  • [Cite as Grand Valley Local School Dist. Bd. of Edn. v. Buehrer Group Architechture & Engineering, Inc., 2016-
    Ohio-716.]
    IN THE COURT OF APPEALS OF OHIO
    TENTH APPELLATE DISTRICT
    Grand Valley Local School District                  :
    Board of Education et al.,
    :
    Plaintiffs-Appellees,
    :
    v.                                                                          No. 15AP-412
    :               (Ct. of Cl. No. 2014-00469-PR)
    Buehrer Group Architecture &
    Engineering, Inc. et al.,                           :            (ACCELERATED CALENDAR)
    Defendants-Appellees,               :
    Jack Gibson Construction Company,                   :
    Defendant-Appellant.                :
    D E C I S I O N
    Rendered on February 25, 2016
    On brief: The Riley Law Firm, and David J. Riley, for
    plantiff-appellee Grand Valley Local School District Board of
    Education.
    On brief: Michael DeWine, Attorney General, David A. Beals
    and Jerry K. Kasai, for plaintiff-appellee the Ohio School
    Facilities Commission. Argued: David A. Beals
    On brief: Lane, Alton & Horst, LLC, Joseph A. Gerling, Scott
    A. Fenton, and Porter, Wright, Morris & Arthur, and Brian L.
    Buzby, for defendant-appellant Jack Gibson Construction Co.
    Argued: Scott A. Fenton
    APPEAL from the Court of Claims of Ohio.
    HORTON, J.
    {¶ 1} Defendant-appellant, Jack Gibson Construction Co. ("Gibson"), appeals
    from the decision of the Court of Claims of Ohio granting summary judgment in favor of
    No. 15AP-412                                                                               2
    plaintiffs-appellees, Grand Valley Local School District Board of Education ("Grand
    Valley") and the Ohio School Facilities Commission ("OSFC"), on Gibson's counterclaim
    for breach of contract. For the reasons set forth below, we affirm.
    I. FACTS AND PROCEDURAL HISTORY
    {¶ 2} The OSFC is an agency of the State of Ohio that provides financial
    assistance to local school districts for the construction and rehabilitation of school
    buildings throughout the state. The agency partnered with Grand Valley to build a new
    school building in Orwell, Ohio in 2001. Grand Valley and the OSFC contracted with a
    number of engineers, architects and contractors for the design and construction of the
    school, which occurred between 2001 and 2005. Pursuant to a contract entered into on
    October 14, 2003 ("General Trades Contract"), Gibson was the general contractor on the
    project.
    {¶ 3} Dissatisfied with the final construction, the OSFC and Grand Valley filed
    suit against the contractors and their sureties in the Ashtabula County Court of Common
    Pleas on February 25, 2014. The complaint included claims against Gibson for breach of
    contract and for breach of implied and express warranties. The OSFC and Grand Valley
    alleged that Gibson failed to construct the school in accordance with the plans and
    specifications, failed to comply with and perform under the terms of the General Trades
    Contract, and failed to correct, repair or remedy defective materials and installations.
    {¶ 4} Gibson brought a counterclaim against the OSFC and Grand Valley on
    May 5, 2014, alleging that the parties had entered into a Memorandum of Understanding
    ("MOU") that authorized Gibson to perform remedial work on the school building. Under
    the terms of the MOU, the OSFC and Grand Valley had allegedly agreed to pay for the
    work that Gibson had performed, including "repairs to the masonry, roofing and asphalt"
    of the school. (Counterclaim, 11 at ¶ 7.) According to Gibson, it had performed
    $156,276.13 worth of work authorized by the MOU, but the OSFC and Grand Valley only
    made a partial payment in the amount of $17,487. (Counterclaim, 12 at ¶10-15.) Gibson
    therefore sought damages in the amount of $138.789.13, as well as pre- and post-
    judgment interest and costs. (Counterclaim, 14.) Because the counterclaim against the
    OSFC and Grand Valley brought the case under the jurisdiction of the Ohio Court of
    Claims, the case was removed to that court on May 15, 2014. (Petition for Removal.)
    No. 15AP-412                                                                                3
    {¶ 5} On July 15, 2014, the OSFC and Grand Valley filed a motion for summary
    judgment or, in the alternative, judgment on the pleadings on Gibson's counterclaim.
    They argued that the MOU was not an enforceable contract because its non-specific terms
    did not demonstrate a meeting of the minds, and because no evidence showed that they
    had approved it in accordance with the certification requirement of R.C. 5705.41. The
    OSFC and Grand Valley also argued that the $17,487 payment to Gibson had been made
    pursuant to a $20,000 purchase order, not the MOU. As evidence, they attached a copy of
    the purchase order to an affidavit from Grand Valley's treasurer swearing that it was the
    only "commitment of funds" that the school district had made to Gibson.
    {¶ 6} Gibson responded on September 29, 2014, with a memorandum in
    opposition, supported by an affidavit of its president, Jim Breese. Gibson pointed to
    signatures by the parties on the MOU, Gibson's performance of work, and payment from
    Grand Valley as evidence that a meeting of the minds had occurred. Gibson also argued
    that a certificate of available funds under R.C. 5705.41 was not required because a more
    specific statute applicable to school boards, R.C. 5705.412, did not require certification for
    contracts funded by proceeds from a local bond levy.
    {¶ 7} On March 11, 2015, the Court of Claims issued a decision sustaining Grand
    Valley and the OSFC's motion for summary judgment, granting them judgment as a
    matter of law on Gibson's counterclaim, and remanding the case to the Ashtabula County
    Court of Common Pleas. In its decision, the court found that the parties had only agreed
    to the $20,000 payment authorized by the purchase order. (Decision, 10.) It further found
    that even if the MOU were construed as a contract, it had not been breached because no
    evidence demonstrated that the work in question had been completed to the satisfaction
    of Grand Valley and the OSFC, as required by the plain language of the agreement.
    (Decision, 9-10.) Furthermore, fiscal certificates that demonstrated compliance with R.C.
    5705.41 had been attached to both the original General Trades Contract and the purchase
    order, but the MOU lacked any such certification, which further demonstrated a lack of
    authorization for work done in excess of the $20,000 authorized by the purchase order.
    (Decision, 10.) The Court of Claims also noted that, under R.C. 3313.46, construction or
    repair of a school building with costs in excess of $25,000 must comply with the
    competitive bidding statutes or be declared an "urgent necessity," but Gibson had pointed
    No. 15AP-412                                                                            4
    to no evidence to demonstrate that either exception applied to the MOU. (Decision, 11.)
    The court concluded that there had been "no meeting of the minds with regard to any
    'reasonable compensation' over $20,000 for Gibson's work under the MOU," and
    remanded the case back to the Ashtabula County Court of Common Pleas. (Decision, 11.)
    {¶ 8} Gibson now brings this timely appeal, asserting the following as
    assignments of error:
    [I.] There exist several genuine issues of material fact
    concerning whether the Memorandum of Understanding was
    an enforceable agreement.
    [II.] R.C. 5705.412 specifically applies to school districts and
    controls over the provisions of R.C. 5705.41, a general statute
    that applies to subdivisions or taxing districts.
    [III.] Because the remedial work at issue in Jack Gibson's
    counterclaim was not paid from an account containing Grand
    Valley's general operating revenues, a R.C. 5705.412 fiscal
    certificate was not required to be attached to the
    Memorandum of Understanding.
    [IV.] Because Grand Valley did not raise R.C. 3313.46 as an
    affirmative defense in their answer to the counterclaim or
    mention this statute in its motion for summary judgment,
    the trial court committed reversible error by relying upon
    R.C. 3313.46 as an additional basis for ruling that the
    Memorandum of Understanding was not an enforceable
    agreement.
    {¶ 9} As an initial matter, we note that Gibson's purported assignments of error
    are framed as legal propositions that would be more properly presented in the statement
    of issues.
    The "Assignments of Error" should designate specific rulings
    which the appellant challenges on appeal. They may dispute
    the final judgment itself or other procedural events in the trial
    court. The "Statement of Issues" should express one or more
    legal grounds to contest the procedural actions challenged by
    the assigned errors.
    North Coast Cookies, Inc. v. Sweet Temptations, Inc., 
    16 Ohio App.3d 342
    , 343-44 (8th
    Dist.1984).
    No. 15AP-412                                                                                5
    {¶ 10} As written, the first, second, and third assignments of error fail to dispute,
    or even identify, any action taken by the Court of Claims. The fourth assignment of error
    references a "ruling" by the Court of Claims, but assigns error only to a conclusion of law,
    not to any procedural action or the final judgment entered by that court. Furthermore, we
    have observed that an assignment of error that, like Gibson's first one above, "only
    generically [claims] that there are genuine issues of material fact remaining without
    specifically setting forth any alleged errors made by the trial court" is vulnerable to being
    "simply overrule[d]." Eichenberger v. Tucker, 10th Dist. No. 12AP-515, 
    2013-Ohio-805
    ,
    ¶ 5, citing North Coast Cookies. Nevertheless, it is clear from Gibson's briefing that it
    believes that the Court of Claims erred by sustaining the motion for summary judgment
    and granting judgment as a matter of law in favor of Grand Valley and the OSFC. The ten
    issues Gibson presents for review adequately "express one or more legal grounds to
    contest th[ose] procedural actions" by the Court of Claims, even without any specific
    reference to those actions in the assignments of error. North Coast Cookies at 343-44.
    Accordingly, we will review the Court of Claim's decision and consider Gibson's
    arguments for its reversal in light of the legal arguments that are stated in the
    assignments of error and, for the most part, largely repeated in the statement of issues.
    II. STANDARD OF REVIEW
    {¶ 11} Appellate review of summary judgment motions is de novo. Helton v.
    Scioto Cty. Bd. of Commrs., 
    123 Ohio App.3d 158
    , 162 (4th Dist.1997). "When reviewing a
    trial court's ruling on summary judgment, the court of appeals conducts an independent
    review of the record and stands in the shoes of the trial court." Mergenthal v. Star Bank
    Corp., 
    122 Ohio App.3d 100
    , 103 (12th Dist.1997). We must affirm the trial court's
    judgment if any of the grounds raised by the movant at the trial court are found to support
    it, even if the trial court failed to consider those grounds. Coventry Twp. v. Ecker, 
    101 Ohio App.3d 38
    , 41-42 (9th Dist.1995).
    {¶ 12} Summary judgment is proper only when the party moving for summary
    judgment demonstrates that: (1) no genuine issue of material fact exists, (2) the moving
    party is entitled to judgment as a matter of law, and (3) reasonable minds could come to
    but one conclusion and that conclusion is adverse to the party against whom the motion
    for summary judgment is made, that party being entitled to have the evidence most
    No. 15AP-412                                                                                6
    strongly construed in that party's favor. Civ.R. 56(C); State ex rel. Grady v. State Emp.
    Relations Bd., 
    78 Ohio St.3d 181
    , 183 (1997).
    {¶ 13} When seeking summary judgment on the ground that the nonmoving party
    cannot prove its case, the moving party bears the initial burden of informing the trial
    court of the basis for the motion, and identifying those portions of the record that
    demonstrate the absence of a genuine issue of material fact on an essential element of the
    nonmoving party's claims. Dresher v. Burt, 
    75 Ohio St.3d 280
    , 293 (1996). A moving
    party does not discharge this initial burden under Civ.R. 56 by simply making a
    conclusory allegation that the nonmoving party has no evidence to prove its case. 
    Id.
    Rather, the moving party must affirmatively demonstrate by affidavit or other evidence
    allowed by Civ.R. 56(C) that the nonmoving party has no evidence to support its claims.
    
    Id.
     If the moving party meets this initial burden, then the nonmoving party has a
    reciprocal burden outlined in Civ.R. 56(E) to set forth specific facts showing that there is a
    genuine issue for trial and, if the nonmoving party does not so respond, summary
    judgment, if appropriate, shall be entered against the nonmoving party. 
    Id.
    III. FIRST ASSIGNMENT OF ERROR
    {¶ 14} In the first assignment of error, Gibson argues that there was sufficient
    evidence that the parties had reached a "meeting of the minds" to enforce the MOU for
    the amount of the work it performed, even in the absence of a provision containing a
    specific price term.
    {¶ 15} " 'A contract is generally defined as a promise, or a set of promises,
    actionable upon breach. Essential elements of a contract include an offer, acceptance,
    contractual capacity, consideration (the bargained for legal benefit and/or detriment), a
    manifestation of mutual assent and legality of object and of consideration.' " Kostelnik v.
    Helper, 
    96 Ohio St.3d 1
    , 
    2002-Ohio-2985
    , ¶ 16, quoting Perlmuter Printing Co. v.
    Strome, Inc., 
    436 F.Supp. 409
    , 414 (N.D.Ohio 1976). "A meeting of the minds as to the
    essential terms of the contract is a requirement to enforcing the contract." Id. at ¶ 28,
    citing Episcopal Retirement Homes, Inc. v. Ohio Dept. of Indus. Relations, 
    61 Ohio St.3d 366
    , 369 (1991). To be enforceable, a contract's terms "must be definite and certain."
    Episcopal Retirement Homes at 369, citing James Ward & Co. v. Wick Bros. & Co., 
    17 Ohio St. 159
    , 164 (1867).
    No. 15AP-412                                                                                7
    {¶ 16} "In construing any written instrument, the primary and paramount
    objective is to ascertain the intent of the parties. The general rule is that contracts should
    be construed so as to give effect to the intention of the parties." Aultman Hosp. Assn. v.
    Community Mut. Ins. Co., 
    46 Ohio St.3d 51
     (1989), citing Employers' Liab. Assur. Corp.
    v. Roehm, 
    99 Ohio St. 343
    , 344 (1919), syllabus, and Skivolocki v. E. Ohio Gas Co., 
    38 Ohio St.2d 244
    , 246 (1974), paragraph one of the syllabus. Parties are free to "contract for
    the terms they want, and the 'intent of the parties is presumed to reside in the language
    they chose to use in their agreement.' " Hope Academy Broadway Campus v. White Hat
    Mgt., L.L.C., Slip Opinion No. 
    2015-Ohio-3716
    , ¶ 35 (Sept. 15, 2015), quoting Graham v.
    Drydock Coal Co., 
    76 Ohio St.3d 311
    , 313 (1996). "Intentions not expressed in the writing
    are deemed to have no existence and may not be shown by parol evidence." 
    Id.,
     citing
    Henderson-Achert Lithographic Co. v. John Shillito Co., 
    64 Ohio St. 236
    , 252 (1901).
    {¶ 17} With these principles in mind, we turn to the MOU itself. In structure, the
    agreement consists of a prefatory paragraph, sixteen "Whereas" clauses, and three
    paragraphs describing how the parties "agree[d] to proceed." The relevant provisions of
    the MOU are as follows:
    This Memorandum of Understanding ("Agreement") is
    entered into between the [OSFC] on behalf of [Grand Valley]
    (collectively "Owners") and [Gibson] (collectively the
    "Parties") concerning issues surrounding work performed by
    subcontractors of Gibson at [Grand Valley].
    WHEREAS, Gibson was awarded a contract with [Grand
    Valley] to perform General Trades Work including masonry at
    the new K-12 School (the "Project"); and
    ***
    WHEREAS, Gibson denies that its work on the Project was
    deficient in any manner but agrees to work with the Owners to
    attempt to address any of their concerns related to the Project;
    and
    WHEREAS, Gibson without admitting to any liability to the
    Owners, has agreed to work with the Owners to attempt to
    settle and compromise all claims related to or arising out of
    the Project; and
    No. 15AP-412                                                                       8
    WHEREAS, Gibson has agreed to work with the Owners to
    identify and correct certain masonry and other work
    ("remedial work") that does not meet the Owners'
    expectations and the Owners have agreed that certain aspects
    of the remedial work will include betterment, and that
    reasonable compensation will be due Gibson for such
    items and will need to be evaluated prior to and/or as
    work progresses, with payment after satisfactory
    completion of said work; and
    WHEREAS, the Owners have also identified certain remedial
    work that is not the responsibility of Gibson or its
    subcontractors and Gibson has agreed to correct this work;
    and
    WHEREAS, it is the intent of the Owners to provide
    reasonable compensation for remedial work that is not
    attributed to Gibson or its subcontractors as agreed by the
    Parties; and
    WHEREAS, Gibson and the Owners have retained consultants
    to determine the items of remedial work referenced herein,
    and the consultants have agreed as set forth in Attachments A
    and B to the approximate scope of the work; and
    WHEREAS, the Owners will provide the design,
    specifications and scope for the remedial work; and
    ***
    WHEREAS, upon Gibson's completion of any remedial work
    pursuant to this MOU, the Owners will release Gibson from
    any and all claims related to or addressed by the remedial
    work undertaken by Gibson on the Project, but reserving any
    claims for the remedial work itself; and
    WHEREAS, the Parties desire to attempt to resolve the
    aforementioned issues in a good faith manner,
    NOW THEREFORE, the Parties agree to proceed as follows:
    1) The Parties agree to move forward in a good faith manner
    to resolve and/or clarify any issues as set forth in the attached
    documents or otherwise discovered during the remediation
    process regarding Gibson's subcontractor's work on the
    Project, or other issues not attributable to Gibson or its
    No. 15AP-412                                                                             9
    subcontractors. Good faith is construed to signify that
    discussions and negotiations are ongoing.
    2) Gibson agrees that it will enter into mediation within 60
    days of a request to do so to resolve any dispute arising under
    this Agreement.
    3) The OSFC agrees that as long as Gibson is involved in good
    faith negotiations with the OSFC on the dispute, that this
    matter will not be used by the OSFC in any determination by
    the OSFC that Gibson is not a responsible bidder.
    Agreed to by the Parties this 23rd day of July, 2013.
    (Emphasis added.)
    {¶ 18} The foregoing provisions do not demonstrate that the parties intended the
    MOU to authorize payment to Gibson in any specific amount for the remedial work
    referenced in the agreement. Rather, the MOU memorializes the parties' respective
    positions on a number of issues that arose after the unsatisfactory construction of the
    school, such as the necessity of having remedial work performed and Gibson's denial of
    liability, as well as the parties' mutual wish to resolve their dispute through negotiation
    and mediation instead of litigation. The provision Gibson points to as the basis for its
    counterclaim contains no specific price term for the work it mentions. In the absence of
    any specific term, we will not presume that Grand Valley or the OSFC intended to
    authorize payment to Gibson for over $150,000 worth of work by entering into the MOU.
    Hope Academy Broadway Campus at ¶ 35.
    {¶ 19} In fact, the MOU expressly states that any "reasonable compensation" paid
    to Gibson "will need to be evaluated prior to and/or as work progresses, with payment
    after satisfactory completion of said work." This language should have put Gibson on
    notice that it would have to obtain approval for compensation before starting work, or, at
    the very least, while performing the work. Based on this provision, the only point on
    which the parties clearly reached a "meeting of the minds" was that any compensation
    needed to be approved by Grand Valley and the OSFC. Thus, Gibson began and completed
    work without approved compensation at its own risk. Any specific amount of payment for
    the remedial work was outside the scope of the MOU, and by implication, required a
    No. 15AP-412                                                                             10
    separate agreement for authorization of payment, such as the purchase order for $20,000
    worth of remedial work.
    {¶ 20} The MOU also references the "approximate scope" of the remedial work,
    based on attached inspections by consultants, but then states that "the Owners will
    provide the design, specifications and scope for the remedial work" to be performed.
    (Emphasis added.) This language gave Grand Valley and the OSFC the authority to
    determine the scope of the work. Furthermore, this language contemplates approval at
    some future time. If the scope of the work was to be determined later, any "reasonable
    compensation" for performing it would have to be determined later as well. This further
    supports our conclusion that the parties did not intend for the MOU to authorize any
    specific amount of compensation when the parties entered into it.
    {¶ 21} Citing Oglebay Norton Co. v. Armco, 
    52 Ohio St.3d 232
     (1990), Gibson
    argues that the lack of a specific pricing provision does not render the MOU
    unenforceable because a court may fill in gaps with extrinsic evidence if the parties have
    clearly intended to be bound. Oglebay relied upon the "gap filling" provision that typically
    applies to the sale of goods in Section 2-305 of the Uniform Commercial Code, as well as
    Comment a to Section 33 of the Restatement of the Law 2d, Contracts, to enforce a
    contract for shipping services. Id. at 236-37. As codified at R.C. 1302.18(A), the "gap
    filling provision" states that:
    The parties if they so intend can conclude a contract for sale
    even though the price is not settled. In such a case the price is
    a reasonable price at the time for delivery if:
    (1) nothing is said as to price; or
    (2) the price is left to be agreed by the parties and they fail to
    agree; or
    (3) the price is to be fixed in terms of some agreed market or
    other standard as set or recorded by a third person or agency
    and if it is not so set or recorded.
    {¶ 22} Oglebay quoted the following language from Comment a to the
    Restatement, which similarly provides that:
    [T]he actions of the parties may show conclusively that they
    have intended to conclude a binding agreement, even though
    No. 15AP-412                                                                                11
    one or more terms are missing or are left to be agreed upon.
    In such cases courts endeavor, if possible, to attach a
    sufficiently definite meaning to the bargain.
    An offer which appears to be indefinite may be given precision
    by usage of trade or by course of dealing between the parties.
    Terms may be supplied by factual implication, and in
    recurring situations the law often supplies a term in the
    absence of agreement to the contrary.
    Oglebay at 236.
    {¶ 23} We have previously held that a two-step process applies to determine the
    enforceability of "a services contract with a significant open term" under Oglebay. Malaco
    Constr. v. Jones, 10th Dist. No. 94APE10-1466 (Aug. 24, 1995); Cook & Son-Pallay, Inc.
    v. Hillman, 10th Dist. No. 14AP-44, 
    2014-Ohio-5444
    . First, a court must determine
    "whether the parties intended to be bound by the terms of the contract despite the failure
    to reach an accommodation on price." Malaco at 18. If so, the court may then "fill the
    open price term with a 'reasonable price' in accordance with the above-cited restatement
    language and by analogy with sale of goods situations under R.C. 1302.18(A) (UCC
    Section 2-305)." Id. at 19.
    {¶ 24} Here, the Oglebay analysis fails at the first step. As discussed, in light of the
    precondition that any "reasonable compensation" must "be evaluated" before payment,
    we conclude that the MOU expresses no intent by the parties to be bound to a breachable
    price term. Moreover, the MOU does not suggest that the parties contracted in spite of a
    "failure to reach an accommodation on price," a situation addressed by the second
    Oglebay step. Malaco at 18. Rather, the MOU evidences an intent to postpone any
    discussion of "reasonable compensation," contingent upon future "evaluation" and
    approval, in light of Grand Valley and the OSFC's authority to determine the permissible
    scope of the remedial work to be performed.
    {¶ 25} For a number of other reasons, the Oglebay holding does not extend to this
    case. First, unlike the MOU, the Oglebay contract contained a mechanism for calculating
    a specific price. Oglebay at 235. For 25 years, the Oglebay parties performed under an
    agreement to ship steel, all the while charging and collecting a price that the contract set
    by reference to an annually published industry standard, until economic conditions forced
    them to renegotiate the price each year. Id. By the time negotiations failed and the parties
    No. 15AP-412                                                                              12
    litigated the price in court, the industry standard was no longer being published. Id. In the
    instant case, however, the MOU references no external pricing mechanism to determine a
    specific price, but mentions only "reasonable compensation" that must be "evaluated."
    Nor have the parties repeatedly performed in accordance with this provision over an
    extended period, which was another factor that led the Oglebay court to analogize the
    shipping contract to a sale of goods under the UCC. Furthermore, in the cases where we
    have applied Oglebay to a services contract, the agreements contained stronger
    indications of the parties' intent to be bound by a pricing term. Malaco at 15 (applying
    Oglebay where term in agreement titled "Compensation" required a minimum payment
    of $10,000 on a specific day of each month); Cook at ¶ 2, 10 (applying Oglebay and
    holding that a contract for funeral services "contain[ing] a series of preprinted boxes for
    itemization of charges" that listed all charges except for obituaries, indicating item "to be
    added," indicated intention to be bound to "the as-yet unascertainable cost of placing
    obituaries in local news outlets"). We discern no such intent in the plain language of the
    MOU.
    {¶ 26} Gibson also argues that Court of Claims erred by finding that it had not
    produced evidence that Grand Valley or the OSFC agreed to pay for work in excess of the
    $20,000 authorized by the purchase order because the MOU "does not reference the
    purchase order or limit payment to Jack Gibson to $20,000." (Appellant's Brief, 19.) It is
    not clear how a reference to the MOU in the purchase order would support Gibson's
    argument. If anything, it would only reinforce the MOU's requirement to obtain approval
    of compensation for any work performed, as the purchase order represents the only
    instance when the parties complied with that condition before paying Gibson for the
    remedial work. The Court of Claims correctly identified the purchase order as the only
    agreement before it that authorized payment to Gibson.
    {¶ 27} Finally, Gibson argues that Grand Valley and the OSFC did not present
    undisputed evidence that entitled them to summary judgment on its breach of contract
    counterclaim because their refusal to pay did not amount to evidence that the MOU did
    not require them to pay Gibson. Thus, Gibson believes that the Court of Claims should not
    have relied upon the affidavit of a Grand Valley representative discussing the $20,000
    payment under the purchase order. According to Gibson, this creates a genuine issue of
    No. 15AP-412                                                                               13
    material fact regarding the scope of work it performed and whether the parties intended
    to be bound by the MOU. (Appellant's Brief, 20-22.)
    {¶ 28} This argument ignores the fact that the Court of Claims based its analysis on
    the unambiguous language of the MOU and concluded, as a matter of law, that the
    agreement did not contain the term that is the basis for Gibson's counterclaim. We agree
    with that court that the obligation asserted Gibson's breach of contract counterclaim is an
    attempt to read a term into the agreement that did not exist. Thus, without resorting to
    any evidence, whether disputed or not, we conclude that Gibson's counterclaim fails as a
    matter of law.
    {¶ 29} For the foregoing reasons, the first assignment of error is overruled.
    IV. SECOND, THIRD, AND FOURTH ASSIGNMENTS OF ERROR
    {¶ 30} Gibson's second assignment of error states: "R.C. 5705.412 specifically
    applies to school districts and controls over the provisions of R.C. 5705.41, a general
    statute that applies to subdivisions or taxing districts." Gibson states that it was error for
    the Court of Claims to hold that the lack of R.C. 5705.41 funds certification was an
    alternative grounds for holding that the MOU was not enforceable. Gibson asserts that a
    certification of funds under R.C. 5705.412 would actually be the applicable certification, as
    that provision specifically applies to expenditures by school districts. However, the third
    assignment of error further asserts that the MOU did not require any statutory
    certification of funds because the account from which the funds for remedial work was to
    be paid was "funded by proceeds from a local bond levy and state construction assistance
    funds administered by the OSFC," not from Grand Valley's general funds.
    {¶ 31} As we have held, the provision of the MOU on which Gibson bases its
    counterclaim was not enforceable. Because the MOU was not an agreement that
    authorized any particular expenditure of funds, it was not required to be accompanied by
    a certification of funds under either statutory provision. Thus, any error resulting from
    the Court of Claims' alternative basis for granting summary judgment was harmless.
    {¶ 32} The same principle applies to the fourth assignment of error, in which
    Gibson argues that the Court of Claims inappropriately relied on an argument raised by
    Grand Valley and the OSFC in their reply brief as an alternative basis for granting
    summary judgment in their favor. The Court of Claims found that even if the MOU had
    No. 15AP-412                                                                                 14
    been enforceable, Gibson pointed to no evidence in the record to show that the agreement
    satisfied the requirements of R.C. 3313.46, the competitive bidding statute that governs
    contracts for school building repairs. As with the second and third assignments of error,
    the lack of an enforceable agreement renders any error resulting from this alternative
    holding harmless. For these reasons, the second, third, and fourth assignments of error
    are overruled.
    V. CONCLUSION
    {¶ 33} Assuming that Gibson performed repair work on the school building worth
    $138.789.13, as it asserts, this court is mindful that the result of this appeal leaves it
    without a remedy. However, Gibson performed the work without having the
    compensation for it "evaluated prior to and/or as work progresse[d]," as the MOU
    required. Furthermore, Gibson chose to perform this work under an agreement that bore
    no indication of complying with any of the previously mentioned statutory provisions that
    govern school building contracts, even after entering into and performing under a
    purchase order that bore statutory certification. Given these facts, Gibson performed the
    work in question at its own risk. If the result is harsh, hopefully the tale is cautionary. See,
    e.g., Empire Gas Corp. v. Westerville Bd. of Edn., 
    102 Ohio App.3d 613
    , 618 (10th
    Dist.1995) (holding that a contract between a natural gas company and a school board
    that lacked the certification required by R.C. 5705.412 was void under the "clear and
    specific" language of the statute, even though "the result is harsh").
    {¶ 34} Having overruled all assignments of error, the judgment of the Court of
    Claims of Ohio is affirmed.
    Judgment affirmed.
    TYACK, J., concurs.
    LUPER SCHUSTER, J., concurs in judgment only.