State v. Perini Corporation (070558) , 221 N.J. 412 ( 2015 )


Menu:
  •                                                     SYLLABUS
    (This syllabus is not part of the opinion of the Court. It has been prepared by the Office of the Clerk for the
    convenience of the reader. It has been neither reviewed nor approved by the Supreme Court. Please note that, in the
    interest of brevity, portions of any opinion may not have been summarized.)
    State v. Perini Corporation (A-121/122/123/135-11) (070558)
    Argued September 23, 2014 -- Decided April 30, 2015
    CUFF, P.J.A.D. (temporarily assigned), writing for a unanimous Court.
    In this appeal, the Court must determine when the ten-year limitations period of the statute of repose,
    N.J.S.A. 2A:14-1.1(a), begins to run with respect to the installation of a high temperature hot water (HTHW) system
    of a multi-phase construction project. In addition, the Court is asked to decide whether the statute of repose applies
    to claims pertaining exclusively to allegedly defective materials supplied for the HTHW system.
    In February 1995, the State executed a contract with Perini Corporation (Perini) to design and build South
    Woods in Bridgeton (the Project), a twenty-six building medium- and minimum-security correctional facility. Perini
    subcontracted with L. Robert Kimball & Associates, Inc. (Kimball) as the architect and engineer. Defendant Natkin
    & Company (Natkin) was designated the principal contractor for heating, ventilation, and air conditioning (HVAC).
    The design that Kimball provided to Perini included an underground HTHW distribution system to serve the entire
    Project. It also included a central plant from which the hot water was distributed to the various buildings that
    comprised the Project. Perma-Pipe, Inc. (Perma-Pipe) manufactured the underground piping used in the HTHW
    system. Natkin furnished and installed the underground piping system and the boilers and heat exchangers housed
    in the central plant. Defendant Jacobs Facilities, Inc. (Jacobs), formerly known as CRSS Constructors, Inc., was
    retained by the State to provide construction oversight services.
    The contract provided that the Project would be constructed in three phases. Phase I included the central
    plant and certain inmate housing units. Certificates of substantial completion for those elements were executed on
    May 16, 1997. Approximately 960 inmates occupied the Phase I housing units soon thereafter. Phase IIA included
    housing units for another 960 inmates. Certificates of substantial completion for those buildings were executed
    between July 15, 1997 and October 27, 1997. Phase II encompassed approximately ten buildings, including a
    minimum-security unit housing more than 1000 inmates, with May 1, 1998, as the date of substantial completion.
    The various buildings comprising the Project were connected to the HTHW distribution system as they were
    completed. A certificate of substantial completion was not issued specifically for the HTHW system.
    On April 28, 2008, the State filed a complaint against Perini, Kimball, Natkin, Jacobs, and Perma-Pipe in
    which it alleged that the HTHW system failed in March 2000, and on several subsequent occasions, and that these
    failures were caused by various defects including design defects, defective site preparation for the pipes, defective
    pipes, and deficient system design. The State asserted breach of contract against Perini, negligence and professional
    malpractice against Kimball, negligence and breach of contract against Natkin, and breach of contract against
    Jacobs. Against Perma-Pipe, the State asserted a claim under the New Jersey Products Liability Act (PLA), N.J.S.A.
    2A:58C-1 to -11, as well as breach of implied warranties, negligence, and strict liability in tort.
    All defendants moved for summary judgment, arguing that the Project was substantially complete well
    before April 28, 1998, and that, therefore, the statute of repose barred the State’s complaint. The State contended
    that the date of substantial completion of the Project was not until May 1, 1998, if not December 1998. Relying
    primarily on the occupancy of inmates at the facility on or before April 28, 1998, the court determined that the
    HTHW system was substantially complete before April 28, 1998. Therefore, the trial court found that the State’s
    complaint was barred by the ten-year statute of repose and granted summary judgment in favor of contractor-
    defendants Perini, Kimball, Natkin, and Jacobs. On the other hand, the trial court denied Perma-Pipe’s motion for
    summary judgment, concluding that it was a manufacturer of goods and therefore its liability was governed by the
    PLA and the statute of repose did not apply to it.
    The Appellate Division reversed the orders granting summary judgment in favor of defendants Perini,
    Kimball, Natkin, and Jacobs. The panel held that the statute of repose was triggered when defendants substantially
    completed their work on the entire project, no earlier than May 1, 1998, the date when the minimum-security unit
    and garage were certified as substantially complete. The panel determined that the State’s April 28, 2008 complaint
    was timely filed. In addition, the Appellate Division held that the statute of repose does not bar the State’s claims
    against Perma-Pipe because it was a manufacturer of a product rather than a designer or installer of a system.
    The Court granted the contractor-defendants’ motions for leave to appeal, 
    210 N.J. 476
    (2012), and Perma-
    Pipe’s cross-motion for leave to appeal, limited to the issue of whether the statute of repose applies to bar the State’s
    claims against it, 
    211 N.J. 606
    (2012).
    HELD: The statute of repose does not begin to run on claims involving an improvement that serves an entire
    project such as a high temperature hot water (HTHW) system -- including those parts constructed in multiple,
    uninterrupted phases -- until all buildings served by the improvement have been connected to it. In addition, the
    statute of repose does not apply to claims relating solely to manufacturing defects in a product used in the HTHW
    system.
    1. Prior to the enactment of the statute of repose, liability for deficiencies in a construction project was governed by
    the common law “completed and accepted rule.” In Totten v. Gruzen, 
    52 N.J. 202
    , 210 (1968), this Court replaced
    that rule with the limitations on liability derived from ordinary negligence principles. In 1967, New Jersey adopted
    a statute of repose, N.J.S.A. 2A:14-1.1(a). The statute applies only to work that constitutes an “improvement to real
    property.” Generally, “an improvement to real property permanently increases the property’s value.” Ebert v. S.
    Jersey Gas Co., 
    157 N.J. 135
    , 139 (1999). (pp. 14-17)
    2. Calculation of the ten-year limitations period for the statute of repose generally commences one day after
    issuance of the certificate of substantial completion for the project. Substantial completion is “the date when
    construction is sufficiently complete . . . so the owner can occupy or utilize the building.” Russo Farms, Inc. v.
    Vineland Bd. of Educ., 
    144 N.J. 84
    , 117 (1996). When a designer, planner, or person participating in the
    construction of an improvement to real property has continuing responsibility throughout the construction of the
    project or a specific improvement, the ten-year limitations period commences when the project has been certified as
    substantially complete. (pp. 17-20)
    3. The HTHW system is an improvement to real property and the work performed on this system falls within the
    scope of the statute of repose. The HTHW system is designed to form a unified whole that interacts with and is
    connected to every structure of the prison complex. Neither the nature of the HTHW system, the course of
    construction, nor defendants’ role in the construction of the Project permits the issue date of the Phase I certificates
    of substantial completion to trigger the statute of repose time calculation. The record also does not support a finding
    that the HTHW system was substantially complete on May 16, 1997, after the issuance of the certificate of
    substantial completion for the central plant. As a system designed to supply heat and hot water to every building in
    the Project, the Court is loath to embrace an application of the statute of repose that would permit separate trigger
    dates for each section of the HTHW system as a building it serves comes on line. The ten-year statute of repose
    limitations period commenced to run on the day after the final certificates of substantial completion issued for the
    final buildings served by the HTHW system. The final certificates were issued on May 1, 1998. The State filed its
    complaint on April 28, 2008. The statute of repose therefore does not bar the complaint. (pp. 20-27)
    4. Manufacturers of standardized products and sellers of such products are not subject to the statute of repose, but
    rather “are covered by the statute of limitations applicable to the [PLA].” Dziewiecki v. Bakula, 
    180 N.J. 528
    , 532
    (2004). Perma-Pipe’s role was that of a manufacturer of a product used in the construction of the HTHW system.
    While the piping for the Project served a specialized purpose to meet the specific dimensions and specifications of
    the system designed by Kimball and installed by Natkin, the piping and the various fittings manufactured by Perma-
    Pipe are nonetheless a product and Perma-Pipe cannot take refuge in the statute of repose. (pp. 27-30)
    The judgment of the Appellate Division is AFFIRMED as MODIFIED.
    CHIEF JUSTICE RABNER; JUSTICES ALBIN and SOLOMON; and JUDGE FUENTES
    (temporarily assigned) join in JUDGE CUFF’s opinion. JUSTICES LaVECCHIA, PATTERSON and
    FERNANDEZ-VINA did not participate.
    2
    SUPREME COURT OF NEW JERSEY
    A-121/122/123/135
    September Term 2011
    070558
    STATE OF NEW JERSEY,
    Plaintiff-Respondent,
    v.
    PERINI CORPORATION, L. ROBERT
    KIMBALL & ASSOCIATES, INC.,
    PERMA-PIPE, INC., NATKIN &
    COMPANY, JACOBS FACILITIES,
    INC., Successor-in-Interest
    to CRSS Constructors, Inc.,
    FIDELITY AND DEPOSIT CO. OF
    MARYLAND, SWISS REINSURANCE
    AMERICA CORPORATION,
    Successor-in-Interest to
    North America Reinsurance
    Corporation, MUNICH
    REINSURANCE AMERICA, INC.,
    Successor-in-Interest to
    American Re-Insurance
    Company, UNITED STATES
    FIDELITY AND GUARANTY
    COMPANY,
    Defendants-Appellants.
    STATE OF NEW JERSEY,
    Plaintiff-Respondent,
    v.
    PERINI CORPORATION, L. ROBERT
    KIMBALL & ASSOCIATES, INC.,
    NATKIN & COMPANY, JACOBS
    FACILITIES, INC., Successor-
    in-Interest to CRSS
    Constructors, Inc., FIDELITY
    AND DEPOSIT CO. OF MARYLAND,
    1
    SWISS REINSURANCE AMERICA
    CORPORATION, Successor-in-
    Interest to North America
    Reinsurance Corporation,
    MUNICH REINSURANCE AMERICA,
    INC., Successor-in-Interest
    to American Re-Insurance
    Company, UNITED STATES
    FIDELITY AND GUARANTY
    COMPANY,
    Defendants,
    and
    PERMA-PIPE, INC.,
    Defendant-Appellant.
    Argued September 23, 2014 – Decided April 30, 2015
    On appeal from the Superior Court, Appellate
    Division, whose opinion is reported at 
    425 N.J. Super. 62
    (App. Div. 2012).
    Andrew J. Carlowicz, Jr., argued the cause
    for appellant L. Robert Kimball &
    Associates, Inc. (Hoagland, Longo, Moran,
    Dunst & Doukas, attorneys).
    Peter J. Smith argued the cause for
    appellants Perini Corporation, Fidelity and
    Deposit Co. of Maryland, Swiss Reinsurance
    America Corporation, Munich Reinsurance
    America, Inc., and United States Fidelity
    and Guaranty Company (Connell Foley,
    attorneys; Mr. Smith and Thomas J. O’Leary,
    on the briefs).
    James T. Malysiak, a member of the Illinois
    bar, argued the cause for appellant Jacobs
    Facilities, Inc. (Margolis Edelstein,
    attorneys; Bruce E. Barrett, on letter in
    lieu of brief).
    2
    Vincent P. Tomkiewicz, a member of the
    Illinois bar, argued the cause for appellant
    Perma-Pipe, Inc. (McLaughlin & Cooper,
    attorneys; Mr. Tomkiewicz, William F.
    Hartigan, Jr., and Edward F. Ruberry, a
    member of the Illinois bar, on the briefs).
    Christopher A. Edwards, Deputy Attorney
    General, argued the cause for respondent
    (John J. Hoffman, Acting Attorney General of
    New Jersey, attorney; Lewis A. Scheindlin,
    Assistant Attorney General, of counsel; Mr.
    Edwards, Wayne J. Martorelli, Deputy
    Attorney General, on the briefs).
    Patrick J. Greene, Jr., submitted a brief on
    behalf of amicus curiae Building Contractors
    Association of New Jersey (Peckar &
    Abramson, attorneys; Mr. Greene, Charles F.
    Kenny, and Frank A. Hess, on the brief).
    JUDGE CUFF (temporarily assigned) delivered the opinion of
    the Court.
    In this appeal, the Court must determine when the ten-year
    limitations period of the statute of repose, N.J.S.A. 2A:14-
    1.1(a), begins to run with respect to the installation of a high
    temperature hot water (HTHW) system of a multi-phase
    construction project.   In addition, the Court is asked to decide
    whether the statute of repose applies to claims pertaining
    exclusively to allegedly defective materials supplied for the
    HTHW system.
    The sole focus of this case is an allegedly defective HTHW
    system that services the South Woods State Prison (South Woods).
    Built to mitigate the “over-crowded conditions” experienced by
    3
    the Department of Corrections, the contract governing the design
    and construction of the facility provided that housing units for
    more than 3000 inmates and all accessory structures would be
    constructed in three phases.    These phases were designed to
    allow the State to begin housing prisoners in orderly and
    expeditious waves.     Soon after the construction of South Woods
    was completed, the HTHW system experienced a series of
    widespread failures.
    As a result of the failure of the HTHW system, the State of
    New Jersey (State) filed suit against the entities involved in
    the design and construction of South Woods and the HTHW system.
    The State filed its complaint on April 28, 2008, more than ten
    years after it began using the HTHW system and housing the first
    group of inmates, but less than ten years after the system was
    connected to all of the buildings constructed under the
    contract.   The issue before the Court is whether the ten-year
    statute of repose commenced to run when the first inmates
    occupied the correctional facility or when the final buildings,
    including the 1000-plus bed minimum-security unit, were
    connected to the HTHW system.
    We hold that the statute of repose does not begin to run on
    claims involving an improvement that serves an entire project       -
    - including those parts constructed in multiple, uninterrupted
    phases -- until all buildings served by the improvement have
    4
    been connected to it.   Here, the statute of repose did not bar
    any of the State’s claims because the three phases proceeded
    apace and the HTHW system was not complete until all buildings
    were connected to it.   In addition, we hold that the statute of
    repose does not apply to claims relating solely to manufacturing
    defects in a product used in the HTHW system.
    I.
    In February 1995, the State executed a contract with Perini
    Corporation (Perini) to design and build South Woods in
    Bridgeton (the Project), a 3176-bed medium- and minimum-security
    correctional facility, at a cost of approximately $203 million.
    Situated on an eighty-four-acre site, the Project consists of
    twenty-six buildings, including six general housing units, one
    detention unit, one minimum-security unit, and one
    inpatient/extended care unit.   The buildings received heat and
    hot water from the underground HTHW distribution system.   The
    Project was designed to be constructed in three phases, with all
    construction to be completed within 1095 days of issuance of the
    notice to proceed (NTP).
    In its contract with the State, Perini was designated the
    designer/builder.   It designated L. Robert Kimball & Associates,
    Inc. (Kimball) as the architect, the civil engineering
    consultant, the structural engineering consultant, the
    mechanical engineering consultant, the electrical engineering
    5
    consultant, the detention equipment consultant, and the
    electronic security consultant.       Perini also designated various
    other entities as principal contractors or main contractors for
    specific portions of the work.    Defendant Natkin & Company
    (Natkin) was designated the principal contractor for heating,
    ventilation, and air conditioning (HVAC).       Defendant Jacobs
    Facilities, Inc. (Jacobs), formerly known as CRSS Constructors,
    Inc., was retained by the State to provide construction
    oversight services.
    The design that Kimball provided to Perini included an
    underground HTHW distribution system to serve the entire
    Project.   It also included a central plant where water was
    heated by a series of boilers and heat exchangers and from which
    the hot water was distributed to the various buildings that
    comprised the Project.   The hot water flowed through a network
    of underground pipes consisting of insulated black steel carrier
    piping within a galvanized steel casing.       Perma-Pipe, Inc.
    (Perma-Pipe) manufactured the underground piping used in the
    HTHW system.   Pursuant to its subcontract with Perini, Natkin
    furnished and installed the underground piping system and the
    boilers and heat exchangers housed in the central plant.
    The contract provided that the Project would be constructed
    in three phases –- Phase I, Phase IIA, and Phase II -- but the
    entire project was to be completed 1095 calendar days following
    6
    issuance of the NTP.    The contract also provided that Phase I
    was to be completed no later than 730 days from issuance of the
    NTP, Phase IIA was to be completed no later than 910 calendar
    days from issuance of the NTP, and Phase II, no later than 1095
    days from issuance of the NTP.
    Phase I encompassed the central plant, perimeter fencing,
    site work within the perimeter, a patrol roadway, security and
    fire elements of the Project, and certain inmate housing units.
    The central plant contained the boilers and heat exchangers for
    the HTHW system.    Certificates of substantial completion for
    those various elements were executed on May 16, 1997.
    Approximately 960 inmates occupied the Phase I housing units
    soon thereafter.    Phase IIA encompassed several other buildings,
    including housing units for another 960 inmates.    Certificates
    of substantial completion for those buildings were executed
    between July 15, 1997 and October 27, 1997.    Phase II
    encompassed approximately ten buildings, including a minimum-
    security unit housing more than 1000 inmates and a garage.       The
    certificates of substantial completion for the minimum-security
    unit and the garage list May 1, 1998, as the date of substantial
    completion.   The various buildings comprising the Project were
    connected to the HTHW distribution system as they were
    completed.    A certificate of substantial completion was not
    issued specifically for the HTHW system.
    7
    II.
    On April 28, 2008, the State filed a complaint against
    Perini, Kimball, Natkin, Jacobs, and Perma-Pipe in which it
    alleged that the HTHW system designed by Kimball, constructed by
    Perini and Natkin, and overseen by Jacobs failed in March 2000
    and on several subsequent occasions.   The State alleged that
    since the first failure in March 2000, “there have been a total
    of ten (10) HTHW carrier pipe failures, including failures in
    both the supply and return pipelines” and failures of isolation
    valves.   The State alleged that the system failures were caused
    by various defects including design defects, defective site
    preparation for the pipes, defective pipes, and deficient system
    design.   Due to recurrent system failures, the State concluded
    that the entire system had to be replaced.   The State asserted
    breach of contract against Perini, negligence and professional
    malpractice against Kimball, negligence and breach of contract
    against Natkin, and breach of contract against Jacobs.    Against
    Perma-Pipe, the State asserted a claim under the New Jersey
    Products Liability Act (PLA), N.J.S.A. 2A:58C-1 to -11, as well
    as breach of implied warranties, negligence, and strict
    liability in tort.
    All defendants moved for summary judgment.    Each defendant
    argued that the Project was substantially complete well before
    April 28, 1998; therefore, the statute of repose, N.J.S.A.
    8
    2A:14-1.1(a), barred the State’s complaint.       The State contended
    that the date of substantial completion of the Project was not
    until May 1, 1998, if not December 1998.       The trial court
    granted summary judgment in favor of defendants Perini, Kimball,
    Natkin, and Jacobs.   Relying primarily on the occupancy of
    inmates at the facility on or before April 28, 1998, the court
    determined that the HTHW system was substantially complete
    before April 28, 1998.   Therefore, the trial court found that
    the State’s complaint was barred by the ten-year statute of
    repose.   On the other hand, the trial court denied Perma-Pipe’s
    motion for summary judgment.   The court concluded that Perma-
    Pipe was a manufacturer of goods and therefore its liability was
    governed by the PLA and the statute of repose did not apply to
    it.
    On leave granted, the Appellate Division reversed the
    orders granting summary judgment in favor of defendants Perini,
    Kimball, Natkin, and Jacobs and affirmed the order denying
    summary judgment to Perma-Pipe.       State v. Perini Corp., 425 N.J.
    Super. 62 (App. Div. 2012).    The panel concluded that the
    separate phases of a project can have separate trigger dates for
    the statute of repose.   
    Id. at 78.
        However, the panel held that
    regardless of the nature of the project, the statute of repose
    does not provide for separate trigger dates for components of a
    project that do not qualify as discrete “improvements to real
    9
    property.”    
    Ibid. The panel determined
    that the record did not
    support a finding that the HTHW system was a separate
    improvement to real property.    
    Id. at 79.
      Therefore, the
    statute of repose was triggered when defendants substantially
    completed their work on the entire project.    
    Ibid. Accordingly, the panel
    held that the statute of repose was triggered no
    earlier than May 1, 1998, the date when the minimum-security
    unit and garage were certified as substantially complete, and
    the State’s April 28, 2008 complaint was timely filed.     
    Ibid. In addition, the
    Appellate Division affirmed the trial court’s
    holding that the statute of repose does not bar the State’s
    claims against Perma-Pipe because it was a manufacturer of a
    product rather than a designer or installer of a system.       
    Id. at 80-81.
    We granted the contractor-defendants’ motions for leave to
    appeal, 
    210 N.J. 476
    (2012), and Perma-Pipe’s cross-motion for
    leave to appeal, limited to the issue of whether the statute of
    repose applies to bar the State’s claims against it, 
    211 N.J. 606
    (2012).   We also granted amicus curiae status to Building
    Contractors Association of New Jersey.
    III.
    A.
    Perini argues that the Appellate Division erred in
    concluding that the HTHW system was not a separate improvement
    10
    to real property within the meaning of the statute of repose.
    Perini maintains that the Appellate Division contravened its
    prior decisions in Port Imperial Condominium Ass’n v. K.
    Hovnanian Port Imperial Urban Renewal, Inc., 
    419 N.J. Super. 459
    (App. Div. 2011) and Brown v. Jersey Central Power & Light Co.,
    
    163 N.J. Super. 179
    (App. Div. 1978), certif. denied, 
    79 N.J. 489
    (1979), which deemed structural improvements that are
    integral to the structure itself to be “improvements to real
    property.”   Accordingly, Perini submits that the prison could
    not function without the HTHW system, and the statute of repose
    was triggered when the State began to house inmates at South
    Woods more than ten years prior to the filing of the complaint
    by the State.
    Similarly, Kimball argues that the statute of repose was
    triggered when the State took over beneficial use and operation
    of the HTHW system.   Kimball emphasizes that the State began
    using the HTHW system and started to house inmates in May 1997,
    after the substantial completion of the site work and the
    central plant, which housed the boilers for the HTHW system.
    Accordingly, Kimball submits that the statute of repose was
    triggered in May 1997 when the State was able to use the HTHW
    system, and that the trigger date is not affected by the
    completion of the minimum-security unit and the garage.
    B.
    11
    Perma-Pipe argues that it is also entitled to the
    protections of the statute of repose.    Perma-Pipe maintains that
    it was not merely a manufacturer of the piping for the HTHW
    system but was also involved in the design, planning, and
    installation of the system.    In addition, Perma-Pipe contends
    that it did not supply a “stock item” or standardized product
    for the Project, but rather a specialized system that required
    several design changes during construction.    Perma-Pipe also
    submits that the Appellate Division erred in interpreting
    Dziewiecki v. Bakula, 
    180 N.J. 528
    (2004), as establishing a
    blanket proposition that manufacturers are not subject to the
    statute of repose.   Accordingly, Perma-Pipe contends that the
    State’s complaint is untimely because the statute of repose was
    triggered in 1997 when the State began using the HTHW system and
    inmates occupied buildings in the first phase of the Project.
    C.
    The State maintains that its complaint was timely filed.
    In particular, the State argues that even though its claims
    relate only to the HTHW system, the ten-year limitations period
    is triggered by substantial completion of the entire Project,
    not just a portion of it.     It emphasizes that the HTHW system
    was designed to serve the entire Project.     As a result, the
    State submits that the Appellate Division correctly determined
    12
    that the statute of repose was triggered no earlier than May 1,
    1998, when the entire Project was substantially complete.
    Regarding Perma-Pipe’s appeal, the State maintains that the
    statute of repose does not apply to product liability claims.
    Moreover, the State argues that it did not assert any claims
    pertaining to Perma-Pipe’s other purported roles as designer and
    planner of the HTHW system.
    D.
    Amicus curiae Building Contractors Association of New
    Jersey (BCANJ) urges this Court to reverse the Appellate
    Division’s decision.   BCANJ contends that the panel failed to
    give effect to the certificates of substantial completion, which
    should have been interpreted as also declaring the components of
    a project, such as the HTHW system, as substantially complete.
    In addition, BCANJ argues that the Appellate Division
    inappropriately stated in dicta that individual subcontractors
    working on a component of a project would have separate trigger
    dates under the statute of repose.    BCANJ submits that this
    statement represents an unwarranted extension of this Court’s
    decision in Daidone v. Buterick Bulkheading, 
    191 N.J. 557
    (1997).   In particular, BCANJ argues that Daidone, which
    involved an owner acting as general contractor, should be
    confined to the facts of that case.    Otherwise, Daidone’s
    holding will unfairly burden the last remaining party on a
    13
    project with liability for the failures of the other parties to
    the contract.   Last, BCANJ asks this Court to hold that third-
    party claims for contractual indemnification and contribution
    will be deemed as having accrued on the date on which the
    plaintiff originally filed the action.
    IV.
    A.
    The first issue before the Court is whether defendants
    Perini, Kimball, Natkin, and Jacobs are entitled to summary
    judgment and dismissal of the complaint filed against them based
    on the statute of repose.   In reviewing a grant or denial of
    summary judgment, an appellate court is bound by the same
    standard as the trial court under Rule 4:46-2(c).    Town of
    Kearny v. Brandt, 
    214 N.J. 76
    , 91 (2013); Liberty Surplus Ins.
    Corp. v. Nowell Amoroso, P.A., 
    189 N.J. 436
    , 445-46 (2007).     We
    must “consider whether the competent evidential materials
    presented, when viewed in the light most favorable to the non-
    moving party, are sufficient to permit a rational factfinder to
    resolve the alleged disputed issue in favor of the non-moving
    party.”   Brill v. Guardian Life Ins. Co. of Am., 
    142 N.J. 520
    ,
    540 (1995).   To the extent that the grant or denial of summary
    judgment is based on an issue of law, we owe no deference to an
    interpretation of law that flows from established facts.
    
    Kearny, supra
    , 214 N.J. at 92.    Here, the date of the
    14
    commencement of the limitations period of the statute of repose
    is a question of law subject to plenary review.    See 
    ibid. (citing Manalapan Realty,
    L.P. v. Twp. Comm. of Manalapan, 
    140 N.J. 366
    , 378 (1995)).
    B.
    Prior to the enactment of the statute of repose, liability
    for deficiencies in a construction project was governed by the
    common law “completed and accepted rule.”   E.A. Williams, Inc.
    v. Russo Dev. Corp., 
    82 N.J. 160
    , 165 (1980).     In Totten v.
    Gruzen, 
    52 N.J. 202
    , 210 (1968), this Court repudiated the rule,
    replacing it with the limitations on liability derived from
    ordinary negligence principles.
    In 1967, New Jersey adopted a statute of repose.      N.J.S.A.
    2A:14-1.1(a) provides as follows:
    No action, whether in contract, in tort, or
    otherwise,   to   recover   damages  for   any
    deficiency in the design, planning, surveying,
    supervision or construction of an improvement
    to real property, . . . arising out of the
    defective   or   unsafe    condition   of   an
    improvement to real property, nor any action
    for contribution or indemnity for damages
    sustained on account of such injury, shall be
    brought against any person performing or
    furnishing the design, planning, surveying,
    supervision of construction or construction of
    such improvement to real property, more than
    10 years after the performance or furnishing
    of such services and construction.
    15
    As discussed in several prior opinions of the Court, the statute
    of repose responded to the expanding liability of contractors,
    builders, planners, and designers occasioned by the rejection of
    the “completed and accepted rule,” the expanding application of
    the discovery rule, and the evolving development of strict
    liability in tort for injuries arising from defective conditions
    in newly constructed buildings.    See, e.g., Horosz v. Alp
    Estates, Inc., 
    136 N.J. 124
    , 128 (1994); Newark Beth Israel Med.
    Ctr. v. Gruzen, 
    124 N.J. 357
    , 362 (1991); E.A. 
    Williams, supra
    ,
    82 N.J. at 165-66; O’Connor v. Altus, 
    67 N.J. 106
    , 117-19
    (1975); Rosenberg v. Town of N. Bergen, 
    61 N.J. 190
    , 194-98
    (1972).   The statute of repose is construed broadly to
    effectuate its purpose.     Town of 
    Kearny, supra
    , 214 N.J. at 93.
    The statute of repose applies only to work that constitutes
    an “improvement to real property.”      N.J.S.A. 2A:14-1.1(a).
    Generally, “an improvement to real property permanently
    increases the property’s value.”       Ebert v. S. Jersey Gas Co.,
    
    157 N.J. 135
    , 139 (1999).    When a court must determine whether
    work is an improvement to real property, it should consider
    “‘whether the modifications or addition enhances the use of the
    property, involves the expenditure of labor or money, is more
    than mere repair or replacement, adds to the value of the
    property, and is permanent in nature.’”       
    Ibid. (quoting Van Den
    16
    Hul v. Baltic Farmers Elevator Co., 
    716 F.2d 504
    , 508 (8th Cir.
    1983)).
    A service line carrying natural gas from a central main
    onto a residential property is an improvement to real property,
    
    id. at 139-40,
    as is an in-ground swimming pool installed at a
    home, 
    Dziewiecki, supra
    , 180 N.J. at 533.   A structural
    improvement, such as a transfer switch assembly cabinet, is an
    improvement to real property when it is “required for the
    structure to actually function as intended.”   
    Brown, supra
    , 163
    N.J. Super. at 195-96.
    Calculation of the ten-year limitations period for the
    statute of repose generally commences one day after issuance of
    the certificate of substantial completion for the project.
    Russo Farms, Inc. v. Vineland Bd. of Educ., 
    144 N.J. 84
    , 118
    (1996).   In Russo Farms, the Court explained that
    “‘[s]ubstantial completion has a definite meaning in the
    construction industry.’”   
    Id. at 117
    (quoting Perini Corp. v.
    Greate Bay Hotel & Casino, Inc., 
    129 N.J. 479
    , 500 (1992),
    overruled on other grounds by In re Tretina Printing, Inc. v.
    Fitzpatrick & Assocs., Inc., 
    135 N.J. 349
    (1994)).     As defined
    by the American Institute of Architects and incorporated in its
    model contract, it is “the date when construction is
    sufficiently complete . . . so the owner can occupy or utilize
    the building.”   
    Ibid. (internal quotations marks
    omitted).    To
    17
    be sure, there may be instances in which another event signals
    the commencement of the limitations period.   However, any
    departure from the date when the certificate of substantial
    completion is issued is driven by the facts of the individual
    case.   For example, in Town of 
    Kearny, supra
    , the Court held
    that the ten-year period under the statute of repose commenced
    on the date the first temporary certificate of occupancy was
    issued because the certificates of substantial completion bore
    neither the date of issuance nor the date of project 
    completion. 214 N.J. at 95-96
    .
    As noted in Town of Kearny, “[o]ur caselaw distinguishes
    between defendant contractors who are hired to perform limited
    services and defendants with supervisory responsibilities that
    span the entire project, in determining the date upon which the
    ten-year period begins for purposes of the [statute of repose].”
    
    Id. at 93.
      For example, in 
    Daidone, supra
    , the homeowners acted
    as the general contractor and subcontracted with several
    professionals and contractors to perform specific tasks in the
    design and construction of their 
    home. 191 N.J. at 560-61
    .    An
    architectural firm designed the house and another contractor
    installed the pilings for the home’s foundation.   
    Ibid. Following completion of
    their work, neither the architect nor
    the piling contractor performed any other work on the project.
    The Court concluded that the ten-year period of the statute of
    18
    repose commenced to run the day on which each contractor
    completed all work for the project.      
    Id. at 566.
      Similarly, in
    Hopkins v. Fox & Lazo Realtors, 
    242 N.J. Super. 320
    , 322 (App.
    Div. 1990), an architect had been retained by a residential
    developer to provide plans for a prototype house.      The architect
    performed no other work on the house plans and did not supervise
    the construction of any houses erected by the developer.       
    Ibid. Under these circumstances,
    the appellate panel concluded that
    “the statute’s purpose is best served by finding that the ten-
    year statutory period begins when the architect or contractor
    completes its task with respect to the property involved in the
    claim.”   
    Id. at 328.
    By contrast, when a designer, planner, or person
    participating in the construction of an improvement to real
    property has continuing responsibility throughout the
    construction of the project or a specific improvement, the ten-
    year limitations period commences when the project has been
    certified as substantially complete.      Town of 
    Kearny, supra
    , 214
    N.J. at 94.   Thus, in Town of Kearny, the statutory ten-year
    period commenced for the designer, who supervised construction
    of a police/fire facility and certified substantial completion
    of the work, when the first temporary certificate of occupancy
    was issued.   
    Ibid. In Welch v.
    Engineers, Inc., 
    202 N.J. Super. 387
    , 396 (App. Div. 1985), the Appellate Division refused to
    19
    segment a contractor’s responsibilities into stages for
    triggering the ten-year statute of repose period because the
    contractor had continuing responsibility for the project as a
    designer and builder.   The panel reasoned as follows:
    The functions of design, planning, supervision
    or construction of improvements to realty
    could   be  treated   either   separately   or
    unitarily when a single defendant performs two
    or more or indeed all of these functions, as
    [Engineers, Inc.] did here, without distorting
    or diluting the language used by the
    Legislature. . . . [W]e think the Legislature
    most likely meant that when a person rendered
    any   construction-related   services   on   a
    particular job, finished them and walked away
    from the job-site with the work accepted, that
    person could look back ten years and one day
    “after the performance or furnishing of such
    services and construction,” N.J.S.A. 2A:14-
    1.1, and know there was repose from liability.
    We do not think that the Legislature intended
    to let repose turn on serial cut-off dates
    accruing through various stages of the work,
    turning on fact-sensitive determinations and
    various analytic approaches to construction
    staging.
    [Ibid.]
    C.
    Here, the State argues that the Project must be considered
    a unitary undertaking, although the work was divided into phases
    and each individual building was occupied upon its completion.
    It emphasizes that construction continued, uninterrupted, on
    other housing units and accessory structures even after the
    first wave of inmates arrived.   Stated differently, the
    20
    completion of the Project did not experience a lull in activity
    weeks, months, or years in length.     Further, Perini, Natkin, and
    Jacobs were involved continuously from the commencement of
    construction through the completion of the Project.     Kimball, as
    the designer with supervision responsibilities, was involved
    continuously from the very inception of the Project through
    completion of construction.
    The State also contends that the certificate of substantial
    completion issued for the central plant, which housed the
    boilers used for the HTHW system, did not encompass the entirety
    of the HTHW system.     Rather, the network of underground pipes
    was a critical element of the HTHW system.    The State insists
    that the system could be considered substantially complete only
    when the last of the buildings it was designed to service were
    connected to the system.
    Perini, Kimball, Natkin, and Jacobs emphasize that the
    Project was constructed in phases; therefore, calculation of the
    ten-year period should commence with the completion of each
    phase of the Project.    In addition, they assert that the central
    plant was substantially completed on May 15, 1997, thereby
    triggering commencement of the ten-year repose period on May 16,
    1997, the day that the State assumed possession of the building.
    Based on that calculation, the ten-year period for filing the
    State’s complaint expired in May 2007, many months before the
    21
    April 28, 2008 filing date.    Implicit in this argument is the
    notion that the certificate of substantial completion for the
    central plant encompassed the entire HTHW system.
    Viewing the facts contained in the summary judgment record
    in the light most favorable to the State, the non-moving party,
    we conclude that the statute of repose does not bar the State’s
    complaint against defendants Perini, Kimball, Natkin, and
    Jacobs.    Several factors compel this conclusion.
    As a threshold matter, we conclude that the HTHW system is
    an improvement to real property.      Therefore, the work performed
    on this system falls within the scope of the statute of repose.
    We reject, however, the argument advanced by Perini and Kimball
    that the statute of repose was triggered on May 16, 1997, after
    the certificates of substantial completion were executed for the
    central plant and the housing units for the first wave of
    inmates.
    There can be no serious argument that the HTHW system is
    not an improvement to real property.     The system provides heat
    and hot water to every building in the Project.      The HTHW system
    does not simply enhance the use of and add value to the Project;
    South Woods could not function as a correctional facility
    housing more than 3000 inmates without heat and hot water.
    However, having determined that the HTHW system is an
    improvement to real property within the scope of the statute of
    22
    repose does not lead to the inexorable conclusion that
    completion of the central plant and occupancy of the initial
    group of inmate housing units triggered the ten-year statute of
    repose limitations period.   A “system” is “a regularly
    interacting or interdependent group of items forming a unified
    whole.”   System Definition, Merriam-Webster.com,
    http://www.merriam-webster.com/dictionary/system (last visited
    April 17, 2015).   Here, the HTHW system is designed to form a
    unified whole that interacts with and is connected to every
    structure of the prison complex.     The central plant where the
    boilers are located may be viewed as the origination point of
    this system, but it is by no means independent of the
    underground pipes that are connected to it to bring heat and hot
    water to every facet of the prison complex.     Neither the nature
    of the HTHW system, the course of construction, nor defendants’
    role in the construction of the Project permits the issue date
    of the Phase I certificates of substantial completion to trigger
    the statute of repose time calculation.
    Defendants Perini, Kimball, Natkin, and Jacobs were
    involved continuously throughout construction of the Project.
    Defendant Perini was the general contractor for the Project.
    Natkin, as the HVAC subcontractor, and Jacobs, as the
    construction supervisor, oversaw compliance with plans and
    specifications for every aspect of the Project.     They remained
    23
    continuously involved in the Project much like the designer and
    general contractor in Welch, and the designer/construction
    supervisor in Town of Kearny.     Kimball not only designed the
    Project but also provided oversight and consultation services
    throughout construction of the Project.     Unlike the architect in
    Hopkins, who submitted a prototype plan for a house and had no
    further involvement in the construction of any house based on
    that plan, or the designer in Daidone, who did nothing more than
    submit plans for the plaintiffs’ house, Kimball not only
    designed the Project but also remained continuously involved in
    the execution of its design.
    The record also provides no support for the position
    advanced by Perini, Kimball, Natkin, and Jacobs that the HTHW
    system was substantially complete on May 16, 1997, after the
    issuance of the certificate of substantial completion for the
    central plant.    Such a position ignores the design of the HTHW
    system of which the boilers are only a component part, albeit a
    critical part.    This argument also ignores that the HTHW system
    was not designed to only serve the buildings in Phase I that
    house 960 inmates.
    The HTHW system was designed to serve every building in
    the Project.     Therefore, contrary to defendants’ assertion, it
    is of no significance that the minimum-security unit is located
    outside of the fenced perimeter of the Project.     The minimum-
    24
    security unit, housing more than 1000 inmates, is a critical
    element of the Project and receives all of its heat and hot
    water from the HTHW system.   As a system designed to supply heat
    and hot water to every building in the Project, we are loath to
    embrace an application of the statute of repose that would
    permit separate trigger dates for each section of the HTHW
    system as a building it serves comes on line.   Such an approach
    is inconsistent with the purpose of the statute of repose and
    frustrates the ability of the owner to evaluate whether the
    system, as designed and constructed, operates as intended.
    The record also provides no support for the contention
    advanced by Perini, Kimball, Natkin, and Jacobs that the
    completion of each phase of the contract triggered the statute
    of repose for all work performed for that phase.   To the
    contrary, the record demonstrates work on the Project flowed
    virtually seamlessly from phase to phase once the NTP issued.
    The record also demonstrates that the purpose of the division of
    the Project into phases was to permit the Department of
    Corrections to address system-wide overcrowding by moving
    inmates into a portion of the facility while construction
    proceeded on the balance of the Project.
    It is for these reasons that defendants’ concern that
    selecting the date of the certificate of substantial completion
    issued for the minimum-security unit and the garage will subject
    25
    them and other similarly situated contractors in other cases to
    endless liability is unfounded.    The Project had a discrete
    start and end date.    The improvement at issue provides every
    building in the Project with a critical service –- heat and hot
    water.    There were no lengthy gaps of time between one phase and
    another.   Under these circumstances, it is only sensible that we
    focus on the issuance of the certificates of substantial
    completion for the last buildings connected to the HTHW system
    as the trigger for calculating the commencement of the ten-year
    repose period.
    Neither the contract nor the specifications require a
    separate certificate of substantial completion for the HTHW
    system.    No certificate ever issued for only the HTHW system.
    The failure to require a separate certificate for the HTHW
    system supports the conclusion that neither the owner nor the
    designer and builder ever contemplated that the system would be
    completed on a piecemeal basis.    Rather, as an improvement
    designed to service every building in the facility, it was
    complete only when the HTHW system was connected to every
    building it was designed to serve.1
    1 The parties are free to stipulate to a substantial completion
    date via contract. See Town of 
    Kearny, supra
    , 214 N.J. at 95;
    Trinity Church v. Lawson-Bell, 
    394 N.J. Super. 159
    , 170 (App.
    Div. 2007).
    26
    In sum, we conclude that the ten-year statute of repose
    limitations period commenced to run on the day after the final
    certificates of substantial completion issued for the final
    buildings served by the HTHW system.   The final certificates
    were issued on May 1, 1998.   The State filed its complaint on
    April 28, 2008.   The statute of repose therefore does not bar
    the complaint.
    V.
    Finally, we address the Perma-Pipe appeal.    Perma-Pipe
    manufactured and supplied the piping required for the HTHW
    system.   It also participated in laying the pipe throughout the
    site.   Perma-Pipe acknowledges that the statute of repose is
    normally not extended to similarly situated manufacturers of
    construction materials.   It maintains, however, that it was
    inextricably involved in the design and fabrication of the HTHW
    system and is thereby within the ambit of the statute of repose.
    In its complaint, the State asserts three causes of action
    against Perma-Pipe:   breach of implied warranties of
    merchantability and fitness for a particular purpose (Count
    Five); negligence and strict liability in tort (Count Six); and
    breach of its duty under the PLA (Count Seven).   It is
    undisputed that defendant Kimball designed the Project in its
    entirety and the design included the HTHW system.   Perma-Pipe
    27
    manufactured the insulated black steel carrier piping used in
    the HTHW system.
    The statute of repose applies when
    (1) the injury sustained by plaintiff resulted
    from a defective and unsafe condition of an
    improvement to real property; (2) [the
    defendant was] responsible for performing or
    furnishing the design, planning, surveying,
    supervision of construction, or construction
    of the improvement; and (3) the injury
    occurred more than ten years after the
    performance or furnishing of the services.
    [
    Dziewiecki, supra
    , 180 N.J. at 531-32.]
    By contrast, manufacturers of standardized products and
    sellers of such products are not subject to the statute of
    repose, but rather “are covered by the statute of limitations
    applicable to the [PLA].”   
    Id. at 532.
       When a person or entity
    has served as a manufacturer and an installer and thereby falls
    under the coverage of the statute of repose and the PLA, and the
    cause of the injury is attributable to both, the responsibility
    should be allocated between the two.      
    Id. at 533.
      The practical
    effect of allocation may render one of the causes of the injury
    actionable and the other non-actionable, if the civil action is
    not commenced within ten years of substantial completion of the
    improvement.   
    Ibid. The facts in
    Dziewiecki illustrate the distinction between
    manufacturing/distribution and installation.     In that case, the
    Court held that the inground pool surrounded by a concrete apron
    28
    was an improvement to real property.      
    Id. at 532.
      The installer
    of this improvement fell within the coverage of the statute of
    repose.   
    Id. at 533.
      On the other hand, the seller and
    distributor of a pool kit composed of galvanized steel walls, a
    vinyl liner, braces behind the walls, and a coping package “did
    not fall within the class of persons or entities protected by
    the [statute of repose].”   
    Id. at 531.
    A review of the record, particularly the November 7, 1995
    letter accompanying Perma-Pipe’s proposal and the terms and
    conditions of the provision of its product, demonstrate that
    Perma-Pipe’s role was that of a manufacturer of a product used
    in the construction of the HTHW system.     For example, the
    summary of Perma-Pipe’s proposal in the November 1995 letter
    states that “Perma-Pipe’s standard hot water distribution system
    is a completely drainable and dryable system.”     (Emphasis
    added).   Perma-Pipe stated that the piping and fittings would be
    manufactured to job specifications using standard straight
    sections of piping and “our Poly-Piping and Kits product line.”
    It also proposed “to furnish our POLY-THERM product for the
    chilled water distribution system for the . . . project.”
    In its Terms and Conditions of Sale, Perma-Pipe also
    advised the buyer that fabrication would not commence until the
    buyer provided “all job dimensions and angles” and any
    deviations “from the consulting engineer’s designs must be
    29
    counter-approved by the engineer” before fabrication would
    commence.    In addition, the Terms and Conditions of Sale
    expressly stated that the buyer would compensate Perma-Pipe for
    any costs incurred by it due to changes in drawings or
    dimensions.
    To be sure, the record reveals that Perma-Pipe provided
    technical assistance and support during installation.     The
    record also demonstrates that Natkin, not Perma-Pipe, installed
    the piping.    In short, while the piping for the Project served a
    specialized purpose to meet the specific dimensions and
    specifications of the system designed by Kimball and installed
    by Natkin, the piping and the various fittings manufactured by
    Perma-Pipe are nonetheless a product and Perma-Pipe cannot take
    refuge in the statute of repose.
    VI.
    In sum, we hold that the HTHW system is an improvement to
    real property and falls within the scope of the statute of
    repose.     We reject, however, the position advanced by defendants
    Perini, Kimball, Natkin, and Jacobs that the ten-year statute of
    repose limitations period commenced to run when the HTHW system
    began to supply heat and hot water to the buildings completed in
    Phase I.     The HTHW system was designed to supply heat and hot
    water not to some but to all buildings in the system, including
    the 1000-plus bed minimum-security unit substantially completed
    30
    on May 1, 1998.   The statute of repose for a single improvement
    that is intended to supply critical utilities, such as heat and
    hot water, cannot be considered substantially complete until it
    has been connected to every building it is intended to serve.
    In this appeal, the multi-phase construction schedule had no
    effect on when the statute of repose limitations period
    commenced.   This three-phase project proceeded seamlessly from
    one phase to another with no substantial gaps in construction.
    We need not address in this appeal the implications for statute
    of repose purposes of a multi-phase project that proceeds with
    substantial idle intervals between phases.
    Finally, we conclude that Perma-Pipe supplied a product
    that was incorporated in the HTHW system and is therefore not a
    professional contractor whose services fall within the scope of
    the statute of repose.
    VII.
    The judgment of the Appellate Division is therefore
    affirmed as modified.
    CHIEF JUSTICE RABNER; JUSTICES ALBIN and SOLOMON; and JUDGE
    FUENTES (temporarily assigned) join in JUDGE CUFF’s opinion.
    JUSTICES LaVECCHIA, PATTERSON and FERNANDEZ-VINA did not
    participate.
    31
    SUPREME COURT OF NEW JERSEY
    NO.    A-121/122/123/135                        SEPTEMBER TERM 2011
    ON APPEAL FROM             Appellate Division, Superior Court
    STATE OF NEW JERSEY,
    Plaintiff-Respondent,
    v.
    PERINI CORPORATION, ET AL.,
    Defendants-Appellants.
    ______________________________
    STATE OF NEW JERSEY,
    Plaintiff-Respondent,
    v.
    PERINI CORPORATION, ET AL.,
    Defendants,
    and
    PERMA-PIPE, INC.,
    Defendant-Appellant.
    DECIDED                        April 30, 2015
    Chief Justice Rabner                        PRESIDING
    OPINION BY          Judge Cuff (temporarily assigned)
    CONCURRING/DISSENTING OPINION BY
    DISSENTING OPINION BY
    AFFIRMED AS
    CHECKLIST
    MODIFIED
    CHIEF JUSTICE RABNER                   X
    JUSTICE ALBIN                          X
    JUSTICE SOLOMON                        X
    JUDGE CUFF (t/a)                       X
    JUDGE FUENTES (t/a)                    X
    TOTALS                                 5
    

Document Info

Docket Number: A-135-11 A-121-11 A-122-11 A-123-11

Citation Numbers: 221 N.J. 412, 113 A.3d 1199

Judges: Cuff

Filed Date: 4/30/2015

Precedential Status: Precedential

Modified Date: 11/11/2024

Authorities (22)

O'CONNOR v. Abraham Altus , 67 N.J. 106 ( 1975 )

Newark Beth Israel Medical Center v. Gruzen , 124 N.J. 357 ( 1991 )

State v. Perini Corp. , 425 N.J. Super. 62 ( 2012 )

Port Imperial v. Hovnanian Port , 419 N.J. Super. 459 ( 2011 )

Welch v. Engineers, Inc. , 202 N.J. Super. 387 ( 1985 )

Dziewiecki v. Bakula , 180 N.J. 528 ( 2004 )

Brown v. Jersey Central Power and Light Co. , 163 N.J. Super. 179 ( 1978 )

Trinity Church v. Lawson-Bell , 394 N.J. Super. 159 ( 2007 )

Horosz v. Alps Estates, Inc. , 136 N.J. 124 ( 1994 )

E. A. Williams, Inc. v. Russo Development Corp. , 82 N.J. 160 ( 1980 )

Totten v. GRUZEN , 52 N.J. 202 ( 1968 )

Rosenberg v. Town of North Bergen , 61 N.J. 190 ( 1972 )

Tretina Printing, Inc. v. Fitzpatrick & Associates, Inc. , 135 N.J. 349 ( 1994 )

Perini Corp. v. Greate Bay Hotel & Casino, Inc. , 129 N.J. 479 ( 1992 )

State v. Perini Corp. , 210 N.J. 476 ( 2012 )

barbara-van-den-hul-special-administratrix-of-the-estate-of-ralph-van-den , 716 F.2d 504 ( 1983 )

Manalapan Realty v. Township Committee of the Township of ... , 140 N.J. 366 ( 1995 )

Ebert v. South Jersey Gas Co. , 157 N.J. 135 ( 1999 )

Russo Farms, Inc. v. Vineland Board of Education , 144 N.J. 84 ( 1996 )

Brill v. Guardian Life Insurance Co. of America , 142 N.J. 520 ( 1995 )

View All Authorities »