Hulett v. Ohio Dept. of Transp. , 2010 Ohio 6549 ( 2010 )


Menu:
  • [Cite as Hulett v. Ohio Dept. of Transp., 
    2010-Ohio-6549
    .]
    Court of Claims of Ohio
    The Ohio Judicial Center
    65 South Front Street, Third Floor
    Columbus, OH 43215
    614.387.9800 or 1.800.824.8263
    www.cco.state.oh.us
    JUDITH L. HULETT
    Plaintiff
    v.
    OHIO DEPARTMENT OF TRANSPORTATION
    Defendant
    Case No. 2010-04165-AD
    Deputy Clerk Daniel R. Borchert
    MEMORANDUM DECISION
    {¶ 1} Plaintiff, Judith L. Hulett, filed this action against defendant, Department of
    Transportation (ODOT), contending her 2007 Pontiac G6 was damaged as a proximate
    cause of negligence on the part of ODOT in maintaining a hazardous condition on the
    entrance ramp to Interstate 75 from State Route 63 in Warren County. Plaintiff related
    she was traveling on the Interstate 75 North entrance ramp when her automobile “hit (a)
    pot hole at (the) bottom of (the) ramp” causing tire and wheel damage to the vehicle.
    Plaintiff recalled the described incident occurred on February 18, 2010 at approximately
    7:00 a.m. Plaintiff requested damage recovery in the amount of $1,345.60, the stated
    total cost of a tire and two replacement rims. The filing fee was paid.
    {¶ 2} Defendant acknowledged the roadway area where plaintiff’s incident
    occurred was within the limits of a working construction project under the control of
    ODOT contractor, John R. Jurgensen Company (Jurgensen). Defendant explained the
    particular construction project “dealt with widening I-75 between Cincinnati-Dayton
    Road and SR 122 in Butler and Warren Counties.”              According to defendant, the
    construction project limits “corresponds (to) state mileposts 21.0 to 32.0” on Interstate
    75 and plaintiff’s damage incident occurred at milepost 29.12, a location within the
    construction area limits. Defendant asserted that this particular construction project was
    under the control of Jurgensen and consequently ODOT had no responsibility for any
    damage or mishap on the roadway within the construction project limits. Defendant
    argued that Jurgensen, by contractual agreement, was responsible for maintaining the
    roadway within the construction zone. Therefore, ODOT contended that Jurgensen is
    the proper party defendant in this action. Defendant implied that all duties such as the
    duty to inspect, the duty to warn, the duty to maintain, and the duty to repair defects
    were delegated when an independent contractor takes control over a particular section
    of roadway. Furthermore, defendant contended that plaintiff failed to introduce sufficient
    evidence to prove her damage was proximately caused by roadway conditions created
    by ODOT or its contractors. All construction work was to be performed in accordance
    with ODOT requirements and specifications and subject to ODOT approval.              Also
    evidence has been submitted to establish that ODOT personnel were present on site
    conducting inspection activities.
    {¶ 3} For plaintiff to prevail on a claim of negligence, she must prove, by a
    preponderance of the evidence, that defendant owed her a duty, that it breached that
    duty, and that the breach proximately caused her injuries.       Armstrong v. Best Buy
    Company, Inc., 
    99 Ohio St. 3d 79
    , 
    2003-Ohio-2573
    ,¶8 citing Menifee v. Ohio Welding
    Products, Inc. (1984), 
    15 Ohio St. 3d 75
    , 77, 15 OBR 179, 
    472 N.E. 2d 707
    . Plaintiff
    has the burden of proving, by a preponderance of the evidence, that she suffered a loss
    and that this loss was proximately caused by defendant’s negligence. Barnum v. Ohio
    State University (1977), 76-0368-AD. However, “[i]t is the duty of a party on whom the
    burden of proof rests to produce evidence which furnishes a reasonable basis for
    sustaining his claim. If the evidence so produced furnishes only a basis for a choice
    among different possibilities as to any issue in the case, he fails to sustain such
    burden.” Paragraph three of the syllabus in Steven v. Indus. Comm. (1945), 
    145 Ohio St. 198
    , 
    30 O.O. 415
    , 
    61 N.E. 2d 198
    , approved and followed. This court, as trier of
    fact, determines questions of proximate causation. Shinaver v. Szymanski (1984), 
    14 Ohio St. 3d 51
    , 14 OBR 446, 
    471 N.E. 2d 477
    .
    {¶ 4} Defendant had the duty to maintain its highways in a reasonably safe
    condition for the motoring public. Knickel v. Ohio Department of Transportation (1976),
    
    49 Ohio App. 2d 335
    , 3 O.O. 3d 413, 
    361 N.E. 2d 486
    . However, defendant is not an
    insurer of the safety of its highways. See Kniskern v. Township of Somerford (1996),
    
    112 Ohio App. 3d 189
    , 
    678 N.E. 2d 273
    ; Rhodus v. Ohio Dept. of Transp. (1990), 
    67 Ohio App. 3d 723
    , 
    588 N.E. 2d 864
    . The duty of ODOT to maintain the roadway in a
    safe drivable condition is not delegable to an independent contractor involved in
    roadway construction. ODOT may bear liability for the negligent acts of an independent
    contractor charged with roadway construction.            Cowell v. Ohio Department of
    Transportation, Ct. of Cl. No. 2003-09343-AD, jud, 
    2004-Ohio-151
    . Despite defendant’s
    contentions that ODOT did not owe any duty in regard to the construction project,
    defendant was charged with duties to inspect the construction site and correct any
    known deficiencies in connection with the particular construction work. See Roadway
    Express, Inc. v. Ohio Dept. of Transp. (June 28, 2001), Franklin App. 00AP-1119.
    {¶ 5} Alternatively, defendant denied that neither ODOT nor Jurgensen had any
    notice of the particular pothole prior to plaintiff’s property damage event. Defendant
    pointed out that ODOT records “indicate that no calls or complaints were received
    regarding a pothole prior to Plaintiff Hulett’s incident.” Defendant advised, “[i]t should be
    noted that this portion of I-75 has an average daily traffic volume between 73,320 and
    93,130, however, no other complaints were received (regarding a roadway defect) prior
    to plaintiff’s alleged incident.” Defendant contended plaintiff failed to offer any evidence
    of negligent roadway maintenance on the part of ODOT and failed to produce evidence
    to establish her property damage was attributable to conduct on either the part of ODOT
    or Jurgensen. Defendant denied receiving any complaints before February 18, 2010
    regarding a pothole on the Interstate 75 entrance ramp at approximate milepost 29.12.
    {¶ 6} Defendant submitted a letter from Jurgensen Project Manager, Kate
    Holden, who recorded she was notified of a pothole “at the end of the ramp from SR 63
    to northbound I-75” on February 23, 2010 by an e-mail from Jurgensen Project
    Engineer, Mark Wilson, According to Holden, this pothole on the Interstate 75 entrance
    ramp was repaired on February 24, 2010.
    {¶ 7} In order to find liability for a damage claim occurring in a construction
    area, the court must look at the totality of the circumstances to determine whether
    ODOT acted in a manner to render the highway free from an unreasonable risk of harm
    for the traveling public. Feichtner v. Ohio Dept. of Transp. (1995), 
    114 Ohio App. 3d 346
    , 
    683 N.E. 2d 112
    .       In fact, the duty to render the highway free from an
    unreasonable risk of harm is the precise duty owed by ODOT to the traveling public
    under both normal traffic and during highway construction projects. See e.g. White v.
    Ohio Dept. of Transp. (1990), 
    56 Ohio St. 3d 39
    , 42, 
    564 N.E. 2d 462
    .
    {¶ 8} In order to prove a breach of the duty to maintain the highways, plaintiff
    must prove, by a preponderance of the evidence, that defendant had actual or
    constructive notice of the precise condition or defect alleged to have caused the
    accident.   McClellan v. ODOT (1986), 
    34 Ohio App. 3d 247
    , 
    517 N.E. 2d 1388
    .
    Defendant is only liable for roadway conditions of which it has notice but fails to
    reasonably correct. Bussard v. Dept. of Transp. (1986), 
    31 Ohio Misc. 2d 1
    , 31 OBR
    64, 
    507 N.E. 2d 1179
    .
    {¶ 9} Generally, in order to recover in a suit involving damage proximately
    caused by roadway conditions including potholes, plaintiff must prove that either: 1)
    defendant had actual or constructive notice of the pothole and failed to respond in a
    reasonable time or responded in a negligent manner, or 2) that defendant, in a general
    sense, maintains its highways negligently.     Denis v. Department of Transportation
    (1976), 75-0287-AD. There is no evidence that defendant had actual notice of the
    pothole condition. Therefore, in order to recover plaintiff must produce evidence to
    prove constructive notice of the defect or negligent maintenance.
    {¶ 10} “[C]onstructive notice is that which the law regards as sufficient to give
    notice and is regarded as a substitute for actual notice or knowledge.” In re Estate of
    Fahle (1950), 
    90 Ohio App. 195
    , 197-198, 
    48 O.O. 231
    , 
    105 N.E. 2d 429
    . “A finding of
    constructive notice is a determination the court must make on the facts of each case not
    simply by applying a pre-set time standard for the discovery of certain road hazards.”
    Bussard.
    {¶ 11} The trier of fact is precluded from making an inference of defendant’s
    constructive notice, unless evidence is presented in respect to the time the defective
    condition developed. Spires v. Ohio Highway Department (1988), 
    61 Ohio Misc. 2d 262
    , 
    577 N.E. 2d 458
    .
    {¶ 12} In order for there to be constructive notice, plaintiff must show sufficient
    time has elapsed after the dangerous condition appears, so that under the
    circumstances defendant should have acquired knowledge of its existence. Guiher v.
    Dept. of Transportation (1978), 78-0126-AD. Size of the defect is insufficient to show
    notice or duration of existence. O’Neil v. Department of Transportation (1988), 
    61 Ohio Misc. 2d 287
    , 
    587 N.E. 2d 891
    . “Obviously, the requisite length of time sufficient to
    constitute constructive notice varies with each specific situation.” Danko v. Ohio Dept.
    of Transp. (Feb. 4, 1993), Franklin App. 92AP-1183. No evidence has shown ODOT
    had constructive notice of the pothole.
    {¶ 13} Plaintiff has not produced any evidence to infer that defendant, in a
    general sense, maintains its highways negligently or that defendant’s acts caused the
    defective condition. Herlihy v. Ohio Department of Transportation (1999), 99-07011-AD.
    Plaintiff has failed to prove that her damage was proximately caused by any negligent
    act or omission on the part of ODOT or its agents. See Wachs v. Dept. of Transp., Dist.
    12, Ct. of Cl. No. 2005-09481-AD, 
    2006-Ohio-7162
    ; Nicastro v. Ohio Dept. of Transp.,
    Ct. of Cl. No. 2007-09323-AD, 
    2008-Ohio-4190
    .
    Court of Claims of Ohio
    The Ohio Judicial Center
    65 South Front Street, Third Floor
    Columbus, OH 43215
    614.387.9800 or 1.800.824.8263
    www.cco.state.oh.us
    JUDITH L. HULETT
    Plaintiff
    v.
    OHIO DEPARTMENT OF TRANSPORTATION
    Defendant
    Case No. 2010-04165-AD
    Deputy Clerk Daniel R. Borchert
    ENTRY OF ADMINISTRATIVE DETERMINATION
    Having considered all the evidence in the claim file and, for the reasons set forth
    in the memorandum decision filed concurrently herewith, judgment is rendered in favor
    of defendant. Court costs are assessed against plaintiff.
    ________________________________
    DANIEL R. BORCHERT
    Deputy Clerk
    Entry cc:
    Judith L. Hulett                                 Jolene M. Molitoris, Director
    1377 Lakeshore Drive                             Department of Transportation
    Monroe, Ohio 45050                               1980 West Broad Street
    Columbus, Ohio 43223
    RDK/laa
    8/10
    Filed 9/15/10
    Sent to S.C. reporter 12/29/10
    

Document Info

Docket Number: 2010-04165-AD

Citation Numbers: 2010 Ohio 6549

Judges: Borchert

Filed Date: 9/15/2010

Precedential Status: Precedential

Modified Date: 10/30/2014