BROWN, J. There is but little, if any, controversy concerning the facts in this case. That the labor was performed and the material furnished as alleged by Kelly and the lumber company is clearly .apparent. The character of the written contract that placed defendant Tourist Service Corporation in possession and occupancy of the 37 acres of land enwrapped in this cause is evident. That the construction of a tourist auto camp was contemplated by the vendee of the land was known to the vendor when he executed the sales and purchase agreement. The work of construction was commenced with the vendor’s knowledge and consent, and he required that any building constructed on the lands be insured in his favor and remain upon the land until the purchase price of the real property should be fully paid. In the improvement of the premises for use as an
*360 auto park, old buildings were tom down and removed therefrom, brush was cleared from the land preparatory to building, and much excavation for necessary structures for the auto camp was begun and completed in March, 1925, all of which was known to Manary. The reasonable value of the excavation alone was more than nine hundred dollars. In April, 1925, Kelly'went upon the premises for the purpose of mapping out the ground for his work, and on May 5th he commenced the execution of his plumbing contract. Some time in March, 1925, Manary was advised of the financial irresponsibility of the Tourist Service Corporation, and on May 6th, weeks after the commencement of the construction work, he undertook to protect his interest in the real property against all claims for improvement liens, by posting three notices in conspicuous places on the land, warning all persons that he would not be responsible for material furnished or labor performed in the improvement of his 37 acres. The Tourist Service Corporation having failed to pay for the excavation completed in March, Parker-Schram had, on April 22, 1925, filed a lien on the land on account of labor. We have already stated that this claim has been fully settled.This case involves an exposition of the Mechanic’s Lien Law of this state, reading:
“Every * * lumber merchant, laborer, * * and other persons performing labor upon or furnishing material, * * to be used in the construction * * of any building # * shall have a lien upon the same for the work or labor done or * * material furnished at the instance of the owner of the building or other improvement, or his agent; and every contractor, subcontractor, architect, builder, or other person having charge of, the construction * * of any building * *
*361 shall be held to be the agent of the owner for the purpose of this act; provided, that every person * * or corporation furnishing material * * to be used in the construction * * of any building * * shall, not later than five days after the date of the first delivery, to any contractor or agent, of such material or supplies for which a lien may be claimed, deliver or mail to the owner * * of the property * * upon * * which said material or supplies are to be used, a notice in writing stating in substance and effect that such person * * has commenced to deliver material * * for use thereon, with the name of the contractor or agent or other person ordering the same, and that a lien may be claimed for all material * * furnished by such person * * for use thereon * * . No materialmen’s lien for material * * furnished to the contractor or the agent of any owner * * shall be enforced unless the above provisions of this act have been complied with.” Or. L., § 10191.The foregoing section of our Code, when complied with, creates a lien for material or labor upon the building or structure. Section 10192 extends the lien on the structure to the land upon which it rests, together with a convenient space about the same, or so much thereof as may be required for its convenient use and occupation: Chenoweth v. Spencer, 64 Or. 540 (131 Pac. 302, Ann. Cas. 1914D, 678). Section 10193 provides for priority between liens and mortgages, and, as to the enforcement of liens which do not extend to the land, says:
“In enforcing such lien, such building or other improvement may be sold separately from said land; and when so sold, the purchaser may remove the same, within a reasonable time thereafter, not to exceed thirty days, upon the payment to the owner of the land of a reasonable rent for its use from the date of its purchase to the time of removal; provided, that if such removal be prevented by legal pro
*362 ceedings, said thirty days shall not begin to run until the final determination of such proceedings in the court of first resort, or the appellate court if appeal be taken.”Under this section, a mechanic’s lien upon a structure shall be preferred to any lien, mortgage or other encumbrance attaching to the land subsequent to the time when the structure was commenced “or the materials were commenced to be furnished and placed upon or adjacent to the land,” and to all prior liens, mortgages, or other encumbrances upon such land as well. Such lien is also regarded as superior to any encumbrance unrecorded at the time the building or structure was commenced or the materials for such structure were commenced to be furnished. In support of the right of sale and removal announced by the foregoing statutory provision, see Allen and Krosel v. Rowe et al., 19 Or. 188 (23 Pac. 901); Cooper Mfg. Co. v. Delahunt, 36 Or. 402 (51 Pac. 649, 60 Pac. 1); 2 Jones on Liens (3 ed.), § 1250.
Prom the evidence it does not appear that Kelly, or any other person in his behalf, complied with the mandatory provisions pf Section 10191, Or. L., that he give notice in writing to the owner sought to be held stating, in effect, that he had commenced to deliver material and supplies for use in the construction of the improvement to be erected upon the land. It follows that he is not entitled to a lien for materials upon Manary’s interest in the land: Auld v. Starbard, 89 Or. 284 (173 Pac. 664); Columbia River Door Co. v. Todd, 90 Or. 147 (175 Pac. 443, 860); Boise-Payette Lumber Co. v. Dominican Sisters, 102 Or. 314 (202 Pac. 554); Christman v. Salway, 103 Or. 666 (205 Pac. 541); Nicolai-Nep
*363 pach Co. v. Poore, 120 Or. 163 (251 Pac. 268); Johnson v. Alm, et al., 121 Or. 285 (254 Pac. 803).What constitutes an owner, within the meaning of the Mechanic’s Lien Law? The meaning of the term “owner,” as used in the Mechanic’s Lien Law, is controlled by the context and purpose of the statute. The term, as applied to real property, has no fixed meaning which can be declared to be applicable under all circumstances and under. any and every enactment. It usually implies that the estate possessed is an estate in fee simple, but it has been defined to include one who has the usufruct control or occupation of land with a claim of ownership, whether his interest be an absolute fee or a less estate: Binhoff v. State, 49 Or. 419 (90 Pac. 586). See, also, Anderson’s Dictionary of Law; 2 Jones on Liens (3 ed.), § 1248. As used in Section 10191, Or. L., the term “owner” is not limited in meaning to the ownership of the fee, but includes also the ownership of a lesser estate. If the person who causes improvements to be made upon land is the owner of the fee, the lien is upon the fee; but if he owns a lesser estate, the lien is upon that estate. In the cause at issue the vendee in possession, i. e., the owner of the equitable interest and likewise the corporation that contracted for the improvements to be constructed, was an owner within the meaning of that section, and its estate was subject to a mechanic’s lien: Willamette Falls Co. v. Riley, 1 Or. 183; Kezartee v. Marks & Co., 15 Or. 529 (16 Pac. 407); Myers v. Strowbridge Estate Co., 82 Or. 29 (160 Pac. 135); Boisot, Mechanics’ Liens, §301; 18 E. C. L., p. 885; 40 O. J., p. 61, § 26.
Now, alluding to the owner’s interest in the real property: Manary,’the owner of the fee, is an owner
*364 under Section 10194, and under the provisions of Section 10191 he is likewise an owner and entitled to the five days ’ notice required of any person claiming the benefit of a lien for material furnished in accordance therewith, before his premises can be charged with the materials that went into the improvements. See the recent case of Nicolai-Neppach Co. v. Poore, supra.From the statute and its application by this court in a number of instances it is clear that Kelly is not entitled to a lien upon the interest of Manary in the real property, for the materials that went into the structures or superstructures erected upon that land at the instance of the equitable owner. As found by the trial court, he is, however, entitled to a lien upon the land for the amount of the labor claims, unless the notice posted by Manary constitutes a bar.
The claim of the Eagle Lumber Company likewise involves the sufficiency of the Manary notice, We shall now consider that notice. It appears from the record that the Eagle Lumber Company furnished its first material on May 27, 1925, and, on June 1, 1925, mailed to the defendant Manary a notice in writing in compliance with Section 10191, Or. L., which notice informed Manary that the Lumber Company had commenced to furnish material upon the order of the Tourist Service Corporation, to be used in the construction of buildings upon the real property involved herein, and that a lien might be claimed for all material furnished for use thereon. On this point, the lower court found:
“That said buildings or improvements were constructed with the knowledge and consent of said James Manary.”
*365 Section 10194, Or. L., announces a rule of evidence that has been invoked in the instant case. That section provides:“Every building or other improvement mentioned in Section 10191, constructed upon any lands with the knowledge of the owner or the person having or claiming any interest therein shall be held to have been constructed at the instance of such owner or person having or claiming any interest therein; and the interest owned or claimed shall be subject to any lien filed in accordance with the provisions of this act, unless such owner or person having or claiming an interest therein shall, within three days after he shall have obtained knowledge of the construction, alteration or repair, give notice that he will not be responsible for the same by posting a notice in writing to that effect in some conspicuous place upon said land, or upon the building or other improvement situated-thereon.”
Under the foregoing statutory provision, the interest of the owner of the fee in the land is subject to the lien claims, notwithstanding the labor and material was furnished at the instance of another person, if the owner, knowing that the “construction, alteration or repair” was made, failed to give notice that he would not be responsible for the same: Allen v. Rowe, 19 Or. 188 (23 Pac. 901); 2 Jones on Liens, (3 ed.), § 1255.
Manary seeks to relieve himself from all responsibility by reason of having posted notice on the lands upon which the auto camp was constructed. However, it will be remembered that this notice was posted, not within the three days after the commencement of the construction of the improvements came to his knowledge, but weeks thereafter. For a definition of the phrase “the commencement of a structure,” within the meaning of the Mechanic’s Lien Law,
*366 see Mutual Benefit Life Ins. Co. v. Rowand, 26 N. J. Eq. 389. It is a well-established rule that, in order for an owner to relieve himself from responsibility by posting notices, he must act within the prescribed period of three days after obtaining knowledge of the construction of the improvements. It is said in 40 C. J., Section 138, Mechanics’ Liens:“ Strict compliance with a statute of the character under consideration is necessary to relieve an owner from responsibility in a case falling within its terms. * # The notice prescribed by statute may be given on any day the work is in progress, provided it is given within the time limited after acquiring knowledge of the improvement.”
That Manary knew that his vendee intended to construct a large number of buildings upon the land described in the contract, for the purpose of establishing an auto camp thereon, is mánifest. It is equally plain that he knew that the corporation entered into the execution of that intent and commenced the construction of its camp, yet it was weeks after the construction was commenced that he finally sought to hold his premises free from liens by posting notices. This is the decisive point in the case. Under the theory of our Mechanic’s Lien Law, it was not equitable for Manary, the owner of the fee, to authorize, or knowingly to permit, his vendee to contract with laborers and materialmen for the improvement of his real property by the construction of a valuable auto camp thereon, without compensating those who toiled and those who furnished the material that went into the structures placed upon his property: Or. L., § 10194.
Manary invokes the protection of the five days’ materialmen’s notice prescribed by Section 10191,
*367 Or. L. It is Ms right. The contractor and material-men now seek the 'benefit, inuring to them by the terms of Section 10194 thereof. They too are within their right. It is our duty, in the administration of the Mechanic’s Lien Law, to carry out the legislative intent as expressed in each of the foregoing sections, and thus secure to the litigants the rights wMch the law gives them.Manary likewise assails the validity of what he terms a lump sum lien on separate buildings and improvements. This objection is without merit. It was unnecessary for the contractor furnishing labor and material to show the value of the labor and material that went into each structure. Under the terms of a single contract, the contractor performed labor and furnished material indiscriminately for the building of a number of structures upon a single tract of land. Likewise the lumber company under a single contract furnished material that went into the several structures upon a single tract of land described in its lien. Hence it was proper for each lienor to claim a lien against all of the structures: McCormack v. Bertschinger, 115 Or. 250 (237 Pac. 363); Warrenton Lumber Co. v. Smith, 117 Or. 530 (245 Pac. 313).
The record discloses no valid reason for reversing this case. The decree of the trial court should be affirmed. It is so ordered. Affirmed.
Rossman, J., did not participate in the consideration of this case. *368 For the petition, Mr. John Vcm Zante and Mr. Albert H. Tanner.No appearance contra.