S. Davis-Haas v. Exeter Twp. ZHB and MetroDev V, LP and Exeter Twp. , 2017 Pa. Commw. LEXIS 478 ( 2017 )


Menu:
  •            IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Sue Davis-Haas, Richard H. Haas,              :
    Ida C. Smith, Zildia Perez, Leon              :
    Perez, Donna Galczynski, Kevin                :
    Galczynski, Alan Ganas, Renee                 :
    Froelich, Scott Matthews, Patricia            :
    J. Miravich, John J. Miravich and             :
    William Ryan,                                 :
    Appellants          :
    :   No. 1739 C.D. 2016
    v.                            :   Argued: June 5, 2017
    :
    Exeter Township Zoning Hearing                :
    Board and MetroDev V, LP and                  :
    Exeter Township                               :
    BEFORE:         HONORABLE ROBERT SIMPSON, Judge
    HONORABLE ANNE E. COVEY, Judge (P.)
    HONORABLE BONNIE BRIGANCE LEADBETTER, Senior Judge
    OPINION
    BY JUDGE SIMPSON                              FILED: July 12, 2017
    In this, the most recent of several related appeals in this land use case,
    Objectors1 ask whether the Court of Common Pleas of Berks County2 (trial court)
    erred in affirming a decision of the Exeter Township Zoning Hearing Board (ZHB)
    that sustained MetroDev V, LP’s (Landowner) procedural validity challenge.
    Objectors argue the trial court erred in failing to: (1) enforce a settlement
    agreement reached by the parties; (2) find that Landowner’s 2005 procedural
    1
    Objectors are Sue Davis-Haas, Richard H. Haas, Ida C. Smith, Zildia Perez, Leon Perez,
    Donna Galczynski, Kevin Galczynski, Alan Ganas, Renee Froelich, Scott Matthews, Patricia J.
    Miravich, John J. Miravich and William Ryan.
    2
    The Honorable Madelyn S. Fudeman presided.
    challenge to and the process Landowner followed was defective and Objectors’
    rights were violated; and (3) determine Landowner lacked standing to prosecute its
    procedural validity challenge. Upon review, we affirm.
    I. Background
    This case has an extensive procedural history, most of which was set
    forth in this Court’s decision in Metro Dev V, LP v. Exeter Township Zoning
    Hearing Board (Pa. Cmwlth., No. 1367 C.D. 2013, filed July 24, 2014), 
    2014 WL 3697529
     (unreported). There, we explained that Objectors own properties adjacent
    to Landowner’s proposed residential development. Landowner’s property (subject
    property) consists of approximately 46.36 acres3 in an area where the boundary
    lines of the Township of Exeter (Township), and two surrounding municipalities,
    Lower Alsace Township and Alsace Township, meet.
    Prior to July 25, 2005, the Township’s Zoning Ordinance No. 500 (old
    ordinance) was in effect. Under the old ordinance, the subject property was zoned
    low density residential.      On July 25, 2005, the Township enacted Zoning
    Ordinance No. 596 (new ordinance), which changed the zoning classification of
    the property from low density residential to suburban residential. The changed
    classification had the practical effect of reducing the number of residential lots
    permitted on the subject property from 30 to 7.
    3
    As explained more fully below, in 2012, Landowner sold a 0.51-acre portion of its
    property, but retained the remainder.
    2
    In August 2005, Landowner filed a challenge to the validity of the
    new ordinance with the ZHB pursuant to former Section 10909.1(a)(2) of the
    Pennsylvania     Municipalities    Planning     Code    (MPC)4     alleging    procedural
    irregularities in its adoption.
    In September 2005, a preliminary subdivision plan was submitted for
    a residential development on the subject property called “Windy Willows,”
    comprising 34 residential lots, 26 of which were located within the Township. The
    plan was based on a sketch plan that was previously submitted while the old
    ordinance was still in effect.        Waivers were sought from the Township’s
    Subdivision and Land Development Ordinance (SALDO).
    On September 26, 2005, the Township and Landowner entered into a
    settlement agreement in which Landowner agreed to withdraw its procedural
    validity challenge to the new ordinance in exchange for the Township’s agreement
    to review and potentially approve the plan under the terms of the old ordinance.
    Shortly thereafter, Landowner withdrew its validity challenge.
    In July 2008, the Township approved Landowner’s plan, subject to
    certain conditions. The Township also granted waivers from certain SALDO
    sections but it reserved its determination of other waiver requests until the final
    plan approval stage.      Pursuant to the terms of the settlement agreement, the
    Township reviewed the plan under the old ordinance.
    4
    Act of July 31, 1968, P.L. 805, added by the Act of December 21, 1988, P.L. 1329, as
    amended, formerly 53 P.S. §10909.1(a)(2), deleted by the Act of July 4, 2008, P.L. 319.
    3
    Objectors subsequently filed a land use appeal with the trial court.
    Landowner intervened.     The Township filed a motion to dismiss the appeal,
    arguing Objectors lacked standing to appeal because they did not appear in the
    proceedings below. The trial court granted the Township’s motion and dismissed
    Objectors’ appeal. On appeal, this Court held Objectors, as adjacent landowners,
    had substantive standing to object to subdivision plans both before the Township
    and in land use appeals, even though they did not appear before the Township or
    its Planning Commission. Miravich v. Twp. of Exeter 
    6 A.3d 1076
     (Pa. Cmwlth.
    2010) (Miravich I). We reversed and remanded.
    On remand, the trial court denied Objectors’ land use appeal. The
    trial court determined the Township did not err by reviewing the plan under the old
    ordinance based on the terms of the settlement agreement because municipalities
    are legally authorized to settle challenges to zoning ordinances. The trial court
    also upheld the Township’s grant of waivers to Landowner, and it held Landowner
    had standing to submit the plan.
    Objectors filed another appeal to this Court, asserting: (1) the proper
    procedure to challenge the new ordinance was to have a hearing before the ZHB;
    (2) the settlement agreement was an invalid exercise of the Township’s authority to
    settle the challenge to the new ordinance; (3) the Township erred by applying the
    old ordinance instead of the new ordinance to the plan; (4) the Township’s
    approval of the plan was defective; and, (5) Landowner lacked standing to seek
    preliminary plan approval. Miravich v. Twp. of Exeter 
    54 A.3d 106
     (Pa. Cmwlth.
    2012) (Miravich II).
    4
    Ultimately, this Court held the Township lacked authority to
    determine which zoning ordinance would be applied to the plan for three reasons.
    First, Landowner’s procedural challenge fell within the exclusive jurisdiction of
    the ZHB, not the Township. Additionally, Landowner filed its challenge with the
    ZHB and did not bring the matter before the Township as a substantive validity
    challenge. Finally, even if Landowner filed its challenge with the Township, the
    Township was required to hold a hearing within 60 days of the request and provide
    notice of the hearing, events which did not occur. This Court concluded that, by
    entering into the settlement agreement with Landowner and agreeing the old
    ordinance would apply to the plan, the Township usurped the ZHB’s role and
    violated the MPC’s notice and hearing provisions. Citing the trial court’s opinion,
    this Court also noted that the parties did not dispute that the enactment process for
    the new ordinance was procedurally defective.
    This Court also held that the settlement agreement was an invalid
    exercise of the Township’s authority to settle the procedural validity challenge to
    the new ordinance. We determined the settlement agreement was akin to contract
    zoning, which the Pennsylvania Supreme Court expressly disapproved in Carlino
    v. Whitpain Investors, 
    453 A.2d 1385
     (Pa. 1982).
    Further, this Court held the Township erred when it considered the
    plan under the old ordinance rather than the new ordinance.          We concluded
    Landowner submitted its plan after passage of the new ordinance; therefore, under
    Section 508(4)(i) of the MPC, 53 P.S. §10508(4)(i), which provides that an
    application for subdivision approval is governed by the ordinance in effect at the
    5
    time the application is filed, the new ordinance applied.                 Additionally, as to
    Objectors’ arguments that the Township’s approval of the plan was defective, this
    Court rejected some arguments and accepted others.5
    Thereafter, both parties filed petitions for allowance of appeal to the
    Supreme Court, which were ultimately denied.                    The plan approval appeal
    proceeded on remand. Meanwhile, however, while the petitions for allowance of
    appeal were pending, Landowner sent a letter to the ZHB requesting that it conduct
    a hearing on the procedural validity challenge Landowner filed in 2005 and
    subsequently withdrew pursuant to the settlement agreement.6
    The ZHB held a hearing on the validity challenge at which it heard
    testimony and received exhibits regarding the legal status of the 2005 challenge
    and the relevancy of this Court’s decision in Miravich II declaring the settlement
    agreement invalid. The ZHB concluded there was nothing before it to consider
    because Landowner unconditionally withdrew its challenge in October 2005. The
    5
    More particularly, this Court rejected Objectors’ assertion that sewage certification was
    required at the initial stage. This Court held that Section 512.1 of the MPC, added by the Act of
    December 21, 1988, P.L. 1329, 53 P.S. §10512.1, vests discretion with the Township to grant or
    deny any and all waivers sought by Landowner. The Court concluded that, because the
    Township did not explain the nature of the hardship for the waivers granted, it did not provide a
    proper basis for this Court to review whether it erred or abused its discretion in granting the
    waivers. Finally, this Court held Landowner had standing as an equitable owner to seek
    preliminary plan approval.
    6
    Landowner asserted the matter was remanded from this Court and that the validity
    challenge was filed before a 2008 statutory change. In 2008, the General Assembly repealed
    Section 909.1(a)(2) of the MPC, 53 P.S. §10909.1(a)(2), which provided that procedural validity
    challenges were to be heard before a ZHB. Currently, Section 5571.1 of the Judicial Code, 42
    Pa. C.S. §5571.1, contains the procedures governing procedural validity challenges and provides
    that such challenges are to be initiated in common pleas courts.
    6
    ZHB also held it could not exercise equity powers to conclude Landowner’s
    withdrawal of the challenge was nullified by this Court’s determination that the
    settlement agreement was invalid because zoning boards lack equity powers.
    Landowner appealed to the trial court, challenging both the ZHB’s
    denial based on jurisdictional grounds and the validity of the new ordinance. The
    trial court determined Landowner properly filed an appeal within 30 days after the
    adoption of the new ordinance, which was only withdrawn after the parties reached
    a settlement agreement.          Thus, the trial court remanded to the ZHB for a
    determination on the merits. The trial court explained the settlement agreement
    was a contract between Landowner and the Township, and when this Court held it
    was invalid in Miravich II, Landowner did not receive the benefit of its contractual
    bargain. As such, the trial court determined Landowner should be placed back to
    its original position, and the ZHB had jurisdiction to hear the 2005 procedural
    validity challenge. The trial court also determined that in Miravich II this Court
    intended the matter to be remanded to the ZHB because only the ZHB had
    jurisdiction over a procedural validity challenge filed in 2005.7
    On further appeal by Objectors, this Court affirmed, holding,
    “[b]ecause the settlement agreement has been invalidated, unmaking the contract
    between [Landowner] and the Township by judicial order, equity requires that
    7
    The trial court further stated the validity challenge was not barred by laches because the
    delay was caused by ongoing litigation and because Landowner properly relied on the
    Township’s apparent authority as to its pursuit of its land development application. The trial
    court also held unclean hands did not apply as both the Township and the trial court found the
    settlement agreement valid.
    7
    [Landowner] must be returned to its position prior to execution of the settlement
    agreement. Therefore, the ZHB is required to decide the merits of the procedural
    validity challenge under the statutory procedure in effect in 2005.” Metro Dev V,
    Slip Op. at 11, 
    2014 WL 3697529
     at *5.8
    Thereafter, the ZHB held hearings on Landowner’s procedural
    validity challenge to the new ordinance.               Ultimately, the ZHB sustained
    Landowner’s procedural validity challenge, and it declared the new ordinance void
    ab initio. In so doing, the ZHB made the following relevant determinations.
    In 2005, the Township undertook a project to amend its zoning
    ordinance. After various meetings, the Township decided to advertise for public
    hearing and enact a proposed ordinance to amend and restate the Township zoning
    ordinance and the zoning map in their entirety (collectively, the draft ordinance).
    The Township advertised a notice in the Reading Eagle, a newspaper
    of general circulation in the area, on June 29 and July 6, 2005, which stated:
    The Exeter Township Board of Supervisors
    [(Supervisors)] will hold a public hearing at 7:00 P.M. on
    July 18, 2005 to hear [p]ublic [c]omment on the [draft
    ordinance]. The [Supervisors] will consider adoption of
    the [draft ordinance] at their July 25, 2005 meeting. Full
    text of the [draft ordinance] is available for public
    inspection at the Township Office, 4974 DeMoss Road,
    8
    Additionally, in a separate (but related) decision, this Court remanded to the
    Township’s governing body following an appeal relating to Landowner’s preliminary
    subdivision plan, and we stayed that proceeding pending the outcome of Landowner’s procedural
    validity challenge to the new ordinance. See Miravich v. Twp. of Exeter (Pa. Cmwlth., No. 2066
    C.D. 2013, filed July 24, 2014), 
    2014 WL 3697542
     (unreported) (Miravich III).
    8
    Reading, PA 19606.          If you require special
    accommodations in order to attend Township meetings,
    please call the Township office at 610-779-5660. The
    Township will make every reasonable attempt to
    accommodate you.
    Troy S. Bingaman, Manager/Secretary.
    ZHB Op., 9/24/15, Finding of Fact (F.F.) No. 28 (Reading Eagle Notice).
    The Reading Eagle Notice did not provide “the time and place” of the
    meeting on July 25, 2005 in which the Supervisors would consider enactment of
    the draft ordinance. F.F. No. 29. Also, the Reading Eagle Notice did not provide
    either “the full text” of the draft ordinance or “a brief summary which lists
    provisions [of the draft ordinance] in reasonable detail[.]” F.F. No. 30. Although
    the Reading Eagle Notice did indicate that copies of the Draft Ordinance could be
    obtained at the Township Building, the Notice did not state “copies of the proposed
    ordinance or amendment may be examined without charge or obtained for a charge
    not greater than the cost hereof.” F.F. No. 31. Further, the Reading Eagle Notice
    was prepared by the Township Manager, not the Township Solicitor. The draft
    ordinance provided for changes to the zoning map that did not constitute
    comprehensive rezoning as only a few areas of the Township were rezoned.
    The ZHB further determined a notice of the public hearing on July 18,
    2005 and proposed enactment at the July 25, 2005 meeting were not conspicuously
    posted along tracts of land that were the subject of zoning map changes under the
    draft ordinance.   Also, a notice of the public hearing on July 18, 2005 and
    proposed enactment at the July 25, 2005 meeting was not mailed to the owners of
    the tracts of land within the Township that were the subject of zoning map changes
    9
    under the draft ordinance. An attested copy of the draft ordinance or any revised
    version was not filed in the County Law Library at any time prior to July 25, 2005.
    Additionally, a copy of the full text of the draft ordinance or any revised version
    was not filed with the Reading Eagle at any time prior to July 25, 2005.
    On July 18, 2005, the Supervisors held a public hearing at which time
    the draft ordinance was reviewed. At the hearing, the Supervisors made several
    substantial changes to the draft ordinance including changes to uses within zoning
    districts, changes to definitions and changes to objective criteria for uses. The
    Township Planning Commission reviewed the draft ordinance with the changes
    recommended at the July 18 hearing at a workshop meeting on July 20, 2005. At
    that time the Township Planning Commission recommended additional changes to
    Sections 400 and 500 of the draft ordinance.
    On July 25, 2005, the Supervisors held a public meeting at which time
    the draft ordinance (with the changes recommended at the July 18 hearing and the
    July 20 Planning Commission workshop meeting) was considered for adoption.
    As a result of public comment at the July 25 Supervisors’ meeting, the draft
    ordinance was revised again. F.F. No. 42.
    On July 25, 2005, the Supervisors adopted the new ordinance, which
    was in the form and content of the draft ordinance with the changes recommended
    at the July 18 public hearing, the July 20 Planning Commission workshop meeting,
    as well as the July 25 Supervisors’ meeting, and served to amend and restate the
    zoning ordinance in its entirety.
    10
    Between July 18 and prior to the adoption of the new ordinance on
    July 25, neither any of the revised versions of the draft ordinance nor the final
    version of the new ordinance were: (a) submitted to the County Planning
    Commission for review; (b) submitted to the Township Planning Commission for
    review of the changes made at the July 25 meeting; (c) submitted to the County
    Law Library to be available for public inspection; (d) submitted to the Reading
    Eagle to be available for public inspection; (e) re-advertised in the Reading Eagle
    for a public hearing or enactment at a public meeting; (f) posted conspicuously
    along tracts in the Township that were the subject of zoning map changes; or, (g)
    mailed to the owners of the tracts of land within the Township that were the subject
    of zoning map changes. F.F. No. 44.
    The new ordinance became effective on August 5, 2005, 10 days after
    its passage by the Supervisors.       On August 24, 2005, Landowner filed its
    procedural validity challenge with the Township, which was within 30 days of the
    new ordinance’s effective date.
    The ZHB explained that a procedural challenge must be brought
    within 30 days of an ordinance’s effective date. 42 Pa. C.S. §5571(c)(5). Where a
    challenge is filed within 30 days of the ordinance’s effective date, the party
    alleging a defect must prove there was a failure to strictly comply with statutory
    procedure. However, where a challenge is filed outside the 30-day period, a party
    must prove its right to an exemption from the deadline. This is accomplished by
    evidence showing the municipality’s “failure to substantially comply” with
    applicable procedures prevented the public from commenting on the ordinance.
    11
    Hawk v. Eldred Twp. Bd. of Supervisors, 
    983 A.2d 216
     (Pa. Cmwlth. 2009). If the
    challenging party meets its burden of proof, the challenged ordinance is void ab
    initio. 
    Id.
    Section 609 of the MPC, 53 P.S. §10609, establishes the procedures to
    be followed in the enactment process of zoning ordinance amendments.
    Additionally, Section 610 of the MPC, 53 P.S. §10610, establishes the
    requirements for publication, advertisement and availability of proposed zoning
    ordinances.
    Here, the ZHB found Landowner submitted credible evidence to meet
    its burden of establishing that its application was filed within 30 days of the
    effective date of the new ordinance, and that the Township did not strictly comply
    with the required statutory procedure.          Specifically, the ZHB determined the
    Township did not strictly comply with the required statutory procedure in the
    enactment process of the new ordinance based on 11 defects, detailed more fully
    below.        In light of these determinations, the ZHB sustained Landowner’s
    procedural validity challenge, and it declared the new ordinance void ab initio.
    Objectors appealed to the trial court raising numerous issues.
    Before the trial court, the parties engaged in settlement discussions
    and reached a tentative agreement; however, a final settlement agreement was not
    reached.
    12
    Ultimately, without taking additional evidence on Objectors’ land use
    appeal, the trial court affirmed. Additionally, the trial court denied Objectors’
    motion to enforce the purported settlement agreement reached before the trial
    court. This appeal followed.
    II. Issues
    On appeal,9 Objectors assert the trial court erred in failing to: (1)
    enforce a settlement agreement reached by the parties after the trial court
    determined Landowner was unable to comply with one of the terms of the
    agreement; and, (2) find Landowner’s 2005 procedural challenge to the new
    ordinance and the process Landowner followed was defective and Objectors’ rights
    were violated where (a) substantial and actual notice of the new ordinance was
    provided to all Township residents; (b) substantial reliance was shown by
    Objectors that the new ordinance was properly enacted; and, (c) the defective
    process undertaken by Landowner denied Objectors due process. Objectors also
    argue the trial court erred in failing to conclude Landowner lacked standing to
    prosecute its 2005 procedural validity challenge where it sold the subject property.
    III. Discussion
    A. Purported 2016 Settlement Agreement
    1. Contentions
    Objectors first argue the trial court erred or abused its discretion when
    it failed to enforce a 2016 settlement agreement reached by the parties following
    9
    Where, as here, the trial court did not receive any additional evidence, this Court’s
    review is limited to determining whether the ZHB committed an error of law or abuse of
    discretion. Oxford Corp. v. Zoning Hearing Bd. of Oxford, 
    34 A.3d 286
     (Pa. Cmwlth. 2011).
    13
    Objectors’ appeal of the ZHB’s 2015 decision declaring the new ordinance
    procedurally invalid. Objectors assert Pennsylvania has a strong judicial policy in
    favor of voluntarily settling lawsuits. Mastroni-Mucker v. Allstate Ins. Co., 
    976 A.2d 510
     (Pa. Super. 2009). Objectors contend settlement agreements are enforced
    according to principles of contract law. McDonald v. Ford Motor Co., 
    643 A.2d 1102
     (Pa. Super. 1994). Under Pennsylvania law, a contract exists when parties
    exhibit mutual assent to the terms of an agreement. Shovel Transfer & Storage,
    Inc. v. Pa. Liquor Control Bd., 
    739 A.2d 133
     (Pa. 1999).
    If a settlement contains all of the requisites for a valid contract, a court
    must enforce the terms of the agreement, even if the terms are not yet formalized in
    writing. Mastroni-Mucker. The intent of the parties to a written contract is
    contained in the writing itself. Mace v. Atl. Refining & Mktg. Corp., 
    785 A.2d 491
     (Pa. 2001). Moreover, after the parties reach a meeting of the minds as to the
    essential terms of their agreement, the existence of gaps in the contract will not
    vitiate it. See Commerce Bank/Pa. v. First Union Nat’l Bank, 
    911 A.2d 133
     (Pa.
    Super. 2006). Thus, “[t]he law in this Commonwealth makes clear that … [i]f
    parties agree upon essential terms and intend them to be binding, a contract is
    formed even though they intend to adopt a formal document with additional terms
    at a later date.” Shovel Transfer & Storage, 739 A.2d at 136 (internal quotations
    omitted); see also Commerce Bank.
    Here, Objectors maintain, the parties agreed to the essential terms of a
    settlement. The parties did not contemplate any additional terms that needed to be
    agreed on as a condition precedent to enforceability. Objectors argue that before
    14
    the trial court, the parties made no effort to clarify or object to any of the terms of
    the proposal upon accepting it.
    Objectors contend that, as admitted by Landowner, the parties entered
    into a settlement agreement. Reproduced Record (R.R.) at 25a-33a, 1123a-24a.
    The terms of that agreement were simple: (1) an entrance road would be moved;
    (2) Landowner would receive certifications from the three township engineers that
    the township boundary lines depicted on the plan were accurate; (3) Landowner
    would pay the immediately adjacent neighbors $60,000; and, (4) the parties would
    release each other, thus requiring Objectors not to further challenge Landowner’s
    development.    R.R. at 70a-77a.      Objectors maintain Landowner itself sought
    enforcement of the settlement agreement, and it admitted in its motion that there
    was a “meeting of the minds.” R.R. at 32a. Therefore, no basis exists to not
    enforce the essential terms of the settlement agreement.
    Objectors contend Pennsylvania courts frequently enforce agreements
    that contemplate the execution of a formal contract with additional terms in the
    future. See, e.g., Shovel Transfer & Storage. Indeed, Objectors argue, when
    compared to other settlement agreements enforced under Pennsylvania law, the
    agreement here is much more definitive and clearly enforceable.              See e.g.,
    Hatalowich v. Redev. Auth. of Monessen, 
    312 A.2d 22
    , 24-25 (Pa. 1973)
    (acceptance of proposal created a contract despite the fact that parties intended to
    later execute formal document); Compu Forms Control, Inc. v. Altus Grp., 
    574 A.2d 618
     (Pa. Super. 1990) (oral settlement agreement was enforceable even
    though the parties were unable to agree on, and execute, formal agreement). Here,
    15
    Objectors argue there can be no dispute that the parties entered into an agreement
    that was simply not yet reduced to a writing signed by the parties, but the parties
    agreed on all essential terms. See Commerce Bank, 
    911 A.2d at 147
     (enforcing
    terms of draft settlement agreement where parties reached “meeting of the minds”
    regarding essential terms of the agreement).
    Objectors further contend the term of the agreement relating to
    certification of municipal boundary lines was important to Objectors because they
    believed Landowner intentionally misrepresented the boundaries between the
    municipalities to allow more development in the Township given that it allows for
    smaller lots. Although this was not a specific legal issue before the trial court,
    Objectors maintain, the trial court agreed this term would be included so Objectors
    would provide Landowner a general release not to challenge Landowner’s
    development again. Objectors argue Landowner’s failure to comply with this term
    constituted a breach of the agreement; therefore, this case should be remanded to
    enforce the settlement agreement.
    Landowner10 responds that the trial court correctly held that a
    settlement agreement that cannot be performed is not enforceable as a matter of
    law.   As detailed by the trial court, Landowner and the Township could not
    perform a material term of the proposed settlement agreement; as such, the contract
    could not be enforced. Landowner contends the trial court laid out the term that
    Landowner and the Township could not perform and the reasons the parties
    10
    The Township joins and adopts by reference the briefs filed by Landowner and the
    ZHB.
    16
    rejected the settlement proposal. As such, no meeting of the minds ever occurred;
    thus, nothing suggests the ability to enforce a settlement proposal.
    Landowner argues it is critical to note that the settlement agreement
    Landowner sought to enforce through its motion was substantially different than
    the purported agreement Objectors now seek to enforce. In fact, Objectors never
    responded to the settlement’s writing and the parties relied on a spoken agreement.
    Despite this discussion, Landowner asserts, throughout the entire summer of
    2016—again to the delay of Landowner’s development—the terms of the
    agreement continually changed. From the loss of lots in April, to the payment of
    funds in May, to boundary certifications in June and then to loss of lots again in
    July, Objectors repeatedly changed the terms of any agreement.
    Moreover, Landowner maintains, as the draft agreements indicate, the
    Township always proposed a full release. R.R. at 72a-77a. However, at no time
    from April through June did Objectors respond to that requirement, until the
    motion to enforce settlement was filed. Essentially, Landowner argues Objectors
    want it both ways. They refused to settle in the midst of litigation, R.R. at 2a, and
    then they demanded enforcement of a purported settlement agreement after losing
    before the trial court.
    As noted by the trial court, Landowner contends, the final version of
    the settlement agreement could not be satisfied by Landowner and the Township.
    As such, the agreement failed as a matter of law. See, e.g., West v. Peoples First
    Nat’l Bank & Trust Co., 
    106 A.2d 427
     (Pa. 1954).            Importantly, Landowner
    17
    argues, the cases Objectors cite in support of their position include scenarios
    involving a clear meeting of the minds where the only outstanding issue was a
    finalized writing. No meeting of the minds occurred here.
    Landowner maintains that, as to the purported agreement, the trial
    court specifically referenced the boundary issue and made a finding that the parties
    could not survey the boundary in the manner demanded by Objectors. Thus, not
    all terms were satisfied. Landowner asserts our Supreme Court holds: “As with
    any contract, it is essential to the enforceability of a settlement agreement that ‘the
    minds of the parties should meet upon all the terms, as well as the subject-matter,
    of the [agreement].’” Mazzella v. Koken, 
    739 A.2d 531
    , 536 (Pa. 1999) (citing
    Onyx Oils & Resins, Inc. v. Moss, 
    80 A.2d 815
    , 817 (Pa. 1951)). Moreover,
    Landowner argues, the boundary issue was only one of several items upon which
    the parties could not agree, thus showing the settlement agreement was not
    enforceable as a matter of law.
    For its part, the ZHB notes, although present and a party to the matter,
    it was not directly involved in negotiations and attempts to resolve the matter
    through the proposed settlement agreement before the trial court. Nevertheless, the
    ZHB opposes Objectors’ argument that the trial court should have enforced the
    proposed settlement agreement. The ZHB joins Landowner’s argument on this
    issue in support of the trial court’s finding that the proposed settlement agreement
    was not enforceable based on the impossibility of performance of a material term.
    18
    2. Analysis
    In resolving this issue, the trial court here explained (with emphasis
    added):
    [Objectors] requested that this court enforce a settlement
    agreement reached amongst the parties in court in April,
    2016, and reduced to writing, but never finalized. The
    agreement discussed in court contained financial terms
    and several other provisions, but it was never finalized,
    and no party performed any of the obligations contained
    in the agreement. A material term of that agreement
    required [Landowner] and [the Township] to obtain
    certification from the engineers of the three
    municipalities of each of the municipal boundaries as
    depicted on [Landowner’s] preliminarily approved land
    development plans. [The Township] and [Landowner]
    were unable to obtain the certifications, but proposed in
    the alternative, in accordance with the recommendations
    of their relative engineers, that determination of the
    municipalities’ boundaries be obtained in accordance
    with the procedures [set forth in] [S]ection 302 of the
    [Second Class Township Code11]. This proposal was
    rejected by [Objectors] who insisted that they would not
    entertain any agreement absent certification from the
    engineers.
    [The] Township and [Landowner] could not
    perform a material term of the settlement agreement. ‘If
    performance on one side or another of a contract
    becomes excusably impossible while the transaction is
    wholly executory on both sides, not only is the contract
    discharged, but neither party is subject to obligation of
    any kind.’ [West, 106 A.2d at 433] citing Williston on
    Contracts, vol. 6 (Rev. Ed.). See also, Ellwood City
    Forge Corp. v. Fort Worth Heat Treating Co., Inc., [
    636 A.2d 219
     (Pa. Super. 1994)]. Accordingly, impossibility
    of performance of the material term rendered the
    agreement, if indeed any was reached, terminated.
    11
    Act of May 1, 1933, P.L. 103, as reenacted and amended, 53 P.S. §65302.
    19
    Tr. Ct., Slip Op., 9/15/16, at 9.
    Despite Objectors’ claims that the parties reached a settlement
    agreement after Objectors’ appeal of the ZHB’s decision invalidating the new
    ordinance, Objectors point to no record evidence to support their claim that an
    enforceable agreement actually existed.       Objectors note that, in June 2016,
    Landowner filed a motion to enforce the purported settlement agreement between
    the parties in which Landowner indicated there was a “meeting of the minds.” See
    R.R. at 32a. Shortly thereafter, the trial court issued an order marking the case
    settled and discontinued. See Certified Record (C.R.), Item #23.
    However, in response to Objectors’ motion for reconsideration, C.R.,
    Item #24, the trial court vacated its order marking the case settled and
    discontinued, and it ordered the parties to finalize settlement within 30 days. C.R.,
    Item #28.     Around the same time, the trial court issued orders scheduling
    settlement conferences for July 2016. C.R., Item #s 25-27.          The trial court
    subsequently scheduled a hearing for July 25, 2016 on Landowner’s petition to
    post bond, and it ordered the parties to file briefs on Objectors’ land use appeal.
    C.R., Item #s 29, 30. The trial court then issued its decision denying Objectors’
    land use appeal and rejecting Objectors’ assertion that the trial court should
    enforce the purported settlement agreement reached by the parties based on the
    above-quoted rationale.
    Unfortunately, the record does not contain any transcripts from the
    proceedings before the trial court. Thus, it is unclear whether adequate support
    exists for the trial court’s factual determination that it was impossible for the
    20
    parties to perform an essential term, i.e., obtaining engineer certifications from the
    municipal engineers of each of the municipal boundaries depicted on Landowner’s
    preliminarily approved land development plans.
    Nevertheless, in their brief to this Court, Objectors do not directly
    dispute the underlying basis for the trial court’s factual determination on this point.
    Rather, they assert the parties’ failure to comply with that term of the agreement
    rendered the agreement “breached not voided.” Appellants’ Br. at 20. Thus,
    Objectors challenge the result when a material term of an agreement is deemed
    impossible to perform.
    Section 261 of the Restatement (Second) of Contracts defines “legal
    impossibility” as follows:
    Where, after a contract is made, a party’s performance is
    made impracticable without his fault by the occurrence of
    an event the non-occurrence of which was a basic
    assumption on which the contract was made, his duty to
    render that performance is discharged, unless the
    language or the circumstances indicate to the contrary.
    RESTATEMENT (SECOND) OF CONTRACTS §261 (1981).
    Thus, “[u]nder the doctrine of impossibility of performance[12]
    applicable to the construction of contracts, if, after a contract is made, a party’s
    12
    “Impossibility of performance” means “not only strict impossibility but
    impracticability because of extreme and unreasonable difficulty, expense, or loss involved.” In
    re Busik, 
    759 A.2d 417
    , 423 n.9 (Pa. Cmwlth. 2000) (quoting West v. Peoples First Nat’l Bank
    & Trust Co., 
    106 A.2d 427
    , 432 (Pa. 1954)). “Impossibility of performance,” however, does not
    include mere inconvenience even though it may work a hardship. 
    Id.
     (citing Int’l Brotherhood of
    (Footnote continued on next page…)
    21
    performance is made impracticable through no fault of his or her own, the parties
    may waive the difficulties or terminate the agreement, ending all contractual
    obligations.” In re Busik, 
    759 A.2d 417
    , 423 (Pa. Cmwlth. 2000) (citing West).
    Further, “when impracticability excuses a party’s duty to perform, it ends all
    contractual obligations under the contract.” Lichtenfels v. Bridgeview Coal Co.,
    
    531 A.2d 22
    , 26 (Pa. Super. 1987) (citing West; RESTATEMENT (SECOND)                     OF
    CONTRACTS § 377 cmt. a (1981) (“in cases of impracticability or frustration the
    other party is also ordinarily relieved of any obligation of rendering the return
    performance that he has promised on the ground of failure of performance (§
    267)”)).
    Here, the trial court determined the performance of a material term of
    the purported settlement agreement was impracticable. Further, Objectors refused
    an alternative proposed procedure to satisfy this term, instead insisting they would
    not entertain any agreement absent certification from the municipal engineers. Tr.
    Ct., Slip Op., at 9. Under these circumstances, the trial court correctly determined
    that “impossibility of performance of [this] material term rendered the agreement,
    if indeed any was reached, terminated.”           Id.; see West.      Objectors offer no
    persuasive reason to disturb the trial court’s determination on this point.
    (continued…)
    Firemen & Oilers, Local 1201, AFL-CIO v. Bd. of Educ. of Sch. Dist. of Phila., 
    457 A.2d 1269
    (Pa. 1983)). Nor does it include a party’s financial inability to perform. 
    Id.
    22
    B. Procedural Validity Challenge to New Ordinance
    1. Contentions
    Objectors next argue Landowner’s 2005 procedural challenge and the
    process it followed was defective and shows Objectors’ rights were violated. They
    assert the purpose of a notice provision under the MPC is to prevent municipalities
    from enacting zoning ordinances that affect specific tracts of land without
    providing notice of their intention to act.     Northampton Residents Assoc. v.
    Northampton Twp. Bd. of Supervisors, 
    322 A.2d 787
     (Pa. Cmwlth. 1974).
    Further, where the ordinance adopted is different from the ordinance
    included in the notice, it shall not be declared invalid if the changes in the
    ordinance finally adopted were largely inconsequential. 
    Id.
     Also, the advertising
    of an ordinance complies with the MPC even if the full text of the ordinance is not
    included.   Instead, only a brief summary of the principal provisions must be
    included. Graack v. Bd. of Supervisors of L. Nazareth Twp., 
    330 A.2d 578
     (Pa.
    Cmwlth. 1975). Thus, where insignificant changes or amendments are made to a
    proposed ordinance after advertisement and public hearing, a re-advertisement and
    second public hearing are not required. 
    Id.
     In other words, Objectors contend, a
    zoning ordinance is not invalid because certain amendments to the advertised
    ordinance were made at the public meeting without re-advertising.           This is
    particularly true where the changes are de minimis. 
    Id.
    Objectors maintain that in Nockamixon Township v. Nockamixon
    Township Zoning Board, 
    8 A.3d 434
     (Pa. Cmwlth. 2010), this Court upheld a trial
    court’s reversal of a zoning board’s decision to sustain a procedural challenge to a
    zoning ordinance based in part on a claim of improper notice. There, this Court
    23
    recognized it was undisputed that the township violated the MPC because it did not
    provide timely notice of the meeting in which the ordinance was considered.
    However, this Court reasoned that in recent years courts softened the result of
    failure to strictly comply with notice requirements and instead relied on the
    concept of appropriate due process and likewise whether the due process right of
    others would be denied when they relied on and were bound by what appeared to
    be a valid ordinance. Id.; see also Bartkowski Inv. Grp., Inc. v. Bd. of Comm’rs of
    Marple Twp., 
    18 A.3d 1259
     (Pa. Cmwlth. 2011) (failure to strictly comply with
    MPC’s notice provision would not result in invalidation of zoning ordinance).
    In addition, Objectors contend, to bring a procedural challenge to the
    adoption of an ordinance, the challenger must present evidence of demonstrable
    prejudice to succeed on its challenge. Oxford Corp. v. Zoning Hearing Bd. of
    Borough of Oxford, 
    34 A.3d 286
     (Pa. Cmwlth. 2011). Further, a party bringing a
    procedural challenge must carry the additional burden of showing the ordinance
    was not reasonably relied on by other parties. Messina v. E. Penn Twp., 
    62 A.3d 363
     (Pa. 2012).
    Here, Objectors argue, evidence was presented that a summary of the
    ordinance was published in the Reading Eagle Newspaper notifying all landowners
    that the Township was considering a township-wide zoning ordinance. R.R. at
    1215a-16a. Moreover, Objector John Miravich testified the affected landowners
    received mailed notice reflecting the proposed zoning change. R.R. at 422a. In
    fact, there was testimony that over at least a six-month period, the Township held
    public forums that landowners could attend and comment on the zoning changes.
    24
    R.R. 422a-23a; see also R.R. 423a-25a. Further, maps were displayed allowing
    landowners to identify how their properties may be affected by the zoning change.
    Objectors point out Landowner claimed the new ordinance was not
    delivered to the County Law Library.         However, Landowner did not present
    testimony by the law librarian working at the time the new ordinance was
    considered. Instead, it produced a witness who only began working there five
    years after the Township considered the new ordinance. Moreover, Landowner’s
    representative acknowledged he did not know where the law library was and never
    went there to review an ordinance even though he was Landowner’s representative
    working on the land development plan.
    In addition to the claim that the new ordinance was not provided to
    the law library, Objectors maintain, Landowner claimed the new ordinance was not
    provided to the County Planning Commission. However, the County Planning
    Commission representative testified the new ordinance was provided for review.
    The County Planning Commission’s records showed the new ordinance was
    received and the Planning Commission specifically commented on the new
    ordinance and returned its comments to the Township. Objectors point out that
    Landowner appears to claim that because some minor changes to the new
    ordinance were made after the comments were received that the Township was
    required to resubmit the new ordinance to the Planning Commission. However,
    Objectors maintain, Landowner cites no authority that suggests these rounds of
    comments were required when the changes were minor and made at the Planning
    Commission’s request.
    25
    Further, Objectors argue, Landowner received substantial notice of the
    ordinance change.     Landowner’s representative testified he knew where the
    Township building was, previously attended Township meetings and reviewed the
    Township documents. R.R. at 138a-48a.
    Also, Objectors contend the new ordinance was available at the
    Township building.     Objectors argue further testimony was offered and was
    unrefuted that the Township provided prior notice and set up workshops and
    notified each landowner in writing. R.R. at 1147a. Again, none of this testimony
    was refuted. Additionally, Objectors assert, Landowner offered no testimony that
    it was prejudiced by not receiving more detailed notice.
    Objectors further maintain they offered significant testimony that they
    relied on the new ordinance. R.R. at 425a-27a. Additionally, testimony was
    offered that Objectors now cannot develop their property under the old ordinance
    that Landowner seeks to apply only to it. R.R. at 426a-27a. As set forth in
    Messina, Objectors maintain, a challenger, like Landowner here, must show there
    was no reasonable reliance by others that the new ordinance was valid. Here,
    Objectors argue, Landowner presented no evidence to refute the fact that after 10
    years it was reasonable for other landowners to believe the new ordinance was
    valid and could no longer be challenged.
    Objectors further contend, in addition to the fact that they could
    reasonably rely on the new ordinance as it was on the books for over 10 years,
    Objectors never received notice that Landowner filed an application challenging
    26
    the new ordinance. Although the Township attempted to show a memorandum
    was prepared internally to schedule a hearing and notify Objectors, no hearing was
    scheduled and no evidence that a hearing was scheduled was ever presented.
    Moreover, Objectors assert, no evidence was presented that Objectors
    ever received any notice. Instead, the parties conspired to hide Landowner’s
    special treatment from Objectors. In fact, Objectors contend, the only testimony
    on this issue was the testimony that no hearing occurred. R.R. at 419a-20a.
    Objectors assert they had a due process right that, to the extent an ordinance was
    going to be challenged, it would be done timely, see Messina, rather than 5 or 10
    years after the initial application was filed and placed on hold by Landowner. As
    the evidence showed, Objectors assert, through the minutes of the Township
    meeting, it was Landowner who prepared and presented the settlement agreement
    to the Township, which placed the procedural challenge on hold without notice to
    Objectors. Objectors maintain it was not the Township’s fault that Landowner
    chose to proceed in a way that would allow only the Township and Landowner to
    know Landowner intended to overturn the new ordinance as it applied only to the
    subject property.
    Objectors argue the MPC requires timely prosecution of a zoning
    application.     Here, Landowner placed its validity challenge in limbo thus
    prejudicing Objectors who were never notified the application was filed. Objectors
    assert it would deny them due process to allow Landowner not to prosecute its
    challenge in a timely manner.
    27
    In response, Landowner argues the trial court correctly agreed that the
    enactment of the new ordinance in 2005 was procedurally defective. Landowner
    contends that, based on the history and voluminous record, the new ordinance was
    adopted with significant procedural flaws. Landowner asserts Objectors’ argument
    concerning the ZHB’s ability to hear the case is improper as a matter of law, as the
    procedural validity challenge hearing was correctly advertised and all parties
    attended the 2015 hearings consistent with this Court’s directive in Metro Dev V.
    Landowner maintains the trial court properly recognized the procedural flaws and
    sustained the ZHB’s decision. Importantly, it contends, the trial court agreed that
    the phantom procedural requirements suggested by Objectors in the zoning appeal
    process are not binding on any of the parties.
    To that end, Landowner argues, Objectors’ arguments regarding
    notice of an application are not grounded in any legal requirement in the MPC, the
    Second Class Township Code, the zoning ordinance or this Court’s directive in
    Metro-Dev V. As such, no legal basis exists to adopt the novel argument that the
    case should be dismissed because in 2005 no parties knew an application was filed.
    Objectors’ failure to cite supporting authority reveals the frivolous nature of their
    notice argument.
    Landowner further maintains the procedural flaws in the 2005
    adoption of the new ordinance are undisputed. During the 2015 ZHB hearings,
    Objectors did not present evidence to suggest the new ordinance’s adoption
    procedure was not flawed. Further, the Township admitted the new ordinance was
    28
    flawed, and this Court recognized the procedural defects inherent in the ordinance
    adoption in Metro Dev V.
    In addition to the various admissions of invalidity, Landowner
    contends, the ZHB record is filled with procedural flaws including, but not limited
    to: (1) failure to properly summarize the ordinance in the advertisement; (2) failure
    to have the proper municipal official advertise the ordinance; (3) making
    substantial changes without additional comment by the County or Township
    Planning Commissions; (4) failure to file a copy with the County Law Library
    prior to adoption; and, (5) failure to advertise the time and place of the meeting in
    which the new ordinance would be considered.
    Landowner further maintains the trial court properly found that strict
    compliance with each MPC provision was the proper standard here. Thus, one
    flaw was enough to sustain Landowner’s burden. As noted, Landowner argues,
    countless errors occurred here. As the trial court properly concluded, based on this
    Court’s directive, the law in place in 2005 was to be applied to the new ordinance’s
    adoption process. See Metro Dev V. At that time, Glen-Gery Corp. v. Zoning
    Hearing Board of Dover Township, 
    907 A.2d 1033
     (Pa. 2006), and its progeny
    controlled, mandating the strictest of all standards in ordinance adoption, requiring
    satisfaction of every statutory provision or an ordinance was void.
    Landowner argues this appeal is simply one more roadblock in a
    series of legal objections that were filed without a valid legal basis, but rather in an
    effort to halt Landowner’s development.
    29
    Landowner further contends the hearing protocol for the procedural
    validity challenge satisfied the MPC. It asserts the crux of Objectors’ argument is
    that no advertisement occurred when the procedural validity challenge was filed
    with the ZHB.       Landowner argues nothing in any statute suggests that
    advertisement of a procedural validity challenge application must occur. Further,
    Objectors cite no such authority. Rather, the only advertisement requirement for a
    ZHB is prior to a hearing. See Section 908 of the MPC, 53 P.S. §10908.
    Here, Landowner argues, the issue of the procedural hearing process
    was already decided. See Metro Dev V. Further, in Miravich v. Township of
    Exeter (Pa. Cmwlth., No. 2066 C.D. 2013, filed July 24, 2014), 
    2014 WL 3697542
    (unreported) (Miravich III), the same Objectors requested the matter proceed
    before the ZHB and raised no issue with that hearing process through extensive
    briefing. Landowner asserts Objectors’ procedural complaints are only intended to
    confuse and complicate a 10-year-old legal dispute.
    Landowner further argues that, in 2005, as with today, Section 908 of
    the MPC governs hearing procedures before the ZHB. It provides a specific notice
    provision:
    The board shall conduct hearings and make decisions in
    accordance with the following requirements:
    (1) Public notice shall be given and written notice shall
    be given to the applicant, the zoning officer, such other
    persons as the governing body shall designate by
    ordinance and to any person who has made timely
    request for the same. Written notices shall be given at
    such time and in such manner as shall be prescribed by
    ordinance or, in the absence of ordinance provisions, by
    30
    the rules of the board. In addition to the written notice
    provided herein, written notice of said hearing shall be
    conspicuously posted on the affected tract of land at least
    one week prior to the hearing.
    53 P.S. §10908(1) (emphasis added). Landowner argues Section 908(1.2) of the
    MPC discusses receipt of the application, but only states the timing of the hearing
    after the application is received. See 53 P.S. §10908(1.2). Nothing in Section 908
    suggests any special handling or notice of the application itself upon receipt.
    Landowner further asserts all parties agree that no hearing on its
    procedural validity challenge occurred in 2005. All parties agree that until 2016
    the ZHB did not rule on its validity challenge. Before the ZHB, Objector Miravich
    admitted the zoning ordinance in place before the 2005 application had no
    procedure for notifying anyone of the mere receipt of an application on a
    procedural validity challenge. R.R. at 436a. Rather, the MPC and the ordinance
    simply required notice of the hearing. In any event, Landowner contends, during
    the 2015 ZHB hearings, the Township’s solicitor specifically asked if there were
    any objections to the hearing and Objectors’ counsel did not raise any. R.R. at
    131a.
    Landowner also argues that in Metro Dev V, this Court directed the
    ZHB to hear the merits of the procedural challenge, not to debate whether there
    was a flaw in the underlying application, as that issue was long since withdrawn.
    Id. Since this Court’s decision in Metro Dev V, hearings were scheduled and
    property owners were notified, two attorneys represented Objectors’ interests,
    31
    subpoenas were issued for several witnesses and the property was posted as
    evidenced by the exhibits entered into evidence, without objection.
    Finally, Landowner notes, Objectors assert their due process rights
    were violated. Landowner argues this contention lacks merit based on this Court’s
    decision in Metro Dev V, which cured any irregularity based on the 2005
    settlement agreement. Landowner contends due process assertions would only
    have merit if the 2015 ZHB hearing was not advertised, posted or the mandates of
    the MPC violated. Here, all parties admit the 2015 process was satisfied. As such,
    as a matter of law the process was proper and no due process violation occurred.
    For its part, the ZHB reiterates the reasoning set forth in its decision
    sustaining Landowner’s procedural validity challenge and declaring the new
    ordinance void ab initio. The ZHB argues that, despite Objectors’ attempts to
    confuse and complicate the matter by rearguing and raising issues previously
    addressed or ruled on in the years of protracted litigation in this case, the scope of
    the issue here is straightforward.
    To that end, in Metro Dev V, this Court was clear in its remand and
    directive that the ZHB should: (1) hear the procedural validity challenge to the new
    ordinance as contained in Landowner’s application; and, (2) decide the merits of
    the validity challenge under the statutory procedure in effect in 2005.
    Based on the law in effect in 2005 and upon review of the credible
    evidence, the ZHB contends it did not err in finding Landowner’s application was
    32
    filed within 30 days of the effective date of the new ordinance, and the Township
    did not strictly comply with the statutory procedures required to enact a zoning
    ordinance amendment; therefore, the new ordinance is void ab initio.
    The ZHB maintains the 11 procedural defects that it found existed are
    supported by the credible testimony and substantial evidence it received at the
    hearings. The Township neither challenged nor disputed any of the evidence
    submitted at the hearings to support these procedural defects. Additionally, the
    Township Manager’s testimony can be fairly construed as an admission that the
    procedural defects occurred. R.R. at 227a-244a.
    The ZHB contends Objectors did not submit any credible evidence to
    overcome the ZHB’s finding that Landowner met its burden in establishing these
    procedural defects. Rather, Objectors appear to assert these defects are waivable.
    The ZHB asserts this is not a valid statement of the law in effect in 2005. Rather,
    because Landowner’s application was filed within 30 days of the effective date of
    the new ordinance, the enactment process had to strictly comply with the MPC.
    The ZHB asserts that, if Landowner filed its application more than 30 days from
    the date of enactment, Objectors’ argument that the defects may be waivable could
    have merit. Here, however, Landowner filed its application within 30 days of
    enactment; thus, Objectors’ position is misplaced and the cases they cite are
    distinguishable.
    The ZHB further points out that Objectors argue that because
    Landowner may have known the new ordinance was being considered in 2005, it
    33
    was not prejudiced by the procedural defects and, as a result, Landowner should
    now be barred from prosecuting its challenge. The ZHB argues this contention
    lacks merit as this Court’s decision in Metro Dev V required the ZHB to hear the
    challenge and, based on applicable legal standards, the ZHB and the trial court
    were required to determine if the Township strictly complied with the statutory
    procedure for enactment.
    The ZHB further contends, although Objectors argue their rights were
    violated through application of the strict compliance standard, they cite no
    precedential or persuasive authority other than Messina to support their theory.
    And, the ZHB argues, Messina is distinguishable. In Messina, the challengers
    waited 12 years to challenge a zoning ordinance. Here, the challenge was made
    less than 30 days from enactment. Additionally, Objectors did not rely on the new
    ordinance without knowledge of Landowner’s challenge to its procedural validity.
    Instead, as evidenced by the history of this case and related cases, Objectors were
    fully aware of the issues involved and the potential for invalidation of the new
    ordinance. In fact, Objectors previously sought to prevent invalidation of the new
    ordinance in Miravich I. Thus, Objectors’ reliance on Messina is misplaced and is
    insufficient to overcome this Court’s directive to the ZHB in Metro Dev V.
    2. Analysis
    Initially, we note, this Court may not substitute its interpretation of the
    evidence for that of the ZHB. Taliaferro v. Darby Twp. Zoning Hearing Bd., 
    873 A.2d 807
     (Pa. Cmwlth. 2005). It is the function of a ZHB to weigh the evidence
    before it. 
    Id.
     The ZHB is the sole judge of the credibility of witnesses and the
    weight afforded their testimony. 
    Id.
     Assuming the record contains substantial
    34
    evidence, we are bound by the ZHB’s findings that result from resolutions of
    credibility and conflicting testimony rather than a capricious disregard of evidence.
    
    Id.
     A ZHB is free to reject even uncontradicted testimony it finds lacking in
    credibility. 
    Id.
    In Metro Dev V, this Court required the ZHB to “decide the merits of
    [Landowner’s] procedural validity challenge under the statutory procedure in effect
    in 2005.” Slip Op. at 11, 
    2014 WL 3697529
     at *5.
    In 2005, Section 909.1(a)(2) of the MPC stated, in relevant part:
    (a) The [ZHB] shall have exclusive jurisdiction to hear
    and render final adjudications in the following matters:
    (2) Challenges to the validity of a land use ordinance
    raising procedural questions or alleged defects in the
    process of enactment or adoption which challenges shall
    be raised by an appeal taken within 30 days after the
    effective date of said ordinance. …
    Further, in 2005, Section 5571(c)(5) of the Judicial Code (“Appeals
    generally”) stated:
    (c) Exceptions.—
    ****
    (5) Ordinances, resolutions, maps, etc.-- Notwithstanding
    section 909.1(a)(2) of the … [MPC], questions relating to
    an alleged defect in the process of enactment or adoption
    of any ordinance, resolution, map or similar action of a
    political subdivision, including appeals and challenges to
    the validity of land use ordinances adopted pursuant to
    the [MPC], shall be raised by appeal or challenge
    35
    commenced within 30 days after the intended effective
    date of the ordinance, resolution, map or similar action.
    As used in this paragraph, the term ‘intended effective
    date’ means the effective date specified in the ordinance,
    resolution, map or similar action or, if no effective date is
    specified, the date 60 days after the date the ordinance,
    resolution, map or similar action was finally adopted but
    for the alleged defect in the process of enactment or
    adoption.
    Although not in effect at the time Landowner filed its procedural
    validity challenge in 2005, it is helpful to acknowledge the current statutory
    framework, including the applicable burdens of proof for procedural validity
    challenges (adopted in 2008), which states, as relevant:
    (b) Appeals of defects in statutory procedure.--
    (1) Any appeal raising questions relating to an alleged
    defect in statutory procedure shall be brought within 30
    days of the intended effective date of the ordinance.
    (2) Except as provided in subsection (c), it is the express
    intent of the General Assembly that this 30-day limitation
    shall apply regardless of the ultimate validity of the
    challenged ordinance.
    (c) Exemption from limitation.--An appeal shall be
    exempt from the time limitation in subsection (b) if the
    party bringing the appeal establishes that, because of the
    particular nature of the alleged defect in statutory
    procedure, the application of the time limitation under
    subsection (b) would result in an impermissible
    deprivation of constitutional rights.
    (d) Presumptions.--Notwithstanding any other provision
    of law, appeals pursuant to this section shall be subject to
    and in accordance with the following:
    36
    (1) An ordinance shall be presumed to be valid and to
    have been enacted or adopted in strict compliance with
    statutory procedure.
    (2) In all cases in which an appeal filed in court more
    than two years after the intended effective date of the
    ordinance is allowed to proceed in accordance with
    subsection (c), the political subdivision involved and
    residents and landowners within the political subdivision
    shall be presumed to have substantially relied upon the
    validity and effectiveness of the ordinance.
    (3) An ordinance shall not be found void from inception
    unless the party alleging the defect in statutory procedure
    meets the burden of proving the elements set forth in
    subsection (e).
    (e) Burden of proof.--Notwithstanding any other
    provision of law, an ordinance shall not be found void
    from inception except as follows:
    (1) In the case of an appeal brought within the 30-day
    time limitation of subsection (b), the party alleging the
    defect must meet the burden of proving that there was a
    failure to strictly comply with statutory procedure.
    (2) In the case of an appeal which is exempt from the 30-
    day time limitation in accordance with subsection (c), the
    party alleging the defect must meet the burden of proving
    each of the following:
    (i) That there was a failure to strictly comply with
    statutory procedure.
    (ii) That there was a failure to substantially comply with
    statutory procedure which resulted in insufficient
    notification to the public of impending changes in or the
    existence of the ordinance, so that the public would be
    prevented from commenting on those changes and
    intervening, if necessary, or from having knowledge of
    the existence of the ordinance.
    37
    (iii) That there exist facts sufficient to rebut any
    presumption that may exist pursuant to subsection (d)(2)
    that would, unless rebutted, result in a determination that
    the ordinance is not void from inception.
    (f) Void ordinances.--A determination that an ordinance
    is void from inception shall not affect any previously
    acquired rights of property owners who have exercised
    good faith reliance on the validity of the ordinance prior
    to the determination.
    42 Pa. C.S. §5571.1(b)-(f) (emphasis added).
    Further, as of 2005, “[t]he precedents of [the Supreme] Court [were]
    consistent in holding that statutory publication requirements [were] mandatory and
    that ordinances adopted without strict compliance [were] void.” Glen-Gery, 907
    A.2d at 1041 (quoting L. Gwynedd Twp. v. Gwynedd Props., Inc., 
    591 A.2d 285
    ,
    288 (Pa. 1991)). Thus, the Supreme Court’s “‘consistent view [was] that the
    statutory steps for enactment of ordinances [were] mandatory and nonwaivable,”
    and “the procedures established by the legislature for the enactment of ordinances
    must be followed strictly in order for an ordinance to be valid[.]” 
    Id.
     (quoting L.
    Gwynedd Twp., 591 A.2d at 286, 287).
    Here, Landowner filed its procedural validity challenge within 30
    days of the effective date of the new ordinance. F.F. No. 46. Where, as here, a
    challenge is filed within 30 days of the ordinance’s effective date, a challenger
    must only prove the municipality failed to strictly comply with statutory
    procedures. Hawk v. Eldred Twp. Bd. of Supervisors, 
    983 A.2d 216
     (Pa. Cmwlth.
    2009). As set forth above, this remains the law currently in Pennsylvania. See 42
    Pa. C.S. §5571.1(e)(1).
    38
    The ZHB here determined Landowner proved that the enactment of
    the new ordinance did not strictly comply with numerous procedural requirements
    in Sections 609 and 610 of the MPC. As of 2005, Section 609 of the MPC
    (“Enactment of zoning ordinance amendments”) stated, as relevant (with emphasis
    added):
    (a) For the preparation of amendments to zoning
    ordinances, the procedure set forth in section 607 for the
    preparation of a proposed zoning ordinance shall be
    optional.
    (b) (1) Before voting on the enactment of an amendment,
    the governing body shall hold a public hearing thereon,
    pursuant to public notice…. In addition, if the proposed
    amendment involves a zoning map change, notice of said
    public hearing shall be conspicuously posted by the
    municipality at points deemed sufficient by the
    municipality along the tract to notify potentially
    interested citizens. The affected tract or area shall be
    posted at least one week prior to the date of the hearing.
    (2) (i) In addition to the requirement that notice be posted
    under clause (1), where the proposed amendment
    involves a zoning map change, notice of the public
    hearing shall be mailed by the municipality at least 30
    days prior to the date of the hearing by first class mail to
    the addressees to which real estate tax bills are sent for
    all real property located within the area being rezoned, as
    evidenced by tax records within the possession of the
    municipality. The notice shall include the location, date
    and time of the public hearing. A good faith effort and
    substantial compliance shall satisfy the requirements of
    this subsection.
    (ii) This clause shall not apply when the rezoning
    constitutes a comprehensive rezoning.
    (c) In the case of an amendment other than that prepared
    by the planning agency, the governing body shall submit
    39
    each such amendment to the planning agency at least 30
    days prior to the hearing on such proposed amendment to
    provide the planning agency an opportunity to submit
    recommendations.
    (d) If, after any public hearing held upon an amendment,
    the proposed amendment is changed substantially, or is
    revised, to include land previously not affected by it, the
    governing body shall hold another public hearing,
    pursuant to public notice ….
    (e) If a county planning agency shall have been created
    for the county in which the municipality proposing the
    amendment is located, then at least 30 days prior to the
    public hearing on the amendment by the local governing
    body, the municipality shall submit the proposed
    amendment to the county planning agency for
    recommendations. …
    53 P.S. §10609(a)-(e).
    In addition, Section 610(a) and (b) of the MPC stated (with emphasis
    added):
    (a) Proposed zoning ordinances and amendments shall
    not be enacted unless notice of proposed enactment is
    given in the manner set forth in this section, and shall
    include the time and place of the meeting at which
    passage will be considered, a reference to a place within
    the municipality where copies of the proposed ordinance
    or amendment may be examined without charge or
    obtained for a charge not greater than the cost thereof.
    The governing body shall publish the proposed ordinance
    or amendment once in one newspaper of general
    circulation in the municipality not more than 60 days nor
    less than 7 days prior to passage. Publication of the
    proposed ordinance or amendment shall include either
    the full text thereof or the title and a brief summary,
    prepared by the municipal solicitor and setting forth all
    the provisions in reasonable detail. If the full text is not
    included:
    40
    (1) A copy thereof shall be supplied to a
    newspaper of general circulation in the
    municipality at the time the public notice is
    published.
    (2) An attested copy of the proposed ordinance
    shall be filed in the county law library or other
    county office designated by the county
    commissioners, who may impose a fee no greater
    than that necessary to cover the actual costs of
    storing said ordinances.
    (b) In the event substantial amendments are made in the
    proposed ordinance or amendment, before voting upon
    enactment, the governing body shall, at least ten days
    prior to enactment, readvertise, in one newspaper of
    general circulation in the municipality, a brief summary
    setting forth all the provisions in reasonable detail
    together with a summary of the amendments. …
    53 P.S. §10610(a), (b).
    Here, the ZHB determined the following 11 procedural deficiencies
    occurred in the enactment of the new ordinance:
     The Reading Eagle Notice does not provide ‘the
    time and place’ of the meeting on July 25, 2005
    that the [Supervisors] would consider the
    enactment/passage of the Draft Ordinance as
    required by 53 P.S. §10609(b)(1) and 53 P.S.
    §10610(a);
     The Reading Eagle Notice does not provide either
    ‘the full text’ of the Draft Ordinance or ‘a brief
    summary which lists provisions in reasonable
    detail’ or even any details of the Draft Ordinance
    as required by 53 P.S. §10609(b)(1) and 53 P.S.
    §10610(a);
     Although the Reading Eagle Notice does indicate
    that copies of the Draft Ordinance may be obtained
    41
    at the Township Building, the Reading Eagle
    Notice does not state that ‘copies of the proposed
    ordinance or amendment may be examined without
    charge or obtained for a charge not greater than the
    cost hereof’ as required by 53 P.S. §10610(a);
     The Reading Eagle Notice was prepared by the
    [Township] Manager and not the [Township]
    Solicitor as required by 53 P.S. §10610(a);
     A notice of the public hearing on July 18, 2005
    and proposed enactment at the July 25, 2005
    meeting was not conspicuously posted along tracts
    of land within [the] Township that were the subject
    of zoning map changes under the Draft Ordinance
    as required by 53 P.S. §10609(b)(1);
     A notice of the public hearing on July 18, 2005
    and proposed enactment at the July 25, 2005
    meeting was not mailed to the owners of the tracts
    of land within [the] Township that were the subject
    of zoning map changes under the Draft Ordinance
    as required by 53 P.S. §10609(b)(2);
     An attested copy of the Draft Ordinance or any
    revised version thereof was not filed in the
    [County Law Library] at any time prior to July 25,
    2005 as required by 53 P.S. §10610(b)(2);
     A copy of the full text of the Draft Ordinance or
    any revised version thereof was not filed in the
    Reading Eagle at any time prior to July 25, 2005 as
    required by 53 P.S. §10610(b)(1);
     Prior to adoption on July 25, 2005, Ordinance 596,
    which contained substantial amendments from the
    Draft Ordinance, was not submitted to the [County
    Planning Commission] for review as required by
    53 P.S. §10609(e);
     Prior to adoption on July 25, 2005, Ordinance 596,
    which contained substantial amendments from the
    Draft Ordinance, was not submitted to the
    42
    [Township Planning Commission] for review of all
    of the changes made at the July 25, 2005 meeting
    as required by 53 P.S. §10609(c); and
     Prior to adoption on July 25, 2005, Ordinance 596,
    which contained substantial amendments from the
    Draft Ordinance, was not re-advertised for public
    notice in the Reading Eagle for a public hearing or
    enactment at a public meeting as required by 53
    P.S. §10610(b).
    ZHB Op., Concls. of Law No. 3(a)-(k).           The record supports the ZHB’s
    determinations that the Township did not strictly comply with several requirements
    set forth in Sections 609 and 610 of the MPC in enacting the new ordinance.
    More specifically, among other things, the notice published in the
    Reading Eagle: (1) did not provide the time and place of the meeting at which the
    Supervisors would consider passage of the new ordinance; (2) did not provide
    either the full text of the new ordinance or the title and a brief summary setting
    forth all provisions in reasonable detail; and, (3) was not prepared by the Township
    Solicitor. C.R., Item #9, Ex. 12; R.R. at 1216a; see also 145a-47a.
    In addition, the Township Manager, who prepared the advertisement
    of the new ordinance, acknowledged he had no proof that a copy of the full text of
    the new ordinance was provided to the Reading Eagle or the County Law Library.
    R.R. at 231a-32a; see also R.R. at 148a, 210a-11a. The Township Manager also
    testified he could not recall whether notices were sent to those property owners
    whose properties were being rezoned as a result of the enactment of the new
    ordinance. R.R. at 263a. In light of these obvious procedural defects, it is not
    necessary to address the remaining deficiencies found by the ZHB.
    43
    Further, based on these defects, no error is apparent in the ZHB’s
    conclusion that Landowner, which filed its challenge within 30 days of the
    effective date of the new ordinance, proved the Township did not strictly comply
    with the MPC’s procedural requirements when enacting the new ordinance. As
    such, the ZHB properly deemed the new ordinance void ab initio.
    Nevertheless, citing Messina, Objectors argue Landowner was
    required to show there was no reasonable reliance on the new ordinance by other
    landowners in the Township. Contrary to this assertion, the challenge at issue in
    Messina was filed 12 years after the enactment of the ordinance at issue (and more
    than 30 days after the effective date of the 2008 amendment to Section 5571.1 of
    the Judicial Code). Where, as in Messina, a procedural validity challenge is filed
    more than two years after an ordinance’s intended effective date, a challenger must
    rebut the presumption that the municipality and its residents substantially relied on
    the validity and effectiveness of the ordinance. See 42 Pa. C.S. §5571.1(e)(2).
    The same is not true for challenges filed within 30 days of an ordinance’s effective
    date, such as Landowner’s challenge here.
    To that end, unlike in Messina, Landowner filed its procedural
    validity challenge within 30 days of the effective date of the new ordinance. Thus,
    Landowner was only required to show the Township failed to strictly comply with
    statutory procedures, a burden which, as set forth above, it carried here.
    Further, in Nockamixon, Bartowski, and Oxford, cited by Objectors
    for the proposition that strict compliance was not required here, the challengers did
    44
    not file their procedural validity challenges within 30 days of the enactment of the
    ordinances. Thus, those cases are distinguishable.
    In addition, while Objectors claim they did not receive notice of
    Landowner’s procedural validity challenge when it was filed in 2005, as the trial
    court explained:
    [T]here is no dispute that [Objectors] were notified of
    and participated in the hearings held in 2015 on
    [Landowner’s] procedural challenge to the [n]ew
    [o]rdinance. At that time, [Objectors] were given the
    opportunity to be heard regarding … their argument for
    improper notice in 2005 …. Further, MPC Section 908(1)
    provides that public notice [of a ZHB hearing] be given
    ‘to the applicant, the zoning officer, such other persons as
    the governing body shall designate by ordinance and to
    any person who has made a timely request of the same.’
    53 P.S. § 10908(1). Accordingly, not only was notice to
    [Objectors] not necessarily required of the 2005
    proceedings, but due to the settlement agreement, and the
    several appeals by [Objectors] contributing to the delay,
    the 2005 proceedings were never held. For [Objectors]
    to suggest that they are harmed by the delay in the
    issuance of a final unappealable resolution of the
    challenge to the ordinance is somewhat disingenuous
    since much of the delay was occasioned by [Objectors’]
    own appeals. Needless to say, every party has the right
    to file reasonable good faith appeals, however, in the face
    of an adverse ruling, to suggest that the delay occasioned
    by the appeal prejudiced [Objectors] is, at the very least,
    somewhat circular. …
    Tr. Ct., Slip Op., at 6. Additionally, as explained above, in Metro Dev V, this
    Court directed the ZHB to decide the merits of Landowner’s procedural validity
    challenge, originally filed in 2005. In light of this and the fact that Objectors fully
    45
    participated in the ZHB proceedings on Landowner’s procedural validity challenge
    with the aid of counsel, Objectors received all process due.
    Finally, while Objectors argue Landowner had actual notice of the
    enactment of the new ordinance, as the Supreme Court stated in Schadler v. Zoning
    Hearing Board of Weisenberg Township, 
    850 A.2d 619
    , 627 n.12 (Pa. 2004):
    [T]he procedural requirements for the enactment of a law
    are nonwaivable, and when the lawfulness of the
    enactment is in question, the law is either void or not
    void, without regard to the identity of the challenger.
    Meanwhile, finding the notice of an individual litigant to
    have any bearing on the litigant’s ability to challenge the
    law in the circumstances of this case would lead to the
    absurd result of a single township ordinance being valid
    with respect to some citizens and simultaneously invalid
    with respect to others.
    See also L. Gwynedd, 591 A.2d at 287 (citing Fierst v. William Penn Mem. Corp.,
    
    166 A. 761
    , 763 (Pa. 1933)) (“If a published notice fails to satisfy the statutory
    requirements, the fact that members of the public, or even the appellants
    themselves, appeared at the hearing does not breathe life into an otherwise void
    ordinance”).
    The flaw in Objectors’ logic stems from their failure to distinguish
    between the deprivation of an individual’s right to due process (notice), and the
    deprivation of a shared public right to participate in the proceedings involving
    adoption of ordinances. See Messina, 62 A.3d at 370; see also Ness v. York Twp.
    Bd. of Comm’rs, 
    81 A.3d 1073
    , 1083 (Pa. Cmwlth. 2013). The parameters of the
    shared public right to participate in the enactment proceedings are set forth in the
    46
    MPC’s notice requirements. See 
    id.
     While actual notice of the enactment of the
    new ordinance would impact an analysis of deprivation of Landowner’s individual
    right to procedural due process, Landowner also may advance the shared public
    right to participate in the proceedings involving the adoption of the new ordinance.
    The strict compliance test is applied to prompt assertions of the shared public right
    to participate in the adoption of the new ordinance. 
    Id.
    Thus, while Objectors contend Landowner did not prove prejudice
    stemming from its purported lack of notice, the fact remains that Landowner filed
    its procedural validity challenge within 30 days of the new ordinance’s effective
    date. As a result, it only had to prove the Township failed to strictly comply with
    the required procedures set forth in the MPC, which, as explained above, it did.
    C. Standing
    1. Contentions
    As a final issue, Objectors argue Landowner lacked standing to bring
    its 2005 procedural validity challenge where it later sold the subject property.
    Specifically, Objectors assert, when Landowner filed its application, it identified
    the subject property as 112 Old Friedensburg Road.           However, Landowner
    continued to prosecute its challenge without amending its application. In fact, its
    failure to amend its application caused the ZHB to post the property of another
    neighbor, who later purchased the property at that address. Objectors contend
    Landowner sold the original 112 Old Friedensburg Road, and the new owner
    objected to the posting of his property. Moreover, that owner informed the ZHB’s
    solicitor that he had no intention of prosecuting the application. As such, the
    application belongs to that property owner, and he abandoned it. Objectors argue
    47
    Landowner did not receive an assignment of the application from the new property
    owner.   Thus, Landowner must file a new application to challenge the new
    ordinance.
    Landowner responds that the ZHB’s findings make clear that
    Landowner had a property interest in the same property as the underlying 2005
    validity challenge. F.F. Nos. 1-10. Further, Landowner argues at no point at the
    outset of the ZHB hearings did Objectors raise any standing issue or issue that the
    matter could not proceed before the ZHB for resolution of the procedural validity
    challenge. As properly noted by the trial court, Landowner contends, failure to
    raise this issue before the ZHB results in waiver. See Sojtori v. Douglass Twp. Bd.
    of Supervisors, 
    296 A.2d 532
     (Pa. Cmwlth. 1972).
    Landowner further argues, even if not waived, Objectors’ argument
    fails. To that end, in 2005, Landowner filed its challenge. Any landowner could
    properly raise a procedural defect. In 2005, Landowner was such a landowner, and
    it maintained possession of the subject property as set forth in the 2005 challenge.
    More specifically, as referenced by the ZHB at the outset of the
    hearing and in the advertisement, the subject property consists of approximately
    19.2 acres in the Township at Tax Parcel Number 5337-01-19-1692.                 The
    advertisement for the ZHB hearing used the same Tax Parcel Number and the same
    property description. No one disagreed that Landowner maintained ownership of
    the subject property as advertised in 2015 and as the application stated in 2005.
    Landowner argues that, while a small lot was excised, it maintained ownership of
    48
    the remainder of the property. It asserts the MPC and case law on the definition of
    “landowner” make clear that standing remains on an original application as long as
    any property interest exists. See Section 107 of the MPC, 53 P.S. §10107. Indeed,
    in interpreting Section 107, this Court determined a landowner must only possess
    an interest in the property. See, e.g., Bradley v. Zoning Hearing Bd. of Borough of
    Milford, 
    63 A.3d 488
     (Pa. Cmwlth. 2013).
    In sum, Landowner argues the record makes clear that it owns the
    subject property and that has not changed. In fact, the entire settlement discussion
    regarding the design of Landowner’s residential development confirms that the
    underlying property is still owned by Landowner.
    Similarly, the ZHB argues, Landowner had standing to bring and
    prosecute its challenge both in 2005 and in 2015. Landowner’s application states
    that the subject property is located along Old Friedensburg Road in the Township,
    at 112 Old Friedensburg Road and bearing Tax Parcel Number 5337-01-19-1629.
    The ZHB notes Landowner sold a portion of the subject property (referred to as the
    “Bercek Parcel”) after it filed its challenge. As a result, Landowner owned the
    remainder of the subject property and maintained the original Tax Parcel Number,
    despite the fact that the numerical postal address of 112 Old Friedensburg Road
    was assigned to the Bercek Parcel. Thus, the ZHB asserts, Landowner was in 2005
    and still was in 2015 at the time of the ZHB hearings, the owner of the subject
    property as identified in its application. Thus, Landowner meets the definition of a
    “landowner” in Section 107 of the MPC. As a result, it had standing to file the
    challenge.
    49
    In addition, the ZHB argues, Objectors did not raise Landowner’s
    alleged lack of standing at all during the ZHB hearings. To the contrary, Objectors
    did not object to any of the notices, advertisements or postings completed for the
    2015 hearings and acquiesced to their admission into the record at the hearings. As
    stated in the trial court’s opinion, Objectors argue, this issue was not properly
    before the trial court because Objectors did not raise it before the ZHB.
    2. Analysis
    Our review of the record here reveals no indication that Objectors
    raised any issue regarding Landowner’s standing to challenge the procedural
    validity of the new ordinance before the ZHB.         Therefore, as the trial court
    determined, because no party raised this issue before the ZHB, it is waived. See
    THW Grp., LLC v. Zoning Bd. of Adjustment, 
    86 A.3d 330
     (Pa. Cmwlth. 2014).
    Indeed, failure to raise the issue of an applicant’s standing to seek zoning relief
    during the proceedings before the fact-finder results in waiver. Id.; Friedlander v.
    Zoning Hearing Bd. of Sayre Borough, 
    546 A.2d 755
     (Pa. Cmwlth. 1988).
    Nevertheless, even if not waived, Objectors’ argument fails. To that
    end, at the time Landowner filed its procedural validity challenge, the applicable
    MPC provision permitted the filing of such challenges with the ZHB “by the
    landowner affected, any officer or agency of the municipality, or any person
    aggrieved.” Section 913.3 of the MPC, added by the Act of December 21, 1988,
    P.L. 1329, 53 P.S. §10913.3. Section 107 of the MPC defines “Landowner” as
    “the legal or beneficial owner … of land … or other person having a proprietary
    interest in land.”
    50
    Here, when Landowner filed its procedural validity challenge in 2005,
    it owned the subject property, which had an address of 112 Old Friedensburg
    Road. ZHB Op. at 1 n.1. In 2012, Landowner sold a small portion of the subject
    property comprised of 0.51 acres, referred to as the Bercek Parcel. Id. After the
    sale, the Bercek Parcel was assigned the numerical address of 112 Old
    Friedensburg Road, id.; however, the Tax Map Identification Number for the
    subject property remained the same. R.R. at 510a; F.F. No. 2. More importantly,
    Landowner retained ownership of the remainder of the subject property, a sizeable
    portion of which lies within the Township. Because Landowner maintained an
    ownership interest in the subject property, it had standing to pursue its procedural
    validity challenge.
    IV. Conclusion
    For all the foregoing reasons, we affirm the order of the trial court,
    which affirmed the ZHB’s order sustaining Landowner’s procedural validity
    challenge to the new ordinance.
    ROBERT SIMPSON, Judge
    51
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Sue Davis-Haas, Richard H. Haas,        :
    Ida C. Smith, Zildia Perez, Leon        :
    Perez, Donna Galczynski, Kevin          :
    Galczynski, Alan Ganas, Renee           :
    Froelich, Scott Matthews, Patricia      :
    J. Miravich, John J. Miravich and       :
    William Ryan,                           :
    Appellants    :
    :   No. 1739 C.D. 2016
    v.                          :
    :
    Exeter Township Zoning Hearing          :
    Board and MetroDev V, LP and            :
    Exeter Township                         :
    ORDER
    AND NOW, this 12th day of July, 2017, the order of the Court of
    Common Pleas of Berks County is AFFIRMED.
    ROBERT SIMPSON, Judge