Montana Public Employees' Ass'n v. City of Bozeman ( 2015 )


Menu:
  •                                                                                             March 3 2015
    DA 14-0333
    Case Number: DA 14-0333
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    
    2015 MT 69
    MONTANA PUBLIC EMPLOYEES’ ASSOCIATION,
    (MPEA), a not for profit corporation,
    Plaintiff, Counterclaim Defendant, and Appellant,
    v.
    CITY OF BOZEMAN, MONTANA,
    Defendant, Counterclaimant, and Appellee.
    APPEAL FROM:           District Court of the Eighteenth Judicial District,
    In and For the County of Gallatin, Cause No. DV 13-232A
    Honorable Holly Brown, Presiding Judge
    COUNSEL OF RECORD:
    For Appellant:
    Carter N. Picotte, Attorney at Law, Helena, Montana
    For Appellee:
    Jason S. Ritchie; Michael P. Manning; Michelle M. Sullivan, Holland &
    Hart LLP, Billings, Montana
    Submitted on Briefs: December 31, 2014
    Decided: March 3, 2015
    Filed:
    __________________________________________
    Clerk
    Justice Beth Baker delivered the Opinion of the Court.
    ¶1     The Montana Public Employees’ Association (MPEA) filed this action in the
    Eighteenth Judicial District Court, Gallatin County, seeking a declaratory judgment
    requiring the City of Bozeman to submit to arbitration. Concluding that the dispute
    between MPEA and the City is not arbitrable, the District Court entered summary
    judgment in the City’s favor. We restate the issue on appeal as whether the District Court
    correctly awarded summary judgment to the City and denied summary judgment to
    MPEA based on the procedural arbitrability of the dispute. We conclude that the District
    Court improperly resolved a question of procedural arbitrability. Because we further
    conclude that the dispute is substantively arbitrable, we vacate and remand for entry of
    summary judgment in MPEA’s favor.
    PROCEDURAL AND FACTUAL BACKGROUND
    ¶2     In 2009, Robert Chase was a building inspector for the City and a union member
    of MPEA. In March of that year, the City dismissed Chase. Chase claims that the
    dismissal was improper. The collective bargaining agreement between MPEA and the
    City (the Agreement) provides a procedure for addressing employee grievances.
    Following the first three steps of this procedure, Chase and MPEA successively
    submitted Chase’s grievance to a supervisor, a management representative, and the City
    Manager—all of whom denied the grievance.
    ¶3     The grievance procedure’s fourth step calls for notifying the City Manager of the
    decision to arbitrate the grievance and, within ten days of that notice, “call[ing] upon the
    2
    Montana Board of Personnel Appeals for a list of seven potential arbitrators” from which
    the parties may choose their arbitrator. The Agreement further states, “A grievance not
    filed or advanced by the grievant within the time limits provided shall be deemed
    permanently withdrawn as having been settled on the basis of the decision most recently
    received.” MPEA gave timely notice to the City Manager of its decision to arbitrate
    Chase’s grievance, but then failed to timely request a list of potential arbitrators from the
    Montana Board of Personnel Appeals.
    ¶4     In June 2010, over a year after the dispute first arose, MPEA contacted the City to
    proceed with arbitration. The City declined to cooperate due to MPEA’s failure to call
    upon the Montana Board of Personnel Appeals in a timely manner. In April 2013—over
    four years after the dispute first arose—MPEA filed this lawsuit, seeking a declaratory
    judgment that the City must participate in arbitration. The next month, the City asserted
    a counterclaim for declaratory relief, requesting that the District Court declare that “there
    remains no grievance to arbitrate . . . because it was not pursued pursuant to the terms of
    the [Agreement].” In 2014, both the City and MPEA requested summary judgment.
    Concluding that Chase’s grievance did not survive MPEA’s failure to follow the
    Agreement’s time limits, and that MPEA waived any right to arbitrate through its
    four-year delay, the District Court granted summary judgment and issued declaratory
    relief to the City. MPEA appeals.
    3
    STANDARD OF REVIEW
    ¶5     We apply de novo review to an entry of summary judgment, using the same M. R.
    Civ. P. 56 standards as a district court. Estate of Hendrick v. Lamarch, 
    2014 MT 118
    ,
    ¶ 7, 
    375 Mont. 74
    , 
    324 P.3d 1202
    . Summary judgment is appropriate if the moving party
    shows the absence of a genuine issue of material fact and proves that it is entitled to
    judgment as a matter of law. M. R. Civ. P. 56(c)(3); Hendrick, ¶ 7. Where, as here, the
    parties do not dispute the material facts, we determine whether either party is entitled to
    judgment under the law. See Clark Fork Coal. v. Mont. Dep’t of Env’t Quality, 
    2008 MT 407
    , ¶ 19, 
    347 Mont. 197
    , 
    197 P.3d 482
    .
    DISCUSSION
    ¶6     An arbitration agreement is a matter of contract law. Section 27-5-114, MCA;
    Kelker v. Geneva-Roth Ventures, Inc., 
    2013 MT 62
    , ¶ 11, 
    369 Mont. 254
    , 
    303 P.3d 777
    .
    The role of a court interpreting a contract is to effectuate the mutual intentions of the
    parties as reflected in the document’s clear and explicit language. Sections 28-3-301,
    -301, MCA; A.M. Welles, Inc. v. Mont. Materials, Inc., 
    2015 MT 38
    , ¶ 8, ___ Mont. ___,
    ___ P.3d ___. When parties enter an agreement to arbitrate, they manifest the intention
    to have an arbitrator and not a judge resolve matters that fall within the terms of the
    agreement. See, e.g., United Steelworkers of Am. v. Am. Mfg. Co., 
    363 U.S. 564
    , 568, 
    80 S. Ct. 1343
    , 1346 (1960) (explaining that a court has “no business” replacing what the
    parties bargained for—an arbitrator). The distinction between substantive arbitrability
    4
    and procedural arbitrability effectuates that intention. See John Wiley & Sons, Inc. v.
    Livingston, 
    376 U.S. 543
    , 557-59, 
    84 S. Ct. 909
    , 918-19 (1964).
    ¶7     Questions of substantive arbitrability concern whether a valid arbitration
    agreement exists and whether the subject matter of the dispute falls within the arbitration
    agreement’s terms. Howsam v. Dean Witter Reynolds, 
    537 U.S. 79
    , 84, 
    123 S. Ct. 588
    ,
    592 (2002). A court has authority to decide an issue of substantive arbitrability. AT&T
    Techs., Inc. v. Commc’ns Workers of Am., 
    475 U.S. 643
    , 649, 
    106 S. Ct. 1415
    , 1418
    (1986).
    ¶8     “Once it is determined . . . that the parties are obligated to submit the subject
    matter of the dispute to arbitration, procedural questions which grow out of the dispute
    and bear on its final disposition should be left to the arbitrator.” John 
    Wiley, 376 U.S. at 557
    , 84 S. Ct. at 918.        Questions of procedural arbitrability include “whether
    prerequisites such as time limits, notice, laches, estoppel, and other conditions precedent
    to an obligation to arbitrate have been met . . . .” 
    Howsam, 537 U.S. at 85
    , 123 S. Ct. at
    592 (emphasis removed) (citation omitted).         Unless the parties expressly provide
    otherwise in their agreement, only an arbitrator, and not a court, has authority to decide
    an issue of procedural arbitrability. 
    Howsam, 537 U.S. at 85
    , 123 S. Ct. at 592-93.
    ¶9     We have adopted the distinction between procedural and substantive arbitrability
    in Montana. In Int’l Bhd. of Elec. Workers, AFL-CIO, Local 1638 v. Montana Power
    Co., 
    280 Mont. 55
    , 
    929 P.2d 839
    (1996) (IBEW), an employer claiming that an employee
    withdrew or waived his grievance sought a court order preventing arbitration. IBEW, 
    280 5 Mont. at 56
    , 
    59, 929 P.2d at 840
    , 842. We noted that a “substantive challenge to
    arbitrability is one where a grievance is not within the scope of the grievance and
    arbitration provisions of the collective bargaining agreement between the parties,”
    whereas “a procedural challenge is presented when the arbitrability of an indisputably
    arbitrable issue is impeded in some way.” 
    IBEW, 280 Mont. at 60
    , 929 P.2d at 842-43
    (citation omitted). Because the withdrawal and waiver issues were “procedural, not
    substantive,” we determined that it “should be resolved by the arbitrator, not [by] the
    court,” and reversed the District Court’s order preventing further arbitration. 
    IBEW, 280 Mont. at 61
    , 929 P.2d at 843.
    ¶10    Here, the District Court concluded that MPEA’s failure to follow the time limits
    for requesting a list of arbitrators from the Montana Board of Personnel Appeals meant
    that Chase’s grievance was no longer arbitrable. On appeal, the City similarly argues that
    it has no duty to arbitrate due to MPEA’s failure to follow time limits and conditions
    precedent to arbitration.   But an arbitration agreement’s time limits and conditions
    precedent to arbitration are procedures that bear on arbitrability. Whether a dispute
    remains arbitrable despite the failure to follow these procedures is a classic question of
    procedural arbitrability that is for an arbitrator and not for a court to decide. 
    Howsam, 537 U.S. at 85
    , 123 S. Ct. at 592-93.
    ¶11    The City therefore attempts to recast its argument as one of substantive
    arbitrability. The City argues that there is no dispute to arbitrate in this case because the
    6
    Agreement states that a “grievance not filed or advanced by the grievant within the time
    limits provided shall be deemed permanently withdrawn as having been settled.”
    ¶12    In John Wiley, the Supreme Court addressed an arbitration agreement with similar
    language. The contract in John Wiley stated that the “failure by either party to file the
    grievance with this time limitation shall be construed and be deemed to be abandonment
    of the grievance.” John 
    Wiley, 376 U.S. at 556
    n. 
    11, 84 S. Ct. at 917
    n. 11. The
    Supreme Court held that questions concerning the contractual prerequisites that
    conditioned the parties’ duties to arbitrate were questions of procedural arbitrability to be
    decided by an arbitrator. John 
    Wiley, 376 U.S. at 557
    -59, 84 S. Ct. at 918-19.
    ¶13    There is no material difference between the agreement construed in John Wiley
    and the grievance provision at issue in this case. Replacing “abandon[ed]” (as used in
    John Wiley) with “withdrawn” (as used in this case) does not change what would
    otherwise be a question of procedural arbitrability into a question of substantive
    arbitrability. As the Supreme Court observed, “[I]t best accords with the usual purposes
    of an arbitration clause . . . to regard procedural disagreements not as separate disputes
    but as aspects of the dispute which called the grievance procedures into play.” John
    
    Wiley, 376 U.S. at 559
    , 84 S. Ct. at 919. Absent clear language showing that parties to an
    arbitration agreement intend questions of procedural arbitrability to be determined by a
    judge, the role of a court is to leave these questions to an arbitrator.
    ¶14    The City also argues that the District Court did not have jurisdiction to order the
    parties to arbitrate this dispute because there was no longer a live dispute to arbitrate.
    7
    But § 27-5-115(1), MCA, provides that a party to an arbitration agreement can move to
    compel arbitration and that a district court shall order arbitration if the dispute is
    arbitrable and the opposing party has refused to arbitrate.            We have interpreted
    § 27-5-115(1) to require that a district court determine whether the dispute is
    substantively arbitrable, but we leave procedural arbitrability questions to the arbitrator.
    See Greater Missoula Area Fed’n of Early Childhood Educators & Related Pers. v. Child
    Start, Inc., 
    2009 MT 362
    , ¶¶ 26-30, 
    353 Mont. 201
    , 
    219 P.3d 881
    .                “[C]ourts are
    empowered to resolve disputes that solely involve whether a particular claim should be
    resolved in court or arbitration.”     Greater Missoula, ¶ 26 (quoting Klay v. United
    Healthgroup, Inc., 
    376 F.3d 1092
    , 1109 (11th Cir. 2004)). The District Court was “in a
    position to grant effective relief” by either granting or denying MPEA’s request that the
    City be required to submit to arbitration. Greater Missoula, ¶ 29. MPEA’s claim is
    accordingly justiciable.
    ¶15    The District Court also determined that MPEA waived the right to arbitrate
    through its failure to pursue that right diligently. A party asserting that another party has
    waived the right to arbitrate bears the burden of demonstrating (1) the other party’s
    knowledge of the right to arbitrate, (2) acts by the other party that are inconsistent with
    the right to arbitrate, and (3) resulting prejudice. Downey v. Christensen, 
    251 Mont. 386
    ,
    389, 
    825 P.2d 557
    , 559 (1992). On appeal, the City contends that it met this burden and
    that waiver of the right to arbitrate is a question of substantive arbitrability for a judge to
    determine.
    8
    ¶16    In IBEW, an employer argued that an employee’s signature on a contract
    withdrawing the employee’s grievance waived the union’s right to arbitrate that
    grievance. 
    IBEW, 280 Mont. at 59
    , 929 P.2d at 842. We determined that “whether the
    grievance brought by the Union on [the employee’s] behalf can be waived through a
    written release” to which the union was not a party was a question of procedural
    arbitrability for an arbitrator to determine in the first instance. 
    IBEW, 280 Mont. at 59
    -61, 929 P.2d at 842-43.
    ¶17    By contrast, we have evaluated on the merits claims raising a party’s waiver of
    arbitration where the party participated in judicial proceedings in the same dispute. For
    example, in Holm-Sutherland Co., Inc. v. Town of Shelby, 
    1999 MT 150
    , 
    295 Mont. 65
    ,
    
    982 P.2d 1053
    —in which the party seeking arbitration had actively participated in
    litigation, demanded a jury trial, and did not seek arbitration until shortly before trial—
    we found waiver instead of leaving that decision to an arbitrator. Holm-Sutherland,
    ¶¶ 26-34. And in Downey, we concluded that a party who participated in litigation did
    not waive its right to seek arbitration where, from the outset, the party asserted its right to
    arbitration. 
    Downey, 251 Mont. at 391-92
    , 825 P.2d at 560-61 (“Answering on the
    merits, asserting a counterclaim, and participating in discovery, without more, is
    insufficient to constitute waiver.”). See also Stewart v. Covill & Basham Constr., LLC,
    
    2003 MT 220
    , ¶ 13, 
    317 Mont. 153
    , 
    75 P.3d 1276
    (filing of construction lien “was not to
    advance litigation, but rather to protect [the party’s] statutorily created security interest in
    the property,” and participation in mediation did not constitute waiver, where party
    9
    asserted intent to enforce arbitration agreement if mediation failed); Gordon v. Kuzara,
    
    2012 MT 206
    , ¶¶ 25-27, 
    366 Mont. 243
    , 
    286 P.3d 895
    (participation in litigation
    concerning arbitration of previous petition for judicial dissolution did not waive party’s
    right to seek arbitration on a different matter).
    ¶18    The City’s waiver argument rests on MPEA’s four-year delay in invoking the
    Agreement and pursuing arbitration. While we concluded that Holm-Sutherland acted
    inconsistently with its contractual right to arbitrate by “embrac[ing] and engag[ing] in
    litigation for a lengthy period of time,” Holm-Sutherland, ¶ 26, MPEA did not act
    inconsistently with its right to arbitrate in this case—it just did not act. MPEA never
    litigated this dispute except to seek to compel arbitration. The City’s allegations of
    undue delay fall within the Supreme Court’s presumption that “allegations of waiver”
    through “laches, estoppel, and other conditions precedent to an obligation to arbitrate” are
    questions of procedural arbitrability that an arbitrator should decide. Howsam, 537 U.S.
    at 84-
    85, 123 S. Ct. at 592
    . We conclude that the City’s waiver argument is an issue for
    an arbitrator to determine.
    ¶19    What remains is the question whether this dispute is substantively arbitrable. The
    Agreement lays out rules related to discharging employees. The Agreement’s arbitration
    clause is intended to address “all disputes involving the interpretation, application or
    alleged violation of a specific provision of” the Agreement. There appears to be no
    dispute that the dismissal of an employee is a subject matter that the parties agreed to
    arbitrate.   Nor does there appear to be a dispute about the validity of the parties’
    10
    agreement to arbitrate. Without evidence to the contrary, the dispute in this case is
    substantively arbitrable. We leave all other issues to the arbitrator.
    CONCLUSION
    ¶20    The District Court’s order granting summary judgment to the City is reversed. We
    remand for the District Court to enter summary judgment in MPEA’s favor and to issue
    an order compelling the City to arbitrate the remainder of this dispute—including any
    questions of procedural arbitrability that it wishes to raise.
    /S/ BETH BAKER
    We concur:
    /S/ MIKE McGRATH
    /S/ PATRICIA COTTER
    /S/ JAMES JEREMIAH SHEA
    /S/ JIM RICE
    11