J. Bowers Constr. Co., Inc. v. Gilbert , 2014 Ohio 3576 ( 2014 )


Menu:
  • [Cite as J. Bowers Constr. Co., Inc. v. Gilbert, 
    2014-Ohio-3576
    .]
    STATE OF OHIO                     )                          IN THE COURT OF APPEALS
    )ss:                       NINTH JUDICIAL DISTRICT
    COUNTY OF SUMMIT                  )
    J. BOWERS CONSTRUCTION CO., INC.                             C.A. No.   27044
    Appellee
    v.                                                   APPEAL FROM JUDGMENT
    ENTERED IN THE
    EDWARD L. GILBERT, et al.                                    COURT OF COMMON PLEAS
    COUNTY OF SUMMIT, OHIO
    Appellants                                           CASE No.   CV 2011 08 4841
    DECISION AND JOURNAL ENTRY
    Dated: August 20, 2014
    WHITMORE, Judge.
    {¶1}     Defendant-Appellants, Edward and Delphenia Gilbert (collectively, “the
    Gilberts”), appeal from the judgment of the Summit County Court of Common Pleas. This Court
    affirms.
    I
    {¶2}     In August 2009, the Gilberts received a call from their home security company
    notifying them that an alarm had been activated. When the Gilberts arrived home, the police and
    fire department were already on scene. The Gilberts discovered their home was flooded from a
    burst water pipe in an upstairs room. Someone from the fire department recommended J.
    Bowers Construction Company, Inc. (“Bowers”) to do emergency repairs.
    {¶3}     Bowers was contacted and sent an agent to the Gilberts’ that same day. Edward
    Gilbert signed an authorization form for the emergency repairs and Bowers began work
    immediately. The Gilberts had a home insurance policy with Travelers Insurance, and Travelers
    2
    provided a written estimate for the repairs. At some point, it was determined that Bowers would
    also do the necessary repairs to the home after the emergency repairs were completed. However,
    the Gilberts did not sign any additional documentation.
    {¶4}    Over the next year-and-a-half, Bowers worked with the Gilberts and Travelers to
    complete the repairs. During this process, the Gilberts chose not to repair certain things that
    were covered by their insurance policy and to upgrade things that were not covered. While the
    repairs were being made, Travelers issued partial payments to the Gilberts, and the Gilberts made
    $65,000 in payments to Bowers. In February 2011, Travelers issued a final estimate totaling
    $132,451.98. Bowers and Edward Gilbert met on March 2, 2011, and reviewed various credits
    and charges for upgrades. Gilbert tendered a check for $6,624.89, and, it appears, both parties
    believed the remaining balance of $67,451.98 would be paid by Travelers.
    {¶5}    In August 2011, having received no additional payments, Bowers filed a claim for
    breach of contract and quantum meruit. The Gilberts counterclaimed alleging fraud, damage to
    the property by the construction workers, and the use of substandard materials. After a bench
    trial, the court entered a judgment in favor of Bowers for $67,451.98. The Gilberts now appeal
    and raise seven assignments of error for our review.
    II
    Assignment of Error Number One
    THE TRIAL COURT ERRED WHEN IT RULED THAT J. BOWERS WAS
    ENTITLED TO JUDGMENT BASED ON QUANTUM MERUIT WHEN IT
    ALREADY DETERMINED THAT THERE WAS AN EXPRESS CONTRACT.
    {¶6}    In their first assignment of error, the Gilberts argue that the court erred by
    awarding judgment in favor of Bowers under the theory of quantum meruit because the court
    found that there was an express contract between the parties.
    3
    {¶7}    The Gilberts’ first assignment of error raises a question of law, which this Court
    reviews de novo. See Fuline v. Green, 9th Dist. Summit No. 26586, 
    2013-Ohio-2171
    , ¶ 6. In
    conducting a de novo review, an appellate court does not give deference to the trial court’s
    determination. Akron v. Frazier, 
    142 Ohio App.3d 718
    , 721 (9th Dist.2001).
    {¶8}    “A contract is generally defined as a promise, or a set of promises, actionable
    upon breach. Essential elements of a contract include an offer, acceptance, contractual capacity,
    consideration (the bargained for legal benefit and/or detriment), a manifestation of mutual assent
    and legality of object and of consideration.” Kostelnik v. Helper, 
    96 Ohio St.3d 1
    , 2002-Ohio-
    2985, ¶ 16, quoting Perlmuter Printing Co. v. Strome, Inc., 
    436 F.Supp. 409
    , 414 (N.D.Ohio
    1976). There is no valid contract where the parties have not had a meeting of the minds as to the
    essential terms. See Minster Farmers Coop. Exchange Co., Inc. v. Meyer, 
    117 Ohio St.3d 459
    ,
    
    2008-Ohio-1259
    , ¶ 28.
    {¶9}    In the absence of a valid contract, a party may still recover under a quasi-contract
    theory. “Recovery in quasi-contract prevents the defendant from unjustly enriching himself at
    the expense of the plaintiff.” Bokar v. Lax, 9th Dist. Medina No. 2630-M, 
    1997 WL 557333
    , *2
    (Sept. 3, 1997), citing Hughes v. Oberholtzer, 
    162 Ohio St.3d 330
    , 335 (1954). An example of a
    quasi-contract claim is quantum meruit. See Hammontree & Associates, Ltd. v. Stephens, 9th
    Dist. Wayne No. 2222, 
    1987 WL 15106
    , *2 (July 29, 1987).
    {¶10} Quantum meruit is an equitable remedy giving “rise to obligations imposed by
    law, irrespective of the intentions of the parties, in order to prevent an injustice when one party
    retains a benefit from another’s labors.” (Internal quotations and citations omitted.) In re
    Suchodolski, 9th Dist. Lorain No. 10CA009833, 
    2011-Ohio-6333
    , ¶ 8, quoting In re Estate of
    Kirkland, 
    175 Ohio App.3d 73
    , 
    2008-Ohio-421
    , ¶ 23 (2d Dist.). “Quantum meruit is generally
    4
    awarded when one party confers some benefit upon another without receiving just compensation
    for the reasonable value of services rendered.” (Emphasis sic.)           Aultman Hosp. Assn. v.
    Community Mut. Ins. Co., 
    46 Ohio St.3d 51
    , 55 (1989). To prevail on a claim of quantum
    meruit, a plaintiff is required to show “(1) a benefit has been conferred by [the] plaintiff upon
    [the] defendant; (2) the defendant had knowledge of the benefit; and (3) the defendant retained
    the benefit under circumstances where it would be unjust to do so without payment.” In re
    Suchodolski at ¶ 8, quoting Bldg. Industry Consultants, Inc. v. 3M Parkway, Inc., 
    182 Ohio App.3d 39
    , 
    2009-Ohio-1910
    , ¶ 16 (9th Dist.).
    {¶11} Because a quasi-contract claim only exists when there is no valid contract, “a
    party cannot claim that both an express contract and a quasi-contract exist over the same subject
    matter.” (Emphasis omitted.) Champion Contracting Const. Co., Inc. v. Valley City Post No.
    5563, 9th Dist. Medina No. 03CA0092-M, 
    2004-Ohio-3406
    , ¶ 25. “While it is true that a party
    may not recover for the same services under both a contractual claim and a claim for quantum
    meruit, a party is not barred from seeking alternative theories and recovering under a quantum
    meruit theory if his contractual claim fails.” Bldg. Industry Consultants, Inc. at ¶ 17.
    {¶12} On September 12, 2009, the Gilberts received a call from their security company
    that an alarm had been activated at their home. When the Gilberts arrived at their house, the
    police and fire department were already there. The Gilberts opened the door and discovered that
    their house was flooded from a burst water pipe. According to Edward Gilbert’s testimony,
    someone from the fire department recommended Bowers to come out and perform emergency
    repairs. There is some dispute about who actually contacted Bowers.             In any event, it is
    undisputed that a representative of Bowers went to the Gilberts’ home that same day, and
    5
    Edward Gilbert signed a document entitled “Access & Authorization for Emergency &
    Temporary Repairs.” This authorization form provided:
    I hereby give access and authorization to J. Bowers Construction Inc. for the
    purpose of making necessary temporary emergency repairs to the above address
    as a result of 9-12-09, date of loss 9-12-09. It is my understanding that the
    services performed by J. Bowers Construction Inc. will be limited to those which
    are authorized by owner/agent or by my/our insurance company, unless other
    arrangements for payment are agreed upon in writing in advance. All charges will
    be based on time and material. All labor costs are charged portal to portal.
    {¶13} Stephen Hayes, Bowers’ project manager, testified that this authorization form
    “g[a]ve [Bowers] permission to come into the home to do – dry-out mitigation.”            Hayes
    explained that the emergency services performed at the Gilberts’ home involved “[w]ater
    extraction, demolition, [and] dry-out.” Hayes further testified that these “emergency services”
    did not involve the repairs to the home. According to Hayes, the emergency work, totaling
    approximately $9,000, was completed and paid for.
    {¶14} Hayes testified that after the emergency repairs were complete, a request was
    made for Bowers to perform repairs to the home. However, no contract for repairs was ever
    drafted, and the Gilberts never signed any additional documentation. Over the next couple of
    years, Hayes managed the repairs to the Gilberts’ home. In doing so, Hayes worked closely with
    the Gilberts and the Gilberts’ insurance company, Travelers. Throughout the project Travelers
    provided numerous estimates, at least some of which were shared with the Gilberts. The Gilberts
    made decisions not to repair certain things that were covered under their insurance policy and
    also to perform certain upgrades that were not covered.
    {¶15} The trial court found that “Mr. Gilbert entered into a contract with Bowers to
    perform remedial work on the Gilbert home; that the contract was orally modified to include
    upgrades to the kitchen countertops and the carpeting[.]” A review of the record supports the
    6
    finding that Edward Gilbert entered into contract for “necessary temporary emergency repairs.”
    However, the record does not support a finding that a contract existed for the subsequent repairs
    of the home. Hayes himself testified that the emergency services were separate and apart from
    the repairs to the home.
    {¶16} While we conclude that the trial court erred in finding a valid contract for non-
    emergency repairs existed, we also conclude that this error is not reversible under the facts of
    this case. If an error is not prejudicial, an appellate court shall affirm the judgment of the trial
    court. See Cook Family Invests. v. Billings, 9th Dist. Lorain Nos. 05CA008689 & 05CA008691,
    
    2006-Ohio-764
    , ¶ 19.
    {¶17} The court ultimately found that “the Gilberts accepted the work performed and
    materials provided and [that] Bowers [wa]s entitled to a judgment based on quantum meruit.”
    After a careful review of the record, we agree. The record shows that Edward Gilbert was very
    involved in selecting which repairs to make to the home. Further, Gilbert was corresponding
    with Travelers and Hayes throughout the project about the insurance estimates and what was and
    was not covered. Because we conclude that the court correctly determined that Bowers was
    entitled to a judgment against the Gilberts based on a theory of quantum merit, the court’s
    erroneous finding of a repair contract is not prejudicial.
    {¶18} The Gilberts’ first assignment of error is overruled.
    Assignment of Error Number Two
    THE TRIAL COURT ERRED WHEN IT RULED THAT J. BOWERS WAS
    ENTITLED TO A JUDGMENT BASED ON QUANTUM MERUIT,
    ALTHOUGH J. BOWERS DID NOT PROVIDE SUFFICIENT EVIDENCE OF
    THE VALUE OF THE SERVICES RENDERED.
    7
    {¶19} In their second assignment of error, the Gilberts argue that Bowers failed to
    provide sufficient evidence of the “reasonable value of the materials and services rendered.” We
    disagree.
    {¶20} “In civil cases, as in criminal cases, the sufficiency of the evidence is
    quantitatively and qualitatively different from the weight of the evidence.” Eastley v. Volkman,
    
    132 Ohio St.3d 328
    , 
    2012-Ohio-2179
    , paragraph two of the syllabus. “‘[S]ufficiency’ is a term
    of art meaning that legal standard which is applied to determine * * * whether evidence is legally
    sufficient to support [a finding] as a matter of law.” (Alterations sic.) Raykov v. Raykov, 9th
    Dist. Summit No. 26107, 
    2012-Ohio-2611
    , ¶ 8, quoting State v. Thompkins, 
    78 Ohio St.3d 380
    ,
    386 (1997). Sufficiency challenges the burden of production and is a test of adequacy. Eastley
    at ¶ 11, quoting Thompkins at 386.
    {¶21} “Whether the evidence is legally sufficient to sustain a verdict is a question of
    law.” 
    Id.
     This Court reviews questions of law de novo. See Gugliotta v. Morano, 
    161 Ohio App.3d 152
    , 
    2005-Ohio-2570
    , ¶ 56 (9th Dist.). In conducting a de novo review, this Court gives
    no deference to the trial court’s legal conclusions. Lanning v. Stanford-Black, 9th Dist. Lorain
    No. 09CA009561, 
    2009-Ohio-6022
    , ¶ 8. However, this Court will not reverse a trial court’s
    factual finding if it is supported by competent, credible evidence. Maxwell v. Maxwell, 9th Dist.
    Wayne No. 07CA0047, 
    2008-Ohio-1324
    , ¶ 6.
    {¶22} “The standard for review of the sufficiency of the evidence in a civil case is
    similar to the standard for determining whether to sustain a motion for judgment notwithstanding
    the verdict, which is whether the defendant is entitled to judgment as a matter of law when the
    evidence is construed most strongly in favor of the prevailing party.” Warden v. Ohio Dept. of
    Natural Resources, 10th Dist. Franklin No. 13AP-137, 
    2014-Ohio-35
    , ¶ 46, quoting In re J.B.,
    8
    10th Dist. Franklin Nos. 08AP-1108, 09AP-39, 08AP-1109 & 08AP-1122, 
    2009-Ohio-3083
    , ¶
    20.
    {¶23} “To prove its claim [of quantum meruit], Bowers had to show that it conferred a
    benefit on the [Gilberts], that they had knowledge of the benefit, and that they retained the
    benefit under circumstances in which it would be unjust for them to do so without payment.”
    Bowers Constr. Co., Inc. v. Chuparkoff, 9th Dist. Summit No. 24775, 
    2010-Ohio-419
    , ¶ 10.
    Bowers also had to prove the reasonable value of the benefit conferred. 
    Id.,
     citing Stoebermann
    v. Beacon Journal Publishing Co., 
    177 Ohio App.3d 360
    , 
    2008-Ohio-3769
    , ¶ 29 (9th Dist.).
    {¶24} The Gilberts argue that Bowers failed to provide sufficient evidence of the
    reasonable value of the materials and services rendered.          Therefore, we limit our review
    accordingly.
    {¶25} Stephen Hayes is an estimator with Bowers and served as the project manager for
    the repairs to the Gilberts’ home. According to Hayes, Bowers specializes in insurance work.
    Hayes testified that he has thirteen years of experience in writing estimates and currently writes
    between 100 to 150 estimates a year. Hayes explained that if an insurance company is involved
    in a case from the beginning, the insurance company will typically write the estimate.
    {¶26} Hayes testified that Bowers uses “Xactimate” when writing estimates. Hayes
    stated that Xactimate is a software program that calculates the average cost of a repair based on
    the county and the square footage. Hayes explained, “[i]f a wall needs to be torn out, you put in
    that square footage of the wall and it calculates the pricing.” Hayes testified that the pricing used
    by Xactimate is “somewhere in the middle of the pricing of the area” and is “basically an
    industry standard.” Hayes further testified that most insurance companies write estimates in
    Xactimate, but even those that do not “at least recognize what it is.”
    9
    {¶27} According to Hayes, an estimate is often modified throughout the project. For
    example, it is common to have a situation where a homeowner does not want to make certain
    repairs that are covered by the insurance policy and, at the same time, wants to make certain
    upgrades that are not covered. In those circumstances, Hayes explained, “we’ll take what is in
    the estimate and we’ll move things around to accommodate everybody.” In doing so, the
    homeowner receives a credit for the work that is not done, which is then applied toward the cost
    of any upgrade.
    {¶28} Hayes testified that the Gilberts had an insurance policy through Travelers and
    that Travelers wrote the estimate for the repairs to the Gilberts’ home. Hayes further testified
    that Travelers uses Xactimate in writing estimates. Travelers, working with the Gilberts and
    Hayes, revised its estimate numerous times throughout the year-and-a-half project. In February
    2011, the final estimate from Travelers was forty pages long and totaled $132,451.98. Hayes
    testified that he went “through the estimate line by line by line” with Gilbert. As a result, Hayes
    produced a typed, itemized list of credits, detailing the corresponding page and line number in
    the estimate for which the credit was given. Additionally, the page contained a list of the various
    charges for upgrades.
    {¶29} On March 2, 2011, Hayes and Gilbert met to review the itemized list of credits
    and upgrade charges. According to Hayes, he agreed to two additional credits, handwrote them
    on the sheet, and calculated the balance due. Hayes wrote on the sheet that the insurance
    company owed $67,451.98, leaving a balance of $6,624.89. Gilbert immediately tendered a
    check for $6,624.89 and signed the itemized list of credits and charges. Hayes testified that
    because he had only received $65,000 from the Gilberts, he believed Travelers still owed
    $67,451.98 to bring the total disbursement amount to the final estimate of $132,451.98.
    10
    {¶30} After a review of the record, we conclude Bowers provided sufficient evidence of
    the reasonable cost of materials and services rendered. Bowers used Travelers’ written estimate
    created through Xactimate. Hayes testified that the Xactimate software produces a mid-range
    cost of repairs based on the county and square footage. Moreover, Hayes testified that Gilbert
    agreed to the credits and upgrade charges on the itemized sheet when he signed the sheet and
    tendered a check for the out-of-pocket expenses.
    {¶31} The Gilberts’ second assignment of error is overruled.
    Assignment of Error Number Three
    THE TRIAL COURT ERRED WHEN IT RULED THAT J. BOWERS WAS
    ENTITLED TO A JUDGMENT BASED ON QUANTUM MERUIT AGAINST
    EDWARD GILBERT BECAUSE HE IS NOT THE OWNER OF THE
    RESIDENCE.
    {¶32} In the third assignment of error, Edward Gilbert argues that the court erred in
    entering a judgment against him because Bowers “did not prove that it conferred a benefit upon
    Edward Gilbert because he is not the owner of the property.” We disagree.
    {¶33} To prevail on a claim of quantum meruit, a plaintiff is required to show “(1) a
    benefit has been conferred by [the] plaintiff upon [the] defendant; (2) the defendant had
    knowledge of the benefit; and (3) the defendant retained the benefit under circumstances where it
    would be unjust to do so without payment.” In re Suchodolski, 
    2011-Ohio-6333
    , at ¶ 8, quoting
    Bldg. Industry Consultants, Inc., 
    182 Ohio App.3d 39
    , 
    2009-Ohio-1910
    , at ¶ 16. Quantum
    meruit is intended to prevent “the defendant from unjustly enriching himself at the expense of
    the plaintiff.” Bokar, 
    1997 WL 557333
    , at *2.
    {¶34} Knowing he was not the legal owner of the property, Gilbert signed the
    emergency repair authorization. Additionally, he continued to work with Travelers and Hayes
    for almost two years to repair the property and settle the related bills. Gilbert never informed
    11
    anyone involved that he did not legally own the property. While the property at issue is titled
    solely in his wife’s name, there is no dispute that Edward Gilbert lives in the home with his wife.
    Gilbert’s argument that he received no benefit from the repair of his primary residence simply
    because he is not the person named on the deed is without merit.
    {¶35} The Gilberts’ third assignment of error is overruled.
    Assignment of Error Number Four
    THE TRIAL COURT ERRED WHEN IT FOUND THAT THERE WAS A
    BINDING CONTRACT BETWEEN J. BOWERS AND EDWARD GILBERT,
    ALTHOUGH J. BOWERS FAILED TO PROVIDE THE REQUIRED THREE-
    DAY CANCELLATION NOTICE.
    {¶36} In their fourth assignment of error, the Gilberts argue that the trial court erred in
    enforcing the contract between the Gilberts and Bowers because the contract failed to provide the
    statutorily required three-day cancellation notice.
    {¶37} “A failure to provide a cancellation notice in a transaction covered by [The Home
    Solicitation Act] constitutes a violation of the [Consumer Sales Practices Act] under R.C.
    1345.02.” Garber v. STS Concrete Co., L.L.C., 8th Dist. Cuyahoga No. 99139, 
    2013-Ohio-2700
    ,
    ¶ 19. Where there is a violation of R.C. 1345.02, “the consumer may, in an individual action,
    rescind the transaction or recover the consumer’s actual damages * * *.” R.C. 1345.09(A). “The
    Home Solicitation Act is designed to provide a consumer with a weapon against high pressure
    sales tactics occurring in the home.” Carpet One Mentor, Inc. v. Bridge, 11th Dist. Lake No.
    2006-L-005, 
    2007-Ohio-3028
    , ¶ 62.
    {¶38} In their counterclaim, the Gilberts requested damages based on fraud, damage
    done to the property by the construction workers, and the use of substandard materials. The
    Gilberts did not allege a violation of the Home Solicitation Act based on Bowers’ failure to
    12
    provide a three-day cancellation notice.      Because the Gilberts did not properly plead this
    statutory violation, the court did not err in failing to award damages.
    {¶39} To the extent that the Gilberts argue that the court erred in enforcing the contract
    because Bowers did not provide the three-day cancellation notice, we find this argument moot
    because the judgment is affirmed base on quantum meruit, not on the enforcement of a contract.
    {¶40} The Gilberts’ fourth assignment of error is overruled.
    Assignment of Error Number Five
    THE TRIAL COURT ERRED WHEN IT FAILED TO RULE THAT EDWARD
    GILBERT COULD RESCIND THE CONTRACT.
    {¶41} In their fifth assignment of error, the Gilberts argue that the court erred in finding
    that they were not able to rescind the contract with Bowers.
    {¶42} Where there is a violation of the Consumer Sales Practices Act, “the consumer
    may, in an individual action, rescind the transaction or recover the consumer’s actual damages *
    * *.” R.C. 1345.09(A). However, “in any action for rescission, revocation of the consumer
    transaction must occur within a reasonable time * * * and before any substantial change in
    condition of the subject of the consumer transaction.” R.C. 1345.09(C).
    {¶43} The Gilberts argue that the court erred in not permitting them to rescind their
    contract with Bowers. However, as discussed above, the Gilberts did not have a contract with
    Bowers to repair the home. Therefore, there was no contract to rescind. Moreover, there is no
    evidence in the record that the Gilberts ever sought to rescind the contract in the trial court. In
    their counterclaim, the Gilberts requested damages based on fraud, damage done to the property
    by the construction workers, and the use of substandard materials.
    {¶44} Assuming arguendo that the Gilberts had requested to rescind the transaction, the
    statute requires that the buyer seek rescission prior to a “substantial change in condition.” See
    13
    R.C. 1345.09(C). Accord Garber, 
    2013-Ohio-2700
    , at ¶ 20, quoting Reichert v. Ingersoll, 
    18 Ohio St.3d 220
    , 224 (1985) (“rescission is not an appropriate remedy under the [Consumer Sales
    Practices Act] where ‘there has been a substantial change in the subject of the consumer
    transaction.’”). Here, Bowers had completed extensive repairs to the Gilberts’ home. Even if
    the Gilberts had sought to rescind the transaction, we conclude that rescission would not be
    appropriate because a substantial change in condition had already occurred.                See R.C.
    1345.09(C).
    {¶45} The Gilberts’ fifth assignment of error is overruled.
    Assignment of Error Number Six
    THE TRIAL COURT ERRED WHEN IT FOUND THAT THERE WAS A
    BINDING CONTRACT, ALTHOUGH THE ALLEGED CONTRACT
    VIOLATED THE STATUTE OF FRAUDS.
    {¶46} In their sixth assignment of error, the Gilberts argue that the court erred in
    enforcing a contract that did not satisfy the statute of frauds.
    {¶47} Because we have already concluded that there was no valid contract and that
    Bowers was entitled to judgment based on quantum meruit, this assignment of error is moot and
    we decline to address it. See App.R. 12(A)(1)(c).
    Assignment of Error Number Seven
    THE TRIAL COURT ERRED WHEN IT RULED THAT TRAVELERS
    INSURANCE WAS NOT AN INDISPENSABLE PARTY.
    {¶48} In their seventh assignment of error, the Gilberts argue that the court erred in
    finding that Travelers Insurance was not a necessary and indispensable party. We disagree.
    A person who is subject to service of process shall be joined as a party in the
    action if (1) in his absence complete relief cannot be accorded among those
    already parties, or (2) he claims an interest relating to the subject of the action and
    is so situated that the disposition of the action in his absence may (a) as a practical
    matter impair or impede his ability to protect that interest or (b) leave any of the
    14
    persons already parties subject to a substantial risk of incurring double, multiple,
    or otherwise inconsistent obligations by reason of his claimed interest, or (3) he
    has an interest relating to the subject of the action as an assignor, assignee,
    subrogor, or subrogee. If he has not been so joined, the court shall order that he
    be made a party upon timely assertion of the defense of failure to join a party as
    provided in Rule 12(B)(7).
    Civ.R. 19(A). An indispensable party has been defined as:
    one whose absence seriously prejudices any party to the action or prevents the
    court from rendering any effective judgment between the parties, or is one whose
    interests would be adversely affected or jeopardized by the judgment rendered
    between the parties to the action. Mere avoidance of multiple litigation is not a
    sufficient basis to render one an indispensable party.
    Englehart v. C.T. Taylor C., Inc., 9th Dist. Summit No. 19325, 
    1999 WL 1215110
    , *2, quoting
    Layne v. Huffman, 
    43 Ohio App.2d 53
    , 59 (10th Dist.1974).
    {¶49} The Gilberts argue that “Bowers mainly dealt with Travelers Insurance with
    regard to the goods purchased and services provided; therefore, it is a necessary and
    indispensable party.” We disagree.
    {¶50} Bowers brought suit against the Gilberts to recover the costs associated with the
    repairs it performed in the Gilberts’ home. Bowers had contact with Travelers Insurance to
    discuss what repairs were necessary, determine what repairs were covered under the Gilberts’
    policy, and to ensure the repair costs remained within the insurance estimate that had been
    written by Travelers.     There is no evidence, however, of a contract between Bowers and
    Travelers. The record shows that Bowers also worked closely with Edward Gilbert over the
    course of the repairs. Gilbert received copies of at least some of the insurance estimates and
    declined certain repairs that had been authorized by Travelers, opting instead to receive a credit
    toward chosen upgrades.
    {¶51} At trial, Edward Gilbert testified that he had received money from Travelers for
    the repairs to the home, but that he had concerns about whether the proper amount for the
    15
    building repair had been disbursed. Specifically, Gilbert averred that “the first adjuster [at
    Travelers] included everything into the checks, contents, depreciation, building and so forth.
    That was the confusion, and, quite frankly, still is the confusion, because there’s some question
    as to what was allocated for what.” Even assuming Travelers has not distributed the full amount
    owed to the Gilberts under their insurance policy, this does not make Travelers an indispensable
    party to this action. See Englehart, 
    1999 WL 1215110
    , at *2. (“Mere avoidance of multiple
    litigation is not a sufficient basis to render one an indispensable party.”). The Gilberts are free to
    pursue a claim against Travelers if they feel their policy was breached by Travelers.
    {¶52} We cannot conclude that the absence of Travelers as a party “seriously
    prejudice[d] any party to the action or prevent[ed] the court from rendering [an] effective
    judgment between the parties.” See 
    id.
     Nor is there any evidence that Travelers’ interests would
    be adversely affected by a judgment between the parties.
    {¶53} The Gilberts’ seventh assignment of error is overruled.
    III
    {¶54} The Gilberts’ sixth assignment of error is moot. Their remaining assignments of
    error are overruled. The judgment of the Summit County Court of Common Pleas is affirmed.
    Judgment affirmed.
    There were reasonable grounds for this appeal.
    We order that a special mandate issue out of this Court, directing the Court of Common
    Pleas, County of Summit, State of Ohio, to carry this judgment into execution. A certified copy
    of this journal entry shall constitute the mandate, pursuant to App.R. 27.
    16
    Immediately upon the filing hereof, this document shall constitute the journal entry of
    judgment, and it shall be file stamped by the Clerk of the Court of Appeals at which time the
    period for review shall begin to run. App.R. 22(C). The Clerk of the Court of Appeals is
    instructed to mail a notice of entry of this judgment to the parties and to make a notation of the
    mailing in the docket, pursuant to App.R. 30.
    Costs taxed to Appellants.
    BETH WHITMORE
    FOR THE COURT
    HENSAL, J.
    CONCURS.
    BELFANCE, P. J.
    DISSENTING.
    {¶55} I respectfully dissent.     The trial court in this case misapplied the law in its
    judgment, and, therefore, the matter must be remanded so that the trial court may apply the law
    correctly in the first instance and enter judgment.
    {¶56} The record reflects that the Gilberts suffered water damage at their home and that
    they signed an agreement for J. Bowers Construction to perform the initial remediation work to
    forestall any more damage by virtue of the water coming into the home. As this took place, the
    Gilberts’ insurance company examined the damage and began the process of determining the
    appropriate coverage for the damage. With the assistance of the insurance adjuster, the insurance
    company used a computer program to create a document, which itemized the estimated cost of
    repairs and reflected the sum the insurance company would pay the Gilberts for the water
    17
    damage to the structure. Upon completing the water remediation work, J. Bowers Construction
    proceeded to render services to the Gilberts; however, the company did not present the Gilberts
    with a contract delineating the scope of the work to be performed or its cost. In particular, at the
    outset, J. Bowers Construction did not enter into an agreement with the Gilberts providing that
    the Gilberts would pay the amount ultimately authorized by the insurance company. Instead, it
    began to render services without entering into a written contract.
    {¶57} After the work was completed, Mr. Hayes met with Mr. Gilbert as the
    representative of J. Bowers Construction to discuss the final cost of the work. Mr. Hayes
    explained that the insurance estimate had been for $132,451.98 but that the Gilberts had
    requested upgrades beyond those provided for in the estimate, increasing the cost of the project
    by $8,024.89. Mr. Hayes further explained that, since the insurance company had already paid
    $65,000 for the work, it would only cover $67,451.98 of the outstanding balance, making the
    Gilberts responsible for $6,624.89, which was the additional value of the work less credits for
    damage to the home caused by employees of J. Bowers Construction and allegedly subpar carpet
    used. Mr. Gilbert signed the document presented by Mr. Hayes containing all these numbers and
    wrote a check for $6,624.89. Mr. Gilbert subsequently signed a form indicating that he was
    satisfied with the work performed by J. Bowers Construction so that the insurance company
    would release the final disbursement.
    {¶58} However, prior to giving J. Bowers Construction any of the insurance distribution,
    the Gilberts requested to see the material and labor costs so that they could determine the actual
    value of the services performed by J. Bowers Construction. J. Bowers Construction refused to
    provide the information, stating that such information was proprietary, and brought suit against
    the Gilberts, demanding payment based upon the values itemized by the insurance company in
    18
    its estimate. It appears that J. Bowers Construction believes that, at some point along the way, it
    entered into an express contract with the Gilberts. The Gilberts deny that an express contract
    existed and instead suggest that J. Bowers Construction was required to settle up with the
    Gilberts through reviewing the labor and material costs actually expended by J. Bowers
    Construction.
    {¶59} It is evident from the record that J. Bowers Construction performed services such
    that payment is required. However, a critical threshold question for the trial court was whether
    there existed an express contract between J. Bowers Construction and the Gilberts. In this
    regard, the evidence reveals that there was an initial written document authorizing the initial
    water remediation, and no other writings evidencing an agreement to pay J. Bowers Construction
    a specific sum of money when it undertook the actual repair of the home. However, the trial
    court found that a contract did exist. Notwithstanding this finding, it proceeded to award
    damages based upon the remedy of quantum meruit.1 This was improper because quantum
    meruit is an equitable remedy which is based upon the law implying an obligation and is founded
    upon the absence of an express contract. See Zeck v. Sokol, 9th Dist. Medina No. 07CA0030-M,
    
    2008-Ohio-727
    , ¶ 13 (noting that equitable recovery is inapplicable if an express agreement
    exists concerning the services at issue); see also In re Estate of Kirkland, 
    175 Ohio App.3d 73
    ,
    
    2008-Ohio-421
    , ¶ 25 (2d Dist.), quoting Motzer v. Estate of Carpenter, 2d Dist. Montgomery
    No. 11869, 
    1990 WL 68690
    , *2 (May 18, 1990), citing 18 Ohio Jurisprudence 3d, Contracts,
    Section 314, 315 (“‘An action in quantum meruit is brought upon an implied promise to pay the
    reasonable worth of services rendered or materials furnished by one person for another and
    1
    In addition, given its determination that a contract existed, the trial court did not address
    all of the contractual issues raised by the Gilberts (e.g., whether they could rescind the contract
    pursuant to R.C. 1345.22).
    19
    which are knowingly and voluntarily accepted by the recipient. Upon proof of those facts, the
    law presumes that the services were given and received in the expectation of payment and
    implies a promise to pay what they are reasonably worth.’”). Thus, the remedies available under
    quantum meruit are substantively different than those under an express contract, which are
    limited to the damages caused by the breach. See Schottenstein Zox & Dunn Co., L.P.A. v.
    Reineke, 9th Dist. Medina No. 10CA0138-M, 
    2011-Ohio-6201
    , ¶ 12. Therefore, if an express
    contract existed and was enforceable, the trial court was required to determine the damages
    caused by the breach. Thus, I would reverse and remand the matter for the trial court to further
    clarify its entry. To the extent that the trial court determined that an express contract existed, it
    should clarify this finding and proceed to award contract damages. If such was not the intent of
    the trial court, it should proceed to evaluate damages under quantum meruit.
    {¶60} In this regard, the record reflects that, because J. Bowers Construction believed it
    had an express contract with the Gilberts, its focus was not upon demonstrating the reasonable
    value of the services it actually rendered to the Gilberts for purposes of demonstrating recovery
    under quantum meruit. Mr. Hayes testified that the values set forth in the insurance estimate
    were merely the average expected cost for the work.2 However, the insurance company’s
    estimate represents what it proposed to pay the Gilberts based upon the contract of insurance it
    had with them rather than the value of the work specifically performed by J. Bowers
    Construction. Thus, the Gilberts’ agreement with their insurer to accept the payout proposed by
    the insurance company as reflected in its itemized estimate did not in any way bind them to pay
    those same sums to J. Bowers Construction and was not dispositive of the damage award under
    2
    For example, J. Bowers Construction could have used inferior materials than those in
    the insurance estimates, had subpar skill or had lower actual labor costs in installing the
    materials, any of which could affect the determination of the reasonable value of the services it
    rendered.
    20
    quantum meruit.3 However, although unclear, J. Bowers Construction may have convinced the
    trial court to award it the theoretical value for its work rather than the reasonable value of the
    services it actually rendered because the trial court simply awarded the value of the insurance
    estimate.
    {¶61} The majority has determined that the trial court’s error in finding that J. Bowers
    Construction had a contract with the Gilberts was harmless. However, in light of the trial court’s
    erroneous analysis, which was based upon the intermingling of distinctly different legal theories
    of recovery, the trial court’s decision should be reversed, and the matter should be remanded so
    that the trial court may clarify and determine in the first instance the existence of any enforceable
    contract. If there is a contract, the trial court should then determine the contractual damages, not
    the reasonable value of the work. However, to the extent there is no enforceable contract, the
    trial court should then consider whether J. Bowers Construction was entitled to recover under
    quantum meruit upon consideration of appropriate evidence demonstrating the reasonable value
    of the services J. Bowers Construction rendered.
    {¶62} Accordingly, I dissent.
    APPEARANCES:
    EDWARD L. GILBERT, Attorney at Law, for Appellants.
    THOMAS C. LOEPP, Attorney at Law, for Appellee.
    3
    Of course, J. Bowers Construction and the Gilberts could have formed an express
    contract that, in exchange for completing the work delineated in the insurance estimate, J.
    Bowers Construction would receive all of the insurance distributions for the repairs delineated in
    the insurance estimate.