Ta v. Chaudhry , 2016 Ohio 4944 ( 2016 )


Menu:
  • [Cite as Ta v. Chaudhry, 2016-Ohio-4944.]
    IN THE COURT OF APPEALS OF OHIO
    TENTH APPELLATE DISTRICT
    Phu Ta,                                        :
    Plaintiff-Appellee/            :
    [Cross-Appellant],
    :
    v.                                                               No. 15AP-867
    :             (M.C. No. 2014CVH-8474)
    Muhammad Chaudhry,
    :            (REGULAR CALENDAR)
    Defendant-Appellant/
    [Cross-Appellee].              :
    D E C I S I O N
    Rendered on July 12, 2016
    On brief: Strip, Hoppers, Leithart, McGrath & Terlecky Co.,
    LPA, and Nelson E. Genshaft, for appellee/cross-appellant.
    Argued: Nelson E. Genshaft.
    On brief: Gillett Law Office, LLC, and Gary A. Gillett, for
    appellant/cross-appellee. Argued: Gary A. Gillett.
    APPEAL from the Franklin County Municipal Court
    TYACK, J.
    {¶ 1} Plaintiff-appellee, Phu Ta, and defendant-appellant, Muhammad Chaudhry,
    both appealed from the decision of the Franklin County Municipal Court.                Ta and
    Chaudhry both filed cross-appeals against each other. For the following reasons, we
    affirm the decision of the trial court.
    {¶ 2} Chaudhry filed one assignment of error for our consideration:
    The Municipal Court erred in its Decision and Entry of
    August 17, 2015 by denying the Counterclaim of Appellant
    Muhammad Chaudhry for Breach of Contract against
    Appellee/Cross-Appellant, Phu Ta on Grounds that no
    Contract Existed Among the Parties.
    No. 15AP-867                                                                                2
    {¶ 3} Ta has filed two cross-assignments of error for our consideration:
    [I.] The Trial Court improperly held that the Remodeling
    Agreement entered into by the parties was not an enforceable
    contract.
    [II.] The Trial Court improperly held that a separate oral
    agreement regarding installation of the fire wall [sic] between
    the two units was an unenforceable contract without
    disposing of the Cross-Appellant's damages for lost rent.
    Factual and Case History
    {¶ 4} Ta is the owner of a building located at 895 Parsons Avenue, Columbus,
    Ohio. On June 16, 2012, Chaudhry and Cheryl Solomon signed a lease with Ta to run a
    daycare business by leasing unit C of the building. At the same time, the three parties
    signed a remodeling agreement regarding the cost of upgrades that were to be done to the
    property to accommodate the new daycare. These costs were to be shared.
    {¶ 5} Sometime after signing the lease, it was discovered that the building lacked
    a firewall between rental units B and C. This firewall was required by the Columbus City
    Code in order to run a daycare.        Ta claims that the parties entered into an oral
    modification of the remodeling agreement to add the necessary firewall between units B
    and C while Chaudhry claims there was no enforceable agreement.
    {¶ 6} On March 18, 2014, Ta filed suit to recover damages from Chaudhry and
    Solomon for their alleged failure to reimburse him for money spent to make repairs to the
    property and for lost rent due to not completely making the repairs in a timely manner
    which prevented adjoining units from being leased. Solomon settled with Ta, and Ta
    dismissed his claims against her and Solomon dismissed her counterclaim against Ta. On
    September 4, 2014, Chaudhry filed a counterclaim against Ta alleging Ta failed to
    reimburse him for expenses Ta was obligated to pay under the remodeling agreement.
    {¶ 7} On June 29, 2015, the trial court conducted a trial in which both Ta and
    Chaudhry were represented by counsel and admitted exhibits into evidence.                 On
    August 17, 2015, the trial court found that both parties failed to prove that the remodeling
    agreement was a contract. "[T]he remodeling agreement entered into by the parties does
    not contain definite and certain terms such that it is a legally enforceable contract." (Trial
    No. 15AP-867                                                                               3
    court decision at 3.) The trial court ruled that the document is simply too vague and
    uncertain to have either party recover under a breach of contract claim.
    {¶ 8} The trial court also ruled that the alleged oral agreement entered into by the
    parties for the installation of the firewall was not proved by clear and convincing evidence.
    "The evidence before the Court does not establish when the alleged oral agreement was
    made or the terms of the oral agreement. In particular, the parties have not indicated any
    words, deeds, acts, or silence on behalf of the parties that suggest that a contract was
    formed." (Trial court decision at 4.) The court found that neither party is entitled to
    prevail on a breach of oral contract claim. Chaudhry filed an appeal on September 16,
    2015 and Ta filed a cross-appeal on September 23, 2015.
    Proving the Existence of a Contract
    {¶ 9} Both parties to the appeal argue that the trial court erred in ruling that the
    remodeling agreement and the oral agreement for the firewall were not enforceable
    contracts.
    {¶ 10} A contract is a promise or a set of promises for the breach of which the law
    gives a remedy, or the performance of which the law in some way recognizes a duty.
    McSweeney v. Jackson, 
    117 Ohio App. 3d 623
    , 631 (4th Dist.1996). "To successfully
    prosecute a breach of contract claim, a plaintiff must present evidence of (1) the existence
    of a contract, (2) plaintiff's performance of the contract, (3) defendant's breach of the
    contract, and (4) plaintiff's loss or damage as a result of defendant's breach." Barlay v.
    Yoga's Drive-Thru, 10th Dist. No. 03AP-545, 2003-Ohio-7164, ¶ 6, citing Doner v.
    Snapp, 
    98 Ohio App. 3d 597
    , 600 (2d Dist.1994).
    {¶ 11} It is well-settled that "[t]he existence of a contract is dependent upon an
    offer, an acceptance and consideration." DeHoff v. Veterinary Hosp. Operations of Cent.
    Ohio, Inc., 10th Dist. No. 02AP-454, 2003-Ohio-3334, ¶ 47, quoting Renaissance
    Technologies, Inc. v. Speaker Components, Inc., 9th Dist. No. 21183, 2003-Ohio-98. An
    offer is defined as "the manifestation of willingness to enter into a bargain, so made as to
    justify another person in understanding that his assent to that bargain is invited and will
    conclude it." Reedy v. Cincinnati Bengals, Inc., 
    143 Ohio App. 3d 516
    (1st Dist.2001).
    Courts generally determine the existence of a contract as a matter of law. Motorists Mut.
    Ins. Co. v. Columbus Fin., Inc., 
    168 Ohio App. 3d 691
    , 2006-Ohio-5090 (10th Dist.2006).
    No. 15AP-867                                                                                 4
    {¶ 12} To prove the existence of a contract, written or oral, " 'a plaintiff must show
    that both parties consented to the terms of the contract, that there was a "meeting of the
    minds" of both parties, and that the terms of the contract are definite and certain.' "
    Barlay at ¶ 6, quoting Nilavar v. Osborn, 
    137 Ohio App. 3d 469
    , 484 (2d Dist.2000),
    citing McSweeney at 631; Episcopal Retirement Homes, Inc. v. Ohio Dept. of Indus.
    Relations, 
    61 Ohio St. 3d 366
    , 369 (1991).
    {¶ 13} It is well established that a contract is not enforceable when the terms are
    not sufficiently definite. Isquick v. Classic Autoworks, 
    89 Ohio App. 3d 767
    , 772 (8th
    Dist.1993) (two-page typewritten "Notes" submitted by Fuller to Isquick concerning the
    restoration project upon which the claim was based contained absolutely no provision
    concerning the extent or scope of the restoration or methods to be followed to restore the
    vehicles). A valid contract must be specific as to its essential terms, such as the identity of
    the parties to be bound, the subject matter of the contract, and consideration. Alligood v.
    Procter & Gamble Co., 
    72 Ohio App. 3d 309
    (1st Dist.1991).
    {¶ 14} The terms of a contract are sufficiently certain or definite where they
    "provide a basis for determining the existence of a breach and for giving an appropriate
    remedy." Mr. Mark Corp. v. Rush, Inc., 
    11 Ohio App. 3d 167
    (8th Dist.1983), quoting
    Restatement of the Law 2d, Contracts, Section 33 at 92 (1981). Furthermore, " '[a]n offer
    which appears to be indefinite may be given precision by usage or trade or by course of
    dealing between the parties. Terms may be supplied by factual implication, and in
    recurring situations the law often supplies a term in the absence of agreement to the
    contrary. * * * Where the parties have intended to conclude a bargain, uncertainty as to
    incidental or collateral matters is seldom fatal to the existence of the contract.' " Mr.
    Mark Corp. at 169, quoting Restatement of the Law 2d, Contracts, Section 33 at 95 (1981),
    Comment f.
    {¶ 15} Thus, if it can be determined that the parties intend to be bound, a court
    may fashion less essential terms that were omitted in order to reach a fair and just result.
    Inhalation Plastics, Inc. v. Medex Cardio-Pulmonary, Inc., S.D.Ohio No. 2:07-cv-116
    (Mar. 13, 2013), citing Litsinger Sign Co. v. Am. Sign Co., 
    11 Ohio St. 2d 1
    (1967).
    However, "if the parties' manifestations taken together as making up the contract, when
    reasonably interpreted in the light of all the circumstances, do not enable the court to
    No. 15AP-867                                                                               5
    determine what the agreement is and to enforce it without, in effect, 'making a contract
    for the parties,' no enforceable obligation results." Litsinger Sign Co. at 14.
    {¶ 16} Information regarding the work timetable and monetary remuneration are
    examples of the requisite definite and certain terms of a contract of a construction project.
    Episcopal Retirement Homes, Inc. at 369. When a contract does not specify a time for
    performance and time is not of the essence, the law implies that performance must take
    place within a reasonable time. Morton Bldgs., Inc. v. Correct Custom Drywall, Inc.,
    10th Dist. No. 06AP-851, 2007-Ohio-2788, ¶ 16. A breach of the implied duty to perform
    within a reasonable time constitutes a material breach of the contract. 
    Id. {¶ 17}
    An appellate review of the existence of a contract raises a mixed question of
    fact and law:
    We accept the facts found by the trial court on some
    competent, credible evidence, but freely review application of
    the law to the facts. A reviewing court should be guided by a
    presumption that the findings of a trial court are correct, since
    the trial judge is best able to view the witnesses and observe
    their demeanor, gestures and voice inflections, and use their
    observations in weighing credibility of the proffered
    testimony.
    {¶ 18} McSweeney at 632; see In re Jane Doe 1, 
    57 Ohio St. 3d 135
    (1990), see also
    Seasons Coal Co. v. Cleveland, 
    10 Ohio St. 3d 77
    (1984). However, reviews of questions of
    law regarding the existence of a contract are de novo. Continental W. Condominium Unit
    Owners Assn. v. Howard E. Ferguson, Inc., 
    74 Ohio St. 3d 501
    , 502 (1995).
    The Remodeling Agreement does Not Constitute an Enforceable
    Contract
    {¶ 19} As a threshold issue, we examine the remodeling agreement to determine if
    it creates a contract. The agreement reads in relevant part:
    The Landlord (Phu Ta) and the Tenant (Mohamad A.
    Chaudhry and Cheryl E. Solomon) agree to pay for the
    upgrades at 895-C Parsons Ave location. Each party
    (Landlord and Tenant) agrees to pay One Half (1/2) of the
    following remodeling expenses:
    1. Install a new Heating/Air conditioner unit to cover the back
    area (in front of the Overhead door).
    No. 15AP-867                                                                                  6
    2. Expand the Two (2) existing Restrooms to meet ADA
    requirements.
    3. Install a new Cement Block Wall and an Emergency Exit
    door in place of the existing Overhead door.
    4. Fire system.
    5. Drop ceiling above Garage Door.
    Landlord also agrees to pay One Third (1/3) of the Architect
    Expenses (Blue print and new Design Layout for the
    Restrooms). Landlord will pay up to One Thousand Dollars
    for his share of the Architect expenses.
    Landlord will provide Tenant an estimate cost of the listed
    repairs. Tenant agrees to pay Landlord One Half (1/2) of the
    repair cost before the remodeling work is begun.
    {¶ 20} Examining the agreement, we must determine if the terms of the contract
    are sufficiently certain and definite. The parties to the contract is one term that is certain.
    {¶ 21} The agreement specifies where the upgrades are to take place, in section C
    of the building at 895 Parsons Ave. However, some of these upgrades might not only
    relate to unit C of the building. Item 4 "Fire system" would likely need to be part of some
    larger fire detection and suppression system that covers the whole of the property. We
    cannot determine what the scope of "Fire system" means. Similarly, the other upgrades
    themselves also lack specificity to aid a court in determining whether a party is in breach
    or not. The trial court noted that there is no specificity to size of the restroom expansion,
    the nature of the fire system, or the manner in which the ceiling was to be repaired or how
    low the ceiling would be lowered.
    {¶ 22} The short one-page agreement further uses the terms "upgrades,"
    "remodeling," and "repair" interchangeably. These terms clearly do not have the same
    meaning and when combined with such scant information about the provisions of the
    agreement, a court could not be able to determine when the contract would be breached.
    The agreement could be read to either repair or upgrade the "Fire system" and the "Drop
    ceiling above Garage Door."
    {¶ 23} The agreement does not specify which party is responsible for actually
    completing the upgrades. The only indication is that the landlord would provide an
    No. 15AP-867                                                                              7
    estimate for repairs and the tenants would provide one-half of the repair costs before
    remodeling work was to begin. This provision only further confuses the matter as now
    there could be two possible categories of work to be done, repairs and remodeling. What
    work constitutes repairs and what is remodeling is anything but clear. Therefore, a court
    could not possibly determine which party was responsible for what work was to be
    completed.
    {¶ 24} Further, there is no monetary limit on the scope of the project. Nor is there
    any provision for a party to decline a particular repair or remodeling. Without being
    certain which party is responsible for the work, the lack of monetary limits and lack of set
    costs for the project only exacerbate the uncertainty of the agreement as a whole.
    {¶ 25} There is no time limit or time table for the completion of the work, an
    important consideration when dealing with a combination of remodeling a building space
    and a lease. The law implies that performance must take place within a reasonable time.
    Morton Bldgs., Inc. at ¶ 16.
    {¶ 26} We find that there are few certain and definite terms in the remodeling
    agreement. On the whole, the agreement does not contain enough certain definite terms
    to create an enforceable contract.      When reasonably interpreted in light of all the
    circumstances, we are not able to determine what the terms of the agreement are. To
    enforce the agreement as written, in effect, forces the court to make a contract for the
    parties. There is no enforceable obligation that results from the remodeling agreement.
    {¶ 27} Chaudhry's assignment of error is overruled and Ta's first cross-assignment
    of error is overruled.
    {¶ 28} Ta's second assignment of error only argues the trial court improperly held
    that a separate oral agreement regarding the installation of a firewall between two of the
    units of the building was not an amendment to the original remodeling agreement but
    rather a separate unenforceable oral contract. Ta only argues that the firewall agreement
    was an oral modification to the remodeling agreement and that Chaudhry was in breach
    of the modification resulting in damages of lost rent in the adjacent unit.
    {¶ 29} Having affirmed that the remodeling agreement is not an enforceable
    contract, the agreement to install the firewall cannot be found to be an enforceable oral
    modification. Therefore, we find Ta's argument to be incorrect.
    {¶ 30} Ta's second cross-assignment of error is overruled.
    No. 15AP-867                                                                         8
    {¶ 31} Having overruled all the assignments of error the judgment of the Franklin
    County Municipal Court is affirmed.
    Judgment affirmed.
    BRUNNER and HORTON, JJ., concur.