Tpl, Incorporated v. United States , 2014 U.S. Claims LEXIS 971 ( 2014 )


Menu:
  •        In the United States Court of Federal Claims
    No. 11-482C
    (Filed: September 16, 2014)
    * * * * * * * * * * * * * * * * * *
    *
    TPL, INC.,                        *                      Jurisdiction; Contract Disputes Act;
    *                      41 U.S.C. §§ 7101–7109; Summary
    Plaintiff,        *                      Judgment; RCFC 56; Breach of
    *                      Contract; Impossibility;
    v.                         *                      Impracticability; Mutual Mistake;
    *                      Unconscionability; Mitigation of
    THE UNITED STATES OF AMERICA,     *                      Damages; Failure to Raise Defense
    *                      with Contracting Officer.
    Defendant.        *
    *
    * * * * * * * * * * * * * * * * * *
    Robert Stewart Gardner, Law Office of Robert S. Gardner, Colorado Springs,
    CO, for plaintiff.
    Daniel B. Volk, Civil Division, United States Department of Justice, Washington,
    D.C., for defendant. With him were Donald E. Kinner, Assistant Director, Bryant
    G. Snee, Acting Director, and Stuart F. Delery, Assistant Attorney General.
    OPINION AND ORDER
    This case is before the Court on the government’s motion for summary judgment.
    Plaintiff, TPL, Incorporated (hereinafter “TPL”), seeks relief from the decision of a U.S. Army
    contracting officer finding that it owes the United States $11,958,046 as compensation for TPL’s
    breach of contractual obligations to demilitarize and dispose of certain Army ammunitions. The
    government, in turn, has filed a counterclaim seeking damages in the amount of $11,887,509.72
    for TPL’s alleged breach of contract. For the reasons set forth below, the government’s motion
    for summary judgment is GRANTED.
    BACKGROUND
    I.     The Contracts
    In 1994 and 1996, the U.S. Army Material Command awarded TPL two contracts
    involving the demilitarization and disposal of ammunitions. The first contract, No. DAAA09-
    94-C-0386 (“the 1994 demilitarization contract”), was awarded on June 30, 1994, and the
    second, No. DAAA09-96-C-0065 (“the 1996 demilitarization contract”), was awarded on
    September 17, 1996. Def.’s Mot. Summ. J., ECF No. 34, A1, A126 (hereinafter “Def.’s Mot.”).
    The third contract at issue in this case, No. DAAA09-94-E-0014 (“the facilities use contract”),
    was awarded on September 30, 1994, Def.’s Mot. A17, and permitted TPL to use portions of an
    Army installation located at Fort Wingate, New Mexico on a rent-free basis to conduct
    demilitarization operations under the demilitarization contracts. 
    Id. at A105.
    The statement of work for the 1994 demilitarization contract called for “disassembly for
    reuse and resource recovery of various pyrotechnic ammunition items.” 
    Id. at A6.
    The
    statement of work for the 1996 demilitarization contract contemplated “the incineration and/or
    reuse/resource recovery of Armor Piercing and Anti-Personnel loaded ammunition.” 
    Id. at A130,
    ¶ 1.1. Both demilitarization contracts provided that the “[t]he contractor shall take title to
    all material/components arising out of the disassembly and demilitarization of the Government
    Furnished Ammunition.” 
    Id. at A15,
    ¶ 5.1; A140, ¶ 5.1. The contracts further provided: “Title
    to the recovered material/components shall pass to the contractor upon Government inspection
    and acceptance . . . . At that point, the contractor assumes complete responsibility and liability
    for disposition of the recovered material/components.” 
    Id. at A16,
    ¶ 5.3; A140, ¶ 5.2.3.
    The demilitarization contracts stated that “the contractor shall use best efforts to recover
    the maximum materials/components possible” and that “[t]he Government does not guarantee
    the quantum of recoverable materials/components.” 
    Id. at A6,
    ¶ 1.3; A130 ¶ 1.3. They further
    stated that “[t]he negotiated firm-fixed price reflects full consideration to the contractor for its
    performance under the contract” and that “[t]he proposed price will reflect any estimated or
    anticipated proceeds from recovered materials/components.” 
    Id. Under the
    facilities use contract, the parties agreed that at the conclusion of TPL’s use of
    the facilities, all government-furnished property “shall, at the contractor’s sole expense and
    without direct charge to this contract, be returned to the Government in the same condition . . . as
    when originally provided less normal wear and tear.” 
    Id. at A18,
    ¶ 3(c). The facilities use
    contract initially had a term of four years, 
    id. at A18,
    ¶ 2, but it was extended several times at
    TPL’s request. 
    Id. at A69
    (extension to September 30, 2000), A86 (extension to September 30,
    2002), A92 (extension to December 31, 2006 “or until transfer of the Government property to the
    Department of the Interior, whichever first occurs”), A180 (requesting 90-day extension beyond
    December 31, 2006), A102, A183 (granting extension to March 31, 2007), A186 (requesting
    extension to April 27, 2007), A191-93 (granting extension to April 27, 2007). TPL ultimately
    vacated Fort Wingate on April 27, 2007. 
    Id. at A194-96,
    A197-98, A199-200.1
    1
    Initially, the Army stated that it would not permit TPL to invoice for its demilitarization work
    until TPL had disposed of all components of the ammunitions. See 
    id. at A108
    (In an April 9,
    1995 letter, TPL noted that “[t]he requirement being imposed . . . that final end-state disposal is
    achieved for all components before a DD250 can be approved and demilitarization credit
    compiled[] is not consistent with . . . our contract”). The Army eventually agreed that TPL
    could take title to the energetic materials and invoice for its demilitarization work before having
    fully disposed of the energetic material extracted from the ammunitions. See 
    id. at A115
    (“agreed to the three-part DD250 suggestion to avoid a confrontation on the definition of when
    Demilitarization was sufficiently complete to allow transfer of title to us.”).
    2
    II.    TPL’s Failure to Dispose of Materials as Required by the Contracts
    The Army permitted TPL to use a variety of facilities at Fort Wingate, including storage
    igloos, for its demilitarization work. On January 30, 1998, the Army requested that TPL remove
    any residual material from previous contracts within sixty days. 
    Id. at A158
    (January 30, 1998
    letter reminding TPL of a previous agreement to remove all energetics within 60 days after title
    transfer via form DD250). In a letter dated February 9, 1998, TPL responded that, although it
    could not accomplish removal of these materials within sixty days, it “plan[ned] to sell the
    pyrotechnic materials over the next three years, emptying the last of the storage magazines
    during 2000.” 
    Id. at A159;
    see also 
    id. at A162.
    As the facilities use contract neared its September 30, 1998 expiration, and with the
    Army anticipating a transfer of the land on which Fort Wingate was situated to the Department
    of the Interior, the Army expressed reluctance to agree to another extension of the facilities use
    contract. 
    Id. at A142;
    see also 
    id. at A161.
    Ultimately, after inquiries from members of
    Congress, the Army agreed to a two-year extension of the contract. 
    Id. at A69
    ; see also 
    id. at A121,
    A155.
    In December 2001, a safety survey revealed that TPL continued to store a large quantity
    of energetic material at Fort Wingate despite its promise in the February 9, 1998 letter to empty
    the storage igloos by 2000. 
    Id. at A172.
    Accordingly, in January 2002, the Army once again
    requested a written disposal plan. 
    Id. In a
    March 1, 2002 letter, however, TPL responded that
    “any detailed plan is worthless.” 
    Id. at A173.
    TPL stated that it
    regretfully must decline your requirement for a formal plan by contract and lot
    number for disposal of the energetic materials at Fort Wingate . . . . [T]here was
    no requirement in the basic contracts for a disposal plan nor was there a time line
    placed on disposal of those assets. In addition[,] . . . those materials fall under the
    direct supervision of the Bureau of Alcohol Tobacco and Firearms (ATF) and not
    the Department of Defense.
    
    Id. TPL further
    reported: “Slurry Explosives Corporation (“SEC”) our main customer for
    propellant (approximately 30,000# daily) has had their Explosives Manufacturing License
    revoked by ATF and may be out of production for several months.” Id.; see also 
    id. at A149-54
    (contract with Slurry Explosives Corporation), A178.
    On November 27, 2006, approximately one month before the facilities use contract, as
    amended, was to expire, TPL requested a ninety-day extension of the contract. 
    Id. at A180.
    TPL
    explained that “[t]he reason for this request is to allow TPL sufficient time to remove the stored
    energetic materials and complete other required departure activities.” 
    Id. The Army
    granted the
    request, extending the contract to March 31, 2007. 
    Id. at A102,
    A183.
    On March 21, 2007, TPL requested an extension of the facilities use contract through
    April 27, 2007, stating, “[w]e hope to complete shipping prior to that date.” 
    Id. at A186.
    The
    Army agreed to grant the requested extension, on certain terms, 
    id. at A191-93,
    and forwarded a
    modification to TPL for signature. 
    Id. at A194-96.
    TPL declined to sign the modification, and
    3
    vacated Fort Wingate on April 27, 2007, leaving behind approximately 400,000 pounds of
    energetic material it had recovered from the demilitarization contracts. 
    Id. at A197-202.
    III.   The Government’s Disposal of the Materials
    After TPL vacated Fort Wingate, the Army disposed of the energetic materials TPL left
    behind. 
    Id. at A356.
    To dispose of this material, the Army incurred $11,887,509.72 in total
    costs. 
    Id. at A357.
    The largest components of these costs consist of amounts the Army paid to
    other ammunition disposal contractors. See 
    id. at A356.
    To dispose of the hundreds of
    thousands of pyrotechnic items left at Fort Wingate by TPL, the Army modified a pre-existing
    contract it had with General Dynamics Ordnance and Tactical Systems, Inc. (GDOTS), at a cost
    of $7,896,626. 
    Id. at A242-46,
    A269, A356, A361.
    In addition to the pyrotechnic items, TPL also left sixteen boxes of miscellaneous
    energetic material at Fort Wingate. 
    Id. at A356.
    To dispose of this material, the Army issued a
    delivery order for a contract it had in place with PIKA International, Inc. (PIKA). 
    Id. at A222-
    23. The Army incurred costs of $1,441,424.15 under the delivery order issued to PIKA. 
    Id. at A324,
    A343, A356, A361.
    The Army also incurred costs contracting for security at Fort Wingate, to replace the
    security that TPL was required to provide under its facility use contract. See 
    id. at A35.
    The
    Government obtained the necessary security under a contract with Vista Sciences Corporation
    (Vista). 
    Id. at A187-90.
    Vista began providing security in April 2007 under Contract No.
    W52P1J-07-D-3004. 
    Id. at A189-90.
    The first two months of security under delivery order 0001
    for this contract cost the Army $250,829.30. 
    Id. at A189.
    The security contract was extended
    thereafter by several delivery orders at a monthly rate of $71,887.08. 
    Id. at A204
    (delivery order
    0002), A212 (delivery order 0003), A289 (delivery order 0004), A299 (delivery order 0005),
    A325 (delivery order 0006), A329, A339 (cancellation of delivery order 0006). For security at
    Fort Wingate between April 2007 and the beginning of March 2008, the Army incurred costs
    totaling $914,046.01.2. 
    Id. at A187,
    A204, A212, A216, A289, A299, A325, A329, A339.
    The Army also expended resources in managing and coordinating the disposal of the
    energetic material TPL left at Fort Wingate. The Army incurred $1,089,534 in costs for the
    deployment of the Mobile Ammunition Renovation Inspection and Demil (MARID) team to
    assess and inventory the energetic material and then to repackage, apply proper shipping
    markings, and palletize the material for the shipment to disposal sites. 
    Id. at A208-09,
    A210,
    A298, A356, A360. The Army incurred $11,860.03 in expenses for Government personnel who
    traveled to Fort Wingate. 
    Id. at A357;
    see also A221, A293, A360-61 (providing evidence of the
    involvement and costs of government personnel). The Army also incurred $57,276.97 in costs
    for 1,587 total labor hours logged by a variety of Army personnel. 
    Id. at A357;
    see also A293,
    A360-61. In the spreadsheet included with defendant’s motion at page A360-61, the hours spent
    by each individual are recorded, described, and multiplied by the appropriate hourly rate for that
    individual’s pay grade.
    The Army also incurred $3,200 in costs for the removal of a compressor belonging to
    TPL from Fort Wingate. 
    Id. at A307,
    A361. In addition, it expended $16,232.80 for hazardous
    4
    waste fees related to TPL’s energetic material, which it paid to the State of New Mexico
    Environment Department Hazardous Waste Bureau. 
    Id. at A349-50,
    A354, A357, A361; see 
    id. at A315.
    IV.    This Action
    On July 30, 2010, the Army issued a contracting officer’s final decision under the
    facilities use contract. 
    Id. at A355.
    In that decision, the contracting officer demanded
    reimbursement in the amount of $11,958,046.72 for the expenses identified above. 
    Id. at A357.
    TPL filed the instant suit in this Court on July 26, 2011 seeking relief from that decision.
    Thereafter, the government filed a counterclaim for breach of contract, requesting damages in the
    amount of $11,887,509.72 plus interest. See Def.’s Mot. 6 n.2, 7 n.3. The government
    subsequently filed the present motion for summary judgment.
    DISCUSSION
    It is undisputed and TPL acknowledges that it did not dispose of all of the energetics
    materials as required by the demilitarization contracts. Decl. of H. M. (Hap) Stoller ¶ 6, Pl.’s
    App. 3 (“Stoller Decl.”) (observing that “TPL does not contest the fact that it did not dispose of
    all of the materials which it undertook to dispose of under the 1994 demilitarization contract”).
    TPL alleges, however, that it should be excused from reimbursing the government for the
    expenses it incurred as a result of this breach because: (1) the government committed its own
    breach of the contracts which contributed to TPL’s failure to perform; (2) TPL’s performance
    under the contracts was made impossible or impracticable by changed circumstances; (3) the
    contracts in question were based on mutual mistake of fact; and/or (4) the contracts were
    unconscionable.2 Am. Compl. ¶¶ 67-93, ECF No. 8. TPL also claims that the expenses the
    government incurred to remove and dispose of the materials it left behind were not fair and
    reasonable, and that the government could have performed the services needed to complete the
    disposal of all remaining materials for $1,850,000, rather than the approximately $11.8 million
    the government seeks in its counterclaim. Am. Compl. ¶¶ 97 – 99; Pl.’s Resp. to Def.’s Mot.
    Summ. J. 13, ECF No. 39 (“Pl.s’ Resp.”).
    In response, the government contends: (1) that this Court lacks jurisdiction to consider
    TPL’s defenses because TPL did not file claims or otherwise raise the defenses before the
    contracting officer; and (2) that, in any event, the defenses are meritless as a matter of law. It
    also argues that TPL has failed to raise a genuine issue of material fact as to the reasonableness
    of the government’s actions to mitigate the damages it suffered as a result of TPL’s breach of
    contract. Def.’s Mot. 9-15.
    For the reasons set forth below, the Court finds that the material facts are not in dispute
    and that the government is entitled to judgment as a matter of law for the full amount of its
    claimed damages. Accordingly, the government’s motion for summary judgment is granted.
    2
    TPL also alleged in its amended complaint that the provisions of the contracts were illegal.
    Am. Compl. ¶¶ 94-96. At oral argument, counsel indicated that TPL was no longer pressing that
    claim. Oral Arg. Tr. 18, September 3, 2014, ECF No. 44.
    5
    I.     Summary Judgment Standards
    The government has moved for summary judgment pursuant to Rules of the Court of
    Federal Claims 56. A moving party is entitled to summary judgment when there are no genuine
    issues of material fact, and the moving party is entitled to judgment as a matter of law. RCFC
    56(a); Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 322 (1986). The moving party bears the initial
    burden of showing that there are no genuine issues of material fact. Celotex 
    Corp., 477 U.S. at 322-23
    . A fact is material if it “might affect the outcome of the suit under the governing law.”
    Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 248 (1986). A dispute about a material fact is
    “genuine” “if the evidence is such that a reasonable jury could return a verdict for the nonmoving
    party.” 
    Id. The movant’s
    burden can be met by demonstrating an absence of evidence to support the
    nonmoving party’s case. Celotex 
    Corp., 477 U.S. at 325
    . Once the moving party has satisfied its
    initial burden, the opposing party must establish a genuine issue of material fact and cannot rest
    on mere allegations, but must present actual evidence. 
    Anderson, 477 U.S. at 248
    . Summary
    judgment is mandated, “after adequate time for discovery and upon motion, against a party who
    fails to make a showing sufficient to establish the existence of an element essential to that party’s
    case, and on which that party will bear the burden of proof at trial.” Celotex 
    Corp., 477 U.S. at 322
    .
    II.    The Government Is Entitled to Summary Judgment as to TPL’s Liability for Breach
    of Contract Because TPL Failed to Raise Its Defenses Before the Contracting
    Officer, and Because, in Any Event, Those Defenses Are Meritless as a Matter of
    Law.
    The facilities use contract required TPL to return the premises to their original condition
    at the conclusion of their use. Contract No. DAAA09-94-E0014, ¶ 3(c), Def.’s Mot. A18. As
    noted, it is undisputed that TPL failed to meet this obligation. See Pl.’s Resp. 2 (observing that
    “[p]laintiff does not take issue with the facts as stated in Defendant’s Motion as far as they go”).
    TPL argues, nonetheless, that the government’s motion for summary judgment should be denied
    because the assorted defenses it seeks to assert against the government’s breach of contract claim
    create genuine issues of material fact. 
    Id. at 3.
    TPL’s argument must be rejected; the Court
    lacks jurisdiction to consider its defenses because TPL failed to raise them before the contracting
    officer. Further, the defenses lack merit as a matter of law.
    A.      Defense based on the government’s alleged breach of contract
    First, TPL argues that it cannot be held liable for its breach of contract because of the
    government’s own alleged breach of the contracts. Am. Compl. ¶¶ 67-77; Pl.’s Resp. 7-8.
    Relying upon the affidavit of its president, H. M. Stoller, TPL argues that “[d]uring the course of
    performance, TPL experienced multiple instances of the Government failing to perform its
    responsibilities.” Pl. Resp. 7 (citing Stoller Decl. ¶¶ 7-8). Specifically, Mr. Stoller alleges that
    the government failed to provide “Technical Data Packages” (TDPs) on the ammunitions that
    were to be demilitarized. Stoller Decl. ¶ 7. He claims that this failure (which apparently
    occurred during the first year of contract performance) violated the government’s obligations
    6
    under the 1994 demilitarization contract to “provide the contractor with technical data, to include
    a final assembly drawing and component assembly drawing(s) as applicable . . . for each type of
    ammunition delivered to the Contractor’s site.” 
    Id. (citing Statement
    of Work for Contract No.
    DAAA09-94-C-0386, Def.’s Mot. A14). He states that “[t]he extent to which the failure of the
    Government to perform its responsibilities contributed to the circumstances which led to this
    Government claim is difficult to quantify. But it certainly was a contributing factor in TPL’s
    inability to fully perform in a timely and responsive fashion.” 
    Id. at ¶
    8.
    Even assuming that TPL could prove that the alleged failure to provide TDPs some
    twenty years ago was a breach of contract, the Court lacks jurisdiction to consider this or any
    other breach of contract claim asserted by TPL. Claims for breach of contract must be brought
    under the Contract Disputes Act, 41 U.S.C. §§ 7101–7109 (2012). Gonzales-McCauley Inv.
    Grp., Inc. v. United States, 
    93 Fed. Cl. 710
    , 716 (2010) (citing Dalton v. Sherwood Van Lines,
    
    50 F.3d 1014
    , 1017 (Fed. Cir. 1995)). Under that Act, presentation of a claim for breach to a
    contracting officer is a prerequisite to this Court’s jurisdiction to hear the claim. M. Maropakis
    Carpentry, Inc. v. United States, 
    609 F.3d 1323
    , 1329 (Fed. Cir. 2010); England v. Swanson
    Grp., Inc., 
    353 F.3d 1375
    , 1379 (Fed. Cir. 2004); Scott Timber Co. v. United States, 
    333 F.3d 1358
    , 1365 (Fed. Cir. 2003). See 41 U.S.C. § 7103(a) (providing that all claims by a contractor
    against the government shall be in writing, submitted to the contracting officer for a decision,
    and certified if more than $100,000).3
    It is undisputed that TPL never raised its breach of contract claim (or any other claim)
    with the contracting officer. In that regard, the fact that TPL is asserting its breach of contract
    claim solely as a defense to the government’s counterclaim is of no moment. Raytheon Co. v.
    United States, 
    747 F.3d 1341
    , 1354 (Fed. Cir. 2014) (citing 
    Maropakis, 609 F.3d at 1331
    ). The
    court of appeals has clearly stated that the CDA’s “jurisdictional prerequisite applies even when
    a claim is asserted as a defense.” 
    Id. Therefore, the
    Court concludes that it lacks jurisdiction to
    consider TPL’s claim for breach of contract. 4
    3
    The purpose of this requirement is to resolve all claims at the contracting officer level.
    
    Maropakis, 609 F.3d at 1331
    . Here, that objective would be frustrated if the Court heard a claim
    for breach of contract that was not presented to the contracting officer.
    4
    In its Amended Complaint at ¶¶ 75-77, TPL asserts as part of its claim of relief for breach of
    contract that the government failed to use appropriated funds that were supposedly intended to
    assist TPL in meeting its obligations to dispose of the material. This claim is not supported by
    citation to any specific legislation. In fact, at the oral argument, counsel for TPL conceded that
    there is no specific statutory language earmarking any funds for this particular demilitarization
    project. Oral Arg. Tr. 18-19. In any event, TPL also does not explain how its allegations of
    frustration of Congressional intent, even if accurate, constitute a breach of contract by the
    government.
    7
    B.      Defense based on impossibility/impracticability
    TPL also claims that it should be excused from performance of its obligations to dispose
    of the ammunitions by the doctrines of impossibility or impracticability of performance. Am.
    Compl. ¶¶ 78-83. Relying upon the assertions in the affidavit of its president, TPL claims that it
    had planned to dispose of the pyrotechnic materials in the ammunitions by selling them or giving
    them to companies in the fireworks industry. It further claims that intervening changes in U.S.
    tariff policies put the domestic fireworks companies with whom TPL planned to work out of
    business. Stoller Decl. at ¶¶ 10-11. In particular, TPL was unable to find other reuses for
    photoflash cartridges and was unable to timely develop an alternative and affordable process for
    disposing of them. 
    Id. at ¶
    ¶ 11-13. Similarly, TPL notes, the company with which it had an
    agreement to purchase demilitarized propellant for use as an explosive product in the mining
    industry abrogated its agreement with TPL because it concluded that the product could not be
    manufactured economically. 
    Id. at ¶
    14. According to Mr. Stoller, “[t]his left TPL with over
    15,000,000 pounds of demilitarized propellant in storage at Fort Wingate.” 
    Id. “Impossibility” of
    performance exists “when it is objectively determined that no
    contractor could perform the work.” Conner Bros. Const. Co., Inc. v. United States, 
    65 Fed. Cl. 657
    , 686 (2005) (citations omitted). While TPL asserts “impossibility” as a defense, the
    gravamen of its complaint is not that it was impossible for any contractor to dispose of the
    ammunitions (in fact, another contractor has now removed the ammunitions). Rather, TPL’s
    assertion is that the costs of the disposal were prohibitive, which constitutes a claim of
    commercial impracticability, not impossibility. See 
    id. As with
    TPL’s defense based on breach of contract, this Court lacks jurisdiction to
    entertain TPL’s impracticability defense. In Maropakis, the court of appeals held that a
    contractor could not assert a defense of excusable delay against the government’s claim for
    liquidated damages where the contractor failed to present that claim to the contracting 
    officer. 609 F.3d at 1331
    . The Court noted that there was no authority for the contractor’s argument for
    an exception to the CDA’s notice requirement when a contractor’s claim for contract
    modification is made in defense to a government claim. 
    Id. It held
    that “a contractor seeking an
    adjustment of contract terms must meet the jurisdictional requirements and procedural
    prerequisites of the CDA, whether asserting the claim against the government as an affirmative
    claim or as a defense to a government action.” Id.; see also Raytheon Co. v. United 
    States, 747 F.3d at 1354
    .
    TPL argues that Maropakis is inapposite because it does not seek an adjustment to the
    contract terms in this case but only asserts impracticability as a defense to the government’s
    counterclaim. Pl.’s Resp. 6. But TPL fails to appreciate that impracticability is “treated as a
    type of constructive change to the contract; because a commercially impracticable contract
    imposes substantial unforeseen costs on the contractor, the contractor is entitled to an equitable
    adjustment.” Raytheon Co. v. White, 
    305 F.3d 1354
    , 1367 (Fed. Cir. 2002); see also Ace
    Constructors v. United States, 
    499 F.3d 1357
    , 1364 (Fed. Cir. 2007). And, as previously
    discussed, Maropakis is very clear that—for purposes of determining this Court’s jurisdiction
    under the CDA—it is irrelevant whether a claim for equitable adjustment of a contract is asserted
    offensively or defensively.
    8
    For the first time at the oral argument on the government’s motion for summary
    judgment, counsel for TPL cited Sikorsky Aircraft Corp. v. United States, 
    102 Fed. Cl. 38
    , 48
    n.14 (2011). TPL’s counsel referred specifically to footnote 14 of the decision, which he argued
    provided support for TPL’s position that this Court has jurisdiction over its various defenses
    because TPL is purportedly not seeking to adjust the terms of the contract, but rather to defend
    itself against the government’s counterclaims. TPL’s reliance upon Sikorsky is unavailing.
    In Sikorsky, the contracting officer issued a final decision that the plaintiff owed damages
    for violations of cost accounting 
    standards. 102 Fed. Cl. at 40
    , 44. In response, plaintiff filed a
    complaint in this court pleading affirmative defenses based on accord and satisfaction, waiver,
    laches, and the statute of limitations. 
    Id. at 44.
    Seven months after the complaint was filed, the
    court of appeals decided the Maropakis case. 
    Id. As a
    protective matter and “out of an
    abundance of caution,” the plaintiff filed a new claim with the contracting officer raising its
    affirmative defenses. 
    Id. After the
    contracting officer declined to issue a decision on the
    defenses, the plaintiff filed a second complaint with the court, which was consolidated with the
    original complaint. 
    Id. The issue
    before the court was whether it had jurisdiction over either
    complaint in light of Maropakis.
    The court concluded that even assuming that Maropakis did apply to these defenses, the
    court would have jurisdiction over the case because the plaintiff had raised the defenses with the
    contracting officer before it filed its second complaint in the 
    case. 102 Fed. Cl. at 47-48
    . The
    court then went on in footnote 14 to discuss whether it would have had jurisdiction to consider
    the defenses, in any event, in connection with plaintiff’s first complaint. It concluded that
    Maropakis was inapplicable to the plaintiff’s defenses based on accord and satisfaction, waiver,
    laches, and the statute of limitations because the holding in Maropakis “only extends to
    counterclaim defenses that seek contract modification” (which the affirmative defenses at issue
    in Sikorsky did not) and because the affirmative defenses at issue in Sikorsky (unlike the defense
    of excusable delay in Maropakis) “are not claims for additional 
    relief.” 102 Fed. Cl. at 48
    n.14.
    As is readily apparent, the court’s discussion in Sikorsky does not support TPL’s
    argument because—as described above—other than its arguments concerning the reasonableness
    of the government’s mitigation efforts, TPL’s defenses (unlike those the plaintiff interposed in
    Sikorsky) do, in effect, seek contract modification. TPL’s defenses are thus squarely within the
    rationale of Maropakis.
    In any event, TPL’s invocation of the impracticability defense lacks legal merit and/or
    sufficient evidentiary support to defeat the government’s motion for summary judgment. As a
    general matter, a contract is commercially impracticable “when, because of unforeseen events, it
    can be performed only at an excessive and unreasonable cost, or when all means of performance
    are commercially senseless.” Raytheon Co. v. 
    White, 305 F.3d at 1367
    (internal citations
    omitted). Commercial impracticability “excuses a party from performing unless the party has
    assumed the risk of the event” that rendered performance impracticable. 
    Id. That is,
    “a party’s
    performance under [a contract] is impracticable without [the party’s] fault because of a fact of
    which [the party] has no reason to know and the non-existence of which is a basic assumption on
    which the contract is made.” Mass. Bay Transp. Auth. v. United States, 
    254 F.3d 1367
    , 1374
    (Fed. Cir. 2001) (emphasis in original) (quoting Restatement (Second) of Contracts § 266(1)).
    9
    As the Court of Claims observed, the “commercial impracticability standard can be easily
    abused; thus this court has not applied it with frequency or enthusiasm.” Jennie-O-Foods v.
    United States, 
    580 F.2d 400
    , 409 (Ct. Cl. 1978). In particular, the doctrine “is not invoked
    merely because costs have become more expensive than originally contemplated.” 
    Id. Further, a
    party may not rely upon the doctrine of impracticability where increased costs are based on
    changes in market conditions that are part of the risk the party assumed in entering the contract.
    Agility Def. & Gov’t Servs., Inc. v. United States, 
    115 Fed. Cl. 247
    , 252 (2014) (citing Seaboard
    Lumber Co. v. United States, 
    308 F.3d 1283
    , 1294 (Fed. Cir. 2002)).
    Here, TPL’s claims of unanticipated costs arising out of changes in tariff policy and
    environmental regulations are insufficient to establish impracticability of performance. The
    nonoccurrence of such changes was not a basic assumption of the contract. To the contrary, the
    contract is clear that once title to the materials passed to TPL, TPL “assume[d] complete
    responsibility and liability” for their disposition. Def.’s Mot. A16, ¶ 5.3; A140, ¶ 5.2.3. Further,
    in the contract the government expressly disclaimed any “guarantee” regarding “the quantum of
    recoverable material/components.” 
    Id. at A6,
    ¶ 1.3; A130, ¶ 1.3. Because TPL assumed the risk
    that changes in market conditions might occur and make its performance more expensive, it
    cannot rely upon “impracticability” as a defense to its liability for breach of the contracts. See
    Conner Bros. Const. Co., Inc. v. Geren, 
    550 F.3d 1368
    , 1379 (Fed. Cir. 2008).5
    C.      Defense based on mutual mistake of fact
    Citing the same factual assertions as those upon which it relies for its
    impossibility/impracticability argument, TPL urges that its performance should be excused under
    the doctrine of mutual mistake of fact. Am. Compl. ¶¶ 84-90. According to TPL, both it and the
    government mistakenly believed “that the energetic materials could be disposed of in a manner
    that was both commercially feasible and legally possible.” Pl.’s Resp. 10 (citing Stoller Decl. ¶¶
    17-20).
    In order to establish mutual mistake of fact, a plaintiff must demonstrate that: “(1) the
    parties to the contract were mistaken in their belief regarding a fact; (2) that mistaken belief
    constituted a basic assumption underlying the contract; (3) the mistake had a material effect on
    the bargain; and (4) the contract did not put the risk of the mistake on the party seeking
    reformation.” Atlas Corp. v. United States, 
    895 F.2d 745
    , 750 (Fed. Cir. 1990). Reformation,
    rescission, and restitution are all available remedies in the case of a mutual mistake. Rosenburg
    Lumber Co. v. Madigan, 
    978 F.2d 660
    , 665 (Fed. Cir. 1992).
    5
    Also, TPL has not specified the extent to which its costs would have been increased had it met
    its obligations to dispose of the pyrotechnic material. In order to demonstrate impracticability
    based on the existence of excessive costs that would make performance “commercially
    senseless,” TPL would be required to produce evidence that any cost overrun was “so
    significantly disparate so as to warrant a finding of impracticability.” Conner Bros., 
    65 Fed. Cl. 657
    , 687 (2005) (citing cases in which cost overruns of up to 70% were not sufficient to
    demonstrate impracticability).
    10
    Like TPL’s impossibility/impracticability defense, the defense of mutual mistake of fact
    seeks a reformation of the terms of the contract. But TPL did not submit a claim to the
    contracting officer seeking reformation of the contract on the basis of mistake. Accordingly, this
    Court lacks jurisdiction to consider this defense. See 
    Maropakis, 609 F.3d at 1331
    ; Raytheon
    Co. v. United 
    States, 747 F.3d at 1354
    .
    Further, and in any event, the defense lacks merit as a matter of law. Among other
    things, as described above, the contract clearly placed the risk of paying for the disposal of the
    materials on TPL. It also expressly disclaimed any guarantees regarding the amount of materials
    that TPL might recover and convert for sale or other purposes. Because the contract “put the risk
    of the mistake on the party seeking reformation,” TPL cannot assert a defense based on mutual
    mistake of fact. Atlas 
    Corp., 895 F.2d at 750
    .
    D.      Defense based on unconscionability
    Finally, TPL also asks to be excused from its contractual obligation on the grounds that
    the 1994 demilitarization contract was unconscionable. Am. Compl. ¶¶ 91-93; Pl.’s Resp. 10-11.
    Specifically, Mr. Stoller states in his declaration that “[i]n hindsight, the 1994 Pyro Demil
    contract was an unconscionable contract” because, among other similar reasons, the government
    “knew or should have known” that the process of “resource recovery and reuse” of energetic
    materials was not a commercially viable one. Stoller Decl. ¶¶ 21-25.
    An unconscionable contract provision is one “which no man in his senses, not under a
    delusion, would make, on the one hand, and which no fair and honest man would accept on the
    other.” Fraass Surgical Mfg. Co. v. United States, 
    571 F.2d 34
    , 40 (Ct. Cl. 1978) (quoting Hume
    v. United States, 
    21 Ct. Cl. 328
    , 330 (1886), aff’d, 
    132 U.S. 406
    (1889)); see also Peters v.
    United States, 
    694 F.2d 687
    , 694 (Fed. Cir. 1982). In cases where a court finds a contractual
    provision unconscionable, it has the power “to refuse to enforce the agreement in its entirety, to
    delete the unconscionable clause and enforce the remainder of the contract, or to limit the
    unconscionable clause’s application so that an unconscionable result will be avoided.” 8
    Williston on Contracts § 18:17 (4th ed.). As the Court of Claims explained in 
    Fraass, 571 F.2d at 40
    , “[t]he grant of discretion to deny enforcement to an unconscionable clause . . . is not intended
    to permit courts to redistribute risks allocated by differences in bargaining power, but rather to
    prevent oppression and unfair surprise.”
    TPL’s unconscionability argument is meritless on its face, as it is expressly based on
    “hindsight.” Unconscionability is determined at the time the parties entered into the contract.
    Glopak Corp. v United States, 
    851 F.2d 334
    , 338 (Fed. Cir. 1988). Therefore, “[t]he fact that the
    actual application of [a contractual provision] had an adverse effect on [one of the contracting
    parties] would not justify retroactively invalidating it as unconscionable.” 
    Id. In a
    ny case, as with its impossibility/impracticability and mutual mistake of fact defenses,
    TPL’s defense based on unconscionability seeks to modify its obligations under the contracts
    with the government. TPL did not, however, raise this claim with the contracting officer.
    Accordingly, under Maropakis, this Court lacks the jurisdiction to consider this defense.
    11
    III.   The Government Is Entitled to an Award of Damages for the Full Amount of Its
    Claimed Costs.
    As noted above, the government seeks an award of $11,887,509.72 in damages as
    reimbursement for the costs it incurred to dispose of the demilitarized ammunitions at Fort
    Wingate. TPL challenges the amount of damages claimed by the government, contending that it
    is excessive. It urges that there are genuine issues of material fact regarding the reasonableness
    of the government’s expenditures, precluding a grant of summary judgment in the government’s
    favor.
    A non-breaching party has a duty to mitigate its damages. Ind. Mich. Power Co. v.
    United States, 
    422 F.3d 1369
    , 1375 (Fed. Cir. 2005); Robinson v. United States, 
    305 F.3d 1330
    ,
    1336 (Fed. Cir. 2002); Restatement (Second) of Contracts § 350, cmt. b (1981) (“As a general
    rule, a party cannot recover damages for loss that he could have avoided by reasonable efforts.”).
    The obligation to mitigate damages arises “once a party has reason to know that performance by
    the other party will not be forthcoming.” Ind. Mich. Power 
    Co., 422 F.3d at 1375
    (quoting
    Restatement (Second) of Contracts § 350, cmt. b).
    When mitigating damages from a breach, the non-breaching party must “make only
    ‘those efforts that are fair and reasonable under the circumstances.’” First Heights Bank, FSB v.
    United States, 
    422 F.3d 1311
    , 1316 (2005) (quoting Home Sav. of Am.v. United States, 
    399 F.3d 1341
    , 1353 (Fed. Cir. 2005)). It “is not required to make extraordinary efforts to ferret out the
    single best situation which will absolutely minimize the breaching party’s damages. All that is
    required is that the [non-breaching party] act reasonably and promptly given the circumstances.”
    Ketchikan Pulp Co. v. United States, 
    20 Cl. Ct. 164
    , 166 (1990). The breaching party bears the
    burden of proof to show that the non-breaching party failed to take reasonable steps to mitigate
    its damages. T. C. Bateson Const. Co. v. United States, 
    319 F.2d 135
    , 160 (Ct. Cl. 1963).
    As noted above, summary judgment is mandated “after adequate time for discovery and
    upon motion, against a party who fails to make a showing sufficient to establish the existence of
    an element essential to that party’s case, and on which that party will bear the burden of proof at
    trial.” Celotex 
    Corp., 477 U.S. at 322
    . Because TPL bears the burden of proof, in order to avoid
    summary judgment, it must produce evidence sufficient to allow a reasonable fact finder to
    conclude that the government’s mitigation efforts were not fair and reasonable under the
    circumstances. For the reasons set forth below, the Court concludes that TPL has failed to
    produce such evidence. Accordingly, the government is entitled to summary judgment for the
    entire amount that it seeks in its counterclaim.
    A.      Expenditures for security
    TPL challenges as unreasonable the $958,933.09 that the government spent for security.
    Its challenge is based entirely on assertions contained in the declaration of its president, H. M.
    Stoller, that “TPL had previously performed these services in its tenure at Fort Wingate through
    three different contractors in Gallup, NM at a cost of approximately $8,000 per month” and that
    12
    “[i]t was possible with simple competition to obtain these services for a total of approximately
    $100,000.” Stoller Decl. ¶ 27a.
    These bare assertions by Mr. Stoller are unsupported by any specific details or
    documentation. Among other things, Mr. Stoller fails to identify the contractors through whom
    TPL performed security services or explain the precise services that they provided or supply the
    contracts under which those services were provided. Without such documentation or at least a
    detailed explanation, TPL is left with only an unsupported assertion that “[i]t was possible with
    simple competition” for the Army to have secured for only $100,000 the same services for which
    it spent $958,933.09.
    As the court of appeals has observed, “[m]ere conclusory statements and denials do not
    take on dignity by placing them in affidavit form.” Sweats Fashions, Inc. v. Pannill Knitting Co.,
    Inc., 
    833 F.2d 1560
    , 1564 (Fed. Cir. 1987); see also Lathan Co. v. United States, 
    20 Cl. Ct. 122
    ,
    125 (1990) (citing Barmag Barmer Maschinenfabrik AG v. Murata Mach., Ltd., 
    731 F.2d 831
    ,
    836 (Fed. Cir. 1984) (“[B]ald assertions and speculation do not create an evidentiary conflict
    sufficient to defeat a summary judgment motion.”). Mr. Stoller’s bare assertions would not be
    sufficient for a reasonable finder of fact to conclude that the Army’s expenditures for security
    services were excessive or unreasonable. Because it is TPL’s burden to demonstrate the
    unreasonableness of the Army’s mitigation efforts, the government is entitled to summary
    judgment as to the $958,933.09 it spent for security.
    B.      Expenditures for disposal of materials left by TPL
    TPL also challenges as excessive and unreasonable the $7,896,626 that the Army spent to
    modify a pre-existing contract it had with GDOTS to secure other contractors to dispose of the
    hundreds of thousands of pyrotechnic items left at Fort Wingate. Mr. Stoller asserts that TPL
    had obtained a bid from another contractor (Clean Harbors Environmental) to perform the
    majority of this same work for the price of $1,600,000. Stoller Decl. ¶ 27b.6 According to Mr.
    Stoller, TPL “informed the Army of the Clean Harbors bid,” but “Army officials stated that they
    were not concerned with the cost” and so performed the work through a sole source bid. 
    Id. He claims
    that “[f]lares and candles were shipped to the TPL-developed Magnesium Recovery
    Facility at the Crane Army Ammunition Activity, an option denied to TPL.” 
    Id. Mr. Stoller’s
    affidavit is again inadequate to defeat the government’s motion for
    summary judgment. Among other things, it fails to allege specific facts or to provide any
    documentation to support a conclusion that the Clean Harbors bid of $1,600,000 (a copy of
    which was not submitted along with Mr. Stoller’s declaration) was for the same work that the
    Army ultimately enlisted GDOTS to perform.7 In fact, the government has produced copies of
    6
    Mr. Stoller asserts that this contract would have included all but sixteen boxes of too-
    hazardous-to-move materials. Stoller Decl. ¶ 27b.
    7
    The government has submitted what appears to be a spreadsheet that was used by Clean
    Harbors to come up with its quote. That document appears to indicate that the Clean Harbors
    quotation upon which TPL relies here was based on inaccurate assumptions about the weights of
    13
    the quotation TPL secured from another contractor (EBV Explosives Environmental Company)
    that ultimately performed the work for the Army as a subcontractor. Def.’s Reply S.A. 1, 4.
    EBV’s quotation ($7,123,517.21) was significantly higher (by a magnitude of almost 450%) than
    Clean Harbors’ quotation and much closer to the costs the Army actually incurred. 
    Id. at 4.
    Thus, the Court concludes that TPL has failed to raise a genuine issue with respect to the
    reasonableness of the Army’s expenditure of $7,896,626 to dispose of the pyrotechnic materials.
    C.      Expenditures to destroy sixteen boxes of hazardous material
    TPL’s objection to the $1,441,424.15 expense the Army claims it incurred to destroy
    sixteen boxes of material that were unstable and too hazardous to move is similarly inadequate to
    defeat the government’s motion for summary judgment. Mr. Stoller states that TPL “initially
    proposed to perform this task at its own cost and would have used its own on-site explosion
    ordinance disposal personnel,” but that “[t]he Government8 denied permission to TPL to perform
    this action.” Stoller Decl. ¶ 27c. Mr. Stoller’s statement contains no basis for concluding that
    the method that the Army chose to dispose of this material—through a delivery order for a
    contract it had in place with PIKA International, Inc.—was excessive or otherwise unreasonable.
    Thus, the Court concludes that TPL has failed to raise a material factual dispute with respect to
    the reasonableness of the Army’s expenditure of $1,441,424.15 to destroy the sixteen boxes of
    material that were unstable and too hazardous to move.
    D.      Expenditures to inventory and prepare energetic material for shipment to
    disposal sites
    TPL challenges $1,089,534 in costs that the Army incurred for the deployment of the
    MARID team to assess and inventory the energetic material and then to repackage, apply proper
    shipping markings, and palletize the material for the shipment to disposal sites. Mr. Stoller
    asserts that these costs were incurred unnecessarily because TPL had already accurately
    inventoried, packaged, and prepared the material for shipment, including “palletizing” and
    “banding” the material. Stoller Decl. ¶ 27.
    On its face, Mr. Stoller’s assertion is insufficient to raise a genuine issue regarding the
    reasonableness of this expenditure by the Army. Whether or not TPL’s prior inventory had been
    an accurate one, with a new plan in place for transport of energetic material to disposal sites, it
    was self-evidently not unreasonable for the Army to do a new inventory, repackage the material,
    apply new shipping labels and markings, and repalletize the material for shipment. Indeed,
    doing otherwise would have arguably been reckless. Thus, the Court concludes that TPL has
    the materials that would be subject to disposal. See Def.’s Reply, Supplemental Appendix (S.A.)
    at 7 (quote based on assumption that each unit to be disposed of weighs one pound).
    8
    At the oral argument on the government’s motion for summary judgment, counsel for TPL
    clarified that the statement that “the Government denied permission to TPL” to dispose of the
    sixteen boxes on site referred to the New Mexico Environmental Department’s refusal to
    approve TPL’s proposal to destroy the materials in place. Oral Arg. Tr. 6.
    14
    failed to raise a material factual dispute with respect to the reasonableness of the Army’s
    expenditure of $1,089,534 for these purposes.
    E.      Miscellaneous Expenditures
    Finally, TPL concedes that it lacks any evidence to establish the unreasonableness of the
    following government expenditures: (1) $11,860.03 for government travel costs; (2) $16,232.80
    for hazardous waste fees; and (3) $57,276.97 in labor costs. Stoller Decl. ¶¶ 27(e)-(h).
    Accordingly, the government is entitled to summary judgment as to these elements of damages
    as well.
    CONCLUSION
    On the basis of the foregoing, the government’s motion for summary judgment is
    GRANTED. The Clerk of the Court is directed to enter final judgment for the defendant in the
    amount of $11,887,509.72, plus interest, calculated pursuant to section 7109 of the Contract
    Disputes Act.
    IT IS SO ORDERED.
    s/Elaine D. Kaplan
    ELAINE D. KAPLAN
    Judge, U.S. Court of Federal Claims
    15
    

Document Info

Docket Number: 1:11-cv-00482

Citation Numbers: 118 Fed. Cl. 434, 2014 U.S. Claims LEXIS 971, 2014 WL 4628311

Judges: Elaine D. Kaplan

Filed Date: 9/16/2014

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (21)

Massachusetts Bay Transportation Authority v. United States , 254 F.3d 1367 ( 2001 )

Home Savings of America, Fsb v. United States , 399 F.3d 1341 ( 2005 )

Ace Constructors, Inc. v. United States , 499 F.3d 1357 ( 2007 )

Gene Peters v. The United States , 694 F.2d 687 ( 1982 )

GLOPAK CORPORATION, Plaintiff-Appellant, v. the UNITED ... , 851 F.2d 334 ( 1988 )

Hume v. United States , 10 S. Ct. 134 ( 1889 )

Celotex Corp. v. Catrett, Administratrix of the Estate of ... , 106 S. Ct. 2548 ( 1986 )

Anderson v. Liberty Lobby, Inc. , 106 S. Ct. 2505 ( 1986 )

T. C. Bateson Construction Company v. The United States , 319 F.2d 135 ( 1963 )

Roseburg Lumber Company v. Edward R. Madigan, Secretary of ... , 978 F.3d 660 ( 1992 )

First Heights Bank, Fsb, Pulte Diversified Companies, Inc., ... , 422 F.3d 1311 ( 2005 )

Barmag Barmer Maschinenfabrik Ag v. Murata MacHinery Ltd., ... , 731 F.2d 831 ( 1984 )

Seaboard Lumber Company and Capital Development Company v. ... , 308 F.3d 1283 ( 2002 )

Raytheon Company (Doing Business as Raytheon Systems ... , 305 F.3d 1354 ( 2002 )

atlas-corporation-kerr-mcgee-chemical-corporation-quivira-mining-company , 895 F.2d 745 ( 1990 )

Sweats Fashions, Inc. v. Pannill Knitting Company, Inc. , 833 F.2d 1560 ( 1987 )

John H. Dalton, Secretary of the Navy v. Sherwood Van Lines,... , 50 F.3d 1014 ( 1995 )

James T. Robinson and Florida Businessmen's Association, ... , 305 F.3d 1330 ( 2002 )

Indiana Michigan Power Company v. United States , 422 F.3d 1369 ( 2005 )

Gordon R. England, Secretary of the Navy v. The Swanson ... , 353 F.3d 1375 ( 2004 )

View All Authorities »