Image Group of Toledo, Inc. v. Holland-Springfield Twp. Joint Economic Dev. Zone , 93 N.E.3d 343 ( 2017 )


Menu:
  • [Cite as Image Group of Toledo, Inc. v. Holland-Springfield Twp. Joint Economic Dev. Zone, 
    2017-Ohio-4470
    .]
    IN THE COURT OF APPEALS OF OHIO
    SIXTH APPELLATE DISTRICT
    LUCAS COUNTY
    The Image Group of Toledo, Inc., et al.                   Court of Appeals No. L-16-1058
    Appellants/Cross-Appellees                        Trial Court No. CI0201503107
    v.
    Holland-Springfield Township Joint
    Economic Development Zone, et al.                         DECISION AND JUDGMENT
    Appellees/Cross-Appellants                        Decided: June 23, 2017
    *****
    Cary Rodman Cooper and Margaret J. Lockhart, for appellants/
    cross-appellees.
    Gary O. Sommer, R. Kent Murphree and John P. Lewandowski,
    for appellees/cross-appellants.
    Paul Skaff, for appellee village of Holland.
    *****
    PIETRYKOWSKI, J.
    {¶ 1} This is an appeal and cross-appeal from the judgment of the Lucas County
    Court of Common Pleas. Appellants/cross-appellees, The Image Group of Toledo, Inc.,
    as well as 14 other businesses and one individual (collectively “appellants”), appeal the
    trial court’s determination on summary judgment that Springfield Township and the
    village of Holland complied with the relevant statutory requirements when they created
    the Holland-Springfield Township Joint Economic Development Zone (“JEDZ”).
    Appellees/cross-appellants, Springfield Township, the JEDZ, and the Board of the JEDZ
    (collectively “appellees”), cross-appeal the trial court’s determination that appellants
    have standing to maintain this action. Appellee, the village of Holland (“the Village”),
    did not join in the cross-appeal. For the reasons that follow, we affirm.
    I. Facts and Procedural Background
    {¶ 2} The facts in this matter are undisputed. Effective June 5, 2014, R.C.
    715.691 was amended to provide that a township and municipal corporation “may enter
    into a contract whereby they agree to share in the costs of improvements for an area or
    areas located in one or more of the contracting parties that they designate as a joint
    economic development zone for the purpose of facilitating new or expanded growth for
    commercial or economic development in the state.” The amended statute, however,
    limited the time to create a joint economic development zone to any time before
    January 1, 2015.
    {¶ 3} In July 2014, Springfield Township and the Village entered into an
    agreement to create the JEDZ, which has as its boundaries Angola Road on the north,
    Airport Highway on the south, Holland-Sylvania Road on the east, and McCord Road on
    the west. The agreement was approved by voters in November 2014. In December 2014,
    2.
    the JEDZ Board of Directors enacted a 1.5 percent income tax, to become effective on
    July 1, 2015. On June 24, 2015, appellants, who are all within the boundaries of the
    JEDZ and thus subject to the tax, filed an action to enjoin the implementation of the tax,
    and to obtain a declaratory judgment that the contract creating the JEDZ is void. As the
    basis for their complaint, appellants alleged that appellees failed to adhere to the statutory
    requirements in R.C. 715.691 when creating the JEDZ.
    {¶ 4} On July 21, 2015, appellees filed a motion for summary judgment, arguing
    that appellants lacked standing to challenge the validity of the JEDZ.1 On August 21,
    2015, appellees filed an additional motion for partial summary judgment, arguing that
    there is no genuine issue of material fact that the JEDZ was validly created, leaving only
    the issue of the validity of the tax imposed by the JEDZ. Also on August 21, 2015,
    appellants filed their motion for summary judgment, arguing that the JEDZ itself was
    invalid because appellees failed to satisfy the statutory requirements, and that the tax
    imposed by the JEDZ was invalid because it did not comply with R.C. 715.691(H).
    {¶ 5} On October 20, 2015, the trial court entered its judgment in which it found
    that appellants had standing to pursue the action, but that the creation of the JEDZ
    complied with the statutory requirements and thus was valid. Appellants appealed the
    October 20, 2015 judgment, but we dismissed the appeal for lack of a final appealable
    order because the judgment entry did not resolve the issue of whether the tax imposed by
    the JEDZ was valid. On February 18, 2016, the trial court entered a second judgment,
    1
    The Village filed a similar motion on August 18, 2015.
    3.
    incorporating its determination that the 1.5 percent income tax imposed by the JEDZ was
    invalid.
    II. Assignments of Error
    {¶ 6} Appellants have timely appealed the trial court’s February 18, 2016
    judgment, asserting seven assignments of error for our review:
    1. The trial court erred as a matter of law in ruling that the Village
    agreed in the JEDZ Contract to share in the costs of improvements for the
    Joint Economic Development Zone as required by R.C. 715.691(B).
    2. The trial court erred as a matter of law in ruling that the JEDZ
    Contract is valid even though the Defendants did not include in the JEDZ
    Contract or in the Economic Development Plan a schedule for the
    implementation or provision of any new, expanded or additional services,
    facilities or improvements within the JEDZ as required by R.C.
    715.691(C); and further by ruling that there is no requirement that at least
    50% of the revenue from the new tax must be spent for such improvements
    as required by R.C. 715.691(H).
    3. The trial court erred as a matter of law in ruling that the JEDZ
    Contract sets forth the Village’s contribution to the Joint Economic
    Development Zone as required by R.C. 715.691(C).
    4.
    4. The trial court erred as a matter of law in ruling that the Joint
    Economic Development Review Council was properly appointed as
    required by R.C. 715.692.
    5. The trial court erred as a matter of law in ruling, without analysis,
    that the Township and Village held a public hearing concerning the
    Contract and the Zone and that they made a final copy of the JEDZ
    Contract and Economic Development Plan available 30 days in advance of
    the public hearing as required by R.C. 715.691(D).
    6. The trial court mistakenly disregarded undisputed evidence and
    erred as a matter of law in ruling that the Township properly filed with the
    Board of Elections a copy of the Resolution approving the JEDZ Contract
    as required by R.C. 715.691(F).
    7. The trial court erred as a matter of law in ruling that there was
    sufficient consideration for the JEDZ Contract and that Plaintiffs could not
    challenge the JEDZ Contract for lack of consideration because Plaintiffs are
    not parties or third-party beneficiaries to the JEDZ Contract.
    {¶ 7} Additionally, appellees have timely cross-appealed the trial court’s
    February 18, 2016 judgment, asserting one assignment of error for our review:
    1. The trial court erred in finding the Appellants have standing to
    challenge the tax.
    5.
    III. Analysis
    {¶ 8} We will begin with appellees’ assignment of error in their cross-appeal.
    A. Standing
    {¶ 9} “Whether a party has established standing to bring an action before the court
    is a question of law, which we review de novo.” Moore v. City of Middletown, 
    133 Ohio St.3d 55
    , 
    2012-Ohio-3897
    , 
    975 N.E.2d 977
    , ¶ 20. “‘Standing’ is defined at its most basic
    as ‘[a] party’s right to make a legal claim or seek judicial enforcement of a duty or
    right.’” Clifton v. Village of Blanchester, 
    131 Ohio St.3d 287
    , 
    2012-Ohio-780
    , 
    964 N.E.2d 414
    , ¶ 15, quoting Ohio Pyro, Inc. v. Ohio Dept. of Commerce, 
    115 Ohio St.3d 375
    , 
    2007-Ohio-5024
    , 
    875 N.E.2d 550
    , ¶ 27. “‘[T]he question of standing depends upon
    whether the party has alleged such a personal stake in the outcome of the controversy
    * * * as to ensure that the dispute sought to be adjudicated will be presented in an
    adversary context and in a form historically viewed as capable of judicial resolution.’”
    (Internal quotations omitted.) 
    Id.
     “To succeed in establishing standing, plaintiffs must
    show that they suffered (1) an injury that is (2) fairly traceable to the defendant’s
    allegedly unlawful conduct, and (3) likely to be redressed by the requested relief.”
    Moore at ¶ 22, citing Lujan v. Defenders of Wildlife, 
    504 U.S. 555
    , 560-561, 
    112 S.Ct. 2130
    , 
    119 L.Ed.2d 351
     (1992). Notably, the Ohio Supreme Court has cautioned that
    “standing is not a technical rule intended to keep aggrieved parties out of court. ‘Rather,
    it is a practical concept designed to insure that courts and parties are not vexed by suits
    brought to vindicate nonjusticiable interests and that judicial decisions which may affect
    6.
    the rights of others are forged in hot controversy, with each view fairly and vigorously
    represented.’” Id. at ¶ 47, quoting Fort Trumbull Conservancy, L.L.C. v. Alves, 
    262 Conn. 480
    , 486, 
    815 A.2d 1188
     (2003).
    {¶ 10} In support of their assignment of error, appellees argue that appellants lack
    standing to challenge the creation of the JEDZ because they have not alleged an injury
    that is different from that suffered by the public in general. See Cuyahoga Cty. Bd. of
    Commrs. v. State, 
    112 Ohio St.3d 59
    , 
    2006-Ohio-6499
    , 
    858 N.E.2d 330
    , ¶ 22 (“In Ohio,
    it is well established that standing to attack the constitutionality of a legislative enactment
    exists only where a litigant has suffered or is threatened with direct and concrete injury in
    a manner or degree different from that suffered by the public in general, that the law in
    question has caused the injury, and that the relief requested will redress the injury.”).
    Appellees point out that appellants are similarly situated to the other 400 business that are
    located within the JEDZ. Thus, appellees conclude that appellants’ complaint is a
    generalized grievance in that appellants have not established a particularized injury.
    {¶ 11} Appellants respond that they do not share the same burden as the public
    generally. Appellants argue that the voters of all of Springfield Township approved the
    JEDZ, but that the JEDZ is limited in application to a discreet group of businesses and
    employees located within a small portion of Springfield Township. Appellants rely on
    State ex rel. Masterson v. Ohio State Racing Comm., 
    162 Ohio St. 366
    , 
    123 N.E.2d 1
    (1954), in which the Ohio Supreme Court held that an individual did not have standing as
    7.
    a general taxpayer to challenge expenditures by the Ohio State Racing Commission. The
    court quoted the general rule regarding standing under the common law,
    Even in the absence of legislation, a taxpayer has a right to call upon
    a court of equity to interfere to prevent the consummation of a wrong such
    as occurs when public officials attempt to make an illegal expenditure of
    public money, or to create an illegal debt, which he, in common with other
    property holders of the taxing district, may otherwise be compelled to pay.
    It is equally fundamental that at common law and apart from statute,
    a taxpayer can not bring an action to prevent the carrying out of a public
    contract or the expenditure of public funds unless he has some special
    interest therein by reason of which his own property rights are put in
    jeopardy. In other words, private citizens may not restrain official acts
    when they fail to allege and prove damage to themselves different in
    character from that sustained by the public generally. (Internal citations
    omitted.) Id. at 368.
    {¶ 12} Appellants argue that, unlike the public generally, they are required to pay
    taxes created by the JEDZ, a portion of which is to be used to reinvest in the JEDZ.
    Thus, appellants reason that they have a special interest in the JEDZ tax funds, and
    therefore have standing to challenge the legality of the JEDZ. We agree.
    {¶ 13} Here, the limited applicability of the JEDZ tax constitutes a discreet and
    particularized injury to appellants and others located within the JEDZ that is different
    8.
    from that suffered by the public at large. Consequently, we hold that appellants have
    standing to challenge the legality of the JEDZ. See Brinkman v. Miami Univ., 12th Dist.
    Butler No. CA2006-12-313, 
    2007-Ohio-4372
    , ¶ 35 (“Masterson established that if a
    challenged expenditure derives from a special fund, and if the plaintiff belongs to the
    class of individuals who contributed to the fund, the plaintiff has standing.”).
    {¶ 14} Accordingly, appellees’ assignment of error on cross-appeal is not well-
    taken.
    B. Validity of JEDZ Contract
    {¶ 15} In their appellate brief, appellants challenge the trial court’s determination
    on summary judgment that the creation of the JEDZ adhered to the statutory
    requirements. We review the grant of a motion for summary judgment de novo, applying
    the same standard as the trial court. Lorain Natl. Bank v. Saratoga Apts., 
    61 Ohio App.3d 127
    , 129, 
    572 N.E.2d 198
     (9th Dist.1989); Grafton v. Ohio Edison Co., 
    77 Ohio St.3d 102
    , 105, 
    671 N.E.2d 241
     (1996). Under Civ.R. 56(C), summary judgment is appropriate
    where (1) no genuine issue as to any material fact exists; (2) the moving party is entitled
    to judgment as a matter of law; and (3) reasonable minds can come to but one conclusion,
    and viewing the evidence most strongly in favor of the nonmoving party, that conclusion
    is adverse to the nonmoving party. Harless v. Willis Day Warehousing Co., 
    54 Ohio St.2d 64
    , 66, 
    375 N.E.2d 46
     (1978).
    9.
    1. R.C. 715.691(B)
    {¶ 16} In their first assignment of error, appellants argue that the JEDZ contract
    does not satisfy the requirements of R.C. 715.691(B), which provides,
    This section provides procedures and requirements for creating and
    operating a joint economic development zone. This section applies only if
    one of the contracting parties to the zone does not levy a municipal income
    tax under Chapter 718. of the Revised Code.
    At any time before January 1, 2015, two or more municipal
    corporations or one or more townships and one or more municipal
    corporations may enter into a contract whereby they agree to share in the
    costs of improvements for an area or areas located in one or more of the
    contracting parties that they designate as a joint economic development
    zone for the purpose of facilitating new or expanded growth for commercial
    or economic development in the state. The contract and zone shall meet the
    requirements of divisions (B) to (J) of this section.
    In particular, appellants challenge the conclusion that the Village agreed to share in the
    costs of improvements for the JEDZ.
    {¶ 17} Section 2.3 of the Joint Economic Development Zone Contract between
    Holland and Springfield Township sets forth the parties relative contributions:
    The Township shall furnish or cause to be furnished to the JEDZ all
    usual and customary governmental services furnished by the Township to
    10.
    the other territory of the Township, including, but not limited to
    maintenance and snow removal of Township-owned roads, fire protection,
    emergency medical services and general administration, and furnish to the
    JEDZ such services allowed by law and which the Township and the
    [JEDZ] Board deem appropriate and agree.
    The Village shall, pursuant to the JEDZ Income Tax Agreement,
    furnish or cause to be furnished the services set forth in the Income Tax
    Agreement and may furnish to the JEDZ such services as allowed by law
    and which the Village and the Board deem appropriate and agree. The
    Village will also engage in activities to promote, compliment and benefit
    economic development in the JEDZ as determined in the sole discretion of
    the Village. The Village is not expected or required to undertake any such
    activity to the detriment of economic development in the Village. Other
    than the services to be provided by the Village pursuant to the JEDZ
    Income Tax Agreement and this paragraph, nothing contained herein shall
    be construed as obligating the Village to provide any particular service,
    level of service, or financial commitment to the JEDZ, and such matters
    shall be left to the further agreement of the Village and the [JEDZ] Board.
    {¶ 18} Appellants argue that under the terms of the agreement, the Village is not
    required to contribute money or services for improvements in the JEDZ. In further
    support of their position, appellants cite an Addendum to the Joint Economic
    11.
    Development Zone Contract to clarify the fourth paragraph in Section 4.3, which
    provided,
    In accordance with paragraph (H) of R.C. 715.691, as amended by
    HB No. 289, not less than fifty percent (50%) of the revenue from the tax
    shall be used solely to provide the new, expanded, or additional services,
    facilities, or improvements specified in the economic development plan.
    Said moneys shall come from and include the tax administration payments
    (4.1 herein), the revenues allocated to the Board, (3.2 herein), and the
    balance from the contracting parties.
    The Addendum clarified,
    The parties agree that Section 4.3 of the Agreement, specifically the
    fourth paragraph of said Section, is intended to set forth that Holland will,
    at its sole discretion, provide services to the JEDZ area, including, but not
    limited to, maintenance and improvements to rights of way, and that the
    value of such services shall be applied to the fifty percent requirement set
    forth in R.C. 715.691. Holland shall not be obligated to contribute money
    or services to the JEDZ beyond those services provided by it at its
    discretion. And, further, that the Township shall make up any deficiency
    resulting after application of the value of Holland services to the JEDZ to
    the extent that Township has received a Section 715.691 distribution of Net
    Revenue during the previous annual period.
    12.
    Finally, appellants cite the minutes of the July 28, 2014 Springfield Township Trustees’
    Meeting, in which it was acknowledged that “the Village of Holland is only a partner for
    legislative purposes.” From this evidence, appellants conclude that the Village has no
    obligation to share in the costs of the improvements to the JEDZ, and therefore the JEDZ
    Contract does not satisfy R.C. 715.691(B).
    {¶ 19} In response, appellees note that under R.C. 715.691(C), each party’s
    contributions to the JEDZ “may be in any form that the contracting parties agree to, and
    may include, but are not limited to, the provision of services, money, or equipment.”
    Appellees then assert that the Village agreed to “engage in activities to promote,
    compliment and benefit economic development in the JEDZ,” and, in the Village’s
    discretion, “provide services to the JEDZ area, including, but not limited to, maintenance
    and improvements to rights of way.” The Village also adds that its agreement to provide
    tax administration services constitutes a contribution to the JEDZ. Appellees argue that
    R.C. 715.691(B) and (C) do not require an even split of the costs of the improvements to
    the JEDZ, and therefore because the Village has agreed to contribute to the JEDZ in some
    manner, the statute is satisfied.
    {¶ 20} Upon consideration, we are persuaded by appellees’ argument. R.C.
    715.691(B) requires only that the parties agree to share in the costs of improvements for
    the purpose of “facilitating new or expanded growth for commercial or economic
    development in the state.” R.C. 715.691(C) then defines “contributions” broadly to be in
    any form to which the contracting parties agree. Here, the parties agreed to the Village’s
    13.
    nominal contribution to “engage in activities to promote, compliment and benefit
    economic development in the JEDZ as determined in the sole discretion of the Village,”
    and the Village’s possible contribution to “maintenance and improvements to rights of
    way,” as provided in the Village’s discretion. While not a significant contribution, the
    Village’s role is nonetheless what the parties agreed to for the stated purpose of
    facilitating new or expanded growth for commercial and economic development within
    the JEDZ. Therefore, we hold that the JEDZ Contract satisfies R.C. 715.691(B).
    {¶ 21} Accordingly, appellants’ first assignment of error is not well-taken.
    2. R.C. 715.691(C)
    {¶ 22} In their second assignment of error, appellants present two arguments why
    the JEDZ contract does not comply with R.C. 715.691(C), which provides, in pertinent
    part,
    The contract shall set forth each contracting party’s contribution to
    the joint economic development zone. The contributions may be in any
    form that the contracting parties agree to, and may include, but are not
    limited to, the provision of services, money, or equipment. * * * If the
    contract is approved by the electors of any contracting party under division
    (F) of this section or substantially amended after the effective date of H.B.
    289 of the 130th general assembly, the contracting parties shall include
    within the contract or the amendment to the contract an economic
    development plan for the zone, a schedule for the implementation or
    14.
    provision of any new, expanded, or additional services, facilities, or
    improvements within the zone or in the area surrounding the zone, and any
    provisions necessary for the contracting parties to create a joint economic
    development review council in compliance with section 715.692 of the
    Revised Code.
    {¶ 23} Appellants’ first argument is that the contract fails to set forth any
    contribution to be made by the Village. This is also the subject of appellants’ third
    assignment of error, which they do not argue separately. Appellants’ first argument is
    effectively a reassertion of the argument made in appellants’ first assignment of error,
    and for the reasons stated above is not persuasive.
    {¶ 24} In their second argument, appellants contend that the parties have failed to
    provide “a schedule for the implementation or provision of any new, expanded, or
    additional services, facilities, or improvements within the zone or in the area surrounding
    the zone,” because there are no proposed new, expanded, or additional services or
    improvements. Relevant here, the JEDZ Economic Development Plan states,
    4. Schedule for provision of new, expanded, or additional services,
    facilities, or improvement:
    A. The Township shall use a portion of the allocation of the income
    tax it receives to pay a portion of the costs of public services. The
    Township shall provide for the construction and improvement of such roads
    15.
    in the Township it deems appropriate to provide an improved transportation
    network to benefit JEDZ.
    B. The Township shall furthermore provide expanded public
    services to the JEDZ in the form of: police protection, fire protection, civil
    defense, and local government administration, commensurate with
    economic growth. The Township expects to provide a superior level of
    services in order to attract development and to support commerce once it is
    established. Participating in JEDZ revenues may enable Township
    expenditures in furtherance of improvements which are already planned and
    utilization of tax increment financing and inter-governmental agreements
    pertaining thereto also in furtherance of improvements.
    ***
    F. Intended contributions of the parties assume adequacy of net tax
    revenues, anticipated revenues, funding from other sources, and availability
    of financing upon acceptable terms in order to provide necessary funding
    for projects and services. As of the day of commencement of the JEDZ
    Contract, the contracting parties do not have the specific revenue
    projections and final construction estimates to enable defined
    improvements and improvement schedules. Nevertheless, the contracting
    parties shall exercise due diligence in planning for improvements and
    undertaking construction in furtherance of economic development to
    16.
    benefit the JEDZ, the contracting parties, Lucas County, and the State of
    Ohio.
    {¶ 25} Appellants argue that R.C. 715.691(C) requires that the economic
    development plan provide for new or additional services and improvements. They reason
    that the word “any,” which immediately precedes “new, expanded, or additional services,
    facilities, or improvements,” is not a term of limitation, but instead means “every” or
    “all.” Appellants further support their argument by referencing R.C. 715.691(H), which
    states,
    The contract may grant to the board of directors appointed under
    division (G) of this section the power to adopt a resolution to levy an
    income tax within the zone. The income tax shall be used for the purposes
    of the zone and for the purposes of the contracting parties pursuant to the
    contract. Not less than fifty per cent of the revenue from the tax shall be
    used solely to provide the new, expanded, or additional services, facilities,
    or improvements specified in the economic development plan until all such
    services, facilities, or improvements have been completed as specified in
    that plan.
    From this, it could be derived that the legislature presumed and intended that the
    economic development plan include new, expanded, or additional services, facilities, or
    improvements.
    17.
    {¶ 26} Appellees, on the other hand, argue that the use of the word “any” in R.C.
    715.691(C) must be read to mean “if any;” that is, if there are any new, expanded, or
    additional services, facilities, or improvements, then the economic development plan
    must include a schedule for them. We agree.
    {¶ 27} “The primary rule in statutory construction is to give effect to the
    legislature’s intention.” Cline v. Ohio Bur. of Motor Vehicles, 
    61 Ohio St.3d 93
    , 97, 
    573 N.E.2d 77
     (1991). “In determining intent, it is the duty of the court to give effect to the
    words used, not to delete words used or insert words not used.” 
    Id.
     “Where the language
    of a statute is plain and unambiguous and conveys a clear and definite meaning, there is
    no need to apply rules of statutory interpretation.” Id. at 96. “However, where a statute
    is found to be subject to various interpretations, a court called upon to interpret its
    provisions may invoke rules of statutory construction in order to arrive at legislative
    intent.” Id. Here, we find that the language of the statute is plain and unambiguous.
    {¶ 28} Under R.C. 715.691, there is no affirmative mandate that an economic plan
    must provide for new, expanded, or additional services, facilities, or improvements. Had
    the legislature intended such a mandate, it simply could have omitted the word “any” in
    R.C. 715.691(C). Rather, the clear meaning of the statute as written is that if new,
    expanded, or additional services, facilities, or improvements are part of the economic
    development plan, a schedule for them must be included. In this case, because there are
    no identified new or additional services, facilities, or improvements, the JEDZ Economic
    18.
    Development Plan is not flawed for failing to include a schedule. Therefore, we hold that
    the JEDZ Economic Development Plan satisfies R.C. 715.691(C).
    {¶ 29} As an additional matter, we note that appellants contest the trial court’s
    conclusion that because there are no scheduled new, expanded, or additional services,
    facilities, or improvements, none of the income tax revenue generated by the JEDZ must
    be spent in the JEDZ. However, we do not reach this issue at this time because under the
    facts on summary judgment, no income tax revenue has yet been collected. Thus, any
    directive as to how the revenue is permitted to be used under R.C. 715.691(H) would be
    purely advisory. See Reinbolt v. Natl. Fire Ins. Co., 
    158 Ohio App.3d 453
    , 2004-Ohio-
    4845, 
    816 N.E.2d 1083
    , ¶ 13 (6th Dist.) (“[C]ourts have the power to resolve present
    disputes and controversies, but do not have authority to issue advisory opinions to
    prevent future disputes.”).
    {¶ 30} Accordingly, appellants’ second and third assignments of error are not
    well-taken.
    3. R.C. 715.692(C)(2)(c)
    {¶ 31} In their fourth assignment of error, appellants challenge the method by
    which the Joint Economic Development Review Council (“JEDRC”) was formed.
    Relevant here, R.C. 715.692(C)(2)(c) provides,
    Except as provided by division (C)(2)(d) of this section, four
    appointed members shall be owners of businesses operating within the zone
    or an individual designated by such an owner. The contracting parties shall
    19.
    first appoint the owners of the four businesses that employ the most persons
    within the zone. If one or more of these owners is unwilling or unable to
    serve as a member of the council or to designate an individual to serve in
    the owner’s place, the contracting parties shall appoint the owner of the
    business that employs the next most number of persons within the zone
    until each position to be appointed under this division is filled. No business
    may have more than one owner or a designee thereof serving as a member
    of the council at any time.
    {¶ 32} To demonstrate their compliance with R.C. 715.692(C)(2)(c), appellees
    submitted the affidavit of Leslie Kohli, the Springfield Township Administrator, in which
    she described her efforts to ascertain and appoint the four largest employers. Kohli stated
    that she identified the businesses that might be the larger employers in the JEDZ through
    publicly available information, consultation with the Lucas County Auditor, and
    experience living and working in Springfield Township. Kohli then contacted those
    businesses by telephone, email, or in person to inquire as to the number of their
    employees, and their willingness to serve on the JEDRC. Kohli identified Sam’s Club,
    First Energy, Kroger, and Kohl’s as the four largest employers. Sam’s Club and First
    Energy accepted appointments. Kroger declined an appointment since the store was
    moving out of the JEDZ. Kohl’s was unavailable to attend the JEDRC meeting and
    failed to respond to future requests and notices regarding a new date for the meeting.
    Kohli stated that Target also was considered for an appointment, and was contacted by
    20.
    phone, email, in person, and by delivering a letter. However, Target failed to respond
    with how many employees it had until July 28, 2014, well after the meeting time for the
    JEDRC. The next two businesses reporting the most employees were McDonald’s (90
    employees) and Kellermeyer (77 employees), both of which accepted appointments.
    {¶ 33} Appellants posit that the statute requires that representatives of the four
    businesses with the most employees be appointed, and only if they are then unwilling or
    unable to serve will a replacement be appointed. Thus, appellants conclude that Kohli’s
    process of determining whether businesses were willing and able to serve before
    appointing them was in contravention of the statute. In their brief, appellants argue that
    the trial court erred by granting deference to the Township’s interpretation of what was
    required by R.C. 715.692(C)(2)(c). However, we note that this is a matter of statutory
    compliance, not interpretation. Thus, the relevant issue is whether a genuine issue of
    material fact exists that appellees have not complied with the unambiguous language of
    R.C. 715.692(C)(2)(c). We hold that it does not.
    {¶ 34} R.C. 715.692(C)(2)(c) requires that the four largest employers who are
    willing and able to serve be appointed to the JEDRC, and provides a method for
    achieving this result. We find that appellants’ argument that businesses must first be
    appointed and then removed elevates form over substance. Here, appellees have
    presented evidence through Kohli’s affidavit that the four willing and able businesses
    employing the most employees have been appointed to the JEDRC. Appellants have not
    21.
    presented any evidence to the contrary.2 Therefore, we hold that appellees have complied
    with R.C. 715.692(C)(2)(c) in forming the JEDRC.
    {¶ 35} Accordingly, appellants’ fourth assignment of error is not well-taken.
    4. R.C. 715.691(D)
    {¶ 36} In their fifth assignment of error, appellants argue that the parties to the
    JEDZ failed to comply with the public hearing requirements in R.C. 715.691(D), which
    provides,
    Before the legislative authority of any of the contracting parties
    enacts an ordinance or resolution approving a contract to designate a joint
    economic development zone, the legislative authority of each of the
    contracting parties shall hold a public hearing concerning the contract and
    zone. Each legislative authority shall provide at least thirty days public
    2
    Although not referenced in their brief on appeal, in their opposition to appellees’ motion
    for summary judgment, appellants submitted the affidavit of Anna Williams, an
    authorized custodian of records for Texas Roadhouse, Inc., which authenticated records
    of pay checks issued to employees for time worked in July and December 2014. The
    number of paychecks issued was well over 100 for each pay period in both months. In
    contrast, Kohli’s affidavit indicates that she was informed by a manager over the phone
    that Texas Roadhouse, Inc., had fewer than 50 employees. Similarly, in support of their
    motion for summary judgment, appellants submitted the affidavit of Larissa Sipprell, the
    Workforce Administration Manager for Best Buy Enterprise Services. Sipprell’s
    affidavit authenticated records showing that 80 employees were employed at Best Buy
    Store #247 in July 2014, and 110 during November to December 2014. Notably, there is
    no indication that store #247 is located in the JEDZ. In contrast, Kohli’s affidavit states
    that she was informed in person that there were 60 employees at the store. Nevertheless,
    neither Williams’ affidavit nor Sipprell’s affidavit states that the companies were willing
    and able to serve on the JEDRC, and thus the affidavits do not demonstrate that the
    companies were wrongfully excluded.
    22.
    notice of the time and place of the public hearing in a newspaper of general
    circulation in the municipal corporation or township. During the thirty-day
    period prior to the public hearing, all of the following documents shall be
    available for public inspection in the office of the clerk of the legislative
    authority of a municipal corporation that is a contracting party and in the
    office of the fiscal officer of a township that is a contracting party:
    (1) A copy of the contract designating the zone;
    (2) A description of the area or areas to be included in the zone,
    including a map in sufficient detail to denote the specific boundaries of the
    area or areas;
    (3) An economic development plan for the zone that includes a
    schedule for the provision of any new, expanded, or additional services,
    facilities, or improvements.
    A public hearing held under division (D) of this section shall allow
    for public comment and recommendations on the contract and zone. The
    contracting parties may include in the contract any of those
    recommendations prior to approval of the contract.
    {¶ 37} In support of their assignment of error, appellants argue solely that the
    parties to the JEDZ failed to provide 30 days to review the amended JEDZ Contract and
    JEDZ Economic Development Plan. Springfield Township and the Village held public
    hearings on the proposed JEDZ in June 2014. Thereafter, on July 11, 2014, the JEDRC
    23.
    approved the JEDZ Economic Development Plan with one amendment. Prior to the
    amendment, Section 4(C)(3) of the plan read: “C. Holland may upon request of the
    JEDZ Board provide: * * * (3) Provide (sic) maintenance of a roundabout and McCord
    Rd. underpass right-of-way / ramp area.” The amendment changed Section 4(C)(3) to
    state: “C. Holland may upon request of the JEDZ Board provide: * * * (3) Provide (sic)
    maintenance and improvements to public rights of way.” Ten days later, on July 21,
    2014, Springfield Township approved the proposed JEDZ Contract, which incorporated
    the JEDZ Economic Development Plan. The Village reviewed the JEDZ Contract on
    July 22, 2014, and proposed the addendum to clarify the fourth paragraph in Section 4.3
    discussed in appellant’s first assignment of error. The addendum was agreed to on
    July 29, 2014, and the JEDZ Contract and addendum were approved by the Village by
    emergency ordinance on the same day. Springfield Township did not separately pass an
    ordinance approving the addendum to the JEDZ Contract. Because the amended JEDZ
    Economic Development Plan and the JEDZ Contract with the addendum were not
    available for inspection for 30 days prior to a public hearing, appellants conclude that
    R.C. 715.691(D) was violated.
    {¶ 38} We are not persuaded by appellants’ argument. As identified by appellees,
    715.691(D) does not require an additional 30 days of public inspection every time a
    change is made to the proposed contract. Indeed, the last sentence of R.C. 715.691(D)
    expressly provides that the contracting parties may include any recommendations prior to
    approval of the contract. Here, it is not in dispute that the JEDZ Contract, a description
    24.
    of the boundaries of the zone, and the JEDZ Economic Development Plan were available
    for public inspection for 30 days prior to a public hearing. Therefore, we hold that the
    parties to the JEDZ complied with R.C. 715.691(D), and our decision is not impacted by
    the fact that minor amendments and clarifications were made prior to the final approval
    of the JEDZ Contract.
    {¶ 39} Accordingly, appellant’s fifth assignment of error is not well-taken.
    5. R.C. 715.691(E)
    {¶ 40} In their sixth assignment of error, appellants assert that the JEDZ is invalid
    because Springfield Township did not submit the full resolution approving the JEDZ
    Contract, or any resolution approving the addendum, to the Board of Elections as
    required by R.C. 715.691(E). That section provides,
    After the public hearings required under division (D) of this section
    have been held and the economic development plan has been approved
    under division (D) of section 715.692 of the Revised Code, and before
    January 1, 2015, each contracting party may enact an ordinance or
    resolution approving the contract to designate a joint economic
    development zone. After each contracting party has enacted an ordinance
    or resolution, the clerk of the legislative authority of a municipal
    corporation that is a contracting party and the fiscal officer of a township
    that is a contracting party shall file with the board of elections of each
    county within which a contracting party is located a copy of the ordinance
    25.
    or resolution approving the contract and shall direct the board of elections
    to submit the ordinance or resolution to the electors of the contracting party
    on the day of the next general, primary, or special election occurring at least
    ninety days after the ordinance or resolution is filed with the board of
    elections. If any of the contracting parties is a township, however, then
    only the township or townships shall submit the resolution to the electors.
    R.C. 715.691(E).
    {¶ 41} In this case, Springfield Township did not submit a copy of the JEDZ
    Contract with the resolution, despite the fact that the resolution referred to it as an
    exhibit. However, it did submit a copy of the resolution itself, which is all that is
    required by the statute. Therefore, we hold that Springfield Township complied with
    R.C. 715.691(E).
    {¶ 42} Accordingly, appellants’ sixth assignment of error is not well-taken.
    6. Adequacy of Consideration
    {¶ 43} In their seventh and final assignment of error, appellants contend that the
    JEDZ Contract is void for lack of consideration under the general principles of contract
    law. Specifically, appellants argue that Springfield Township agreed in the contract only
    to provide the “usual and customary services” of road maintenance, fire protection,
    emergency medical services, and general administration. Because Springfield Township
    is already legally obligated to provide those services, appellants argue that Springfield
    Township has offered no consideration.
    26.
    {¶ 44} However, under general contract law, appellants are incidental beneficiaries
    to the JEDZ Contract and thus lack standing to challenge the adequacy of the contract’s
    consideration. See Huff v. FirstEnergy Corp., 
    130 Ohio St.3d 196
    , 
    2011-Ohio-5083
    , 
    957 N.E.2d 3
    , ¶ 11 (an incidental beneficiary “has no enforceable rights under the contract.”).
    Furthermore, Springfield Township has provided consideration in that it has agreed under
    the JEDZ Contract to provide “expanded” public services, beyond those which it was
    already providing, and to “provide for the construction and improvement of such roads in
    the Township it deems appropriate to provide an improved transportation network to
    benefit the JEDZ.” Therefore, we hold that the JEDZ Contract does not fail for lack of
    consideration.
    {¶ 45} Accordingly, appellants’ seventh assignment of error is not well-taken.
    IV. Conclusion
    {¶ 46} For the foregoing reasons, we hold that appellants have standing to
    challenge the creation of the JEDZ. We further hold that the creation of the JEDZ meets
    the statutory requirements. Thus, we find that substantial justice has been done the
    parties complaining, and the judgment of the Lucas County Court of Common Pleas is
    affirmed. Pursuant to App.R. 24, appellants are ordered to pay the costs associated with
    the appeal, and appellees are ordered to pay the costs associated with the cross-appeal.
    Judgment affirmed.
    27.
    The Image Group of Toledo, Inc.
    v. Holland-Springfield Twp. Joint
    Economic Dev. Zone
    C.A. No. L-16-1058
    A certified copy of this entry shall constitute the mandate pursuant to App.R. 27.
    See also 6th Dist.Loc.App.R. 4.
    Mark L. Pietrykowski, J.                       _______________________________
    JUDGE
    Arlene Singer, J.
    _______________________________
    Thomas J. Osowik, J.                                       JUDGE
    CONCUR.
    _______________________________
    JUDGE
    28.