Frank Novak & Sons, Inc. v. A-Team, L.L.C. , 2014 Ohio 922 ( 2014 )


Menu:
  • [Cite as Frank Novak & Sons, Inc. v. A-Team, L.L.C., 
    2014-Ohio-922
    .]
    Court of Appeals of Ohio
    EIGHTH APPELLATE DISTRICT
    COUNTY OF CUYAHOGA
    JOURNAL ENTRY AND OPINION
    No. 99777
    FRANK NOVAK & SONS, INC.
    PLAINTIFF-APPELLEE/
    CROSS-APPELLANT
    vs.
    A-TEAM, L.L.C., D.B.A. SERVICEMASTER
    DEFENDANT-APPELLANT/
    CROSS-APPELLEE
    JUDGMENT:
    AFFIRMED IN PART, REVERSED IN PART,
    AND REMANDED
    Civil Appeal from the
    Cuyahoga County Court of Common Pleas
    Case No. CV-09-685057
    BEFORE: Boyle, A.J., E.A. Gallagher, J., and Blackmon, J.
    RELEASED AND JOURNALIZED:                             March 13, 2014
    ATTORNEY FOR APPELLANT
    Kevin J. Kelley
    Porter Wright Morris & Arthur
    925 Euclid Avenue
    Suite 1700
    Cleveland, Ohio 44115
    ATTORNEYS FOR APPELLEE
    Keith R. Kraus
    Grant J. Keating
    Dworken & Bernstein Co., L.P.A.
    50 South Park Place
    Painesville, Ohio 44077
    MARY J. BOYLE, A.J.:
    {¶1} Defendant-appellant,         A-Team,       L.L.C.,     d.b.a.     ServiceMaster
    (“ServiceMaster”) appeals the trial court’s judgment in favor of plaintiff-appellee, Frank
    Novak & Sons, Inc. (“Novak”) on Novak’s breach of contract claim and ServiceMaster’s
    counterclaims for breach of contract and unjust enrichment.      Novak also cross-appeals,
    challenging the trial court’s judgment with respect to its claim under R.C. 4113.61 (“Ohio’s
    Prompt Payment Act”).     We affirm the trial court’s award in favor of Novak on its breach
    of contract claim, reverse the trial court on its application of the Prompt Payment Act, and
    remand for further proceedings.
    Procedural History and Facts
    {¶2} This case involves a dispute between a general contractor and subcontractor
    related to work performed in the summer of 2007 to restore the Cleveland Browns Stadium
    (the “Property”) in time for the Browns’ first pre-season game. On July 14, 2007, during a
    concert, the Property sustained severe water damage because of faulty plumbing.         The
    next day, ServiceMaster was hired as the general contractor to perform cleaning,
    restoration, and construction for the Property. ServiceMaster, in turn, hired Novak as a
    subcontractor to perform painting, flooring, and wall covering work. While the parties
    were performing work related to the July 14th incident, a severe rainstorm occurred on
    August 2, 2007, causing further damage to the Property, and resulting in Novak performing
    additional work.
    {¶3} Novak brought the underlying action seeking to recover money allegedly
    owed by ServiceMaster in connection with work Novak performed for the August 2, 2007
    project.   Novak further sought to separately recover prejudgment interest and attorney fees
    under R.C. 4113.61, Ohio’s Prompt Payment Act, for ServiceMaster’s alleged failure to
    timely pay after having received payment itself.
    {¶4} The parties disputed the nature of the contract that governed, and both parties
    ultimately changed their respective positions during the course of the litigation. While
    Novak initially asserted that the parties entered into a “subcontractor agreement” and
    attached a written subcontractor agreement to the complaint, Novak changed its position
    and filed an amended complaint, asserting that the parties “entered into an oral agreement.”
    Conversely, ServiceMaster initially answered the complaint and responded to requests for
    admissions, denying that the subcontractor agreement was the contract between the parties.
    It then, however, amended its answer to state that the parties entered into a written
    subcontractor agreement — the same subcontractor agreement attached to Novak’s original
    complaint (“subcontractor agreement”).
    {¶5} After Novak filed its second amended complaint, ServiceMaster answered
    and asserted two counterclaims for breach of contract and unjust enrichment.
    ServiceMaster alleges that all the work performed by Novak was governed by the single
    written subcontractor agreement, signed by ServiceMaster’s president, Ed Ranieri.
    ServiceMaster alleged that the severe rain of August 2, 2007, resulted in an expanded scope
    of work but that the parties agreed that Novak would continue to provide flooring and
    painting services “under the terms of their agreement.”    ServiceMaster further alleged that
    Novak “breached this agreement as it has been paid substantially more than what is
    provided in their agreement.”    ServiceMaster’s claim is based on two specific provisions
    in the subcontractor agreement — (1) “an administrative fee provision” providing that all
    payments are subject to a 20 percent administrative fee, and (2) “a pay when paid
    provision” providing that Novak will be paid when ServiceMaster has received payment
    from the property owner, the property owner’s agent and/or the relevant insurance
    company.
    {¶6} In support of its unjust enrichment claim, ServiceMaster alleged that it made
    payments to Novak totaling $430,000 and that Novak negotiated an additional payment of
    $100,450 directly from the Cleveland Browns, of which it never informed ServiceMaster.
    Based on these collective payments, ServiceMaster alleged that Novak has been overpaid
    for its work on the Property and that “it would be unjust for [Novak] to retain this benefit.”
    {¶7} The case ultimately proceeded to a bench trial.
    {¶8} Novak presented documentary evidence establishing that ServiceMaster
    entered into separate contracts with the property owner’s agent to perform restoration work
    on the Property in response to the pipe–sewer backup of July 14th (“Loss 1”) and the
    rainwater intrusion on August 2nd (“Loss 2”).
    {¶9} Bradley Pinchot, vice president of Novak, testified that his company was
    hired by ServiceMaster to perform services related to both Loss 1 and Loss 2, but that Loss
    1 and Loss 2 were two separate projects. Pinchot expressly denied that Loss 2 was an
    extension of the scope of work under Loss 1.           According to Pinchot, ServiceMaster
    specifically required Novak to distinguish from the work it performed with respect to Loss
    1 and Loss 2 because they were two separate projects.
    {¶10} With respect to Loss 2, Pinchot testified that Novak had an oral contract with
    ServiceMaster to perform the work.       Specifically, Pinchot testified that he entered into an
    oral contract with Pete D’Agostino, a project executive from ServiceMaster, for Novak to
    perform the work on Loss 2 and that ServiceMaster would pay on a “time and material
    basis.”
    {¶11} Pinchot further testified that he had received the subcontractor agreement
    “two or three weeks after” Novak commenced work at the stadium.          Pinchot stated that he
    never signed or approved the terms.       With respect to the administrative fee provision in
    the subcontractor agreement, Pinchot testified that the 20 percent administrative fee “is
    actually more than what is in [Novak’s] billing rate for allowable overhead and profit,” and
    therefore Novak never agreed to the agreement.          Pinchot explained that Novak would
    have lost money from day one if it agreed to the subcontractor agreement so “we didn’t
    execute it for that reason.”    Pinchot further explained that Novak pulled its people from
    other jobs to work on Loss 1 and that it never would have pulled labor off other paying jobs
    to work on another job that Novak would lose money from the inception.
    {¶12} Novak submitted invoices totaling $535,000 for flooring work performed on
    Loss 1. It is undisputed that Novak received $430,000 in payment from ServiceMaster.
    According to Pinchot’s testimony, these payments were applied to Loss 1 invoices, which
    were their oldest outstanding invoices. Pinchot testified that ServiceMaster never applied
    a 20 percent administrative fee to the invoices submitted by Novak.      With respect to the
    outstanding balance on Loss 1 and other unpaid invoices that Novak had from other
    contractors that it performed work for related to the faulty plumbing, Novak placed a
    mechanic’s lien on the Property, prompting the Browns to directly negotiate a settlement
    with Novak on its Loss 1 claims ($100,450) in return for its release of the lien. The
    settlement agreement was executed on June 13, 2008, and releases any claims with respect
    to Loss 1 against ServiceMaster and the other contractors.        The settlement agreement,
    however, expressly excludes any claim that Novak may have regarding Loss 2 and
    preserves its right to pursue such a claim.
    {¶13} As for the Loss 2 work, Pinchot testified that Novak initially submitted an
    invoice, dated August 21, 2007, for its services in the amount of $39,643.15, which
    included an estimate of future work to finish the project that ServiceMaster requested
    Novak to include. According to Pinchot, Novak subsequently submitted a revised invoice,
    which reflected the actual labor and materials used, resulting in a reduced invoice of
    $37,158.82. Pinchot testified that, although the insurance company approved this invoice
    for payment in the amount of $31,000, Novak never received any payment from
    ServiceMaster on this invoice.
    {¶14} Novak further presented the testimony of Erica Burmeister, who previously
    worked in the administrative department of ServiceMaster and was assigned as the project
    auditor for the Cleveland Browns job.         According to an internal document prepared by
    Burmeister, the $430,000 in payments made by ServiceMaster were for Loss 1 payments,
    and no payments were made toward Loss 2.
    {¶15} Novak called ServiceMaster’s president, Ed Ranieri, as a witness, who
    admitted on direct examination that all of the work performed by Novak on Loss 1 and
    Loss 2 was “excellent.” Ranieri further testified that Pete D’Agostino hired Novak with
    respect to Loss 2. Although Ranieri initially stated that Novak entered into an “oral”
    contract with ServiceMaster, he immediately recanted, indicating that the relationship was
    always governed by the written subcontractor agreement.
    {¶16} Ranieri acknowledged that he never objected to any of the invoices submitted
    by Novak.    Ranieri further corroborated Pinchot’s testimony that the insurance company
    approved $31,617.28 on Novak’s final Loss 2 invoice. Ranieri further confirmed that
    ServiceMaster received two separate $100,000 checks on January 9, 2008, with respect to
    Loss 2 invoices.
    {¶17} On cross-examination, Ranieri testified that ServiceMaster hired “probably
    20, 25” subcontractors on the Cleveland Browns Stadium job and that it required executed
    written subcontractor agreements from all of its subcontractors given that it involved a
    “multimillion dollar gig.”   According to Ranieri, there was no oral contract with Novak.
    Ranieri testified further that the additional work caused by the August 2, 2007 rainstorm
    fell within the scope of the original written subcontractor agreement.   Ranieri stated that
    Novak never indicated that it considered the additional work to be a “separate job” nor did
    it ever discuss separate contractual terms for Loss 2.
    {¶18} Ranieri further testified that ServiceMaster, as the general contractor, received
    invoices from the subcontractors that it forwarded to the insurance adjustor, the city of
    Cleveland, and the Cleveland Browns. According to Ranieri, ServiceMaster’s invoices
    were not paid in full — “not even close.”    Ranieri stated that ServiceMaster “took a 1.2
    million hit” on this job. Ranieri also testified that, when it received payment from the
    owner or the owner’s agent, the payment was never accompanied with instructions as to
    which subcontractor’s invoices should be paid. According to Ranieri, ServiceMaster paid
    Novak $430,000 on its invoices despite only $409,000 being approved. Applying the
    administrative fee in the written agreement and the allowed adjusted amount, Ranieri
    testified that Novak was only entitled to $327,578.50 with respect to all the work
    performed.
    {¶19} The trial court also heard testimony from Gregory Zeigler, an account
    manager at Affiliated FM Global, who was the adjustor handling the claims submitted in
    response to Loss 1 and Loss 2. According to Zeigler, Affiliated FM Global received a
    total of $297,346 in invoices regarding work performed for Loss 2. Of the invoices
    submitted, $31,617.28 was specifically approved and earmarked for Novak’s work on Loss
    2.
    {¶20} In support of its case, ServiceMaster offered the testimony of Gary Cerasi,
    ServiceMaster’s accountant for approximately the last ten years.     According to Cerasi, a
    20 percent administrative fee provision is very common in the construction industry.
    Cerasi testified as to his familiarity with the invoices submitted by Novak to ServiceMaster
    regarding the Property. Cerasi assisted ServiceMaster “to help job cost the job” and
    oversaw the invoices to “make sure the overall accounting of the job was being taken care
    of.” According to Cerasi, he never knew “about Loss 1 or Loss 2 until we saw the
    Affiliated things way down the road.”   Cerasi further testified that, even if the insurance
    company for the owner asked the subcontractor to classify the job as “Loss 1 [and] Loss 2,”
    there is no accounting reason for ServiceMaster to consider the job that way. Cerasi
    further testified that ServiceMaster never received any instructions as to how to apply
    payments upon receipt from either the Cleveland Browns, Affiliated FM Global, or the city
    of Cleveland.
    {¶21} According to Cerasi, after applying the adjustments made to the invoices
    submitted, Novak should have been paid no more than $409,473. Cerasi further testified
    that the administrative fee should have applied to that amount resulting in Novak receiving
    a reduced payment of $327,598.
    {¶22} On cross-examination, Cerasi acknowledged that he did not have any personal
    knowledge as to the parties entering into the written agreement.            Cerasi further
    acknowledged that he had no personal knowledge of Novak ever agreeing to the
    adjustments made to Novak’s invoices.
    {¶23} Following the bench trial, the trial court issued its findings of facts and
    conclusions of law, awarding judgment in favor of Novak on its breach of contract claim in
    the amount of $37,158.82 and on ServiceMaster’s counterclaims.           The court found,
    however, that ServiceMaster was not in violation of the Ohio Prompt Payment Act and
    awarded judgment in favor of ServiceMaster on this claim.
    {¶24} ServiceMaster appeals from this judgment, raising three assignments of error:
    I. The trial court erred in finding that the relationship between the
    parties was governed by an oral contract and not the written subcontractor
    agreement.
    II. The trial court erred in concluding that plaintiff met its burden of
    establishing an oral contract.
    III. Even if an oral contract was formed, the trial court erred by
    failing to determine the reasonable value of the services dating back to July
    15, 2007.
    {¶25}    Novak    has   filed    a   cross-appeal,   asserting   the   following   single
    cross-assignment of error:
    I. The trial court erred in denying Novak’s claim for relief against
    ServiceMaster pursuant to R.C. 4113.61 (Ohio’s Prompt Payment Act).
    {¶26} We turn first to ServiceMaster’s stated assignments of error.
    Standard of Review
    {¶27} In a civil case, “[j]udgments supported by some competent, credible evidence
    going to all the essential elements of the case will not be reversed by a reviewing court as
    being against the manifest weight of the evidence.” C.E. Morris Co. v. Foley Constr. Co.,
    
    54 Ohio St.2d 279
    , 
    376 N.E.2d 578
     (1978), syllabus.
    A reviewing court should not reverse a decision simply because it holds a
    different opinion concerning the credibility of the witnesses and evidence
    submitted before the trial court. A finding of an error in law is a legitimate
    ground for reversal, but a difference of opinion on credibility of witnesses
    and evidence is not.
    Seasons Coal Co., Inc. v. Cleveland, 
    10 Ohio St.3d 77
    , 81, 
    461 N.E.2d 1273
     (1984).
    Type of Contract
    {¶28} In its first assignment of error, ServiceMaster argues that the trial court erred
    in concluding that the parties’ relationship was governed by an oral contract and not the
    standard subcontractor agreement that ServiceMaster offered into evidence (hereby “the
    written agreement”).     ServiceMaster’s argument hinges on the following alleged facts: (1)
    Novak was presented with the written agreement drafted and signed by Edward Ranieri,
    president of ServiceMaster, at the inception of the project, namely, on or about July 15,
    2007; (2) Novak received the contract and understood its terms; and (3) Novak began
    performing the work contemplated in the written contract.      Although Novak never signed
    the contract, ServiceMaster contends that Novak’s performance under the contract
    constitutes an acceptance of the written contract, thereby binding Novak under the contract.
    {¶29} In support of this argument, ServiceMaster cites to several cases that hold a
    written contract that is not executed is enforceable if the parties proceed to act as if the
    contract is in effect.   Specifically, ServiceMaster relies on this court’s decision in Jatsek
    Constr. Co. v. Burton Scot Contrs., L.L.C., 8th Dist. Cuyahoga No. 98142,
    
    2012-Ohio-3966
    , and contends that it is controlling.
    {¶30} In Jatsek, the subcontractor filed suit seeking payment for services it provided
    on a construction project.     The general contractor, Burton Scot, faxed an agreement to
    Jatsek prior to the start of the project. Jatsek made some changes, signed it, and then
    returned a modified version of the agreement.       Burton Scot, however, never signed the
    agreement.    In response to Jatsek’s complaint, Burton Scot moved to stay the proceedings
    and compel arbitration based on an arbitration agreement contained in the agreement signed
    by Jatsek.   The trial court ruled that no contract existed for the project and consequently
    denied the motion to stay.   This court, however, reversed the trial court, finding an actual
    implied contract was formed between the parties upon the start of the work by Jatsek.
    Specifically, relying on G. Herschman Architects, Inc. v. Ringco Mfg. Co., Inc., 8th Dist.
    Cuyahoga No. 67758, 
    1995 Ohio App. LEXIS 1940
     (May 11, 1995), the court held that
    Jatsek’s subsequent performance constituted an acquiescence to the written agreement
    containing the arbitration clause.
    {¶31} We find Jatsek distinguishable. None of the parties in Jatsek asserted that an
    express oral contract governed their dispute.   Nor was the trial court weighing evidence to
    resolve disputed facts. In this case, Brad Pinchot, Novak’s vice president, testified that
    an express oral contract governed the parties’ relationship.    Specifically, he denied that
    there was a written contract.   According to Pinchot, the parties had a “time and material
    agreement” — a method of contracting common in the construction industry.
    {¶32} The evidence reveals that the written agreement was presented to Novak after
    Novak had already commenced work on the project.       Specifically, Pinchot testified that he
    received the written agreement by fax two to three weeks after Novak had commenced
    work on the project.    In Jatsek, the court’s holding was based on the reasoning of G.
    Herschman and the principle that a party’s commencement of the work may be sufficient
    evidence that the party has accepted the terms of the agreement — the critical point being
    that the party was presented with the agreement prior to commencement of the work.    This
    reasoning, therefore, does not apply in this case.
    {¶33} Further, Novak presented evidence at trial that ServiceMaster denied the
    existence of a written contract between the parties in its response to Novak’s request for
    admissions.    And while both parties changed their respective positions during the
    litigation, the trial court was free to find one party more credible than the other.
    Moreover, ServiceMaster never applied a 20 percent administrative fee to Novak’s invoices
    submitted with respect to Loss 1 — a key provision under the written agreement giving rise
    to ServiceMaster’s overpayment claim. The first time that ServiceMaster even alleged
    that it overpaid Novak was nearly a year after Novak filed its lawsuit and more than two
    years after it made its last payment to Novak.       Thus, ServiceMaster’s specific conduct
    belies its claim that the written agreement governed.
    {¶34} Accordingly, we find that the trial court was free to find that the parties
    entered an oral contract with respect to Loss 2 and that the written agreement signed by
    ServiceMaster’s president did not govern either Loss 1 or Loss 2.            Indeed, given
    ServiceMaster’s inconsistent actions with the terms of the written agreement, we find that
    the trial court’s finding that the written agreement does not govern is consistent with the
    weight of the evidence.
    {¶35} The first assignment of error is overruled.
    Proof of Oral Contract
    {¶36} In its second assignment of error, ServiceMaster argues that the trial court
    erred in concluding that Novak had met its burden of establishing an oral contract with
    respect to Loss 2.
    {¶37} “To succeed on a breach of contract claim, a party must prove the existence of
    a contract, that party’s performance under the contract, the opposing party’s breach, and
    resulting damage.”     Ruple v. Midwest Equip. Co., 8th Dist. Cuyahoga No. 95726,
    
    2011-Ohio-2923
    , ¶ 18.     To prove the existence of a contract, a plaintiff must show that
    both parties consented to the terms of the contract, that there was a “meeting of the minds”
    of both parties, and that the terms of the contract are definite and certain. 
    Id.,
     citing
    Nilavar v. Osborn, 
    137 Ohio App.3d 469
    , 
    738 N.E.2d 1271
     (2d Dist.2000); McSweeney v.
    Jackson, 
    117 Ohio App.3d 623
    , 631, 
    691 N.E.2d 303
     (4th Dist.1996).
    1.   Evidence of Offer and Acceptance
    {¶38} ServiceMaster contends that Novak failed to present evidence of an offer and
    acceptance of an oral contract, and therefore there was never a meeting of the minds
    between the parties.   We disagree.
    {¶39} Pinchot testified that he entered into an oral contract with Pete D’Agostino,
    who had the authority to contract on ServiceMaster’s behalf. Pinchot further testified that
    D’Agostino agreed to compensate Novak on a “time and material basis” and reimburse
    Novak for its expenses in exchange for Novak performing the required work.       The record
    further reveals that Novak completed the work and then submitted its final invoice,
    detailing its time and material on the job.   ServiceMaster never expressed any objection to
    the invoice and indicated that payment would be forthcoming upon its receipt of payment
    from the Cleveland Browns and the city of Cleveland. We find Pinchot’s testimony,
    coupled with the actions of the parties, provides competent, credible evidence to support
    the trial court’s finding that the parties entered into an oral contract with respect to Loss 2.
    2. Definite Terms
    {¶40} ServiceMaster also contends that the alleged oral contract was lacking any
    definite terms to be enforceable.   We disagree.
    {¶41} The record contains sufficient evidence of definite terms to enforce the oral
    contract. The record reveals that Novak is a union shop with published union rates.
    Pinchot explained at trial that price terms in a time and material contract are calculated by
    adding hours worked at the published union rate to the cost of materials plus 10 percent.
    According to Pinchot, this method of pricing is understood in the construction industry,
    “including people from ServiceMaster.” Pinchot further testified that Novak has done
    work for ServiceMaster in the past and that ServiceMaster understood Novak’s rates.
    Based on this competent, credible evidence, we find that Novak met its burden to establish
    an oral contract with respect to Loss 2.
    3. Trial Court’s Stated Reasoning
    {¶42} ServiceMaster also argues that the trial court’s reasoning supporting the basis
    for an oral contract is inconsistent and chronologically impossible. Pointing to the trial
    court’s finding that Pinchot’s testimony was the only probative evidence of contract
    formation, ServiceMaster argues that the trial court relied on Pinchot’s testimony to
    conclude that ServiceMaster orally contracted with Novak to perform work in response to
    the August 2, 2007 damage.     The trial court later concludes that the “parties’ relationship
    with regards to the entire Cleveland Browns Stadium restoration project (Loss 1 and Loss
    2) was governed by an oral contract.”      ServiceMaster argues that it is chronologically
    impossible that a single contract formed in response to the damage of August 2, 2007 (Loss
    2) could also govern the formation of a contract for the earlier July 14, 2007 event (Loss 1).
    {¶43} We find ServiceMaster’s argument misplaced and no basis for reversal.        The
    trial court’s finding regarding contract formation specifically related to the oral contract
    governing Loss 2. Indeed, Novak’s case was based solely on recovering for Loss 2, and
    therefore focused its presentation of the evidence on the contract formation for Loss 2.
    With respect to Loss 1, the trial court found that ServiceMaster failed to meet its burden
    that a breach of contract occurred under a written agreement.       Based on our discussion
    above, the record supports the trial court’s finding in favor of Novak on ServiceMaster’s
    counterclaim.   Thus, while the trial court also found that an oral contact governed Loss 1,
    the critical point is that it did not find that the written agreement governed Loss 1, thereby
    supporting its judgment in favor of Novak on ServiceMaster’s counterclaim.
    {¶44} The second assignment of error is overruled.
    Value of Novak’s Services
    {¶45} In its third assignment of error, ServiceMaster argues that the trial court erred
    in failing to determine the reasonable value of Novak’s services.              According to
    ServiceMaster, even assuming the written agreement did not govern and that an oral
    contract was formed, the trial court was required to determine the reasonable value of
    Novak’s services for both Loss 1 and Loss 2.
    {¶46} In support of this argument, ServiceMaster relies on the testimony of Gregory
    Zeigler, who was the insurance adjustor for Affiliated FM Global handling the two
    insurance claims submitted with respect to Loss 1 and Loss 2. Zeigler testified as to the
    amount of money approved with respect to Loss 1 and Loss 2, indicating that the insurance
    company made downward adjustments to the rates submitted by Novak for several reasons.
    He explained that the adjustments “could be because they aren’t covered under the policy;
    it might not be loss related, or we might not based on disagreement over the rates or hours
    they were on site.”   Specifically, ServiceMaster contends that the amount approved by
    Affiliated FM Global, namely, $377,855.85 on Loss 1 and $31,617.28 on Loss 2, is the
    only evidence of the reasonable value of the Novak’s services and the amount that Novak
    should have been paid.      ServiceMaster further points to the testimony of its own
    accountant, Gary Cerasi, who indicated that Novak should have only been paid the amount
    approved by Affiliated FM Global.
    {¶47} This argument, however, ignores that the trial court awarded Novak the
    amount submitted on Novak’s Loss 2 final invoice, which contained line item charges for
    the time and materials that Novak furnished in response to Loss 2, totaling $37,158.82.
    Novak proved by a preponderance of the evidence that, under the terms of the oral contract
    for Loss 2, ServiceMaster agreed to pay Novak on a time and material basis.       Notably,
    ServiceMaster never objected to the charges contained in Novak’s final Loss 2 invoice
    prior to the lawsuit. Instead, ServiceMaster excused its nonpayment on the basis that it
    had not been paid in full by the property owner.
    {¶48} There is no evidence that Novak agreed to perform the work in exchange for
    the amount approved by the insurance company.             Moreover, Affiliated FM Global’s
    property damage summary, detailing downward adjustments to Novak’s invoices, does not
    reflect a determination of the “reasonable value” of Novak’s work.     Instead, the summary
    simply addresses those portions of Novak’s work covered under the policy of insurance.
    As stated by Zeigler, “we really don’t review the work.    We review the insurance contracts
    and decide what’s recoverable.”       This testimony directly contradicts ServiceMaster’s
    accountant’s testimony that the reasonable value of services is based on the amount
    approved by the insurance company.
    {¶49} Accordingly, we find that the trial court properly awarded Novak $37,158.82
    on its breach of contract claim for Loss 2.
    {¶50} Additionally, we find no merit to ServiceMaster’s claim that the trial court
    failed to consider the reasonable value of Novak’s services with respect to Loss 1 in
    resolving the counterclaim.    ServiceMaster’s counterclaim for breach of contract hinged
    on its assertion that the written agreement governed both Loss 1 and Loss 2 and, therefore,
    based on the “pay when paid” provision and the 20 percent administrative fee provision, it
    had overpaid Novak.     Given that the trial court found that the written agreement did not
    govern Loss 1 and Loss 2, either individually or collectively, the trial court properly
    concluded that there was no merit to ServiceMaster’s overpayment claim and resolved the
    counterclaim in Novak’s favor.
    {¶51} We further find that ServiceMaster failed to meet its burden of proof that the
    amount it paid to Novak exceeded the reasonable value of the services provided.        Again,
    the thrust of ServiceMaster’s argument is based on the amount approved by Affiliated FM
    Global for the claim submitted with respect to Loss 1. As discussed above, this testimony
    is not persuasive proof of the reasonable value of Novak’s services. Moreover, we find no
    basis to attribute the Cleveland Browns’ payment toward Novak’s Loss 1 invoices as
    grounds to support an unjust enrichment claim on ServiceMaster’s behalf.
    {¶52} The third assignment of error is overruled.
    Prompt Payment Statute
    {¶53} Novak argues in its sole cross-assignment of error that the trial court’s refusal
    to award it damages under R.C. 4113.61 is against the manifest weight of the evidence and
    contrary to law.
    {¶54} The statute provides in relevant part:
    (A)(1) If a subcontractor * * * submits * * * an invoice for materials to a
    contractor in sufficient time to allow the contractor to include the * * *
    invoice in the contractor’s own pay request submitted to an owner, the
    contractor, within ten calendar days after receipt of payment from the owner
    for improvements to property, shall pay to the:
    (a) Subcontractor, an amount that is equal to the percentage of completion of
    the subcontractor’s contract allowed by the owner for the amount of labor or
    work performed;
    ***
    The contractor may reduce the amount paid by any retainage provision
    contained in the contract, invoice, or purchase order between the contractor
    and the subcontractor * * *, and may withhold amounts that may be necessary
    to resolve disputed liens or claims involving the work or labor performed or
    material furnished by the subcontractor * * *.
    If the contractor fails to comply with division (A)(1) of this section, the
    contractor shall pay the subcontractor * * *, in addition to the payment due,
    interest in the amount of eighteen per cent per annum of the payment due,
    beginning on the eleventh day following the receipt of payment from the
    owner and ending on the date of full payment of the payment due plus interest
    to the subcontractor * * *.
    R.C. 4113.61(A)(1).
    {¶55} Therefore, pursuant to R.C. 4113.61(A)(1), if a subcontractor makes a timely
    request for payment, a contractor must pay the subcontractor in proportion to the work
    completed within ten calendar days of receiving payment from the owner. Masiongale
    Elec.-Mechanical, Inc. v. Constr. One, Inc., 
    102 Ohio St.3d 1
    , 
    2004-Ohio-1748
    , 
    806 N.E.2d 148
    , ¶ 16.   A contractor, however, is permitted to withhold “amounts that may be necessary
    to resolve disputed liens or claims involving the work or labor performed or material
    furnished by the subcontractor.” 
    Id.,
     quoting R.C. 4113.61(A).
    {¶56} Failure to comply with these provisions obligates a contractor to pay interest
    on the overdue payment at a rate of 18 percent per annum.         R.C. 4113.61(A)(1) and
    (B)(1).     A subcontractor also may file a civil action to recover the amount due and the
    statutory interest. R.C. 4113.61(B)(1). If the court determines that the contractor has not
    complied with the prompt-payment statute, the court must award the subcontractor the
    statutorily prescribed interest.   Masiongale Elec.-Mechanical, Inc. at ¶ 17.
    {¶57} Novak argues that the record overwhelmingly establishes a violation of R.C.
    4113.61. Specifically, Novak relies on the following factual findings by the trial court:
    · The insurance company approved total payments of the Loss 2
    subcontractors’ invoices in the amount of $235,460.82. Affiliated FM
    specifically earmarked $31,617.28 of the $235,460.82 to pay Novak’s final
    invoice.
    · According to their own records, ServiceMaster received $200,000.00
    in the form of two $100,000.00 checks on January 9, 2008.
    · The final check paid to Novak by ServiceMaster in the amount of
    $75,000.00 was issued on December 28, 2007.
    · Defendant’s internal records establish that as of February 12, 2008,
    the entire balance associated with Loss 2 was not paid by ServiceMaster.
    {¶58} Based on these findings, which are supported by competent, credible evidence
    in the record, we find that there is a violation of Ohio’s Prompt Payment Act. The trial
    court’s verdict to the contrary is against the manifest weight of the evidence.      Indeed, the
    record reveals that ServiceMaster never paid Novak on the Loss 2 contract, despite having
    received a partial payment of $31,617.28 that was specifically designated for Novak’s Loss
    2 invoice, and despite there being no objection to the invoice or dispute over Novak’s
    services.     The statute prohibits and penalizes this exact conduct.
    {¶59} The trial court’s finding that ServiceMaster’s payment of $75,000 issued on
    December 28, 2007, was a prepayment of the $31,617.28 that ServiceMaster received on
    the Loss 2 claim is not supported by the evidence. At the time the $75,000 payment was
    received, Novak had open invoices for Loss 1 and Loss 2. Pinchot testified that the
    $75,000 payment was applied toward Loss 1 invoices — the oldest outstanding invoices.
    ServiceMaster’s own internal bookkeeping records confirm that the $75,000 payment was
    made toward Loss 1 invoices.       For this same reason, we cannot say that Ranieri’s
    testimony that ServiceMaster’s payment of $75,000 was for Loss 2 is credible; his
    testimony directly contradicts ServiceMaster’s business records.   Notably, even after the
    $75,000 payment, an outstanding balance of $54,297.01 remained on Novak’s Loss 1
    invoices — this amount, however, was settled through the agreement negotiated directly
    with the Cleveland Browns.
    {¶60} ServiceMaster counters that the trial court’s decision should stand based on
    the evidence that the $75,000 payment was made within ten days of ServiceMaster’s receipt
    of the two checks it received from the owner and owner’s agent to cover Loss 2 invoices.
    The record reveals, however, that these two checks were documented as received by
    ServiceMaster on January 9, 2008.    ServiceMaster’s bookkeeping records also show, as
    the trial court found, that as of February 12, 2008, the entire amount of Novak’s Loss 2
    invoice remained unpaid.
    {¶61} In finding that the statute was not violated, the trial court improperly focused
    on the total payments made under Loss 1 and the insurance company’s approval of less than
    what ServiceMaster actually paid Novak on Loss 1. But we cannot ignore that Loss 2
    constituted a separate agreement and, therefore, the trial court should have focused solely
    on ServiceMaster’s conduct with respect to Loss 2.
    {¶62} Because the record reveals that ServiceMaster did not make any payment to
    Novak with respect to Loss 2, nor did it ever dispute the invoice prior to Novak’s
    commencement of the lawsuit, we fail to see how ServiceMaster escapes application of
    Ohio’s Prompt Payment Act. This is not a situation where the contractor, in good faith,
    withholds amounts when there is a disputed claim. See Consortium Communications v.
    Cleveland Telecommunications, Inc., 10th Dist. Franklin No. 97APG08-1090, 
    1998 Ohio App. LEXIS 524
     (Feb. 10, 1998). Here, Novak is entitled to prejudgment interest because
    ServiceMaster did not assert a good faith basis to withhold the money.           See Gary
    Moderalli Excavating, Inc. v. Trimat Constr., Inc., 5th Dist. Tuscarawas Nos.
    2012AP030022 and 2012AP030023, 
    2013-Ohio-1701
    , ¶ 49 (“if the contractor does not
    assert a good faith basis to withhold the money, then the subcontractor is entitled to
    prejudgment interest”).
    {¶63} But although Novak is entitled to prejudgment interest, the award of attorney
    fees is not automatic. In fact, R.C. 4113.61(B)(3) states that the court shall not award
    attorney fees if the court determines, following a hearing on the payment of attorney fees,
    that such an award would be inequitable.        And while ServiceMaster has presented
    compelling reasons as to why the application of the attorney fees would be inequitable, this
    determination lies within the sound discretion of the trial court. We therefore remand on
    this issue for the trial court to consider.
    {¶64} In summary, ServiceMaster’s three assignments of error are overruled, and the
    judgment is affirmed awarding Novak damages on its breach of contract claim. Novak’s
    sole cross-assignment of error is sustained, thereby entitling it to prejudgment interest as set
    forth in R.C. 4113.61(A)(1), but the issue of attorney fees must be remanded for the trial
    court to consider.
    {¶65} Judgment affirmed in part, reversed in part, and remanded to the lower court
    for further proceedings consistent with this opinion.
    It is ordered that appellee recover from appellant the costs herein taxed.
    The court finds there were reasonable grounds for this appeal.
    It is ordered that a special mandate issue out of this court directing the common
    pleas court to carry this judgment into execution.
    A certified copy of this entry shall constitute the mandate pursuant to Rule 27 of the
    Rules of Appellate Procedure.
    MARY J. BOYLE, ADMINISTRATIVE JUDGE
    EILEEN A. GALLAGHER, J., and
    PATRICIA ANN BLACKMON, J., CONCUR