In re Application of Ohio Power Co. (Slip Opinion) , 140 Ohio St. 3d 509 ( 2014 )


Menu:
  • [Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as In
    re Application of Ohio Power Co., Slip Opinion No. 2014-Ohio-4271.]
    NOTICE
    This slip opinion is subject to formal revision before it is published in
    an advance sheet of the Ohio Official Reports. Readers are requested
    to promptly notify the Reporter of Decisions, Supreme Court of Ohio,
    65 South Front Street, Columbus, Ohio 43215, of any typographical or
    other formal errors in the opinion, in order that corrections may be
    made before the opinion is published.
    SLIP OPINION NO. 2014-OHIO-4271
    IN RE APPLICATION OF OHIO POWER COMPANY TO UPDATE ITS TRANSMISSION
    COST RECOVERY RIDER RATES; INDUSTRIAL ENERGY USERS-OHIO,
    APPELLANT; OHIO POWER COMPANY ET AL., APPELLEES.
    [Until this opinion appears in the Ohio Official Reports advance sheets,
    it may be cited as In re Application of Ohio Power Co.,
    Slip Opinion No. 2014-Ohio-4271.]
    Public utilities—Transmission cost recovery rider—R.C. 4928.144(A)(2)—
    Transmission costs recovery rider—Public Utilities Commission order
    permitting utility to recoup underrecovered transmission costs from all
    customers over three years on nonbypassable basis not unlawful or
    unreasonable—Order did not constitute impermissible retroactive
    ratemaking—Collection on nonbypassable basis not unauthorized—
    Orders affirmed.
    (No. 2013-0154—Submitted July 9, 2014—Decided October 7, 2014.)
    APPEAL from the Public Utilities Commission, No. 12-1046-EL-RDR.
    ____________________
    SUPREME COURT OF OHIO
    KENNEDY, J.
    SUMMARY
    {¶ 1} In the case below, the commission authorized the Ohio Power
    Company to recover costs associated with providing transmission service to its
    standard-service-offer customers (those who take generation service from the
    incumbent distribution utility instead of buying it on the market). The cost of
    transmission service is set by the Federal Energy Regulatory Commission
    (“FERC”). Under Ohio law, electric-distribution utilities are allowed to recover
    from their retail customers all transmission-related costs imposed on the utility by
    FERC or by an organization approved by FERC. R.C. 4928.05(A)(2). Ohio
    Power recovers these costs through a reconciling rate mechanism called the
    Transmission Cost Recovery Rider (“TCRR”).           Ohio Adm.Code 4901:1-36-
    03(A). The commission annually reviews and adjusts the TCRR to ensure that the
    utility is recovering only its actual costs of providing the service.         Ohio
    Adm.Code 4901:1-36-03(B). By commission rule, shopping customers—those
    who shop for electric service from a competitive supplier—bypass the TCRR and
    thus avoid having to pay the rider. Ohio Adm.Code 4901:1-36-04(B).
    {¶ 2} During the period under review in this case, Ohio Power reported
    that it had underrecovered $36 million in transmission costs. The commission’s
    order determined that Ohio Power could collect the underrecovered costs from
    both shopping and nonshopping customers. The commission found that a large
    percentage of shopping customers who were receiving transmission service from
    Ohio Power at the time the underrecovery was created had since decided to take
    service from an alternative generation provider.        Although these shopping
    customers would normally be able to avoid paying the TCRR, the commission
    reasoned that it would be unfair to require nonshopping customers to shoulder the
    entire burden of paying for the underrecovery, since the underrecovery was
    caused in part by these shopping customers.
    2
    January Term, 2014
    {¶ 3} Industrial Energy Users-Ohio (“IEU”) challenges the commission’s
    decision to allow the company to recover the underrecovered transmission costs
    from shopping customers. For the reasons discussed in detail below, we affirm
    the commission.
    FACTS AND PROCEDURAL BACKGROUND
    {¶ 4} Since competition began in the provision of electric-generation
    service, the law has required incumbent electric-distribution utilities to transfer
    control of their transmission assets to “one or more qualifying transmission
    entities.” R.C. 4928.12(A). On October 1, 2004, Ohio Power transferred control
    of its transmission assets to PJM Interconnection, L.L.C., one of six regional
    power grids regulated by FERC.1                 PJM, a qualifying entity under R.C.
    4928.12(B)(1), now coordinates and directs the operation of Ohio Power’s
    transmission network.
    {¶ 5} Ohio Power, as a member of PJM, is charged for securing
    transmission service through the organization. Currently, PJM bills Ohio Power
    based on rates set by FERC for transmission service associated with serving the
    company’s customer load. In turn, Ohio law permits Ohio Power (and all other
    electric-distribution utilities) to recover from the utility’s retail customers the
    FERC-approved transmission charges billed by PJM.                       R.C. 4928.05(A)(2)
    (allowing      electric distribution utilities to recover “all transmission and
    transmission-related costs * * * imposed on or charged to the utility by * * * a
    regional transmission organization * * * approved by” FERC). This provision
    authorizes the commission to provide for recovery through a “reconcilable rider”
    added to the electric utility’s distribution rates. 
    Id. 1 PJM
    is a multiutility transmission organization designated by FERC to coordinate the movement
    of wholesale electricity in all or part of 13 states—including Ohio—and the District of Columbia.
    See generally Ohio Consumers’ Counsel v. Pub. Util. Comm., 
    111 Ohio St. 3d 384
    , 2006-Ohio-
    5853, 
    856 N.E.2d 940
    , ¶ 5-6.
    3
    SUPREME COURT OF OHIO
    {¶ 6} Consistent with this statutory provision, Ohio Power asked the
    commission to approve the TCRR to recover such costs as part of the company’s
    first Electric Security Plan (“ESP”). The commission approved the TCRR as
    proposed by the company. See In re Application of Columbus S. Power Co. for
    Approval of Elec. Sec. Plan, Pub. Util. Comm. Nos. 08-917-EL-SSO and 08-918-
    EL-SSO, 49-50 (Mar. 18, 2009). The TCRR was then carried over as part of
    Ohio Power’s second and current ESP, covering 2012 through 2014. See Pub.
    Util. Comm. Nos. 11-346-EL-SSO, 5, 63-64 (Aug. 8, 2012).
    {¶ 7} The TCRR is structured as a pass-through mechanism, meaning that
    it is designed so that Ohio Power can recover the same amount in transmission
    costs from its customers as the amount billed by PJM. Once a year Ohio Power
    projects the amount of transmission costs it expects to be billed by PJM, and those
    costs are used as a revenue requirement to calculate the TCRR rate over the next
    12-month period.     Because the costs included in the TCRR are based on
    projections that will vary from actual costs, the TCRR contains a true-up
    mechanism to reconcile any over- or underrecovered charges from the preceding
    12-month period.
    {¶ 8} Pursuant to Ohio Adm.Code 4901:1-36-03(B), Ohio Power files an
    application each year with the commission to update the rates charged under the
    TCRR and to reconcile any over- or underrecoveries stemming from the prior
    period. R.C. 4928.05(A)(2) and Ohio Adm.Code 4901:1-36-03(B). This case
    began when Ohio Power filed an application with the commission to update the
    TCRR rates for the period from September 2012 through August 2013. The
    application reflected that Ohio Power’s TCRR had failed to recover enough
    revenue to recoup the costs that Ohio Power incurred to provide transmission
    service during the period of July 2011 through June 2012.
    {¶ 9} The    amount     of   underrecovered     transmission   costs    was
    approximately $36 million. According to Ohio Power, these underrecovered costs
    4
    January Term, 2014
    were caused primarily by (1) the difference between the costs projected in the
    company’s most recent TCRR update case and the actual costs incurred to provide
    transmission service over that period (i.e., transmission charges billed to Ohio
    Power by PJM from July 2011 through June 2012) and (2) a substantial increase
    (from less than 10 percent to nearly 40 percent) in the number of customers in
    Ohio Power’s service territory shopping for generation service.
    {¶ 10} Ohio Power would normally recoup any underrecovered amounts
    through the TCRR over the next 12-month period. But to mitigate the impact of
    the rate increase on customers, Ohio Power proposed to collect the underrecovery
    balance with carrying charges over a three-year period. By commission rule, the
    TCRR is imposed on Ohio Power’s standard-service-offer customers since these
    customers are the ones who were provided the transmission service.                   Ohio
    Adm.Code 4901:1-36-04(B). Therefore, customers can avoid paying the TCRR
    by choosing to shop for generation service from a competitive supplier.2 Ohio
    Power proposed that the rate impact could be further mitigated by collecting the
    underrecovered costs from all customers (shopping and nonshopping) pursuant to
    R.C. 4928.144.
    {¶ 11} As an initial matter, the commission determined that it was not
    necessary to hold an evidentiary hearing in the case. In re Application of Ohio
    Power Co. to Update the Co.’s Transmission Cost Recovery Rider, Pub. Util.
    Comm. No. 12-1046-EL-RDR, 6 (Oct. 24, 2012) (the “TCRR Order”). The
    commission has discretion under Ohio Adm.Code 4901:1-36-05 to decide
    2
    Customers who shop do not have to pay the TCRR to Ohio Power, Ohio Adm.Code 4901:1-36-
    04(B), but they do not entirely avoid paying transmission costs. Shopping customers pay for
    transmission service through their new contracts with competitive suppliers.
    5
    SUPREME COURT OF OHIO
    whether a hearing on the application is necessary.3 No party challenged the
    commission’s decision not to conduct a hearing.4
    {¶ 12} As to the merits, the commission’s opinion and order approved
    Ohio Power’s proposed TCRR rates for the next annual period. The commission
    also agreed with Ohio Power that it was necessary to minimize the rate impact
    that would otherwise occur if Ohio Power were to collect $36 million in
    transmission costs in just one year. The commission therefore ordered Ohio
    Power to collect the underrecovered transmission costs over a three-year period,
    with carrying costs. The commission also found that it was unfair to require
    nonshopping customers to shoulder the entire burden of paying for the
    underrecovery since the underrecovery was caused in part by customers who were
    now shopping but who had received transmission service from Ohio Power at the
    time the underrecovery was created. To that end, the commission ordered that
    Ohio Power should collect the underrecovered balance from all customers
    (shopping and nonshopping) and authorized Ohio Power to establish a separate,
    nonbypassable charge until those costs were fully collected. TCRR Order at 7.
    {¶ 13} IEU timely applied for rehearing, which was denied.                        In re
    Application of Ohio Power Co. to Update its Transmission Cost Recovery Rider
    Rates, Pub. Util. Comm. No. 12-1046-EL-RDR (Dec. 12, 2012) (“TCRR
    3
    The rule provides that “[u]nless otherwise ordered, * * * the commission shall approve the
    application or set the matter for hearing within seventy-five days after the filing of a complete
    application” to recover transmission costs. The commission did not rule on the application within
    75 days because the attorney examiner suspended the deadline in order to give the commission’s
    staff additional time to review Ohio Power’s application. TCRR Order at 2.
    4
    IEU states in its reply brief that there is no evidence in the record as to what caused the
    underrecovery balance because the commission did not conduct an evidentiary hearing in this
    matter. IEU has forfeited any arguments that the commission’s order lacked record support. We
    have jurisdiction only over arguments raised on rehearing before the commission, and IEU never
    challenged the commission’s refusal to conduct an evidentiary hearing in an application for
    rehearing. See R.C. 4903.10; Office of Consumers’ Counsel v. Pub. Util. Comm., 
    70 Ohio St. 3d 244
    , 247, 
    638 N.E.2d 550
    (1994).
    6
    January Term, 2014
    Rehearing Entry”).      IEU then filed the instant appeal challenging the
    commission’s orders.
    STANDARD OF REVIEW
    {¶ 14} “R.C. 4903.13 provides that a PUCO order shall be reversed,
    vacated, or modified by this court only when, upon consideration of the record,
    the court finds the order to be unlawful or unreasonable.”          Constellation
    NewEnergy, Inc. v. Pub. Util. Comm., 
    104 Ohio St. 3d 530
    , 2004-Ohio-6767, 
    820 N.E.2d 885
    , ¶ 50. We will not reverse or modify a PUCO decision as to questions
    of fact where the record contains sufficient probative evidence to show that the
    commission’s decision was not manifestly against the weight of the evidence and
    was not so clearly unsupported by the record as to show misapprehension,
    mistake, or willful disregard of duty. Monongahela Power Co. v. Pub. Util.
    Comm., 
    104 Ohio St. 3d 571
    , 2004-Ohio-6896, 
    820 N.E.2d 921
    , ¶ 29.              The
    appellant bears the burden of demonstrating that the commission’s decision is
    against the manifest weight of the evidence or is clearly unsupported by the
    record. 
    Id. {¶ 15}
    Although we have “complete and independent power of review as
    to all questions of law” in appeals from the PUCO, Ohio Edison Co. v. Pub. Util.
    Comm., 
    78 Ohio St. 3d 466
    , 469, 
    678 N.E.2d 922
    (1997), we may rely on the
    expertise of a state agency in interpreting a law when “highly specialized issues”
    are involved and when “agency expertise would, therefore, be of assistance in
    discerning the presumed intent of our General Assembly.” Consumers’ Counsel
    v. Pub. Util. Comm., 
    58 Ohio St. 2d 108
    , 110, 
    388 N.E.2d 1370
    (1979).
    DISCUSSION
    {¶ 16} IEU challenges the order on three grounds: (1) the commission
    engaged in unlawful retroactive ratemaking, (2) the commission erred in relying
    on R.C. 4928.144 to authorize the recovery of costs on a nonbypassable basis, and
    (3) the commission failed to follow precedent. After review, we find that none of
    7
    SUPREME COURT OF OHIO
    these grounds has merit. We address IEU’s propositions of law out of order for
    ease of discussion.
    I. IEU’s Proposition of Law No. 2: The commission cannot rely on its phase-
    in authority under R.C. 4928.144 to authorize Ohio Power to collect the
    underrecovery balance on a nonbypassable basis
    {¶ 17} In its second proposition of law, IEU argues that the commission
    erred when it relied on its statutory phase-in authority to allow the collection of
    Ohio Power’s underrecovered transmission costs on a nonbypassable basis. The
    statute at issue here is R.C. 4928.144, which provides:
    The public utilities commission by order may authorize any just
    and reasonable phase-in of any electric distribution utility rate or
    price established under sections 4928.141 to 4928.143 of the
    Revised Code * * * as the commission considers necessary to
    ensure rate or price stability for consumers. If the commission’s
    order includes such a phase-in, the order also shall provide for the
    creation of regulatory assets pursuant to generally accepted
    accounting principles, by authorizing the deferral of incurred costs
    equal to the amount not collected, plus carrying charges on that
    amount. Further, the order shall authorize the collection of those
    deferrals through a nonbypassable surcharge on any such rate or
    price so established for the electric distribution utility by the
    commission.
    {¶ 18} IEU raises three arguments under the second proposition: (1) the
    commission could not utilize R.C. 4928.144 in the underlying TCRR proceedings
    because any phase-in under the statute must be authorized in a standard-service-
    offer proceeding, (2) even if R.C. 4928.144 could be utilized in the TCRR
    8
    January Term, 2014
    proceedings, the commission did not rely on the statute to authorize the recovery
    of the TCRR, and (3) the commission could not authorize recovery of the TCRR
    on a nonbypassable basis because the TCRR was not a rate or price established
    under R.C. 4928.143. We address each argument in turn.
    A. The plain language of R.C. 4928.144 does not support IEU’s argument
    that the statute applies only to standard-service-offer proceedings
    {¶ 19} IEU first argues that the commission’s phase-in authority under
    R.C. 4928.144 could not be invoked in the underlying TCRR proceedings. In
    IEU’s view, the commission can invoke its phase-in authority only in the same
    proceeding that establishes the utility’s standard service offer, the rate charged to
    customers who take generation service from the utility instead of a competitive
    supplier. See R.C. 4928.141(A) (requiring electric distribution utilities to provide
    a standard service offer). Because Ohio Power has chosen to provide its standard
    service offer in the form of an electric-security plan, IEU asserts that the
    commission could phase in rates only in the orders approving the company’s
    electric-security plans. See R.C. 4928.143(A) (“For the purpose of complying
    with section 4928.141 of the Revised Code, the electric distribution utility may
    file an application for public utilities commission approval of an electric security
    plan * * *”).
    {¶ 20} We begin our analysis of this issue with the language of the statute.
    See e.g., State v. Hanning, 
    89 Ohio St. 3d 86
    , 91, 
    728 N.E.2d 1059
    (2000).
    {¶ 21} R.C. 4928.144 provides that “[t]he public utilities commission by
    order may authorize any just and reasonable phase-in of any electric distribution
    utility rate or price established under sections 4928.141 to 4928.143 of the
    Revised Code * * *.” (Emphasis added.) IEU interprets the italicized language as
    limiting the exercise of the commission’s authority to the proceedings that
    established the rate or price. IEU contends that because the commission did not
    invoke its phase-in authority during Ohio Power’s ESP proceedings, when rates
    9
    SUPREME COURT OF OHIO
    and prices were established under R.C. 4928.143, it could not phase in those rates
    or prices in any subsequent proceeding.
    {¶ 22} R.C. 4928.144 does limit the commission’s authority.             The
    commission may phase in only those rates and prices that are established under
    R.C. 4928.141 to 4928.143.         It also requires that the phase-in be “just and
    reasonable.” The statute, however, says nothing about when the commission may
    invoke its phase-in authority. The error in IEU’s argument is that it interprets the
    statute as though it included the italicized words:
    {¶ 23} The public utilities commission by order under sections 4928.141
    to 4928.143 of the Revised Code may authorize any just and reasonable phase-in
    of any electric distribution utility rate or price.
    {¶ 24} But R.C. 4928.144 simply does not read that way. In construing a
    statute, a court may not add or delete words. State ex rel. Cincinnati Bell Tel. Co.
    v. Pub. Util. Comm., 
    105 Ohio St. 3d 177
    , 2005-Ohio-1150, 
    824 N.E.2d 68
    , ¶ 32.
    {¶ 25} The statute imposes few other restrictions on the commission’s
    authority over the design of the phase-in. R.C. 4928.144 allows the commission
    to “authorize any just and reasonable phase-in” of electric-security-plan rates “as
    the commission considers necessary to ensure rate or price stability for
    consumers.” While the end result must be “just and reasonable,” the emphasized
    language grants the commission considerable discretion to determine if and when
    to phase in rates. See In re Application of Columbus S. Power Co., 129 Ohio
    St.3d 568, 2011-Ohio-4129, 
    954 N.E.2d 1183
    , ¶ 10. See also Payphone Assn. of
    Ohio v. Pub. Util. Comm., 
    109 Ohio St. 3d 453
    , 2006-Ohio-2988, 
    849 N.E.2d 4
    ,
    ¶ 25 (“When a statute does not prescribe a particular formula, the PUCO is vested
    with broad discretion”).
    {¶ 26} IEU, then, is challenging a judgment call, but it has not come close
    to showing an abuse of discretion. Notably, IEU focuses solely on the phrase
    “rate or price established under sections 4928.141 to 4928.143 of the Revised
    10
    January Term, 2014
    Code,” yet never discusses it in context. Context matters, and at no point does
    IEU identify any language in the statute that imposes timing limitations.
    {¶ 27} In the end, IEU’s interpretation fails on the plain language of the
    statute. The statutory language not only supports the commission’s reading, but
    no other part of the statute expressly contradicts it.         The commission’s
    interpretation of R.C. 4928.144—that it allows the commission to invoke its
    phase-in authority outside of standard-service-offer proceedings—is reasonable.
    And given that this statute implicates a matter of rate design, we defer to the
    commission’s reasonable interpretation. See Consumers’ Counsel v. Pub. Util.
    Comm., 
    10 Ohio St. 3d 49
    , 50, 
    461 N.E.2d 303
    (1984) (the setting of a “phase-in
    period” in which to recover certain expenses “is clearly within the discretionary
    purview of the commission”); Consumers’ Counsel v. Pub. Util. Comm., 
    125 Ohio St. 3d 57
    , 2010-Ohio-134, 
    926 N.E.2d 261
    , ¶ 20 (commission possesses
    “broad discretion” to design rates); Citywide Coalition for Util. Reform v. Pub.
    Util. Comm., 
    67 Ohio St. 3d 531
    , 534, 
    620 N.E.2d 832
    (1993) (“We have afforded
    the commission considerable discretion in matters of rate design * * *”).
    B. The commission properly invoked R.C. 4928.144
    {¶ 28} IEU next argues that the commission failed to state that it relied on
    R.C. 4928.144 to authorize Ohio Power to recoup the underrecovered TCRR
    balance on a nonbypassable basis.      And, according to IEU, the commission
    repeated this error on rehearing when instead of stating that it had invoked its
    phase-in authority under R.C. 4928.144, it merely “stated that the TCRR Order
    was ‘consistent with the Commission’s authority under Section 4928.144,
    Revised Code.’ ” This argument lacks merit for two reasons.
    {¶ 29} First, the commission by clear implication did rely on R.C.
    4928.144. In the initial order, the commission approved Ohio Power’s application
    to update its TCRR, which included the proposal to phase in rates on a
    nonbypassable basis pursuant to R.C. 4928.144. In doing so, the commission
    11
    SUPREME COURT OF OHIO
    rejected IEU’s argument that R.C. 4928.144 was inapplicable and therefore could
    not serve as a basis for making the TCRR nonbypassable. TCRR Order at 7. The
    commission also specifically noted that the TCRR had been approved in each of
    Ohio Power’s ESP proceedings, in reference to the requirement under R.C.
    4928.144 that the phased-in “rate or price [be] established under sections
    4928.141 to 4928.143 of the Revised Code.” TCRR Order at 7.
    {¶ 30} Moreover, even leaving aside the commission’s initial order, the
    commission expressly stated on rehearing that a phase-in of the recovery of the
    underrecovered TCRR balance is appropriate under R.C. 4928.144, that it was
    proper to apply R.C. 4928.144 under the circumstances of this case, and that the
    conditions in R.C. 4928.144 for phasing in rates had been met.       See TCRR
    Rehearing Entry at 4, 8-9.
    {¶ 31} Second, IEU overlooks a basic point of procedure that is necessary
    to reverse a commission order: this court “will not reverse an order of the
    commission absent a showing of prejudice by the party seeking reversal.” Myers
    v. Pub. Util. Comm., 
    64 Ohio St. 3d 299
    , 302, 
    595 N.E.2d 873
    (1992). See also
    Parma v. Pub. Util. Comm., 
    86 Ohio St. 3d 144
    , 149, 
    712 N.E.2d 724
    (1999); and
    Ohio Commt. of Cent. Station Elec. Protection Assn. v. Pub. Util. Comm., 50 Ohio
    St.2d 169, 174, 
    364 N.E.2d 3
    (1977). Moreover, IEU does not even attempt to
    show how it or its constituents suffered harm from the commission’s failure to
    expressly rely on R.C. 4928.144 in the orders below.
    {¶ 32} In sum, IEU failed to show reversible error. We therefore reject
    this argument.
    C. IEU’s argument regarding R.C. 4928.143 lacks a coherent legal theory
    {¶ 33} Finally, IEU argues that the commission cannot authorize recovery
    of the TCRR on a nonbypassable basis because the TCRR was not a “rate or price
    established under sections 4928.141 to 4928.143 of the Revised Code,” as
    required by R.C. 4928.144. The commission found that the TCRR was approved
    12
    January Term, 2014
    as part of Ohio Power’s first and second electric-security plans, consistent with
    R.C. 4928.143.       IEU challenges that determination, contending that the
    commission did not rely on R.C. 4928.143 when it authorized the TCRR. Rather,
    IEU claims that the commission authorized the TCRR under R.C. 4928.05. IEU
    has again failed to demonstrate reversible error.
    {¶ 34} R.C. 4928.143 governs electric-security plans (“ESPs”) and the
    types of rate components that may be included in such plans.                     R.C.
    4928.143(B)(2)(g) provides that an ESP may include “[p]rovisions relating to
    transmission * * * service required for the standard service offer, including
    provisions for the recovery of any cost of such service that the electric distribution
    utility incurs * * * pursuant to the standard service offer.”          In 2009, the
    commission approved a TCRR mechanism as a part of the company’s ESP. See
    Pub. Util. Comm. No. 08-918-EL-SSO, 49-50 (Mar. 18, 2009). In Ohio Power’s
    second ESP case, covering the time period from 2012 through 2014, the
    commission approved the current version of the TCRR. See Pub. Util. Comm.
    No. 11-348-EL-SSO, 63-64 (Aug. 8, 2012).
    {¶ 35} IEU does not dispute that R.C. 4928.143 allows Ohio Power to
    include a TCRR mechanism in the company’s ESP. Nor does it claim that the
    commission failed to approve the TCRR in the company’s ESP proceedings. Its
    only complaint is that the commission did not expressly rely on R.C. 4928.143
    when it approved the TCRR in the ESP orders. It is true that the commission did
    not mention R.C. 4928.143 in approving the TCRR in either ESP case. Even so,
    IEU does not explain why it was necessary to do so in light of the commission’s
    clear authority under R.C. 4928.143 to approve a TCRR mechanism as part of an
    ESP. IEU’s failure to offer a coherent legal theory is grounds for rejecting its
    argument. See, e.g., In re Complaint of Wilkes v. Ohio Edison Co., 131 Ohio
    St.3d 252, 2012-Ohio-609, 
    963 N.E.2d 1285
    , ¶ 10; Util. Serv. Partners, Inc. v.
    Pub. Util. Comm., 
    124 Ohio St. 3d 284
    , 2009-Ohio-6764, 
    921 N.E.2d 1038
    , ¶ 53.
    13
    SUPREME COURT OF OHIO
    II. IEU’s Proposition of Law No. 3: Without a lawful and reasonable
    justification for its change of direction, the commission departed from
    commission precedent requiring that the TCRR remain fully bypassable
    {¶ 36} In its third proposition of law, IEU argues that the commission
    declined to follow precedent, namely, In re Application of Duke Energy Ohio, Inc.
    for Approval of a Market Rate Offer, Pub. Util. Comm. No. 10-2586-EL-SSO
    (Feb. 23, 2011). IEU maintains that the commission established the following
    precedent in Duke: reconcilable riders (such as the TCRR) that are originally
    avoidable by shopping customers must remain so and can never be collected from
    shopping customers. We disagree.
    {¶ 37} The rider at issue in Duke—Rider SCR—was designed to be
    avoidable for customers taking generation service from a competitive supplier.
    Duke had proposed to make the rider unavoidable to such customers if amounts
    underrecovered through the rider reached a certain threshold. The commission
    rejected Duke’s proposal with the following statement:
    In considering Duke’s request to include a “circuit breaker”
    provision in Rider SCR, the Commission does not believe that
    such a provision would advance the policy of the state as
    articulated in Section 4928.02, Revised Code. Specifically, [R.C.
    4928.02(H)] provides that it is the policy of the state to avoid
    anticompetitive subsidies flowing from a noncompetitive retail
    electric service to a competitive retail electric service and vice
    versa. If Duke were permitted to recover the costs included in
    Rider SCR from shopping customers, under any circumstances, we
    believe that it would create an anticompetitive subsidy. * * *
    Accordingly, the Commission does not believe that Rider SCR
    could be approved as a potentially unavoidable charge.
    14
    January Term, 2014
    Pub. Util. Comm. No. 10-2586-EL-SSO, at 63-64.
    {¶ 38} According to IEU, the commission held in Duke that a true-up of a
    bypassable rider cannot be collected on a nonbypassable basis “ ‘under any
    circumstances.’ ” But IEU’s selective reading of the quoted passage from the
    Duke order gives a misleading impression of what the case stands for. As can be
    gleaned from reading the entire excerpt in context, the commission did not hold
    that a reconcilable rider that was originally made bypassable can never be
    collected from shopping customers under any circumstances.         Rather, the
    commission merely held that Duke could not collect Rider SCR (which was
    proposed as a bypassable rider) from shopping customers under any
    circumstances, because to do so would create an anticompetitive subsidy. In
    short, the commission did not depart from precedent in the case below because
    Duke never established the precedent that IEU alleges.     We therefore reject
    proposition of law No. 3.
    III. Proposition of Law No. 1: The commission engaged in retroactive
    ratemaking when it authorized the collection of the TCRR under-recovery
    balance on a nonbypassable basis
    {¶ 39} IEU argues in proposition of law No. 1 that the commission
    engaged in unlawful retroactive ratemaking when it allowed Ohio Power to
    collect under-recovered transmission costs from shopping customers. IEU asserts
    that the commission’s TCRR Order is unlawful because it makes shopping
    customers—who avoided paying the TCRR before the order—retroactively
    responsible for paying transmission costs that Ohio Power had incurred to serve
    nonshopping customers. For the reasons that follow, we find that the commission
    did not engage in unlawful retroactive ratemaking.
    15
    SUPREME COURT OF OHIO
    A. R.C. 4928.144 authorized the commission to defer the collection
    of the TCRR, and the statute mandates that deferrals be collected
    through a nonbypassable surcharge
    {¶ 40} IEU concedes that Ohio Power is entitled to recover the $36
    million in underrecovered transmission costs. IEU, however, maintains that the
    commission engaged in unlawful retroactive ratemaking when it allowed Ohio
    Power to collect these underrecovered costs from shopping customers. IEU states
    that before the TCRR Order, shopping customers were not responsible to Ohio
    Power for any transmission costs, and only nonshopping customers were required
    to pay the TCRR. According to IEU, the rule against retroactive ratemaking
    prohibits the commission from authorizing Ohio Power to collect the
    underrecovered transmission costs through a nonbypassable charge, because use
    of this mechanism imposes revenue responsibility on shopping customers for
    unrecovered costs incurred to serve nonshopping customers.
    {¶ 41} It is true that before the TCRR Order, shopping customers were not
    required to pay the TCRR. But the commission’s decision to allow Ohio Power
    to collect the underrecovered transmission costs from shopping customers was not
    unlawful retroactive ratemaking. R.C. 4928.144 authorizes the commission to
    phase in rates or prices established in an electric-security plan, and it plainly gives
    the commission discretion over the design of the phase-in. Specifically, R.C.
    4928.144 allows the commission to “authorize any just and reasonable phase-in of
    any electric distribution utility rate * * * as the commission considers necessary
    to ensure rate or price stability for consumers.” (Emphasis added.) Ohio Power
    would normally recoup any underrecovered amounts through the TCRR over the
    next 12-month period (here, from September 2012 through August 2013). In
    order to mitigate the impact of the rate increase on customers, the commission
    authorized Ohio Power to collect the shortfall over three years instead of one year.
    Once the commission determined that it was necessary to phase in the recovery of
    16
    January Term, 2014
    the shortfall over three years, R.C. 4928.144 required that the commission order
    the collection of deferred rates “through a nonbypassable surcharge on any such
    rate.” In short, even if the commission’s TCRR Order did amount to retroactive
    ratemaking, it was not unlawful because the commission had statutory authority to
    phase in the collection of rates through a nonbypassable surcharge.
    {¶ 42} For its part, IEU has not shown an abuse of discretion. IEU’s only
    arguments against the commission’s use of its phase-in authority under R.C.
    4928.144 are found in the second proposition of law, which we have already
    rejected, and there is no need to discuss those issues again. The commission is a
    creature of statute and can exercise only the authority conferred upon it by the
    General Assembly. Tongren v. Pub. Util. Comm., 
    85 Ohio St. 3d 87
    , 88, 
    706 N.E.2d 1255
    (1999). In the end, IEU has not shown that the commission’s
    exercise of its statutory phase-in authority was unlawful or unreasonable.
    B. IEU’s remaining arguments under its first proposition
    of law do not compel reversal
    {¶ 43} IEU raises two other arguments under proposition of law No. 1.
    One has been forfeited; the other lacks merit.
    1. IEU’s claim regarding the 2011 TCRR Order was not presented
    to the commission on rehearing
    {¶ 44} IEU argues that the commission violated the prohibition against
    retroactive ratemaking because the commission’s order in Ohio Power’s 2011
    TCRR case failed to include any mechanism to shift revenue responsibility to
    shopping customers. See In re Application of Ohio Power Co. to Update the
    Co.’s Transmission Cost Recovery Rider, Pub. Util. Comm. No. 11-2473-EL-
    RDR (June 22, 2011) (the “2011 TCRR Order”).              The 2011 TCRR Order
    implemented the rates that led to the $36 million underrecovery at issue in this
    case.     According to IEU, the commission was required to approve the
    17
    SUPREME COURT OF OHIO
    nonbypassable charge in the 2011 TCRR Order in order to avoid the proscription
    against retroactive ratemaking.
    {¶ 45} IEU has forfeited this argument by failing to present it to the
    commission in an application for rehearing. That jurisdictionally bars us from
    considering the claim. R.C. 4903.10; Office of Consumers’ Counsel v. Pub. Util.
    Comm., 
    70 Ohio St. 3d 244
    , 247, 
    638 N.E.2d 550
    (1994) (“setting forth specific
    grounds for rehearing is a jurisdictional prerequisite for our review”).
    2. Lost revenue due to regulatory delay is not at issue
    {¶ 46} IEU also argues that the commission was wrong in finding that the
    under-recovery balance did not result from revenue lost due to regulatory delay.
    IEU asserts that the underrecovered transmission costs were the function of the
    delay inherent in the TCRR review process. According to IEU, the underrecovery
    balance resulted from revenue that Ohio Power was unable to collect from
    nonshopping customers during the prior annual review period. Therefore, IEU
    asserts that the commission violated the rule against retroactive ratemaking when
    it adjusted rates in the TCRR Order to allow Ohio Power to retroactively recover a
    portion of those costs from shopping customers.
    {¶ 47} Contrary to IEU’s contention, the TCRR Order does not
    compensate Ohio Power for revenues lost during the pendency of the
    commission’s proceedings. See In re Application of Columbus S. Power Co., 
    128 Ohio St. 3d 512
    , 2011-Ohio-1788, 
    947 N.E.2d 655
    , ¶ 11 (making up for revenues
    lost due to regulatory delay is precisely the sort of rate increase that the court
    ruled out in Keco Industries, Inc. v. Cincinnati & Suburban Bell Tel. Co., 
    166 Ohio St. 254
    , 
    141 N.E.2d 465
    (1957)). To begin with, R.C. 4928.05 uses a
    retrospective approach to cost recovery and thus differs from a traditional
    ratemaking statute that sets rates prospectively. Specifically, R.C. 4928.05(A)(2)
    guarantees that the utility will recover transmission costs imposed by FERC or by
    a FERC-approved organization, and it does so through the use of a reconcilable
    18
    January Term, 2014
    rider (the commission may “provide for the recovery, through a reconcilable rider
    on * * * distribution rates, of all transmission and transmission-related costs”
    imposed by FERC and others). The TCRR Order had no impact on Ohio Power’s
    ability to recoup the entire $36 million underrecovery. Rather, the commission’s
    only concern was whether Ohio Power would recover those costs from
    nonshopping customers only or from both shoppers and nonshoppers. In short,
    this is not a case where the commission altered present rates to make up for
    dollars lost “ ‘during the pendency of commission proceedings.’ ”          In re
    Application of Columbus S. Power Co., at ¶ 11, quoting Lucas Cty. Commrs. v.
    Pub. Util. Comm., 
    80 Ohio St. 3d 344
    , 348, 
    686 N.E.2d 501
    (1997). Revenue lost
    due to regulatory delay is simply not at issue here.
    CONCLUSION
    {¶ 48} IEU has the burden of demonstrating that the commission’s orders
    were unjust, unreasonable, or unlawful. R.C. 4903.13; AT & T Communications
    of Ohio, Inc. v. Pub. Util. Comm., 
    51 Ohio St. 3d 150
    , 154, 
    555 N.E.2d 288
    (1990). IEU has not carried that burden in this appeal. Therefore, we affirm the
    commission’s orders.
    Orders affirmed.
    O’CONNOR, C.J., and PFEIFER, O’DONNELL, LANZINGER, FRENCH, and
    O’NEILL, JJ., concur.
    ____________________
    McNees, Wallace & Nurick, L.L.C., Samuel C. Randazzo, Frank P. Darr,
    and Matthew R. Pritchard, for appellant.
    Steven T. Nourse, Matthew J. Satterwhite, and Yazen Alami, for appellee
    Ohio Power Company.
    19
    SUPREME COURT OF OHIO
    Michael DeWine, Attorney General, and William L. Wright and Thomas
    W. McNamee, Assistant Attorneys General, for appellee Public Utilities
    Commission of Ohio.
    _________________________
    20
    

Document Info

Docket Number: 2013-0154

Citation Numbers: 2014 Ohio 4271, 140 Ohio St. 3d 509

Judges: Kennedy, O'Connor, Pfeifer, O'Donnell, Lanzinger, French, O'Neill

Filed Date: 10/7/2014

Precedential Status: Precedential

Modified Date: 10/19/2024