Westlake v. VWS, Inc. , 2014 Ohio 1833 ( 2014 )


Menu:
  • [Cite as Westlake v. VWS, Inc., 2014-Ohio-1833.]
    Court of Appeals of Ohio
    EIGHTH APPELLATE DISTRICT
    COUNTY OF CUYAHOGA
    JOURNAL ENTRY AND OPINION
    No. 100180
    CITY OF WESTLAKE
    PLAINTIFF-APPELLANT
    vs.
    VWS, INC., ET AL.
    DEFENDANTS-APPELLEES
    JUDGMENT:
    REVERSED AND REMANDED
    Civil Appeal from the
    Cuyahoga County Court of Common Pleas
    Case No. CV-12-790603
    BEFORE: S. Gallagher, J., Boyle, A.J., and Rocco, J.
    RELEASED AND JOURNALIZED: May 1, 2014
    ATTORNEYS FOR APPELLANT
    John D. Wheeler
    Director of Law
    Robin R. Leasure
    Sean F. Kelleher
    Assistant Directors of Law
    City of Westlake
    27700 Hilliard Blvd.
    Westlake, OH 44145
    ATTORNEYS FOR APPELLEE
    For VWS, Inc., et al.
    T. Christopher O’Connell
    Michael R. Stavnicky
    Singerman, Mills, Desburg & Kauntz Co., L.P.A.
    3333 Richmond Road
    Suite 370
    Beachwood, OH 44122
    For Board of Education of Westlake City Schools
    Bill J. Gagliano
    Ulmer & Berne, L.L.P.
    Skylight Office Tower
    1660 West 2nd Street, Suite 1100
    Cleveland, OH 44113
    For Cleveland-Cuyahoga County Port Authority
    Dennis R. Wilcox
    Climaco, Wilcox, Peca, Tarantino & Garofoli Co., L.P.A.
    55 Public Square, Suite 1950
    Cleveland, OH 44113
    For Cleveland Metroparks
    Rosalina M. Fini
    Law Director
    Cleveland Metroparks
    4101 Fulton Parkway
    Brooklyn, OH 44144
    For Cuyahoga Community College
    Mike DeWine
    Ohio Attorney General
    By: Holly E. LeClair
    Assistant Attorney General
    Education Section
    30 East Broad Street, 16th Floor
    Columbus, OH 43215
    For Cuyahoga County Fiscal Officer, et al.
    Timothy J. McGinty
    Cuyahoga County Prosecutor
    By: Brian R. Gutkoski
    Assistant Prosecuting Attorney
    Justice Center - 8th Floor
    1200 Ontario Street
    Cleveland, OH 44113
    SEAN C. GALLAGHER, J.:
    {¶1} Plaintiff-appellant city of Westlake, Ohio (“Westlake”), appeals the decision of
    the Cuyahoga County Court of Common Pleas that denied its motion for summary judgment
    and granted the cross-motion for summary judgment of defendants-appellees VSM Sewing,
    Inc. For the reasons stated herein, we reverse the judgment of the trial court, grant summary
    judgment in favor of Westlake in the amount of $359,913, and remand the matter to the trial
    court.
    {¶2} On September 4, 2012, Westlake filed a complaint for money damages against
    VSM Sewing, Inc., and VWS, Inc. (collectively referred to herein as “VSM”). 1                      The
    complaint raised a claim for breach of contract arising from a community reinvestment area
    agreement (“CRA Agreement”) entered on May 5, 1998, between Westlake and VWS, Inc.,
    which is now known as VSM Sewing, Inc.
    {¶3} The CRA Agreement set forth VSM’s desire to construct a new 100,000 square
    foot facility in Westlake’s community reinvestment area provided that appropriate
    development incentives were made available. It also set forth Westlake’s understanding that
    “[VSM] is qualified by financial responsibility and business experience to create and
    preserve employment opportunities in said Community Reinvestment Area and improve the
    1
    The complaint also named VSM Group, A.B., as a defendant, but this party was voluntarily
    dismissed from the action by Westlake. Also named to the action, because of their potential interest
    in any recovery by Westlake, were the Cuyahoga County Fiscal Officer, the Board of Education of the
    Westlake City Schools, Westlake Porter Public Library, Cleveland Metroparks, Cleveland-Cuyahoga
    County Port Authority, and Cuyahoga Community College.
    economic climate of Westlake.” The CRA Agreement contained mutual covenants agreed
    to between the parties and provided for a 15-year tax-exemption period.
    {¶4} The CRA Agreement was entered pursuant to and in conformance with R.C.
    3735.671, following application by VSM pursuant to R.C. 3735.67.            Pursuant to R.C.
    3735.67(D)(1), exemptions may be granted for the construction of new commercial structures
    located within a community reinvestment area for a period determined by the legislative
    authority, but not exceeding 15 years.     R.C. 3735.671 provides for the written agreement
    for the exemption from taxation of commercial or industrial property located in a community
    reinvestment area. It specifically states that the written agreement is “binding on both
    parties for a period of time that does not end prior to the end of the period of the exemption”
    and shall include “all of the information and statements prescribed by this section.” R.C.
    3735.671(A). Further, the statute permits parties to include additional terms, provided they
    “in no way derogate from the information and statements prescribed by this section.” 
    Id. {¶5} The
    CRA Agreement contained the prescribed language, as well as additional
    terms. Relevant sections of the CRA Agreement were as follows.
    {¶6} Section 1 of the CRA Agreement provided for the construction of the 100,000
    square foot facility to be leased by VSM and set forth VSM’s obligations for the purchase
    and installment of new machinery and equipment.
    {¶7} Section 2 of the CRA Agreement contained VSM’s hiring schedule, under which
    VSM agreed that it would increase its number of employees over five years, thereby
    benefitting Westlake with increased payroll and income tax revenue. Section 2 provides the
    following:
    Applicants’ schedule for hiring is as follows: * * * A total number of
    twenty-six (26) new full-time jobs and two (2) new part-time jobs will be
    created by the end of the year 2003. * * *.
    The increase in the number of employees will result in approximately
    Nine Hundred Ninety-Eight Thousand Dollars ($998,000.00) of additional
    payroll over five (5) years for [VSM]. The retention of the existing jobs will
    maintain the current payroll of Two Million One Hundred Ninety-Three
    Thousand Dollars ($2,193,000.00).
    {¶8} Section 3 of the CRA Agreement provides in part that VSM “shall make its best
    efforts” to ensure at least 25 percent of the new employees are residents of Westlake and that
    VSM “will create one or more temporary internship positions for students” enrolled within
    the Westlake School District.
    {¶9} Section 4 of the CRA Agreement contains tax incentives offered by Westlake,
    providing in relevant part:
    Westlake hereby grants [VSM] a tax exemption for real property
    improvements made to the Project Site pursuant to Section 3735.67 of the Ohio
    Revised Code and shall be for fifteen (15) years at a tax exemption amount of
    fifty percent (50%). As a condition of this tax exemption, [VSM’s] income
    payroll tax must be eighty percent (80%) of the amount projected herein or the
    abatement will be subject to amendment of the terms of this Agreement or
    Westlake may rescind the tax exemptions granted herein.
    The exemption commences the first year for which the real property
    would first be taxable were the property not exempted from taxation. No
    exemption shall commence before December 31, 1998 nor extend beyond
    December 31, 2013.
    (Emphasis added.)
    {¶10} Under Section 5 of the CRA Agreement, VSM agreed to pay an annual fee to
    Westlake.
    {¶11} Section 6 of the CRA Agreement requires VSM to pay non-exempted real
    property taxes and to file all tax reports and returns required by law. The failure to do so
    results in “all incentives granted under this Agreement are rescinded beginning with the year
    for which such taxes are charged or such reports or returns are required to be filed and
    thereafter.”
    {¶12} Section 9 of the CRA Agreement sets forth Westlake’s rights in the event of a
    material breach and contains what is referred to as a “clawback” provision:
    If [VSM] materially fails to fulfill its obligations under this Agreement *
    * * , Westlake may terminate or modify the exemptions from taxation granted
    under this Agreement and may require the repayment from the Applicant of the
    amount of taxes that would have been payable had the property not been
    exempted from taxation under this Agreement.
    {¶13} VSM commenced operations in Westlake in 1999 and remained there until late
    2008 or early 2009, when it closed its Westlake facility and moved its headquarters out of
    Ohio. VSM met or exceeded the income payroll tax level for tax years 1999 through 2008
    and received a real property tax abatement for those years.
    {¶14} Westlake claims that VSM breached the CRA Agreement by closing its facility
    and thereby failing to fulfill its contractual obligations to increase and maintain employees,
    payroll and payroll income tax, and to pay an annual fee to Westlake. Westlake’s position is
    that VSM only met its obligations for ten years of the 15-year agreement and that there was a
    complete failure of material obligations when VSM closed its operations and reduced its
    payroll to zero.
    {¶15} On or about May 6, 2010, Westlake’s city council passed ordinance No.
    2010-66, which reduced the abatement percentage for VSM to 0 percent and revoked all
    abatement exemptions previously granted to VSM.             Westlake Ordinances 2010-66.
    Thereafter, Westlake filed this action for breach of contract. Under the complaint, Westlake
    sought to recover exempted taxes and annual unpaid fees in the amount of $363,767.38.
    {¶16} Westlake filed a motion for summary judgment, and VSM filed a cross-motion
    for summary judgment. In moving for summary judgment, Westlake sought damages in the
    amount of $359,913.00 and submitted an affidavit of Robert Parry, Director of Planning and
    Economic Development of the city of Westlake, with supporting documentation.
    {¶17} In their motions, the parties agreed that the CRA Agreement was unambiguous
    and presented a question of interpretation for the court. The trial court denied Westlake’s
    motion and granted VSM’s cross-motion. The trial court found in part as follows:
    VSM did not breach the Agreement by remaining in Westlake only ten
    to eleven years of the fifteen years of tax abatement. The provision of the
    Agreement requiring VSM to maintain payroll tax at a minimum of 80 percent
    was a condition precedent. Failure to meet this threshold resulted in VSM not
    receiving a tax exemption but does not constitute a breach of the Agreement.
    There is no set minimum duration which required VSM to perform any task
    including remaining in Westlake. Westlake does not argue that VSM did not
    meet any of its obligations which resulted in a breach invoking Section 9 prior
    to leaving Westlake. As a result, the court finds there is no genuine issue of
    fact as to whether VSM breached the agreement with the city.
    {¶18} Westlake timely filed this appeal. Westlake’s sole assignment of error is as
    follows:
    The trial court erred in finding defendants did not breach the tax abatement
    agreement between the city of Westlake and VWS, Inc. when it ceased
    operations within the city and moved its corporate headquarters out of the city
    of Westlake and the state of Ohio prior to the expiration of the agreement.
    {¶19} Appellate review of summary judgment is de novo. Comer v. Risko, 106 Ohio
    St.3d 185, 2005-Ohio-4559, 
    833 N.E.2d 712
    , ¶ 8. Additionally, the construction of a written
    contract presents a question of law that is reviewed de novo. Saunders v. Mortensen, 
    101 Ohio St. 3d 86
    , 2004-Ohio-24, 
    801 N.E.2d 452
    , ¶ 9. The intent of the parties is presumed to
    be reflected within the language used in the written instrument. 
    Id. at ¶
    9.
    Where the parties following negotiation make mutual promises which
    thereafter are integrated into an unambiguous contract duly executed by them,
    courts will not give the contract a construction other than that which the plain
    language of the contract provides.
    Aultman Hosp. Assn. v. Community Mut. Ins. Co., 
    46 Ohio St. 3d 51
    , 
    544 N.E.2d 920
    (1989),
    paragraph one of the syllabus.
    {¶20} The facts of this case are undisputed, and resolution of the matter involves the
    construction of the CRA Agreement. Westlake claims the trial court erred in finding VSM
    failed to satisfy a condition precedent, as opposed to materially breaching the CRA
    Agreement, by failing to remain in the Westlake facility. Westlake argues that there was a
    material failure of performance through VSM’s act of closing its Westlake operation and
    reducing its employment level to zero. Westlake states that VSM completely deprived
    Westlake of the income tax revenue it reasonably expected to receive through the entire
    15-year exemption period.
    {¶21} The trial court determined there was no set minimum duration for VSM to
    remain in Westlake. We recognize the trial court relied upon the lack of a specific provision
    in the CRA Agreement requiring VSM to continue its operations for a specific duration of
    time. However, the 15-year exemption period was fundamental to the agreement and the
    parties’ performance. The CRA Agreement included Westlake’s understanding that VSM
    would create and preserve employment opportunities in the community reinvestment area.
    VSM promised to increase its payroll and income taxes to Westlake in exchange for
    Westlake’s promise to provide the 15-year tax-exemption period.         The parties thereby
    expressed an intent to perform for 15 years under the CRA Agreement.
    {¶22} Further, the parties were statutorily bound to perform through the end of the
    exemption period. R.C. 3735.671(A). Section 4 of the CRA Agreement provided “[n]o
    exemption shall commence before December 31, 1998 nor extend beyond December 31,
    2013.” The obligations created under the CRA Agreement were mutually agreed upon
    promises that were binding upon both parties for the entire tax-exemption period.
    {¶23} Pursuant to Section 4 of the CRA Agreement, as a “condition of this tax
    exemption” VSM was required to maintain income payroll tax at 80 percent of the projected
    amount. If the threshold was not met, the abatement was subject to either amendment or
    rescission. The trial court found this created a condition precedent and that the failure of the
    condition could not amount to a breach of contract.
    {¶24} Under basic contract law, “[a] condition is an event, not certain to occur, which
    must occur, unless its non-occurrence is excused, before performance under a contract
    becomes due.” Restatement of the Law 2d, Contracts, Section 224 (1981). A condition
    precedent is an event that must take place before a duty to perform arises. Atelier Dist. v.
    Parking Co. of Am., Inc., 10th Dist. Franklin No. 07AP-87, 2007-Ohio-7138, ¶ 35.
    “Whether a provision in a contract is a condition precedent is a question of the parties’ intent.
    Intent is ascertained by considering not only the language of a particular provision, but also
    the language of the entire agreement and its subject matter.” Troha v. Troha, 105 Ohio
    App.3d 327, 334, 
    663 N.E.2d 1319
    (2d Dist.1995). Conditions precedent are not favored
    under contract law and will not be found unless the agreement plainly shows an intent to the
    contrary.    Campbell v. George J. Igel & Co., 4th Dist. Hocking No. 13CA4,
    2013-Ohio-3584, ¶ 13.
    {¶25} Here, even if we viewed the 80-percent threshold as a condition to performance
    under the contract, VSM would not be excused from performing because it caused the failure
    of the condition. A party is not excused from its contractual obligations when the condition
    is in its best interest and sole responsibility. Atelier at ¶ 37. Put simply, a party to a
    contract may not rely upon the failure of a condition that the party’s own action or inaction
    caused to occur. See Gulf Oil Corp. v. Am. Louisiana Pipe Line Co., 
    282 F.2d 401
    , 404-405
    (6th Cir.1960).
    {¶26} Additionally, a review of the CRA Agreement shows the parties did not intend
    to excuse the performance of their contractual obligations. It is clear from a review of the
    entire agreement that a mutual exchange of promises was intended by the parties. VSM
    agreed to conduct operations at a new facility constructed in Westlake and to provide
    80-percent of the promised income payroll tax in exchange for the agreed-upon 15-year tax
    exemption. These bargained-for promises were fundamental to the agreement.
    {¶27} VSM was obligated to perform for the entire term of the agreement. The
    failure to meet the 80-percent threshold authorized Westlake to amend or rescind the
    exemptions. It did not call for a termination of the CRA Agreement. This was consistent
    with Section 6 of the CRA Agreement, which provided that if VSM failed to pay the
    non-exempt real property taxes that were owed, then the tax abatement would be rescinded
    “beginning with the year for which such taxes are charged.”
    {¶28} Under Section 2 of the CRA Agreement, VSM agreed that it would retain its
    existing jobs and maintain the current payroll, in addition to increasing its number of
    employees over five years, resulting in additional payroll. Further, pursuant to Section 3 of
    the CRA Agreement, VSM was required to make its best efforts to ensure that at least 25
    percent of its employees were residents of Westlake and provide a Westlake internship. By
    ceasing its operations in Westlake, VSM failed to fulfill its contractual obligations through
    the entire term of the CRA Agreement. The trial court found that these alleged breaches
    arose from VSM’s closing its operations in Westlake and were first raised in Westlake’s
    reply in support/opposition to cross-motion for summary judgment. Our review reflects that
    Westlake maintained throughout its pleadings that by closing its operations and moving out
    of Westlake, VSM failed to fulfill its obligations under the CRA Agreement. Moreover, we
    find these provisions are relevant to ascertaining the intent of the parties and whether a
    material breach of the contract occurred.
    {¶29} Section 9 of the CRA Agreement authorized Westlake to exercise the clawback
    option if a material breach occurred. “A ‘material breach of contract’ is a failure to do
    something that is so fundamental to a contract that the failure to perform defeats the essential
    purpose of the contract or makes it impossible for the other party to perform.” Marion
    Family YMCA v. Hensel, 
    178 Ohio App. 3d 140
    , 2008-Ohio-4413, 
    897 N.E.2d 184
    , ¶ 7 (3d
    Dist.).
    {¶30} We would agree that the failure to meet the 80-percent threshold in any given
    year despite good-faith efforts to do so would not have been a material breach for purposes
    of the clawback provision.        However, by closing its operations, VSM abandoned its
    contractual obligations and made it impossible for Westlake to perform. Westlake was
    deprived of income tax revenue it reasonably expected to receive through the 15-year
    exemption period. The essential purpose of the contract was defeated. Moreover, it cannot
    be said that VSM substantially performed under the contract when it completely failed to
    perform for five of the fifteen years required.      Because VSM materially breached the
    agreement, Westlake was entitled to invoke the clawback provision.
    {¶31} Accordingly, we reverse the judgment of the trial court and grant summary
    judgment in favor of Westlake in the amount of $359,913.00. The case is remanded to the
    trial court to enter judgment in favor of Westlake and to determine the respective interests of
    all other defendants as it relates to plaintiff’s claim.
    {¶32} Judgment reversed; case remanded.
    It is ordered that appellant recover from appellees costs herein taxed.
    The court finds there were reasonable grounds for this appeal.
    It is ordered that a special mandate issue out of this court directing the common pleas
    court to carry this judgment into execution.
    A certified copy of this entry shall constitute the mandate pursuant to Rule 27 of the
    Rules of Appellate Procedure.
    SEAN C. GALLAGHER, JUDGE
    MARY J. BOYLE, A.J., CONCURS;
    KENNETH A. ROCCO, J., DISSENTS (WITH SEPARATE OPINION)
    KENNETH A. ROCCO, J., DISSENTING:
    {¶33} I respectfully dissent from the majority opinion’s disposition of this appeal. In
    my view, the CRA Agreement is subject to more than one reasonable interpretation;
    therefore, summary judgment should not have been granted by the trial court in favor of
    VSM or by this court in favor of Westlake.
    {¶34} When faced with an issue of contract interpretation, a court must give effect to
    the intent of the parties as reflected in the language of the contract. Shifrin v. Forest City
    Ents., Inc., 
    64 Ohio St. 3d 635
    , 637, 
    597 N.E.2d 499
    (1992). A contract is construed as a
    matter of law if the contract is “clear and unambiguous.” Nationwide Mut. Fire Ins. Co. v.
    Guman Bros. Farm, 
    73 Ohio St. 3d 107
    , 108, 
    652 N.E.2d 684
    (1995).          The meaning of an
    ambiguous contract, however, is an issue of fact to be decided by the trier of fact. Brown v.
    Columbus All-Breed Training Club, 
    152 Ohio App. 3d 567
    , 2003-Ohio-2057, 
    789 N.E.2d 648
    , ¶ 18 (10th Dist.). A contract is ambiguous if it is “susceptible to more than one
    reasonable interpretation.” Michael A. Gerard, Inc. v. Haffke, 8th Dist. Cuyahoga No.
    98488, 2013-Ohio-168, ¶ 11, citing Hillsboro v. Fraternal Order of Police, Ohio Labor
    Council, Inc., 
    52 Ohio St. 3d 174
    , 177, 
    556 N.E.2d 1186
    (1990).
    {¶35} The CRA Agreement is inartfully drafted.          While the CRA Agreement
    includes form language specified in R.C. 3735.671, as required by law, the key provision at
    issue, section 4 of the CRA Agreement, is not part of the form language specified by the
    statute.
    {¶36} Section 4 of the Agreement states that VSM must maintain the 80% income
    payroll tax threshold “[a]s a condition of [the] tax exemption” granted by Westlake.   Section
    4 further provides that if the income payroll tax threshold is not met, “the abatement will be
    subject to amendment of the terms of this Agreement or Westlake may rescind the tax
    exemptions granted herein.”     Section 4 does not reference the “clawback” provision in
    section 9, and there is nothing in section 4 or any other section of the CRA Agreement that
    expressly requires VSM to maintain the 80% income payroll tax threshold for the entire
    15-year tax-exemption period in order to receive (and retain) a tax exemption for years in
    which the threshold was met.    Reading the CRA Agreement as a whole and giving effect to
    all of the language used by the parties, I believe the agreement is ambiguous as to VSM’s
    obligations under the CRA Agreement, in particular VSM’s obligations with respect to the
    income payroll tax threshold in section 4 of the agreement and the consequences of VSM’s
    failure to meet that threshold in any given year.
    {¶37} The majority opinion acknowledges that the CRA Agreement contains no
    “specific provision * * * requiring VSM to continue its operations for a specific duration of
    time.”    Nevertheless, based on its determination that “the 15-year exemption period was
    fundamental to the agreement and the parties’ performance,” the majority reads into the
    agreement an “intent to perform for 15 years under the CRA Agreement” and, then, based on
    that presumed intent, interprets the agreement as setting forth “mutually agreed upon
    promises that were binding upon both parties for the entire tax-exemption period.”      In the
    absence of an express provision obligating VSM to perform for a specific duration, I do not
    believe that it is the role of this court to construe the CRA Agreement, as a matter of law, as
    obligating VSM to maintain the income payroll tax threshold specified in section 4 of the
    agreement for the entire 15-year tax-exemption period. DDR Rio Hondo, L.L.C. v. Sunglass
    Hut Trading, L.L.C., 8th Dist. Cuyahoga No. 98986, 2013-Ohio-1800, ¶ 24 (“principles of
    contract interpretation preclude us from rewriting the contract by reading into it language or
    terms that the parties omitted”).      Although the majority’s interpretation may be one
    reasonable interpretation of the CRA Agreement, I do not believe it is the only reasonable
    interpretation of the agreement as drafted.   Where a contract is ambiguous, and “[t]he clear
    intent of the parties * * * cannot be ascertained on the face of the contract,” the granting of
    summary judgment “based on the four corners of the contract” is improper, and the matter
    “must be resolved by the consideration of extrinsic evidence to be decided by the trier of
    fact.” 
    Id. at ¶
    24; see also Inland Refuse Transfer Co. v. Browning-Ferris Industries of
    Ohio, Inc., 
    15 Ohio St. 3d 321
    , 322-324, 
    474 N.E.2d 271
    (1984).
    {¶38} Based on my belief that the CRA Agreement is ambiguous and that a genuine
    issue of material fact, therefore, exists as to whether VSM materially breached the CRA
    Agreement, I would find that the trial court should have denied both parties’ motions for
    summary judgment. Accordingly, I would sustain Westlake’s assignment of error to the
    extent Westlake contends that the trial court erred in entering summary judgment in favor of
    VSM. However, I would find that Westlake is not entitled to summary judgment either and
    would remand the case so that the issue of liability may be properly determined by the trier of
    fact.