-
McCulloch, O. J. Appellant, Arkansas Construction Company, under contract with Special School District of Pine Bluff, constructed additions and improvements to two separate school buildings in the city of Pine Bluff, and the other appellant, the JEtna Casualty and Surety Company, became surety on the bond of the contractor. Appellee, a foreign corporation, doing business in Memphis, Tennessee, furnished the structural iron and steel building material used by the Arkansas Construction Company in the performance of the contract, and this is an action instituted by appellee to recover the amount of balance alleged to be due. The total bill of the material furnished by appellee was $1,428.08, and, after allowing certain credits, not now in dispute, appellee recovered below the sum of $607.69. The action was instituted and tried in the chancery court. Appellants filed an answer, and went to trial without objection to the cause having been instituted in the chancery court, but, several days after the cause had been submitted to the court and decree had been pronounced, but before entry of the decree, appellants filed a motion to transfer the cause to the law court, on the ground that the court of equity had no jurisdiction. This was overruled, and decree entered, and an appeal duly prosecuted.
It is first contended that the court should have sustained the motion to transfer, even though it was filed after the court had announced its decree. We cannot agree with counsel, for the motion came too late. It should have been presented before the submission of the case to the court, and especially before judgment had been pronounced. Of course, the court, even after pronouncing decree, could have set aside the same and granted the motion, if proper, but it was a matter of discretion with the court whether it would entertain the motion at that late date, hence we cannot say'there was any abuse of discretion, after permitting- the case to go to judgment. It is unnecessary to say whether or not the motion should have been granted if presented in apt time.
The only other question involved on the appeal relates to the amount of recovery. There is a dispute as to the terms of the contract between the parties and as to the prices to be paid for the material. Appellee contends that the aggregate contract price was $1,428.08, but appellants contend that the total price was $1,099.65, and admitted liability for a balance of $390. Appellants made a tender of that amount, which tender was refused. The inquiry therefore turned on questions of fact, and there was a conflict in the testimony. The testimony adduced by appellee was to the effect that the agent handling the matter for appellee, as salesman, entered into an agreement to furnish the material at reasonable prices, it being impossible to specify, in advance, the quantity of material and the prices. On the other hand, the contention of appellants was that appellee agreed to furnish the material “as low as anybody in Pine Bluff,” and not exceeding a bid which the construction company had already received from a dealer in Pine Bluff, who had offered to furnish the material at an aggregate price of $1,099.65.
The court found in favor of appellants, that the contract was that appellee was to furnish the material for prices not exceeding the bid therefor which the construction company* then had from the Pine Bluff Iron Works,
The court also found from the testimony that the bid of the Pine Bluff Iron Works “was incomplete, in that it did not include all of the iron and steel which was used in the buildings. ’ ’
It appears from the testimony also that, after the buildings were completed, or rather, after all the material had been furnished, appellee’s agent presented a bill, specifying all the items, with prices extended on the bill, to the manager of the construction company, and that the latter agreed to pay the bill, and placed his O. K. thereon. The manager testified on behalf of appellants, and ádmitted that he placed his 0. K. on the bill, stating that the prices were not marked thereon, and that he only approved the list of material furnished. There is a sharp conflict on this point between the agent of appellee and the manager of the construction company. But we are unable to say that the findings of the chancery court were against the preponderance of the evidence.
Decree affirmed.
Document Info
Citation Numbers: 291 S.W. 57, 172 Ark. 721, 1927 Ark. LEXIS 78
Judges: McCulloch
Filed Date: 1/31/1927
Precedential Status: Precedential
Modified Date: 10/19/2024