Bigge Crane & Rigging Co. v. Entergy Ark. Inc , 457 S.W.3d 265 ( 2015 )


Menu:
  •                                      Cite as 
    2015 Ark. 58
    SUPREME COURT OF ARKANSAS
    No.   CV-14-549
    BIGGE CRANE & RIGGING CO.;                        Opinion Delivered   February 26, 2015
    CLAUS FREDERIKSEN; DP
    ENGINEERING, LTD.; JOHN                           APPEAL FROM THE POPE COUNTY
    SCROGGINS; AND VEI GENERAL                        CIRCUIT COURT
    CONTRACTORS, INC.                                 [NO. CV-2013-176-IV]
    APPELLANTS
    HONORABLE DENNIS CHARLES
    V.                                                SUTTERFIELD, JUDGE
    AFFIRMED.
    ENTERGY ARKANSAS, INC.; AND
    ENTERGY OPERATIONS, INC.
    APPELLEES
    JIM HANNAH, Chief Justice
    Appellants, Bigge Crane and Rigging Co. and Claus Frederiksen (“Bigge”), appeal an
    order of the Pope County Circuit Court denying a motion to compel arbitration with
    appellees, Entergy Arkansas, Inc., and Entergy Operations, Inc. (“Entergy”). Bigge sought
    to arbitrate tort claims as a purported third-party beneficiary of a contract between Entergy
    and Siemens Energy, Inc. (“Siemens). For reversal, Bigge contends that the circuit court
    erred in concluding (1) that issues of arbitrability were matters for judicial determination and
    (2) that Bigge could not invoke arbitration. We affirm the circuit court’s order.
    In March 2010, Entergy entered into an Alliance Agreement with Siemens, under
    which Siemens was to provide Entergy with multi-outage turbine generator work; field
    maintenance and repair services; equipment, modernization, and upgrade services; and other
    Cite as 
    2015 Ark. 58
    technical services at three nuclear facilities. The Alliance Agreement included an arbitration
    provision, which stated that “[a]ny claim, dispute or controversy arising out of or relating to
    this Agreement, shall be submitted to binding arbitration.” Pursuant to the Alliance
    Agreement, Entergy and Siemens agreed to a contract order for Siemens to replace a large
    component of a generator called a stator at Entergy’s Arkansas Nuclear One (“ANO”) facility
    in London, Arkansas.
    Siemens had a separate, long-term agreement called the Master Services Agreement
    (“MSA”) with Bigge. Under the MSA, Bigge was to provide “rigging, lifting, loading,
    transporting, transloading to rail trucks, and other services associated with crane services
    . . . and materials associated with lifting and crane services.” The dispute-resolution terms in
    the MSA called for Bigge and Siemens to use all reasonable efforts to resolve disputes
    amicably prior to commencing any formal legal proceedings, but if they were unable to
    resolve such disputes, they were free to pursue any and all remedies at law or in equity.1
    Bigge and Siemens executed a separate purchase order under the MSA to govern
    Bigge’s removal of the existing stator at ANO. On March 31, 2013, a gantry crane designed,
    engineered, built, and operated by Bigge collapsed while moving the 524-ton stator out of
    ANO. The crane failure and collapse killed one person, injured ten others, and caused
    significant damages to ANO.
    On July 12, 2013, Entergy filed suit against Bigge and others in circuit court, alleging
    1
    The dispute-resolution terms required Bigge to file any action against Siemens in
    Orlando, Florida.
    2
    Cite as 
    2015 Ark. 58
    tort claims for negligence, gross negligence, and willful and wanton conduct. Bigge moved
    to dismiss parts of Entergy’s complaint on August 22, 2013.2 On November 26, 2013, Bigge
    filed a motion in Arkansas state court to compel arbitration of Entergy’s tort claims against
    Bigge. Bigge’s motion relied exclusively on the arbitration provisions contained in the
    Alliance Agreement between Entergy and Siemens. Bigge argued that the arbitration
    provisions deprived the circuit court of jurisdiction to determine whether Entergy and Bigge
    had a valid agreement to arbitrate. Bigge also argued that, even if the circuit court had
    jurisdiction to make that determination, Bigge could enforce the Alliance Agreement’s
    arbitration provisions as a third-party beneficiary or through equitable estoppel.
    Following a hearing, the circuit court denied Bigge’s motion to compel arbitration.
    The circuit court ruled that because there was no agreement to arbitrate that applied to
    disputes between Entergy and Biggee, it was appropriate for the court to decide the issue of
    arbitrability; that Bigge was not a third-party beneficiary of the Alliance Agreement; and that
    Entergy was not equitably estopped from pursuing its remedies in court. In addition, the
    circuit court found that Bigge had waived any right to compel arbitration by litigating some
    of the same issues in Florida federal court and by filing a motion to dismiss and engaging in
    discovery in Arkansas state court. Bigge appeals.
    An order denying a motion to compel arbitration is an immediately appealable order.
    2
    On August 30, 2013, Bigge filed its own lawsuit against Entergy and Siemens in a
    Florida federal court. The Florida litigation has since been transferred to the United States
    District Court for the Eastern District of Arkansas. Bigge Crane & Rigging Co. v. Entergy
    Operations, Inc., No. 4:14-cv-00298-DPM (E.D. Ark. transferred May 14, 2014), ECF No.
    76.
    3
    Cite as 
    2015 Ark. 58
    Ark. R. App. P.–Civ. 2(a)(12) (2014). This court reviews a circuit court’s order denying a
    motion to compel arbitration de novo on the record. E.g., Bank of the Ozarks v. Walker, 
    2014 Ark. 223
    , at 4, 
    434 S.W.3d 357
    , 360.
    Entergy does not dispute Bigge’s contention that the Federal Arbitration Act (“FAA”),
    9 U.S.C. §§ 1–16, governs the arbitration provisions in the Alliance Agreement. A party
    seeking to compel arbitration under the FAA must establish that (1) there is a valid agreement
    to arbitrate between the parties, and (2) the claims in dispute fall within that agreement’s
    scope. See LegalZoom.com, Inc. v. McIllwain, 
    2013 Ark. 370
    , at 8–9, 
    429 S.W.3d 261
    , 265.
    Bigge is not a party to the Alliance Agreement, but in some instances, a nonparty may
    compel arbitration through “traditional principles of state law” such as “assumption, piercing
    the corporate veil, alter ego, incorporation by reference, third-party beneficiary theories,
    waiver and estoppel.” Arthur Andersen, LLP v. Carlisle, 
    556 U.S. 624
    , 631 (2009). In this case,
    Bigge contends that it may compel arbitration because it is a third-party beneficiary of the
    Alliance Agreement between Entergy and Siemens and, as such, it has the right to invoke
    that contract’s arbitration provisions. Before addressing the merits of Bigge’s position, we
    must consider Bigge’s contention that the arbitrator, and not the circuit court, should have
    decided issues of arbitrability.
    I. Who Decides Arbitrability
    Although the Supreme Court of the United States has
    recognized and enforced a liberal federal policy favoring arbitration agreements, it has
    made clear that there is an exception to this policy: The question whether the parties
    have submitted a particular dispute to arbitration, i.e., the “question of arbitrability,” is
    an issue for judicial determination [u]nless the parties clearly and unmistakably provide
    4
    Cite as 
    2015 Ark. 58
    otherwise.
    Howsam v. Dean Witter Reynolds, Inc., 
    537 U.S. 79
    , 83 (2002) (internal citations omitted); see
    also HPD, LLC v. TETRA Techs., Inc., 
    2012 Ark. 408
    , at 6, 
    424 S.W.3d 304
    , 308 (stating
    that the court, rather than the arbitrator, decides the question of arbitrability unless the parties
    clearly and unmistakably delegate that question to the arbitrator).
    The relevant arbitration provisions are contained in Article 56 of the Alliance
    Agreement between Entergy and Siemens:
    56.1 The parties, through their respective Project Managers, shall use all reasonable
    efforts to resolve any disputes that may arise between them under this Agreement. If
    a dispute is not resolved at the Project Manager level, a meeting shall be held
    promptly between the parties’ Alliance Directors.
    ....
    56.2 If the Alliance fails to resolve the dispute . . . they shall . . . prepare and transmit
    a briefing package regarding the dispute to an assigned “Alliance Steering Committee”
    for review.
    ....
    56.3 If the Steering Committee also fails to resolve the dispute . . . the Alliance
    Directors shall . . . submit the issue to an assigned “Advisory Committee” for final
    resolution.
    ....
    56.4 If the parties are not successful in resolving the dispute, they may mutually agree
    to submit the dispute to non-binding third party mediation. . . . If the parties are not
    successful in resolving the dispute through mediation, or if the dispute otherwise
    remains unresolved . . . then either party may submit the dispute to binding arbitration
    as provided in 56.5 below, which shall be the exclusive method of resolving such
    disputes. Each party shall bear its own costs and expenses of any mediation or
    arbitration.
    56.5 Any claim, dispute, or controversy arising out of or relating to this Agreement
    5
    Cite as 
    2015 Ark. 58
    shall be submitted to binding arbitration by the American Arbitration Association for
    arbitration in Little Rock, Arkansas in accordance with the Commercial Arbitration
    Rules then in effect. There shall be three arbitrators, with each party selecting one; the
    third neutral arbitrator, who shall be the chairman of the panel, shall be elected by the
    two party-appointed arbitrators. The claimant shall name its arbitrator in the demand
    for arbitration and the responding party shall name its arbitrator within 30 days after
    the receipt of the demand for arbitration. The third arbitrator shall be named within
    30 days after the appointment of the second arbitrator. The American Arbitration
    Association shall be empowered to appoint any arbitrator not named in accordance
    with the procedure herein. The arbitrators shall have no jurisdiction to consider (i)
    claims for consequential damages or damages beyond the limitations of liability
    contained in the Contract and (ii) any challenge to the limitation of the liability
    contained in the Contract. The decision of the arbitrators shall be final and binding
    upon the parties without the right of appeal to the courts. The award rendered by the
    arbitration shall be final and judgment thereon may be entered by any court having
    jurisdiction thereof. Each Party shall bear its own cost and expenses in connection with
    such arbitration. Provided, however, that nothing herein shall in any way be deemed
    or construed to limit or restrict either Party from seeking or obtaining injunctive relief
    to protect its patents, copyrights, trade secrets, or other intellectual property in any
    court of competent jurisdiction, and the arbitrators shall have no jurisdiction to
    consider any issue of intellectual property infringement or validity.
    (Emphasis added.)
    Assuming arguendo that there is clear and unmistakable evidence in the arbitration
    provisions that the parties to the Alliance Agreement—Entergy and Siemens—agreed to
    arbitrate arbitrability, there is no clear and unmistakable evidence in the arbitration provisions
    that Entergy and Bigge agreed to arbitrate the issue of whether their dispute is arbitrable. See
    Republic of Iraq v. ABB AG, 
    769 F. Supp. 2d 605
    , 610 (S.D.N.Y. 2011) (concluding that
    there was no clear and unmistakable evidence from the arbitration agreement that a signatory
    and a nonsignatory agreed to arbitrate the issue of whether their dispute was arbitrable for
    the simple reason that there was no contract between them). Nor can it be said that the
    Alliance Agreement between Entergy and Siemens clearly and unmistakably provides for
    6
    Cite as 
    2015 Ark. 58
    arbitral resolution of arbitrability disputes with third parties. See 
    id. The arbitration
    provisions
    in the Alliance Agreement contain no reference to Bigge or to third parties in general.3 To
    the contrary, the Alliance Agreement states that either party, that is, either Entergy or Siemens,
    “may submit [a] dispute to binding arbitration.” There is nothing in the arbitration provisions
    to suggest that Entergy and Siemens intended to afford anyone other than themselves the
    right to arbitrate arbitrability.
    In urging otherwise, Bigge relies on this court’s decision in HPD, 
    2012 Ark. 408
    , 
    424 S.W.3d 304
    , in which we observed that a majority of the courts that have considered the
    issue have held that, when a contract requires arbitration pursuant to rules that expressly
    delegate the question of arbitrability to the arbitrator, the contract clearly and unmistakably
    vests the arbitrator, and not the court, with the authority to decide which issues are subject
    to arbitration. In HPD, we concluded that the parties’ incorporation of the American
    Arbitration Rules into the arbitration agreement, along with other language in the
    agreement, constituted clear and unmistakable evidence of the parties’ intent to arbitrate the
    question of arbitrability. 
    2012 Ark. 408
    , at 
    11–12, 424 S.W.3d at 311
    . In the instant case, the
    Alliance Agreement incorporates the American Arbitration Association’s Commercial
    Arbitration Rules, and Rule R-7(a) of those Rules states that “[t]he arbitrator shall have the
    power to rule on his or her own jurisdiction, including any objections with respect to the
    existence, scope, or validity of the arbitration agreement or to the arbitrability of any claim
    3
    The fact that the Alliance Agreement does not mention third-party beneficiaries does
    not, by itself, preclude Bigge from establishing that it is a third-party beneficiary. See Republic
    of Iraq v. ABB AG, 
    769 F. Supp. 2d 605
    , 610, n.1 (S.D.N.Y. 2011).
    7
    Cite as 
    2015 Ark. 58
    or counterclaim.” Bigge claims, therefore, that the parties intended for an arbitrator to
    determine whether a dispute was arbitrable.
    In making this argument, Bigge overlooks a crucial distinction between the facts in
    this case and those in HDP. At issue in HDP was the arbitrability of a dispute between two
    signatories to an arbitration clause. Here, however, the issue is the arbitrability of a dispute
    between a nonsignatory, Bigge, and a signatory, Entergy. Evidence of intent to have an
    arbitrator determine its jurisdiction of disputes submitted by either party to an arbitration
    agreement does not clearly and unmistakably demonstrate the parties’ intent to have the
    arbitrator determine its jurisdiction with respect to any dispute raised by a nonparty. See
    Republic of Iraq v. BNP Paribas USA, 472 Fed. App’x 11, 13 (2d Cir. 2012); see also ABB 
    AG, 769 F. Supp. 2d at 610
    –11 (“[S]imply because a party has agreed to arbitrate questions of
    arbitrability with its contractual counterpart does not mean that it must arbitrate with any
    non-signatory to the contract.”) (emphasis in original) (internal quotations omitted); QPro,
    Inc. v. RTD Qual. Servs. USA, Inc., 
    761 F. Supp. 2d 492
    , 497 (S.D. Tex. 2011) (“When, as
    here, the issue is whether a nonsignatory to an arbitration clause may enforce it against a
    signatory, the courts have viewed this as a matter for the courts to decide.”).
    Finally, Bigge cites Contec Corp. v. Remote Solution, Inc., 
    398 F.3d 205
    (2d Cir. 2005),
    in which the United States Court of Appeals of the Second Circuit allowed a nonsignatory
    defendant to compel a signatory to arbitrate issues of arbitrability. Bigge’s reliance on Contec
    is misplaced. In Contec, the court concluded that Contec Corporation could compel
    arbitration of the arbitrability of a dispute arising under an agreement signed by its prior
    8
    Cite as 
    2015 Ark. 58
    corporate form, Contec L.P., and defendant Remote Solution, even though the arbitration
    clause was limited to disputes between the “parties.” In a later case, the Second Circuit
    explained that two facts informed its conclusion in Contec: (1) the undisputed relationship
    between each corporate form of Contec and Remote Solution and (2) the parties continued
    to conduct themselves as subject to the agreement, regardless of the change in corporate
    form. BNP, 472 Fed. App’x 11, 13 (citing 
    Contec, 398 F.3d at 209
    ) (internal quotations
    omitted). Thus, in Contec, the court allowed the nonsignatory defendant to compel the
    signatory to arbitrate issues of arbitrability because the defendant was essentially equivalent
    to the original signatory to the arbitration agreement.
    Here, Bigge, the nonsignatory defendant, was a subcontractor to Siemens, the prime
    contractor who entered into the Alliance Agreement with Entergy. Bigge was not, however,
    essentially equivalent to a signatory. In sum, Bigge has failed to demonstrate that it is entitled
    to an arbitral resolution of arbitrability. Therefore, we hold that the circuit court did not err
    in concluding that, under the facts of this case, issues of arbitrability were matters for judicial
    determination.
    II. Whether the Dispute is Arbitrable
    Bigge asserts that, even if the circuit court properly exercised its jurisdiction to address
    issues regarding the scope and validity of the arbitration provisions, it decided those issues
    erroneously. Generally, the terms of an arbitration contract do not apply to those who are
    not parties to the contract. Amer. Ins. Co. v. Cazort, 
    316 Ark. 314
    , 320, 
    871 S.W.2d 575
    , 579
    (1994). But a litigant who is not a party to an arbitration agreement may invoke arbitration
    9
    Cite as 
    2015 Ark. 58
    under the FAA if the relevant state contract law allows the litigant to enforce the agreement.
    See 
    Carlisle, 556 U.S. at 632
    . Bigge claims that two doctrines of Arkansas law allow it to
    enforce the arbitration provisions as a nonsignatory: (1) third-party beneficiary and (2)
    equitable estoppel.
    In Arkansas, the presumption is that parties contract only for themselves and, thus, a
    contract will not be construed as having been made for the benefit of a third party unless it
    clearly appears that such was the intention of the parties. E.g., Elsner v. Farmers Ins. Group,
    Inc., 
    364 Ark. 393
    , 395, 
    220 S.W.3d 633
    , 635 (2005). If a contract is made for the benefit of
    a third party, then it is actionable by such third party if there is substantial evidence of a clear
    intention to benefit that third party. 
    Id., 220 S.W.3d
    at 635. But a third party may not
    recover upon a contract under which the parties did not intend to benefit him, one under
    which he is a mere incidental beneficiary. Cook v. U.S. Fid. & Guar. Co., 
    216 Ark. 743
    , 745,
    
    227 S.W.2d 165
    , 136 (1950).
    In support of its argument that it is a third-party beneficiary to the Alliance
    Agreement, Bigge cites Little Rock Wastewater Utility v. Larry Moyer Trucking, Inc., 
    321 Ark. 303
    , 
    902 S.W.2d 760
    (1995). In that case, the Arkansas Highway and Transportation
    Department needed to relocate sewer lines before other contractors could perform road
    work. 
    Id. at 306,
    902 S.W.2d at 762. Little Rock Wastewater Utility, which had contracted
    with the highway department to relocate the lines, did not complete its work in a timely
    manner, and a subcontractor who was supposed to prepare the site brought suit as a third-
    party beneficiary of the utility’s contract. 
    Id., 902 S.W.2d
    at 762–63. This court noted that
    10
    Cite as 
    2015 Ark. 58
    the utility’s contract provided that the utility would perform its work within 150 days and
    in a manner that would result in no avoidable interference or delay in the highway
    department’s construction work. 
    Id., 902 S.W.2d
    at 762. The subcontractor testified that
    when making the bid for the subcontract, he relied on the fact that the utility essentially had
    completed its work and would coordinate the remaining work with the highway department
    while construction on the roadway was in progress. 
    Id. at 308,
    902 S.W.2d at 764. Because
    there was clear evidence of an intent to benefit the other contractors who were waiting on
    the utility to perform before they could start their construction work, this court concluded
    that the circuit court correctly refused to grant a directed verdict in favor of the utility and
    correctly allowed the third-party-beneficiary issue to be submitted to the jury. 
    Id. at 309,
    902 S.W.2d at 764–65.
    Although Larry Moyer Trucking involved a subcontractor, it does not stand for the
    proposition that, in all cases, subcontractors are third-party beneficiaries of contracts between
    prime contractors and owners. Indeed, the general rule is that a subcontractor that agrees to
    supply materials or labor to a general contractor is only an incidental beneficiary of any
    contract between the general contractor and the ultimate client. See GS4 Tech. LLC v. United
    States, 
    114 Fed. Cl. 662
    , 670 (2014); see also 9 Corbin on Contracts § 45.3 (rev. ed. 2007);
    Restatement (Second) of Contracts § 302 cmt. e, illus. 19; accord BIS Computer Solutions, Inc.
    v. City of Richmond, 122 Fed. App’x 608, 610, 612 (4th Cir. 2005) (finding that, under
    Virginia law, the subcontractor was not an intended third-party beneficiary, despite being
    named in the prime contract and despite the inclusion of a contract provision prohibiting the
    11
    Cite as 
    2015 Ark. 58
    subcontractor’s removal without the government’s approval).
    The Alliance Agreement between Entergy and Siemens is analogous to a standard
    construction contract in which a property owner retains a contractor to complete a project,
    and the contractor hires subcontractors to assist in performing the contractor’s work. See BIS,
    122 Fed. App’x at 612. Unless the parties specify otherwise, the sole intended beneficiaries
    of any such contract are the property owner and the contractor, and any third party
    benefitting from the contract, such as a subcontractor, is merely an incidental beneficiary. See
    
    id. Here, Bigge
    was merely an incidental beneficiary of the contract. Accordingly, we hold
    that the circuit court correctly found that Bigge was not entitled to invoke arbitration as a
    third-party beneficiary.
    Next, Bigge contends that it may compel Entergy to arbitrate its claims through the
    doctrine of equitable estoppel. Courts have recognized that equitable estoppel can apply
    when a signatory to a written agreement containing an arbitration clause must rely on the
    terms of the written agreement in asserting claims against the nonsignatory. E.g., Donaldson
    Co. v. Burroughs Diesel, Inc., 
    581 F.3d 726
    , 733 (8th Cir. 2009). Bigge, citing Cazort, 
    316 Ark. 314
    , 
    871 S.W.2d 575
    , contends that Entergy relied on the terms of the Alliance Agreement
    in asserting its claims. In that case, Cazort filed suit against his broker, Berman; the financial
    institution holding the brokerage account, NAP; and the corporate bond holder, American
    Insurance Company. 
    Id. at 316,
    871 S.W.2d at 577. NAP and Berman moved to compel
    arbitration and were voluntarily dismissed by Cazort from the litigation. 
    Id., 871 S.W.2d
    at
    577. American’s motion to compel arbitration was denied. 
    Id. at 318,
    871 S.W.2d at 577. At
    12
    Cite as 
    2015 Ark. 58
    issue on appeal was whether American could compel Cazort to arbitrate since Cazort did not
    sign an arbitration agreement with American. In reversing the circuit court’s denial of
    American’s motion to compel arbitration, we stated:
    Cazort’s allegation, in part, is that NAP and Berman breached their contract with
    him, and they are liable for that breach of contract. He relies on the contract for his
    breach of contract claim, but, at the same time, seeks to circumvent the arbitration
    provision of the same contract by dismissing his claims against the principals NAP and
    Berman. The indemnitor, American, had filed a cross-complaint against NAP and
    Berman. If this procedure were to be allowed, NAP and Berman would be denied the
    benefit of their arbitration agreement.
    
    Id. at 321–22,
    871 S.W.2d at 579.
    Cazort is distinguishable from the instant case. There, Cazort relied on the contract
    to prove his breach-of-contract claim, but he sought to avoid the contract’s arbitration
    provision. We concluded that it would have been inequitable to allow Cazort to maintain
    such inconsistent positions to avoid arbitration and noted that a plaintiff “cannot have it both
    ways. It cannot rely on the contract when it works to its advantage and ignore it when it
    works to its disadvantage.” 
    Id. at 322,
    871 S.W.2d at 579–80 (citing Tepper Realty Co. v.
    Mosaic Tile Co., 
    259 F. Supp. 688
    , 692 (S.D.N.Y. 1966)); see also Avila Group, Inc. v. Norma
    J., 
    426 F. Supp. 537
    , 542 (D.C.N.Y. 1979) (“To allow [the litigant] to claim the benefit of
    the contract and simultaneously avoid its burdens would both disregard equity and
    contravene the purposes underlying enactment of the Arbitration Act.”).
    In the instant case, Bigge has not shown that Entergy, in resisting arbitration, has
    attempted to have it both ways. The circuit court found that
    Entergy has no contract with Bigge. Entergy is not suing and cannot sue Bigge for a
    breach of the Alliance Agreement. Rather, Entergy has filed claims against Bigge for
    13
    Cite as 
    2015 Ark. 58
    negligence, gross negligence, and willful and wanton conduct. Entergy’s tort claims
    against Bigge would exist regardless whether a written contract existed between
    Entergy and Siemens or between Siemens and Bigge or what the terms of those
    contracts were. The fact that these contracts do exist does not alter Entergy’s tort
    claims, and Entergy has in no way relied on the terms of the Alliance Agreement in
    asserting its claims against Bigge.
    We agree. Accordingly, we hold that the circuit court did not err in concluding that
    Entergy was not equitably estopped from pursuing its claims against Bigge in court rather
    than in arbitration.
    Bigge also contends that the circuit court erred in finding that Bigge had waived its
    right to arbitration. Because we have determined that Bigge had no right to invoke
    arbitration, we need not consider the issue of waiver.
    Finally, the concurrence appears to assert that, in this case, it is wholly unnecessary for
    this court to address the arguments raised by the parties on appeal because article 51 of the
    Alliance Agreement “specifically except[s] Entergy’s tort claims against Bigge.” The
    concurrence’s reliance on that article is misplaced. Article 51, which limits the recovery of
    consequential damages, has no bearing on the issues before this court.
    Affirmed.
    BAKER and HART, JJ., concur.
    JOSEPHINE LINKER HART, Justice, concurring.                  In its complaint, Entergy
    Arkansas, Inc., and Entergy Operations, Inc. (Entergy), allege tort claims based on the alleged
    negligence of Bigge Crane and Rigging Company and Claus Frederiksen (Bigge), a
    subcontractor of Siemens Energy, Inc. (Siemens). Entergy seeks from Bigge damages for
    injury to property and other economic losses. These claims, however, are not arbitrable under
    14
    Cite as 
    2015 Ark. 58
    the Alliance Agreement entered into by Entergy and Siemens. Thus, I agree to affirm the
    circuit court’s denial of Bigge’s motion to compel arbitration but do so for reasons other than
    those stated by the majority.
    In order to grant a motion to compel arbitration, there must be a valid agreement to
    arbitrate between the parties and a dispute that falls within its scope. HPD, LLC v. TETRA
    Techs., Inc., 
    2012 Ark. 408
    , at 6, 
    424 S.W.3d 304
    , 308. The court decides these questions of
    arbitrability unless the parties clearly and unmistakably delegate that issue to the arbitrator. 
    Id., 424 S.W.3d
    at 308.
    In concluding that “there is no clear and unmistakable evidence in the arbitration
    provisions that Entergy and Bigge agreed to arbitrate the issue of whether their dispute is
    arbitrable,” the majority—contrary to its analysis later in the opinion—ignores the proposition
    that certain common-law principles may allow a nonsignatory to enforce the arbitration
    agreement, such as a nonsignatory third-party beneficiary of the contract. 4 Am. Jur. 2d
    Alternative Dispute Resolution § 60. In fact, Bigge argues that it is a third-party beneficiary to
    the Alliance Agreement.
    After reaching this conclusion, the majority then turns to the next issue, whether the
    dispute is arbitrable, and concludes that Bigge is not a third-party beneficiary to the Alliance
    Agreement because “there is no evidence in the Alliance Agreement that Entergy and
    Siemens intended to benefit Bigge,” and that “Bigge was merely an incidental beneficiary of
    the contract.” This conclusion, however, is not based on a discussion of the specific provisions
    of the Alliance Agreement that Bigge argues cause it to be a third-party beneficiary of the
    15
    Cite as 
    2015 Ark. 58
    Alliance Agreement.
    For instance, the Alliance Agreement specifically provides as follows:
    Notwithstanding any conflicting or inconsistent provisions set forth elsewhere,
    neither party nor their subcontractors of any tier shall be liable to the other for
    damages for loss of anticipated profits, loss of use of revenue, losses by reason of plant
    shutdown or service interruption, cost of purchased or replacement power, cost of
    capital, damage to or loss of property (except as specifically set forth . . . in paragraph
    52.2), claims of customers of the Owners and Entergy Operations, or any other
    indirect, special, incidental, or consequential damages (including negligence) of any
    other nature whether claims arises in contract, tort (including negligence and strict
    liability), under warranty or otherwise. The exclusion of consequential damage shall
    not relieve either party of its obligations pursuant to Article 9, Laws, Project Rules and
    Licenses, Article 15, Nuclear Liability Protection, Article 16, Property Damage
    Protection, Article 18, Indemnity, (only with respect to damage to third party property
    or personal injury), Article 19, Infringement, Article 21, Warranties, Article 36, Force
    Majeure, Article 52, Limitation of Liability, or Article 53, Transfer.
    Arguably, this release of subcontractors from liability for damages caused by negligence would
    make Bigge a third-party beneficiary of the Alliance Agreement.1
    Further, the majority concludes that a form of estoppel identified by this court in
    American Insurance Company v. Cazort, 
    316 Ark. 314
    , 
    871 S.W.2d 575
    (1994), did not require
    Entergy to arbitrate its tort claims against Bigge. By quoting at length the circuit court’s
    findings and stating, “We agree,” the majority apparently concludes that Entergy is not suing
    Bigge for a breach of the Alliance Agreement, that “Entergy’s tort claims against Bigge would exist
    regardless [of] whether a written contract existed between Entergy and Siemens or between Siemens and
    Bigge or what the terms of those contracts were,” (emphasis added), that “[t]he fact that these
    contracts do exist does not alter Entergy’s tort claims,” and that “Entergy has in no way relied
    1
    The exceptions in that paragraph do not address tort claims against subcontractors for
    property damage and economic loss.
    16
    Cite as 
    2015 Ark. 58
    on the terms of the Alliance Agreement in asserting its claims against Bigge.”
    However, the majority’s conclusion that Entergy’s tort claims exist regardless of the
    Alliance Agreement ignores a specific provision of the Alliance Agreement—the provision
    quoted above—which establishes that the Alliance Agreement itself precludes Entergy from
    seeking from Bigge property and economic-loss damages caused by Bigge’s negligence. Thus,
    the Alliance Agreement specifically excepted Entergy’s tort claims against Bigge.
    The arbitration provision in Entergy and Bigge’s Alliance Agreement provides, “Any
    claim, dispute or controversy arising out of or relating to the Agreement, shall be submitted
    to binding arbitration.” By excluding these claims against subcontractors, the Alliance
    Agreement does not show that Entergy clearly and unmistakably delegated to an arbitrator the
    determination of the arbitrability of its tort claims against Seimen’s subcontractors. Further,
    because the Alliance Agreement specifically excludes Entergy’s tort claims against Bigge for
    damages to property and economic loss, these claims do not arise out of or relate to the
    Alliance Agreement.2 See Walton v. Lewis, 
    337 Ark. 45
    , 
    987 S.W.2d 262
    (1999) (holding that
    tort claims asserted by an employee did not fall under the subject matter of the arbitration
    agreement). Accordingly, we need not address Bigge’s remaining arguments whether they
    may enforce the arbitration agreement as third-party beneficiaries or that Entergy is estopped
    from denying the applicability of the arbitration provision. 
    Id. at 53,
    987 S.W.2d at 267.
    2
    Without stating any basis for its position, the majority opines that “Article 51, which
    limits the recovery of consequential damages, has no bearing on the issues before this court.”
    The majority’s dismissive remark is nothing more than a bare assertion that it does not even
    attempt to support.
    17
    Cite as 
    2015 Ark. 58
    BAKER, J., joins in this concurrence.
    Munson, Rowlett, Moore and Boone, P.A., by: Bruce E. Munson, Elizabeth A. Fletcher, and
    Beverly A. Rowlett; and Kane Russell Coleman & Logan PC, by: Lawrence T. Bowman and Sanjay
    K. Minocha, for appellants.
    Quattlebaum, Grooms, Tull & Burrow, PLLC, by: Steven W. Quattlebaum, John E. Tull
    III, and Michael N. Shannon, for appellees.
    18