Sierra Club v. Federal Energy Regulatory Commission , 827 F.3d 59 ( 2016 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued November 13, 2015               Decided June 28, 2016
    No. 14-1249
    SIERRA CLUB,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    AMERICAN PETROLEUM INSTITUTE, ET AL.,
    INTERVENORS
    On Petition for Review of Orders of the
    Federal Energy Regulatory Commission
    Nathan Matthews argued the cause for petitioner. With him
    on the brief was Sanjay Narayan.
    Robert H. Solomon, Solicitor, Federal Energy Regulatory
    Commission, argued the cause for respondent. With him on the
    brief was Karin L. Larson, Attorney.
    Jonathan S. Franklin argued the cause for respondent-
    intervenors Sabine Pass Liquefaction, LLC and Sabine Pass
    LNG, L.P. With him on the brief were Lisa M. Tonery and
    Charles R. Scott.
    2
    Catherine E. Stetson was on the brief for intervenor
    American Petroleum Institute in support of respondent. Stacy R.
    Linden and Benjamin Norris IV entered appearances.
    Before: ROGERS, GRIFFITH and MILLETT, Circuit Judges.
    Opinion for the Court filed by Circuit Judge ROGERS.
    ROGERS, Circuit Judge: Sierra Club seeks review of the
    authorization by the Federal Energy Regulatory Commission of
    an increase in production capacity at a liquefied natural gas
    terminal in Louisiana.          According to Sierra Club, the
    Commission failed to consider certain environmental
    consequences of its authorization, in violation of the National
    Environmental Policy Act of 1969 (“NEPA”), 42 U.S.C. § 4321
    et seq. The Commission initially challenges Sierra Club’s
    standing under Article III of the Constitution to bring this
    petition. For reasons we explain, we conclude that Sierra Club
    has standing but that its challenges to the Commission’s orders
    fail on the merits, largely for the reasons stated in the companion
    case, Sierra Club v. FERC (Freeport), No. 14-1275 (D.C. Cir
    June 28, 2016), and otherwise the court lacks jurisdiction over
    challenges to the Commission’s cumulative impacts analysis due
    to Sierra Club’s failure to exhaust its administrative remedies.
    Accordingly, we dismiss the petition in part and deny the
    petition in part.
    I.
    Until 1977, section 3 of the Natural Gas Act of 1938, Pub.
    L. No. 75-688, 52 Stat. 821, 822 (codified as amended at 15
    U.S.C. § 717b), required the now-defunct Federal Power
    Commission (“FPC”) to approve any application to export
    natural gas to a foreign country unless the proposed export “will
    not be consistent with the public interest.” 15 U.S.C. § 717b(a);
    3
    see also 
    id. § 717a(9).
    In 1977, Congress abolished the FPC,
    created the Federal Energy Regulatory Commission, and
    transferred the section 3 authority to the Secretary of the
    Department of Energy (“the Secretary”). Department of Energy
    Organization Act, §§ 301(b), 401(a), 402(a), Pub. L. No. 95-91,
    91 Stat. 565, 578, 582–84 (codified at 42 U.S.C. §§ 7151(b),
    7171(a), 7172(a)). Subsequently, Congress amended section 3
    to vest in the Secretary “the exclusive authority to approve or
    deny an application for the siting, construction, expansion, or
    operation of [a liquefied natural gas] terminal.” Energy Policy
    Act of 2005, Pub. L. No. 109-58, § 311(c)(2), 119 Stat. 594, 686
    (codified at 15 U.S.C. § 717b(e)(1)). The Secretary has
    delegated to the Commission the decision under section 3
    whether to “[a]pprove or disapprove the construction and
    operation of particular facilities” used for the import or export
    of natural gas, the location of such facilities, and when new
    construction is involved, the entry point for imports and exit
    point for exports of natural gas. See Dep’t of Energy,
    Delegation Order No. 00-004.00A, § 1.21(A) (May 16, 2006);
    42 U.S.C. § 7172(f). The Commission, however, lacks the
    power to authorize the actual import and export of natural gas;
    the Secretary has delegated that section 3 function to the
    Assistant Secretary of Energy for Fossil Energy. See Dep’t of
    Energy, Redelegation Order No. 00-006.02, § 1.3(A) (Nov. 17,
    2014).
    The Commission, in exercising its section 3 authority, must
    comply with NEPA and its implementing regulations, which
    require that all federal agencies include an environmental impact
    statement (“EIS”) “in every recommendation or report on . . .
    major Federal actions significantly affecting the quality of the
    human environment.” 42 U.S.C. § 4332(2)(C); see also 40
    C.F.R. § 1508.11. To determine whether an EIS is necessary, an
    agency first prepares an environmental assessment, 40 C.F.R.
    § 1508.9, which must include, among other information, a
    4
    discussion of “the environmental impacts of the proposed
    action,” 
    id. § 1508.9(b).
    “Indirect effects . . . are caused by the
    action and are later in time or farther removed in distance, but
    are still reasonably foreseeable.” 
    Id. § 1508.8(b).
    “Cumulative
    impact is the impact on the environment which results from the
    incremental impact of the action when added to other past,
    present, and reasonably foreseeable future actions regardless of
    what agency (Federal or non-Federal) or person undertakes such
    other actions.” 
    Id. § 1508.7;
    see also 
    id. § 1508.8.
    After
    preparing an environmental assessment, an agency may
    conclude that the proposed action would have no significant
    impact (often referred to as a “FONSI,” for “finding of no
    significant impact”) in lieu of issuing an EIS.                 
    Id. §§ 1508.9(a)(1),
    1508.13.
    The petition before the court challenges whether the
    Commission complied with NEPA when, pursuant to its
    delegated section 3 powers, it approved an increase in
    production capacity at a liquefied natural gas terminal (“the
    Terminal”) in Cameron Parish, Louisiana, operated by Sabine
    Pass Liquefaction, LLC, and Sabine Pass LNG, L.P.
    (collectively “Sabine Pass”). The Commission initially
    approved the construction and operation of the Terminal as a
    facility for the import of liquefied natural gas into the United
    States. Sabine Pass LNG, L.P. & Cheniere Sabine Pass Pipeline
    Co., 109 F.E.R.C. ¶ 61,324 (2004); Sabine Pass LNG, L.P., 115
    F.E.R.C. ¶ 61,330 (2006). Changes in market conditions,
    however, prompted Sabine Pass to seek Commission
    authorization to construct and operate facilities that would
    permit the Terminal to receive natural gas produced in the
    United States, liquefy it, and prepare it for export to points
    abroad. In 2012, the Commission authorized Sabine Pass to
    liquefy and prepare for export up to 16 million tons of natural
    gas per year. Sabine Pass Liquefaction, LLC & Sabine Pass
    LNG, L.P. (the “2012 Order”), 139 F.E.R.C. ¶ 61,039 at PP 1, 4.
    5
    (2012). Sierra Club, which participated in the Commission
    proceedings, did not petition for judicial review of the 2012
    Order.
    The Commission orders that Sierra Club now challenges
    amend the 2012 Order and deny rehearing of the decision to
    amend. On October 25, 2013, Sabine Pass requested that the
    Commission authorize it to use the Terminal to liquefy and
    prepare for export an additional 4 million tons of natural gas per
    year — in total up to 20 million tons per year. NEPA required
    the Commission to conduct an environmental analysis of Sabine
    Pass’s proposed amendment, and Sierra Club, which intervened
    in the application process, argued that the Commission needed
    to consider several specific environmental consequences in its
    analysis. Among them were two environmental consequences
    that form the core of Sierra Club’s petition to the court. First,
    Sierra Club argued that increasing the volume of exported
    natural gas would induce U.S. natural gas producers to extract
    and process more gas in order to meet the increase in demand
    and thereby cause more gas production-related environmental
    harm. Second, Sierra Club argued there would be increased air
    pollution resulting from increased coal burning, because
    (1) increasing the volume of natural gas exports would more
    fully integrate the domestic natural gas market with the global
    market, where the price of natural gas is generally higher;
    (2) market integration would cause domestic natural gas prices
    to rise as the lower domestic price and the higher global price
    reach an equilibrium; (3) this hike in domestic gas prices would
    prompt U.S. energy consumers — in particular electric utilities
    — to switch from using natural gas to using coal, which is
    cheaper than natural gas but generates more air pollution. In
    Sierra Club’s view, both of these environmental consequences
    of Sabine Pass’s proposal constituted “indirect effects” of the
    proposed amendment and therefore had to be considered in the
    Commission’s NEPA analysis. Sierra Club also maintained that
    6
    the Commission must consider these indirect effects as
    “cumulative impacts” alongside all other pending natural gas
    export proposals.
    Pursuant to NEPA, the Commission produced an
    environmental assessment of Sabine Pass’s latest proposal. It
    summarily rejected Sierra Club’s comments, stating that it had
    addressed them in the environmental assessment that it
    conducted in connection with the 2012 Order. The Commission
    proceeded to grant Sabine Pass’s request and amended the 2012
    Order to increase the maximum volume of natural gas that it
    could liquefy at the Terminal from 16 to 20 million tons per
    year. Sabine Pass Liquefaction, LLC & Sabine Pass LNG, L.P.
    (“2014 Amend.”), 146 F.E.R.C. ¶ 61,117 at PP 5, 12 (2014)
    (“the 2014 Amendment”).          In so doing, the Commission
    explained in greater detail its rejection of Sierra Club’s
    comments. 
    Id. at PP
    15, 19. The Commission observed that
    with respect to effects flowing from export-driven increases in
    domestic natural gas prices, the Department of Energy — and
    not the Commission — possessed the legal authority to approve
    any increase in the volume of natural gas actually exported. 
    Id. at P
    10. The Commission also determined that induced natural
    gas production was not a reasonably foreseeable consequence of
    the 2014 Amendment and therefore not an indirect effect under
    NEPA. 
    Id. at P
    15. Furthermore, in the Commission’s view, the
    2014 Amendment did not generate any new impacts that NEPA
    required it to consider cumulatively. 
    Id. at P
    19. Instead of
    generating an EIS, the Commission therefore issued a FONSI.
    
    Id. at P
    20. The Commission denied Sierra Club’s request for
    rehearing, reiterating the determinations it had made in granting
    the 2014 Amendment. Sabine Pass Liquefaction, LLC & Sabine
    Pass LNG, L.P. (“Rehr’g Order”), 148 F.E.R.C. ¶ 61,200 at
    PP 10–14 (2014).
    7
    II.
    Sierra Club challenges the Commission’s orders granting
    the 2014 Amendment and denying rehearing on the ground that
    the Commission’s NEPA analysis was deficient. That analysis,
    Sierra Club contends, failed to consider two indirect effects and
    should also have considered those effects cumulatively
    alongside all pending and approved proposals to increase the
    volume of natural gas prepared for export nationwide. To
    determine whether the court has jurisdiction to consider these
    challenges, the court must first determine whether Sierra Club
    has standing under Article III of the Constitution.
    An organization has associational standing to bring suit on
    its members’ behalf when: (1) at least one of its members would
    have standing to sue in his or her own right; (2) “the interests it
    seeks to protect are germane to the organization’s purpose”; and
    (3) “neither the claim asserted nor the relief requested requires
    the participation of individual members in the lawsuit.”
    WildEarth Guardians v. Jewell, 
    738 F.3d 298
    , 305 (D.C. Cir.
    2013) (quoting Hunt v. Wash. State Apple Adver. Comm’n, 
    432 U.S. 333
    , 343 (1977)); see also Del. Dep’t of Natural Res. &
    Envtl. Control v. EPA, 
    785 F.3d 1
    , 7 (D.C. Cir. 2015). That
    Sierra Club meets the latter two requirements is unchallenged
    and clear, while the first requirement warrants discussion.
    To satisfy the first requirement of the associational standing
    inquiry, Sierra Club must show that: (1) at least one of its
    members has suffered an “injury-in-fact” that is “concrete and
    particularized” and “actual or imminent, not conjectural or
    hypothetical”; (2) the injury is “fairly traceable to the challenged
    action”; and (3) it is “likely, as opposed to merely speculative,
    that the injury will be redressed by a favorable decision.”
    Friends of the Earth, Inc. v. Laidlaw Envtl. Servs. (TOC), Inc.,
    
    528 U.S. 167
    , 180–81 (2000) (citing Lujan v. Defenders of
    8
    Wildlife, 
    504 U.S. 555
    , 560–61 (1992)). It must demonstrate a
    “substantial probability” that it satisfies each element of
    standing. Sierra Club v. EPA, 
    292 F.3d 895
    , 898–99 (D.C. Cir.
    2002). Where, as here, a party alleges deprivation of its
    procedural rights, courts relax the normal standards of
    redressability and imminence. Summers v. Earth Island Inst.,
    
    555 U.S. 488
    , 496–97 (2009) (citing 
    Lujan, 504 U.S. at 572
    n.7).
    As for causation, in a NEPA procedural injury case, the
    petitioner need demonstrate only that “the procedural step was
    connected to the substantive result,” not that “the agency would
    have reached a different substantive result” but for the alleged
    procedural error. WildEarth 
    Guardians, 738 F.3d at 306
    (internal citations omitted); see also City of Dania Beach v.
    FAA, 
    485 F.3d 1181
    , 1186–87 (D.C. Cir. 2007); Sugar Cane
    Growers Co-op. of Fla. v. Veneman, 
    289 F.3d 89
    , 94–95 (D.C.
    Cir. 2002). “[A]n adequate causal chain must contain at least
    two links: one connecting the omitted [NEPA analysis] to some
    substantive government decision that may have been wrongly
    decided because of the lack of [proper NEPA analysis] and one
    connecting that substantive decision to the plaintiff’s
    particularized injury.” Fla. Audubon Soc. v. Bentsen, 
    94 F.3d 658
    , 668 (D.C. Cir. 1996) (en banc). It must be substantially
    probable “that the substantive agency action that disregarded a
    procedural requirement created a demonstrable risk, or caused
    a demonstrable increase in an existing risk, of injury to the
    particularized interests of the plaintiff . . . .” 
    Id. at 669.
    Sierra Club meets the requirements of associational
    standing on the basis of a declaration submitted by one of its
    members, John Paul. Paul “fish[es], boat[s], and seasonal duck
    hunt[s] frequently around Keith Lake, the south side of Sabine
    Lake,” “the Texas Point National Wildlife Refuge,” and “the
    Sabine River (on the south side of the Sabine Lake).” Decl. of
    John Paul (“Paul Decl.”) ¶¶ 5, 9 (May 19, 2015). The Terminal
    sits along the shoreline of the Sabine Pass Channel, a waterway
    9
    through which Sabine Lake empties into the Gulf of Mexico.
    Paul attests “the increase in [liquefied natural gas] vessel traffic
    from the Sabine Pass [Terminal]” will: (1) harm his aesthetic
    interests in the waterways around the Terminal;
    (2) inconvenience him, given the “large exclusion zone the
    Coast Guard maintains around [tankers]”; and (3) “diminish
    [his] use and enjoyment of the waterways, and specifically the
    Sabine River and Texas Wildlife Refuge.” 
    Id. In fact,
    due in
    part to existing levels of operation at the Terminal, Paul recently
    moved his “primary boat” from Sabine Pass to Galveston,
    Texas. 
    Id. ¶ 7.
    Sierra Club contends that Paul satisfies the
    elements of standing because: (1) increased tanker (i.e., cargo
    vessel) traffic will harm Paul’s aesthetic and recreational
    interests; (2) the 2014 Amendment will result in increased
    production of liquefied natural gas for export, the transport of
    which will require additional tankers; and (3) a decision in favor
    of Sierra Club would give the Commission the chance to
    reconsider the increase in production capacity it approved in the
    2014 Amendment after it corrects its NEPA analysis.
    There can be little doubt that Paul will suffer cognizable
    aesthetic and recreational harm were the volume of tanker
    traffic to and from the Terminal to grow. See Friends of the
    
    Earth, 528 U.S. at 182
    –83; 
    Lujan, 504 U.S. at 562
    –63; Sierra
    Club v. Morton, 
    405 U.S. 727
    , 734–35 (1972); Minisink
    Residents for Envtl. Preservation & Safety v. FERC, 
    762 F.3d 97
    , 106 (D.C. Cir. 2014). The Commission’s suggestion that
    Paul “appears to no longer fish near the Sabine Pass terminal”
    after moving his boat to Galveston, Resp’t’s Br. 25, misreads
    the Paul Declaration. Paul states, in the present tense, that he
    “frequently” fishes, boats, and hunts in waterways near the
    Terminal. Paul Decl. ¶ 5. He also expresses concern that
    greater tanker traffic “will” diminish his use and enjoyment of
    those waterways. 
    Id. ¶ 9.
    That Paul moved his “primary boat”
    to Galveston does not undermine his claim that he presently
    10
    boats near the Terminal and will continue to do so in the future.
    If anything, Paul’s decision to move one of his boats partly in
    response to the Terminal’s current production levels (up to
    16 million tons per year) gives credence to his assertion that
    additional tanker traffic will compound his aesthetic and
    recreational injury.
    Sierra Club has also demonstrated a substantial probability
    that an increase in production capacity at the Terminal will
    cause an increase in tanker traffic. The Commission insists that
    the 2014 Amendment will not result in a greater number of
    tankers traversing the waters around the Terminal. See Resp’t’s
    Br. 26. Throughout the process of approving an additional
    4 million tons of annual production capacity at the Terminal, the
    Commission maintained that the 2014 Amendment would not
    increase the maximum number of tankers — 400 per year —
    authorized to serve the Terminal in the 2012 Order. Sabine Pass
    Amend. Envtl. Assessment (“2014 Envtl. Assessment”) at 5
    (2014); 2014 Amend., 146 F.E.R.C. ¶ 61,117 at P 18; Rehr’g
    Order, 148 F.E.R.C. ¶ 61,200 at PP 8–9. Yet keeping constant
    the authorized maximum number of tankers is not the same
    thing as keeping constant the actual number of tankers plying
    the waterways near the Terminal.
    To the contrary, the record demonstrates that even when the
    authorized maximum number of tankers remains steady, an
    increase in the volume of natural gas prepared for export
    corresponds with an increase in the number of tankers needed
    to ferry it into foreign commerce. In fact, there is a roughly
    linear relationship between production capacity and the number
    of tankers needed. A production capacity of 8 million tons of
    liquefied natural gas per year requires an estimated 69 to 147
    tankers, whereas a production capacity of 16 million tons per
    year requires twice that — between an estimated 138 and 294
    tankers.     See Sabine Pass Liquefaction Project Envtl.
    11
    Assessment at 2-15 (2011). Sabine Pass has entered into
    contracts to export 18 million tons of liquefied natural gas per
    year. 2014 Amend., 146 F.E.R.C. ¶ 61,117 at P 12 n.18. That
    is 2 million tons above the maximum production capacity of
    16 million tons per year authorized by the 2012 Order. 
    Id. at P
    5. There is a very substantial probability that Sabine Pass will
    require more tankers to transport the additional 2 million tons
    of natural gas per year, a quantity it could not legally liquefy
    and prepare for export but for the 2014 Amendment.
    Therefore, Sierra Club satisfies the causation and
    redressability requirements of Article III standing. First, the
    alleged omissions in the Commission’s NEPA analysis are
    connected to the Commission’s decision to authorize the
    increased volume of production in the 2014 Amendment. If
    Sierra Club prevails on the merits, the Commission will have to
    incorporate into its NEPA analysis the omitted indirect effects
    and cumulative impacts. Upon considering those effects, the
    Commission could change its position and deny Sabine Pass’s
    application for additional production capacity. Second, the
    decision to authorize additional production capacity in the 2014
    Amendment is connected to the harm to Paul’s aesthetic and
    recreational interests. Absent the 2014 Amendment, Sabine
    Pass could not fulfill its contractual obligations to export
    2 million tons of liquefied natural gas per year above the pre-
    2014 Amendment production ceiling. It is substantially
    probable — if not more likely still — that those 2 million tons
    of additional export will require additional tankers, and those
    additional tankers are the source of the harm to Paul’s aesthetic
    and recreational interests.
    The Paul Declaration is distinguishable from the
    declarations submitted in National Committee for the New
    River, Inc. v. FERC, 
    433 F.3d 830
    (D.C. Cir. 2005). Petitioners
    in that case challenged the realignment of a natural gas pipeline,
    12
    yet their affidavits focused not on harms arising from the
    realignment but on general harms arising from the construction
    of the pipeline in the first place. 
    Id. at 831–32.
    Nothing in the
    affidavits explained how their injuries depended on whether the
    pipeline crossed one part of the New River versus another. 
    Id. at 832.
    Here, by contrast, the Paul Declaration attributes his
    injury to the “increase in operations” at the Terminal and
    “additional operation of the export facility.” Paul Decl.
    ¶¶ 7–10. Even if Paul would suffer a similar type of harm in the
    absence of the 2014 Amendment, the 2014 Amendment will
    cause him to suffer an additional quantum of that harm.
    The Commission’s reliance on Center for Biological
    Diversity v. U.S. Department of the Interior, 
    563 F.3d 466
    (D.C.
    Cir. 2009), mistakes sufficiency for necessity. There, members
    of the petitioner organization detailed in their affidavits
    “definitive dates in the near future” when they planned to
    observe animals affected by offshore oil and gas drilling. 
    Id. at 479.
    But the court did not hold that a statement of definite dates
    is necessary to establish Article III standing where, as here, a
    member of a petitioner organization lives an hour’s drive from
    the affected area and attests in a sworn statement that he
    “frequently” fishes, boats, and duck hunts in the waters around
    the Terminal. Paul Decl. ¶¶ 2, 5.
    III.
    Turning to the merits of Sierra Club’s petition for review,
    the court’s review of the Commission’s compliance with NEPA
    is limited to determining whether the Commission’s NEPA
    analysis was “arbitrary, capricious, an abuse of discretion, or
    otherwise not in accordance with law.” Nat’l Comm. for the
    New River v. FERC, 
    373 F.3d 1323
    , 1327 (D.C. Cir. 2004)
    (citing 5 U.S.C. § 706(2)(A)). NEPA requires a federal agency
    to take a “hard look” at the environmental consequences of a
    13
    major action prior to undertaking it. Balt. Gas & Elec. Co. v.
    Natural Res. Def. Council, Inc., 
    462 U.S. 87
    , 97 (1983). As a
    procedural statute, NEPA does not mandate any particular
    outcome. Minisink 
    Residents, 762 F.3d at 111
    –12.
    A.
    Sierra Club contends that the Commission’s NEPA analysis
    failed to consider two indirect effects of the 2014 Amendment.
    Both presuppose that the 2014 Amendment will increase natural
    gas export capacity and thereby expose the domestic natural gas
    market to new international demand. First, natural gas
    producers in the United States will extract and process more gas
    to meet this newly heightened demand for their product, thereby
    intensifying production-related pollution. Second, increasing
    export capacity will raise the domestic price of natural gas, and
    that, in turn, will prompt greater reliance on coal, a cheaper but
    more pollution-intensive fuel.
    We disagree for the reasons stated in Sierra Club
    (Freeport), No. 14-1275, Slip Op. at 13–20. What Sierra Club
    challenges here is the potential environmental effects flowing
    from greater natural gas exports from the Terminal. The two
    indirect effects at the heart of Sierra Club’s petition cannot
    occur unless a greater volume of liquefied natural gas is shipped
    from the Terminal and enters the international marketplace. But
    the Commission orders challenged here do not authorize Sabine
    Pass to increase exports from the Terminal. 2014 Amend., 146
    F.E.R.C. ¶ 61,117 at P 5 n.10; Rehr’g Order, 148 F.E.R.C.
    ¶ 61,200 at PP 3 n.6, 14. Those orders only authorize an
    increase in production capacity at the Terminal. 2014 Amend.,
    146 F.E.R.C. ¶ 61,117 at PP 11–12; Rehr’g Order, 148 F.E.R.C.
    ¶ 61,200 at P 3. As the Commission explained, the Department
    of Energy alone has the legal authority to authorize Sabine Pass
    to increase commodity exports of liquefied natural gas. 2014
    Amend., 146 F.E.R.C. ¶ 61,117 at P 10; Rehr’g Order, 148
    14
    F.E.R.C. ¶ 61,200 at PP 12–13; see also 15 U.S.C. § 717b(a); 42
    U.S.C. § 7151(b); compare also Dep’t of Energy, Redelegation
    Order No. 00-006.02, § 1.3(A) (Nov. 17, 2014), with Dep’t of
    Energy, Delegation Order No. 00-004.00A, § 1.21(A) (May 16,
    2006). The challenged Commission orders therefore are not the
    legally relevant cause of the indirect effects Sierra Club raises.
    See Dep’t of Transp. v. Pub. Citizen, 
    541 U.S. 752
    , 769–70
    (2004). Accordingly, the Commission did not need to consider
    those effects in its NEPA review. 
    Id. at 770.
    Sierra Club, of
    course, remains free to raise these issues in a challenge to the
    Energy Department’s NEPA review of its export decision.
    Nothing in our opinion should be read to foreclose that
    challenge or predetermine its outcome.
    Furthermore, the Commission adequately explained why it
    was not reasonably foreseeable that greater production capacity
    at the Terminal — separate and apart from any export activity
    — would induce additional domestic natural gas production.
    See 40 C.F.R. § 1508.8(b). It concluded that the Terminal’s
    liquefaction operations did not necessitate an increase in
    domestic natural gas production. 2014 Amend., 146 F.E.R.C.
    ¶ 61,117 at P 15 (citing 2012 Order, 139 F.E.R.C. ¶ 61,039 at
    PP 94–99); Rehr’g Order, 148 F.E.R.C. ¶ 61,200 at P 13; see
    also 2012 Order, 139 F.E.R.C. ¶ 61,039 at P 98. Whatever
    effect increased natural gas exports might have on domestic
    production levels, the Commission’s conclusion was reasonable
    with respect to the effect of increasing production capacity.
    B.
    Next, Sierra Club contends the Commission failed to take
    into account certain cumulative impacts of the 2014
    Amendment.      In particular, Sierra Club maintains the
    Commission should have considered the impacts of the 2014
    Amendment alongside several other proposals to increase
    natural gas export capacity nationwide, some pending, some
    15
    already approved. Those proposals include two other projects
    at the Terminal (the “Sabine Pass projects”). During
    administrative proceedings, the Commission determined that the
    2014 Amendment would not contribute to any cumulative
    impacts. 2014 Amend., 146 F.E.R.C. ¶ 61,117 at P 19. On
    appeal, the Commission contends that Sierra Club’s argument
    fails on two grounds: (1) The court lacks jurisdiction to hear
    Sierra Club’s contention regarding the other projects — save for
    one of the Sabine Pass projects — because it failed to raise them
    in its petition for rehearing before the Commission, and (2) in
    any event, NEPA did not require the Commission to consider
    the effects of the 2014 Amendment cumulatively with the other
    projects.
    1. The court lacks jurisdiction to consider Sierra Club’s
    challenge as it pertains to any projects other than the Sabine
    Pass projects. Section 19(a) of the Natural Gas Act requires that
    a party seek rehearing by the agency before challenging an
    order issued pursuant to the Act. 15 U.S.C. § 717r(a). Section
    19(b) bars a court from hearing an objection to such an order
    where the objecting party failed to raise the objection in its
    application for rehearing and there are no reasonable grounds to
    excuse the party’s failure. 
    Id. § 717r(b).
    The purpose of the
    exhaustion requirement in § 717r is to give the Commission the
    first opportunity to consider challenges to its orders and thereby
    narrow or dissipate the issues before they reach the courts.
    Moreau v. FERC, 
    982 F.2d 556
    , 564 (D.C. Cir. 1993). The
    Natural Gas Act’s jurisdictional provisions are stringent. See
    Columbia Gas Transmission Corp. v. FERC, 
    477 F.3d 739
    , 741
    (D.C. Cir. 2007).
    Sierra Club endeavors to hang jurisdiction on a very thin
    reed. In its Motion to Intervene, Sierra Club commented that
    the Commission needed to “consider the cumulative impacts of
    all pending export proposals.” Mot. to Intervene, Protest &
    16
    Cmt. at 19 (Nov. 14, 2013). Its Motion for Rehearing, however,
    contains no mention of any projects besides other Sabine Pass
    projects. The header of the relevant section reads: “FERC
    Violated NEPA by Failing to Consider Connected Actions or
    the Cumulative Effect of Other Proposed Sabine and Related
    Pipeline Projects.” Mot. for Rehr’g at 6 (Mar. 24, 2014). In
    that section, Sierra Club notes that the 2014 Amendment “is one
    of only a number [sic] of pending proposals for expansion of the
    Sabine Pass project” and mentions that “Sabine Pass has also
    applied for authorization to construct two additional
    liquefaction trains and pipeline modifications. CP13-552 and
    CP13-553.” 
    Id. Sierra Club
    maintains that this merely “drew
    the Commission’s attention to” the specified Sabine Pass project
    but “did not suggest that these were the only relevant actions,
    for purposes of a cumulative impacts analysis.” Pet’r’s Reply
    Br. 33–34. This reads too much into its Motion for Rehearing.
    Nothing in that motion put the Commission on notice that Sierra
    Club was challenging the Commission’s cumulative impacts
    analysis as it pertained to projects other than the Sabine Pass
    projects. In granting the 2014 Amendment, the Commission
    understood Sierra Club to contend that the Commission needed
    to consider natural gas projects unrelated to the Terminal. 2014
    Amend., 146 F.E.R.C. ¶ 61,117 at P 19. In denying rehearing,
    the Commission addressed only one of the other Sabine Pass
    projects while noting that Sierra Club on rehearing did not
    challenge the Commission’s cumulative impacts analysis as to
    projects unrelated to the Terminal. Rehr’g Order, 148 F.E.R.C.
    ¶ 61,200 at P 11 n.22. Because the Commission was not on
    notice of Sierra Club’s broader objection, it did not have the
    opportunity to consider them in the first instance. By contrast,
    in Louisiana Intrastate Gas Corp. v. FERC, 
    962 F.2d 37
    (D.C.
    Cir. 1992), on which Sierra Club relies, the petitioner expressly
    and clearly stated its objection, albeit in a single sentence, 
    id. at 41–42,
    and the Commission addressed the merits of the
    17
    objection in denying rehearing, 
    id. at 42.
    Neither indicia of
    notice is present here.
    2. On the merits, we hold that the Commission’s orders are
    not arbitrary or capricious for failing to address the cumulative
    impacts of the 2014 Amendment and the Sabine Pass projects
    for largely the same reason stated in Sierra Club (Freeport),
    No. 14-1275, Slip Op. at 22–23. The Commission provided a
    reasonable explanation for why it was unnecessary to conduct
    a cumulative impact analysis: The 2014 Amendment did not
    generate environmental impacts of the sort that NEPA requires
    it to consider cumulatively. 2014 Amend., 146 F.E.R.C.
    ¶ 61,117 at P 19; see also Minisink 
    Residents, 762 F.3d at 113
    .
    Accordingly, we dismiss Sierra Club’s petition for review
    in part and deny it in part.
    

Document Info

Docket Number: 14-1249

Citation Numbers: 423 U.S. App. D.C. 417, 827 F.3d 59, 46 Envtl. L. Rep. (Envtl. Law Inst.) 20116, 182 Oil & Gas Rep. 1060, 82 ERC (BNA) 1860, 2016 U.S. App. LEXIS 11747, 2016 WL 3525562

Judges: Rogers, Griffith, Millett

Filed Date: 6/28/2016

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (15)

Baltimore Gas & Electric Co. v. Natural Resources Defense ... , 103 S. Ct. 2246 ( 1983 )

Sugar Cane Growers Cooperative of Florida v. Veneman , 289 F.3d 89 ( 2002 )

louisiana-intrastate-gas-corporation-v-federal-energy-regulatory , 962 F.2d 37 ( 1992 )

National Committee for the New River, Inc. v. Federal ... , 433 F.3d 830 ( 2005 )

Hunt v. Washington State Apple Advertising Commission , 97 S. Ct. 2434 ( 1977 )

Sierra Club v. Environmental Protection Agency , 292 F.3d 895 ( 2002 )

National Committee for the New River, Inc. v. Federal ... , 373 F.3d 1323 ( 2004 )

Lujan v. Defenders of Wildlife , 112 S. Ct. 2130 ( 1992 )

Columbia Gas Transmission Corp. v. Ederal Energy Regulatory ... , 477 F.3d 739 ( 2007 )

City of Dania Beach v. Federal Aviation Administration , 485 F.3d 1181 ( 2007 )

Friends of the Earth, Inc. v. Laidlaw Environmental ... , 120 S. Ct. 693 ( 2000 )

Department of Transportation v. Public Citizen , 124 S. Ct. 2204 ( 2004 )

Center for Biological Diversity v. United States Department ... , 563 F.3d 466 ( 2009 )

judith-b-moreau-n-robert-moreau-clara-lawrence-and-walter-lawrence-v , 982 F.2d 556 ( 1993 )

Sierra Club v. Morton , 92 S. Ct. 1361 ( 1972 )

View All Authorities »