configurations. This means that the majority of the flooding,
    especially as the distance downstream of the spillway increases, results from
    runoff that enters the stream below the spillway and not a direct result of spillway
    flow itself.”
    {¶ 28} In a May 26, 2010 memorandum, Stantec responded to relators’
    expert’s questions and concerns by explaining and updating its analysis. The
    results of the revision showed slightly less effect on the relators’ property from
    the new spillway. Stantec concluded that (1) ten of relators’ parcels were affected
    by increased maximum depth and duration of flooding during a 15-year rain
    event, (2) 46 parcels were affected by increased duration of flooding during a 15-
    10
    January Term, 2011
    year rain event, and (3) 35 parcels were not affected by flows from the new
    spillway during a 15-year rain event.
    {¶ 29} Stantec also concluded that (1) 25 of relators’ parcels were affected
    by increased maximum depth and duration of flooding during a 100-year rain
    event, (2) 41 parcels were affected by increased duration of flooding during a
    100-year rain event, and (3) 25 parcels were not affected by flows from the new
    spillway during a 100-year rain event.         Stantec determined that only 16 of
    relators’ parcels had additional acreage affected by flooding resulting from the
    new spillway during a 15-year rain event and that only 24 parcels had increased
    acreage affected during a 100-year rain event.
    {¶ 30} Stantec’s     modeling,    however,     was     flawed   because     it
    underestimated the infiltration, or antecedent moisture, of the soil, which affects
    runoff, and which is therefore important in determining the amount of flooding
    affecting relators’ property.
    {¶ 31} In addition, although Stantec attempted to show that increased
    rainfall was the main cause of the flooding of relators’ property, its senior
    associate could point to only a slight increase in the average number of severe
    rainfall days after 1997, when the new spillway was completed.
    {¶ 32} The parties subsequently submitted briefs, and the Ohio Farm
    Bureau Federation filed an amicus curiae brief in support of relators.            Oral
    argument was held on September 20, 2011.
    Legal Analysis
    Applicable Statute of Limitations
    {¶ 33} We must first resolve the question of which statute of limitations
    applies in this case.
    {¶ 34} “Under R.C. 2305.09(E), an action for relief on the grounds of a
    physical or regulatory taking of real property must generally be brought within
    11
    SUPREME COURT OF OHIO
    four years after the cause accrued.” State ex rel. Nickoli v. Erie MetroParks, 
    124 Ohio St.3d 449
    , 
    2010-Ohio-606
    , 
    923 N.E.2d 588
    , ¶ 29.
    {¶ 35} Thus, as we held in Nickoli, the four-year statute of limitations in
    R.C. 2305.09(E), which was expressly promulgated by the General Assembly to
    address takings claims, is generally applicable to such claims.
    R.C. 2305.09(E) Does Not Bar the Takings Claim
    {¶ 36} Respondents contend that because relators’ claim is based
    primarily on the 1997 construction of the replacement spillway, their claim is
    time-barred by R.C. 2305.09(E).        Respondents argue that relators or their
    predecessors-in-title either knew or should have known of any damage allegedly
    caused by the spillway by 2003 at the latest, when a catastrophic flood occurred
    that relators claim was caused by the spillway. Relators did not institute this
    action until 2009; thus, respondents argue, relators’ claim is barred by the four-
    year limitations period of R.C. 2305.09(E).
    {¶ 37} Nevertheless, in assessing respondents’ statute-of-limitations claim,
    we note that R.C. 2305.09 contains a comparable four-year limitations period for
    “trespassing upon real property.” R.C. 2305.09(A). In construing the statute of
    limitations for actions for trespass upon real property, we have held that if a
    trespass is continuing rather than a single completed act, the limitations period is
    tolled. Sexton v. Mason, 
    117 Ohio St.3d 275
    , 
    2008-Ohio-858
    , 
    883 N.E.2d 1013
    ,
    ¶ 30-33; Valley Ry. Co. v. Franz (1885), 
    43 Ohio St. 623
    , 
    4 N.E. 88
    .
    {¶ 38} In Valley Ry., the railway company built a dam and an artificial
    channel on its own land to divert the river from its natural channel.          This
    construction was completed in 1874. The diverted water damaged the plaintiff’s
    land, and the plaintiff filed suit for trespass in 1881. We held that the case was
    not barred by the four-year statute of limitations, because of the continuing nature
    of the company’s trespass:
    12
    January Term, 2011
    {¶ 39} “[W]hen the owner of land rightly and lawfully does an act entirely
    on his own land, and by means of such act puts in action or directs a force against
    or upon, or that affects, another’s land, without such other’s consent or
    permission, such owner and actor is liable to such other for the damages thereby
    so caused the latter, and at once a cause of action accrues for such damages; and
    such force, if so continued, is continued by the act of such owner and actor, and it
    may be regarded as a continuing trespass or nuisance; and each additional damage
    thereby caused is caused by him, and is an additional cause of action; and, until
    such continued trespass or nuisance by adverse use ripens into and becomes a
    presumptive right and estate in the former, the latter may bring his action.” Id. at
    627.
    {¶ 40} Although the railway company’s actions in diverting the river
    ended in 1874, the company’s continued control over the diverted channel
    resulted in a continuing trespass that tolled the four-year statute of limitations:
    {¶ 41} “The company remained upon its own land, and cut the new
    channel, and took control of the stream, and directed its course when the same
    passed from its land and its control, and has ever since so controlled and directed
    the stream that has caused the damage complained of. The amended petition
    states a cause of action that is not barred by the statute of limitations provided for
    such cases.” Id., 43 Ohio St. at 628, 
    4 N.E. 88
    .
    {¶ 42} Similarly, in State v. Swartz (2000), 
    88 Ohio St.3d 131
    , 
    723 N.E.2d 1084
    , the defendant was charged with creating a nuisance by erecting a bridge and
    culvert on his property, which allegedly caused a backup of water and ponding on
    a neighbor’s property with each heavy water flow. The structures constituting the
    nuisance were completed in 1992, and prosecution was not commenced until
    1998. Nevertheless, we held that the two-year limitations period had not expired,
    because the alleged nuisance remained within the control of the defendant so as to
    constitute a continuing course of conduct:
    13
    SUPREME COURT OF OHIO
    {¶ 43} “Where one creates a nuisance as defined in R.C. 3767.13(C) and
    permits it to remain, so long as it remains, and is within the control of the actor,
    the nuisance constitutes a continuing course of conduct tolling the limitations
    period pursuant to R.C. 2901.13(D).” 
    Id.
     at syllabus.
    {¶ 44} Finally, in Sexton, 
    117 Ohio St.3d 275
    , 
    2008-Ohio-858
    , 
    883 N.E.2d 1013
    , we applied Valley Ry., 
    43 Ohio St. 623
    , 
    4 N.E. 88
    , and Swartz and held that
    the “defendant’s ongoing conduct or retention of control is the key” to
    distinguishing a continuing trespass, which tolls a statute of limitations, from a
    permanent trespass, which does not. Id. at ¶ 45. “We hold that a continuing
    trespass in this context occurs when there is some continuing or ongoing allegedly
    tortious activity attributable to the defendant. A permanent trespass occurs when
    the defendant’s allegedly tortious act has been fully accomplished.” Id. The
    defendants in Sexton had finished their work on the subdivision development and
    had ceded control by 1995. Because the neighboring homeowners did not bring
    suit until 2003, well after the four-year statute of limitations had expired, their
    trespass claim was barred.
    {¶ 45} Sexton, Valley Ry., and Swartz lead inexorably to the conclusion
    that when an act carried out on the actor’s own land causes continuing damage to
    another’s property and the actor’s conduct or retention of control is of a
    continuing nature, the statute of limitations is tolled. There is no logical rationale
    for refusing to apply this rule to takings cases and R.C. 2305.09(E). Otherwise, a
    person whose property is damaged by flooding caused by another’s actions might
    have a cause of action against a private person or entity but not against a
    governmental entity. Here, respondents constructed the new spillway in 1997 and
    continued to exercise control over both the spillway and the lake level by making
    decisions not to draw down the water either annually or before heavy rains.
    Therefore, based on this court’s precedent, relators’ mandamus claim is not barred
    14
    January Term, 2011
    by the four-year statute of limitations in R.C. 2305.09(E), because respondents’
    ongoing control has tolled the running of the limitations period.
    {¶ 46} In fact, in their merit brief, respondents do not even attempt to
    distinguish or otherwise argue the inapplicability of these cases.           Instead,
    respondents rely on Nickoli, 
    124 Ohio St.3d 449
    , 
    2010-Ohio-606
    , 
    923 N.E.2d 588
    , and Painesville Mini Storage, Inc. v. Painesville, 
    124 Ohio St.3d 504
    , 2010-
    Ohio-920, 
    924 N.E.2d 357
    , in support of their argument that the four-year
    limitations period in R.C. 2305.09(E) was not tolled. These cases, however, are
    manifestly distinguishable.     In Nickoli, the act constituting the taking—the
    construction and opening of a recreational trail—occurred on the relators’
    property rather than on the respondents’ property. Unlike the relators here, the
    relators in Nickoli thus had direct and immediate notice of any alleged taking as
    well as the cause of the taking. In Painesville, the contested action was the city’s
    issuance of a building permit for construction that, relator argued, interfered with
    its use of its own property. Unlike the alleged taking by ODNR and its director
    here, the city in Painesville did not retain control. And as with the relators in
    Nickoli, the relator in Painesville had direct and immediate notice of any alleged
    taking of its easement and right of access, as well as the cause of the taking.
    {¶ 47} By contrast, this case arises from facts that are similar to those in
    Swartz and Valley Ry., where defendants had allegedly engaged in conduct on
    their own property that caused flooding or water damage to adjoining landowners’
    property, and the defendants had retained control over their property.
    {¶ 48} Moreover, as we observed in Nickoli at ¶ 34, quoting Hopland
    Band of Pomo Indians v. United States (Fed.Cir.1988), 
    855 F.2d 1573
    , 1577, a
    cause of action against the government does not accrue until “ ‘all the events
    which fix the government’s alleged liability have occurred and the plaintiff was or
    should have been aware of their existence.’ (Emphasis omitted.)” See also United
    States v. Dickinson (1947), 
    331 U.S. 745
    , 749, 
    67 S.Ct. 1382
    , 
    91 L.Ed. 1789
    15
    SUPREME COURT OF OHIO
    (“when the Government chooses not to condemn land but to bring about a taking
    by a continuing process of physical events, the owner is not required to resort
    either to piecemeal or to premature litigation to ascertain the just compensation
    for what is really ‘taken’ ”).
    {¶ 49} Respondents’ expert, Stantec, stated that “[s]tandard engineering
    practice calls for at least 10 and preferably 15 years or more of record in order to
    produce meaningful hydrologic statistics.”
    {¶ 50} Consequently, even assuming that respondents are correct that all
    the events that fixed their liability to downstream landowners like relators were
    completed in 1997, when the new spillway was built, their mandamus action in
    2009 was still filed within the four-year period of R.C. 2305.09(E). The ten to 15
    years necessary to gather data to prove a taking had not yet passed. Relators
    needed time to determine whether the flooding that followed respondents’
    construction of the spillway in 1997 and their refusal to lower the lake level at
    GLSM was of sufficient frequency to constitute a taking.
    {¶ 51} Therefore, the R.C. 2305.09(E) statute of limitations does not bar
    relators’ takings claim.
    Mandamus: General Considerations
    {¶ 52} “The United States and Ohio Constitutions guarantee that private
    property shall not be taken for public use without just compensation.” State ex
    rel. Shemo v. Mayfield Hts. (2002), 
    95 Ohio St.3d 59
    , 63, 
    765 N.E.2d 345
    ,
    judgment modified in part on other grounds, 
    96 Ohio St.3d 379
    , 
    2002-Ohio-4905
    ,
    
    775 N.E.2d 493
    ; Fifth and Fourteenth Amendments to the United States
    Constitution; Section 19, Article I, Ohio Constitution. The right of property is a
    fundamental right, and “[t]here can be no doubt that the bundle of venerable rights
    associated with property is strongly protected in the Ohio Constitution and must
    be trod upon lightly, no matter how great the weight of other forces.” Norwood v.
    Horney, 
    110 Ohio St.3d 353
    , 
    2006-Ohio-3799
    , 
    853 N.E.2d 1115
    , ¶ 38.
    16
    January Term, 2011
    {¶ 53} “Mandamus is the appropriate action to compel public authorities
    to institute appropriation proceedings where an involuntary taking of private
    property is alleged.” Shemo at 63. To be entitled to the requested writ of
    mandamus, relators must establish a clear legal right to compel the respondents to
    commence an appropriation action, a corresponding clear legal duty on the part of
    respondents to institute that action, and the lack of an adequate remedy in the
    ordinary course of law. State ex rel. Gilbert v. Cincinnati, 
    125 Ohio St.3d 385
    ,
    
    2010-Ohio-1473
    , 
    928 N.E.2d 706
    , ¶ 15.
    {¶ 54} The parties disagree over the appropriate burden of proof in this
    mandamus case. Relators argue that they need prove the required elements of
    mandamus only by a preponderance of the evidence, whereas respondents argue
    that the applicable standard is proof by clear and convincing evidence.          A
    preponderance of the evidence is defined as that measure of proof that convinces
    the judge or jury that the existence of the fact sought to be proved is more likely
    than its nonexistence. See Pang v. Minch (1990), 
    53 Ohio St.3d 186
    , 197, 
    559 N.E.2d 1313
    . “Clear and convincing evidence is ‘that measure or degree of proof
    which is more than a mere “preponderance of the evidence,” but not to the extent
    of such certainty as is required “beyond a reasonable doubt” in criminal cases, and
    which will produce in the mind of the trier of facts a firm belief or conviction as
    to the facts sought to be established.’ ” State ex rel. Husted v. Brunner, 
    123 Ohio St.3d 288
    , 
    2009-Ohio-5327
    , 
    915 N.E.2d 1215
    , ¶ 18, quoting Cross v. Ledford
    (1954), 
    161 Ohio St. 469
    , 
    53 O.O. 361
    , 
    120 N.E.2d 118
    , paragraph three of the
    syllabus.
    {¶ 55} We have held that the appropriate standard of proof in mandamus
    cases is proof by clear and convincing evidence. In State ex rel. Pressley v.
    Indus. Comm. (1967), 
    11 Ohio St.2d 141
    , 161, 
    40 O.O.2d 141
    , 
    228 N.E.2d 631
    ,
    we observed that in mandamus cases, “ ‘[t]he facts submitted and the proof
    produced must be plain, clear, and convincing’ ” before a writ will be granted.
    17
    SUPREME COURT OF OHIO
    
    Id.,
     quoting 35 Ohio Jurisprudence 2d (1959) 285, Section 37. And a few years
    later, in State ex rel. Henslee v. Newman (1972), 
    30 Ohio St.2d 324
    , 325, 
    59 O.O.2d 386
    , 
    285 N.E.2d 54
    , we held that the burden of proof on the relator in a
    mandamus case is to “ ‘demonstrate that there is plain, clear, and convincing
    evidence which would require the granting of the writ.’ ” 
    Id.,
     quoting the court of
    appeals’ opinion.
    {¶ 56} Parties seeking extraordinary relief bear a more substantial burden
    in establishing their entitlement to this relief. In mandamus cases, this heightened
    standard of proof is reflected by two of the required elements—a “clear” legal
    right to the requested extraordinary relief and a corresponding “clear” legal duty
    on the part of the respondents to provide it.
    {¶ 57} Therefore, we reaffirm our holdings in Pressley and Henslee by
    specifying that relators in mandamus cases must prove their entitlement to the
    writ by clear and convincing evidence.
    {¶ 58} Finally, relators seem to suggest that Post and Case Leasing are res
    judicata on relators’ takings claim. We rejected a similar contention in Nickoli,
    
    124 Ohio St.3d 449
    , 
    2010-Ohio-606
    , 
    923 N.E.2d 588
    . Relators are not in privity
    with the claimants in Post and Case Leasing merely because they own property in
    the same general area. Id. at ¶ 23-26. As to the evidence from those cases that
    has been submitted in this case, we will consider it to the extent that it is relevant
    to the takings claims of relators.
    Mandamus: Taking by Flooding
    {¶ 59} Relators’ claim is based on a taking by flooding resulting from the
    state’s public-improvement construction of a replacement spillway and its
    subsequent lake-level-management policies.        “Any direct encroachment upon
    land, which subjects it to a public use that excludes or restricts the dominion and
    control of the owner over it, is a taking of his property, for which he is guaranteed
    a right of compensation by section 19 [Article I of the Ohio Constitution].”
    18
    January Term, 2011
    Norwood v. Sheen (1933), 
    126 Ohio St. 482
    , 
    186 N.E. 102
    , paragraph one of the
    syllabus.
    {¶ 60} In cases of flooding caused by actions of the government, we have
    held that “[t]he construction and operation of a municipal storm sewer system so
    as to cause material damage to a down-stream landowner, as a result of flooding
    from rains or other causes which are reasonably foreseeable, is a direct
    encroachment upon that land which subjects it to a public use that excludes or
    restricts the landowner’s dominion and control over his land, and such owner has
    a right to compensation for the property taken under Section 19, Article I of the
    Ohio Constitution.” Masley v. Lorain (1976), 
    48 Ohio St.2d 334
    , 
    2 O.O.3d 463
    ,
    
    358 N.E.2d 596
    , syllabus; see also Lucas v. Carney (1958), 
    167 Ohio St. 416
    , 
    5 O.O.2d 63
    , 
    149 N.E.2d 238
     (construction on county property that increased the
    amount and force of surface water flowing onto landowners’ property, causing
    frequent inundation, raised a claim of appropriation); Gilbert, 
    125 Ohio St.3d 385
    ,
    
    2010-Ohio-1473
    , 
    928 N.E.2d 706
    , ¶ 30-33 (evidence that city’s pump station
    deposited sewage on at least 79 days between 1998 and 2008 in the creek that ran
    through landowners’ property was sufficient to establish a physical taking).
    {¶ 61} Our precedent is consistent with federal precedent. “[W]here the
    government by the construction of a dam or other public works so floods lands
    belonging to an individual as to substantially destroy their value there is a taking
    within the scope of the 5th Amendment.” United States v. Lynah (1903), 
    188 U.S. 445
    , 470, 
    23 S.Ct. 349
    , 
    47 L.Ed. 539
    , overruled in part on other grounds,
    United States v. Chicago, Milwaukee, St. Paul & Pacific RR. Co. (1941), 
    312 U.S. 592
    , 598, 
    61 S.Ct. 772
    , 
    85 L.Ed. 1064
    .         Even when the flooding is only
    occasional, a taking may result. See United States v. Cress (1917), 
    243 U.S. 316
    ,
    328, 
    37 S.Ct. 380
    , 
    61 L.Ed. 746
     (“There is no difference of kind, but only of
    degree, between a permanent condition of continual overflow by backwater and a
    19
    SUPREME COURT OF OHIO
    permanent liability to intermittent but inevitably recurring overflows; and, on
    principle, the right to compensation must arise in the one case as in the other”).
    {¶ 62} Relators’ mandamus action is one for inverse condemnation, which
    is “a cause of action against the government to recover the value of property taken
    by the government without formal exercise of the power of eminent domain.”
    Moden v. United States (Fed.Cir.2005), 
    404 F.3d 1335
    , 1342.
    {¶ 63} The United States Court of Appeals for the Federal Circuit, in a
    case involving a claimed taking by the government due to increased storm-water
    runoff caused by the construction of a post office, set forth the following two-part
    test for inverse-condemnation claims:
    {¶ 64} “[N]ot every ‘invasion’ of private property resulting from
    government activity amounts to an appropriation.           The line distinguishing
    potential physical takings from possible torts is drawn by a two-part inquiry.
    First, a property loss compensable as a taking only results when the government
    intends to invade a protected property interest or the asserted invasion is the
    ‘direct, natural, or probable result of an authorized activity and not the incidental
    or consequential injury inflicted by the action.’ Columbia Basin Orchard v.
    United States (Ct.Cl.1955), 
    132 F.Supp. 707
    , 709 * * *. * * * Second, the nature
    and magnitude of the government action must be considered. Even where the
    effects of the government action are predictable, to constitute a taking, an
    invasion must appropriate a benefit to the government at the expense of the
    property owner, or at least preempt the owner’s right to enjoy his property for an
    extended period of time, rather than merely inflict an injury that reduces its
    value.”      (Citations omitted in part.)     Ridge Line, Inc. v. United States
    (Fed.Cir.2003), 
    346 F.3d 1346
    , 1355-1356.
    {¶ 65} In eminent-domain cases involving claims of government-induced
    flooding, the claimant establishes a taking by proving that (1) the flooding is
    either intended by the government or is the direct, natural, or probable result of
    20
    January Term, 2011
    government-authorized activity and (2) the flooding is either a permanent
    invasion or creates a permanent liability because of intermittent, but inevitably
    recurring, overflows. See generally Cary v. United States (Fed.Cir.2009), 
    552 F.3d 1373
    , 1377, 1380-1381; Arkansas Game & Fish Comm. v. United States
    (Fed.Cir.2011), 
    637 F.3d 1366
    , 1374-1375; Ridge Line, 
    346 F.3d at 1355, 1357
    .
    {¶ 66} The first part of this test, which requires that the flooding is either
    intended by the government or is the direct, natural, or probable result of the
    government-authorized activity, is characterized as the causation prong. Cary at
    1376-1377. There is some evidence here that respondents made an intentional
    choice to favor recreational users of the lake and south-side lakefront landowners
    over landowners and farmers on the western side of the lake. But there is no
    credible evidence that ODNR and its director intended to flood relators’ land. In
    fact, it appears that the intent of respondents in constructing the new spillway was
    to prevent flooding—to prevent the dam at GLSM from failing and causing a
    catastrophic flooding event—and not to create or exacerbate it.
    {¶ 67} Therefore, relators must establish that the flooding that occurred on
    relators’ property was the direct, natural, or probable result of respondents’
    actions. See also Barnes v. United States (Ct.Cl.1976), 
    538 F.2d 865
    , 871 (“in
    cases such as these, plaintiffs need not allege or prove that defendant specifically
    intended to take property. There need be only a governmental act, the natural and
    probable consequences of which effect such an enduring invasion of plaintiffs’
    property as to satisfy all other elements of a compensable taking”). In essence,
    relators must prove both that respondents’ actions caused the flooding and that the
    flooding was a foreseeable result of their actions. Nicholson v. United States
    (2007), 
    77 Fed.Cl. 605
    , 617.
    {¶ 68} For the following reasons, relators have met their burden of proof
    with respect to the causation prong of the taking-by-flooding test.
    21
    SUPREME COURT OF OHIO
    {¶ 69} First, relators presented substantial, credible, and uncontroverted
    firsthand testimonial and documentary evidence that following respondents’
    construction of the new spillway in 1997 and its subsequent abandonment of lake-
    level management, their properties flooded more frequently, over a larger area, for
    longer duration, and with greater damage.
    {¶ 70} Second, relators’ primary expert, engineer Pressley L. Campbell,
    testified that the redesigned spillway caused frequent and severe flooding in the
    Beaver Creek-Wabash River area.        This flooding would have been “highly
    unlikely, if not impossible” without the new spillway and respondents’
    subsequent failure to manage the lake level. Notwithstanding respondents’ claims
    to the contrary, Campbell’s conclusions were not based simply on his Case
    Leasing work. Other engineers in Campbell’s company visited the properties and
    took photographs of the area, which Campbell reviewed.
    {¶ 71} Third, the reliance of respondents and their expert on a 1981
    United States Army Corps of Engineers report to discount Campbell’s expert
    opinion is misplaced. According to engineer James Moir, the current conditions
    differ substantially from those in existence when that report was completed.
    There are now no trees along Beaver Creek, and thus the creek has a much greater
    capacity to convey water than it had previously.
    {¶ 72} Fourth, significantly, respondents’ own expert, Stantec, concluded
    in its hydrologic and hydraulic analysis that for the 15-year rain event that
    respondents claim to be the applicable frequency for a takings analysis, ten of
    relators’ parcels suffered increased maximum depth and duration of flooding, and
    46 of their parcels experienced increased duration of flooding since the redesign
    of the spillway and the abandonment of lake-level management. That is, even
    Stantec concedes that flooding of at least some of relators’ property was caused
    by the new spillway and the lack of lake-level management.
    22
    January Term, 2011
    {¶ 73} Fifth, Stantec also concluded that the peak flow from the new
    spillway in even ten-year rain events now exceeds the peak flow from historical
    100-year rain events with the old spillway. For a 96-hour ten-year rain event with
    the new spillway, Stantec determined that the peak spillway flow was 650 cubic
    feet per second (“cfs”), which exceeds the 345 cfs peak spillway flow for a 96-
    hour 100-year rain event with the old spillway. According to the stipulations that
    ODNR agreed to in Case Leasing, Beaver Creek has a capacity of approximately
    480 to 500 cfs, meaning that if the water discharged into the creek exceeds this
    capacity, Beaver Creek will overtop its banks. Therefore, based on respondents’
    own expert’s analysis, since the 1997 construction of the new spillway and their
    cessation of lake-level management for GLSM, flooding in excess of prior 100-
    year rain events is occurring on at least a ten-year frequency, with the banks of the
    Beaver Creek overtopping enough to create the inevitably recurring flooding
    downstream that all the relators testified to experiencing.
    {¶ 74} Finally, the flooding caused by respondents’ new spillway and
    lake-level-management practices was foreseeable. ODNR was warned repeatedly
    by landowners, the Mercer County Engineer, and public officials about the
    likelihood of greater flooding. As the county engineer concluded, ODNR made a
    conscious choice to disregard that foreseeable risk in favor of recreational users of
    the lake and landowners on the southern end of the lake.
    {¶ 75} ODNR and its director argue that relators have not met their burden
    of proof because they have not provided the requisite expert evidence on the issue
    of causation. Respondents maintain that relators’ experts “made no effort to
    scientifically evaluate the impacts of the new spillway on individual Relator
    properties.” Thus, relators have presented only lay evidence, which is insufficient
    to establish that the flooding was caused by governmental action.
    {¶ 76} Even assuming that respondents have correctly characterized the
    relators’ expert evidence as deficient on causation, we reject respondents’
    23
    SUPREME COURT OF OHIO
    argument that relators have failed to sustain their burden on that issue. It is true
    that “[t]he determination of causation in flooding cases is particularly difficult,”
    Mildenberger v. United States (2010), 
    91 Fed.Cl. 217
    , 260, and that in certain
    circumstances, lay testimony is insufficient, and expert testimony is required. See
    generally Alost v. United States (2006), 
    73 Fed.Cl. 480
    , 495, and 496, fn. 14; see
    also Cox v. Tennessee Valley Auth. (C.A.6, 1993), 
    989 F.2d 499
    , 
    1993 WL 72488
    ,
    *4 (unpublished disposition).       Nevertheless, expert evidence is not always
    required to prove causation. Moore v. Associated Material & Supply Co., Inc.
    (1997), 
    263 Kan. 226
    , 242, 
    948 P.2d 652
     (causation of flooding can be proved by
    lay testimony).
    {¶ 77} In fact, even in cases holding that lay testimony is insufficient to
    establish causation in a takings case involving flooding, the holdings appear to be
    limited to the specific circumstances therein. For example, in Alost, the United
    States Court of Federal Claims emphasized that “the only evidence the plaintiffs
    presented with regard to the cause of the overflow flooding on their land was lay
    testimony,” that half of the plaintiffs had owned their land for only one or two
    years before the government river-regulation project, and that the federal
    government provided uncontroverted expert testimony that the project did not
    cause the flooding of the plaintiffs’ property.     
    Id. at 495-496
    . This case is
    manifestly distinguishable from Alost because (1) relators introduced lay
    testimony and documentary evidence that was not merely conclusory, (2) some of
    the relators have been lifelong residents and farmers of the relevant property, (3)
    relators also submitted expert evidence, and (4) respondents’ own evidence
    supports a finding that flooding of at least some of relators’ property was caused
    by respondents’ actions.         See also Tarrant Reg. Water Dist. v. Gragg
    (Tex.App.2001), 
    43 S.W.3d 609
    , 618 (“Credible lay testimony is relevant to
    causation” in flooding cases).
    24
    January Term, 2011
    {¶ 78} As the court of appeals held in Post, 
    2006-Ohio-6339
    , 
    2006 WL 3477024
    , at ¶ 66, relators’ own testimony, “although not expert testimony,
    supports the hypothetical analysis that flooding will increase because of the new
    spillway. [The landowners] were not required to prove that every increased
    flooding event they had experienced was solely caused by the change in the
    spillway design.”
    {¶ 79} Therefore, relators have satisfied the first part of the two-part test
    for establishing a taking of their property by flooding caused by respondents.
    They proved by the requisite clear and convincing evidence that flooding that
    occurred on their property was the direct, natural, or probable result of
    respondents’ actions. Ridge Line, 
    346 F.3d at 1355
    .
    {¶ 80} For the second part of the test, referred to as the appropriation
    prong, the nature and magnitude of the government action are considered. 
    Id. at 1356
    ; Cary, 
    552 F.3d at 1380
    .        This part requires an analysis of whether
    respondents’ interference with relators’ property rights “was substantial and
    frequent enough to rise to the level of a taking.” Ridge Line at 1357. “Generally
    speaking, property may be taken by the invasion of water where subjected to
    intermittent, but inevitably recurring, inundation due to authorized Government
    action.” Lenoir v. Porters Creek Watershed Dist. (C.A.6, 1978), 
    586 F.2d 1081
    ,
    1094. “The cases disclose the rule that the permanent, intermittent flooding
    which amounts to a taking must be frequent * * *.” Id.; Alost, 73 Fed.Cl. at 495
    (“A plaintiff seeking to establish a government taking of an easement by flooding
    must demonstrate * * * that the flooding is intermittent, frequent, and inevitably
    recurring”); Fromme v. United States (Ct.Cl.1969), 
    412 F.2d 1192
    , 1196 (“In a
    situation where works constructed by the Government on land owned or
    controlled by it cause the land of another to be subject to intermittent, frequent,
    and inevitably recurring floodings—although not to constant flooding—it is held
    25
    SUPREME COURT OF OHIO
    that the Government thereby takes a flowage easement over the affected land and
    must pay just compensation under the Constitution for the easement”).
    {¶ 81} “There is no absolute rule regarding the magnitude or duration of
    flooding necessary to constitute a taking.” 2A Nichols on Eminent Domain (3d
    Ed.2010), Section 601[14][c][iii]; Lea Co. v. North Carolina Bd. of Transp.
    (1983), 
    308 N.C. 603
    , 620, 
    304 S.E.2d 164
     (“a mechanical approach should not
    be taken with regard to the frequency of flooding required to constitute a taking”).
    A landowner is “not entitled to recover for a Fifth Amendment taking where the
    intermittent flooding of his land was not increased in elevation, frequency, and
    duration as a result of the government’s project.”         Bistline v. United States
    (Ct.Cl.1981), 
    640 F.2d 1270
    , 1275; Alost at 495.
    {¶ 82} Relators have also established by the requisite clear and convincing
    evidence that the flooding of their property, while intermittent, is inevitably
    recurring. As discussed previously, they testified concerning the frequency of the
    flooding, which many have experienced on a yearly basis, including in 2011.
    Moreover, Stantec’s own expert report established that respondents’ actions
    regarding the spillway and lake-level management are now causing 100-year
    flooding events every ten years. And according to the evidence submitted by
    some of the relators, flooding can now occur after even a minimal rain event.
    {¶ 83} Based on the foregoing, relators have established that respondents,
    by their actions, effected a taking of at least some of their property.
    Prescriptive Easement
    {¶ 84} Respondents argue that even should this court find a taking, the
    taking is not compensable, because ODNR had acquired a prescriptive easement
    to flood relators’ property.    Respondents waived this affirmative defense by
    failing to raise it before the parties proceeded to submit evidence and argument in
    this case. See generally State ex rel. Plain Dealer Publishing Co. v. Cleveland
    (1996), 
    75 Ohio St.3d 31
    , 33, 
    661 N.E.2d 187
     (“An affirmative defense is waived
    26
    January Term, 2011
    under Civ.R. 12(H), unless it is presented by motion before pleading pursuant to
    Civ.R. 12(B), affirmatively in a responsive pleading under Civ.R. 8(C), or by
    amendment under Civ.R. 15”).
    Conclusion
    {¶ 85} Based on the foregoing, this case is not barred by the four-year
    statute of limitations of R.C. 2305.09(E), and relators have established that
    respondents’ construction of the spillway and concomitant refusal to lower the
    lake level at GLSM caused flooding with the requisite frequency to constitute a
    taking. As we recently noted, “[t]his court has a history of protecting property
    rights, and our decision today continues that long-standing precedent.” State ex
    rel. Merrill v. Ohio Dept. of Natural Resources, 
    130 Ohio St.3d 30
    , 2011-Ohio-
    4612, 
    955 N.E.2d 935
    , ¶ 60. Respondents were free to determine that the old
    spillway needed to be replaced for the dam at GLSM to survive a probable
    maximum flood. And they were also authorized to determine that redesigning the
    spillway and abandoning lake-level management were the preferable ways to
    remedy the probable-maximum-flood problem and to appeal to both recreational
    users of the lake and homeowners on the southern shore of the lake. Once they
    made that decision, however, they were liable for the damage to downstream
    landowners caused by the intermittent, but inevitably recurring, flooding that
    resulted from the new western spillway.
    {¶ 86} Therefore, we grant a writ of mandamus to compel respondents to
    commence appropriation proceedings to determine the amount of their taking of
    the property. Shemo, 95 Ohio St.3d at 69, 
    765 N.E.2d 345
     (writ of mandamus
    granted to compel respondents to commence appropriation proceedings to
    determine the amount of the city’s temporary taking of relators’ property). The
    determination of the extent of the taking will be made by the court presiding over
    the appropriation proceeding. See R.C. 163.05 (requiring that a petition for
    27
    SUPREME COURT OF OHIO
    appropriation of property interests less than a fee be in sufficient detail “to permit
    a determination of the nature, extent, and effect of the taking”).
    Writ granted.
    O’CONNOR, C.J., and PFEIFER, LUNDBERG STRATTON, O’DONNELL,
    LANZINGER, and BELFANCE, JJ., concur.
    EVE V. BELFANCE, J., of the Ninth Appellate District, sitting for CUPP, J.
    _____________________
    Vorys, Sater, Seymour & Pease, L.L.P., Bruce L. Ingram, Joseph R.
    Miller, Thomas H. Fusonie, and Martha C. Brewer, for relators.
    Michael DeWine, Attorney General, and William J. Cole, Mindy Worley,
    Jennifer S.M. Croskey, Dale T. Vitale, Daniel J. Martin, and Tara L. Paciorek,
    Assistant Attorneys General, for respondents.
    Larry R. Gearhardt and Chad A. Endsley, urging granting of the writ for
    amicus curiae, Ohio Farm Bureau Federation.
    ______________________
    28
    

Document Info

Docket Number: 2009-1292

Citation Numbers: 2011 Ohio 6117, 130 Ohio St. 3d 446

Judges: Brown, O'Connor, Pfeifer, Stratton, O'Donnell, Lanzinger, Belfance, Ninth, Cupp

Filed Date: 12/1/2011

Precedential Status: Precedential

Modified Date: 10/19/2024

Cited By (47)

State ex rel. Crowley v. Dept. of Rehab. & Corr. , 2018 Ohio 2526 ( 2018 )

Turfco Landscaping, Inc. v. Shenigo , 2021 Ohio 4259 ( 2021 )

State ex rel. Mars Urban Solutions, L.L.C. v. Cuyahoga Cty. ... , 155 Ohio St. 3d 316 ( 2018 )

State ex rel. Ware v. Crawford (Slip Opinion) , 2022 Ohio 295 ( 2022 )

State ex rel. Ware v. Crawford (Slip Opinion) , 2022 Ohio 295 ( 2022 )

Nwankwo v. Uzodinma , 2022 Ohio 565 ( 2022 )

Bollinger v. Ohio Dept. of Edn. , 2018 Ohio 3714 ( 2018 )

State ex rel. Caldwell v. Gallagher , 2012 Ohio 4608 ( 2012 )

Jochum v. Jackson Twp. , 2013 Ohio 3592 ( 2013 )

State ex rel. E. Ohio Gas Co. v. Stark Cty. Bd. of Commrs. , 2012 Ohio 4533 ( 2012 )

State ex rel. Community Journal v. Reed , 2014 Ohio 5745 ( 2014 )

State ex rel. Lutheran Hosp. v. Buehrer , 2015 Ohio 380 ( 2015 )

In re Adult Protective Servs. of Devanan , 2023 Ohio 121 ( 2023 )

State ex rel. Cuyahoga Lakefront, L.L.C. v. Cleveland (Slip ... , 2016 Ohio 7640 ( 2016 )

State ex rel. Young v. Pomeroy , 2017 Ohio 8600 ( 2017 )

State Ex Rel. Lee v. Vill. of Plain City , 102 N.E.3d 10 ( 2017 )

17AP-230 , 2018 Ohio 2270 ( 2018 )

Franta v. State Teachers Retirement Sys. , 2020 Ohio 6843 ( 2020 )

State Ex Rel. Wasserman v. City of Freemont , 131 Ohio St. 3d 52 ( 2012 )

State ex rel. Ribo v. Uhrichsville , 2012 Ohio 3927 ( 2012 )

View All Citing Opinions »