-
* Corpus Juris-Cyc. References: Assignments, 5 C.J., p. 953, n. 36; p. 958, n. 89; Subrogation, 37 Cyc, p. 380, n. 85; p. 415, n. 9; p. 417, n. 24: Priority as between different assignees of same chose in action as affected by notice to debtor, see note in 31 A.L.R. 876; 2 R.C.L., p. 628, 1 R.C.L. Supp. 595; 5 R.C.L. Supp., p. 105 et seq.; Commencement of right of surety to subrogation, see 25 R.C.L., p. 1329; 4 R.C.L. Supp., p. 1629; 5 R.C.L. Supp., p. 1373. This is an appeal from the chancery court of Yazoo county, wherein the board of supervisors of said county filed its bill of interpleader wherein it is alleged that on account of its contract with J.R. Parker for the construction of the Benton and Moore ferry road there was due and owing on such contract from said county the sum of seven thousand seven hundred eighty-five dollars and eighteen cents, and the laborers, materialmen, and their assignees, on the one hand, and the Canton Exchange Bank, another defendant, were each claiming said fund.It further set up that the guaranty company was surety on the bond executed with the contract by Parker, and that the surety company claimed that in the application for the bond Parker assigned and set over to the said surety company all the money due him or to become due him under said contract, and, further, that the surety company claimed that laborers and materialmen were *Page 595 undertaking to hold it liable for labor and material and were claiming that said balance due under the contract should be turned over to it by reason of such assignment. There was set forth a list of claims for material and labor furnished on account of said contract to the amount of more than seven thousand dollars. Other claims were set up in the bill which it is unnecessary to detail here.
The county further stated that it had no personal interest in the subject-matter of the controversy and was indifferent to the contention between the claimants, and paid the seven thousand seven hundred eighty-five dollars and eighteen cents balance due under said contract, into court, prayed process, prayed that the respective claims be adjudicated and that the rights of the several claimants be adjudicated by the court.
It appears that after the filing of the bill and other steps had been taken therein the case was removed to the Jackson division of the United States district court for the Southern district of Mississippi, and was by that court, on June 3, 1924, remanded to the chancery court of Yazoo county.
Briefly stated, the Canton Exchange Bank in its answer and cross-bill admitted that the several laborers and materialmen were claiming the money, but set up that it was entitled to the funds by virtue of an assignment to it made by J.R. Parker, the contractor; that said assignment of the amount due under the contract was made for advances to said Parker with which to construct the road; and that at the March meeting, 1922, notice of said assignment was served on the board of supervisors, accepted by them, spread upon their minutes, and recorded.
The assignment in form was an assignment of all the retainage on that date in the hands of Yazoo county or that "hereafter may accrue to me to be held by the board of supervisors of Yazoo county on my contract for roads, or part of the road from Moore's ferry towards Yazoo City of which I am contractor." And the *Page 596 assignment further directed the board of supervisors to pay all such funds to the assignee of the bank, and was dated February 18, 1922.
The bank claimed that there was due on account of said assignment of said retainage fund to the bank by Parker the sum of five thousand three hundred thirty-five dollars and sixty-nine cents, including attorney's fees, it being alleged that the notes for advances made to Parker by virtue of the assignment provided for ten per cent. attorney's fees, and that the notes had been placed with an attorney for collection. Copies of the notes were attached. The bank further alleged that it relied upon the law as announced by the court allowing contractors to assign the money to be earned under such contract, on the acceptance by the board of supervisors, in making these loans.
The respondent further denied that Parker made an assignment to the United States Fidelity Guaranty Company, denied that under the bond and contract of Parker the guaranty company as surety had any rights either by assignment or otherwise as against it which could be lawfully maintained as to the fund in controversy, but alleged that, in so far as the assignment in the application of Parker to the guaranty company is concerned, there was no notice to it of such assignment, and that same was not served on the board, or notice given the board, until the work of constructing the road was practically completed, and that the guaranty company had no claim on the fund which was superior to the claim of said bank, and that, as a matter of law and of equity, the bank would be entitled to preference as to said fund; and the cross-bill sought to enforce the assignment hitherto referred to, and prayed that a decree be entered awarding it priority of payment out of the retainage funds. The contract was made an exhibit to the answer and cross-bill, together with the copy of the assignment and copy of the notes. *Page 597
Parker, the contractor, filed a separate answer admitting substantially the facts set up in the answer and cross-bill, and prayed that the bank be awarded payment of its claim and that he was entitled to some additional sum. He made a copy of the bank's assignment an exhibit to his answer.
The United States Fidelity Guaranty Company filed its answer admitting the contract, admitted that Parker performed and completed the work under such contract, admitted that payments were made on monthly estimates to Parker, admitted that laborers and materialmen were claiming an interest in the fund, admitted that the Canton Exchange Bank was claiming the fund by virtue of the assignment heretofore mentioned, but denied that the bank had any assignment valid or binding in so far as it sought priority over the right and claim of the surety company, set up that the bond was executed by virtue of chapter 217 of the Laws of Mississippi of 1918, and was conditioned for the performance of said contract and payment of all persons furnishing said Parker with material or labor in the course of the performance of such work, as provided by said statute. A copy of the complete bond and complete contract was filed as exhibit to its answer.
The guaranty company further averred that the contract contemplated and required the retention of fifteen per cent. of the monthly estimates; that the said fifteen per cent., to which we shall refer hereafter as "retainage," was for its security and protection against default under said contract with reference to any of its principal duties and obligations thereunder.
The guaranty company averred that the amount paid in by the county with its bill of interpleader alleged to be due to Parker was a part of said final estimate and retainage, and alleged that there was some five thousand three hundred dollars due by the county on the estimate of engineers to Parker, that it was the duty of the county to retain fifteen per cent. of the amount due Parker, that *Page 598 the entire amount of the contract was one hundred thousand two hundred one dollars and twenty-seven cents, fifteen per cent. of which was fifteen thousand thirty dollars and nineteen cents, that a difference of more than seven thousand dollars was illegally paid to the Canton Exchange Bank by the county, and alleged that the county should be required to account to it for this difference.
The guaranty company further averred that it had paid various amounts to various and sundry subcontractors, materialmen, and laborers, and that it might be called upon to pay others, and that this retainage fund was for its protection against any unperformed part of said contract and bond, that all assignees of said Parker are charged with notice of its prior rights, and that the claim of the Canton Exchange Bank as assignee was subordinate to the claim, right, and title of the guaranty company.
It averred that Parker did not pay all persons having performed labor and furnished material in the construction of the road; set up a list of payments made by it, aggregating ten thousand seven hundred seventeen dollars and thirty cents, all of which sums it alleged were due for material furnished and labor performed before and at the time of the completion of the work by the principal, Parker; that it, the guaranty company, was liable for said sums under the statute and this bond, and that it had paid on account of said liability such claims, amounting in all to ten thousand seven hundred seventeen dollars and thirty cents and by such payment had made absolute its right to the fund paid in said court.
The proof in this case was confined to the exhibits and agreed statements of facts. To sum up and state the case succinctly: The county let a road contract to Parker. Parker executed a bond for the faithful performance of that contract in accordance with the plans and specifications, the plans and specifications being made a part of the bond and a part of the contract, and the bond being made a part of the contract; and the bond further stipulated *Page 599 under chapter 217, Laws of 1918, that the principal, Parker, would pay all the agents, servants, and employees and persons furnishing the principal, Parker, with material and labor in the course of the performance of said work, and carry out to the letter each and all of the stipulations and obligations of the contract. The fund involved here was embraced within the fifteen per cent. stipulated to be retained under the contract, called "retainage." The bank claimed the fund by virtue of its assignment from the date it served notice on the county, the debtor, and the guaranty company claimed the fund by virtue of its equitable subrogation to the rights of the county in the fifteen per cent., because it had paid the laborers and materialmen on its bond obligation dated September 6, 1921.
We think it unnecessary to set out the contract and bond in detail here, but will say that, except for names and amounts, this record is the same in its essential details as the record in the case of First National Bank v. Monroe County,
131 Miss. 828 , 95 So. 727, except that in the instant case the fund in controversy is the "retainage" fund, and in the Monroe county case the lawsuit arose between the assignee and the surety company as to the "progress" fund. It is conceded in this case that the bank made its advancements in aid of the construction of the road, and it is conceded that the guaranty company had paid claims of laborers and materialmen in excess of the amount of the fund (now agreed to be correct) paid into court by Yazoo county on its interpleader.The precise question presented to us for decision is whether or not under the facts stated above the bank is entitled to the funds by virtue of its assignment, notice of which was given the debtor, the county, in due time, or whether the guaranty company, having paid the laborers and materialmen, which its principal has failed to pay, is entitled by subrogation to the rights of the county to have this fund applied for its protection in the carrying out of the contract of its principal in the payment of *Page 600 laborers and materialmen incurred by Parker in the construction of the road.
In the case of First National Bank v. Monroe County, County,supra, this court set out excerpts from the contract and from the bond, and there decided in a similar contest as to which of the two, the assignee of the contractor or the surety of the contractor, was entitled to the balance of the "progress" fund then unpaid and due from the county. After a statement of the case and a review of the authorities this court reached the conclusion that, as to the "progress" fund, by virtue of a valid and binding assignment fully executed, the contractor's assignee was entitled to the "progress" fund unpaid and owing from the county as against the surety company. But in that case this court distinctly refrained from any decision as to which of the two would be entitled to the "retainage" fund, and the court, speaking through Judge COOK, said, "The retained percentages are not here involved, and as to that feature we express no opinion, but, as to the amount which the contract provided should be paid to the contractor monthly, we think the doctrine herein announced is in nearer accord with reason and sound policy," and then proceeds to hold that the assignee is entitled to the "progress" fund.
In addition to the specific provisions of the contract, section 363, Code of 1906 (Hemingway's Code, section 3736), among other things, provides:
"In all cases of public work let by the board of supervisors where the contract price exceeds five thousand dollars the board may contract so as to provide for making partial payment to the contractor therefor as the work progresses, but in no case shall such partial payments exceed eighty-five per cent. of the value of the work done and material used in the performance of the contracts," etc.
Section 361, Code of 1906 (Hemingway's Code, section 3734), provides how contracts for public work may be made, and applies to all contracts made by the board of *Page 601 supervisors in excess of fifty dollars not otherwise specifically provided, provides for a bond, and that the bond shall be conditioned for the prompt, proper, and efficient performance of the contract.
Chapter 217, Laws of 1918, is a provision that the bond shall provide for the prompt payment of all laborers and materialmen, and provides that the usual bond should be executed.
As we have before set out, the contract provided for progress payments, and provided further for the retention of the retainage fund in the following language:
"Maintenance. — The contractor will be required to maintain the road in first class condition for thirty days after it is completed, and fifteen (15) per cent. of the final estimate will be retained by the county or district to enforce this requirement, except that the state highway engineer may in his discretion release the contractor from the further maintenance of sections of the road, not less than two miles in length, which have been satisfactorily maintained under traffic for at least thirty days."
The chancellor in a written opinion awarded this retainage fund to the guaranty company, holding it entitled to same by virtue of its equity of subrogation, and the bank, the assignee, appeals here.
The appellant contends throughout the several briefs filed in this case that it is covered and controlled in its entire aspect by the case of First National Bank v. Monroe County mentioned in the statement of facts, and in addition it urges that the recitals of the proposals for the bond were, in effect, an attempt on the part of Parker to make a legal assignment of these funds to the guaranty company absolute in its nature, including not only these funds involved here but all the property and money used and acquired in and about the contract, and, having undertaken to take an assignment and thus acquire the title, that the guaranty company could not thereafter set up an equitable title derived by subrogation, the guaranty *Page 602 company never having served notice on the county or on the bank until long after the bank had served its notice and after the breach or failure to pay these laborers had occurred in Parker's "proposal for bond" mentioned above. After assigning all funds, progress and retainage, to the guaranty company as indemnity or protection, conditional and effective only on Parker's breach of the contract, there is this language:
"That the said company, as surety on said bond, as of this date, shall be subrogated to all of our rights, privileges, and properties as principal and otherwise in said contract, and said principal does hereby assign, transfer, and convey to said company all the deferred payments and retained percentages, and any and all moneys and properties that may be due and payable to said principal at the time of such breach or default, or that may thereafter become due and payable to said principal on account of said contract, or on account of extra work or materials supplied in connection therewith, hereby agreeing that all such moneys and the proceeds of such payments and properties shall be the sole property of the said company, and to be by it credited upon any loss, damage, charge, and expense sustained or incurred by it as above set forth under its bond of suretyship."
It is well settled in this state that in a contest between several parties claiming legal title to the fund assigned, that he who first brings same to the notice of the debtor of the assignee has priority. Mathews v. Hamblin,
28 Miss. 611 ;Lumber Co. v. Newcomb,79 Miss. 462 , 30 So. 608; FirstNational Bank v. Monroe County,131 Miss. 828 , 95 So. 727. So that as between the two assignments on this legal phase the bank's rights were not affected by the effort to assign this fund in the proposal made by Parker to the guaranty company for his bond. We might say in passing that the guaranty company made no effort to interfere with Parker in his handling of the progress money in this case. *Page 603Counsel for appellant argue strenuously that the guaranty company by its service of notice on the county of its "proposal for bond" rendered such assignment subordinate to the bank's assignment. We think it is clear that it only presented the paper as additional evidence that the contractor conceded the right of the guaranty company to be subrogated to the county's rights in this contract and in this "retainage" fund, and we do not think there is any merit in that contention, for in Parker's written "proposal for bond," and in the notice of the guaranty company to the supervisors, there was distinct recognition of this claim of the guaranty company to an equity of subrogation in and to this "retainage" fund.
However, the serious question raised in this case is, whether or not under the language of the contract, and the provisions of chapter 217, Laws of 1918, and under sections 361 and 363, Code of 1906 (Hemingway's Code, sections 3734, 3736), the county has any right in this retained fund when the work has been completed in every detail according to the plans and specifications and contract, and retained for thirty days for the proper maintenance of the completed road. To put it in simpler form, when every detail of the work has been completed and there remains all or a part of the fifteen per cent. "retainage" fund in the hands of the county, can the county legally pay this fund or any part of it to any one save the contractor or to his order, even though the contractor may still owe for material used and labor performed in the construction of the roads?
If, as stated by counsel for appellant, the case of FirstNational Bank v. Monroe County, supra, is controlling and decisive here, then, of course, we have but to cite that case, or that part of the decision which is controlling, and rest content. But a critical examination of the case discloses that no effort was made in the statement of the case, in the reasoning of the case, in the authorities cited, or in the conclusion reached, to settle the question of *Page 604 whether or not there is an equity of subrogation in the surety whose principal had failed to pay the laborers and materialmen, so that, in our opinion, the court expressly pretermitted expressing any opinion on this question as to the retainage fund, and only held that there was no equity of subrogation to the surety on the bond in the progress fund as against the assignee of the contractor. No other thing is adverted to or decided. Nor is the case considered with reference to the question now under consideration.
It must be borne in mind that Laws of 1918, chapter 217, is not the only statute controlling this contract — a road contract with more than five thousand dollars involved. Section 63, Code of 1906 (Hemingway's Code, section 3736), permits "progress" payments, but requires a retainage fund of fifteen per cent., as follows:
"In all cases of public work let by the board of supervisors where the contract price exceeds five thousand dollars the board may contract so as to provide for making partial payments to the contractor therefor as the work progresses, but in no case shall such partial payments exceed eighty-five per cent. of the value of the work done and material used in the performance of the contracts, to be estimated by some competent person employed by the board to superintend such work, and not until the superintendent shall furnish to the board such estimate, in writing, on his oath (as to the correctness of such estimate), which estimate, with the oath annexed thereto, shall be filed with and recorded in the minutes of the board," etc.
It is elementary that the assignee obtains no greater right in the thing assigned than was possessed by the assignor, and the disposition of the retainage fund in this case must be determined by the relative rights of the parties to this litigation, considering the legal as well as the equitable rights.
If the guaranty company acquired any right to this fund it must be under the doctrine of the well-established *Page 605 rule governing equitable subrogation, which originated, if at all, on the day of the execution of the bond of the contractor by the guaranty company.
It must be remembered that it has been the law of this state since the enactment of chapter 141, Laws of 1904, that the board of supervisors was to make contracts providing for partial payments to the contractor as the work progressed, not to exceed eighty-five per cent. of the work at actual value. Then this chapter 141 became section 363, Code of 1906 (Hemingway's Code, section 3736), clearly showing that there was a purpose to retain fifteen per cent. for the protection of the county in securing the completion of the contract according to its terms.
When we consider the requirements as to bond and as to what the bond guaranteed in the statutes embraced in the chapter on boards of supervisors of the Code of 1906, hitherto cited, and which the Laws of 1918, chapter 217, can in no sense be urged to have repealed, but only enacted further obligations in the bond, the contract was not complied with until all the obligations of the contract and bond were complied with. The requirements of chapter 217, Laws of 1918, are a part of the bond, which is a part of the contract, and postpones the due date of the retainage fund until the road work shall have been open for inspection for thirty days longer than would have been required by section 363 of the Code of 1906.
In the court below the chancellor in his written opinion based his decision for the guaranty company squarely on the old, well-recognized doctrine of equitable subrogation, holding in effect that, where the contract and bond were entered into in this case, the right of equitable subrogation in the retained percentage involved here was vested in the guaranty company and dated back to the date of the bond and contract, and that the retained percentage was for the benefit of the surety as well as of the county. *Page 606
We have already noticed that counsel for appellant contend that the case of First National Bank v. Monroe County settles this case, and have answered that in our opinion the question of retained percentages was entirely eliminated from that decision. Nor can it be argued that by analogy the same rule applied to the "progress" money to which the contractor, the principal, has the right, is analogous to and is controlled by the same principle as the retained percentages to which the contractor by law and by contract has not a right until the entire contract in every detail is completed in accordance with its terms and the law.
Counsel cite the case of Peck-Hammond Co. v. Williams,
77 Miss. 824 , 27 So. 995, as authority for the proposition that the bank, the assignee, is entitled to the money, the retained percentage, in this case as against the surety on his contractor's bond. There are only about eleven lines in that opinion, and an examination of the statement of facts and the briefs of counsel show that the contest as viewed by the court was one between a preferred creditor (by assignment of the fund) and a general or nonpreferred creditor, and the question of equitable subrogation did not and could not have entered into that decision, nor were involved the surety's rights as against the assignee.In National Surety Co. v. Hall-Miller Decorating Co.,
104 Miss. 626 , 61 So. 700, 46 L.R.A. (N.S.) 325, also cited by appellant, Judge COOK delivered the opinion of the court, and simply held that the provision requiring the contractor to pay all material and labor claims was not unreasonable or improper, was plain and unambiguous, and that the provision did not render the bond or contract ultra vires.Counsel for the appellant further rely upon the case ofHipwell v. National Surety Co., 130 Iowa, 656, 105 N.W. 318, which case sustains the theory of the appellant that the assignee here, the bank, would be entitled to collect the retained percentage fund to the exclusion of *Page 607 the guaranty company on the bond, and is the strongest case for that view to which we have had access. But the case recognizes the fact that the retained percentage was for the benefit of the surety as well as the building committee, and seems to decide the case on the theory that the contractor, the principal in the bond, might assign the fund so as to deprive the surety of his right of equitable subrogation because nothing would remain. A statement of the position assumed by the court displays the weakness of the position just assumed, because we do not think there is any break in the authorities that the subrogation begins at the time the surety assumes the obligation under which the thing subrogated is deposited as security or arises.
In an early report of this court the doctrine of equitable subrogation was not only recognized but commended by the High Court of Errors and Appeals.
In Gowing v. Bland's Administrators and Heirs, 2 How. (Miss.) 813, Mr. Justice PRAY, as the organ of the court, said:
"Having thus ascertained the rights of executor or administrator when discharging the debts of his testator or intestate, we will inquire what are the rights of one who pays those debts as the surety of the executor or administrator? In [Enders v. Brune], 4 Randolph (Va.) 444, we find the question thus emphatically decided: ``The surety is entitled to every remedy, which the creditor has against the principal debtor, to enforce every security; in short, to stand completely in the place of the creditor.'
"If the authorities here cited are to be relied on, and their character is too elevated to be questioned, they dispose of the whole case. . . . .
"The doctrine of substitution is not regarded in equity, as founded on contract, but as the offspring of natural justice, and courts should rather incline to extend than restrict the operation of a principle so elevated and pure." *Page 608
This principle is reinforced in the cases of Conway v.Strong,
24 Miss. 665 ; Bowen v. Hoskins,45 Miss. 183 , 7 Am. Rep. 728; Osborn v. Noble,46 Miss. 449 .The supreme court of the United States, as well as the circuit courts of appeals, has frequently applied the the doctrine of equitable subrogation to the state of facts which we have before us, as have the courts of last resort of Arkansas, Maryland, Montana, Minnesota, Nebraska, North Carolina, North Dakota, Oregon, Pennsylvania, Texas, and Ohio.
In the case of Prairie State National Bank of Chicago v.United States,
164 U.S. 227 , 17 S. Ct. 142, 41 L. Ed. 412, Sundberg had entered into a contract to erect a public building at Galveston, Tex. Hitchcock was the surety on his bond. The president of the bank furnished the contractor with funds which it was understood and asserted were used by the contractor in doing the work. The contractor drew an order in favor of the bank for the amount reserved, wherein M. Justice WHITE said:"Under the principles thus governing subrogation, it is clear whilst Hitchcock was entitled to subrogation, the bank was not. The former in making his payments discharged an obligation due by Sundberg for the performance of which he, Hitchcock, was bound under the obligation of his suretyship. The bank, on the contrary, was a mere volunteer, who lent money to Sundberg on the faith of a presumed agreement and of supposed rights acquired thereunder. The sole question, therefore, is whether the equitable lien, which the bank claims it has, without reference to the question of its subrogation, is paramount to the right of subrogation which unquestionably exists in favor of Hitchcock. In other words, the rights of the parties depend upon whether Hitchcock's subrogation must be considered as arising from and relating back to the date of the original contract, or as taking its origin solely from the date of the advance by him."
The opinion, after quoting numerous authorities and analyzing the English cases, concludes with this statement (17 S.Ct. at page 147 [
164 U.S. 239 ]): *Page 609"Applying the principles, which are so clearly settled by the foregoing authorities, to the case at bar, it is manifest that if the transaction in February, 1890, by which the Prairie Bank acquired its alleged lien on the fund possessed the effect contended for by the bank, it would necessarily operate to alterand impair rights acquired by the surety under the originalcontract. (Italics ours.)
"Sundberg Company could not transfer to the bank any greater rights in the fund than they themselves possessed. Their rights were subordinate to those of the United States and the sureties. Depending, therefore, solely upon rights claimed to have been derived in February, 1890, by express contract with Sundberg Company, it necessarily results that the equity, if any, acquired by the Prairie Bank in the ten per cent. fund then in existence and thereafter to arise was subordinate to the equity which had, in May, 1888, arisen in favor of the surety Hitchcock."
It will be noted that Chief Justice WHITE was of the opinion that the right of the surety to subrogation related back to the date of the original contract, and of course a party could not partake of the fruits of a contract without being held to have notice of the claim of the surety company to its equity of subrogation in this retained percentage fund arising from the identical contract. We think the reasoning is sound, and we are persuaded to follow it in this case.
In the case of Title Guaranty Surety Co. v. First NationalBank,
94 Wash. 55 , 162 P. 23, the court sustains the surety's equity of subrogation in the fifteen per cent. retained as against a bank which had taken an assignment of the particular fund. True it is that in this case the actual labor and work of the contract had not been fully performed, but the surety's right was based upon the equity of subrogation, and, as said by Chief Justice WHITE, relates back to the date of the original contract, "which could not be impaired or altered by a subsequent assignment by the contractor." *Page 610The same court in the case of Northwestern National Bank v.Guardian Casualty Guaranty Co.,
93 Wash. 635 , 161 P. 473, Ann. Cas. 1918D, 644, held that where there was no specific percentage fund retained the assignment of the bank was superior to the claim of the subrogation by the surety on the contractor's bond. But the same court in the case of Maryland Casualty Co. v. Washington National Bank,92 Wash. 497 , 159 P. 689, said:"In the Liebes case [State ex rel. Bartelt v. Liebes,
19 Wash. 589 , 54 P. 26], and in First Nat. Bank v. Seattle,71 Wash. 122 , 127 P. 837, we announced a trust to creditors in a contractor's reserved balance. Here, holding the surety liable for the contractor's debts by a contract supplementing statutory obligations, we have a surety's right of subrogation to that balance should he be compelled to pay the principal's creditors, and of his right to prevent the dissipation of the fund. In this portion justice must rigorously protect the surety. His expectation when he goes on the bond is plain; the principal may squander eighty per cent., leaving the surety at the mercy of the creditors, but there is at least twenty that will be applied to the creditors in spite of him. This amount, originally reserved to protect merely the creditors, is a collateral security of the principal available to the paying surety."Chief Justice MARSHALL, speaking for the Ohio court, on March 16, 1926, in the case of State v. Schlesinger,
151 N.E. 177 , at page 179, reviews the authorities pro and con, and clearly, cogently, and convincingly, establishes that the surety is subrogated to the rights of the state and takes priority over the assignee of the contractor, saying:"All the foregoing cases quite clearly and uniformly support the claims of the surety in the instant case. As against this long line of authorities we are cited by counsel for the bank to the case of Puget Sound State Bank v. Gallucci,
82 Wash. 445 , 144 P. 698, Ann. Cas. 1916A, 767, *Page 611 but a careful examination of that case discloses that it was decided upon the peculiar language of the statute governing such matters in force at that time in the state of Washington. By virtue of that statute, and more especially by virtue of the contract made pursuant to that statute, the surety became obligated, not only to pay the claims of laborers and materialmen, but to pay ``all just debts, dues, and demands incurred in the performance of said work.' Whatever force that case might have had as an authority in the instant case, much of that force was destroyed by the facts that at a subsequent date the legislature of the state of Washington amended the law, leaving out the words above quoted, thereby indicating that it was not the intention of the legislature, in the declaration of a sound public policy for that state, to destroy the rights of sureties to subrogation upon public contracts in that state."And he further said:
"It is urged on behalf of the bank that by reason of its assignment of the contract it becomes entitled to all the security of the contract. Even if this should be admitted, it adds no strength to the position of the bank. Conceding that the bank by the assignment had transferred to it all the value of the contract, it turns out in this particular case that the contract had no value. Whether or not a contract has value depends upon whether the contractor made a good bid. If the contract can be executed at a profit, it has value. If it is executed at a loss, it becomes a liability. And this is perhaps the best answer to the contentions of the bank — that it had transferred to it what turned out to be a liability instead of an asset.
"It may clearly be deduced from all the foregoing authorities, and it must further be resolved upon principle, that the right of subrogation in the surety operates as an equitable assignment, and that, inasmuch as the surety is a party to the original contract, such equitable assignment takes priority over any assignment, legal or equitable, which may be given by the contractor to any third *Page 612 party who enters the transaction after its inception.
"It has further been urged on behalf of the bank that it is entitled to be subrogated, and therefore entitled to claim an equitable assignment of the claims of laborers and materialmen who were paid by the funds loaned by the bank to the contractor. This question was fully met in the case of Illinois Surety Co. v. City of Galion (D.C.), 211 F. 161, where the court determined to the contrary. Laborers and materialmen who were paid by the money loaned by the bank to the contractor had no liens and the bank cannot therefore be said to have acquired existing and vested liens. We therefore hold upon principle, as well as authority, that the surety company must prevail."
We think in this case that Parker, the contractor herein, could not have required the county to pay him the reserved percentage until he had discharged his obligation to the county and complied with his contract, which he failed to do in the payment of materialmen and laborers, and which his surety carried out for him after his default. In this state of case the assignee, the bank, could not acquire any right higher or superior to the claim of the assignor, Parker, and neither of them could have enforced payment of this retained percentage until the contract had been complied with. The bank in the payment of its money was a mere volunteer in paying material and labor claims, while the surety company at the inception of the contract, had the retained percentages as a part of the contract to which it could look — as that part which could not be wasted or dissipated by the contractor — and so likewise the bank in law was advised that the surety company was entitled to be equitably subrogated to the rights of the county and to the rights of the contractor, and, as we conceive this case, no amount became due to Parker unless and until his contract with the county had in all respects been fully complied with in all of its details for which he and his surety were bound. *Page 613
Counsel argue that the authorities quoted above all apply to cases where the courts decline to recognize the assignment by the creditor of a particular fund. The answer is this — that the same rule announced herein is followed and approved in the case ofMass. Bonding Co. v. Ripley County Bank, 208 Mo. App. 560,
237 S.W. 182 ; and the courts of Missouri determine priority of assignments just as they are determined by us in this state.We think the guaranty company, having paid out more than the amount of the percentage retained by Yazoo county in this case, is entitled, under the doctrine of equitable subrogation applied to its bond contract at its inception, to collect this retained percentage fund in a contest with the bank which voluntarily paid out its money to laborers and materialmen and claims by virtue of an assignment of the percentage fund retained, duly served on the county in ample time in manner and form required under our decisions, to complete an assignment of the funds. The court below so held.
We want it understood that the conclusion here announced applies only to the "retainage" fund, and we adhere to the rule announced in the case of First National Bank v. Monroe County,supra, as to the progress fund there involved, which has no application to the "retainage" fund or retained percentage.
Affirmed. *Page 614
Document Info
Docket Number: No. 25395.
Citation Numbers: 109 So. 1, 144 Miss. 579, 1926 Miss. LEXIS 337
Judges: McGowen
Filed Date: 6/15/1926
Precedential Status: Precedential
Modified Date: 11/10/2024