K-Con Building Systems, Inc. v. United States , 778 F.3d 1000 ( 2015 )


Menu:
  •   United States Court of Appeals
    for the Federal Circuit
    ______________________
    K-CON BUILDING SYSTEMS, INC.,
    Plaintiff-Appellant
    v.
    UNITED STATES,
    Defendant-Appellee
    ______________________
    2014-5062
    ______________________
    Appeal from the United States Court of Federal
    Claims in No. 1:05-cv-01054-MMS, Judge Margaret M.
    Sweeney.
    ______________________
    Decided: February 12, 2015
    ______________________
    WILLIAM ATKINS SCOTT, Pederson & Scott, P.C.,
    Charleston, SC, argued for plaintiff-appellant.
    DANIEL B. VOLK, Commercial Litigation Branch, Civil
    Division, United States Department of Justice, Washing-
    ton, DC, argued for defendant-appellee. Also represented
    by STUART F. DELERY, ROBERT E. KIRSCHMAN, JR., BRYANT
    G. SNEE.
    ______________________
    Before PROST, Chief Judge, NEWMAN and TARANTO, Cir-
    cuit Judges.
    2                         K-CON BUILDING SYSTEMS, INC.   v. US
    TARANTO, Circuit Judge.
    K-Con Building Systems, Inc., entered into a contract
    with the federal government to construct a building for
    the Coast Guard. Once K-Con finished, the government
    imposed liquidated damages for delay in completion. K-
    Con sued in the Court of Federal Claims, seeking two
    forms of relief. First, it requested remission of the liqui-
    dated damages on two grounds—that the contract’s
    liquidated-damages clause was unenforceable and that K-
    Con was entitled to an extension of the completion date.
    Second, it requested additional compensation based on
    work performed in response to government requests that
    K-Con alleges amounted to contract changes. The Court
    of Federal Claims held that the contract’s liquidated-
    damages clause is enforceable and that K-Con did not
    comply with the written-notice precondition for invoking
    the contract clause governing changes. It also held that
    K-Con’s claim for an extension on the completion date
    must be dismissed for lack of jurisdiction. We affirm.
    BACKGROUND
    On January 20, 2004, K-Con entered into a contract
    with the Coast Guard, under which K-Con would con-
    struct a “cutter support team building” in Port Huron,
    Michigan, for $582,641. The project was to be completed
    by November 20, 2004, with K-Con agreeing to pay $589
    in liquidated damages for each day of delay. On May 23,
    2005, the Coast Guard accepted the building as substan-
    tially complete. It withheld payment of $109,554 as
    liquidated damages for what it calculated to be tardiness
    of 186 days. No party challenges the calculation.
    On July 28, 2005, K-Con sent a letter to the govern-
    ment contracting officer requesting remission of the
    liquidated damages “wrongfully withheld from the con-
    tract.” J.A. 259, Letter from K-Con to Contracting Officer
    (July 8, 2005) (first letter). As grounds for remission, K-
    Con asserted that the “liquidated damages [constituted]
    K-CON BUILDING SYSTEMS, INC.   v. US                     3
    an impermissible penalty” and that the Coast Guard
    “failed to issue extensions to the completion date as a
    result of changes to the contract.” 
    Id. It provided
    no
    details regarding its request for a time extension based on
    contract changes. After the contracting officer denied K-
    Con’s request for remission, K-Con sued in the Court of
    Federal Claims under the Contract Disputes Act (CDA),
    41 U.S.C. §§ 601-613 (2006). 1 K-Con sought remission of
    $109,554 plus interest in liquidated damages on the two
    grounds asserted in its July 28, 2005 letter. Original
    Complaint, K-Con Bldg. Sys., Inc. v. United States, No.
    05-01054C (Fed. Cl. Sept. 30, 2005).
    On December 15, 2006, while litigation in the Court of
    Federal Claims was underway, K-Con submitted a second
    letter to the contracting officer. J.A. 263–64, Letter from
    K-Con to Contracting Officer (Dec. 15, 2006) (second
    letter). The second letter extensively details the contract
    changes allegedly made by the Coast Guard during the
    contract term and asks for a new remedy—$196,126.38
    for additional work necessitated by the changes—as well
    as an extension of the completion date of the contract.
    The contracting officer denied K-Con’s requests. K-Con
    then amended its complaint in the Court of Federal
    Claims to add allegations about the matter covered in its
    second letter and to seek, beyond the liquidated-damages
    relief, a judgment of $196,126.38 and a 186-day extension.
    Amended Complaint, K-Con Bldg. Sys., No. 05-01054C
    (Fed. Cl. Mar. 18, 2007).
    The Court of Federal Claims first ruled, in deciding
    an initial government motion for summary judgment, that
    the contract’s liquidated-damages clause is enforceable.
    1   The cited provisions apply to this case. Since
    2011, the Contract Disputes Act has been codified at 41
    U.S.C. §§ 7101-7109. See Pub. L. No. 111-350, 124 Stat.
    3677 (2011).
    4                         K-CON BUILDING SYSTEMS, INC.   v. US
    The court later issued two rulings in deciding a second
    government motion for summary judgment. It held that
    K-Con did not provide valid written notice regarding
    contract changes and therefore had not satisfied a pre-
    condition to claiming additional compensation under the
    contract’s changes clause. And it dismissed, for lack of
    jurisdiction, K-Con’s time-extension claim for remission of
    liquidated damages.
    K-Con appeals all three rulings. We have jurisdiction
    under 28 U.S.C. § 1295(a)(3).
    DISCUSSION
    Whether the Court of Federal Claims had jurisdiction
    under the CDA is a question of law we decide de novo.
    Reflectone, Inc. v. Dalton, 
    60 F.3d 1572
    , 1575 (Fed. Cir.
    1995) (en banc). A plaintiff “bears the burden of estab-
    lishing subject matter jurisdiction by a preponderance of
    the evidence.” Reynolds v. Army & Air Force Exch. Serv.,
    
    846 F.2d 746
    , 748 (Fed. Cir. 1988). “[W]e review a grant
    of summary judgment by the Court of Federal Claims de
    novo, drawing justifiable factual inferences in favor of the
    party opposing the judgment.” Long Island Sav. Bank,
    FSB v. United States, 
    503 F.3d 1234
    , 1244 (Fed. Cir.
    2007). “Once the moving party has satisfied its initial
    burden, the opposing party must establish a genuine issue
    of material fact and cannot rest on mere allegations, but
    must present actual evidence.” 
    Id. A Before
    turning to the merits, we must determine
    which issues the Court of Federal Claims had jurisdiction
    to decide under the CDA. “The CDA grants [the Court of
    Federal Claims] jurisdiction over actions brought on
    claims within twelve months of a contracting officer’s final
    decision.” James M. Ellett Constr. Co. v. United States, 
    93 F.3d 1537
    , 1541 (Fed. Cir. 1996) (citing 41 U.S.C.
    § 609(a)). Jurisdiction requires both that a claim meeting
    K-CON BUILDING SYSTEMS, INC.   v. US                       5
    certain requirements have been submitted to the relevant
    contracting officer and that the contracting officer have
    issued a final decision on that claim. 
    Id. at 1541–42.
         A claim is “ ‘a written demand or written assertion by
    one of the contracting parties seeking, as a matter of
    right, the payment of money in a sum certain, the ad-
    justment or interpretation of contract terms, or other
    relief arising under or relating to the contract.’ ” Reflec-
    
    tone, 60 F.3d at 1575
    (quoting regulation then codified at
    48 C.F.R. § 33.201; current version at 48 C.F.R. § 52.233-
    1). A claim need not “be submitted in any particular form
    or use any particular wording . . . [, but it must provide] a
    clear and unequivocal statement that gives the contract-
    ing officer adequate notice of the basis and amount of the
    claim.” Contract Cleaning Maint., Inc. v. United States,
    
    811 F.2d 586
    , 592 (Fed. Cir. 1987). A contracting officer’s
    final decision on a claim may either be written, 41 U.S.C.
    § 605(a), or implied from “[a]ny failure by the contracting
    officer to issue a decision on a contract claim within the
    period required,” 
    id. § 605(c)(5).
        Identifying what constitutes a separate claim is
    important. We have long held that the jurisdictional
    standard must be applied to each claim, not an entire
    case; jurisdiction exists over those claims which satisfy
    the requirements of an adequate statement of the amount
    sought and an adequate statement of the basis for the
    request. See Joseph Morton Co. v. United States, 
    757 F.2d 1273
    , 1281 (Fed. Cir. 1985) (“Congress did not intend the
    word ‘claim’ to mean the whole case between the contrac-
    tor and the Government; but, rather, that ‘claim’ mean
    each claim under the CDA for money that is one part of a
    divisible case.”); see also M. Maropakis Carpentry, Inc. v.
    United States, 
    609 F.3d 1323
    , 1327–32 (Fed. Cir. 2010)
    (reaching different results for different claims in deter-
    mining Court of Federal Claims jurisdiction). Claim
    identification is important also for application of the rule
    that, once a claim is in litigation, the contracting officer
    6                          K-CON BUILDING SYSTEMS, INC.   v. US
    may not rule on it—even if the claim is not properly in
    litigation because it was not properly submitted to and
    denied by the contracting officer before it was placed in
    litigation. Sharman Co. v. United States, 
    2 F.3d 1564
    ,
    1571–72 (Fed. Cir. 1993) (“Once a claim is in litigation,
    the Department of Justice gains exclusive authority to act
    in the pending litigation . . . [,] divest[ing] the contracting
    officer of his authority to issue a final decision on the
    claim.”) (citing 28 U.S.C. §§ 516–520), overruled on other
    grounds, Reflectone, 
    60 F.3d 1572
    ; see also John Cibinic,
    Jr., et al., Administration of Government Contracts 1292–
    93 (4th ed. 2006) (“The contracting officer’s authority to
    settle claims does not extend to cases in which litigation
    has commenced in a court. . . . [N]o final decision may be
    issued on a matter that is already in litigation.”).
    Our longstanding demand that a claim adequately
    specify both the amount sought and the basis for the
    request implies that, at least for present purposes, we
    should treat requests as involving separate claims if they
    either request different remedies (whether monetary or
    non-monetary) or assert grounds that are materially
    different from each other factually or legally. See Con-
    tract 
    Cleaning, 811 F.2d at 592
    (evaluating the adequacy
    of a claim on the notice it gives of the remedy requested
    and the basis for that remedy); 48 C.F.R. § 52.233-1(c)
    (defining a claim as a written demand for a remedy “as a
    matter of right”). This approach, which has been applied
    in a practical way, serves the objective of giving the
    contracting officer an ample pre-suit opportunity to rule
    on a request, knowing at least the relief sought and what
    substantive issues are raised by the request.
    We have not treated the different-remedies compo-
    nent as imposing so rigid a standard as to preclude all
    litigation adjustments in amounts “based upon matters
    developed in litigation.” Tecom, Inc. v. United States, 
    732 F.2d 935
    , 937–38 (Fed. Cir. 1984) (“ ‘It would be most
    disruptive of normal litigation procedure if any increase
    K-CON BUILDING SYSTEMS, INC.   v. US                       7
    in the amount of a claim based upon matters developed in
    litigation before the court [or board] had to be submitted
    to the contracting officer before the court [or board] could
    continue to a final resolution on the claim.’ ”) (alterations
    in original; quoting J.F. Shea Co. v. United States, 4 Cl.
    Ct. 46, 54 (1983)). But we have differentiated claims
    seeking different types of remedy, such as expectation
    damages versus consequential damages. Case, Inc. v.
    United States, 
    88 F.3d 1004
    , 1010 (Fed. Cir. 1996) (hold-
    ing that two cases “involved different claims” even though
    both “arose out of the same underlying set of facts and
    involved [similar, if not the same] allegations of defective
    specifications,” because the later-filed case requested
    “additional compensation” beyond the progress payments
    requested in the other case, including lost profits). In a
    similar vein, merely adding factual details or legal argu-
    mentation does not create a different claim, but present-
    ing a materially different factual or legal theory (e.g.,
    breach of contract for not constructing a building on time
    versus breach of contract for constructing with the wrong
    materials) does create a different claim. See Santa Fe
    Eng’rs, Inc. v. United States, 
    818 F.2d 856
    , 858–60 (Fed.
    Cir. 1987) (holding that a claim for damages related to
    three change orders was different from a claim for dam-
    ages related to “ ‘the collective nature of all the problems,
    changes and directives issued on the project’ ”) (emphasis
    in original). We have gone beyond the face of claims to
    make these distinctions. See, e.g., 
    Sharman, 2 F.3d at 1571
    (equating claims that “allege[d] entitlement to the
    same money based on the same partial performance, only
    under a different legal label”); Scott Timber Co. v. United
    States, 
    333 F.3d 1358
    , 1366 (Fed. Cir. 2003) (“Scott may
    have posed slightly different legal theories for the breach,
    but Scott’s claim is essentially the same as presented to
    the CO.”).
    In its amended complaint in this case, K-Con present-
    ed three discrete claims—i.e., three distinct combinations
    8                         K-CON BUILDING SYSTEMS, INC.   v. US
    of a request for a remedy and a basis for that request.
    First, it claimed that the liquidated-damages clause is
    unenforceable and on that basis sought remission of
    $109,554 plus interest in liquidated damages withheld by
    the Coast Guard. Second, as an additional basis for
    seeking the same remedy of remission, it claimed that it
    was entitled to time extensions that the Coast Guard
    never provided. Third, it claimed that, because of con-
    tract changes made by the Coast Guard, it had to do
    additional work that entitled it to $196,126.38 over and
    above remission of liquidated damages. We agree with
    the Court of Federal Claims that it had jurisdiction to
    decide the first and third claims, which relate to enforcea-
    bility of the liquidated-damages clause and to alleged
    contract changes, but not the second claim, which chal-
    lenges the Coast Guard’s failure to grant time extensions.
    Jurisdiction over the unenforceability claim is undis-
    puted, and properly so. There was adequate pre-suit
    notice to the contracting officer in K-Con’s first letter, in
    which K-Con clearly requested a sum certain ($118,950.68
    plus interest, in remission of liquidated damages) on the
    ground that the liquidated damages imposed in this case
    amounted to an “impermissible penalty.” J.A. 259. There
    was also, in the contracting officer’s first denial, a valid
    pre-suit final decision rejecting K-Con’s contentions.
    Jurisdiction over the contract-changes claim is dis-
    puted. Like the Court of Federal Claims, we conclude
    that there was CDA jurisdiction over that claim, based on
    K-Con’s second letter to the contracting officer. That
    letter provides ample detail regarding the basis for the
    claim, including what specific actions by the Coast Guard
    allegedly made constructive changes to contract require-
    ments; and the letter clearly requests award of a sum
    certain as a remedy ($196,126.38 in compensation for
    extra work performed).
    K-CON BUILDING SYSTEMS, INC.   v. US                      9
    The government urges that there was no authorized
    final decision on that claim before litigation on it com-
    menced, because K-Con sent its second letter after filing
    its original complaint, which the government says already
    contained the contract-changes claim. See 
    Sharman, 2 F.3d at 1571
    –72. We disagree with the premise that the
    second letter’s contract-changes claim was already in
    litigation when K-Con sent that letter. The original
    complaint does complain about contract changes and
    include some factual assertions shared by the contract-
    changes claim presented in the second letter. Compare
    J.A. 68 (original complaint) (“[T]he Coast Guard changed
    and modified the Contract in among other ways, by failing
    to properly review and approve drawings submitted by K-
    Con, and directing K-Con to perform additional work that
    was not required by the Contract.”) with J.A. 264–66
    (second letter) (complaining of contract-changes from the
    Coast Guard’s review of design submittals). But the
    remedy requested in the two documents is categorically
    different: the original complaint asks for remission of
    liquidated damages, whereas the second letter asks for
    compensation for extra work performed. That is enough
    to make the requests different claims. Consequently, the
    contracting officer’s rejection of the second letter’s con-
    tract-changes claim, a rejection issued upon full consider-
    ation of its merits, was an authorized final decision
    sufficient to establish jurisdiction in the Court of Federal
    Claims.
    The Court of Federal Claims did not have jurisdiction
    over K-Con’s time-extension claim. At bottom, the time-
    extension claim is a request for remission of liquidated
    damages on the ground that the Coast Guard failed to
    issue time extensions for additional work added to the
    10                        K-CON BUILDING SYSTEMS, INC.   v. US
    contract. 2 K-Con squarely placed that claim in litigation
    through its original complaint, which means that K-Con
    had to present that claim adequately in its first letter, not
    in the post-suit second letter. But the first letter plainly
    fails to allege enough detail to provide adequate notice of
    the basis for any time extension. Indeed, K-Con admitted
    to the Court of Federal Claims that its first letter “could
    not be a valid [time-extension] claim.” J.A. 44.
    2   It might be argued that there are in fact two time-
    extension claims at issue: (1) a time-extension claim from
    the first letter and original complaint requesting remis-
    sion of liquidated damages; and (2) a time-extension claim
    from the second letter and amended complaint requesting
    a declaratory judgment of a 186-day extension. Compare
    J.A. 259 (first letter) (requesting remission in part be-
    cause “the government failed to issue extensions”), and
    J.A. 68 at ¶ 6, 11 (original complaint) (same), with J.A.
    266 (second letter) (requesting “an extension in the con-
    tract performance period resulting from [certain contract]
    changes”), and J.A. 85 (amended complaint) (same). But
    K-Con has identified only one concrete benefit it would
    receive from its requested declaratory judgment of enti-
    tlement to a 186-day extension: remission of the liquidat-
    ed damages withheld for tardiness under the contract.
    See 
    Sharman, 2 F.3d at 1571
    . In other circumstances, a
    declaratory judgment of a time extension might be a free-
    standing and independently meaningful remedy.
    K-CON BUILDING SYSTEMS, INC.   v. US                    11
    B
    1
    On the merits, we first address K-Con’s claim that the
    liquidated-damages clause is unenforceable as imposing
    an impermissible penalty. K-Con faces a steep climb in
    trying to establish unenforceability. “When damages are
    uncertain or difficult to measure, a liquidated damages
    clause will be enforced as long as ‘the amount stipulated
    for is not so extravagant, or disproportionate to the
    amount of property loss, as to show that compensation
    was not the object aimed at or as to imply fraud, mistake,
    circumvention or oppression.’ ” DJ Mfg. Corp. v. United
    States, 
    86 F.3d 1130
    , 1133 (Fed. Cir. 1996) (quoting Wise
    v. United States, 
    249 U.S. 361
    , 365 (1919)). “With that
    narrow exception, ‘[t]here is no sound reason why persons
    competent and free to contract may not agree upon this
    subject as fully as upon any other, or why their agree-
    ment, when fairly and understandingly entered into with
    a view to just compensation for the anticipated loss,
    should not be enforced.’ ” 
    Id. (alteration in
    original)
    (quoting 
    Wise, 249 U.S. at 365
    ); see also 48 C.F.R.
    § 11.501(b). “[T]he test is objective,” and “regardless of
    how the liquidated damage figure was arrived at, the
    liquidated damages clause will be enforced if the amount
    stipulated is reasonable for the particular agreement at
    the time it is made.” DJ Mfg. 
    Corp., 86 F.3d at 1137
    (citations and internal quotation marks omitted).
    We agree with the Court of Federal Claims that the
    liquidated-damages clause here is enforceable. The clause
    sets a rate of $589 per day of delay for a $582,641 con-
    tract. K-Con has alleged that the Coast Guard made
    certain errors in arriving at the $589 figure for inclusion
    in the contract, such as a “mathematical error [amounting
    to an additional] $26.30/day.” Appellant’s Br. at 18. K-
    Con’s allegations, however, are immaterial. Even if the
    alleged errors were made, the ultimate rate of $589 per
    12                       K-CON BUILDING SYSTEMS, INC.   v. US
    day is reasonable. DJ Mfg. 
    Corp., 86 F.3d at 1137
    . At the
    time of contracting, it was foreseeable that delay would
    create a number of costs for the Coast Guard, including
    costs for travel, inspection, and other work by government
    personnel—all continuing beyond the date by which such
    activities for this contract should have ended. J.A. 203–
    04 (contracting officer tabulating various costs); see also
    48 C.F.R. § 11.502(b) (requiring that rates in
    “[c]onstruction contracts with liquidated damages provi-
    sions . . . include the estimated daily cost of Government
    inspection and superintendence” as well as “other ex-
    pected expenses”). The exact dollar figure of those costs
    was “uncertain or difficult to measure,” but given the
    general existence of such costs, it cannot be said that the
    $589-per-day rate agreed upon by the parties at the time
    of contracting was “so extravagant[] or disproportionate to
    the amount of property loss” as to constitute an imper-
    missible penalty on K-Con, rather than a reasonable
    estimate of the costs that delay in job completion would
    likely impose. See DJ Mfg. 
    Corp., 86 F.3d at 1133
    –34.
    K-Con counters that the rate cannot reflect a reason-
    able estimate of costs because it includes personnel costs
    that “would have been incurred no matter what.” Appel-
    lant’s Br. at 19. Specifically, K-Con argues that Coast
    Guard “personnel did not work any more hours, work any
    differently, or get paid any more or any less” due to delay
    under the contract. 
    Id. This argument
    is meritless. It is
    reasonable to expect that delay, if it occurs, will require
    personnel to devote more time and resources to the project
    than they would have if the project had been completed on
    time. Moreover, even if the same personnel might work
    the same number of hours regardless of delay, it is rea-
    sonable to expect that delay would force them to re-
    allocate their hours and impair their ability to give
    planned attention to other projects, to the detriment of
    those other projects. In short, inefficiency plausibly
    breeds administrative costs, which the agreed-upon rate
    K-CON BUILDING SYSTEMS, INC.   v. US                       13
    here properly estimated. See Jennie-O Foods, Inc. v.
    United States, 
    580 F.2d 400
    , 413 (Ct. Cl. 1978). K-Con
    has not raised a genuine issue of material fact regarding
    the rate’s reasonableness.
    2
    The second merits issue involves K-Con’s claim that it
    is entitled to compensation for additional work it per-
    formed because of what it says were constructive changes
    made to the contract by the Coast Guard. The relevant
    portion of the contract’s changes clause reads as follows:
    (b) Any other written or oral order . . . from
    the Contracting Officer that causes a change shall
    be treated as a change order under this clause;
    provided, that the Contractor gives the Contract-
    ing Officer written notice stating
    (1) the date, circumstances, and source of the
    order and
    (2) that the Contractor regards the order as a
    change order.
    ....
    (d) . . . [E]xcept for an adjustment based on de-
    fective specifications, no adjustment for any
    change under paragraph (b) of this clause shall be
    made for any costs incurred more than 20 days be-
    fore the Contractor gives written notice as re-
    quired.
    48 C.F.R. § 52.243-4 (Aug. 1987); see J.A. 145 (contract
    incorporating the changes clause).
    K-Con alleges that the Coast Guard made two sets of
    changes to the contract. First, it alleges that, on January
    28, 2004, the Coast Guard requested that the building’s
    eave height be increased by four inches. Second, it alleges
    that, starting in April 2004 and continuing through July
    14                        K-CON BUILDING SYSTEMS, INC.   v. US
    2004, the Coast Guard requested various changes upon
    reviewing K-Con’s design submissions. We agree with the
    Court of Federal Claims that, with regard to all of the
    alleged changes, K-Con did not comply with the written-
    notice requirement of the contract’s changes clause.
    Throughout the period that the Coast Guard was al-
    legedly making changes, K-Con never objected to the
    Coast Guard’s actions or suggested that it was entitled to
    an adjustment of contract terms. Rather, K-Con repeat-
    edly expressed its intent to incorporate the Coast Guard’s
    requests as though they were consistent with the terms of
    the contract. E.g., J.A. 345–46 (K-Con responding to
    Coast Guard’s review comments with brief, affirmative
    statements, such as “[w]ill comply,” “[c]orrection will be
    made,” and “[d]etail will be revised”). It was only once K-
    Con submitted its contract-changes claim in its second
    letter to the contracting officer—more than two years
    after any of the changes at issue were allegedly ordered—
    that K-Con seems to have provided written notice ade-
    quate under paragraph (b). Only then did K-Con identify
    the “date, circumstances, and source of the order[s]” it
    objected to and indicate that it “regard[ed] the order[s] as
    change order[s].” 48 C.F.R. § 52.243-4(b).
    Two years is well beyond the 20-day time limit im-
    posed by paragraph (d). And the notice provision serves
    an important purpose in a contract in which some gov-
    ernment requests are plainly contemplated under the
    contract. Timely written notice differentiates requests
    the contractor views as outside the contract from those it
    deems contemplated by the contract. See Singer Co.
    Librascope Div. v. United States, 
    568 F.2d 695
    , 711 (Ct.
    Cl. 1977) (“[T]he work was done without notice to the
    contracting officer that Librascope considered the effort
    involved to be extra-contractual. . . . The contractor’s
    failure to protest, while perhaps not an outright bar to the
    claim, is nevertheless an evidentiary consideration which,
    in these circumstances, takes on controlling signifi-
    K-CON BUILDING SYSTEMS, INC.   v. US                     15
    cance.”). And it gives the government timely notice of
    what amounts it might be on the hook for, so that it will
    not be surprised by money claims later, as well as an
    opportunity to address demands for more money when it
    might yet avoid them.
    Sometimes, extenuating circumstances have weighed
    against strict enforcement of the time limit. See generally
    Powers Regulator Co., GSBCA No. 4668, 80-2 BCA
    ¶ 14,463 (Apr. 30, 1980) (reviewing how the time limit has
    been enforced by boards of contract appeals and enumer-
    ating exceptions to its strict enforcement); see also Hoel-
    Steffen Const. Co. v. United States, 
    456 F.2d 760
    , 767–68
    (Ct. Cl. 1972) (noting that a “severe and narrow applica-
    tion of the notice requirements [of the suspension clause
    in the then-extant Federal Procurement Regulations] . . .
    would be out of tune with the language and purpose of the
    notice provisions, as well as with this court’s wholesome
    concern that notice provisions in contract-adjustment
    clauses not be applied too technically and illiberally
    where the Government is quite aware of the operative
    facts”). But there are no such extenuating circumstances
    here. K-Con has proffered no evidence suggesting that
    the Coast Guard knew or should have known that K-Con
    considered the work requests to be contract changes until,
    at the earliest, K-Con submitted its first letter to the
    contracting officer. That letter, sent a year after the last
    of the alleged changes, lacks any detail with regard to
    what K-Con considered to be the changes made and offers
    the Coast Guard a simple choice between acceding to K-
    Con’s demands or being sued. Such notice does not com-
    ply with the changes clause.
    K-Con’s sole counterargument is that it did not have
    to comply with the notice provision of the changes clause
    because compliance would have been futile. Even if a
    futility exception exists, however, K-Con’s argument fails
    because it has not shown that compliance would have
    been futile. The Coast Guard never stated or implied in
    16                       K-CON BUILDING SYSTEMS, INC.   v. US
    advance that it would reject allegations of contract chang-
    es. See J.A. 252 (“Design Coordination Review Com-
    ments” form, which left a space for the contractor to
    respond with action code “dc,” meaning “[d]o not concur
    with [the Coast Guard’s] comment for reasons as indicat-
    ed”). And although the contracting officer, in response to
    K-Con’s second letter, did ultimately reject K-Con’s con-
    tract-changes claim, deeming that fact sufficient to estab-
    lish futility would threaten to erase the notice
    requirement. In any event, it is unknown what would
    have happened had K-Con broached the issue of changes
    around the time the Coast Guard made the work requests
    at issue. The submission of the second letter prompted
    the Coast Guard to make a choice between giving in to K-
    Con’s demands or subjecting itself to further litigation;
    timely objections would have presented a very different
    choice between at least four options—refraining from
    making requests regarding K-Con’s work, altering the
    nature of the requests, keeping the requests the same but
    making equitable adjustments to the contract, or rejecting
    the allegations of changes altogether and thereby risking
    litigation or a halt to the project. K-Con failed to comply
    with the changes clause, and its after-the-fact specula-
    tions about what would have happened had it complied do
    not create a genuine dispute of material fact regarding
    whether it should be excused for its failure.
    CONCLUSION
    For the foregoing reasons, the judgment of the Court
    of Federal Claims is affirmed.
    AFFIRMED