Rischard v. Miller ( 1920 )


Menu:
  • The plaintiff appeals from the judgment.

    The complaint alleges that the plaintiff and the defendant made a contract whereby the defendant undertook to construct a dwelling-house on a lot belonging to the plaintiff, in accordance with certain plans and specifications, for the sum of two thousand six hundred dollars; that the defendant had completed the building but had failed to construct it according to the plans and specifications, whereby the plaintiff was damaged in the sum of $1,378.

    The answer denies the allegations of the complaint concerning the failure to construct the building as provided in the plans and specifications. The defendant also filed a cross-complaint alleging that by the terms of the contract sued on, the sum of $1,250 of the contract price was to be paid to the defendant by the plaintiff thirty-five days after notice of completion, and that this payment was to be made by the conveyance from the plaintiff to the defendant of a lot adjoining that upon which the building was constructed, free and clear of encumbrance, valued in the contract at $1,250; that the defendant had constructed the building in accordance with the terms of the contract and gave notice of completion thereof to the plaintiff, and that plaintiff had refused to convey to the defendant, as the final payment thereon, the said lot, as he had agreed to do. Thereupon he prayed for a decree enforcing performance of the agreement to convey the said lot to him.

    The court made findings in accordance with the allegations of the cross-complaint, and that, although in a few minor and trivial matters the building did not strictly and technically comply with the terms of the contract, the departure was not willful nor intentional on the part of the *Page 353 defendant, and that the defects were capable of being easily remedied to conform to the terms of the contract at an expense not exceeding $99.50. Thereupon the court concluded that the defendant was entitled to have the contract enforced in his favor, with an abatement of $99.50 on the contract price on account of the defects found to exist, by the conveyance of said lot by the plaintiff to the defendant, upon the payment by defendant to the plaintiff of the difference between the sum of $1,250, at which the lot was to be accepted as payment, and the amount found due and unpaid on the contract price. Judgment was given accordingly in favor of the defendant for specific performance.

    The plaintiff insists that the defects of construction found by the court were so serious and important to the performance of the contract that the case does not come within the rule which allows the enforcement of a contract by one party where it has been substantially performed by him, although not completely performed in accordance with its terms. InConnell v. Higgins, 170 Cal. 556, [150 P. 769], the court considered this question and quoted a passage from section 1607 of Elliott on Contracts defining the meaning of the term "substantial performance," as applied to questions of this character. [1] The rule there stated is that if there has been no willful departure from the terms of the contract, and no omission of any of its essential parts, if the contractor has performed in good faith all of its substantive terms, or if the omission is so slight that it cannot be regarded as an integral or substantive part of the contract and the other party can be compensated therefor by a recoupment in the way of damages, the contractor may recover whatever is due upon the contract less such recoupment, especially in a case where the other party has received the benefit of what has been done and is enjoying the fruits of the work.

    The defects stated in the findings are all of the character thus defined. On the foundation wall there was what is termed a "slight burning of the concrete" at one point, which could be removed at the cost of $25. There was a slight settling of the floor around a pillar in one of the rooms. Ten dollars would have paid for correcting the defect. The pieces of glass in a cabinet door were not of precisely the size specified in the contract. The change could *Page 354 have been made for $3.50. Half-inch water-pipe had been used as laterals to connect the service-pipe with half-inch openings in the faucets. Three-quarter inch was specified. The change could have been made for $25. The evidence showed that half-inch pipe was usual in such cases and was as serviceable in all respects as three-quarter inch pipe. In one of the rooms No. 2 flooring had been used instead of No. 1, but it was so clear of all imperfections that the plaintiff himself did not discover it at the time, although he was present when it was being laid. In one of the closets a hat cupboard was specified and was not put in. It could have been put in for $5. A depression in the cement floor on the front porch could have been corrected for $1. These comprise all the defects in the findings for which the $99.50 was involved. [2] The uncontradicted evidence would have supported findings much less favorable to the plaintiff than those made by the court. The defects did not to any appreciable extent affect the use or value of the house as a dwelling place.

    [3] The objection that the cross-complaint does not aver that the price fixed for the lot was adequate, or that the contract was just and reasonable to the plaintiff, is without merit, or at all events, not sufficient to warrant a reversal, (Const., art. VI, sec. 4 1/2.) It does show that the plaintiff himself valued it at the price fixed when he made the contract to convey it, and by himself suing to enforce the contract, he, in effect, affirmed that it was just and reasonable. [4] The objection that a demand for the conveyance was not alleged is also and for like reasons insufficient for reversal. It alleges that the plaintiff was given notice that the building was completed and that he refused to convey the lot, as he had agreed to do. His own suit for damages on the ground that the building was not completed shows that a formal demand at the time the cross-complaint was filed would have been but an idle ceremony. In such a case an averment of a demand for a deed is unnecessary. (Gray v. Dougherty, 25 Cal. 281.)

    We find no ground upon which the appeal can be sustained.

    The judgment is affirmed.

    Lawlor, J., and Olney, J., concurred. *Page 355

Document Info

Docket Number: L. A. No. 5319.

Judges: Shaw

Filed Date: 3/1/1920

Precedential Status: Precedential

Modified Date: 10/19/2024