* Pending decision of this case on rehearing, stipulation dismissing same was filed January 7, 1938. See, also,DeTroyer v. Ernst Kern Co., 282 Mch. 689. — REPORTER. Plaintiff, employed by the City Ice Fuel Company, August 25, 1933, suffered an injury to the right forearm and minor bruises on the upper arm and shoulder, as reported by the employer. Plaintiff was taken to the Hurley hospital at Flint. September 7, 1933, an agreement for compensation was made which described the injuries as "severe laceration of right forearm — minor bruises on right upper arm and shoulder." This agreement for compensation was approved by the department of labor and industry September 21, 1933. Other agreements for compensation were made and approved. August 28, 1934, still another agreement for compensation was made which was approved by the department November 2, 1934, which recited the accident and that compensation had been paid for a total of 27-2/6 weeks at $13.67 a week, and for partial disability for 18 weeks at $4.34 a week, a total of $451.77. This supplemental agreement recited:"It is now hereby agreed that in the opinion of all the parties hereto, that disability has ended, and that because thereof payment of all further compensation shall stand suspended from and after the 22d day of July, 1934." *Page 594
The agreement also contained a stipulation:
"If further disability from such injuries shall hereafter develop, this agreement shall not bar plaintiff's rights to petition the department for such further and added compensation as he may be entitled to; that on the hearing of such petition the plaintiff shall bear the burden of proof, and the department shall determine such petition according to the facts."
Subsequently and on May 13, 1935, plaintiff petitioned for further compensation, and on June 12, 1935, filed a petition for lump sum settlement. Defendant opposed plaintiff's petition for further compensation upon the ground he was not permanently disabled as a result of the accident; that he was able to work and earn substantially the same wages he was earning at the time of the accident; there was no change for the worse in plaintiff's condition since the approval of the agreement suspending further compensation, approved November 2, 1934; and that the defendant tendered work to the plaintiff, but plaintiff refused to do the same. Upon this petition for further compensation, the deputy commissioner, October 4, 1935, made a finding that plaintiff was suffering total disability and said disability had continued since May 14, 1935, and awarded compensation on the basis of $13.67 a week for total disability. Defendant filed a claim for review and this came on before the department of labor and industry which affirmed the finding of the deputy commissioner. Whereupon, defendant appealed to this court, claiming (1) the order of the department approving the supplemental agreement suspending further compensation constituted an arbitral award and that the matters therein contained are res judicata; (2) that the plaintiff had not alleged or *Page 595 offered any proof of change of condition, and consequently the department had no jurisdiction to hear the case; and (3) that the findings did not substantiate the plaintiff's claim of total disability.
A final settlement receipt, such as was before the court inRichards v. Rogers Boiler Burner Co.,
252 Mich. 52 , was not involved. The agreement was not one suspending compensation, approved conditionally, as in Seem v. Consolidated Fuel Lumber Co.,234 Mich. 637 .The agreement of August 28, 1934, must be construed as a whole. Neither the employer nor the employee may claim the benefit of that part of it beneficial to him and repudiate that part which is onerous. The agreement and the order approving the same are either valid or invalid. The agreement is either within or without the terms of the workmen's compensation act.
A trick agreement valid for the purpose of terminating the compensation of the employee and void so far as it imposes obligations on the employer is not such a one as the statute contemplates. Carpenter v. Detroit Forging Co.,
191 Mich. 45 .The supplemental agreement above mentioned was not one to stop compensation. It did not contemplate its permanent cessation or discontinuance. It was one to suspend compensation — " further compensation shall stand suspended." Its language connotes such compensation was to be temporarily withheld; should cease temporarily; was to be held in an undetermined state, in suspense; was to be kept waiting.
An agreement stopping compensation must be without contingency or condition, and not based upon a possible or probable event which may render it inoperative.Carpenter v. Detroit Forging Co., *Page 596 supra; Dettloff v. Hammond, Standish Co.,
195 Mich. 117 .If the agreement is not warranted by the statute, the order of the department of labor and industry approving it was made without authority.
"Such agreements shall be approved by said board* only when the terms conform to the provisions of this act." 2 Comp. Laws 1929, § 8444.
And the order of the department in force at the time of the making of such agreement and its approval by the department of labor and industry remains in full force and effect. The order here under consideration was without authority and void abinitio. Dettloff v. Hammond, Standish Co., supra.
The order of the department of labor and industry of November 2, 1934, approving the agreement of August 28, 1934, is set aside and held for naught, and the last prior order of the department of labor and industry reinstated in full force and effect, with costs.
BUTZEL, BUSHNELL, SHARPE, and CHANDLER, JJ., concurred with POTTER, J.
* The powers and duties of the industrial accident board, here referred to, have been transferred to the department of labor and industry and the board abolished. See 2 Comp. Laws 1929, § 8812. — REPORTER.
Document Info
Docket Number: Docket No. 82, Calendar No. 39,070.
Judges: Butzel, Bushnell, Sharpe, Chandler, Potter, North, Wiest, Fead
Filed Date: 5/21/1937
Precedential Status: Precedential
Modified Date: 10/19/2024