Caddell Construction Company v. United States , 2016 U.S. Claims LEXIS 69 ( 2016 )


Menu:
  •              In the United States Court of Federal Claims
    No. 15-645C
    (Bid Protest)
    (Filed: February 10, 2016) 1
    **************************
    *                          Post-award Bid Protest; 28 U.S.C.
    CADDELL CONSTRUCTION     *                          § 1491(b)(1);    Omnibus       Diplomatic
    COMPANY,                 *                          Security and Antiterrorism Act of 1986;
    *                          Lowest Priced Technically Acceptable
    Plaintiff,     *                          Offeror; Misleading Discussions; Price
    *                          Reasonableness; FAR 15.306; FAR
    v.             *                          15.404-1; Price Verification; FAR 14.403;
    *                          FAR 1.102; Prejudice; Injunctive Relief.
    THE UNITED STATES,       *
    *
    Defendant,     *
    *
    and            *
    *
    PERNIX GROUP, INC.,      *
    *
    Intervenor.     *
    *
    **************************
    Dirk Haire, Alexa Santora, and P. Sean Milani-nia, Fox Rothschild LLP, 1030 15th
    Street, NW, Suite 380 East, Washington, D.C. 20005, for Plaintiff.
    Benjamin Mizer, Robert E. Kirschman, Jr., Deborah Bynum, and Sosun Bae, U.S.
    Department of Justice, Civil Division, Commercial Litigation Branch, P.O. Box 480, Ben
    Franklin Station, Washington, D.C. 20044, for Defendant.
    J. Randolph MacPherson and Rebecca Bailey Jacobsen, Halloran & Sage, LLP, 1717
    Pennsylvania Avenue, NW, Suite 675, Washington, D.C. 20006, for Intervenor.
    1
    The Court issued this opinion orally on January 22, 2016. This opinion memorializes the
    Court’s oral ruling.
    The Court issued this opinion under seal on January 28, 2016, and directed the parties to
    file proposed redactions by February 8, 2016. The Court publishes this Opinion indicating
    redactions by asterisks “[***].”
    _________________________________________________________
    OPINION AND ORDER
    _________________________________________________________
    WILLIAMS, Judge.
    In this post-award bid protest, Plaintiff, Caddell Construction Company (“Caddell”),
    challenges the Department of State, Bureau of Overseas Building Operations’ (“DOS”) award of
    a contract to Pernix Group, Inc. (“Pernix”) for the construction of a New Embassy Compound in
    Maputo, Mozambique. This is the second opinion in this case. In the first opinion, the Court
    denied Caddell’s claim that Pernix was ineligible for award under the Omnibus Diplomatic
    Security and Antiterrorism Act of 1986 (“the Act”) because Pernix had not demonstrated either
    the total business volume or the performance of similar work required by the Act. Caddell
    Constr. Co. v. United States, 
    123 Fed. Cl. 469
    (2015).
    This opinion concerns Caddell’s claim that DOS’ misleading discussions tainted the
    pricing evaluation and resulted in an illegal award. DOS admittedly advised the awardee that its
    price was higher than the Independent Government Estimate (“IGE”), when it was actually [***]
    lower than the IGE. As such, award was based on a misinformed price, the price competition
    was skewed, there was no level playing field in what had become a price-based competition, and
    the procurement process lacked integrity. Given the arbitrary and capricious conduct of this
    procurement, the Court vacates the award and directs DOS to correct its erroneous discussion
    letter, afford Pernix the opportunity to revise its pricing based upon an accurate discussion letter,
    and make a new award decision.
    This Court recognizes that typically when discussions are reopened with one offeror, they
    should be reopened with all offerors. Here, however, two circumstances taken together militate
    against such relief. First, the misleading discussions only affected the awardee’s pricing. All
    other offerors received accurate information and had an opportunity to submit informed revised
    offers. Second, the awardee’s price and the IGE have been publicly disclosed. This information
    would give Plaintiff and other offerors an unfair advantage over the awardee in a price re-
    evaluation. As such, based upon the circumstances of this case, the Court grants this limited
    injunction.
    Findings of Fact2
    The Solicitation and Pre-Qualification
    On February 2, 2014, DOS issued a Notice of Solicitation for the construction of a New
    Embassy Compound in Maputo, Mozambique. AR 1-3 (Solicitation No. SAQMMA-14-R0073).
    2
    These findings of fact are derived from the Administrative Record (“AR”). The Court
    has not corrected grammatical errors in quotations from the AR and the filings. Additional
    findings of fact are in the Discussion, and in the Court’s earlier opinion, Caddell Construction
    Co. v. United States, 
    123 Fed. Cl. 469
    , 471-75 (2015).
    2
    This project was to involve the “construction and commissioning” of a new office building,
    marine security guard quarters, shops, storage and maintenance facilities, vehicle and pedestrian
    access control pavilions, a utility building, a bathhouse/cabana, and a vehicle parking structure,
    on a site totaling approximately four hectares. AR 1. The estimated construction cost in the
    Notice provided to prospective offers was stated to be $160-$210 million. 
    Id. The procurement
    consisted of two phases – Phase I, in which DOS would pre-qualify
    offerors for compliance with statutory and security clearance requirements, and Phase II, in
    which DOS would evaluate pre-qualified offerors’ technical and price proposals. AR 1-2. This
    was a “lowest price technically acceptable acquisition” to result in a firm fixed-price contract.
    AR 1, 1067. The project was anticipated to last for 33 months, with work beginning between
    November 1, 2014, and February 1, 2015. AR 134.
    The Solicitation required proposals to be evaluated for price reasonableness under the
    price analysis techniques provided in FAR 15.404-1. Section M.3 of the Solicitation entitled
    Evaluation of Price provided:
    M.3.1. Price proposals will be evaluated for price reasonableness based on the
    total price proposed for performance of the Building Project as specified in
    Section B [Pricing] of this solicitation. Analysis shall be performed in accordance
    with Federal Acquisition Regulation 15.404-1 and Section M [Evaluation Factors
    for Award] of this solicitation.
    AR 239.
    Phase II Evaluations and Discussions
    Following Phase I of the procurement, four pre-qualified offerors remained in the
    competition: Caddell, Pernix, Framaco International, Inc. (“Framaco”), and B.L. Harbert
    International, LLC (“BL Harbert”). AR 1054-55. DOS issued its Request for Proposals (“RFP”)
    following Phase I on September 30, 2014, and these four entities timely submitted proposals.3
    
    Id. The Technical
    Evaluation Panel (“TEP”) reviewed the proposals and scored them on a
    pass/fail basis. AR 877. Caddell, Pernix, and BL Harbert received overall “pass” ratings. AR
    855. Framaco received a “fail” rating, as it did not meet proposal requirements. 
    Id. DOS’ Bureau
    of Overseas Building Operations, Program Development Coordination and
    Support, and Office of Cost Management (“COST”) evaluated the price proposals, and issued a
    memorandum to Contracting Officer Lai setting forth the following price comparison table:
    3
    The original proposal submission deadline of December 1, 2014, was extended to January
    13, 2015. AR 1054.
    3
    (IGE)4          Pernix            Framaco      Caddell         BL Harbert
    CLIN 001,
    Construction
    of New         [***]           [***]             [***]        [***]           [***]
    Embassy
    Compound
    CLIN 003,
    Offsite
    [***]           [***]             [***]        [***]           [***]
    Landscaping
    Plan
    CLIN 004,
    Offsite
    Access Road    [***]           [***]             [***]        [***]           [***]
    Improvement
    Plan
    CLIN 005,
    Offsite
    Conveyance
    [***]           [***]             [***]        [***]           [***]
    Plan for
    Channels A
    &B
    CLIN 006,
    Offsite
    Avenida de
    Marginal       [***]           [***]             [***]        [***]           [***]
    Road
    Improvement
    Plan
    CLIN 007,
    Fixed Price
    [***]           [***]             [***]        [***]           [***]
    Security
    Equipment
    Total          $186,932,794    [***]             [***]        [***]           [***]
    AR 878, 883.
    COST separately analyzed each CLIN and its subelements. AR 879-82. Because CLIN
    001, the construction of the new embassy compound, accounted for approximately 99% of the
    overall project based on the IGE, COST provided two charts: the first comparing the offerors’
    total building costs to complete construction of CLIN 001, and the second comparing the
    4
    The IGE was not disclosed to offerors.
    4
    offerors’ individual building costs to complete construction of the new embassy compound
    required by CLIN 001. AR 879-80. The total construction cost chart set forth the following:
    CLIN 001 Costs
    IGE            Pernix             Framaco     Caddell          BL Harbert
    Total Building
    and Site Work [***]               [***]              [***]       [***]            [***]
    (TBSW)
    General
    Requirements [***]                [***]              [***]       [***]            [***]
    (GR)
    Indirects          [***]          [***]              [***]       [***]            [***]
    General and
    Administrative [***]              [***]              [***]       [***]            [***]
    (G&A)
    Profit             [***]          [***]5             [***]       [***]            [***]
    Total
    Construction       [***]          [***]              [***]       [***]            [***]
    Costs (TCC)
    AR 879. COST noted with respect to total building and site work in CLIN 001 that all but one of
    the bidders were above the IGE and stated: “[t]here are wide differences from the IGE that
    ranged from [***] below the IGE from Pernix, to [***] above the IGE from [***].” 
    Id. (internal parentheticals
    omitted). With respect to profit as a percentage of total construction costs, COST
    wrote:
    Profit - . . . The bids ranged from a low of [***] from Pernix to a high of [***]
    from Caddell. One would question Pernix’s ability because they have the [***]
    throughout their proposal and a [***] profit margin.
    [Total Construction Cost] – [***] and Caddell are within [***] of the IGE; Pernix
    and [***] are at the extremes with [***] the IGE respectively. The differences
    ranged from [***] the IGE.
    AR 879-80 (emphasis added).
    5
    Pernix’s profit was erroneously listed as [***]; Pernix’s actual profit was [***]. AR 789,
    884. In the COST analysis, Pernix’s total construction cost for CLIN 001 is correctly listed as
    [***]. The parties’ briefing, however, continues to assume that Pernix’s initial profit figure was
    [***] and was [***] in its subsequent proposal. See Def.’s Suppl. Br. 11; Intervenor’s Suppl. Br.
    6; Pl.’s Suppl. Br. 24.
    5
    COST’s individual building cost comparison chart for CLIN 001 provided:
    Individual Building Costs in CLIN 001
    IGE            Pernix           Framaco     Caddell       BL Harbert
    [New Office
    [***]          [***]            [***]       [***]         [***]
    Building]
    [Main
    Campus
    [***]          [***]            [***]       [***]         [***]
    Access
    Pavilion]
    [Consular
    Campus
    [***]          [***]            [***]       [***]         [***]
    Access
    Pavilion]
    [Service
    Campus
    [***]          [***]            [***]       [***]         [***]
    Access
    Pavilion]
    Utility
    [***]          [***]            [***]       [***]         [***]
    Building
    Support
    Annex &        [***]          [***]            [***]       [***]         [***]
    Shops
    Recreational
    [***]          [***]            [***]       [***]         [***]
    Facility
    Parking
    [***]          [***]            [***]       [***]         [***]
    Structure
    [Marine
    Security
    [***]          [***]            [***]       [***]         [***]
    Guard
    Residence]
    Mail
    Screening      [***]          [***]6           [***]       [***]         [***]
    Facility
    Sitework       [***]          [***]            [***]       [***]         [***]
    AR 880.
    COST lastly provided a “Summary and Recommendation” section highlighting specific
    pricing concerns for each offeror. AR 882. For Pernix, COST stated:
    6
    Pernix priced this prefabricated facility as [***].
    6
    Their proposal is consistently the [***]. Of the four their proposal [***]. COST
    does not recommend award to Pernix, however if they are to be considered,
    COST recommends that they verify their costs especially for the [***].
    
    Id. (emphasis added).
           For Caddell, COST stated:
    There are substantial differences in Caddell’s [***] and their [***] when
    compared to the IGE. Overall their estimate is very competitive at [***] above
    the IGE. What should be noted is CLIN 001 is priced at [***] the IGE. The other
    costs in [***] than the IGE.
    
    Id. After COST
    submitted this price analysis, Contracting Officer Lai7 prepared a
    competitive range determination memorandum and opened discussions with the four remaining
    offerors on April 15, 2015. AR 1054-56. In the memorandum, Contracting Officer Lai noted:
    The highest proposal [***], vis-à-vis the IGE, appears outside the acceptable
    range for further consideration. Proposals submitted by [***] compared to the
    IGE, are considered within the acceptable range.          [Overseas Building
    Operations]/[Program Development Coordination and Support]/COST does not
    recommend award to Pernix, but stated that if it is to be considered that the
    company should have to verify its proposed costs.
    AR 1055 (emphasis added). Contracting Officer Lai concluded that all four prequalifying
    companies were in the competitive range. AR 1056.
    On April 17, 2015, Contracting Officer Lai sent discussion letters to each of the four
    offerors and set a deadline for revised proposals of May 4, 2015. See, e.g., AR 892-93. In his
    discussion letter to Caddell, Contracting Officer Lai wrote:
    Caddell’s price proposal appears to be [***] in comparison to the Independent
    Government Estimate (IGE). The proposed [***] and Caddell may wish to revise
    its proposed costs here. Moreover, the [***] proposed price appears to be [***]
    and Caddell may wish to revise. Additionally, the [***] total cost is on the [***]
    end and this is another area that Caddell may wish to revise.
    AR 893. Caddell’s price was [***] while the IGE was $186,932,794. AR 878. Caddell’s
    General Requirements cost was [***] IGE, and its [***] IGE. AR 879. On the basis of this
    letter, Caddell made several changes to its technical proposal, but did not alter its price, stating:
    Caddell has reviewed proposed CLIN 001 cost, specifically as it applies to
    General Requirements and General and Administrative total cost. Caddell
    confirms that the pricing submitted January 13, 2015 remains unchanged.
    7
    Mr. Lai identified himself as a Contract Specialist in this document. AR 1056.
    7
    AR 896-98.
    Pernix’s overall price of [***] was [***] below the IGE of $186,932,794. AR 878. In
    his discussion letter to Pernix, the Contracting Officer mistakenly wrote:
    Pernix’s price proposal appears to be [***] in comparison to the Independent
    Government Estimate (IGE). The proposed [***] cost is [***] and Pernix may
    wish to revise its proposed costs here. Additionally, the [***] total cost is on the
    [***] end and this is another area that Pernix may wish to revise.
    AR 895. This statement was admittedly erroneous as Pernix’s price was low, not high – [***]
    below the IGE. Compare AR 878 with AR 895; Tr. 78-79. With respect to General
    Requirements, Pernix’s price was [***] IGE, and Pernix’s General Administrative cost of [***]
    IGE. AR 879. The Contracting Officer described Pernix’s General and Administrative costs as
    “on the [***] end” – when in fact they were [***] the IGE, while he described Pernix’s General
    Requirements cost as [***] when it was only [***] than the IGE. AR 895. Although Pernix’s
    [***] than the IGE listed [***], DOS in its discussion letter did not mention Pernix’s [***] as
    compared with the IGE. 
    Id. In response
    to the Contracting Officer’s erroneous representation, Pernix further reduced
    its total price from [***] to $155,976,154 [***] 16.6% below the IGE. AR 915, 945. In
    reducing its offer, Pernix stated:
    Pernix has taken this opportunity to thoroughly review our price proposal and
    [***]. We are very confident of our new price, and have attached to this letter a
    file with revised pricing for your review.
    AR 915. In CLIN 001, Pernix decreased its price from [***] the IGE, largely by [***] the IGE)
    and [***] the IGE). Compare AR 879 with AR 1006. Pernix then [***] from [***] in its initial
    offer to [***] in its final offer. Compare AR 884 with AR 1006.
    The following chart reflects Pernix’s price revisions to CLIN 001 and Caddell’s
    unchanged pricing of its CLIN 001 costs, as compared to the IGE:
    Caddell
    Pernix            Pernix
    IGE                                                    (Initial and
    (Initial)         (Revised)
    Revised)
    Total Building
    [***]               [***]             [***]              [***]
    and Site Work
    General
    [***]               [***]             [***]              [***]
    Requirements
    Indirects        [***]             [***]             [***]              [***]
    General and
    [***]               [***]             [***]              [***]
    Administrative
    Profit           [***]             [***]             [***]              [***]
    8
    Total
    Construction      [***]             [***]             [***]              [***]
    Costs
    Compare AR 1006 with AR 879, 884.
    Following receipt of revised proposals, COST reevaluated the price proposals, and the
    TEP reevaluated the technical proposals. The TEP gave a “fail” to all four offerors for staffing
    issues. AR 1020, 1022, 1062. On May 13, 2015, COST issued a second price evaluation
    memorandum to Contracting Officer Lai. AR 1005-19. COST noted Pernix’s reduced price,
    stating:
    All the revised bids have been reduced except for Caddell whose bid remains
    unchanged. Pernix still remains the lowest bidder. Their bid has decreased an
    additional [***] to $155 million, and is now [***] 16.6% below the IGE, before it
    was [***] below the IGE.
    AR 1006. COST again raised concerns regarding Pernix’s ability to perform the contract,
    repeating that “[o]ne would question Pernix’s ability because they have the [***] throughout
    their proposal and a [***] profit margin.” AR 1007. COST further noted the “wide differences”
    in the subelement of “Total Building and Site Work” among all bidders. AR 1006.
    Based on technical deficiencies in the proposals, Contracting Officer Lai issued a second
    round of discussion letters on May 21, 2015. DOS’ letters to Pernix and Caddell did not raise
    any pricing issues but solely discussed technical issues. AR 1020-23. Contracting Officer Lai
    requested revised proposals by May 27, 2015. AR 1021, 1023. Caddell and Pernix both made
    technical alterations to their proposals. On June 1, 2015, the TEP issued another revised
    technical evaluation and found that Caddell, Pernix, and BL Harbert met the solicitation
    requirements, while Framaco did not. AR 1042.
    On June 4, 2015, at 10:42 a.m., DOS requested that Pernix verify by 3:00 p.m. that same
    day that it understood the requirements of the scope of work for the project and that its offered
    price was what it proposed on May 4, 2015, i.e., $155,976,154. AR 1052. DOS stated:
    This email is to request clarification regarding the revised price proposal that was
    submitted by Pernix on May 4, 2015. The revised price represents a [***] from
    your original cost/price proposal submitted on January 13, 2015.
    You are hereby requested to verify, in writing, that Pernix understands the
    requirements of the Scope of Work for the Maputo New Embassy Compound
    project, and that your offered price is in the amount that was proposed on May 4,
    2015.
    
    Id. Pernix was
    not notified in this verification request of DOS’ earlier errors advising Pernix that
    its original price was [***] than the IGE, when in fact Pernix’s original price was [***] the IGE,
    or DOS’ exaggeration of the General Requirements costs being [***] as opposed to [***] end,”
    or DOS’ minimization of the General and Administrative cost discrepancy stating it was “on the
    [***] end,” when it was [***] than the IGE. AR 895, 1052.
    9
    In response, Pernix verified its price, stating:
    In response to your request for clarification Pernix hereby confirms it understands
    the requirements of the Scope of Work for Maputo New Embassy Compound
    project as revised through Amendment 03, and that our offered price is the
    amount as proposed on May 4, 2015 [$155,976,154].
    AR 1053.
    Award
    On June 11, 2015, Contracting Officer Lai8 and Contracting Officer James G. Thomas, Jr.
    issued a Price Negotiation Memorandum summarizing the history of the solicitation and
    discussions, and determining that the contract would be awarded to Pernix as the lowest priced
    technically acceptable offeror. AR 1059-63. The final prices for all offerors as compared to the
    IGE were:
    IGE                 Pernix               Framaco           Caddell             BL Harbert
    $186,932,794        $155,976,154         [***]             [***]               [***]
    AR 1005.
    The Price Negotiation Memorandum did not reflect Contracting Officer Lai’s earlier
    mistaken discussion letter to Pernix. The Contracting Officers also noted that the offerors’
    proposed prices were evaluated “in accordance with [FAR] 15.404-1(b)(2)(i)” and “that
    Adequate Price Competition is present and sufficient.” AR 1062. Pernix’s price was determined
    to be fair and reasonable. 
    Id. In their
    Price Negotiation Memorandum, the Contracting Officers relied on Pernix’s price
    verification when finding that Pernix understood the performance requirements of the RFP:
    [COST] advised that bid verification be obtained and a request for clarification
    was sent to Pernix on June 4, 2015. In response, the offeror replied that very
    same day and verified that it understood the requirements of the project and that it
    confirmed its proposed pricing. The price is believed to be a relatively fair
    representation of the RFP performance based on comparison to the IGE which
    was develop[ed] by Government cost estimating professionals referencing the
    same RFP provided to the offerors.
    AR 1063. Contracting Officers Lai and Thomas concluded that “[t]here is sufficient evidence
    that the offeror understood the performance requirements of the RFP and reflected same in [its]
    proposed price” of $155,976,154. 
    Id. In reaching
    this conclusion, the Contracting Officers did
    not realize that the Government had made a mistake in originally advising Pernix its price was
    high, as compared to the IGE. Nor did the Contracting Officers know that Pernix, when
    8
    Contracting Officer Lai referred to himself as Contract Specialist in this document.
    10
    verifying its revised and reduced pricing, was never told that its original price had been low as
    compared to the IGE, not high.
    On June 15, 2015, Contracting Officer Thomas issued a Source Selection Decision
    Memorandum, which noted that “[t]he analysis of proposed pricing was conducted using the
    final revised proposals from each offeror to determine which submitted the lowest priced
    proposal.” AR 1065. In the Source Selection Decision, the Contracting Officers included the
    following chart showing the variance between offerors’ final price proposals and the IGE:
    COMPANY               TOTAL PRICE           VARIANCE
    FROM IGE
    BL Harbert            [***]                 [***]
    Caddell               [***]                 [***]
    Framaco               [***]                 [***]
    Pernix                $155,976,154          -16.6%
    IGE                   $186,932,794
    AR 1066-67. Contracting Officer Thomas conducted an independent analysis of the information
    provided and set forth his comparison of the offerors’ technical ability and price. For Caddell, he
    stated:
    The price proposal submitted by Caddell was evaluated as the second highest
    priced proposal. Caddell’s technical proposal was rated “pass.” Caddell’s
    proposal offers a good proposal compared to that of all submitted proposals.
    Although award to Caddell presents no significant weaknesses and numerous
    valuable strengths, it come[s] at a [***] than the IGE, and since this is a lowest
    priced technically acceptable acquisition, the award will not be made to Caddell.
    AR 1067.
    With respect to Pernix, Contracting Officer Thomas stated:
    The price proposal submitted by Pernix was the lowest priced proposal. Pernix’s
    volume two proposal was rated “pass.” Award to this offer[or] represents the best
    option in this acquisition as the company submitted the lowest priced technically
    acceptable offer. It is to be noted that the TEP found Pernix’s technical proposal
    to be the best written one, demonstrating a good understanding of the project
    requirements and proposing the best method for handling the construction job.
    11
    Id.9 Contracting Officer Thomas, however, made no mention of Pernix’s price proposal as
    compared to the IGE in his assessment. 
    Id. Contracting Officer
    Thomas further stated that Pernix showed “a proven positive record
    of past performance and specialized experience with an approach that demonstrated a
    comprehensive grasp of the scope of work.” AR 1068. In the Contracting Officer’s view, Pernix
    “provided a proposal that generated a fair and reasonable offer to the Government and yielded
    the greatest level of confidence that successful performance for the work on the Maputo [New
    Embassy Compound] will be realized.” 
    Id. Contracting Officer
    Thomas found that adequate price competition established price
    reasonableness and that each offeror was a responsible company before selecting Pernix for
    award. AR 1067-69. According to the Source Selection Decision Memorandum, however,
    Contracting Officer Thomas did not review the discussion letters and responses generated among
    DOS and the offerors during his independent analysis. He wrote:
    I performed an independent analysis of the information provided in order to
    accomplish an integrated assessment of the TEP’s findings. The independent
    analysis included reviewing the Technical Evaluation Panel Evaluation reports
    dated February 6, 2015; May 14, 2015; and June 1, 2015; Price Proposal[]
    Analyses dated February 2, 2015 and May 13, 2015; the RFP; and where
    necessary, the offerors’ proposals.
    AR 1066. As such, the Contracting Officer made award without knowing that Pernix had been
    erroneously advised that its price was [***] than the IGE when in fact it was [***] below the
    IGE – misinformation that may have caused the awardee to further reduce its price.
    Procedural History
    Caddell and Pernix were notified of the award to Pernix on June 17, 2015. AR 1072,
    1074. In its notification letter to Caddell, DOS released the final contract award amount of
    $155,976,154, but not the IGE. AR 1074. Caddell’s bid protest in this Court followed on June
    22, 2015. The Court publicly issued its original opinion on October 2, 2015, and the parties
    further developed the record on the pricing issue presently before the Court. The Government
    voluntarily stayed performance until January 29, 2016.
    During the course of the proceedings before this Court, the Government filed the
    Administrative Record under seal on July 7, 2015. Caddell filed its initial Motion for Judgment
    9
    For [***], Contracting Officer Thomas wrote:
    The price proposal submitted by [***] was evaluated as the highest priced
    proposal. [***] technical proposal was rated “pass.” [***] volume two proposal
    offers a technically acceptable proposal, but at a premium that is over the
    acceptable range per PDCS/COST.
    AR 1067.
    12
    on the Administrative Record (“MJAR”) on July 21, 2015, and a redacted version on August 6,
    2015. In its redacted MJAR, Caddell publicly released the IGE. See Pl.’s Redacted Mot. 21.
    Defendant and Intervenor at no point released the IGE, nor did they release any
    indication of the percentage differences between offerors’ prices and the IGE. See, e.g, Def.’s
    Mot. 25; Intervenor’s Mot. 45-47. In its supplemental briefing filed after its MJAR, Caddell did
    not disclose the IGE publicly, and noted that “[n]either the total IGE nor the IGEs for sub-
    components of work were disclosed to offerors or the public.” Pl.’s Suppl. Br. 3. In this
    supplemental briefing, Caddell redacted the IGE as well as all percentage comparisons of
    offerors’ pricing with the IGE. Pl.’s Redacted Suppl. Br. 3, 4-5, 14-26. In Defendant’s
    supplemental briefing, Defendant stated that Caddell had released the IGE in the redacted
    version of its MJAR and relied upon this disclosure in arguing against injunctive relief “because
    Pernix’s final price of $155,065,084 is now public knowledge, as is the IGE.” Def.’s Suppl. Br.
    15 (citing Pl.’s Redacted Mot. 21, 33)).10
    Discussion
    Jurisdiction and Standard of Review
    This Court has jurisdiction over the instant bid protest under 28 U.S.C. § 1491(b). The
    Court evaluates bid protests in accordance with the Administrative Procedure Act’s standard of
    review for agency action. Bannum, Inc. v. United States, 
    404 F.3d 1346
    , 1351 (Fed. Cir. 2005)
    (citing Impresa Construzioni Geom. Domenico Garufi v. United States, 
    238 F.3d 1324
    , 1332
    (Fed. Cir. 2001)). Under Rule 52.1 of the Rules of the Court of Federal Claims, the parties are
    limited to the AR, and the Court makes findings of fact as if it were conducting a trial on a paper
    record. See 
    id. at 1356.
    Looking to the AR, the Court must determine whether a party has met
    its burden of proof based on the evidence in the record. 
    Id. at 1355.
            This Court will set aside an agency’s procurement decision if the agency abused its
    discretion or acted arbitrarily, capriciously, or otherwise not in accordance with law. 5 U.S.C. §
    706(2)(A) (2012); Adams & Assocs. v. United States, 
    741 F.3d 102
    , 105-06 (Fed. Cir. 2014);
    Ala. Aircraft Indus., Inc. – Birmingham v. United States, 
    586 F.3d 1372
    , 1375 (Fed. Cir. 2009).
    In order to obtain relief, if this Court finds that the agency’s actions were contrary to law or
    regulation, the Plaintiff must also show that the violation was prejudicial. 
    Bannum, 404 F.3d at 1351
    .
    Caddell has Standing to Pursue this Protest
    To establish standing to bring a bid protest under 28 U.S.C. § 1491(b), a plaintiff must
    demonstrate that it is an “interested party” as defined under the Competition in Contracting Act,
    31 U.S.C. § 3551 (“CICA”). Am. Fed’n of Gov’t Emps. AFL-CIO v. United States, 
    258 F.3d 1294
    , 1302 (Fed. Cir. 2001) (“AFGE”) (holding that bid protesters seeking relief under 28
    U.S.C. § 1491 must meet the standing definition of “interested party” under CICA). Under
    CICA the term “interested party,”
    10
    During oral argument, the Court stated, “[Pernix] does not and cannot know that it was
    misled,” and counsel for Intervenor responded that Pernix “does not know, and it would not be
    told. They don’t know anything about that.” Tr. 113.
    13
    (A) with respect to a contract or a solicitation or other request for offers described
    in paragraph (1), means an actual or prospective bidder or offeror whose direct
    economic interest would be affected by the award of the contract or by failure to
    award the contract.
    31 U.S.C. § 3551(2)(A) (2012).
    In Information Technology & Applications Corp. v. United States (“ITAC”), the Federal
    Circuit explained:
    In order to establish standing, ITAC [the protester] must show that it is an “actual
    or prospective bidder or offeror whose direct economic interest would be affected
    by the award of the contract or by failure to award the contract, i.e., that ITAC
    was an interested party, prejudiced by the award to RSIS.
    
    316 F.3d 1312
    , 1319 (Fed. Cir. 2003) (internal citations, alteration, and quotation marks
    omitted); 
    AFGE, 258 F.3d at 1302
    . The Federal Circuit has interpreted the prejudice component
    of demonstrating a “direct economic interest” to mean that a protester would have a “substantial
    chance” of receiving the contract award – i.e., “that it could compete for the contract if the bid
    process were made competitive.” See Myers Investigative & Sec. Servs., Inc. v. United States,
    
    275 F.3d 1366
    , 1370 (Fed. Cir. 2002).
    In arguing that it has standing, Caddell invokes Scanwell Laboratories, Inc. v. Schaffer,
    
    424 F.2d 859
    , 864 (D.C. Cir. 1970), the seminal case on bid protest jurisdiction in the District
    Courts under the Administrative Procedure Act, 5 U.S.C. § 706 (“APA”). Relying on Scanwell,
    Plaintiff posits that “[d]isappointed bidders act in a manner akin to a ‘private attorney general’ in
    bringing forth bid protests to vindicate these public harms.” Pl.’s Suppl. Br. 8. Caddell cites the
    public harm of condoning misleading discussions and undermining the award in violation of the
    basic tenets of fairness and integrity in the procurement process. 
    Id. While Scanwell
    suits were
    brought under the APA’s standing requirements and did not require a protester to demonstrate a
    particularized injury to establish standing, the standing requirement for bid protests in this Court
    – that a plaintiff be an interested party – is markedly different, and does require that a protestor
    show it would have a substantial chance of receiving award absent the procurement error.11
    11
    Given that the Administrative Dispute Resolution Act (“ADRA”), 28 U.S.C. 1491(b), is
    silent on the standing requirements for a bid protest in this Court, courts interpreting ADRA
    could have chosen to import this straightforward private attorney-general standing requirement
    applied in Scanwell and other APA actions, but they did not – instead applying CICA’s
    “interested party” definition previously used in now repealed Brooks Act protests at the General
    Services Administration Board and currently used at the GAO. E.g., Am. Fed’n of Gov’t Emps.
    AFL-CIO v. United States, 
    258 F.3d 1294
    , 1302 (Fed. Cir. 2001). Consistent with Plaintiff’s
    argument, the adoption of a private attorney-general standing requirement would comport with
    the application of the APA standard of review required by ADRA, 28 U.S.C. § 1491(b)(4), and
    would have the salutary effect of reducing the frequent, often complex, threshold challenges to
    standing in these expedited bid protests. See Frederick W. Claybrook Jr., Standing, Prejudice,
    and Prejudging in Bid Protest Cases, 33 Pub. Cont. L. J. 535, 539-40 (Spring 2004). However,
    14
    Caddell argues that it has standing because it was the “offeror next in line for award,” and
    that had Pernix’s proposal been eliminated for its lack of price reasonableness, Caddell could
    have received the award. Pl.’s Mot. 2, 24-27.12 DOS counters that Caddell lacks standing
    because it failed to demonstrate prejudice in that Caddell did not change its price despite having
    been accurately notified that its price was higher than the IGE. DOS and Pernix further argue
    that even if Pernix would have raised its price had DOS not mislead Pernix, it “belies
    believability” that Pernix would have revised its price upward by more than [***] so as to
    overcome the price differential between Pernix’s initial offer price of [***] and Caddell’s initial
    offer price of [***]. Def.’s Suppl. Br. 5; Intervenor’s Suppl. Br. 26-30.
    To establish standing, Caddell need only show that “it would have been a qualified
    bidder” in a competitive procurement, had the procurement error not occurred – it does not “need
    to show that it would have received the award in competition with other hypothetical bidders . . .
    .” 
    Myers, 275 F.3d at 1370-71
    . Essentially, Defendant and Intervenor argue that, given its
    pricing thus far in the procurement, there is no way that Caddell could be the lowest priced
    offeror in another price evaluation. This argument, however, takes the Court too far down the
    path of a merits assessment in ruling on a threshold issue. As the Court in Textron Inc. v. United
    States recognized, addressing questions of standing that presuppose a discussion of the merits
    would “lead the court in a round-robin through the arguments on the merits in order to resolve a
    jurisdictional issue. Such is not a desirable or appropriate procedure.” 
    74 Fed. Cl. 277
    , 284-85
    (2006), appeal dismissed sub nom. Textron, Inc. v. Ocean Tech. Servs., Inc., 222 F. App’x. 996
    (Fed. Cir. 2007), and dismissed per stipulation, 223 F. App’x. 974 (Fed. Cir. 2007). In assessing
    standing, the Court should look to Plaintiff’s allegations, 
    ITAC, 316 F.3d at 1319
    , not prejudge
    the merits of a bid protest. Moreover, the prejudgment that DOS and Intervenor invite would
    entail guessing what Pernix would bid and what the Agency would decide. It is unknown what
    price Pernix may offer given accurate information. This Court should not deny a plaintiff access
    to the courthouse or bar a plaintiff from presenting a claim based upon the speculative construct
    that the plaintiff cannot ultimately win. This is especially compelling in a situation such as this
    where Defendant and Intervenor seek to bar Plaintiff from bringing a claim of an egregious
    pricing misevaluation on the ground that Plaintiff could not have won the award based upon
    pricing.
    unless the Federal Circuit alters the legal standard for assessing bid-protest standing, the
    interested party test is controlling, not the private attorney general theory pressed by Plaintiff.
    12
    In another vein, Caddell argues that had Pernix been provided with accurate information,
    Pernix may have adjusted its price upward, and had Caddell been provided with similarly
    misleading information, it would have lowered its price. Pl.’s Suppl. Br. 16. DOS and Pernix
    argue that Caddell waived any argument that Caddell would have adjusted its price downward if
    given similarly misleading information as Pernix, relying on Qwest Government Services., Inc.
    v. United States, 
    112 Fed. Cl. 24
    , 36 (2013). Def.’s Suppl. Br. 6 n.5; Intervenor’s Suppl. Br. 17-
    18. Qwest does state that a plaintiff in a bid protest must “raise all of its challenges in its
    opening brief” or those arguments are 
    waived. 112 Fed. Cl. at 36
    . Given the fact that this is a
    trial-level proceeding where the record and arguments can be further developed, this Court
    declines to follow Qwest, and finds that Plaintiff did not waive this argument. The Court
    nonetheless rejects the argument as speculative.
    15
    Indeed, Caddell alleged that Pernix’s proposal should have been rejected outright for an
    unreasonable price, thus paving the way for award to Caddell. Pl.’s Mot. 27 (“Had the price
    evaluation been properly conducted, it is clear that Pernix’s price would be deemed unreasonably
    low, leaving Caddell as the lowest price technically acceptable offeror.”). Although the Court
    did not ultimately conclude that Pernix’s proposal should have been definitively rejected as
    noncompliant with the price reasonableness requirement, thus eliminating Pernix from the
    competition, Plaintiff’s allegations were plausible and if successful, would have enabled Plaintiff
    to secure the award. 13 Caddell submitted a proposal and is a qualified offeror determined to be
    technically acceptable and ranked just below Pernix. Plaintiff alleged serious procurement errors
    – misleading unequal discussions that resulted in an invalid award at a price obtained essentially
    under false pretenses. Pl.’s Mot. 22-24, 27; Pl.’s Suppl. Br. 1. The circumstances here persuade
    the Court that Caddell had the requisite direct economic interest in award to pursue this protest.
    See 
    ITAC, 316 F.3d at 1319
    (finding protester established standing because the protester’s
    proposal met the minimum contract requirements and, were the award to be set aside for failure
    to conduct meaningful discussions, the protester might secure it); 
    Impresa, 238 F.3d at 1334
    (finding a protester had standing because the protester could compete for award if the agency
    were obligated to rebid the contract); see also Tinton Falls Lodging Realty, LLC v. United
    States, 
    800 F.3d 1353
    , 1360 (Fed. Cir. 2015) (same).
    The Court Has Subject-Matter Jurisdiction Over the Instant Protest
    Defendant makes a second threshold argument that this Court lacks jurisdiction to hear
    the instant protest because it is a claim for reformation. DOS contends that once a contract
    award has been made, any potential reformation claims over pricing errors in the contract
    between Pernix and the Government fall under the Contracts Disputes Act (“CDA”) and are
    beyond the Court’s subject-matter jurisdiction in a bid protest. Def.’s Suppl. Br. 9. In so
    arguing, Defendant seeks to recast what is a post-award bid protest, where an offeror seeks
    injunctive relief, as a performance dispute where a contractor’s former competitor – a nonparty
    to the contract – would be seeking reformation of another entity’s contract pricing. Plaintiff as a
    disappointed bidder challenging an award has not sought what would be a bizarre remedy of
    reforming the awardee’s contract price. Rather, Plaintiff asks that the Court enjoin an illegal
    contract award and reopen the competition. This is a classic bid protest, not a CDA claim for
    reformation.
    DOS Failed to Conduct Meaningful Discussions with Pernix, Tainting Its Price Evaluation
    and Creating an Uneven Playing Field
    Caddell argues that the Agency misled Pernix by telling Pernix its price was [***] than
    the IGE when it was [***] below the IGE, and that if Pernix had been given accurate
    information, it would have raised its price. Pl.’s Suppl. Br. 14-16. DOS admits that it
    mistakenly informed Pernix that its initial price was [***] than the IGE when it was actually
    [***] below the IGE. Tr. 79 (“[I]t was not any intention to mislead on the part of Department of
    State . . . . They acknowledge that this was an error.”). In its first discussion letter to Pernix,
    DOS wrote:
    13
    Plaintiff also alleged that Pernix should have been deemed nonresponsible, but the Court
    does not find this allegation plausible based upon the facts alleged. Pl.’s Suppl. Br. 25.
    16
    Pernix’s price proposal appears to be [***] in comparison to the Independent
    Government Estimate (IGE). The proposed General Requirements cost is [***]
    and Pernix may wish to revise its proposal costs here. Additionally, the General
    and Administrative total cost is on the [***] end and this is another area that
    Pernix may wish to revise.
    AR 895 (emphasis added).14
    This discussion not only misled Pernix to believe that its overall offer price was [***]
    compared to the IGE, but also improperly told Pernix that its General Requirements amount was
    [***] – when it was only [***] above the IGE – and that its General and Administrative cost was
    “on the [***] end” – when it was [***] the IGE. AR 879. After receiving DOS’ misleading
    statement, Pernix further lowered its price to [***] below the IGE. AR 915, 945. Pernix’s price
    reduction included lowering its CLIN 001 General Requirements cost to [***] the IGE, and its
    General and Administrative cost to a lesser amount [***] the IGE, but still a significant deviation
    of [***] the IGE. Compare AR 879, 884 with AR 1006.
    While an agency has considerable discretion in conducting discussions with offerors, that
    discretion is not a license to mislead an offeror. Gentex Corp. v. United States, 
    58 Fed. Cl. 634
    ,
    653 (2003). FAR 15.306(d) outlines the obligation of an agency to conduct meaningful
    discussions with offerors in negotiated procurements:
    (3) At a minimum the contracting officer must . . . indicate to, or discuss with,
    each offeror still being considered for award, deficiencies, significant weaknesses,
    and adverse past performance information to which the offeror has not yet had an
    opportunity to respond.
    48 C.F.R. § 15.306(d)(3) (2014) (emphasis added). As such, when discussions occur, the
    contracting officer must accurately identify weaknesses. An error in communicating a weakness
    that causes an offeror to revise its proposal is quintessentially a misleading discussion. See
    AshBritt, Inc. v. United States, 
    87 Fed. Cl. 344
    , 369 (2009) (finding the agency’s failure to
    communicate a proposal weakness to a protester but giving that type of guidance to other
    offerors, was arbitrary and capricious agency action). The Court recognizes that DOS awarded
    the contract to Pernix without realizing Pernix’s revised pricing had resulted from misleading
    discussions. However, inadvertency is irrelevant in assessing whether discussions were
    misleading. Analytical & Research Tech., Inc. v. United States, 
    39 Fed. Cl. 34
    , 48 (1997) (“‘An
    agency may not inadvertently mislead an offeror, through the framing of a discussion question,
    into responding in a manner that does not address the agency’s concerns; or that misinforms the
    offeror concerning its proposal weaknesses or deficiencies; or the government’s requirements.’”)
    (quoting SRS Techs., 
    1994 WL 576118
    , at *3 (Comp. Gen. 1994)).
    14
    As Defendant acknowledges, this error appeared to have been a clerical error – with DOS
    repeating verbatim the information in Caddell’s discussion letter in its letter to Pernix. Tr. 79
    (“What happened is that they had sent out letters to all of the offerors who were still in the game
    at this point, and if you look, they sent out a very similar letter to Caddell where they actually
    said the price is [***] in relation to the IGE, and it was just an oversight, a typographical error . .
    . .”).
    17
    The agency unlawfully misled Pernix into lowering its price in violation of FAR
    15.306(d) by advising Pernix its price was [***] than the IGE, when its price was lower. This
    error took on enhanced significance in a procurement where the Agency, without realizing its
    error, had articulated concerns about whether Pernix could perform at such a low price. On
    several occasions during the evaluation the price evaluation team, COST, as well as the
    Contracting Officers, unequivocally stated that they did “not recommend award to Pernix”
    because its price was too low – both before Pernix lowered its price in response to erroneous
    discussions and after. The record reflects the Agency’s concern no less than six times:
       COST’s initial assessment questioned Pernix’s ability to perform the
    contract at its initial offer price “because they have the [***] throughout
    their proposal and a [***] profit margin.” AR 879.
       COST explicitly did not recommend award to Pernix without a price
    verification. AR 882.
       COST’s second price analysis questioned Pernix’s ability to perform the
    contract. AR 1007.
       COST repeated its recommendation not to award Pernix the contract
    award. AR 1010.
       Contracting Officer Lai in the Competitive Range Determination
    memorandum recognized that COST did not recommend award to Pernix
    and that only Caddell and Framaco priced their offers within the
    acceptable range of [***] of the IGE. AR 1055.
       Contracting Officers Thomas and Lai noted in the responsibility
    determination that only Caddell and Framaco submitted offers that were
    priced in the acceptable range. AR 1057.
    These misleading discussions had a cascading effect in this procurement, causing the
    awardee to unwittingly base its pricing on false information and the ensuing price evaluation to
    be a sham. Agencies involved in procuring contracts must “[c]onduct business with integrity,
    fairness, and openness . . . .” 48 C.F.R. § 1.102(b)(3). This provision of the FAR gives rise to
    “mandatory duties that constrain the Government’s discretion in dealing with bidders.” FFTF
    Restoration Co., LLC v. United States, 
    86 Fed. Cl. 226
    , 239 (2009). The misleading discussions,
    Pernix’s resulting misinformed pricing, and the Government’s resulting misinformed award,
    tainted the procurement and removed the requisite integrity, fairness and openness from this
    procurement.
    FAR § 15.306(e)(1)’s prohibition against acquisition personnel engaging in conduct that
    favors one offeror over another, is also implicated here. 48 C.F.R. § 15.306(e)(1). As the
    Federal Circuit in Raytheon Co. v. United States, explained:
    That regulation [15.306(e)(1)], in its common-sense meaning in the context of
    competitive bidding, requires that the agency avoid giving materially disparate
    18
    information to bidders on matters that could easily affect their decisions about
    important aspects of the final competing offers that the agency will be comparing.
    
    809 F.3d 590
    , 596 (Fed. Cir. 2015) (citing 
    AshBritt, 87 Fed. Cl. at 368-69
    ; Metcalf Constr. Co.
    v. United States, 
    53 Fed. Cl. 617
    , 633-35 (2002); Dynacs Eng’g Co., Inc. v. United States, 
    48 Fed. Cl. 124
    , 133-34 (2000)). Here, DOS gave Pernix erroneous information not given to other
    offerors that impacted Pernix’s pricing.
    DOS Failed to Properly Evaluate Proposals for Price Reasonableness
    Caddell argues that the Contracting Officer failed to properly evaluate Pernix’s price for
    price reasonableness under FAR 15.404-1 based on DOS’ erroneous discussion letter and
    inadequate price verification. Pl.’s Mot. 20-26; Pl.’s Reply 26-27.15 DOS counters that “DOS
    [was not] required to conduct an analysis as to whether Pernix’s price was unreasonably low
    because the procurement was a fixed-price one.” Def.’s Suppl. Br. 6 n.6; Def.’s Mot. 23-24.
    Defendant contends that an analysis of whether an offer price is unreasonably low falls within
    the scope of price realism not price reasonableness and that assessing whether Pernix’s price was
    unreasonably low is not required in a firm fixed-price contract, as this type of contract is
    designed to place the risk of an unreasonably low bid on the offerors. Def.’s Mot. 23 (citing
    NVE, Inc. v. United States, 
    121 Fed. Cl. 169
    , 180 (2015)). NVE, Inc., states:
    Where an award of a fixed-price contract is contemplated, a proposal’s price
    realism is not ordinarily considered, since a fixed-price contract places the risk of
    loss on the contractor. Thus, for a price realism analysis to apply in a fixed-price
    contract, the solicitation must expressly or implicitly require a price realism
    analysis for a proposal to be rejected for an unrealistically low 
    price. 121 Fed. Cl. at 180
    (internal citations omitted). Here, although the solicitation did not require a
    price realism analysis, the solicitation did mandate that proposals be analyzed to ensure that a
    final offer price was “fair and reasonable” under FAR 15.404-1. Defendant violated this
    procedural requirement here.
    The solicitation required the Agency to evaluate proposals on the basis of price
    reasonableness in accordance with FAR 15.404-1. AR 239. FAR 15.404-1’s stated objective “is
    to ensure that the final agreed-to price is fair and reasonable.” The responsibility to determine
    price reasonableness falls on the contracting officer. FAR 15.404-1(a)(1) provides:
    The contracting officer is responsible for evaluating the reasonableness of the
    offered prices. The analytical techniques and procedures described in this section
    may be used, singly or in combination with others, to ensure that the final price is
    fair and reasonable.
    15
    Caddell hints that the Agency’s evaluation also revealed unbalanced pricing, stating
    “COST also engaged in significant analysis of how elements of each offeror’s proposal
    compared to other elements of that same offeror’s proposal, essentially discerning instances of
    potentially unbalanced bids.” Pl.’s Suppl. Br. 4. As Caddell has not identified sufficient facts
    supporting this insinuation, the Court summarily rejects any claim of unbalanced bidding.
    19
    48 C.F.R. § 15.404-1(a)(1) (2015). FAR 15.404-1(b)(2)(i) elaborates on appropriate price
    analysis techniques:
    (b)(2) The Government may use various price analysis techniques and procedures
    to ensure fair and reasonable price. Examples of such techniques include, but are
    not limited to, the following:
    (i) Comparison of proposed prices received in response to the solicitation.
    Normally, adequate price competition establishes a fair and reasonable price. (see
    15.403-1(c)(1)(i) [requirements for adequate price competition]).
    ***
    (v) Comparison of proposed prices with independent Government cost estimates.
    
    Id. at §
    15.404-1(b)(2)(i), (v).
    Here, Contracting Officer Thomas attempted to employ “adequate price competition” as
    his technique for determining the reasonableness of the offerors’ proposed prices under FAR 15-
    404-1(b)(2)(1). AR 1062.16 He stated:
    The proposed prices were evaluated in accordance with FAR 15.404-1(b)(2)(1).
    Because all offers were submitted to meet the same requirement within the time
    frame allowed by the RFP, I determined that Adequate Price Competition is
    present and sufficient.
    
    Id. However, unbeknownst
    to the Contracting Officer, all offers had not been submitted to “meet
    the same requirement” as one offer -- the successful offer -- was based upon wrong information
    about its comparison to the IGE. This information was different information than that conveyed
    to other offerors, leading to a misunderstanding about what that so-called “same requirement” for
    competitive pricing was. In short, a misinformed price cannot be properly used as a benchmark
    for achieving adequate price competition.
    The general requirements for “adequate price competition” are set forth in FAR 15.403-
    1(c)(1)(i):
    Two or more responsible offerors, competing independently, submit priced offers
    that satisfy the Government’s expressed requirement and if
    (A) Award will be made to the offeror whose proposal represents the best value
    (see 2.101) where price is a substantial factor in source selection; and
    16
    The Contracting Officers did not articulate that they had applied any other price analysis
    technique under FAR 15.404-1(b)(2), including comparing the proposed prices to the IGE, but in
    discussion letters DOS had informed offerors where their pricing stood vis-à-vis the IGE. In the
    Source Selection Decision Memorandum the Contracting Officer referenced that Caddell’s
    proposed price was [***] the IGE, and included a chart comparing all offerors’ proposed prices
    to the IGE. AR 1066-67.
    20
    (B) There is no finding that the price of the otherwise successful offeror is
    unreasonable. Any finding that the price is unreasonable must be supported by a
    statement of the facts and approved at a level above the contracting officer.
    48 C.F.R. § 15.403-1(c)(1)(i) (2015).
    The “technique” of misinforming an offeror that its price was high when in fact its price
    was low, and concomitantly misguiding that offeror about how “high” certain subelements were,
    is not a “price analysis technique or procedure” that meets the fundamental purpose of the FAR
    to ensure the “final price is fair and reasonable.” FAR 15.404-1(a)(1). Because the awardee’s
    price resulting from the erroneous discussion letter was not based upon reality or the offeror’s
    accurate understanding of its pricing status vis-à-vis the IGE, that price cannot be said to be
    “fair” or “reasonable.” Nor can such a price form the basis of an “adequate price competition”
    within the meaning of FAR 15.404-1, as one offeror’s price was influenced by erroneous,
    misleading discussions that were never corrected. As such, Plaintiff has established that the
    Agency violated the procedure in the FAR for assessing price reasonableness.17
    DOS’ Price Verification was Inadequate and Did Not Cure the Misleading Discussions
    Caddell argues that DOS exacerbated its initial error by seeking only verification that
    Pernix’s final proposed price was correct without informing Pernix that its initial price had been
    [***] below the IGE, rather than [***] than the IGE. Pl.’s Suppl. Br. 17, 23; Pl.’s Resp. 27-28.
    Defendant and Intervenor counter that Pernix’s price verification adequately demonstrated
    Pernix’s ability to perform the contract at the reduced price of $155,976,154, and was
    sufficiently explained as [***]. AR 915; Def.’s Mot. 24; Intervenor’s Suppl. Br. 20-21.
    The duty to verify price is set forth in Part 14 of the FAR that governs sealed biding, not
    in Part 15 that governs negotiated procurements. 48 C.F.R. § 14.407-3(g). However, the Court
    has repeatedly applied the price verification requirement to negotiated procurements. See, e.g.,
    PHT Supply Corp. v. United States, 71 Fed Cl. 1, 21 (2006) (“Although the duty to raise
    mistakes in an offeror’s proposal is no longer set forth explicitly in the regulations governing
    negotiated procurements, that duty undoubtedly still exists.”); Griffy’s Landscape Maint. LLC v.
    United States, 
    46 Fed. Cl. 257
    , 259 (2000) (holding that the duty to verify price extends to
    negotiated procurements).
    FAR 14.403-7(g) provides in pertinent part:
    (g) Suspected or alleged mistakes in bids shall be processed as follows. A mere
    statement by the administrative officials that they are satisfied that an error was
    made is insufficient.
    (1) The contracting officer shall immediately request the bidder to verify
    the bid. Action taken to verify bids must be sufficient to reasonably assure
    the contracting officer that the bid as confirmed is without error, or to
    17
    This is a process violation. This Court does not find that Pernix’s price was
    unreasonable. Rather, the Court finds that under the circumstances, neither the Government nor
    Pernix could or did accurately ascertain whether Pernix’s price met the requirement for a fair and
    reasonable price in FAR 15.404-1.
    21
    elicit the allegation of a mistake by the bidder. To assure that the bidder
    will be put on notice of a mistake suspected by the contracting officer, the
    bidder should be advised as appropriate –
    (i) That its bid is much lower than the other bids or the
    Government’s estimate as to indicate a possibility of error
    ***
    48 C.F.R. § 14.407-3(g).
    A verification request must inform the offeror of all factors that indicate that an error
    might have been made. Id.; United States v. Metro Novelty Mfg. Co., 
    125 F. Supp. 713
    , 714
    (S.D.N.Y. 1954). If the Government fails to disclose a “pertinent factor” to a bidder, the price
    verification is rendered inadequate. United States v. Hamilton Enters., Inc., 
    711 F.2d 1038
    ,
    1045-46 (Fed. Cir. 1983) (finding a price verification inadequate when the Government failed to
    put the offeror on notice of the 69% price disparity between its proposal and the Government
    estimate). When asking Pernix to verify its price, DOS failed to disclose a pertinent factor in
    that it did not notify Pernix of the agency’s prior error – thus continuing to mislead Pernix to
    believe that its original price had been higher than the IGE. Instead, DOS only asked Pernix to
    verify its further price reduction from [***] below the IGE to 16.6% below the IGE, stating that
    Pernix’s “revised price represents a [***] reduction from your original cost/price proposal
    submitted on January 13, 2015.” AR 1052.
    This communication perpetuated the agency’s original error. Pernix’s price was
    originally [***]below the IGE, and after the misleading discussions, its price was 16.6% below
    the IGE. AR 1006. However, the Contracting Officer never advised Pernix either of this
    disparity between its revised price and the IGE or of its original misleading discussion that
    prompted Pernix to reduce its price. Because the awardee was never told where its original or
    revised pricing accurately stood vis-à-vis the IGE, the so-called verification did not put Pernix on
    notice of the nature and extent of the suspected mistake or give the offeror the opportunity to
    meaningfully verify its pricing, as required by FAR 14.407-3. Hamilton Enters, 
    Inc., 711 F.2d at 1046
    .
    DOS’ Error Prejudiced the Protester and All Offerors and Undermined the Integrity of the
    Procurement Process
    Although they acknowledge DOS erred in discussions with the awardee, Defendant and
    Intervenor contend the award should not be disturbed because Plaintiff has failed to show that it
    would have a substantial chance of receiving award because Caddell’s initial price proposal was
    [***] higher than Pernix’s initial price. Defendant focuses on prejudice in arguing lack of
    standing, whereas Intervenor argues that Plaintiff failed to establish prejudice on the merits,
    asserting that the Agency’s discussion letter was a de minimus error and immaterial to the award.
    Def.’s Suppl. Br. 4; Intervenor’s Suppl. Br. 23. 18 In so arguing, Intervenor has failed to
    18
    Defendant does not argue that Caddell was required to establish prejudice to prevail on
    the merits of its protest in its supplemental briefing, but pointed out in its initial Motion that
    under the APA, harmless errors are not prejudicial to a protester. Def.’s Mot. 25.
    22
    appreciate the gravity and reach of the procurement error, and has imposed a far more onerous
    burden to demonstrate merits prejudice than that required by law.
    This Court assesses prejudice under the Administrative Procedure Act (“APA”), 5 U.S.C.
    § 706, as mandated under the Administrative Dispute Resolution Act of 1996 (“ADRA”), 28
    U.S.C. § 1491(b) (2012). ADRA provides:
    (4) in any [bid protest] action under this subsection, the courts shall review the
    agency’s decision pursuant to the standards set forth in section 706 of title 5 [the
    Administrative Procedure Act].
    28 U.S.C. § 1491(b). 5 U.S.C. § 706(2)(A) states:
    To the extent necessary to decision and when presented, the reviewing court shall
    decide all relevant questions of law, interpret constitutional and statutory
    provisions, and determine the meaning or applicability of the terms of an agency
    action. The reviewing court shall –
    (1) compel agency action unlawfully withheld or unreasonably delayed; and
    (2) hold unlawful and set aside agency action, findings, and conclusions found to
    be-
    (A) arbitrary, capricious, an abuse of discretion, or otherwise not in
    accordance with law;
    ***
    In making the foregoing determinations, the Court “shall review the whole record or
    those parts of it cited by a party, and due account shall be taken of the rule of prejudicial error.”
    
    Id. Where, as
    here, “the trial court finds that the government’s conduct fails APA review under
    5 U.S.C. § 706(2)(A), then it proceeds to determine, as a factual matter, if the bid protester was
    prejudiced by that conduct.” 
    Bannum, 404 F.3d at 1351
    . This prejudice inquiry on the merits is
    distinct from the jurisdictional inquiry regarding standing. The Court assesses “prejudice” twice
    in bid protests – once in the standing analysis and again in the review of the merits. For purposes
    of determining standing, the “prejudice” inquiry is part and parcel of whether a protester is an
    “interested party” as defined by the Competition in Contracting Act (“CICA”). See 
    AFGE, 258 F.3d at 1302
    . In contrast to this threshold interested-party standing analysis, the merits analysis
    dictated by ADRA’s mandate importing the APA standard of review, focuses on whether an
    established procurement violation is sufficiently “prejudicial” to be worthy of relief.
    As the APA instructs, in determining whether to set aside agency action, the Court shall
    take “due account . . . of the rule of prejudicial error.” 5 U.S.C. § 706. In the seminal case of
    Kentron Hawaii, Ltd. v. Warner, which harkens from the days when post-award bid protests
    were “Scanwell”19 cases heard in district courts under the APA, the United States Court of
    Appeals for the District of Columbia Circuit emphasized that to be remediable, a procedural
    19
    Scanwell Labs., Inc. v. Shaffer, 
    424 F.2d 859
    (D.C. Cir. 1970).
    23
    procurement error had to result in a “prejudicial violation of applicable statute or regulations,” or
    an irrational award decision. 
    480 F.2d 1166
    , 1169 (D.C. Cir. 1973). Thus, when an irrational or
    arbitrary and capricious agency action has occurred, prejudice is presumed, but when a violation
    of statute or regulation has occurred, there must be a separate showing of prejudice. See
    generally Centech Grp., Inc. v. United States, 
    554 F.3d 1029
    , 1037 (Fed. Cir. 2009) (recognizing
    that “a reviewing court may set aside a procurement action if the procurement official’s decision
    lacked a rational basis or for a challenge involving “a violation of regulation or procedure . . . the
    disappointed bidder must show a clear and prejudicial violation of applicable statutes or
    regulations.”) (emphasis added) (internal citations omitted); Banknote Corp. of Am. Inc. v.
    United States, 
    365 F.3d 1345
    , 1351 (Fed. Cir. 2004) (recognizing that under the APA standard
    applied in ADRA cases “a bid award may be set aside if either (1) the procurement official’s
    decision lacked a rational basis; or (2) the procurement procedure involved a violation of
    regulation or procedure . . . . When a challenge is brought on the second ground, the disappointed
    bidder must show a clear and prejudicial violation of applicable statutes or regulations.”)
    (emphasis added) (internal citation and quotation marks omitted).20
    As the Court in Textron, Inc. v. United States explained, in a bid protest under the APA
    prejudice is presumed when the Government acts 
    irrationally. 74 Fed. Cl. at 329
    . In Textron,
    the Court differentiated the burden of showing prejudice stemming from arbitrary and capricious
    agency action versus prejudice stemming from violations of procurement regulations. As the
    Textron Court explained:
    When the court finds a violation of an applicable procurement regulation the court
    should determine . . . whether the procurement violation was significant to the
    protester’s chance of being awarded the contract. This prejudice analysis,
    however, should only be reached when the protester has shown violation of an
    applicable procurement regulation. If the court finds that the Government has
    acted arbitrarily and capriciously, the analysis stops at that finding. There should
    be no need to continue to prejudice, because a finding that the Government has
    acted arbitrarily and capriciously necessarily invalidates the procurement, and the
    court must enjoin the procurement award or enjoin performance under an award
    already made . . . .
    
    Id. (emphasis added).
    Here, the Agency acted arbitrarily and capriciously in misleading Pernix
    about its pricing and awarding the contract based on misinformed pricing – the award price was
    based upon error, not a legitimate process, rendering award invalid. In this Court’s view, given
    the nature of this error, prejudice should be presumed.
    20
    The Federal Circuit’s recent decision in Raytheon Co. v. United States does not alter this
    result. 
    809 F.3d 590
    , 597 (2015). While the Federal Circuit in Raytheon recognized the
    “substantial chance” test for merits prejudice, it did so in the context of reviewing whether GAO
    had properly taken prejudice into account in an outcome-prediction, not in an adjudication of a
    bid protest by the Court of Federal Claims assessing prejudice under ADRA. GAO’s bid protest
    regime is not governed by ADRA, or the APA standard for assessing prejudice. 31 U.S.C. §
    3551 (2012).
    24
    In the alternative, even if prejudice is not presumed, Plaintiff has nonetheless
    demonstrated prejudice stemming from the Agency’s irrational conduct of this procurement and
    DOS’ violations of procurement regulations. With respect to the Agency’s irrational and
    arbitrary and capricious conduct, the entirety of DOS’ pricing evaluation was tainted by its
    misleading discussions and subsequent inadequate price verification that resulted in an invalid
    award to Pernix. This Court cannot ignore the systemic prejudice here and speculate on what
    might have happened to Pernix’s price had proper discussions, price evaluation, and a fair
    competition occurred. As stated in AshBritt,
    The nature of this procurement and sum total of these procurement errors do not
    lend themselves to a prejudice assessment based only upon assumed pricing
    corrections woodenly applied – using faulty bids resulting from faulty discussions
    – to predict what offerors might propose after proper discussions, or which
    offerors might succeed in a reprocurement – or even to engage in the more modest
    speculation that AshBritt would be a sure bet 
    loser. 87 Fed. Cl. at 378
    . Therefore, although it is uncertain what Pernix may have done if given
    accurate information, “the standard for prejudice adopted by the Federal Circuit and this court
    does not require such certainty.” Overstreet Elec. Co., Inc. v. United States, 
    47 Fed. Cl. 728
    , 743
    (2000).
    Plaintiff has established that DOS violated FAR 1.102 requiring the Agency to conduct
    procurements with integrity, FAR 15.306 prohibiting the Agency from misleading offerors, FAR
    14.403 requiring the Agency to conduct adequate price verifications, and FAR 15.404-1
    requiring the Agency to properly evaluate offerors’ price proposals for price reasonableness. To
    demonstrate that these violations of regulation were prejudicial, Plaintiff only had to show that
    the Agency’s procurement error “at least potentially affected the substantive result” of a
    procedural irregularity in the procurement process. Kentron 
    Hawaii, 480 F.2d at 1181
    . Here,
    Plaintiff demonstrated that DOS’ error “at least potentially affected the substantive result”
    because award was made to an invalid price proposal. 
    Id. The crux
    of the inquiry on whether
    violation of statute or regulation was prejudicial should be focused on the magnitude and
    materiality of error to the procurement at hand – not on the plaintiff’s chances for securing
    award. See Elcon Enters., Inc. v. Wash. Metro. Area Transit Auth., 
    977 F.2d 1472
    , 1478-79
    (D.C. Cir. 1992) (“Nor may courts set aside a procurement decision on the ground that the
    procuring agency potentially or actually violated applicable law in some trivial way – the
    violation must have been clear and prejudicial.”) (emphasis in original). As is the case in
    traditional APA review cases, administrative procurement decisions can only be set aside for
    “substantial procedural or substantive reasons.” Vt. Yankee Nuclear Power Corp. v. Nat. Res.
    Def. Council, Inc., 
    435 U.S. 519
    , 558 (1978).
    An analysis of the standard for demonstrating prejudice on the merits in a COFC bid
    protest is also informed by the available relief spelled out in ADRA. The remedies authorized by
    ADRA – injunctive and declaratory relief, and bid and proposal preparation costs – carry with
    them a burden of proving that the arbitrary and capricious conduct or the procurement illegality
    “prejudiced” the plaintiff. In the most egregious cases where injunctive relief is warranted, a
    plaintiff must show irreparable harm to itself to secure such relief and also demonstrate that any
    harm to third parties and the public interest do not outweigh the harm to plaintiff. Similarly, in
    25
    order to secure declaratory relief, a plaintiff must demonstrate a material procurement error that
    so tainted the process, vacatur of the award would be warranted. These are clearly “prejudice”
    type inquiries to be made in the context of fashioning relief.
    In a similar vein, to recover its bid and proposal costs – essentially reliance damages – a
    plaintiff must show that it wasted its costs because the Government breached its obligation to
    consider the plaintiff’s proposal fairly, thus implicating the harm or prejudice caused by such a
    wasteful loss of effort and expense. See, e.g., 28 U.S.C. § 1491(b)(2) (2012); Gentex 
    Corp., 58 Fed. Cl. at 656
    . For this Court to impose an additional showing of particularized injury in fact –
    that Plaintiff must show it would have lowered its price to win the procurement in order to attain
    relief – would be overkill, and an improper conflation of the prejudice required to show standing
    as distinguished from the prejudice required to show a procurement violation worthy of a
    particular form of relief. See Textron, 
    Inc., 74 Fed. Cl. at 284-85
    .
    DOS and Intervenor rely on Data General Corp. v. Johnson, 
    78 F.3d 1556
    , 1562 (Fed.
    Cir. 1996) for the proposition that the price differential between Pernix and Caddell obviates
    Caddell’s claim of merits prejudice. Def.’s Suppl. Br. 3; Intervenor’s Suppl. Br. 26. Data
    General was a Brooks Act protest decided by the General Services Administration Board of
    Contract Appeals under de novo review, not a protest in this Court under ADRA, and thus did
    not implicate a prejudice analysis required to be done under the APA. As such, in this Court’s
    view, Data General has no applicability here.
    In any event, in a subsequent Brooks Act protest, the Federal Circuit clarified that a price
    differential alone is not dispositive of prejudice. Alfa Laval Separation, Inc. v. United States,
    
    175 F.3d 1365
    , 1368 (Fed. Cir. 2004); see also 
    AshBritt, 87 Fed. Cl. at 376-77
    . In Alfa Laval,
    the Federal Circuit held that a protester was prejudiced by an erroneous award decision, even
    though its proposal was priced 29% higher than the awardee’s technically noncompliant 
    offer. 175 F.3d at 1368
    . The Federal Circuit reasoned that, had the procurement been executed
    properly, the awardee’s technically deficient proposal would have been rejected outright, giving
    the plaintiff a substantial chance of award. Thus, in Alfa Laval the protester was deemed to be
    prejudiced even though its price was 29% higher. Alfa 
    Laval, 175 F.3d at 1368
    . As such, even
    if the Brooks Act prejudice analysis is applied here, this case is more like Alfa Laval because
    Caddell made a plausible claim that Pernix’s proposal should have been rejected outright for lack
    of price reasonableness.
    DOS Conducted a Proper Responsibility Determination
    Caddell additionally argues that DOS erred by not considering Pernix’s performance risk
    in its responsibility determination. Pl.’s Suppl. Br. 25. Caddell claims that the information
    available to the agency in the record suggests that Pernix was incapable of performing the
    contract requirements, and any prior finding of responsibility was negated by the flawed price
    verification. 
    Id. at 25-26.
          An Agency exercises broad discretion in conducting responsibility determinations under
    FAR 9.104-1, which provides:
    To be determined responsible, a prospective contractor must –
    26
    (a) Have adequate financial resources to perform the contract, or the ability to
    obtain them;
    (b) Be able to comply with the required or proposed delivery or performance
    schedule, taking into consideration all existing commercial and governmental
    business commitments;
    (c) Have a satisfactory performance record. A prospective contractor shall not be
    determined responsible or nonresponsible solely on the basis of lack of relevant
    performance history, except as provided in 9.104-2 [special standards for
    particular acquisitions];
    (d) Have a satisfactory record of integrity and business ethics.
    (e) Have the necessary organization, experience, accounting and operational
    controls, and technical skills, or the ability to obtain them (including, as
    appropriate, such elements as production control procedures, property control
    systems, quality assurance measures, and safety programs applicable to materials
    to be produced or services to be performed by the prospective contractor and
    subcontractors) (see 9.104-3(a) [ability to obtain resources]).
    (f) Have the necessary production, construction, and technical equipment and
    facilities, or the ability to obtain them (see 9.104-3(a)); and
    (g) Be otherwise qualified and eligible to receive an award under applicable laws
    and regulations (see also inverted domestic corporation prohibition at 9.108).
    48 C.F.R. § 9.104-1; Afghan Am. Army Servs. Corp. v. United States, 
    106 Fed. Cl. 714
    , 726-29
    (2012); see Bender Shipbuilding & Repair Co., Inc. v. United States, 
    297 F.3d 1358
    , 1362 (Fed.
    Cir. 2002). As such, a finding of responsibility is largely a judgment call on behalf of the
    contracting officer, who is “the arbiter of what, and how much, information he needs.” See John
    C. Grimberg Co., Inc. v. United States, 
    185 F.3d 1297
    , 1303 (Fed. Cir. 1999).
    In making an affirmative responsibility determination regarding Pernix, Contracting
    Officers Lai and Thomas reviewed Pernix’s technical capability and relied on a Dunn &
    Bradstreet report to assess Pernix’s financial capability. AR 1058. With respect to technical
    capability, the Contracting Officers wrote:
    Pernix is not listed on the GSA/OAP List of Parties Excluded from Federal
    Procurement and Non-Procurement Programs dated June 6, 2015. A Federal
    Awardee Performance and Integrity Information System (FAPIIS) report search
    revealed that the company has no record counts of negative past performance (i.e.
    defective pricing, DoD Determination of Contractor Fault, Non-Responsibility
    Determination, Termination for Cause/Default, and so on).
    27
    In the area of past performance, [Pernix] has performed satisfactorily on similar
    contracts for projects of the comparable size, magnitude, and complexity with the
    Department of State.
    AR 1057.
    With respect to financial capability, the Contracting Officers wrote:
    The Dunn & Bradstreet (D&B) report on Pernix revealed a “4A” financial
    strength rating, reaching between $10-$50 million, and that is considered High.
    Under predictive analytics, Pernix is classified at “2,” which represents a failure
    rate of .09% and is considered low. This financial stress class indicates that the
    firm shares some of the same business and financial characteristics of other
    companies with this classification. It does not necessarily mean that the firm will
    experience financial stress. The credit score class is “2,” which shows that 2.5%
    of firms with this classification paid one or more bills severely delinquent, and it
    is noteworthy that the composite credit appraisal is rated fair. The D&B viability
    rating score of 4A3 indicates that Pernix has low risk for probability of becoming
    no longer viable than other companies in the same region and industry.
    AR 1058. DOS thus provided a coherent and informed judgment based on the information
    before the Agency. 
    Id. at 1057-58.
    The explanation provided by the Agency was factually
    supported by Pernix’s proposal and past performance examples of similar comparable projects,
    as well as the Dunn & Bradstreet report on Pernix’s financial capability. 
    Id. The Contracting
    Officers examined all the relevant data and properly exercised their discretion in finding Pernix
    responsible. Bender Shipbuilding & Repair Co., 
    Inc., 297 F.3d at 1362
    (citing 
    Impresa, 238 F.3d at 1334
    -35 (Fed. Cir. 2001)). The misleading discussions and uninformed pricing do not impact
    Pernix’s overall financial wherewithal to perform. The Court thus finds that the Agency did not
    abuse its discretion in finding Pernix responsible. See Afghan Am. Army Servs. Corp., 106 Fed.
    Cl. at 728-29 (2012).
    A Narrow Injunction is Warranted
    Permanent injunctive relief is an exceptional remedy only available to a disappointed
    bidder in limited circumstances, but ultimately is an act of equitable discretion by the trial court.
    eBay Inc. v. MercExchange, LLC, 
    547 U.S. 388
    , 391 (2006); Apple Inc. v. Samsung Elecs. Co.,
    Ltd., 
    809 F.3d 633
    , 639 (Fed. Cir. 2015); FMC Corp. v. United States, 
    3 F.3d 424
    , 427 (Fed. Cir.
    1993). To obtain permanent injunctive relief, Caddell must show that (1) it has succeeded in on
    the merits of the case; (2) it will suffer irreparable harm if the court withholds injunctive relief;
    (3) the balance of hardships to the respective parties favors the grant of injunctive relief; and (4)
    a grant of injunctive relief serves the public interest. 
    eBay, 547 U.S. at 391
    ; PGBA, LLC v.
    United States, 
    389 F.3d 1219
    , 1228-29 (Fed Cir. 2004); 
    AshBritt, 87 Fed. Cl. at 378
    . No
    individual factor is dispositive, but the Court must weigh each factor against the magnitude of
    the injunctive relief requested. Standard Havens Prods. v. Gencor Indus., 
    897 F.2d 511
    , 513
    (Fed. Cir. 1990) (citing Hilton v. Braunskill, 
    481 U.S. 770
    , 778 (1987)). The Court is not
    required to weigh each factor equally, and a strong showing of success on the merits can
    overcome weaknesses with respect to the other four factors. 
    FMC, 3 F.3d at 427
    . If warranted,
    injunctive relief will be issued upon a showing by a preponderance of evidence. Rush Constr.,
    28
    Inc. v. United States, 
    117 Fed. Cl. 85
    , 101 (2014); Career Training Concepts Inc. v. United
    States, 
    83 Fed. Cl. 215
    , 218-19 (2008). 21 The Court addresses each factor in turn.
    First, as discussed above, Caddell has shown success on the merits of its case by a
    preponderance of the evidence by proving arbitrary and capricious Agency conduct as well as
    several violations of the FAR. DOS conducted misleading discussions with Pernix, advising
    Pernix that its price was high when in fact it was low. AR 895. Caddell has further shown that
    DOS’ price verification was inadequate and perpetuated DOS’ original error. There was an
    uneven playing field. It was quintessentially arbitrary and capricious for the agency to tell
    Pernix its price was slightly above the IGE when in fact it was [***] below the IGE, especially
    when the agency had concerns about Pernix’s ability to perform at that price. These arbitrary
    and capricious misleading discussions snowballed into a more pervasive violation when
    Intervenor took the Government’s cue and further lowered its price, and received award at a
    price based upon misinformation. Given that the award price was based on misinformation, but
    neither the awardee nor the Government (at the time of award) knew it, the Government was
    incapable of assessing whether Pernix’s offer price was fair and reasonable as required by FAR
    15.404-1. The Government sought verification of what it did not know was an invalid price.
    The attempted verification was a sham both from the perspective of the awardee and the
    Government because the awardee was never told the correct information about its initial pricing.
    Given these prejudicial Agency errors, Caddell succeeded on the merits of this protest.
    Second, Caddell was irreparably harmed by this flawed procurement process. Absent
    injunctive relief, Caddell and all other qualified offerors would be denied the chance to compete
    on a level playing field. The Court of Federal Claims has repeatedly recognized that the harm of
    being deprived of the opportunity to compete fairly for a contract is irreparable. 
    AshBritt, 87 Fed. Cl. at 378
    -79; United Payors & United Health Servs. v. United States, 
    55 Fed. Cl. 323
    , 333
    (2002). As such, this factor weighs in favor of granting an injunction to ensure a fair
    competition for this award and restore the integrity of the procurement process. 
    AshBritt, 87 Fed. Cl. at 379
    .
    21
    Defendant and Intervenor rely on KSEND v. United States to support applying a “clear
    and convincing” standard of proof to obtain injunctive relief, but such a high standard is not
    required. 
    69 Fed. Cl. 103
    , 112 (2005), aff’d on other grounds, 184 F. App’x 956 (Fed. Cir. 2006)
    (per curiam, nonprecedential). Rather, as the Textron Court noted, “[a]lthough some judges of
    the Court of Federal Claims insist upon the higher ‘clear and convincing’ standard for injunctive
    relief, this court repeatedly has noted that such an approach is utterly without binding
    precedential 
    support.” 74 Fed. Cl. at 287
    (referencing Bannum, Inc. v. United States, 
    60 Fed. Cl. 718
    , 723 (2004)). The reasoning behind applying the “preponderance of the evidence standard
    was articulated in Career Training Concepts, Inc. v. United States, 
    83 Fed. Cl. 215
    , 219 (2008):
    Utilizing the easier to prove, prevalent in civil cases, standard of proof of a
    preponderance of the evidence is more user friendly to the parties and furthers the
    public policy goal of open, accessible and fair government procurement in which
    each offeror becomes a participant and ombudsman to ensure those goals.
    See also Int’l Res. Recovery, Inc. v. United States, 
    64 Fed. Cl. 150
    , 159 (2005); Hunt Bldg Co.,
    Ltd. v. United States, 
    61 Fed. Cl. 243
    , 279 (2004).
    29
    Third, the Court must balance the harms to Caddell against the harm to both the
    Government and the awardee were the Court to grant the injunction. Pernix did nothing wrong
    in participating in this procurement, and will be harmed by an injunction that prohibits the
    Agency from proceeding with the award. Although Pernix itself followed the rules, the
    Government made a fundamental procurement error here that skewed the playing field and
    resulted in an invalid award price and compromised the integrity of the procurement process. All
    offerors – including the awardee – were harmed by the error. The harms to the public interest
    and the integrity of the process outweigh the harm to Pernix of being deprived of this award.
    As for the Government, DOS argues that it will suffer hardship from further delaying the
    construction of the New Embassy because the current embassy is suffering from “critical
    security flaws” that expose its employees to “unnecessary security risks.” Def.’s Suppl. Br. 14.
    As explained below, the Court has taken this concern into account in fashioning limited
    injunctive relief which can be effected expeditiously.
    It is “beyond peradventure that the public interest in honest, open, and fair competition in
    the procurement process is compromised whenever an agency abuses its discretion in evaluating
    a contractor’s bid.” Seattle Sec. Servs., Inc. v. United States, 
    45 Fed. Cl. 560
    , 572 (1999) (citing
    Cincom Sys., Inc. v. United States, 
    37 Fed. Cl. 266
    , 269 (1997). In granting an injunction in a
    bid protest, the Court must consider the “overriding public interest in preserving the integrity of
    the federal procurement process by requiring government officials to follow procurement statutes
    and 
    regulations.”AshBritt, 87 Fed. Cl. at 397
    (quoting CW Gov’t Travel, Inc. v. United States,
    
    61 Fed. Cl. 559
    , 576 (2004) (citing United Int’l Investigative Servs. v. United States, 
    41 Fed. Cl. 312
    , 323 (1998), aff’d, 163 Fed. Appx. 853 (Fed. Cir. 2005))).
    In order to achieve a level playing field here, the Agency must cure its misleading
    discussion with Pernix and afford Pernix the opportunity to revise its price based upon an
    accurate indication of where Pernix’s pricing stood vis-à-vis the IGE. This Court recognizes that
    ordinarily “where an agency reopens discussions with one offeror after the receipt of [final
    proposal revisions], it must afford all offerors in the competitive range an opportunity for
    reopened discussions.” Lockheed Martin Simulation, Training & Support, B-292836.8, B-
    292836.9, 
    2004 WL 3217797
    , at *6 (Comp. Gen. Nov. 24, 2004); Int’l. Res. Grp., B-286663,
    
    2001 WL 206074
    , *4 (Comp. Gen. 2001). However, in the instant case, such a broad reopening
    of discussions is unnecessary to cure the procurement error and would cause more harm than
    good. This is not a case of a misleading discussion that impacted any offeror other than Pernix.
    The other offerors had a fair shot at revising their final pricing proposals, and it would be unfair
    to give them another bite at the apple, especially given that all the other offerors now know the
    IGE and Pernix’s final award price, but Pernix does not know their prices.
    Defendant argues that the public interest “strongly disfavors injunctive relief” in the form
    of DOS re-conducting any aspect of the procurement particularly considering that Pernix’s final
    offer and the IGE have now been made public. Def.’s Suppl. Br. 14-15. Defendant reasons that
    public knowledge of the award price and IGE makes it “almost certain that the price of the
    contract would be driven even lower, perhaps significantly, which would only increase any
    concern that the awardee could perform the contract requirements at the eventual award price.”
    
    Id. at 15.
    The IGE was apparently released in the redacted version of Plaintiff’s Motion for
    Judgment on the AR, even though the IGE had been redacted from the AR and all other filings as
    30
    Protected Information. This release was not sanctioned by the Court and will be addressed in
    further proceedings. Release of the IGE and Pernix’s price supports reopening discussions solely
    with Pernix. This limited injunction will not, as Defendant suggests, necessarily drive Pernix’s
    price lower, because Pernix will learn that its original price was not [***] vis-à-vis the IGE, but
    low, and that its revised price was [***] lower – 16.6% – than the IGE. Further, the process of
    sending Pernix a new discussion letter and requesting a revised price can be done
    expeditiously.22
    The Federal Circuit’s decision in Chapman Law Firm Co. v. Greenleaf Construction Co.
    does not require reopening discussions with all offerors here. 
    490 F.3d 934
    , 938 (Fed. Cir.
    2007). In Chapman, the Federal Circuit affirmed the Court of Federal Claims’ decision that the
    Agency’s corrective action of reopening discussions with only a single offeror was error because
    it excluded a qualified small business from the competition. 
    Id. at 940.
    The limited reopening of
    discussions here has no such harmful discriminatory impact on any qualified offeror. Rather,
    this injunction corrects an erroneous discussion with Pernix without favoring other offerors, who
    had the benefit of accurate discussions and now know both Pernix’s price and the IGE. Indeed,
    reopening discussions with all offerors and soliciting revised prices would unfairly harm Pernix,
    given the disclosure of its price and the IGE, and would cause more delay to the procurement.
    As this Court is granting Caddell’s request for injunctive relief, which restores Caddell’s
    opportunity to receive a fair reevaluation of its offer, the Court denies Caddell’s request for bid
    preparation and proposal costs. Reema Consulting Servs., Inc. v. United States, 
    107 Fed. Cl. 519
    , 533 (2012) (“It follows, a fortiori, that if plaintiff . . . hopes to receive the award in question,
    and must do so regardless of whether [the Agency] evaluated its first offer properly vel non, it
    cannot obtain bid and preparation costs for that first proposal.”); Beta Analytics Int’l Inc. v.
    United States, 
    75 Fed. Cl. 155
    , 159 (2007) (citing Heyer Prods. Co. v. United States, 140 F.
    Supp. 409, 413-14 (Ct. Cl. 1956)).
    Order
    1. The Court GRANTS Plaintiff’s request for declaratory judgment and motion for a
    permanent injunction as follows:23
    a. The Court hereby declares that the Department of State’s selection of Pernix
    Group, Inc. under Solicitation No. SAQMMA-14-R0073 is null and void, and
    the June 15, 2015 selection of Pernix is hereby set aside;
    22
    This is evidenced by Pernix’s ability to verify its price within approximately four hours in
    response to the Agency’s verification request. AR 1052-53. To the extent other offerors need to
    extend their offers, this can also be done expeditiously.
    23
    In fashioning limited injunctive relief here, the Court is cognizant of its role to abstain
    from “undue judicial interference with the lawful discretion given to agencies” and its obligation
    to give due regard to national security concerns. 28 U.S.C. § 1491(b)(3); Axiom Res. Mgmt.,
    Inc. v. United States, 
    564 F.3d 1374
    , 1384 (Fed. Cir. 2009) (citing Norton v. S. Utah Wilderness
    All., 
    542 U.S. 55
    , 67 (2004)).
    31
    b. The Department of State, its officers, agents, servants, employees,
    representatives, and any person acting in concert and participating with them
    respecting the subject procurement, be and they are hereby
    PERMANENTLY RESTRAINED AND ENJOINED from proceeding to
    perform the contract awarded to Pernix in June, 2015, under Solicitation No.
    SAQMMA-14-R0073 for the construction of a new embassy compound in
    Maputo, Mozambique, and shall reopen the procurement as specified below;
    c. Pernix Group, Inc., its subsidiaries, agents and assigns, be and they are hereby
    PERMANENTLY RESTRAINED AND ENJOINED from executing,
    receiving, and performing the contract awarded on June 15, 2015;
    d. The Department of State is ordered to re-open this procurement to issue a
    corrected discussion letter to Pernix identifying the error in its prior
    discussions, conveying accurate information, and requesting Pernix to re-
    submit a final revised pricing offer in place of its May 4, 2015 offer;
    e. If necessary, the Department of State may request offerors to extend their
    offers for a reasonable time in order to re-evaluate offerors’ pricing;
    f. Following issuance of Pernix’s corrected discussion letter and receipt of
    Pernix’s revised final offer, the Department of State shall reevaluate the
    offerors’ final pricing proposals in accordance with this Court’s Opinion, and
    make a new award decision under Solicitation No. SAQMMA-14-R0073.
    2. Plaintiff’s request for bid preparation and proposal costs is DENIED.
    3. The parties shall file a Notice to the Court by February 5, 2016, indicating whether the
    IGE was Protected Information and addressing the propriety of Plaintiff’s disclosure of
    the IGE in its redacted Motion for Judgment on the Administrative Record, ECF No. 31,
    at 21.
    4. Prior to the release of this opinion to the public, the parties shall review this unredacted
    opinion for competition-sensitive, proprietary, confidential or other protected
    information. The parties shall file proposed redactions of this decision by February 8,
    2016.
    5. Plaintiff’s Motion for Judgment on the Administrative Record is GRANTED in part,
    Defendant’s Cross-Motion for Judgment on the Administrative Record is DENIED, and
    Intervenor’s Cross-Motion for Judgment on the Administrative Record is DENIED. The
    Clerk shall enter judgment on the Administrative Record in favor of Plaintiff consistent
    with this opinion.
    32
    6. The case shall remain open, and the Court will retain jurisdiction for further ancillary
    proceedings consistent with this opinion.
    s/Mary Ellen Coster Williams
    MARY ELLEN COSTER WILLIAMS
    Judge
    33
    

Document Info

Docket Number: 15-645C

Citation Numbers: 125 Fed. Cl. 30, 2016 U.S. Claims LEXIS 69, 2016 WL 537314

Judges: Mary Ellen Coster Williams

Filed Date: 2/10/2016

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (24)

elcon-enterprises-inc-v-washington-metropolitan-area-transit-authority , 977 F.2d 1472 ( 1992 )

Impresa Construzioni Geom. Domenico Garufi v. United States , 238 F.3d 1324 ( 2001 )

Bender Shipbuilding & Repair Co., Inc. v. United States, ... , 297 F.3d 1358 ( 2002 )

Chapman Law Firm Co. v. Greenleaf Construction Co. v. ... , 490 F.3d 934 ( 2007 )

United States v. Metro Novelty Manufacturing Co. , 125 F. Supp. 713 ( 1954 )

Pgba, LLC v. United States, and Wisconsin Physicians ... , 389 F.3d 1219 ( 2004 )

Centech Group, Inc. v. United States , 554 F.3d 1029 ( 2009 )

Norton v. Southern Utah Wilderness Alliance , 124 S. Ct. 2373 ( 2004 )

John C. Grimberg Company, Inc. v. United States , 185 F.3d 1297 ( 1999 )

Scanwell Laboratories, Inc. v. John H. Shaffer, ... , 424 F.2d 859 ( 1970 )

Alabama Aircraft Industries, Inc.—Birmingham v. United ... , 586 F.3d 1372 ( 2009 )

United States v. Hamilton Enterprises, Inc. , 711 F.2d 1038 ( 1983 )

Fmc Corporation and Monsanto Company v. The United States, ... , 3 F.3d 424 ( 1993 )

kentron-hawaii-limited-v-john-w-warner-secretary-of-the-navy , 480 F.2d 1166 ( 1973 )

Hilton v. Braunskill , 107 S. Ct. 2113 ( 1987 )

banknote-corporation-of-america-inc-and-guilford-gravure-inc-v-united , 365 F.3d 1345 ( 2004 )

data-general-corporation-v-roger-w-johnson-administrator-general , 78 F.3d 1556 ( 1996 )

american-federation-of-government-employees-afl-cio-american-federation , 258 F.3d 1294 ( 2001 )

eBay Inc. v. MERCEXCHANGE, LL , 126 S. Ct. 1837 ( 2006 )

Bannum, Inc. v. United States , 404 F.3d 1346 ( 2005 )

View All Authorities »