Estermann v. Bose , 296 Neb. 228 ( 2017 )


Menu:
  • Nebraska Supreme Court Online Library
    www.nebraska.gov/apps-courts-epub/
    06/15/2017 05:13 PM CDT
    - 228 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    J. Daniel Estermann, appellant, v. Bill Bose et al.,
    board members of  Nebraska Cooperative R epublican
    Platte Enhancement Project, a political subdivision
    of the State of Nebraska, and Nebraska
    Cooperative R epublican Platte Enhancement
    Project, a political subdivision of the
    State of Nebraska, appellees.
    ___ N.W.2d ___
    Filed April 7, 2017.     No. S-15-1022.
    1.	 Summary Judgment: Appeal and Error. An appellate court will
    affirm a lower court’s grant of summary judgment if the pleadings and
    admitted evidence show that there is no genuine issue as to any material
    facts or as to the ultimate inferences that may be drawn from those facts
    and that the moving party is entitled to judgment as a matter of law.
    2.	 ____: ____. In reviewing a summary judgment, an appellate court views
    the evidence in the light most favorable to the party against whom the
    judgment was granted and gives that party the benefit of all reasonable
    inferences deducible from the evidence.
    3.	 Statutes: Appeal and Error. Statutory interpretation presents a ques-
    tion of law, for which an appellate court has an obligation to reach
    an independent conclusion irrespective of the decision made by the
    court below.
    4.	 Pleadings: Appeal and Error. An appellate court reviews a district
    court’s denial of a motion for leave to amend a complaint for an abuse
    of discretion. However, an appellate court reviews de novo an underly-
    ing legal conclusion that the proposed amendments would be futile.
    5.	 Summary Judgment. On a motion for summary judgment, the question
    is not how the factual issue is to be decided but whether any real issue
    of material fact exists.
    6.	 Summary Judgment: Proof. A party moving for summary judgment
    makes a prima facie case for summary judgment by producing enough
    - 229 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    evidence to demonstrate that the movant is entitled to judgment if the
    evidence were uncontroverted at trial.
    7.	 ____: ____. Once the moving party makes a prima facie case, the bur-
    den shifts to the party opposing the motion to produce admissible con-
    tradictory evidence showing the existence of a material issue of fact that
    prevents judgment as a matter of law.
    8.	 Constitutional Law: Eminent Domain: Taxation: Public Purpose.
    A citizen’s property may not be taken against his or her will, except
    through the sovereign powers of taxation and eminent domain, both of
    which must be for a public purpose.
    9.	 Eminent Domain: Public Purpose: Words and Phrases. Eminent
    domain is the State’s inherent power to take private property for a pub-
    lic use.
    10.	 Constitutional Law: Eminent Domain: Legislature: Statutes. The
    State’s eminent domain power resides in the Legislature and exists inde-
    pendently of the Nebraska Constitution. But the constitution has limited
    the power of eminent domain, and the Legislature can limit its use fur-
    ther through statutory enactments.
    11.	 Constitutional Law: Eminent Domain: Public Purpose. Under Neb.
    Const. art. I, § 21, the State can take private property only for a public
    use and only if it pays just compensation.
    12.	 Eminent Domain: Legislature. Only the Legislature can authorize a
    private or public entity to exercise the State’s power of eminent domain.
    13.	 Pleadings. A district court’s denial of leave to amend pleadings is
    appropriate only in those limited circumstances in which undue delay,
    bad faith on the part of the moving party, futility of the amendment, or
    unfair prejudice to the nonmoving party can be demonstrated.
    14.	 Pleadings: Summary Judgment: Proof. After discovery is closed and
    a motion for summary judgment has been filed, the appropriate standard
    for assessing whether a motion to amend should be determined futile is
    that the proposed amendment must be not only theoretically viable but
    also solidly grounded in the record and supported by substantial evi-
    dence sufficient to give rise to a triable issue of fact.
    15.	 Legislature: Waters. Nebraska’s common law does not allow water
    to be transferred off overlying land. But the Legislature may provide
    exceptions to this common-law rule.
    Appeal from the District Court for Lincoln County: R ichard
    A. Birch, Judge. Affirmed.
    Amy M. Svoboda, of Svoboda Law Office, and George G.
    Vinton for appellant.
    - 230 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    Donald G. Blankenau and Vanessa A. Silke, of Blankenau,
    Wilmoth & Jarecke, L.L.P., for appellees.
    Douglas J. Peterson, Attorney General, Justin D. Lavene,
    and Kathleen A. Miller, for amicus curiae Nebraska Attorney
    General.
    Heavican, C.J., Wright, Miller-Lerman, Cassel, Stacy,
    K elch, and Funke, JJ.
    Miller-Lerman, J.
    NATURE OF CASE
    In this case, J. Daniel Estermann, the appellant, filed a com-
    plaint for injunction in the district court for Lincoln County
    against Bill Bose, Brad Randel, Jerry Weaver, and Terry
    Martin, who are board members of the Nebraska Cooperative
    Republican Platte Enhancement (N-CORPE) project, a politi-
    cal subdivision of the State of Nebraska, and N-CORPE (col-
    lectively the appellees), along with other parties who were
    later dismissed. Estermann filed this complaint in response
    to N-CORPE’s separate condemnation proceedings against
    Estermann pending in the county court for Lincoln County, in
    which N-CORPE sought an easement across Estermann’s real
    estate. Early on in this case, Estermann additionally filed an
    application for a temporary restraining order and a motion for
    temporary injunction, both of which the district court denied.
    The appellees subsequently filed a motion for summary judg-
    ment. After a hearing, the district court granted the appel-
    lees’ motion for summary judgment and dismissed Estermann’s
    complaint. Estermann appeals. We affirm; however, to some
    extent, our reasoning differs from that of the district court.
    STATEMENT OF FACTS
    N-CORPE is a political subdivision of the State of Nebraska
    that was created under the Interlocal Cooperation Act (ICA),
    Neb. Rev. Stat. § 13-801 et seq. (Reissue 2012), by four
    natural resources districts: the Upper Republican, the Middle
    Republican, the Lower Republican, and the Twin Platte.
    - 231 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    Each natural resources district (hereinafter NRD) is a politi-
    cal subdivision of Nebraska. The four NRD’s entered into
    an amended agreement in December 2013, which created
    N-CORPE. The amended agreement states that “N-CORPE
    shall constitute a separate body corporate and politic of the
    State of Nebraska exercising public powers and acting on
    behalf of the Parties hereto.” According to the amended agree-
    ment, the purpose of N-CORPE is to regulate and manage
    water to assist the State with compliance with the Republican
    River Compact (Compact). Nebraska, Kansas, Colorado, and
    the United States of America are parties to the Compact,
    and the Republican River Basin has been the subject of the
    Compact since 1943.
    In Kansas v. Nebraska, ___ U.S. ___, 
    135 S. Ct. 1042
    , 1049,
    
    191 L. Ed. 2d 1
    (2015), the U.S. Supreme Court described the
    Compact by stating:
    The Compact apportions among the three States “the
    virgin water supply originating in” . . . the Republican
    River Basin. . . . “Virgin water supply,” as used in the
    Compact, means “the water supply within the Basin,”
    in both the River and its tributaries, “undepleted by the
    activities of man.” Compact Art. II. The Compact gives
    each State a set share of that supply—roughly, 49% to
    Nebraska, 40% to Kansas, and 11% to Colorado—for
    any “beneficial consumptive use.” 
    Id., Art. IV;
    see Art. II
    (defining that term to mean “that use by which the water
    supply of the Basin is consumed through the activities of
    man”). In addition, the Compact charges the chief water
    official of each State with responsibility to jointly admin-
    ister the agreement. See 
    id., Art. IX.
    Pursuant to that pro-
    vision, the States created the Republican River Compact
    Administration (RRCA). The RRCA’s chief task is to
    calculate the Basin’s annual virgin water supply by meas­
    uring stream flow throughout the area, and to determine
    (retrospectively) whether each State’s use of that water
    has stayed within its allocation.
    - 232 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    In 2002, the Compact was modified via a “Final Settlement
    Stipulation” (FSS), which was approved by the U.S. Supreme
    Court in Kansas v. 
    Nebraska, supra
    .
    In furtherance of its purpose to assist the State with com-
    pliance with the compact, the amended agreement creating
    N-CORPE states that N-CORPE’s business is to be conducted
    by a board and that each of the NRD’s is to have a member on
    the board. The amended agreement provides that “N-CORPE
    shall have all the powers, privileges and authority exercised or
    capable of being exercised by each of the individual and sepa-
    rate Parties [NRD’s] to achieve the purposes of the N-CORPE
    as set forth in this Agreement and as may be otherwise pro-
    vided for in the [ICA].”
    In the condemnation case, Lincoln County Court case No.
    CI 14-496, N-CORPE filed an amended petition to condemn
    in March 2014. N-CORPE stated in its amended petition that
    it was developing a “stream flow augmentation project” in
    Lincoln County in order to manage ground water and surface
    water in the Republican River Basin and to comply with the
    Compact. N-CORPE alleged in its amended petition that its
    project and petition were in response to the claim of the State
    of Kansas that it was not receiving its share of the Republican
    River water that was due to it under the Compact. N-CORPE
    stated in its amended petition that a portion of the water aug-
    mentation project was located over Estermann’s real estate
    in Lincoln County and that therefore, N-CORPE was seek-
    ing a permanent “Flowage and Right-of-Way Easement” over
    Estermann’s real estate in order to augment waterflow into
    Medicine Creek, which is a tributary of the Republican River.
    After N-CORPE filed its amended petition to condemn, on
    April 1, 2014, Estermann filed the complaint in this case seek-
    ing an injunction against the appellees and Jeffrey Bain, Kent
    Florom, and Michael Nozicka. The latter three defendants were
    appraisers appointed by the county court for Lincoln County;
    they were subsequently dismissed as parties and are not parties
    to this appeal.
    - 233 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    Estermann alleged in his complaint that as a result of
    N-CORPE’s water augmentation project his real estate has
    flooded, causing increasing and irreparable damage to his land
    and crops, and that the floodwaters are creating new creek
    channels and are threatening to lower the water table under
    his fields. Estermann alleged that N-CORPE does not have
    the power of eminent domain, because “the [L]egislature has
    not delegated such powers to interlocal agencies under the
    [ICA]” and because the NRD’s do not have the authority to
    delegate to N-CORPE any eminent domain powers they may
    hold. Estermann further alleged in his complaint that (1) the
    condemnation is not for a public use; (2) the amount of real
    estate being condemned is excessive in duration and area; (3)
    means other than an eminent domain action are available to the
    parties; (4) N-CORPE failed to obtain approvals and permits
    from certain agencies, including the Lincoln County Board of
    Commissioners, the Middle Republican NRD, the Twin Platte
    NRD, and the Nebraska Department of Natural Resources
    (DNR); (5) N-CORPE failed to obtain approval of the water
    augmentation project from Kansas; and (6) N-CORPE is pro-
    hibited under Nebraska’s common law from transferring ground
    water off overlying land, and N-CORPE does not fall under
    any of the statutory exceptions to the common law. Therefore,
    Estermann requested that N-CORPE be enjoined from proceed-
    ing with the condemnation proceedings in case No. CI 14-496
    and that N-CORPE be enjoined from discharging water into
    Medicine Creek.
    On the day Estermann filed his complaint for injunction,
    Estermann also filed an application in which he sought a tem-
    porary restraining order enjoining N-CORPE from proceed-
    ing with the eminent domain action and enjoining N-CORPE
    from discharging water into Medicine Creek. Two days later,
    on April 3, 2014, the district court filed an order in which it
    denied Estermann’s application for a temporary restraining
    order. In denying the application, the district court stated that
    “the failure to grant a temporary restraining order will not
    - 234 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    impair [Estermann’s] ability to proceed on his Complaint for
    an Injunction.”
    On April 16, 2014, Estermann filed a motion for temporary
    injunction that would enjoin N-CORPE from discharging water
    into Medicine Creek. Estermann alleged that the discharge of
    water into Medicine Creek during the pendency of the action
    would produce great irreparable injury to him. Estermann
    further alleged that N-CORPE does not have the power of
    eminent domain and therefore is not entitled to condemn an
    easement over his real estate. Estermann also alleged that he
    did not have an adequate remedy at law.
    On April 30, 2014, the office of the Attorney General filed
    a motion for leave to file an amicus brief, in which it stated
    that it sought to offer guidance regarding an opinion that was
    issued by the Attorney General and its impact on the court’s
    interpretation of § 13-804 of the ICA, which generally deals
    with public agencies exercising joint power. See Att’y Gen.
    Op. No. 03026 (Dec. 5, 2003). The district court granted
    the motion.
    On May 15, 2014, the district court filed an order in which
    it denied Estermann’s motion for temporary injunction. In the
    May 15 order, the district court determined that Estermann did
    not establish that he had a clear right to the relief he sought
    or that he would suffer a great or irreparable injury during
    the pendency of the litigation. The district court stated that
    Estermann’s main argument in support of his request for a tem-
    porary injunction was that the NRD’s that created N-CORPE
    cannot authorize N-CORPE to exercise the power of eminent
    domain. The district court rejected this argument.
    In its order, the court noted that N-CORPE was created by
    the four NRD’s pursuant to the ICA. The court recognized
    that pursuant to Neb. Rev. Stat. § 2-3234 (Reissue 2012),
    each of the NRD’s has the power of eminent domain. Relying
    on § 13-804 of the ICA, the court further recognized that the
    NRD’s can authorize N-CORPE to exercise any of their powers
    or authority, including the power of eminent domain. Section
    13-804(1) provides:
    - 235 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    Any power or powers, privileges, or authority exercised
    or capable of exercise by a public agency of this state
    may be exercised and enjoyed jointly with any other
    public agency of this state and jointly with any public
    agency of any other state or of the United States to the
    extent that laws of such other state or of the United
    States permit such joint exercise or enjoyment. Any
    agency of state government when acting jointly with any
    public agency may exercise and enjoy all of the powers,
    privileges, and authority conferred by the [ICA] upon a
    public agency.
    The district court noted in its May 15, 2014, order that
    although the evidence showed that Estermann would sustain
    damages from the water augmentation project, the evidence
    did not support a conclusion that he would “suffer a great
    or irreparable injury” before his complaint could be heard.
    Accordingly, the district court denied Estermann’s motion for
    temporary injunction.
    On June 5, 2015, the appellees filed a motion for summary
    judgment. On July 17, Estermann filed a motion for leave
    to file an amended complaint, in which he proposed to add
    a claim that the acts of N-CORPE were improper because
    N-CORPE had not obtained approval from the Republican
    River Compact Administration (RRCA) for the water augmen-
    tation project.
    On October 2, 2015, the district court filed an order
    regarding the appellees’ motion for summary judgment and
    Estermann’s motion for leave to file an amended complaint.
    The district court first denied Estermann’s motion for leave to
    file an amended complaint, stating that “any issues raised in
    the Amended Complaint can be dealt with under the original
    complaint. As such, the amendment is futile and the Motion for
    Leave to Amend Complaint is therefore overruled.”
    The district court observed that Estermann disagreed with
    the policies that led to N-CORPE’s petitioning to condemn
    and acquire an easement across his property. The district court
    - 236 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    stated that “[t]hose public policy decisions are constitutionally
    entrusted to other branches of government.”
    The district court next rejected Estermann’s argument that
    the condemnation does not meet a public purpose. The dis-
    trict court stated that “complying with Nebraska’s obligation
    . . . under an interstate compact is certainly a public purpose.”
    The court stated that the burden placed on Estermann by
    the condemnation does not eliminate the public purpose of
    the condemnation.
    The district court further stated in its October 2, 2015, order
    that in its previous order filed May 15, 2014, the court had
    concluded that the NRD’s had properly authorized N-CORPE
    to exercise the power of eminent domain. The district court
    stated that it believed that decision was correct and concluded
    that it “again holds that each of the four [NRD’s] that formed
    N-CORPE has the power of eminent domain [and] that such
    authority . . . was properly exercised by N-CORPE.”
    The district court then rejected Estermann’s argument that
    even if N-CORPE had the authority to condemn the easement,
    it did not have the authority to transport water across his prop-
    erty within the easement area. With respect to Estermann’s
    contention that the common law prohibits N-CORPE from
    transferring ground water off the property on which it was
    pumped, the district court recognized that we stated in In re
    Referral of Lower Platte South NRD, 
    261 Neb. 90
    , 94, 
    621 N.W.2d 299
    , 303 (2001), that “Nebraska’s common law does
    not allow water to be transferred off overlying land.” The
    district court stated, however, that we went on to state that
    “‘[t]he Legislature has the power to determine public policy
    with regard to ground water and . . . it may be transferred from
    the overlying land only with the consent of and to the extent
    prescribed by the public through its elected representatives.’”
    
    Id., quoting State
    ex rel. Douglas v. Sporhase, 
    208 Neb. 703
    ,
    
    305 N.W.2d 614
    (1981), reversed on other grounds 
    458 U.S. 941
    , 
    102 S. Ct. 3456
    , 
    73 L. Ed. 2d 1254
    (1982). The district
    court concluded that by enacting statutes “relating to” NRD’s,
    - 237 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    the Legislature modified the common law and removed any
    common-law prohibition against N-CORPE’s transfer of water
    off the overlying property.
    With respect to Estermann’s argument that N-CORPE does
    not have the necessary permits from the DNR to operate the
    water augmentation project, the district court determined that
    even though Estermann had standing to challenge the tak-
    ing of the easement, he did not have standing to challenge
    whether N-CORPE has the permits needed to use the ease-
    ment. The district court further stated that even if Estermann
    had standing, he was not in the appropriate forum to raise
    that issue.
    Based upon the foregoing, the district court determined
    that there were no material issues of fact in dispute, and it
    determined that the appellees were entitled to judgment as a
    matter of law. The district court granted the appellees’ motion
    for summary judgment and dismissed Estermann’s complaint
    with prejudice.
    Estermann appeals.
    ASSIGNMENTS OF ERROR
    Estermann claims, restated, that the district court erred
    when it (1) determined that N-CORPE has authority to exer-
    cise the power of eminent domain, (2) failed to determine
    that certain permits and approvals had to be obtained and set
    forth in writing before N-CORPE could proceed in eminent
    domain, (3) determined that Estermann did not have standing
    to challenge whether N-CORPE lacked required permits and
    authority, (4) determined that Estermann was not in the appro-
    priate forum to contest N-CORPE’s lack of certain permits and
    approvals, (5) failed to determine that the county court did not
    have jurisdiction over N-CORPE’s amended petition to con-
    demn, (6) denied Estermann’s motion for leave to amend his
    complaint for injunction, (7) determined that Nebraska com-
    mon law does not prohibit N-CORPE from removing ground
    water from overlying land, and (8) failed to find there were
    - 238 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    material issues of fact as to whether N-CORPE’s condemna-
    tion action was for a public use.
    STANDARDS OF REVIEW
    [1,2] An appellate court will affirm a lower court’s grant
    of summary judgment if the pleadings and admitted evidence
    show that there is no genuine issue as to any material facts or
    as to the ultimate inferences that may be drawn from those
    facts and that the moving party is entitled to judgment as a
    matter of law. Bixenmann v. Dickinson Land Surveyors, 
    294 Neb. 407
    , 
    882 N.W.2d 910
    (2016), modified on denial of
    rehearing 
    295 Neb. 40
    , 
    886 N.W.2d 277
    . In reviewing a sum-
    mary judgment, an appellate court views the evidence in the
    light most favorable to the party against whom the judgment
    was granted and gives that party the benefit of all reasonable
    inferences deducible from the evidence. 
    Id. [3] Statutory
    interpretation presents a question of law, for
    which an appellate court has an obligation to reach an inde-
    pendent conclusion irrespective of the decision made by the
    court below. Hargesheimer v. Gale, 
    294 Neb. 123
    , 
    881 N.W.2d 589
    (2016).
    [4] We review a district court’s denial of a motion for leave
    to amend a complaint for an abuse of discretion. See Bailey v.
    First Nat. Bank of Chadron, 
    16 Neb. Ct. App. 153
    , 
    741 N.W.2d 184
    (2007). See, also, Gonzalez v. Union Pacific RR. Co., 
    282 Neb. 47
    , 
    803 N.W.2d 424
    (2011). However, as we explain
    in greater detail later in this opinion, we review de novo an
    underlying legal conclusion that the proposed amendments
    would be futile. Bailey v. First Nat. Bank of 
    Chadron, supra
    .
    ANALYSIS
    Estermann generally claims that the district court erred
    when it granted the appellees’ motion for summary judgment.
    We address Estermann’s specific assignments of error below.
    Because we find no merit to any of Estermann’s assignments of
    error, we affirm the decision of the district court.
    [5] The principles regarding summary judgment are well
    established. On a motion for summary judgment, the question
    - 239 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    is not how the factual issue is to be decided but whether
    any real issue of material fact exists. Cisneros v. Graham,
    
    294 Neb. 83
    , 
    881 N.W.2d 878
    (2016). In reviewing a sum-
    mary judgment, an appellate court views the evidence in the
    light most favorable to the party against whom the judgment
    was granted and gives such party the benefit of all reason-
    able inferences deducible from the evidence. Strode v. City
    of Ashland, 
    295 Neb. 44
    , 
    886 N.W.2d 293
    (2016). Summary
    judgment is proper when the pleadings and evidence admitted
    at the hearing disclose no genuine issue regarding any material
    fact or the ultimate inferences that may be drawn from those
    facts and that the moving party is entitled to judgment as a
    matter of law. 
    Id. [6,7] A
    party moving for summary judgment makes a prima
    facie case for summary judgment by producing enough evi-
    dence to demonstrate that the movant is entitled to judgment if
    the evidence were uncontroverted at trial. Cisneros v. 
    Graham, supra
    . Once the moving party makes a prima facie case, the
    burden shifts to the party opposing the motion to produce
    admissible contradictory evidence showing the existence of
    a material issue of fact that prevents judgment as a matter of
    law. 
    Id. N-CORPE Has
    the Authority to
    Exercise Eminent Domain.
    Estermann claims that the district court erred when it con-
    cluded that the NRD’s that created N-CORPE properly autho-
    rized N-CORPE to use the power of eminent domain and that
    N-CORPE properly possessed authority to exercise eminent
    domain. Because we agree with the district court’s legal con-
    clusions, we find no merit to this assignment of error.
    [8,9] As an initial matter, we first summarize the nature of
    eminent domain. Every citizen has the constitutional right to
    acquire, own, possess, and enjoy property. See Neb. Const.
    art. I, § 25. A citizen’s property may not be taken against his
    or her will, except through the sovereign powers of taxation
    - 240 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    and eminent domain, both of which must be for a public pur-
    pose. Thompson v. Heineman, 
    289 Neb. 798
    , 
    857 N.W.2d 731
    (2015). See, also, Burlington Northern Santa Fe Ry. Co. v.
    Chaulk, 
    262 Neb. 235
    , 
    631 N.W.2d 131
    (2001); Burger v. City
    of Beatrice, 
    181 Neb. 213
    , 
    147 N.W.2d 784
    (1967). Eminent
    domain is the State’s inherent power to take private property
    for a public use. Thompson v. 
    Heineman, supra
    .
    [10-12] The State’s eminent domain power resides in
    the Legislature and exists independently of the Nebraska
    Constitution. Thompson v. 
    Heineman, supra
    . But the con-
    stitution has limited the power of eminent domain, and the
    Legislature can limit its use further through statutory enact-
    ments. 
    Id. Under Neb.
    Const. art. I, § 21, the State can take
    private property only for a public use and only if it pays
    just compensation. Thompson v. 
    Heineman, supra
    . See, also,
    Burlington Northern Santa Fe Ry. Co. v. 
    Chaulk, supra
    . Only
    the Legislature can authorize a private or public entity to exer-
    cise the State’s power of eminent domain. 
    Id. Under §
    2-3234, the Legislature has delegated the power of
    eminent domain to NRD’s to carry out their authorized pur-
    poses. Section 2-3234 provides in part: “Except as provided in
    sections 2-3226.11 and 2-3234.02 to 2-3234.09, each district
    shall have the power and authority to exercise the power of
    eminent domain when necessary to carry out its authorized
    purposes within the limits of the district or outside its bound­
    aries.” Accordingly, the four NRD’s that formed N-CORPE
    each had the power of eminent domain.
    Pursuant to the ICA, the NRD’s may exercise their author-
    ity and other powers alone or jointly with other local govern-
    mental units. Nebraska permits interlocal agreements pursuant
    to the ICA. Kubicek v. City of Lincoln, 
    265 Neb. 521
    , 
    658 N.W.2d 291
    (2003). The ICA’s purpose is “to permit local gov-
    ernmental units to make the most efficient use of their taxing
    authority and other powers by enabling them to cooperate with
    other localities on a basis of mutual advantage and thereby to
    provide services and facilities.” See § 13-802.
    - 241 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    Under § 13-804(2), two or more public agencies may enter
    into agreements with one another for joint or cooperative
    action under the ICA. See City of Falls City v. Nebraska Mun.
    Power Pool, 
    279 Neb. 238
    , 
    777 N.W.2d 327
    (2010). The ICA
    authorizes the creation of a joint entity whose express author-
    ity is limited to executing the enumerated powers of the agen-
    cies which created it. Section 13-803(1) of the ICA provides
    that for purposes of the ICA, “[j]oint entity shall mean an
    entity created by agreement pursuant to section 13-804.” As
    quoted earlier in this opinion, with respect to joint entities,
    § 13-804(1) provides:
    Any power or powers, privileges, or authority exercised
    or capable of exercise by a public agency of this state
    may be exercised and enjoyed jointly with any other
    public agency of this state and jointly with any public
    agency of any other state or of the United States to the
    extent that laws of such other state or of the United
    States permit such joint exercise or enjoyment. Any
    agency of state government when acting jointly with any
    public agency may exercise and enjoy all of the powers,
    privileges, and authority conferred by the [ICA] upon a
    public agency.
    Section 13-804(2) provides:
    Any two or more public agencies may enter into agree-
    ments with one another for joint or cooperative action
    pursuant to the [ICA]. Appropriate action by ordinance,
    resolution, or otherwise pursuant to law of the governing
    bodies of the participating public agencies shall be neces-
    sary before any such agreement may enter into force.
    With respect to how the ICA is to be construed, § 13-825
    provides:
    The provisions of the [ICA] shall be deemed to pro-
    vide an additional, alternative, and complete method for
    the doing of the things authorized by the act and shall
    be deemed and construed to be supplemental and addi-
    tional to, and not in derogation of, powers conferred
    - 242 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    upon political subdivisions, agencies, and others by law.
    Insofar as the provisions of the [ICA] are inconsistent
    with the provisions of any general or special law, admin-
    istrative order, or regulation, the provisions of the [ICA]
    shall be controlling.
    Estermann claims that the district court erred when it deter-
    mined that N-CORPE had the authority to exercise the power
    of eminent domain. Estermann contends that the Legislature
    did not specify in the ICA or elsewhere that an interlocal
    agency created pursuant to the ICA could have the power of
    eminent domain. Estermann further asserts that
    the only way an interlocal agency could have condemna-
    tion powers is if the Nebraska Legislature had included
    language in the ICA to the effect that all agencies created
    under the ICA have eminent domain power or perhaps
    language to the effect that any such agency does possess
    eminent domain powers so long as the government agen-
    cies that created it have those powers.
    Brief for appellant at 22. Estermann contends that only the
    Legislature is capable of delegating eminent domain power and
    that because the Legislature did not explicitly state that interlo-
    cal agencies, such as N-CORPE, may have eminent domain
    power, N-CORPE does not have the power to exercise eminent
    domain. We disagree.
    In December 2013, the four NRD’s formed N-CORPE by
    entering into an amended agreement pursuant to the ICA. As
    stated above, pursuant to § 2-3234, the NRD’s that formed
    N-CORPE each had the power of eminent domain. Under
    § 13-804, local governmental units are authorized to jointly
    exercise their individually held authority and powers through
    a joint entity created under the ICA. Therefore, because the
    NRD’s that formed N-CORPE each individually held the
    power of eminent domain, the NRD’s were able to jointly
    exercise that individually held power through the mechanism
    of the joint entity they created, i.e., N-CORPE, and thus,
    N-CORPE was authorized to exercise the power of eminent
    domain. When the NRD’s formed N-CORPE as a joint entity
    - 243 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    under the ICA, they did not lose any of the powers, privileges,
    or authorities that they separately held, including the power of
    eminent domain. Instead, the powers, privileges, and authori-
    ties that the NRD’s were capable of exercising separately
    could be exercised and enjoyed jointly with the other NRD’s
    through the mechanism of their joint entity, N-CORPE. See
    § 13-804(1).
    The foregoing description of the N-CORPE’s authority to
    act and the simultaneous power of eminent domain retained by
    the NRD’s is in accord with § 13-825, which provides:
    The provisions of the [ICA] shall be deemed to pro-
    vide an additional, alternative, and complete method for
    the doing of the things authorized by the act and shall be
    deemed and construed to be supplemental and additional
    to, and not in derogation of, powers conferred upon polit-
    ical subdivisions, agencies, and others by law.
    (Emphasis supplied.) Thus, under § 13-825, the formation
    of N-CORPE did not remove or degrade powers that the
    Legislature had already granted to the NRD’s by statute. Rather,
    the formation by the NRD’s of the joint entity N-CORPE under
    the provisions of the ICA created a method of exercising
    eminent domain which was “supplemental and additional to,
    and not in derogation of, powers” conferred on the NRD’s.
    Statutory language is to be given its plain and ordinary mean-
    ing, and an appellate court will not resort to interpretation
    to ascertain the meaning of statutory words which are plain,
    direct, and unambiguous. Stewart v. Nebraska Dept. of Rev.,
    
    294 Neb. 1010
    , 
    885 N.W.2d 723
    (2016). Under the clear lan-
    guage of §§ 13-804 and 13-825, N-CORPE is authorized by the
    ICA to serve as the method to exercise the power of eminent
    domain to the extent that eminent domain had been conferred
    on the NRD’s.
    We have previously recognized that the authority and pow-
    ers of governmental entities can be exercised and enjoyed
    jointly with other governmental entities through a joint entity
    created pursuant to the ICA. See Kubicek v. City of Lincoln,
    
    265 Neb. 521
    , 
    658 N.W.2d 291
    (2003). Although Kubicek
    - 244 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    did not directly involve the issue of the exercise of the power
    of eminent domain, we find its description of a joint entity
    useful. In Kubicek, we noted that three governmental entities
    created a joint entity—referred to as the “joint administrative
    agency”—pursuant to an interlocal cooperation agreement for
    the purpose of completing a project. This court stated that
    “[b]efore the creation of [the joint agency], each partner had
    the statutory authority to implement certain aspects of the
    project. Together, through [the joint agency], the three part-
    ners have complete statutory authority to implement the whole
    project.” Kubicek v. City of 
    Lincoln, 265 Neb. at 523-24
    , 658
    N.W.2d at 294. Accordingly, the joint entity was able to exer-
    cise the express powers and authorities that were held by the
    governmental agencies which created it. Similarly, in this case,
    N-CORPE may exercise the powers and authorities that were
    held individually by the four NRD’s that created it pursuant to
    the ICA, namely the power of eminent domain.
    For these reasons, we determine that the district court did
    not err when it concluded that N-CORPE had the authority to
    exercise the power of eminent domain. We find no merit to this
    assignment of error.
    N-CORPE Did Not Lack Necessary
    Permits or Approvals.
    Estermann claims that the district court erred when it failed
    to determine that N-CORPE was required to obtain permits and
    approvals from the DNR and the NRD’s in order to implement
    and operate the N-CORPE project and to utilize the easement
    over Estermann’s property. We find no merit to this assignment
    of error.
    Neb. Rev. Stat. § 76-704 (Reissue 2009) provides: “If any
    condemnee shall fail to agree with the condemner with respect
    to the acquisition of property sought by the condemner, a peti-
    tion to condemn the property may be filed by the condemner in
    the county court of the county where the property or some part
    thereof is situated.” Estermann claims that N-CORPE failed to
    comply with Neb. Rev. Stat. § 76-704.01(7) (Reissue 2009),
    - 245 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    which provides that if approval of another agency is required,
    “[a] petition filed pursuant to section 76-704, shall . . . set forth
    the approval in writing of such agency.” Estermann asserts
    that N-CORPE failed to obtain such approvals as required
    by § 76-704.01 and set forth said approvals in its petition
    to condemn.
    We note that the district court determined that Estermann
    does not have standing to challenge whether N-CORPE has the
    permits needed to use the easement and that even if Estermann
    did have standing, he was not in the appropriate forum within
    which to raise the issue. Assuming without deciding that
    Estermann had standing and was in the proper forum, as set
    forth below, we determine that N-CORPE was not required to
    obtain the permits and approvals alleged by Estermann. And in
    view of our resolution of the permits issue, we do not address
    Estermann’s assignments of error to the effect that the district
    court erred when it determined that Estermann did not have
    standing to challenge N-CORPE’s lack of permits and that he
    was not in the appropriate forum to raise the issue. See In re
    Interest of Jackson E., 
    293 Neb. 84
    , 87, 
    875 N.W.2d 863
    , 866
    (2016) (“[a]n appellate court is not obligated to engage in an
    analysis that is not necessary to adjudicate the case and contro-
    versy before it”).
    Estermann first asserts that that N-CORPE was required to
    obtain a permit from the DNR to conduct water into or along
    natural channels pursuant to Neb. Rev. Stat. § 46-252 (Reissue
    2010). We will refer to this as a “conduct water permit.”
    Section 46-252 generally provides that a conduct water permit
    allows a permit holder to utilize naturally occurring waterways
    to move a quantity of water from one point to another. A con-
    duct water permit is required if an applicant wants the DNR to
    monitor and protect the quantity of water as it moves down-
    stream. Section 46-252 provides in part:
    (1) Any person may conduct, either from outside the
    state or from sources located in the state, quantities of
    water over and above those already present into or along
    any of the natural streams or channels of this state, for
    - 246 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    purposes of instream beneficial uses or withdrawal of
    some or all of such water for out-of-stream beneficial
    uses, at any point without regard to any prior appro-
    priation of water from such stream, due allowance being
    made for losses in transit to be determined by the [DNR].
    The [DNR] shall monitor movement of the water by
    meas­urements or other means and shall be responsible for
    assuring that such quantities are not subsequently diverted
    or withdrawn by others unless they are authorized to do
    so by the person conducting the water.
    (2) Except as provided in subsections (3) and (4)
    of this section, before any person may conduct water
    into or along any of the natural streams or channels of
    the state, he or she shall first obtain a permit from the
    [DNR]. Application for the permit shall be made on
    forms provided by the [DNR]. Applications shall include
    plans and specifications detailing the intended times,
    amounts, and streamreach locations and such other infor-
    mation as required by the [DNR]. The water subject to
    such a permit shall be deemed appropriated for the use
    specified in the permit. Permitholders shall be liable
    for any damages resulting from the overflow of such
    stream or channel when water so conducted contributed
    to such overflow.
    The exceptions set forth in subsections (3) and (4) of § 46-252
    are not applicable to this case.
    Although the N-CORPE project adds quantities of water to
    the stream, it does not require a conduct water permit, because
    unlike the scenarios described in § 46-252, N-CORPE is not
    attempting to guarantee that a certain quantity of water is used
    for a beneficial use or reaches a certain point downstream for a
    particular use. Rather, the purpose of the N-CORPE project is
    simply to add water to the Republican River Basin in order to
    offset water depletion.
    We note that while some of the water eventually reaches
    Kansas, this does not mean that a conduct water permit is
    required. A conduct water permit provides protection for a
    - 247 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    quantity of water as it travels along from one point to another.
    Estermann points to the fact that the State of Wyoming was
    granted a water conduct permit under § 46-252 to conduct water
    in the North Platte River from Wyoming’s Pathfinder Reservoir
    to Nebraska’s Kingsley Reservoir in order to comply with
    Wyoming’s obligations under the Nebraska-Wyoming settle-
    ment agreement and the Platte River Recovery Implementation
    Program. Estermann contends that because Wyoming obtained
    a water conduct permit, one is required herein. We do not
    agree. According to the undisputed record, Wyoming sought
    the permit in order to protect the amount of water it was con-
    ducting in the North Platte River from the Wyoming-Nebraska
    State line for delivery to the Kingsley Reservoir in Nebraska.
    In contrast, in this case, N-CORPE is augmenting the flow
    of water into Medicine Creek to the Republican River Basin,
    but it is not attempting to guarantee the delivery of a specific
    quantity of water past the headwaters of Medicine Creek.
    Under the circumstances, N-CORPE does not need a conduct
    water permit pursuant to § 46-252.
    Estermann also asserts that N-CORPE was required to
    obtain a permit from the DNR to transfer ground water pursu-
    ant to Neb. Rev. Stat. § 46-613.01 (Reissue 2010) in order to
    construct and operate the project. Pursuant to § 46-613.01, a
    ground water transfer permit requires that “[a]ny person, firm,
    city, village, municipal corporation, or other entity intend-
    ing to withdraw ground water from any water well located
    in the State of Nebraska and transport it for use in another
    state shall apply to the [DNR] for a permit to do so.”
    (Emphasis supplied.)
    The purpose of the N-CORPE project is to increase the
    amount of water available in the Republican River Basin, but it
    is not the purpose of the N-CORPE project to transport water
    explicitly for use in Kansas. Because the N-CORPE proj-
    ect does not seek to transport water for use in another state,
    N-CORPE did not need to obtain a ground water transfer per-
    mit pursuant to § 46-613.01. Compare, Sporhase v. Nebraska
    - 248 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    ex rel. Douglas, 
    458 U.S. 941
    , 
    102 S. Ct. 3456
    , 
    73 L. Ed. 2d 1254
    (1982) (concerning applicant with contiguous tracts in
    Nebraska and Colorado who pumped ground water from well
    in Nebraska to irrigate applicant’s tracts in both Nebraska and
    Colorado); Ponderosa Ridge LLC v. Banner County, 
    250 Neb. 944
    , 
    554 N.W.2d 151
    (1996) (concerning applicant with con-
    tiguous tracts in Wyoming and Nebraska who sought ground
    water transfer permit to irrigate farmland in Wyoming with
    water from well in Nebraska).
    We additionally note that our resolution of the DNR permit
    issues is supported by the record which shows that the DNR
    was fully aware of the N-CORPE project. Specifically, the
    record shows that the director of the DNR and the predecessor
    acting director of the DNR determined that N-CORPE did not
    require a permit under either § 46-252 or § 46-613.01.
    Estermann also argues that N-CORPE was required under
    its respective rules and regulations to obtain permits from the
    Middle Republican NRD and the Twin Platte NRD before
    operating the N-CORPE project. The Middle Republican NRD
    and the Twin Platte NRD are two of the four NRD’s that cre-
    ated the joint entity, N-CORPE, for the purposes of completing
    the N-CORPE project. Pursuant to the amended agreement
    that created N-CORPE, each of the four NRD’s had a mem-
    ber on the board with a vote regarding the construction and
    operation of the N-CORPE project. During the construction
    and operation of the N-CORPE project, neither the Middle
    Republican NRD nor the Twin Platte NRD required N-CORPE
    to obtain a permit from these individual NRD’s. We determine
    that by voting in favor of the N-CORPE project, the Middle
    Republican NRD and the Twin Platte NRD have concluded
    that the N-CORPE project is in compliance with their rules
    and regulations and have waived the necessity of individual
    permits, if otherwise required.
    Because we determine that N-CORPE was not required to
    obtain the permits specified by Estermann, we find no merit to
    this assignment of error.
    - 249 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    The District Court’s Ruling That the
    County Court Had Jurisdiction Over
    N-CORPE’s Amended Petition
    to Condemn Was Not Error.
    Estermann claims that the district court erred when it
    failed to rule that the county court for Lincoln County in case
    No. CI 14-496 did not have jurisdiction over N-CORPE’s
    amended petition to condemn because N-CORPE failed to
    comply with § 76-704.01 by failing to obtain certain permits
    and approvals. Even assuming that the district court could
    properly entertain this issue collaterally challenging the juris-
    diction of the county court in the condemnation case, given
    our resolution of the permits issue, this assignment of error
    would be unavailing.
    The District Court Did Not Err When It
    Denied Estermann’s Motion to Amend
    His Complaint for Injunction.
    Estermann claims that the district court erred when it denied
    his motion to amend his complaint for injunction. We find no
    merit to this assignment of error.
    We first address the proper standard of review regarding
    a district court’s denial of a motion to amend the pleadings.
    We note that this court has previously stated that we review a
    district court’s decision on a motion for leave to amend a com-
    plaint for an abuse of discretion. See Gonzalez v. Union Pacific
    RR. Co., 
    282 Neb. 47
    , 
    803 N.W.2d 424
    (2011). However, in
    Bailey v. First Nat. Bank of Chadron, 
    16 Neb. Ct. App. 153
    , 
    741 N.W.2d 184
    (2007), the Nebraska Court of Appeals addressed
    a case that was procedurally similar to the present case, and the
    considerations in Bailey and the instant case cause us to refine
    our standard of review.
    In Bailey, the court assessed whether the district court had
    properly denied a request to amend a complaint after a motion
    for summary judgment had been filed but before the district
    court had ruled on the motion. With their motion to amend,
    the plaintiffs sought to add additional theories of recovery to
    - 250 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    the theories set forth in the initial complaint. The district court
    denied the motion to amend, and the plaintiffs appealed.
    The Court of Appeals in Bailey noted that prior to Bailey,
    the Nebraska appellate courts had not discussed the stan-
    dard of review for denial of a motion to amend filed under
    Nebraska’s new rules for notice pleading, specifically, Neb.
    Ct. R. of Pldg. § 6-1115(a) (previously codified as Neb. Ct. R.
    of Pldg. in Civ. Actions 15(a) (rev. 2003)). Section 6-1115(a)
    provides:
    A party may amend the party’s pleading once as a mat-
    ter of course before a responsive pleading is served or,
    if the pleading is one to which no responsive pleading is
    permitted, the party may amend it within 30 days after
    it is served. Otherwise a party may amend the party’s
    pleading only by leave of court or by written consent of
    the adverse party, and leave shall be freely given when
    justice so requires. A party shall plead in response to an
    amended pleading within the time remaining for response
    to the original pleading or within 10 days after service of
    the amended pleading, whichever period may be longer,
    unless the court otherwise orders.
    The Court of Appeals in Bailey acknowledged that
    Nebraska’s current notice pleading rules are modeled after the
    Federal Rules of Civil Procedure and that Nebraska courts may
    therefore look to federal decisions for guidance. See Kellogg
    v. Nebraska Dept. of Corr. Servs., 
    269 Neb. 40
    , 
    690 N.W.2d 574
    (2005). Similarly to Nebraska’s § 6-1115(a), Fed. R. Civ.
    P. 15(a)(2) provides that once a responsive pleading has been
    filed, “a party may amend its pleading only with the opposing
    party’s written consent or the court’s leave. The court should
    freely give leave when justice so requires.”
    [13] With respect to the denial of leave to amend under the
    Federal Rules of Civil Procedure, it has been stated by a fed-
    eral appellate court:
    “Under the liberal amendment policy of Federal Rule of
    Civil Procedure 15(a), a district court’s denial of leave
    to amend pleadings is appropriate only in those limited
    - 251 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    circumstances in which undue delay, bad faith on the
    part of the moving partly [sic], futility of the amend-
    ment, or unfair prejudice to the non-moving party can
    be demonstrated.”
    Bailey v. First Nat. Bank of 
    Chadron, 16 Neb. Ct. App. at 163
    , 741
    N.W.2d at 193, quoting Roberson v. Hayti Police Dept., 
    241 F.3d 992
    (8th Cir. 2001). We have similarly stated that “[a] dis-
    trict court’s denial of leave to amend pleadings is appropriate
    only in those limited circumstances in which undue delay, bad
    faith on the part of the moving party, futility of the amendment,
    or unfair prejudice to the nonmoving party can be demon-
    strated.” Golnick v. Callender, 
    290 Neb. 395
    , 400, 
    860 N.W.2d 180
    , 187 (2015).
    Federal courts generally review the denial of a motion to
    amend for an abuse of discretion. See, e.g., In re K-tel Intern.,
    Inc. Securities Litigation, 
    300 F.3d 881
    (8th Cir. 2002). This
    is consistent with that standard of review generally applied in
    review of such motions in Nebraska. See, Golnick v. Callender,
    supra; Gonzalez v. Union Pacific RR. Co., 
    282 Neb. 47
    , 
    803 N.W.2d 424
    (2011). However, in Bailey v. First Nat. Bank of
    Chadron, 
    16 Neb. Ct. App. 153
    , 
    741 N.W.2d 184
    (2007), the Court
    of Appeals noted that the U.S. Court of Appeals for the Eighth
    Circuit reviews de novo the underlying legal conclusion of
    whether a proposed amendment would have been futile. The
    Bailey opinion stated:
    Federal courts generally review the denial of a motion
    to amend for an abuse of discretion. See, In re K-tel
    Intern., Inc. Securities Litigation, 
    300 F.3d 881
    (8th Cir.
    2002); 6 Charles Alan Wright et al., Federal Practice and
    Procedure § 1484 (2d ed. 1990). Federal case law from
    the Eighth Circuit indicates, however, that the Eighth
    Circuit reviews de novo the underlying legal conclusion
    of whether the proposed amendments to a complaint
    would have been futile. See, Marmo v. Tyson Fresh
    Meats, Inc., 
    457 F.3d 748
    (8th Cir. 2006); U.S. ex rel.
    Joshi v. St. Luke’s Hosp., Inc., 
    441 F.3d 552
    (8th Cir.
    2006) (citing U.S. ex rel. Gaurdineer & Comito, L.L.P.
    - 252 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    v. Iowa, 
    269 F.3d 932
    (8th Cir. 2001)), cert. denied 
    549 U.S. 881
    , 
    127 S. Ct. 189
    , 
    166 L. Ed. 2d 142
    . See, also,
    Corsello v. Lincare, Inc., 
    428 F.3d 1008
    (11th Cir. 2005)
    (underlying legal conclusion of whether particular amend-
    ment to complaint would have been futile is reviewed
    de novo); Miller v. Calhoun County, 
    408 F.3d 803
    (6th
    Cir. 2005) (where district court draws legal conclusion
    that amendment would be futile, conclusion is reviewed
    de 
    novo). 16 Neb. Ct. App. at 163-64
    , 741 N.W.2d at 193.
    In Bailey, the Court of Appeals adopted the federal stan-
    dards of review outlined above. In doing so, the Court of
    Appeals stated that “we review the district court’s denial of
    the [appellants’] motion to amend under Nebraska’s rule 15(a)
    [now codified as § 6-1115(a)] for an abuse of discretion.
    However, we review de novo any underlying legal conclusion
    that the proposed amendments would be futile.” 
    Id. at 164,
    741
    N.W.2d at 193.
    Notably, since Bailey was decided, all the federal cir-
    cuit courts have adopted the standard that an appellate court
    reviews de novo the underlying legal conclusion of whether the
    proposed amendments to a complaint would have been futile.
    See, e.g., Thomas v. Chevron U.S.A., Inc., 
    832 F.3d 586
    (5th
    Cir. 2016); Maiden Creek Assocs. v. U.S. Dept. of Transp., 
    823 F.3d 184
    (3d Cir. 2016); Osborn v. Visa Inc., 
    797 F.3d 1057
    (D.C. Cir. 2015); Runnion v. Girl Scouts of Greater Chicago,
    
    786 F.3d 510
    (7th Cir. 2015); Giorgio Foods, Inc. v. U.S., 
    785 F.3d 595
    (Fed. Cir. 2015); Barnes v. Harris, 
    783 F.3d 1185
    (10th Cir. 2015); U.S. ex rel. Ahumada v. NISH, 
    756 F.3d 268
    (4th Cir. 2014); Mills v. U.S. Bank, NA, 
    753 F.3d 47
    (1st Cir.
    2014); Panther Partners v. Ikanos Communications, 
    681 F.3d 114
    (2d Cir. 2012); Carvalho v. Equifax Information Services,
    LLC, 
    629 F.3d 876
    (9th Cir. 2010).
    We agree with the Court of Appeals’ holding in Bailey,
    and we now hold that an appellate court generally reviews
    the denial of a motion to amend a complaint for an abuse of
    discretion; however, an appellate court reviews de novo an
    - 253 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    underlying legal conclusion that the proposed amendments
    would be futile.
    In Bailey v. First Nat. Bank of Chadron, 
    16 Neb. Ct. App. 153
    ,
    
    741 N.W.2d 184
    (2007), the Court of Appeals expressed the
    appropriate method to be used in assessing whether the pro-
    posed amendment should be denied on the basis of its futility.
    In Hayes v. County of Thayer, 
    21 Neb. Ct. App. 836
    , 842-43, 
    844 N.W.2d 347
    , 353-54 (2014), the Court of Appeals described
    Bailey as follows:
    In 
    Bailey, supra
    , we quoted Hatch [v. Department for
    Children, Youth & Families, 
    274 F.3d 12
    (1st Cir. 2001)],
    in which the First Circuit expressed that if leave to amend
    is not sought until after discovery is closed and a motion
    for summary judgment has been docketed, the proposed
    amendment must be not only theoretically viable but
    also solidly grounded in the record and supported by
    substantial evidence. We also quoted the Second Circuit’s
    expression [in Milanese v. Rust-Oleum Corp., 
    244 F.3d 104
    (2d Cir. 2001),] that in such a situation, the proposed
    amendment may be considered futile when the evidence
    in support of the proposed new claim creates no triable
    issue of fact and would not survive a motion for sum-
    mary judgment.
    Based on its analysis of the standards set forth by the First
    and Second Circuits, the Court of Appeals ably concluded
    in Bailey:
    We find the explanations and rationale used and
    applied by the First and Second Circuits to be sound and
    hold that if leave to amend is sought under Nebraska’s
    rule 15(a) before discovery is complete and before a
    motion for summary judgment has been filed, the ques-
    tion of whether such amendment would be futile is judged
    by reference to Neb. Ct. R. of Pldg. in Civ. Actions
    12(b)(6) (rev. 2003) [now codified as Neb. Ct. R. of Pldg.
    6-1112(b)(6)]. Leave to amend in such circumstances
    should be denied as futile only if the proposed amend-
    ment cannot withstand a rule 12(b)(6) motion to dismiss.
    - 254 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    If, however, the rule 15(a) motion is made in response to
    a motion for summary judgment and the parties have pre-
    sented all relevant evidence in support of their positions,
    then the amendment should be denied as futile only when
    the evidence in support of the proposed amendment cre-
    ates no triable issue of fact and the opposing party would
    be entitled to judgment as a matter of 
    law. 16 Neb. Ct. App. at 169
    , 741 N.W.2d at 196-97.
    [14] In Hayes, the Court of Appeals stated that “[b]oth the
    notion that ‘substantial evidence’ must be presented and the
    notion that the evidence must be such as would create a ‘tri-
    able issue of fact’ that could survive summary judgment are
    expressions of the same 
    standard.” 21 Neb. Ct. App. at 843
    , 844
    N.W.2d at 354. In Hayes, the plaintiffs had filed a motion to
    amend the complaint after discovery had been closed and the
    defendant had filed a motion for summary judgment, and in
    fact, the district court had already sustained the defendant’s
    motion for summary judgment and entered judgment in favor
    of the defendant. Based upon the reasoning set forth in Bailey,
    the Court of Appeals stated in Hayes that “the appropri-
    ate standard for assessing whether [the plaintiffs’] motion to
    amend should be determined futile is that the proposed amend-
    ment must be not only theoretically viable but also solidly
    grounded in the record and supported by substantial evidence
    sufficient to give rise to a triable issue of fact.” 
    Id. at 844,
    844
    N.W.2d at 354.
    In the present case, we apply this standard set forth above
    to assess Estermann’s claim that the district court erred when
    it denied his motion to amend the complaint. Estermann filed
    his motion to amend the complaint after discovery had been
    completed and after N-CORPE had filed its motion for sum-
    mary judgment. In his appellate brief, Estermann states that
    although he alleged in his original complaint that N-CORPE
    failed to obtain necessary approval from Kansas, he did not
    allege in his original complaint that N-CORPE was required
    to obtain approval specifically from RRCA. Estermann sought
    to include the specific allegation that N-CORPE failed to
    - 255 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    obtain approval from RRCA in his proposed amended com-
    plaint. In denying Estermann’s motion for leave to amend his
    complaint, the district court stated that any issues raised in
    the proposed amended complaint could “be dealt with under
    the original complaint,” and “[a]s such, the amendment is
    futile . . . .”
    As stated above, Nebraska, Kansas, Colorado, and the
    United States of America are parties to the Compact, and the
    Republican River Basin has been the subject of the Compact
    since 1943. The Compact allocates to each of the states an
    agreed-upon share of the water supply within the Republican
    River Basin—roughly 49 percent to Nebraska, 40 percent to
    Kansas, and 11 percent to Colorado. Pursuant to the Compact,
    the States created the RRCA to calculate the Republican River
    Basin’s annual virgin water supply and to determine whether
    each State’s use of that water is within its allocation under the
    Compact. See Kansas v. Nebraska, ___ U.S. ___, 
    135 S. Ct. 1042
    , 
    191 L. Ed. 2d 1
    (2015).
    In 2002, the Compact was modified via the FSS, which was
    approved by the U.S. Supreme Court in Kansas v. 
    Nebraska, supra
    . The Court stated that the FSS “established detailed
    mechanisms to promote compliance with the Compact’s 
    terms.” 135 S. Ct. at 1050
    . The FSS “aim[s] to accurately measure the
    supply and use of the Basin’s water, and to assist the States in
    staying within their prescribed limits.” 
    Id. This is
    done through
    detailed accounting procedures and the utilization of a ground
    water model that are set forth in the FSS.
    In support of his argument, Estermann points to section
    III.B.1.k. of the FSS, which states that a moratorium on new
    wells shall not apply to:
    Wells acquired or constructed by a State for the sole
    purpose of offsetting stream depletions in order to com-
    ply with its Compact Allocations. Provided that, such
    Wells shall not cause any new net depletion to stream
    flow either annually or long-term. The determination of
    net depletions from these Wells will be computed by the
    RRCA Groundwater Model and included in the State’s
    - 256 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    Computed Beneficial Consumptive Use. Augmentation
    plans and related accounting procedures submitted under
    this Subsection III.B.1.k. shall be approved by the RRCA
    prior to implementation.
    (Emphasis supplied.) Estermann asserts that the N-CORPE
    project is such an “augmentation plan” that requires approval
    by the RRCA prior to the N-CORPE project’s implementation.
    Brief for appellant at 37.
    We disagree that this or any other section of the FSS
    requires N-CORPE to obtain the RRCA’s approval prior to the
    construction or operation of the N-CORPE project. This sec-
    tion of the FSS refers to the fact that the RRCA must approve
    augmentation plans and related changes to the RRCA account-
    ing procedure before a State may receive augmentation credit.
    The term “augmentation plan” does not refer to the actual
    construction or operation of the project itself, but, rather, an
    augmentation plan under the FSS sets forth the methods for
    how to calculate the augmentation credit the State wishes
    to receive that will be taken into account when considering
    whether the State has complied with its allocated percentage of
    use of the virgin water supply in the Republican Riven Basin
    under the Compact. An augmentation plan does not require
    that the RRCA approve the actual construction or operation of
    such project.
    Our reading of the FSS is consistent with the record. The
    primary author of the N-CORPE augmentation plan explained
    that the DNR developed the N-CORPE augmentation plan
    “consistent with the straightforward methodologies of the
    RRCA Accounting Procedures and Reporting Requirements.”
    He further explained that the N-CORPE augmentation plan
    “provides an example of the accounting method that would
    be used to quantify the [augmented water supply] Credit.”
    Thus, although RRCA approval would be necessary to approve
    the N-CORPE augmentation plan and the related account-
    ing procedures in order to receive an augmentation credit,
    the FFS does not require RRCA approval for the physical
    construction and operation of the N-CORPE project. Stated
    - 257 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    another way, to the extent the State wishes to alter the amount
    of credit it receives for augmentation water under the FSS
    accounting procedures, it would need to obtain approval from
    the RRCA, but the RRCA’s approval is not a prerequisite
    to N-CORPE’s physically implementing the project itself
    or its operation. Therefore, N-CORPE was not required to
    obtain the approval of the RRCA before implementing the
    N-CORPE project.
    Because we determine that N-CORPE was not required to
    obtain the approval of the RRCA in order to implement the
    augmentation plan, Estermann’s proposed amendment to his
    complaint is not theoretically viable and it is not supported by
    substantial evidence sufficient to give rise to a triable issue of
    fact. See Hayes v. County of Thayer, 
    21 Neb. Ct. App. 836
    , 
    844 N.W.2d 347
    (2014). Therefore, upon our de novo review, we
    determine the district court did not err when it determined
    that Estermann’s proposed amendment was futile and denied
    his motion to amend his complaint. We find no merit to this
    assignment of error.
    District Court Did Not Err When It Determined
    That Common Law Does Not Prohibit
    N-CORPE From Removing Ground
    Water From Overlying Land.
    Estermann claims that the district court erred when it
    determined that Nebraska common law does not prohibit
    N-CORPE from removing ground water from the overlying
    land. We find no merit to this assignment of error.
    As an initial matter, we clarify that Estermann does not
    claim that he has an interest in ground water that is being
    adversely impacted by the fact that N-CORPE is withdrawing
    ground water from a well field and releasing that water into
    Medicine Creek to augment the flow of the water. Compare
    In re Referral of Lower Platte South NRD, 
    261 Neb. 90
    ,
    
    621 N.W.2d 299
    (2001) (concerning landowner’s objection
    to withdrawal and transfer of ground water from his prop-
    erty, where ground water was being transferred away from
    - 258 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    overlying land to neighbor’s property, and landowner argued
    there was significant adverse effect upon him).
    [15] We have previously stated that Nebraska’s common law
    does not allow water to be transferred off overlying land. See
    In re Referral of Lower Platte South 
    NRD, supra
    . However, we
    have made it clear that the Legislature may provide exceptions
    to this common-law rule. See 
    id. We have
    stated:
    “Since the Nebraska common law of ground water per-
    mitted use of the water only on the overlying land, legis-
    lative action was necessary to allow for transfers off the
    overlying land, even for as pressing a need as supplying
    urban water users.
    “. . . [T]he Legislature has the power to determine pub-
    lic policy with regard to ground water and . . . it may be
    transferred from the overlying land only with the consent
    of and to the extent prescribed by the public through its
    elected representatives.”
    In re Referral of Lower Platte South 
    NRD, 261 Neb. at 94
    , 621
    N.W.2d at 303, quoting State ex rel. Douglas v. Sporhase, 
    208 Neb. 703
    , 
    305 N.W.2d 614
    (1981), reversed on other grounds
    
    458 U.S. 941
    , 
    102 S. Ct. 3456
    , 
    73 L. Ed. 2d 1254
    (1982).
    With the general rule that the Legislature may provide
    exceptions to the common-law prohibition of the transfer of
    ground water off the overlying land in mind, we turn to the
    present case. In this regard, we note that Neb. Rev. Stat.
    § 2-3238 (Reissue 2012), provides that each NRD
    shall have the power and authority to develop, store
    and transport water, and to provide, contract for, and
    furnish water service for domestic purposes, irrigation,
    milling manufacturing, mining, metallurgical, and any
    and all other beneficial uses, and to fix the terms and
    rates therefor. Each district may acquire, construct, oper-
    ate, and maintain dams, reservoirs, ground water storage
    areas, canals, conduits, pipelines, tunnels, and any and all
    works, facilities, improvements, and property necessary
    therefor. No district shall contract for delivery of water
    for irrigation uses within any area served by any irrigation
    - 259 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    district, public power and irrigation district, or reclama-
    tion district, except by consent of and written agreement
    with such irrigation district, public power and irrigation
    district, or reclamation district.
    Neb. Rev. Stat. § 46-715 (Cum. Supp. 2016) provides that an
    NRD may create an integrated management plan in order to
    manage a river basin, subbasin, or reach. N-CORPE is such
    an integrated management plan, and one of its purposes is to
    augment the flow of Medicine Creek in order to manage the
    water level in the Republic River Basin. N-CORPE does so by
    withdrawing ground water from a well field in Nebraska and
    releasing the water into Medicine Creek to augment the flow.
    The Legislature has specifically authorized NRD’s to utilize
    augmentation projects as part of an integrated management
    plan. See § 46-715(3)(e).
    Components of a series or collection of statutes pertain-
    ing to a certain subject matter are in pari materia and should
    be conjunctively considered and construed to determine the
    intent of the Legislature, so that different provisions are con-
    sistent, harmonious, and sensible. In re Interest of Tyrone K.,
    
    295 Neb. 193
    , 
    887 N.W.2d 489
    (2016). Reading these statutes
    in pari materia, we determine that NRD’s have the power
    and authority to transport water and that they may do so by
    utilizing an augmentation project as part of an integrated
    management plan. Therefore, the district court did not err
    when it determined that N-CORPE is not prohibited by com-
    mon law from utilizing ground water to augment the flow of
    Medicine Creek.
    No Issue of Material Fact Exists as to
    Whether N-CORPE’s Condemnation
    Meets a Public Purpose.
    Estermann claims that the district court erred when it failed
    to find that there were issues of material fact regarding whether
    N-CORPE’s condemnation action was for a public use. He con-
    tends that these issues preclude entry of summary judgment.
    We find no merit to this assignment of error.
    - 260 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    It is well settled that it is essential that property taken
    under the power of eminent domain be for a public use and
    not a private one. Burlington Northern Santa Fe Ry. Co. v.
    Chaulk, 
    262 Neb. 235
    , 
    631 N.W.2d 131
    (2001). In support
    of his argument that N-CORPE’s easement is not for a public
    use, Estermann relies on Burger v. City of Beatrice, 
    181 Neb. 213
    , 
    147 N.W.2d 784
    (1967). Estermann’s reliance on Burger
    is misplaced.
    In Burger, the landowners sought to enjoin a city from
    proceeding in eminent domain to obtain easements over their
    property to install wells and withdraw ground water beneath
    the surface of their lands. This court determined that the with-
    drawal of the ground water was largely for the private use of
    two private companies. We noted that although the benefit of
    the easements to the companies may furnish some employment
    and increase business in the area, “such a public interest does
    not constitute a public purpose under the power of eminent
    domain.” 
    Id. at 223,
    147 N.W.2d at 791. Accordingly, this court
    determined that the purpose of the easements was for a private
    use, not a public use, and that therefore, it was not proper
    under eminent domain.
    Estermann argues that just as in Burger, the easement
    sought by N-CORPE is for private use, not public use, because
    the N-CORPE project’s purpose is to help private irrigators.
    However, at the hearing on the motion for summary judg-
    ment, the district court received evidence which described in
    detail how N-CORPE’s project would be operated and what
    the purpose of the project was. The purpose was to augment
    flows of Medicine Creek to offset surface water depletions
    through the Republican River Basin in order to achieve the tar-
    get flows identified in the Compact. The evidence shows that
    the overriding purpose of the N-CORPE project is to achieve
    compliance with the Compact; any use by private irrigators
    is incidental to this purpose. Further, the evidence indicates
    that the State’s “[f]ailure to comply with the . . . Compact can
    expose the State of Nebraska to significant liability.” Unlike
    in Burger, where the easements sought were for a private
    - 261 -
    Nebraska Supreme Court A dvance Sheets
    296 Nebraska R eports
    ESTERMANN v. BOSE
    Cite as 
    296 Neb. 228
    use, even viewing the evidence in a light most favorable to
    Estermann, the purpose of the easement sought by N-CORPE
    is for a public use. Therefore, we determine that the district
    court did not err when it determined that N-CORPE’s condem-
    nation action is for a public use.
    CONCLUSION
    As explained above, we determine generally that the district
    court did not err when it granted the appellees’ motion for
    summary judgment. Among our determinations are the follow-
    ing: that N-CORPE had the authority to exercise the power of
    eminent domain, that N-CORPE did not need certain permits
    and approvals as alleged by Estermann, that the district court
    did not abuse its discretion when it denied Estermann’s motion
    to amend the complaint, that N-CORPE is not prohibited
    by common law from removing ground water from overly-
    ing land, and that there is no material issue of fact regard-
    ing whether the condemnation is for a public use. Therefore,
    we affirm the decision of the district court which granted
    the appellees’ motion for summary judgment and dismissed
    Estermann’s complaint.
    A ffirmed.
    

Document Info

Docket Number: S-15-1022

Citation Numbers: 296 Neb. 228

Filed Date: 4/7/2017

Precedential Status: Precedential

Modified Date: 10/25/2019

Authorities (24)

rossie-marie-miller-personal-representative-of-the-estate-of-john-king , 408 F.3d 803 ( 2005 )

in-re-k-tel-international-inc-securities-litigation-pasquale-migliaccio , 300 F.3d 881 ( 2002 )

Sporhase v. Nebraska Ex Rel. Douglas , 102 S. Ct. 3456 ( 1982 )

BURLINGTON NORTHERN & SANTA FE v. Chaulk , 262 Neb. 235 ( 2001 )

Kubicek v. City of Lincoln , 265 Neb. 521 ( 2003 )

Chadd v. Lower Platte South Natural Resources District , 261 Neb. 90 ( 2001 )

Strode v. City of Ashland , 295 Neb. 44 ( 2016 )

Hargesheimer v. Gale , 294 Neb. 123 ( 2016 )

PONDEROSA RIDGE LLV v. Banner County , 250 Neb. 944 ( 1996 )

Bailey v. First Nat. Bank of Chadron , 16 Neb. Ct. App. 153 ( 2007 )

In re Interest of Tyrone K. , 295 Neb. 193 ( 2016 )

Richard H. Hatch, Jr. v. Department for Children, Youth and ... , 274 F.3d 12 ( 2001 )

United States Ex Rel. Keshav S. Joshi v. St. Luke's ... , 441 F.3d 552 ( 2006 )

Bixenmann v. Dickinson Land Surveyors , 294 Neb. 407 ( 2016 )

Stewart v. Nebraska Dept. of Rev. , 294 Neb. 1010 ( 2016 )

Kellogg v. Nebraska Department of Correctional Services , 269 Neb. 40 ( 2005 )

Cisneros v. Graham , 294 Neb. 83 ( 2016 )

Floyd L. Roberson v. Hayti Police Department Paul Sheckell, ... , 241 F.3d 992 ( 2001 )

Vito Milanese, Jr. And Suzanne Milanese v. Rust-Oleum ... , 244 F.3d 104 ( 2001 )

City of Falls City v. NE MUN. POWER POOL , 279 Neb. 238 ( 2010 )

View All Authorities »