Spencer v. Quincy, Omaha & Kansas City Railroad , 317 Mo. 492 ( 1927 )


Menu:
  • Action under the Federal Employer's Liability Act for personal injuries alleged to have been caused by defendant's negligence. The injuries complained of were received on August 10, 1923, near Reger, Sullivan County, Missouri, while plaintiff, pursuant to his employment by defendant, was working as a bridge carpenter. For a statement of the facts which disclose the circumstances under which, and the manner in which, the injuries were received we adopt that of appellant (defendant) in part, as follows:

    "Plaintiff was one of a gang of about seven men, working under foreman Cowan, who had reconstructed a wooden pile trestle in defendant's track where it crossed a small stream. They had been at work on the job two or three weeks. The new bridge had been practically completed, and during the work the old timbers had been torn loose and allowed to fall under the bridge, and the old piling had been cut off or sawed off at or about the ground level, and allowed to fall where they would, and the work undertaken on the day of the accident, and a short time before the accident, was the removal of said old piling and timbers from under the bridge to a point at right angles to the track and about fifty feet therefrom, where they were being piled in such way that they could be lifted up and loaded by a derrick on cars standing on or near the bridge, on some other day, by a different crew. To facilitate said loading of the timbers, they were being piled crosswise on ``ways' timbers four inches thick by ten inches wide, which had been used as sway braces in the old bridge, having been *Page 498 selected as the most available timbers for ``ways,' and two of said timbers were used as ``ways' for each pile of piling, said timbers having been laid broadside down on the ground. Immediately previous to the commencement of the pile on which plaintiff was injured, plaintiff, with three helpers, had made a pile of piling on similar skids on the south side of the creek, about the same distance east of the track, and upon completion thereof, they were directed by the foreman to make a similar pile of piling on similar ``ways' on the north side of the creek. The particular timber used for a ``way' and by which plaintiff was later injured, was put in place by plaintiff and after being first so placed by plaintiff, the foreman instructed him to block up one end, and he did so. Plaintiff with another bridge carpenter working opposite him, and two other helpers, started in to make said pile of piling on the north side of the creek, and brought one pile from under the bridge and placed it on the ``ways' and had brought another pile up to and were in the act of placing it upon the ``ways' when the injury to plaintiff occurred. For the handling of the pile, the men were provided with a tool known as a ``lug hook,' and had two of them, two men being assigned to each lug hook. The lug hook consists of a stout wooden handle or shaft, about five feet long, with a grab hook attached in the middle, constructed of iron, to operate on the same principle as the ordinary ice tongs, so that when the horizontal points of the tongs were inserted into the wood of the piles, and force was applied to the handle of the lug hook by lifting up on it, the weight of the pile would keep the points of the hook engaged and tend to drive them deeper into the wood. In the use of the hooks, one man would be at each end of the handle, thereby placing one man on each side of the pile, and they were moving the piles from under the bridge to the ``ways' by a method known as ``lancing.' The four men, with their two lug hooks, had attached the lug hooks near the heavy or butt end of the pile. The two helpers (bridge gang laborers) were handling the lug hook that was attached nearest the east or forward end of the pile, and plaintiff and the other bridge carpenter were handling the second lug hook, which they had affixed to the pile at such distance behind the forward lug as they deemed proper. The method of handling the pile consisted in all four of the men lifting on the two lug hooks at the same time, and swinging the piling as far eastward or forward as they could, while retaining hold of the lug hooks, their feet remaining in the position occupied when the pile was thus lifted. The men would then change the position of their feet forward without releasing the hold of the lug hooks, and lift up and swing forward again. By this method, the movement of the pile in question had proceeded to the point where the *Page 499 easterly or forward end had been moved far enough east to rest on the westerly ``way,' and all four of the men were between the two ``ways' when they made the movement of the pile by which plaintiff was injured. Plaintiff was standing just inside of and near the westerly ``way,' and on the north side of the piling, facing the other bridge carpenter who was opposite him on the south side. They all lifted at the customary signal, and shoved or threw the pile forward, when the pile caught upon the westerly ``way,' and carried the ``way' with it far enough east to strike plaintiff's right leg, thereby injuring it."

    The ravine crossed by the bridge trestle was about 32 feet in width at the bottom. Along this bottom and following its meanderings a narrow water channel threaded its way. Between it and the sloping ground on the north side there was a level strip varying in width from six to eight feet. It was along this narrow way that the piling had to be "lanced" from under the bridge a distance of about fifty feet to where they were being piled on the cross timbers. The ground was wet and muddy, covered with small rocks, blocks and other debris from the recent bridge construction. The piles to be moved were round timbers, varying in length from 12 to 26 feet and weighing from 500 to 1,000 pounds. The one being "lanced" at the time plaintiff was hurt was between 15 and 16 feet in length, weighing from 500 to 600 pounds, and was wet and slick and mud covered in part. The lower or butt end was rotten to a considerable depth from the surface. A portion of this decayed surface fell off while it was being "lanced," exposing a protruding knot. When the piling was swung forward in the act of "lancing" it, the rough surface (caused by the falling off of the decayed part or the protrusion of the knot) engaged the "way" or cross timber and jerked it with great violence against plaintiff's right leg just above the ankle. The nature and extent of the injuries thereby inflicted will be described later on.

    Plaintiff called as witnesses five men who had had many years' experience in building and re-building railroad trestle bridges, including the removal of old piling under circumstances more or less similar to those involved in this case. Some of them had done such work for only one railroad; others had at different times been employed in the bridge department of several railroads. A considerable period of time had elapsed since any of them were so engaged. In answer to a hypothetical question which accurately set forth the surrounding conditions as shown by the evidence, each gave it as his opinion that the "lancing" method of removing piling under those conditions was not a reasonably safe one. For example, Winter said: *Page 500

    "Because those lug hooks are not a safe piece of machinery to grab pile with. I noticed here yesterday in the court room, probably you observed it, where those men picked up that pile, and this lug hook broke its hold, and they will absolutely do it every time you grab into a round pile with them; if you have a timber, a square timber, they will hold reasonably well then, but they are not safe then. They will pull out, and probably the next man behind you, well, he will grab the whole load, and that will break him down; the man ahead of him has to hold it or they will roll on your legs and cripple you, flop around like a chicken with its head cut off. That is my theory, that is the reason why I say that they won't do it."

    And Ford said:

    "In case they let loose it might slide over and catch their feet. And then in piling, putting those pieces down there, and taking and dragging these big timbers over there, of course you are liable to pull them onto you at any time, unless they are fastened."

    In connection with their reasons for saying that the "lancing" method was not a safe one, these witnesses described other methods which they regarded as safe. One method was to drag the piling with a team of horses; others involved the use of a mechanical appliance, such as the derrick. These methods they said were not only safe, but more expeditious and economical than that of "lancing."

    Plaintiff, after serving an apprenticeship of three months, was promoted by the defendant to the position of bridge carpenter. He was what is called a "top man," and had worked as such for three years prior to his injury. With respect to his knowledge of the danger of moving piling by "lancing" them, he testified:

    "Why, I had never moved any pile of that length. I didn't know but what it was all right to move them in that way. I didn't see no danger in it, didn't see anything wrong with it, and I didn't have any more knowledge of it than that. I trusted to the foreman's judgment, as he had worked at the work many years, and I would rather trust his judgment than trust my own, because there is lots of work I had never worked at yet."

    The only evidence offered by defendant was with reference to the nature and extent of plaintiff's injury.

    The petition is long and somewhat argumentative, but the negligence which it charges repetitiously and in varying phraseology seems to be epitomized in the following excerpt:

    "Defendant then and there and thereby, negligently, failed to furnish and provide a reasonably safe method of moving said pile; and, the defendant, then and there and thereby, negligently failed to furnish a reasonably sufficient number of men and a reasonably *Page 501 sufficient force for moving said pile, by the method then used; and, defendant, then and there and thereby, negligently failed to furnish and provide reasonably necessary, and a reasonably sufficient number of lug hooks, tools, machinery and appliances for moving said pile; and, the defendant then and there and thereby, negligently required the plaintiff to pull, lift and work on said pile at, and in a place which was not reasonably safe."

    The answer was a general denial and a plea of assumption of risk.

    Plaintiff sued for $60,000. The jury awarded him $41,375. Such is the size of the judgment appealed from.

    Appellant assigns as error: (1) the refusal of its instruction in the nature of a demurrer to the evidence; (2) the admission over its objection of certain testimony offered by plaintiff; and (3) the giving of certain instructions asked by plaintiff. It further presses as a ground for reversal the excessiveness of the verdict.

    I. Appellant advances a number of reasons why its demurrer to the evidence should have been sustained.

    1. It says in the first place that liability can not be predicated of its use of the "lancing" method of moving piling, because it had the undoubted right to select its own method of doing the work. Its right in that respect, however, was a qualified one, that is, from the standpoint ofRight to incurring liability; it was bound to exercise the rightSelect within the limits of ordinary care. [Kuhn v. Lusk, 281Method. Mo. 324, 338.] If the method employed was not a reasonably safe one and other methods just as practicable and equally available were, as the evidence tended to show, then it was clearly negligent in adopting it.

    2. Appellant next insists that, even though it was guilty of negligence in respect to the method used, such negligence was not the proximate cause of plaintiff's injury; that on the contrary the injury resulted from "the careless way in which the method was applied to a particular pile at a particular stageProximate of the operation." But the contact of the pile withCause. the cross timber over which it was being "lanced" and the consequences which followed, whether an accident or the result of inattention on the part of those engaged in the operation, may be regarded as merely an incident of the method employed and one which could reasonably have been anticipated. Whether the method itself was the efficient and proximate cause of the injury was for the jury to determine.

    3. It is finally contended under this head that plaintiff assumed the risk incident to the "lancing" method of moving piles. Whether he knew of the dangers attendant uponAssumed that method of work, or whether they were so plainlyRisk. observable that as a man of ordinary intelligence he must be presumed to have known them, was on the evidence a question for the jury. *Page 502

    II. The assignment under this head is: "The court erred in permitting plaintiff's witnesses to testify to other methods in use on other railroads for doing the same kind of work, because said evidence was irrelevant, and did not tend to prove any issue in the case." There does not seem to be any basis inIrrelevant the record for it, however. Plaintiff's experts inEvidence. detailing their testimonial qualifications told what railroads they had worked for, how long and when. In doing so they occasionally referred to the method of work used by them when in the service of such roads, but so far as we have been able to find this portion of their testimony was invariably stricken out when objected to by defendant.

    III. 1. Plaintiff's main instruction is alleged to have been in conflict with one given for defendant. Plaintiff's instruction authorized a verdict in his favor, if, among other things, "the jury believe [ed] from the evidence that said four men and two lug hooks were not a reasonably sufficient forceInstructions: to do said work by man-power alone; and, if theyConflicting. believe [ed] from the evidence that said method of doing said work was not a reasonably safe method, under the facts and in the circumstances mentioned in evidence." Defendant's instruction told the jury that there was no evidence that it was guilty of negligence "in not furnishing more men to handle the pile." With these two instructions before them, it must be assumed that the jury found merely that the method of doing the work was not a reasonably safe one. There are other criticisms of plaintiff's instruction but they are without substance.

    2. Plaintiff offered and the court gave two instructions "on the issue of contributory negligence." There was no such issue. What plaintiff's purpose was in setting up a "straw man" to knock down is not discernible. We have read the recordContributory carefully, including the opening statement and theEvidence. closing argument of his counsel, and do not find that plaintiff's freedom from negligence was anywhere featured in the case. The instruction was merely useless luggage. Defendant does not seem to have been prejudiced thereby.

    3. Complaint is made of an accident instruction given at the request of plaintiff which told the jury that if plaintiff was injured by reason of negligence of the defendant, as defined in other instructions, then the injury was not in law theAccident. result of an accident, even though some accident may have occurred at or about the time of the injury. What is said with respect to "accident" in paragraph 2, I, suggests a sufficient reason for the propriety of giving the instruction. *Page 503

    4. At the request of plaintiff the following instruction was given:

    "An expert witness is one who is skilled in any particular art, trade or profession, being possessed of peculiar knowledge concerning the same, acquired by study, observation and practice. Expert testimony is the opinion of such witness, based upon the facts in the case as shown by the evidence, but it doesExpert not even tend to prove any fact upon which it is based,Opinion. and before you can give any weight whatever to the opinion of expert witnesses you must first find from the evidence that the facts upon which it is based are true. The jury is not bound by expert testimony, but it may be considered by you in connection with the other evidence in the case."

    This instruction was taken bodily from Smith v. Telephone Co.,113 Mo. App. 443, where it had the unqualified approval of the Kansas City Court of Appeals. Nevertheless, it was erroneous, at least as applicable to the evidence in this case. There were some five or six medical experts who testified with respect to plaintiff's injuries — torn or strained ligaments and fractured bones at or just above the ankle joint. They had made physical examinations and they had "read" X-ray pictures, and from both had diagnosed the conditions of the injured parts. Their testimony consisted of a mixture of the facts they had observed and the inferences they had drawn from those facts. Neither a skilled lawyer nor a trained psychologist, much less a jury of laymen, could have separated with any sort of precision the fact-testimony of these experts from their opinion-testimony. The first part of the instruction could very properly have been given if the experts' opinions had been based solely on hypothetical facts; but the propriety of giving in any case the direction embodied in the last sentence is extremely doubtful. The opinion of an expert when admissible at all, is evidence; sometimes it is the only evidence by which proof can be made (O'Leary v. Scullin Steel Co., 303 Mo. 363); and its value as evidence is always for the jury. [Thompson v. Ish, 99 Mo. 160.] Besides, what reason can there be for singling out the testimony of experts for comment and caution when their testimony must be considered and weighed just like the testimony of other witnesses? [Morrow v. Gas Electric Service Co., 286 S.W. 106, 116.]

    But all the foregoing is merely by the way. A similar instruction was given at the request of the defendant. The error being common to both parties, the defendant is not in a position to complain of it. *Page 504

    IV. Appellant's final complaint is with reference to the excessiveness of the verdict; that appears to be its real grievance. The facts having an immediate bearing onExcessive that question, as disclosed by plaintiff's evidence,Verdict. are briefly these:

    Plaintiff at the time he received his hurt was thirty-two years of age, normal in every respect and enjoying perfect health. He was, as heretofore stated, a railroad bridge carpenter and as such he was earning $4.25 per day. At the time of the trial, eight months after the injury to his right leg, he was still using a cane or crutch to aid him in walking. When he would put his foot down level and bear any weight on it, the ankle would turn out. He said: "I can't hold the ankle, support the ankle. . . . It will turn to a certain extent just stepping right on the level all the time, if I don't walk . . . on the outside of my foot. . . . I experience pain in the knee, and in stepping on the foot, and when the ankle turns." To avoid the turning of the ankle and the consequent pain he found it necessary to turn the foot in and bear his weight on the outside of it when walking. The X-ray plates to which the ankle joint had been exposed showed that there had been an oblique fracture of the fibula an inch or more above the lower end, and also that a piece of the lower end of the tibia (the internal malleolus) had been broken off. But there had been a perfect union of the parts. The joint was not normal, however, according to plaintiff's experts. In this: where the lower ends of the tibia and fibula come together they form a concave surface which fits over the top bone of the foot (the astragalus) like a saddle; the ligament which holds the two leg bones together at the ankle, in plaintiff's leg, had been torn or loosened, so that it permitted the bones to spread apart, with the result that the "saddle" turned whenever any weight was put upon it. The X-ray further showed some irritation where the upper end of the fibula joined the tibia, which was attributed by one of plaintiff's expert witnesses "to the greater movement imparted at the joint by the loose condition of the bones at the ankle." The condition of the ankle joint just described was said to be chronic and permanent.

    Plaintiff's weight at the time he received the injury was 139 pounds; at the time of the trial it was 126. He did not sleep well at night owing to the continued recurrence of pain in his ankle and the mental worry growing out of the fact that he would in all probability be a cripple during the remainder of his life.

    With respect to plaintiff's future loss of earnings, one of his doctors said: "I think it incapacitates him severely." Another said: "Well, it affects it [the leg] a great deal to labor, he can't walk good on account of that joint being weakened by the spreading *Page 505 of the joint." And a third said: "Well, in my opinion a man couldn't do much work or lifting, or anything when he had to put much weight on his foot." This was all the evidence on that subject.

    Without any intention of minimizing plaintiff's injury, an assessment of his damages at the sum of $41,375 is most extraordinary to say the least. There was no suggestion at the trial that the pain and inconvenience might to some extent be overcome by the use of an artifical brace or support. But in any event a leg with a weak or impaired ankle is better than no leg at all. If our former rulings are to count for anything, $10,000 is the maximum recovery which can be permitted in this case.

    The judgment of the circuit court is affirmed, if the plaintiff will within ten days enter a remittitur in the sum of $31,375 as of the date of the original judgment; otherwise, the judgment will be reversed and the cause remanded. All concur.