Maine v. Federal Energy Regulatory Commission , 854 F.3d 9 ( 2017 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued December 6, 2016              Decided April 14, 2017
    No. 15-1118
    EMERA MAINE, FORMERLY KNOWN AS BANGOR
    HYDRO-ELECTRIC COMPANY, ET AL.,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    ATTORNEY GENERAL FOR THE
    STATE OF CONNECTICUT, ET AL.,
    INTERVENORS
    Consolidated with 15-1119, 15-1121
    On Petitions for Review of Orders of the
    Federal Energy Regulatory Commission
    David B. Raskin argued the cause for petitioners Emera
    Maine, et al. With him on the briefs were Gary A. Morgans,
    Charles G. Cole, Jeffrey M. Jakubiak, Kenneth G. Jaffe, Sean
    2
    A. Atkins, Gunnar Birgisson, Stephen M. Spina, David R. Poe,
    Karen Krug O’Neill, and S. Mark Sciarrotta. Jason J.
    Fleischer and Mary E. Grover entered appearances.
    David E. Pomper argued the cause for petitioners Attorney
    General of Massachusetts, et al. With him on the briefs were
    Scott H. Strauss, Latif M. Nurani, John P. Coyle, Joseph A.
    Rosenthal, Susan W. Chamberlin, Maura Healy, Attorney
    General, Office of the Attorney General for the
    Commonwealth of Massachusetts, Jeffrey A. Schwarz, George
    Jepson, Attorney General, Office of the Attorney General for
    the State of Connecticut, John S. Wright, Michael C.
    Wertheimer, and Clare E. Kindall, Assistant Attorneys
    General, Donald J. Sipe, Cynthia Arcate, Timothy R.
    Schneider, and Leo J. Wold, Assistant Attorney General, Office
    of the Attorney General for the State of Rhode Island.
    Beth G. Pacella, Deputy Solicitor, Federal Energy
    Regulatory Commission, argued the cause for respondent.
    With her on the brief were Robert H. Solomon, Solicitor, and
    Lona T. Perry, Deputy Solicitor.
    Jefffrey M. Jakubiak, Kenenth G. Jaffe, Sean A. Atkins,
    Gunnar Birgisson, Stephen M. Spina, David R. Poe, David B.
    Raskin, Gary A. Morgans, Charles G. Cole, Karen Krug
    O’Neill, and S. Mark Sciarrotta were on the brief for intervenor
    Transmission Owners supporting respondent.
    Scott H. Strauss, David E. Pomper, Latif M. Nurani, John
    P. Coyle, Joseph A. Rosenthal, Susan W. Chamberlin, Maura
    Healy, Attorney General, Office of the Attorney General for
    the Commonwealth of Massachusetts, Jeffrey A. Schwarz,
    George Jepson, Attorney General, Office of the Attorney
    General for the State of Connecticut, John S. Wright, Michael
    C. Wertheimer, and Clare E. Kindall, Assistant Attorneys
    3
    General, Donald J. Sipe, Cynthia Arcate, Timothy R.
    Schneider, and Leo J. Wold, Assistant Attorney General, Office
    of the Attorney General for the State of Rhode Island, were on
    the brief for Customers as Intervenors Supporting FERC
    Authority To Reduce Regulated Returns.
    Before: MILLETT, Circuit Judge, and SENTELLE and
    RANDOLPH, Senior Circuit Judges.
    Opinion for the Court filed by Senior Circuit Judge
    SENTELLE.
    SENTELLE, Senior Circuit Judge: Under the Federal Power
    Act (“FPA”), the Federal Energy Regulatory Commission
    (“FERC” or “the Commission”) must ensure that all rates
    charged for the transmission or sale of electric energy are “just
    and reasonable.” 16 U.S.C. §§ 824d(a), 824e(a). Petitioners
    New England Transmission Owners (“Transmission Owners”)
    provide transmission services for customers in New England.
    In 2011, Petitioners Massachusetts and various consumer-side
    stakeholders (“Customers”) filed a complaint under section
    206 of the FPA, 16 U.S.C. § 824e, alleging that Transmission
    Owners’ base return on equity (“ROE”) had become unjust and
    unreasonable. FERC’s orders in that section 206 proceeding
    are the subjects of the petitions for review in this case.
    After creating a new zone of reasonableness and
    identifying a specific base ROE it found to be just and
    reasonable, FERC held that Transmission Owners’ existing
    ROE—which was within the newly determined zone of
    reasonableness but did not equal FERC’s new ROE—was
    unlawful. FERC explained that by setting a new just and
    reasonable ROE, it necessarily found that Transmission
    Owners’ existing ROE was unjust and unreasonable, thus
    satisfying its burdens under section 206.
    4
    In setting Transmission Owners’ new ROE, FERC
    deviated from its traditional use of the midpoint of the zone of
    reasonableness, citing the presence of anomalous capital
    market conditions and concluding that a mechanical
    application of the midpoint would not result in a just and
    reasonable rate in this case. After considering additional record
    evidence, FERC placed the ROE at the midpoint of the upper
    half of the newly determined zone of reasonableness.
    FERC then informed Transmission Owners that their total
    ROE—base ROE plus any incentive adders—was now capped
    at the upper end of the newly determined zone of
    reasonableness. Rather than change Transmission Owners’
    previously approved incentive adders, FERC explained that its
    decision merely applied the Commission’s well-established
    policy that a utility’s total ROE must remain within the zone of
    reasonableness.
    Both Transmission Owners and Customers filed petitions
    for review challenging whether FERC satisfied the statutory
    requirements under section 206 in setting a new ROE.
    Transmission Owners argue that FERC’s orders must be
    vacated because it failed to find that the existing ROE was
    unjust and unreasonable before setting a new ROE. Customers
    contend that FERC arbitrarily placed the new ROE at the
    midpoint of the upper half of the zone of reasonableness.
    Because FERC failed to articulate a satisfactory explanation for
    its orders, we grant the petitions for review.
    I.
    ISO New England Tariff
    Transmission Owners are a group of privately owned
    utilities that provide transmission services in New England. In
    5
    2004, Transmission Owners and ISO New England, Inc.
    established ISO New England as a regional transmission
    organization. See Conn. Dep’t of Pub. Util. Control v. FERC,
    
    593 F.3d 30
    , 32 (D.C. Cir. 2010). Transmission Owners
    recover their transmission revenue requirements through
    formula rates included in ISO New England, Inc.’s open access
    transmission tariff (“ISO New England Tariff”). To calculate
    the total cost for each Transmission Owner to provide
    transmission service from its facilities, the ISO New England
    Tariff uses formula rates, which are based on the aggregated
    cost of all the transmission assets of each Transmission Owner.
    The revenue requirements for Transmission Owners are
    calculated using the same single base ROE. Each Transmission
    Owner’s costs are calculated under the formula, summed, and
    then divided by the aggregate demand in New England to
    produce the regional transmission rates under the ISO New
    England Tariff. This is known as “rolled-in” ratemaking. See,
    e.g., Otter Tail Power Co., 12 FERC ¶ 61,169 at 61,420 (1980).
    Section 205 Proceedings Before the Commission
    Pursuant to section 205 of the FPA, 16 U.S.C. § 824d,
    Transmission Owners submitted a proposal in 2003 to establish
    ISO New England as a regional transmission organization.
    Transmission Owners also submitted “a related section 205
    filing seeking approval for the ROE component recoverable
    under the regional and local transmission rates charged by ISO
    New England.” Bangor Hydro-Elec. Co., 117 FERC ¶ 61,129
    at P 5 (2006), order on reh’g, 122 FERC ¶ 61,265 (2008), order
    granting clarification, 124 FERC ¶ 61,136 (2008), aff’d sub
    nom. Conn. Dep’t of Pub. Util. Control v. FERC, 
    593 F.3d 30
    (D.C. Cir. 2010). In 2006, FERC established the base ROE for
    Transmission Owners at 11.14 percent. In establishing the base
    ROE, FERC relied on a zone of reasonableness, determined in
    a discounted cash flow analysis, of 7.3 percent to 13.1 percent.
    6
    FERC also approved a number of ROE incentive adders
    applicable to Transmission Owners. Citing section 219 of the
    FPA, 16 U.S.C. § 824s, FERC established “incentive-based
    rate treatments to further encourage the construction of
    transmission facilities and replacement of aging transmission
    infrastructure.” S. Cal. Edison Co. v. FERC, 
    717 F.3d 177
    , 179
    (D.C. Cir. 2013) (citing Promoting Transmission Inv. Through
    Pricing Reform, 116 FERC ¶ 61,057 (2006), order on reh’g,
    117 FERC ¶ 61,345 (2006), order on reh’g, 119 FERC
    ¶ 61,062 (2007)). All rates approved under section 219 must
    meet the FPA’s just-and-reasonable standard. 16 U.S.C.
    § 824s(d). In Transmission Owners’ section 205 proceeding,
    FERC approved a 100-basis-point adder for certain
    transmission projects, which we affirmed. See Conn. Dep’t of
    Pub. 
    Util. 593 F.3d at 33
    –37. Most of Transmission Owners’
    incentives were approved in separate proceedings. See, e.g.,
    Ne. Utils. Serv. Co., 125 FERC ¶ 61,183 (2008), reh’g denied,
    135 FERC ¶ 61,270 (2011); Cent. Me. Power Co., 125 FERC
    ¶ 61,079 (2008), reh’g denied, 135 FERC ¶ 61,136 (2011).
    Section 206 Proceedings Before the Commission
    This case concerns FERC’s determination of Customers’
    section 206 challenge to Transmission Owners’ base ROE set
    in the section 205 proceedings. See Coakley v. Bangor
    Hydro-Elec. Co., 144 FERC ¶ 63,012 (2013) (“ALJ
    Decision”), aff’d in part, rev’d in part, Opinion No. 531, 147
    FERC ¶ 61,234 (2014) (“Opinion No. 531”), order on paper
    hearing, Opinion No. 531-A, 149 FERC ¶ 61,032 (2014)
    (“Opinion No. 531-A”), order on reh’g, Opinion No. 531-B,
    150 FERC ¶ 61,165 (2015) (“Opinion No. 531-B”).
    In 2011, Customers filed a section 206 complaint with
    FERC alleging that Transmission Owners’ 11.14 percent base
    7
    ROE had become unjust and unreasonable. The complaint was
    premised on Customers’ contention that Transmission Owners’
    capital costs had declined since the base ROE was established
    in 2006 due to changes in the capital markets. This section 206
    proceeding was “the first case of its kind to challenge utilities’
    base ROEs [after] the economic recession of 2007-2009 . . . .”
    Opinion No. 531-B, 150 FERC ¶ 61,165 at P 15 n.34.
    Applying a newly created discounted cash flow zone of
    reasonableness of 6.1 percent to 13.2 percent, the
    Administrative Law Judge concluded that Transmission
    Owners’ current 11.14 percent base ROE was unjust and
    unreasonable. ALJ Decision, 144 FERC ¶ 63,012 at PP 544,
    587, 589. Then, using the midpoint of the newly determined
    zone of reasonableness, the ALJ set Transmission Owners’
    base ROE at 9.7 percent. 
    Id. at PP
    544, 587, 590.
    On review of the ALJ’s decision, FERC adopted a new
    two-step discounted cash flow, or DCF, methodology for
    determining an electric utility’s just and reasonable ROE. See
    Opinion No. 531, 147 FERC ¶ 61,234 at PP 7–9, 13–41
    (adopting the methodology historically used to set ROEs for
    natural gas and oil pipelines). Applying the two-step
    methodology in this case, FERC created a new zone of
    reasonableness of 7.03 percent to 11.74 percent. 
    Id. at PP
    125,
    143; Opinion No. 531-B, 150 FERC ¶ 61,165 at P 25. In the
    instant proceeding, Transmission Owners and Customers do
    not challenge FERC’s use of the two-step methodology or the
    resulting zone of reasonableness. Instead, they object to
    FERC’s placement of Transmission Owners’ base ROE within
    that newly determined zone of reasonableness.
    Because the existing 11.14 percent base ROE fell within
    FERC’s newly determined zone of reasonableness,
    Transmission Owners argued that FERC lacked statutory
    8
    authority under section 206 to change the existing base ROE.
    FERC rejected that argument, explaining that “the DCF zone
    of reasonableness does not establish a continuum of just and
    reasonable base ROEs, any one of which the utility would
    equally be free to charge to ratepayers; rather, only the single
    point approved by the Commission within the DCF zone of
    reasonableness is the just and reasonable base ROE.” Opinion
    No. 531-B, 150 FERC ¶ 61,165 at P 32; see also Opinion No.
    531, 147 FERC ¶ 61,234 at P 51; Opinion No. 531-B, 150
    FERC ¶ 61,165 at PP 21–31 & n.52.
    The midpoint of FERC’s newly determined zone of
    reasonableness was 9.39 percent. Although FERC typically
    sets a utility’s base ROE at the midpoint of the zone of
    reasonableness, Transmission Owners argued that a base ROE
    at 9.39 percent would fail to meet the capital attraction
    standards of Hope and Bluefield. See FPC v. Hope Nat. Gas
    Co., 
    320 U.S. 591
    (1944); Bluefield Waterworks &
    Improvement Co. v. Pub. Serv. Comm’n of W. Va., 
    262 U.S. 679
    (1923). FERC agreed, noting that “all methods of
    estimating the cost of equity,” including the discounted cash
    flow analysis, “are susceptible to error when the assumptions
    underlying them are anomalous.” Opinion No. 531-B, 150
    FERC ¶ 61,165 at P 50. Because of “the undisputed presence
    of . . . anomalous capital market conditions,” FERC had “less
    confidence that the midpoint of the zone of reasonableness . . .
    accurately reflect[ed] the equity returns necessary to meet the
    Hope and Bluefield capital attraction standards.” 
    Id. at P
    49
    (quoting Opinion No. 531, 147 FERC ⁋ 61,234 at P 145).
    Accordingly, FERC determined that “a mechanical
    application” of the midpoint in this case would result in an
    ROE that was too low to satisfy Hope and Bluefield. See 
    id. at PP
    36, 50, 56.
    9
    Because it had “less confidence” in the results of its
    discounted cash flow analysis, FERC considered “additional
    record evidence” to inform its placement of Transmission
    Owners’ new base ROE within the zone of reasonableness.
    Opinion No. 531, 147 FERC ¶ 61,234 at P 145. FERC stressed,
    however, that it was “not depart[ing] from [its] use of the DCF
    methodology; rather [it] use[d] the record evidence to inform
    the just and reasonable placement of the ROE within the zone
    of reasonableness established in the record by the DCF
    methodology.” 
    Id. at P
    146. FERC considered the following
    alternative analyses: (1) risk premium analysis; (2) Capital
    Asset Pricing Model (“CAPM”) analysis; (3) expected
    earnings analysis; and (4) comparison of state
    commission-approved ROEs. 
    Id. at PP
    145–46, 149–50;
    Opinion No. 531-B, 150 FERC ¶ 61,165 at P 49. After
    considering these alternative analyses, FERC concluded that
    they “corroborate[d] [its] determination that placement [of the
    base ROE] at a point above the midpoint was warranted.”
    Opinion No. 531-B, 150 FERC ¶ 61,165 at P 49; see also 
    id. at P
    101 n.213 (stating that additional analyses supported
    conclusion “that the ROE should indeed be set above the
    midpoint”). And because it traditionally uses measures of
    central tendency to determine an appropriate return in ROE
    cases, FERC set Transmission Owners’ base ROE at the
    midpoint of the upper half of the newly determined zone of
    reasonableness—10.57 percent. Opinion No. 531-B, 150
    FERC ¶ 61,165 at PP 8, 33, 55; Opinion No. 531-A, 149 FERC
    ¶ 61,032 at PP 1, 10; Opinion No. 531, 147 FERC ¶ 61,234 at
    PP 9–10, 142, 151–52.
    In addressing Transmission Owners’ argument that section
    206 requires an initial finding that the existing rate is unjust and
    unreasonable before FERC can set a new rate, the Commission
    stated that its analysis showing that the base ROE was 10.57
    percent demonstrated “both that the[] existing 11.14 percent
    10
    ROE [was] unjust and unreasonable and that 10.57 percent is
    the . . . just and reasonable replacement base ROE.” Opinion
    No. 531-B, 150 FERC ¶ 61,165 at P 33. More generally, FERC
    held that “both of the burdens of proof under FPA section 206
    can be satisfied using a single ROE analysis—one that
    generates an ROE that both is below the existing ROE (thus
    demonstrating that the existing ROE is excessive) and that also
    is a just and reasonable ROE (thus demonstrating what the new
    ROE should be) . . . .” 
    Id. at P
    32; see also 
    id. (“[S]howing the
    existing base ROE established in the prior case is unjust and
    unreasonable merely requires showing that the Commission’s
    ROE methodology now produces a numerical value below the
    existing numerical value.”).
    It is undisputed that Customers sought only to challenge
    Transmission Owners’ base ROE, and not their previously
    approved ROE incentives. But because the newly determined
    zone of reasonableness reduced the upper end of the zone from
    13.1 percent to 11.74 percent, FERC reminded Transmission
    Owners that their total ROE—base ROE plus any incentives—
    must remain within the zone of reasonableness. Opinion No.
    531, 147 FERC ¶ 61,234 at PP 164–65. Transmission Owners
    asserted that they were not given adequate notice that the
    incentives would be at issue and argued that FERC’s decision
    to cap the previously approved incentives therefore did not
    come within section 206 and violated the Due Process Clause
    and the Administrative Procedure Act. See 16 U.S.C. § 824e(a)
    (stating that complaint must “state the change or changes to be
    made in the rate . . . then in force, and the reasons for any
    proposed change or changes therein”); Pub. Serv. Comm’n of
    Ky. v. FERC, 
    397 F.3d 1004
    , 1012–13 (D.C. Cir. 2005)
    (explaining that FERC must provide parties with adequate
    notice of the issues to be decided). On rehearing, FERC
    countered that it had not “change[d]” Transmission Owners’
    incentives, and thus “the issue of whether to reduce an
    11
    incentive . . . that would otherwise exceed the top of the zone
    of reasonableness d[id] not present any issue of material fact
    that would be appropriate for consideration in a hearing.”
    Opinion No. 531-B, 150 FERC ¶ 61,165 at PP 139–41. FERC
    stated that it was merely following its well-established policy
    that a utility’s total ROE—including any incentives—is
    “capped” at the upper end of the zone of reasonableness. See
    id.; see also Promoting Transmission Inv. Through Pricing
    Reform, 116 FERC ¶ 61,057 at PP 2, 93 (noting that “the
    approved ROE, including the impact of an incentive,” must be
    within the zone of reasonableness). Accordingly, FERC held
    that Transmission Owners’ total ROE, including any
    incentives, “would be capped at the upper end of the . . .
    DCF-determined zone of reasonableness,” meaning that
    Transmission Owners would not be permitted to “fully
    implement” their incentives “due to changes in the zone of
    reasonableness . . . .” Opinion No. 531-B, 150 FERC ¶ 61,165
    at P 139.
    Transmission Owners and Customers each filed petitions
    for review. We have jurisdiction pursuant to 16 U.S.C.
    § 825l(b).
    II.
    The FPA allows public utilities to collect “just and
    reasonable” rates for the transmission or sale of electric energy.
    16 U.S.C. §§ 824d(a), 824e(a); see also Morgan Stanley
    Capital Grp., Inc. v. Pub. Util. Dist. No. 1 of Snohomish Cty.,
    
    554 U.S. 527
    , 531 (2008). Because FERC oversees all prices
    for interstate electricity transactions, FERC v. Elec. Power
    Supply Ass’n, 
    136 S. Ct. 760
    , 767 (2016), it must ensure that
    rates charged by utilities are just and reasonable, Pub. Serv.
    Comm’n of 
    Ky., 397 F.3d at 1006
    ; Towns of Concord,
    Norwood, & Wellesley v. FERC, 
    955 F.2d 67
    , 68 (D.C. Cir.
    12
    1992). As we have stated, “FERC, not the Judiciary, has the
    principal statutory role in determining the reasonableness of
    rates . . . .” Blumenthal v. FERC, 
    613 F.3d 1142
    , 1147 (D.C.
    Cir. 2010). The Natural Gas Act (“NGA”) also employs the
    “just and reasonable” standard, see 15 U.S.C. §§ 717c(a),
    717d(a); therefore, judicial interpretations of the FPA and the
    NGA may be followed interchangeably. Ark. La. Gas Co. v.
    Hall, 
    453 U.S. 571
    , 577 n.7 (1981); City of Anaheim v. FERC,
    
    558 F.3d 521
    , 523 n.2 (D.C. Cir. 2009).
    “Statutory reasonableness is an abstract quality” that
    “allows a substantial spread between what is unreasonable
    because too low and what is unreasonable because too high.”
    FPC v. Conway Corp., 
    426 U.S. 271
    , 278 (1976) (quoting
    Montana-Dakota Util. Co. v. Nw. Pub. Serv. Co., 
    341 U.S. 246
    ,
    251 (1951)). The FPA’s just-and-reasonable requirement “is
    obviously incapable of precise judicial definition . . . .”
    Morgan 
    Stanley, 554 U.S. at 532
    . Thus, FERC’s responsibility
    is to “reduce the abstract concept of reasonableness to concrete
    expression in dollars and cents,” and it is the rate eventually set
    by the Commission “that governs the rights of buyer and
    seller.” 
    Montana-Dakota, 341 U.S. at 251
    . FERC is not
    required “to adopt as just and reasonable any particular rate
    level,” In re Permian Basin Area Rate Cases, 
    390 U.S. 747
    ,
    767 (1968), and it “has discretion regarding the methodology
    by which it determines whether a rate is just and reasonable,”
    S. Cal. Edison Co. v. FERC, 
    717 F.3d 177
    , 182 (D.C. Cir. 2013)
    (citing FPC v. Hope Nat. Gas Co., 
    320 U.S. 591
    , 602 (1944));
    see also S.C. Pub. Serv. Auth. v. FERC, 
    762 F.3d 41
    , 55 (D.C.
    Cir. 2014) (stating that FERC has “considerable latitude in
    developing a methodology responsive to its regulatory
    challenge” (citations and internal quotation marks omitted)).
    At issue in this proceeding is FERC’s determination of a
    just and reasonable ROE. An ROE is “the cost to the utility of
    13
    raising capital.” Canadian Ass’n of Petroleum Producers v.
    FERC, 
    254 F.3d 289
    , 293 (D.C. Cir. 2001). To attract
    investors, a utility must offer a sufficient “risk-adjusted
    expected ROE.” S. Cal. 
    Edison, 717 F.3d at 179
    (citation
    omitted). An ROE “should be commensurate with returns on
    investments in other enterprises having corresponding risks”
    and “sufficient to assure confidence in the financial integrity of
    the enterprise, so as to maintain its credit and to attract capital.”
    Hope Nat. 
    Gas, 320 U.S. at 603
    ; see also Bluefield Waterworks
    & Improvement 
    Co., 262 U.S. at 692
    –93. Otherwise put, an
    ROE should allow a utility “to adequately compete for the
    investor’s dollar.” See Anaheim v. FERC, 
    669 F.2d 799
    , 801,
    803 (D.C. Cir. 1981).
    Because “[r]atemaking . . . is not a science,” however,
    FERC must use models “to inform, not rigidly to determine,
    [its] judgment” as to an appropriate ROE for a utility. Boston
    Edison Co. v. FERC, 
    885 F.2d 962
    , 969–70 (1st Cir. 1989).
    One model FERC employs to determine a utility’s ROE is the
    discounted cash flow, or DCF, analysis. See United Airlines,
    Inc. v. FERC, 
    827 F.3d 122
    , 128 (D.C. Cir. 2016); S. Cal.
    
    Edison, 717 F.3d at 179
    . This model “projects investor growth
    expectations over the long term by adding average dividend
    yields to estimated constant growth in dividends over the
    indefinite future.” Williston Basin Interstate Pipeline Co. v.
    FERC, 
    165 F.3d 54
    , 57 (D.C. Cir. 1999); see also Town of
    Norwood v. FERC, 
    80 F.3d 526
    , 533 (D.C. Cir. 1996). “The
    Discounted Cash Flow model flows from the classical
    valuation theory that the value of a financial asset is determined
    by its ability to generate future cash flows.” Tenn. Gas
    Pipeline Co. v. FERC, 
    926 F.2d 1206
    , 1208 n.2 (D.C. Cir.
    1991) (citation, internal quotation marks, and ellipsis omitted);
    see also United 
    Airlines, 827 F.3d at 128
    .
    14
    To calculate the ROE for a utility that is not publicly
    traded, FERC relies on the ROEs for a “proxy group” of
    comparable publicly traded companies. S. Cal. 
    Edison, 717 F.3d at 179
    ; Williston 
    Basin, 165 F.3d at 57
    . After adjusting
    that range of ROEs to exclude unrepresentative high or low
    rates, “the Commission assembles a zone of reasonable ROEs
    on which to base a utility’s ROE.” S. Cal. 
    Edison, 717 F.3d at 179
    (citations omitted); see also Canadian Ass’n of Petroleum
    Producers v. FERC, 
    308 F.3d 11
    , 12–13 (D.C. Cir. 2002);
    Williston 
    Basin, 165 F.3d at 57
    . The zone of reasonableness is
    intended to balance the interests of investors and consumers,
    Pac. Gas & Elec. Co. v. FERC, 
    306 F.3d 1112
    , 1116 (D.C. Cir.
    2002), and typically results in a broad range of potentially
    reasonable ROEs, see Panhandle E. Pipe Line Co. v. FERC,
    
    777 F.2d 739
    , 746–47 (D.C. Cir. 1985). After assembling this
    zone of reasonableness, FERC assesses the utility’s
    circumstances to determine whether to make “pragmatic
    adjustment[s]” to the rate. Canadian 
    Ass’n, 308 F.3d at 15
    (quoting Tenn. Gas 
    Pipeline, 926 F.2d at 1209
    ); see also
    Williston 
    Basin, 165 F.3d at 57
    (stating that the assigned rate
    “reflect[s] specific investment risks associated with th[e]
    [utility]”).
    FERC’s adjudication of just and reasonable ROEs is
    governed by “[t]wo related but distinct sections of the” FPA.
    FirstEnergy Serv. Co. v. FERC, 
    758 F.3d 346
    , 348 (D.C. Cir.
    2014). Section 205, 16 U.S.C. § 824d, “confers upon FERC
    the duty to ensure that wholesale energy rates and services are
    just and reasonable” by requiring “regulated utilities to file
    with the Commission tariffs outlining their rates for FERC’s
    approval.” 
    FirstEnergy, 758 F.3d at 348
    (citing 16 U.S.C.
    § 824d(a), (c)). In a section 205 proceeding, the utility is not
    required to show that a previous rate was unlawful. See Ala.
    Power Co. v. FERC, 
    993 F.2d 1557
    , 1571 (D.C. Cir. 1993).
    15
    However, in this case we review FERC’s determination
    under section 206, not 205. Section 206 permits, indeed
    requires, FERC to determine whether an existing rate is
    “unjust, unreasonable, unduly discriminatory or preferential
    . . . . ” 16 U.S.C. § 824e(a). Only after having made the
    determination that the utility’s existing rate fails that test may
    FERC exercise its section 206 authority to impose a new rate.
    See, e.g., Atl. City Elec. Co. v. FERC, 
    295 F.3d 1
    , 10 (D.C. Cir.
    2002); Cities of Bethany v. FERC, 
    727 F.2d 1131
    , 1143 (D.C.
    Cir. 1984). The burden of demonstrating that the existing ROE
    is unlawful is on FERC or the complainant, not the utility. 16
    U.S.C. § 824e(b); 
    FirstEnergy, 758 F.3d at 353
    .
    III.
    We review FERC’s ratemaking orders under the
    Administrative Procedure Act’s arbitrary and capricious
    standard. FERC v. Elec. Power Supply Ass’n, 
    136 S. Ct. 760
    ,
    782 (2016). The scope of our review is “narrow.” 
    Id. (quoting Motor
    Vehicle Mfrs. Ass’n of U.S., Inc. v. State Farm Mut.
    Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983)). We must uphold
    FERC’s orders unless they are “arbitrary, capricious, an abuse
    of discretion, or otherwise not in accordance with law.” S.C.
    Pub. Serv. Auth. v. FERC, 
    762 F.3d 41
    , 54 (D.C. Cir. 2014)
    (citing Midwest ISO Transmission Owners v. FERC, 
    373 F.3d 1361
    , 1368 (D.C. Cir. 2004)). “[W]e may not substitute our
    own judgment for that of the Commission,” and we do not ask
    whether FERC’s “decision is the best one possible or even
    whether it is better than the alternatives.” Elec. Power, 136 S.
    Ct. at 782. Instead, “[o]ur role . . . is to [ensure] that the
    Commission’s judgment is supported by substantial evidence
    and that the methodology used in arriving at that judgment is
    either consistent with past practice or adequately justified.”
    Town of 
    Norwood, 80 F.3d at 533
    (citations and internal
    16
    quotation marks omitted); see also S.C. Pub. Serv. 
    Auth., 762 F.3d at 54
    .
    We are mindful that Congress entrusted the regulation of
    electric energy rates to FERC, not the courts. Elec. 
    Power, 136 S. Ct. at 784
    ; Blumenthal v. FERC, 
    552 F.3d 875
    , 884 (D.C.
    Cir. 2009). Moreover, because “[t]he statutory requirement
    that rates be ‘just and reasonable’ is obviously incapable of
    precise judicial definition, . . . we afford great deference to the
    Commission in its rate decisions.” Morgan 
    Stanley, 554 U.S. at 532
    . Our review in ratemaking cases is therefore “limited to
    ensuring that the Commission has made a principled and
    reasoned decision supported by the evidentiary record.” S. Cal.
    
    Edison, 717 F.3d at 181
    (citation omitted). Despite our highly
    deferential standard of review, it bears repeating that “courts
    have never given regulators carte blanche.” Elec. Consumers
    Res. Council v. FERC, 
    747 F.2d 1511
    , 1514 (D.C. Cir. 1984)
    (citation omitted).
    We apply this deferential standard in evaluating the issues
    raised in the petitions before us. First, Transmission Owners
    contend that FERC failed to satisfy its burden under section
    206 of demonstrating that the existing 11.14 percent base ROE,
    which was within FERC’s newly determined zone of
    reasonableness, was unjust and unreasonable.             Second,
    Transmission Owners challenge the impact of FERC’s decision
    to set a new base ROE on their previously approved ROE
    incentives. Customers argue that FERC acted arbitrarily and
    capriciously in placing Transmission Owners’ base ROE at the
    midpoint of the upper half of the newly determined zone of
    reasonableness. We address Transmission Owners’ petition
    first.
    17
    “Unjust and Unreasonable” Determination
    Transmission Owners argue that FERC failed to follow the
    two-step procedure mandated by section 206 when it changed
    their base ROE. Specifically, Transmission Owners contend
    that, rather than first finding that their existing base ROE was
    unjust and unreasonable, FERC began by determining that
    10.57 percent would be a just and reasonable base ROE and
    only then found the existing 11.14 percent ROE to be unlawful
    because it was not equivalent to 10.57 percent. FERC does not
    actually challenge Transmission Owners’ description of its
    process. Rather, it argues that its determination of a new just
    and reasonable base ROE was “sufficient” by itself to prove
    that the existing base ROE was unjust and unreasonable. See
    Resp’t Br. 28–29. We conclude that FERC did not meet the
    first requirement of section 206 that it demonstrate the
    unlawfulness of Transmission Owners’ base ROE.
    We begin our analysis by clarifying what is not required
    of FERC. Transmission Owners, relying on dictum from City
    of Winnfield v. FERC, 
    744 F.2d 871
    (D.C. Cir. 1984), argue
    that FERC must show that an existing rate is “entirely outside
    the zone of reasonableness” before it can exercise its section
    206 authority to change that rate. 
    Id. at 875;
    see also Tex. E.
    Transmission Corp., 32 FERC ¶ 61,056 at 61,150 (1985). The
    crux of Transmission Owners’ argument appears to be that in a
    section 206 proceeding, the established zone of reasonableness
    is “coextensive” with the statutory just-and-reasonableness
    standard, and therefore, FERC must accept as just and
    reasonable all ROEs within the discounted cash flow zone of
    reasonableness. FERC rejected that argument and so do we.
    The zone of reasonableness informs FERC’s selection of a
    just and reasonable rate. See S. Cal. 
    Edison, 717 F.3d at 179
    ;
    Williston 
    Basin, 165 F.3d at 57
    ; Boston 
    Edison, 885 F.2d at 18
    969–70. But the zone of reasonableness represents a “broad”
    range of potentially just and reasonable ROEs, “not an exact
    dollar figure . . . .” Panhandle E. Pipe Line 
    Co., 777 F.2d at 746
    ; see also 
    Conway, 426 U.S. at 278
    ; Permian 
    Basin, 390 U.S. at 770
    . As long as the rate selected by the Commission is
    within the zone of reasonableness, FERC is not required “to
    adopt as just and reasonable any particular rate level.” Permian
    
    Basin, 390 U.S. at 767
    . Whether a particular rate within the
    zone is the just and reasonable rate for the utility at issue
    depends on a number of factors. See, e.g., Canadian 
    Ass’n, 308 F.3d at 15
    . Thus, the fact that a rate falls within the zone of
    reasonableness does not establish that the rate is the just and
    reasonable rate for the utility at issue.
    To support their claim that FERC lacks the authority under
    section 206 to reduce a base ROE that falls within the zone of
    reasonableness, Transmission Owners rely upon cases that
    explain the boundaries for courts reviewing FERC’s
    ratemaking decisions. But these cases do not address the
    showing necessary under section 206 to find that an existing
    rate is unjust and unreasonable. In Montana-Dakota Utilities
    Co. v. Northwestern Public Service Co., 
    341 U.S. 246
    (1951),
    for example, the Supreme Court explained that, because
    statutory reasonableness “allows a substantial spread” of
    potentially reasonable rates, a court has no authority to fix a
    rate different from the one chosen by FERC “on the ground
    that, in its opinion, it is the only or the more reasonable one.”
    See 
    id. at 250–52.
    As we have held, “[a]bsent procedural or
    methodological flaws, the court may only set aside a rate that
    is outside a zone of reasonableness . . . .” Pac. Gas & 
    Elec., 306 F.3d at 1116
    .
    Conversely, although courts afford deference to FERC’s
    ratemaking decisions, a reviewing court must set aside any rate,
    even one within the zone of reasonableness, if FERC’s
    19
    procedure or methodology was flawed. See 
    id. While we
    have
    recognized FERC’s discretion in ratemaking cases, we have
    stated that “in all cases, the Commission must explain its
    reasoning when it purports to approve rates as just and
    reasonable.” TransCanada Power Mktg. Ltd. v. FERC, 
    811 F.3d 1
    , 12 (D.C. Cir. 2015). Whether a rate, even one within
    the zone of reasonableness, is unlawful depends on the
    particular circumstances of the case. As the Supreme Court has
    held, “one rate in its relation to another rate may be
    discriminatory, although each rate [p]er se, if considered
    independently, might fall within the zone of reasonableness.”
    
    Conway, 426 U.S. at 278
    (citation omitted). FERC itself
    recognizes the limits of its discretion.           In Bangor
    Hydro-Electric Co., for example, the Commission stated that
    “[c]ertain rates, though within the zone, may not be just and
    reasonable given the circumstances of the case.” 122 FERC
    ¶ 61,038 at P 11. Neither the language of the FPA nor our
    precedents compel FERC to accept all rates within the
    discounted cash flow zone of reasonableness as just and
    reasonable in a section 206 proceeding.
    The FPA, by requiring FERC to show that an existing rate
    is unlawful before ordering a new rate under section 206,
    provides a form of “statutory protection” to a utility. City of
    
    Winnfield, 744 F.2d at 875
    . Thus, while showing that the
    existing rate is entirely outside the zone of reasonableness may
    illustrate that the existing rate is unlawful, see, e.g., Pub. Serv.
    Comm’n of N.Y. v. FERC, 
    642 F.2d 1335
    , 1350 n.27 (D.C. Cir.
    1980), that is not the only way in which FERC can satisfy its
    burden under section 206. As the parties agree, section 206
    required FERC to make an explicit finding that Transmission
    Owners’ existing rate was unjust and unreasonable before
    proceeding to set a new rate. See Opinion No. 531-B, 150
    FERC ¶ 61,165 at P 33; Opinion No. 531, 147 FERC ¶ 61,234
    at P 50. FERC failed to make such a finding in this case.
    20
    FERC misunderstood and misapplied its dual burden
    under section 206. Sections 205 and 206 are “related but
    distinct” provisions of the FPA. 
    FirstEnergy, 758 F.3d at 348
    .
    The purpose of section 206 is “quite different” from that of
    section 205. City of 
    Winnfield, 744 F.2d at 875
    . Section 205
    enables a utility to propose changes in its own rates. Section
    206 empowers FERC to modify existing rates upon complaint
    or on FERC’s own initiative. 
    FirstEnergy, 758 F.3d at 348
    –
    49. In contrast to section 206, section 205 “is intended for the
    benefit of the utility,” City of 
    Winnfield, 744 F.2d at 875
    , and
    “FERC plays ‘an essentially passive and reactive’ role under
    section 205,” Atl. City 
    Elec., 295 F.3d at 10
    (quoting City of
    
    Winnfield, 744 F.2d at 876
    )). Section 206’s procedures are
    “entirely different” and “stricter” than those of section 205.
    City of 
    Anaheim, 558 F.3d at 525
    .
    One “important difference[]” between section 205 and
    section 206 is the burden of proof, Ala. 
    Power, 993 F.2d at 1571
    , a difference that FERC failed to recognize in this case.
    A utility filing a rate adjustment under section 205 must show
    that the adjustment is lawful. 
    Id. The proponent
    of a rate
    change under section 206, however, bears “the burden of
    proving that the existing rate is unlawful.” 
    Id. (emphasis added)
    (citations omitted); see also Papago Tribal Util. Auth.
    v. FERC, 
    723 F.2d 950
    , 952–53 (D.C. Cir. 1983); N.J. Bd. of
    Pub. Utils. v. FERC, 
    744 F.3d 74
    , 94–95 (3d Cir. 2014).
    Therefore, unlike section 205, section 206 mandates a two-step
    procedure that requires FERC to make an explicit finding that
    the existing rate is unlawful before setting a new rate.
    As “a ‘creature of statute,’” FERC has only those powers
    endowed upon it by statute. Atl. City 
    Elec., 295 F.3d at 8
    . We
    presume that, in a statute, Congress meant what it said and said
    what it meant. See Simmons v. Himmelreich, 
    136 S. Ct. 1843
    ,
    21
    1848 (2016); Va. Dep’t of Med. Assistance Servs. v. Dep’t of
    Health & Human Servs., 
    678 F.3d 918
    , 922–23 (D.C. Cir.
    2012). Section 206 grants FERC the authority to change an
    existing rate “[w]henever the Commission . . . shall find that
    [the] rate . . . is unjust[] [or] unreasonable . . . .” 16 U.S.C.
    § 824e(a). FERC has “undoubted power under section 206” to
    change an existing rate “whenever it determines such rate[] to
    be unlawful.” FPC v. Sierra Pac. Power Co., 
    350 U.S. 348
    ,
    353 (1956) (emphasis added). In section 206, Congress
    specified that “FERC itself may establish the just and
    reasonable rate, provided that it first determines that a rate set
    by a public utility is unjust[] [or] unreasonable . . . .” Cities of
    
    Bethany, 727 F.2d at 1143
    (emphasis added). “[T]he directive
    to impose a just and reasonable rate . . . is triggered only by the
    Commission’s finding that the existing one is ‘unjust[] [or]
    unreasonable . . . .’” Am. Gas Ass’n v. FERC, 
    912 F.2d 1496
    ,
    1504 (D.C. Cir. 1990) (emphasis added) (quoting 15 U.S.C.
    § 717d(a)).
    In other words, a finding that an existing rate is unjust and
    unreasonable is the “condition precedent” to FERC’s exercise
    of its section 206 authority to change that rate. Sierra Pac.
    
    Power, 350 U.S. at 353
    . Section 206 therefore imposes a “dual
    burden” on FERC. 
    FirstEnergy, 758 F.3d at 353
    . Without a
    showing that the existing rate is unlawful, FERC has no
    authority to impose a new rate. See Fla. Gas Transmission Co.
    v. FERC, 
    604 F.3d 636
    , 640–41 (D.C. Cir. 2010) (examining
    similar requirement under the NGA); Sea Robin Pipeline Co.
    v. FERC, 
    795 F.2d 182
    , 187 (D.C. Cir. 1986) (same). Thus,
    while “[t]he ‘just and reasonable’ lodestar is no loftier under
    section 206 than under section 205,” 
    FirstEnergy, 758 F.3d at 353
    , the showing required of FERC to exercise its section 206
    authority to change an existing rate is different from anything
    required for FERC to approve a utility’s proposed rate
    adjustment under section 205.
    22
    FERC recognized its dual burden in this section 206
    proceeding. See Opinion No. 531-B, 150 FERC ¶ 61,165 at PP
    28–29; Opinion No. 531, 147 FERC ¶ 61,234 at P 50. But in
    reaching its decision, FERC rejected Transmission Owners’
    argument that the burden under section 206’s first step was
    “very different from and more difficult to satisfy” than the
    showing required under both section 206’s second step and
    section 205:
    In making these arguments, [Transmission
    Owners] are confusing differences in who bears
    the burden of persuasion as between FPA
    sections 205 and 206 with the substantive “just
    and reasonable” standard contained in both
    those sections. . . . While the party bearing the
    burden of persuasion is different under FPA
    section 205 and FPA section 206, the scope and
    purpose of the Commission’s review remains
    the same — to determine whether the rate fixed
    by the utility is lawful.
    ****
    Because sections 205 and 206 are part of a
    single statutory scheme, it follows that a rate
    that is lawful under one section must also be
    lawful under the other and a rate that is unlawful
    under one section must also be unlawful under
    the other. For this to be true, the substantive
    standard to determine lawfulness under each
    section — the just and reasonable standard —
    must be applied in the same manner under each
    section.
    23
    Opinion No. 531-B, 150 FERC ¶ 61,165 at PP 28–30 (citation,
    internal quotation marks, and alteration omitted). FERC held
    that it could satisfy its dual burden through “a single ROE
    analysis . . . that generates an ROE that both is below the
    existing ROE (thus demonstrating that the existing ROE is
    excessive) and that also is a just and reasonable ROE (thus
    demonstrating what the new ROE should be) . . . .” 
    Id. at P
    32.
    FERC thus concluded that its single ROE analysis showing that
    10.57 percent was a just and reasonable ROE for Transmission
    Owners satisfied “both burdens under section 206.” 
    Id. at P
    33.
    In determining that its “single ROE analysis” satisfied
    both of its burdens, FERC relied on the general principle that it
    is the Commission’s duty to translate the “abstract concept” of
    reasonableness into a “concrete rate,” and it is that rate—“not
    the abstract concept”—that governs the rights of the utility and
    the consumers. 
    Id. at P
    32 & n.65 (citing 
    Montana-Dakota, 341 U.S. at 251
    ). Based on this reasoning, FERC asserted that
    “only the single point approved by the Commission within the
    DCF zone of reasonableness is the just and reasonable base
    ROE.” 
    Id. at P
    32. FERC went on to hold:
    It follows that showing the existing base ROE
    established in the prior case is unjust and
    unreasonable merely requires showing that the
    Commission’s ROE methodology now
    produces a numerical value below the existing
    numerical value.
    ****
    [T]he statute requires that, under section 206,
    before we may change an ROE we must find it
    unjust and unreasonable. And, in Opinion No.
    531, that we did. Our ROE analysis showing
    24
    that the [Transmission Owners’] base ROE is
    10.57 percent demonstrates both that their
    existing 11.14 percent ROE is unjust and
    unreasonable and that 10.57 percent is the
    [Transmission Owners’] just and reasonable
    replacement base ROE. Thus, we met both
    burdens under section 206.
    
    Id. at PP
    32, 33; see also Opinion No. 531-A, 149 FERC
    ¶ 61,032 at P 10 (concluding that existing rate was unlawful
    based on finding that 10.57 percent was a just and reasonable
    rate).
    FERC’s decision—that a single ROE analysis generating
    a new just and reasonable ROE necessarily proved that
    Transmission Owners’ existing ROE was unjust and
    unreasonable—relied on its assumption that all ROEs other
    than the one FERC identifies as the utility’s just and reasonable
    ROE are per se unlawful in a section 206 proceeding. See
    Opinion No. 531-B, 150 FERC ¶ 61,165 at P 33. But, as we
    have explained, the zone of reasonableness creates a broad
    range of potentially lawful ROEs rather than a single just and
    reasonable ROE, meaning that FERC’s finding that 10.57
    percent was a just and reasonable ROE, standing alone, “did
    not amount to a finding that every other rate of return was not.”
    See 
    Papago, 723 F.2d at 957
    ; see also 
    Conway, 426 U.S. at 277
    –79. Because it was a section 206 proceeding, rather than
    a section 205 proceeding, FERC bore the burden of making an
    explicit finding that the existing ROE was unlawful before it
    was authorized to set a new lawful ROE. See, e.g., Atl. City
    
    Elec., 295 F.3d at 9
    –10; Ala. 
    Power, 993 F.2d at 1571
    .
    FERC, however, never actually explained how the existing
    ROE was unjust and unreasonable. FERC correctly noted that
    rates within the zone of reasonableness are not per se just and
    25
    reasonable, depending upon “the circumstances of the case.”
    Opinion No. 531-B, 150 FERC ¶ 61,165 at P 25. But FERC
    “made no effort” to explain what circumstances rendered
    Transmission Owners’ existing rate unlawful. See W. Res., Inc.
    v. FERC, 
    9 F.3d 1568
    , 1580 (D.C. Cir. 1993). Instead, FERC
    concluded that the existing 11.14 percent base ROE was
    unlawful solely because it had determined that 10.57 percent,
    which was “a numerical value below the existing numerical
    value,” was a just and reasonable base ROE. Opinion No.
    531-B, 150 FERC ¶ 61,165 at P 32. That conclusion, without
    any further explanation, is insufficient to prove that
    Transmission Owners’ existing base ROE was unlawful. See
    
    Papago, 723 F.2d at 956
    –58. Further, the mere fact that FERC
    eventually reduces the zone of reasonableness to a single ROE
    does not relieve the Commission of its burden under section
    206. Without the requisite findings, FERC’s reasoning in this
    case effectively eliminated section 206’s statutory directive
    that existing rates be found unlawful before FERC has the
    authority to change those rates.
    To satisfy its dual burden under section 206, FERC was
    required to do more than show that its single ROE analysis
    generated a new just and reasonable ROE and conclusively
    declare that, consequently, the existing ROE was per se unjust
    and unreasonable. Although we defer to FERC’s expertise in
    ratemaking cases, the Commission’s decision must actually be
    the result of reasoned decision-making to receive that
    deference. Without further explanation, a bare conclusion that
    an existing rate is “unjust and unreasonable” is nothing more
    than “a talismanic phrase that does not advance reasoned
    decision making.” See 
    TransCanada, 811 F.3d at 12
    –13.
    Because FERC’s single ROE analysis failed to include an
    actual finding as to the lawfulness of Transmission Owners’
    existing base ROE, FERC acted arbitrarily and outside of its
    statutory authority in setting a new base ROE for Transmission
    26
    Owners. In light of FERC’s failure to satisfy its dual burden
    under section 206, we need not reach Transmission Owners’
    arguments concerning their previously approved ROE
    incentives.
    Placement of the Base ROE within the Zone of
    Reasonableness
    Customers’ petition is also well taken. After performing
    its analysis, FERC abandoned its traditional use of the midpoint
    of the zone of reasonableness in setting Transmission Owners’
    base ROE. Instead, FERC picked the midpoint of the upper
    half of the zone of reasonableness as the new base ROE.
    FERC, however, did not set forth a rational connection between
    the record evidence and its placement of the base ROE.
    FERC has discretion to make “pragmatic adjustments” to
    a utility’s ROE based on the “particular circumstances” of a
    case. FPC v. Nat. Gas Pipeline Co., 
    315 U.S. 575
    , 586 (1942);
    see also Canadian 
    Ass’n, 308 F.3d at 15
    ; Town of 
    Norwood, 80 F.3d at 534
    –35. But, this discretion must be exercised “within
    the ambit of [FERC’s] statutory authority.” Nat. Gas 
    Pipeline, 315 U.S. at 586
    . “Although it is not our role to tell the
    Commission what the ‘correct’ rate of return calculation is, . . .
    we do have an obligation to remand when the Commission’s
    conclusions are contrary to substantial evidence or not the
    product of reasoned decisionmaking . . . .” Pub. Serv. Comm’n
    of N.Y. v. FERC, 
    813 F.2d 448
    , 465 (D.C. Cir. 1987) (citations
    omitted). In determining whether FERC’s ROE decision is just
    and reasonable, we examine “the method employed in reaching
    that result.” City of Charlottesville v. FERC, 
    661 F.2d 945
    , 950
    (D.C. Cir. 1981) (citing Permian 
    Basin, 390 U.S. at 791
    –92).
    In this case, the zone of reasonableness was 7.03 percent
    to 11.74 percent. FERC typically sets a utility’s base ROE at
    27
    the midpoint of the zone of reasonableness—in this case, 9.39
    percent. Opinion No 531-B, 150 FERC ¶ 61,165 at P 36. We
    have noted that the midpoint is a good “starting place” for the
    placement of the ROE. See Tenn. Gas 
    Pipeline, 926 F.2d at 1213
    ; see also Pub. Serv. Comm’n of 
    Ky., 397 F.3d at 1010
    –
    11. As we explained above, however, FERC may make
    adjustments to a utility’s ROE based on the specific
    circumstances of the case. See, e.g., Nat. Gas 
    Pipeline, 315 U.S. at 586
    .
    After FERC performed its discounted cash flow analysis,
    it concluded that “unique” and “anomalous” capital market
    conditions undermined the reliability of the results of that
    analysis in setting Transmission Owners’ new base ROE.
    Opinion No. 531, 147 FERC ¶ 61,234 at PP 142, 145, 150;
    Opinion No. 531-B, 150 FERC ¶ 61,165 at PP 49–50. FERC
    determined that, because of the presence of “unusual capital
    market conditions,” it had “less confidence” that “a mechanical
    application” of the midpoint of the DCF zone of reasonableness
    would result in an ROE that satisfied the Hope and Bluefield
    capital attraction standards. See Opinion No. 531, 147 FERC
    ¶ 61,234 at PP 142, 145; Opinion No. 531-B, 150 FERC
    ¶ 61,165 at PP 49, 56.
    Because of its lack of confidence in the reliability of its
    analysis, FERC turned to “alternative benchmark
    methodologies” and “additional record evidence” to inform its
    placement of the base ROE. Opinion No. 531-B, 150 FERC
    ¶ 61,165 at P 36-37. Although FERC concluded that these
    analyses supported a finding that a 9.39 percent ROE was too
    low to satisfy the Hope and Bluefield standards, see Opinion
    No. 531, 147 FERC ¶ 61,234 at PP 146–50, 152; Opinion No.
    531-B, 150 FERC ¶ 61,165 at P 37, none of the analyses
    necessarily suggested that a 10.57 percent ROE was a just and
    reasonable base ROE. Thus, the only conclusion FERC drew
    28
    from these analyses was that Transmission Owners were
    entitled to an ROE somewhere above the 9.39 percent midpoint
    of the zone of reasonableness. See Opinion No. 531, 147 FERC
    ¶ 61,234 at PP 146–50; Opinion No. 531-B, 150 FERC
    ¶ 61,165 at PP 37, 49, 101 n.213, 128.
    But FERC still needed to settle on a new base ROE for
    Transmission Owners. Noting that it “has traditionally looked
    to the central tendency” in identifying an appropriate ROE,
    FERC selected the midpoint of the upper half of the zone of
    reasonableness—in this case, 10.57 percent—which it had
    done “in the past.” Opinion No. 531, 147 FERC ¶ 61,234 at
    PP 151–52. Notably, this 10.57 percent base ROE was higher
    than 35 of the 38 data points FERC used to construct its DCF
    zone of reasonableness. In reaching its decision, FERC failed
    to explain how any evidence demonstrated that 10.57 percent
    was a just and reasonable base ROE for Transmission Owners.
    This omission is particularly troublesome in light of FERC’s
    prior concerns over the reliability of its newly determined zone
    of reasonableness. We therefore conclude that in placing the
    base ROE within the zone of reasonableness, FERC failed to
    establish a “rational connection” between the record evidence
    and its decision. Elec. 
    Power, 136 S. Ct. at 782
    (citation
    omitted).
    As an initial matter, FERC concluded that the evidence
    supported a finding that 9.39 percent was too low of a rate to
    satisfy the Hope and Bluefield capital attraction standards. See
    Opinion No. 531, 147 FERC ¶ 61,234 at PP 142, 145, 150;
    Opinion No. 531-B, 150 FERC ¶ 61,165 at PP 7, 49–50. But
    it never found that its chosen rate, 10.57 percent, actually
    satisfied those standards. Similarly, although FERC noted that
    a decrease from 11.14 percent (the existing base ROE) to 9.39
    percent (the midpoint of the newly determined zone of
    reasonableness) could “undermine” Transmission Owners’
    29
    ability to attract capital investments, Opinion No. 531, 147
    FERC ¶ 61,234 at P 150, it never explained how its ultimate
    placement of the base ROE at 10.57 percent was appropriate.
    Moreover, FERC never explained how 10.57 percent was
    just and reasonable when the alternative benchmarks and
    additional record evidence it used to justify a departure merely
    pointed to a base ROE somewhere above 9.39 percent. When
    making adjustments in setting a utility’s base ROE, FERC must
    adequately explain how the evidence it relied on “support[ed]
    the conclusion it reached.” Wis. Gas Co. v. FERC, 
    770 F.2d 1144
    , 1156 (D.C. Cir. 1985) (citation omitted); see also Tenn.
    Gas 
    Pipeline, 926 F.2d at 1209
    , 1212–13. In this case, FERC
    stressed that it used the alternative analyses only “to inform the
    just and reasonable placement of the ROE within the zone of
    reasonableness,” see Opinion No. 531, 147 FERC ¶ 61,234 at
    PP 145–46; Opinion No. 531-B, 150 FERC ¶ 61,154 at PP 49–
    50, and the only conclusion it reached from these alternative
    analyses was that “the ROE should . . . be set above the
    midpoint,” see Opinion No. 531-B, 150 FERC ¶ 61,165 at PP
    37, 49, 128, 101 n.213. FERC’s reasoning is unclear. On the
    one hand, it argued that the alternative analyses supported its
    decision to place the base ROE above the midpoint, but on the
    other hand, it stressed that none of these analyses were used to
    select the 10.57 percent base ROE.
    A review of the findings of the alternative analyses
    highlights the problem. FERC found the results of three of the
    alternative benchmark methodologies “informative”: the risk
    premium analysis, the CAPM analysis, and the expected
    earnings analysis. See Opinion No. 531, 147 FERC ¶ 61,234
    at P 146, Opinion No. 531-B, 150 FERC ¶ 61,165 at P 37. The
    risk premium analysis supported a base ROE between 10.7
    percent and 10.8 percent, the CAPM analysis produced a
    midpoint of 10.4 percent (with a zone of reasonableness of 7.4
    30
    percent to 13.3 percent), and the expected earnings analysis had
    a midpoint of 12.1 percent (with a zone of reasonableness of
    8.1 percent to 16.1 percent). Opinion No. 531, 147 FERC
    ¶ 61,234 at P 147. FERC never explained how these analyses
    justified a 10.57 percent base ROE, and, in fact, it stressed that
    it did not rely on those analyses in setting the base ROE. See,
    e.g., Opinion No. 531-B, 150 FERC ¶ 61,165 at PP 91, 103,
    120.        FERC also relied on evidence of state
    commission-approved ROEs, but it acknowledged that 89
    percent of the state commission-authorized ROEs were below
    its chosen rate of 10.57 percent. Opinion No. 531-B, 150
    FERC ¶ 61,165 at P 85; see also Opinion No. 531, 147 FERC
    ¶ 61,234 at P 148. Similar to the alternative benchmarks,
    FERC maintained that it did not use the state
    commission-authorized ROEs in setting Transmission Owners’
    actual base ROE. See, e.g., Opinion No. 531-B, 150 FERC
    ¶ 61,165 at P 80. FERC argues that these analyses, taken
    together, merely supported its conclusion that 9.39 percent was
    too low and that Transmission Owners’ base ROE should be
    set somewhere above the zone of reasonableness’s midpoint.
    Thus, while the alternative benchmarks and additional record
    evidence may have shown that some “upward adjustment” was
    warranted, see Opinion No. 531, 147 FERC ¶ 61,234 at 62,473
    (Norris, dissenting in part), they did not justify the specific
    placement of the base ROE at 10.57 percent.
    Finally, FERC’s explanation for selecting 10.57 percent as
    the base ROE was insufficient. Rather than citing record
    evidence demonstrating that 10.57 percent was a just and
    reasonable base ROE, FERC simply noted that it “traditionally
    looked to the central tendency” to set an ROE and then chose
    the midpoint of the upper half of the zone of reasonableness
    because it had done so “in the past.” Opinion No. 531, 147
    FERC ¶ 61,234 at PP 151–52; see also Opinion No. 531-B, 150
    FERC ¶ 61,165 at P 55.
    31
    To support its assertion that its previous decisions dictated
    a top-quarter placement for the base ROE, FERC relied on two
    prior cases, Southern California Edison Co., 92 FERC ¶ 61,070
    (2000), and Consumers Energy Co., 85 FERC ¶ 61,100 (1998).
    Opinion No. 531, 147 FERC ¶ 61,234 at P 152 n.307. But
    those cases do not support FERC’s decision. In the prior cases,
    a utility’s ROE was set at the midpoint of the upper half of the
    zone of reasonableness because the utility was “more risky”
    than the proxy group. See S. Cal. Edison, 92 FERC ¶ 61,070
    at 61,266–67; Consumers Energy, 85 FERC ¶ 61,100 at
    61,363–64.       In both Southern California Edison and
    Consumers Energy, FERC knew only that the utility at issue
    was riskier than the proxy group, meaning that the utility’s
    costs fell somewhere above the midpoint of the zone of
    reasonableness. Thus, in those cases, the midpoint of the upper
    half was “an obvious place to begin.” See Tenn. Gas 
    Pipeline, 926 F.2d at 1213
    . Conversely, FERC expressly held in this
    case that Transmission Owners were “comparable in risk” to
    the proxy group. Opinion No. 531-B, 150 FERC ¶ 61,165 at P
    47. Without more specific findings as to Transmission
    Owners’ circumstances, FERC’s precedent did not justify its
    decision in this case.
    FERC essentially chose the midpoint of the upper half of
    the zone because it determined that once it concluded that an
    upward adjustment from the midpoint of the zone of
    reasonableness was appropriate, the midpoint of the upper half
    of the zone was the only available ROE. Cf. Opinion No. 531,
    147 FERC ¶ 61,234 at P 151 n.306 (“Nothing in this order
    precludes participants in [unrelated] proceedings from
    developing a record . . . supporting a different point in the range
    of reasonable returns than the midpoint of the upper half of the
    range.” (citation omitted)). Such conclusory reasoning does
    not establish “a rational connection” between the record
    32
    evidence and FERC’s decision. See Elec. 
    Power, 136 S. Ct. at 782
    .
    We emphasize that our review is limited to ensuring that
    FERC “made a principled and reasoned decision supported by
    the evidentiary record.” S. Cal. 
    Edison, 717 F.3d at 181
    (citation omitted). It is not our job to tell FERC what the
    “correct” ROE is for Transmission Owners, but it is our duty
    to ensure that FERC’s decision is “the product of reasoned
    decisionmaking.” Pub. Serv. Comm’n of 
    N.Y., 813 F.2d at 465
    (citations omitted). While the evidence in this case may have
    supported an upward adjustment from the midpoint of the zone
    of reasonableness, FERC failed to provide any reasoned basis
    for selecting 10.57 percent as the new base ROE.
    IV.
    For the foregoing reasons, the petitions for review are
    granted. We therefore vacate FERC’s orders and remand the
    case for proceedings consistent with this opinion.
    So ordered.
    

Document Info

Docket Number: 15-1118 Consolidated with 15-1119, 15-1121

Citation Numbers: 854 F.3d 9, 2017 U.S. App. LEXIS 6406, 2017 WL 1364988

Judges: Millett, Sentelle, Randolph

Filed Date: 4/14/2017

Precedential Status: Precedential

Modified Date: 11/5/2024

Authorities (39)

City of Winnfield, Louisiana v. Federal Energy Regulatory ... , 744 F.2d 871 ( 1984 )

Fed. Energy Regulatory Comm'n v. Elec. Power Supply Ass'n , 136 S. Ct. 760 ( 2016 )

public-service-commission-of-the-state-of-new-york-v-federal-energy , 813 F.2d 448 ( 1987 )

alabama-power-company-georgia-power-company-gulf-power-company-mississippi , 993 F.2d 1557 ( 1993 )

Montana-Dakota Utilities Co. v. Northwestern Public Service ... , 71 S. Ct. 692 ( 1951 )

Federal Power Commission v. Sierra Pacific Power Co. , 76 S. Ct. 368 ( 1956 )

Towns of Concord, Norwood, and Wellesley, Massachusetts v. ... , 955 F.2d 67 ( 1992 )

Papago Tribal Utility Authority v. Federal Energy ... , 723 F.2d 950 ( 1983 )

wisconsin-gas-company-v-federal-energy-regulatory-commission-michigan , 770 F.2d 1144 ( 1985 )

Federal Power Commission v. Natural Gas Pipeline Co. , 62 S. Ct. 736 ( 1942 )

city-of-charlottesville-virginia-v-federal-energy-regulatory-commission , 661 F.2d 945 ( 1981 )

panhandle-eastern-pipe-line-company-v-federal-energy-regulatory , 777 F.2d 739 ( 1985 )

Motor Vehicle Mfrs. Assn. of United States, Inc. v. State ... , 103 S. Ct. 2856 ( 1983 )

Morgan Stanley Capital Group Inc. v. Public Util. Dist. No. ... , 128 S. Ct. 2733 ( 2008 )

Virginia Department of Medical Assistance Services v. ... , 678 F.3d 918 ( 2012 )

Bluefield Water Works & Improvement Co. v. Public Service ... , 43 S. Ct. 675 ( 1923 )

Pacific Gas & Electric Co. v. Federal Energy Regulatory ... , 306 F.3d 1112 ( 2002 )

Pub Svc Cmsn Cm KY v. FERC , 397 F.3d 1004 ( 2005 )

anaheim-riverside-banning-colton-and-azusa-california-v-federal , 669 F.2d 799 ( 1981 )

Can Assn Petro v. FERC , 308 F.3d 11 ( 2002 )

View All Authorities »