JAG Imperial, L.L.C. v. Literski , 2012 Ohio 2863 ( 2012 )


Menu:
  • [Cite as JAG Imperial, L.L.C. v. Literski, 
    2012-Ohio-2863
    .]
    IN THE COURT OF APPEALS
    FIRST APPELLATE DISTRICT OF OHIO
    HAMILTON COUNTY, OHIO
    JAG IMPERIAL, LLC, d.b.a.                             :       APPEAL NO. C-110760
    CINCINNATI GUTTER & ROOF                                      TRIAL NO. 10CV-25509
    PROTECTION,                                           :
    Plaintiff-Appellee,                         :
    vs.                                          :           O P I N I O N.
    COLIN LITERSKI,                                       :
    and                                                :
    DIANE LITERSKI,                                       :
    Defendants-Appellants.                      :
    Civil Appeal From: Hamilton County Municipal Court
    Judgment Appealed From Is: Affirmed in Part, Reversed in Part, and Cause
    Remanded
    Date of Judgment Entry on Appeal: June 27, 2012
    Karen Comisar Prescott, for Plaintiff-Appellee,
    Sams, Fischer, Packard & Schuessler, LLC, and Dwight A. Packard, II, for
    Defendants-Appellants.
    Please note: This case has been removed from the accelerated calendar.
    OHIO FIRST DISTRICT COURT OF APPEALS
    FISCHER, Judge.
    {¶1}   Defendants-appellants Colin and Diane Literski appeal the judgment
    of the Hamilton County Municipal Court denying their counterclaims and entering
    judgment in favor of plaintiff-appellee JAG Imperial, LLC, doing business as
    Cincinnati Gutter & Roof Protection (“JAG”), against Mr. Literski for $8,556.50, plus
    interest. Because we determine that the trial court erred in awarding JAG $731.50
    that was not authorized by the parties’ contract, we reverse the judgment of the trial
    court as to this amount and instruct the court on remand to enter judgment for JAG
    in the amount of $7,825, plus interest.
    Factual and Procedural Background
    {¶2}   The Literskis contacted JAG in the summer of 2009 to provide an
    estimate for installing a new roof on their home and for repairs to the interior of
    their home, after their home had been damaged by a windstorm following Hurricane
    Ike in the fall of 2008. JAG provided the Literskis with an estimate for the roof, but
    told them that JAG did not do interior work. JAG referred the Literskis to Simon
    Trejo. Trejo provided a $500 estimate for the Literskis’ interior work and also
    provided an unsolicited estimate for the roofing work, which JAG had already
    provided. Trejo’s roof estimate was lower than JAG’s.
    {¶3}   Mr. Literski told JAG’s manager, Jamie Cox, that Trejo had tried to
    undercut JAG’s estimate for the roofing, but that the Literskis did not want JAG to
    confront Trejo because they still wanted Trejo to perform the interior work. Cox
    relayed this information to the owner of JAG, John Allen, who then confronted
    Trejo. Trejo subsequently stopped communicating with the Literskis.
    2
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶4}   JAG eventually entered into a contract with the Literskis to repair their
    roof for $10,325. According to Cox’s trial testimony, the contract had been based
    upon an estimate of 33 roofing squares, because of the insurance adjuster’s estimate,
    but Cox had told Mr. Literski that the project would likely take 35 squares. The
    contract contained a clause that “[a]ny alterations or deviations from above
    specifications involving extra costs will be executed only upon written orders, and
    will become an extra charge over and above the estimate.”
    {¶5}   The roofing project took JAG an additional 2.66 squares to complete,
    so JAG invoiced the Literskis for an additional $731.50 above the outstanding
    contract balance of $7,825. Cox testified that he had asked Mr. Literski for the
    Literskis’ insurance adjuster’s contact information so that JAG could submit a
    written request for supplemental payment to the insurance company for the extra
    squares, but that Mr. Literski had refused to give Cox the adjuster’s information.
    Allen testified that JAG had attempted to schedule a time with Mr. Literski for Trejo
    to perform the interior work and to collect the unpaid contract balance, but that Mr.
    Literski had claimed he had been having personal problems and could not pay at the
    time.
    {¶6}   Mr. Literski testified, however, that he had entered into a separate
    written agreement with Cox, on behalf of JAG, whereby JAG promised to perform
    the interior repairs for $500 if Trejo would not do the work. The Literskis produced
    this agreement at trial, and Mrs. Literski signed the agreement as a witness. Cox
    testified that he had not signed the agreement produced by the Literskis, but that he
    had signed an agreement for JAG to do the interior work if Trejo did not, however,
    that agreement had not contained a price term or date. Allen then testified that Mr.
    3
    OHIO FIRST DISTRICT COURT OF APPEALS
    Literski had eventually told Allen that Mr. Literski would take care of the interior
    repairs himself. Mr. Literski testified that he had to hire another company to do the
    interior repairs at a cost of $4,425.
    {¶7}    JAG brought suit against the Literskis in Hamilton County Municipal
    Court, alleging a breach of contract and an action on an account against Mr. Literski
    and unjust enrichment against both Mr. and Mrs. Literski. The Literskis answered
    and counterclaimed for breach of the agreement to perform the interior work for
    $500 that Trejo did not perform. Prior to trial, Diane Literski moved for summary
    judgment as to JAG’s sole claim against her, which the trial court granted. The
    remaining claims proceeded to a bench trial.
    {¶8}    At trial, the court allowed the Literskis to amend their counterclaim to
    add a claim under the roofing contract’s warranty. Mr. Literski testified that, after
    litigation had begun between the parties, the skylight in their home had leaked and
    had caused damage to the interior of their home. The Literskis had the leak repaired
    by Deer Park Roofing, and they produced an invoice from Deer Park Roofing for
    $200. The invoice contained a statement that the skylight had been “re-flashed.”
    The Literskis also produced a proposal from McCoy & Sons Painting and
    Wallpapering for repairs. In rebuttal, Cox testified that, if faulty flashing by JAG
    were to blame, then the skylight would have leaked within the first few rains, not
    after a year and a half. Cox also testified that, in his experience, a skylight leak is
    caused 99 percent of the time by a bad seal.
    {¶9}    In its findings of fact and conclusions of law, the trial court found that
    JAG had not entered into a contract with the Literskis to perform the interior work
    that Trejo was supposed to have performed. The trial court also found that, as to the
    4
    OHIO FIRST DISTRICT COURT OF APPEALS
    Literskis’ counterclaim under the warranty, the skylight leak could have been caused
    by something other than faulty roofing. The court also found that the Literskis had
    failed to notify JAG of the leak, as required by the warranty, which would then have
    given JAG the opportunity to inspect the leak. Therefore, the court denied the
    Literskis’ counterclaims and entered judgment for JAG for $8,556.50, plus interest.
    This appeal ensued.
    First Assignment of Error
    {¶10} The Literskis argue in their first assignment of error that the trial court
    erred in entering final judgment against Mr. Literski on JAG’s breach-of-contract
    claim because the trial court erroneously awarded $731.50 to JAG for work
    performed without a written order, which contradicted the plain language of the
    parties’ contract. JAG argues that this court should review the trial court’s judgment
    under a manifest-weight-of-the-evidence standard, meaning, as the supreme court
    recently clarified, whether the trial court’s judgment was supported by the greater
    amount of credible evidence, and whether the plaintiff met its burden of persuasion
    by a preponderance of the evidence.            SST Bearing Corp. v. Twin City Fan
    Companies, Ltd., 1st Dist. No. C-110611, 
    2012-Ohio-2490
    , ¶ 16, citing Eastley v.
    Volkman, __ Ohio St.3d __, 
    2012-Ohio-2179
    , __ N.E.2d __, ¶ 19.
    {¶11} The interpretation of a written contract is in the first instance a
    question of law that we review de novo. Warmack v. Arnold, 
    195 Ohio App.3d 760
    ,
    767, 
    2011-Ohio-5463
    , 
    961 N.E.2d 1165
     (1st Dist.).         If a contract is clear and
    unambiguous, then the plain language of the contract governs the parties’
    obligations. Aultman Hosp. Assn. v. Community Mut. Ins. Co., 
    46 Ohio St.3d 51
    , 53,
    
    544 N.E.2d 920
     (1989).
    5
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶12} The parties’ contract provided that “[a]ny alterations or deviations
    from above specifications involving extra costs will be executed only upon written
    orders, and will become an extra charge over and above the estimate.”           JAG
    employee Cox testified that the contract entered into between JAG and Mr. Literski
    for $10,325 had been based upon an estimate of approximately 33 roofing squares,
    because of the insurance adjuster’s estimate, but that Cox had told Mr. Literski that
    the project would likely take 35 squares. The project had taken more squares to
    complete than originally estimated, and thus JAG had added an additional $731.50
    to the original contract price. Cox testified that he had asked Mr. Literski for his
    insurance adjuster’s contact information so that JAG could submit a written request
    for supplemental payment for the extra squares. Mr. Literski had refused to give Cox
    the adjuster’s information, Cox testified, so JAG had not made a written request for
    supplement.
    {¶13} The unambiguous language of the parties’ agreement required that any
    deviation from the contract involving an extra cost “be executed only upon written
    orders[.]” Any prior oral agreements between the parties regarding how JAG would
    perform in the event that more squares were needed to do the job was inadmissible
    under the parol evidence rule. See Galmish v. Cicchini, 
    90 Ohio St.3d 22
    , 27, 
    734 N.E.2d 782
     (2000) (stating that, under the parol evidence rule, “absent fraud,
    mistake or other invalidating cause, the parties’ final written integration of their
    agreement may not be varied, contradicted or supplemented by evidence of prior or
    contemporaneous oral agreements, or prior written agreements.”).
    {¶14} Here, JAG performed work that deviated from the original contract,
    and that work was performed before placing a written order, in contravention of the
    6
    OHIO FIRST DISTRICT COURT OF APPEALS
    contract. JAG nonetheless argues that Mr. Literski prevented Cox from submitting a
    written request for supplement to the insurance adjuster by refusing to provide the
    facsimile number of the adjuster to Cox. Even if Mr. Literski refused to provide the
    adjuster’s contact information after JAG installed the additional squares, this would
    not have prevented JAG from complying with the express requirement in the
    contract that JAG place the written order before performing the additional work.
    {¶15} Therefore, because JAG acted outside the scope of the plain language
    of the contract by performing additional work before placing a written order, JAG
    cannot recover the cost of the additional work from the Literskis. See, e.g., Quadtek,
    Inc. v. Foister, 12th Dist. No. CA2004-09-112, 
    2005-Ohio-4191
    , ¶ 23. We sustain the
    Literskis’ first assignment of error to the extent that we hold that the trial court erred
    in awarding JAG an additional $731.50 above the contract balance of $7,825. The
    assignment of error is overruled in all other respects.
    Second Assignment of Error
    {¶16} The Literskis argue in their second assignment of error that the trial
    court erred in denying their counterclaims. Under this assignment of error, the
    Literskis first challenge the trial court’s determination that no contract existed
    between JAG and the Literskis for interior work in their home, despite testimony
    from both Mr. Literski and Cox that they had entered into an agreement for the
    interior work, although they did not agree on the terms. Whether or not a contract
    exists in this instance is a question of fact, which we review under a manifest-weight-
    of-the-evidence standard. See Oglebay Norton Co. v. Armco, 
    52 Ohio St.3d 232
    ,
    235, 
    556 N.E.2d 515
     (1990).
    7
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶17} Mr. Literski testified that he and Mrs. Literski had signed an
    agreement with Cox that if Simon Trejo did not perform the interior work for $500,
    then JAG would do it. The purported agreement was admitted into evidence. Cox
    testified that he had not signed the document that the Literskis alleged he had
    signed. Cox testified that he had signed an agreement for JAG to do the interior
    work if Trejo did not, however, that agreement had not contained a price term or
    date.
    {¶18} The trial court found that no contract had existed between the
    Literskis and JAG for the interior work, despite Cox’s testimony that he had signed
    an agreement for JAG to perform the interior work if Trejo did not. In order to form
    a services contract, the essential terms are, in general, the parties to the contract and
    the subject matter, and the contract terms are sufficiently definite if those terms
    provide a source for determining whether a breach has occurred and provide for a
    remedy. Mantia v. House, 
    178 Ohio App.3d 763
    , 
    2008-Ohio-5374
    , 
    900 N.E.2d 641
    ,
    ¶ 9 (2d Dist.). Therefore, at a minimum, JAG and the Literskis had satisfied the
    essential elements of a services contract when they had agreed that JAG would
    perform the interior work if Trejo did not.
    {¶19} Even though a contract had existed, the burden remained on the
    Literskis to prove the remaining elements of their breach-of-contract claim—
    including breach by JAG and damages. Allen testified that he had requested a time
    from Mr. Literski for Trejo to perform the interior work, but that Mr. Literski
    continually rebuffed JAG’s requests, stating that he had had personal problems.
    Eventually, Mr. Literski had told Allen that he would do the interior work himself.
    8
    OHIO FIRST DISTRICT COURT OF APPEALS
    Therefore, the trial court’s judgment denying the Literskis’ counterclaim for breach
    of contract for the interior work was not against the manifest weight of the evidence.
    {¶20} The Literskis next challenge the trial court’s denial of their claim under
    JAG’s roofing contract warranty. The Literskis argue that the trial court erred in
    finding that they failed to prove JAG’s workmanship caused the leak around the
    skylight. As with the Literskis’ denial of their breach-of-contract claim, we review
    the trial court’s judgment under a manifest-weight-of-the-evidence standard.
    Eastley, 
    2012-Ohio-2179
    , ¶ 19.
    {¶21} The trial court accepted the testimony of Cox that, in his experience, a
    skylight leak is caused 99 percent of the time by a bad seal, and that if faulty flashing
    were to blame, then the skylight would have leaked within the first few rains, not
    after a year and a half, when the Literskis had reported the problem. The Literskis
    argue that Cox’s testimony was improper and speculative because Cox never
    inspected the Literskis’ leak. Admissibility of opinion testimony is committed to the
    discretion of the trial court, and we will only reverse the trial court’s decision if it
    amounts to an abuse of discretion resulting in prejudicial error.         E.g., State v.
    Barton, 
    71 Ohio App.3d 455
    , 469, 
    594 N.E.2d 702
     (1st Dist.1991).
    {¶22} We cannot determine that the admission of Cox’s testimony resulted in
    prejudicial error. The only evidence that the Literskis put forth in support of their
    breach-of-warranty claim was the following: the testimony of the Literskis that their
    skylight had leaked a year and a half after JAG had installed their roof, and that the
    leak had caused damage to the interior of their home; an invoice from Deer Park
    Roofing stating that the skylight had been “re-flashed”; and a proposal from McCoy
    & Sons for painting and wallpaper for the damage caused by the leak. The statement
    9
    OHIO FIRST DISTRICT COURT OF APPEALS
    contained in the Deer Park Roofing invoice that the skylight had been re-flashed was
    hearsay. See Evid.R. 801(C). In the absence of any statements made by Deer Park
    Roofing regarding the cause of the leak, the Literskis failed to prove their breach-of-
    warranty claim by a preponderance of the evidence. Therefore, the trial court’s
    decision denying the Literskis’ warranty claim was not against the manifest weight of
    the evidence. Consequently, we overrule the Literskis’ second assignment of error.
    Conclusion
    {¶23} In conclusion, that portion of the trial court’s judgment awarding JAG
    $731.50 over and above the contract balance of $7,825 is reversed because JAG acted
    beyond the plain language of the contract in performing additional work without a
    written order. We affirm the remainder of the trial court’s judgment. Therefore, we
    reverse the trial court’s award of $8,556.50 for JAG, and we instruct the trial court
    on remand to enter judgment for JAG in the amount of $7,825, plus interest.
    Affirmed in part, reversed in part, and cause remanded.
    SUNDERMANN, P.J., and HENDON, J., concur.
    Please note:
    The court has recorded its own entry on the date of the release of this opinion.
    10