Cornell Narberth, LLC v. Borough of Narberth ( 2017 )


Menu:
  •            IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Cornell Narberth, LLC,                          :
    Appellant                    :
    :
    v.                               :   No. 1577 C.D. 2016
    :   Argued: May 1, 2017
    Borough of Narberth, Montgomery                 :
    County, Pennsylvania and Yerkes                 :
    Associates, Inc., C. O'Brien                    :
    Architects, Inc. and Cheryl A. O'Brien          :
    BEFORE:        HONORABLE MARY HANNAH LEAVITT, President Judge
    HONORABLE RENÉE COHN JUBELIRER, Judge
    HONORABLE MICHAEL H. WOJCIK, Judge
    OPINION
    BY PRESIDENT JUDGE LEAVITT                                              FILED: July 14, 2017
    Cornell Narberth, LLC (Cornell) appeals an order of the Court of
    Common Pleas of Montgomery County (trial court) granting summary judgment to
    the Borough of Narberth (Borough) and its building inspector, Yerkes Associates,
    Inc. (Yerkes). Cornell argues that the trial court erred by finding that its breach of
    contract, promissory estoppel, and negligent misrepresentation claims were barred
    by the governmental immunity provisions under the act commonly known as the
    Political Subdivision Tort Claims Act (Tort Claims Act), 42 Pa. C.S. §§8541-8542,
    and the related official immunity provisions.1 Cornell also argues that the trial
    1
    Section 8541 of the Tort Claims Act provides: “[e]xcept as otherwise provided in this
    subchapter, no local agency shall be liable for any damages on account of any injury to a person
    or property caused by any act of the local agency or an employee thereof or any other person.”
    42 Pa. C.S. §8541. Section 8545 of the Judicial Code further provides: “[a]n employee of a local
    agency is liable for civil damages on account of any injury to a person or property caused by acts
    of the employee which are within the scope of his office or duties only to the same extent as his
    employing local agency and subject to the limitations imposed by this subchapter.” 42 Pa. C.S.
    §8545.
    court erred in holding that its evidence was insufficient to survive summary
    judgment on its equal protection claim. For the following reasons, we affirm.
    Background
    Cornell, a real estate developer, applied to the Borough for building
    permits to construct detached single-family homes on a four-lot subdivision known
    as Narberth Arbors.      Before submitting the permit applications, Cornell’s
    representatives met with William Martin, the Borough manager, and Robert
    Loeper, a representative of Yerkes, which does building inspections for the
    Borough, to discuss the construction of the residences. The Borough informed
    Cornell that the local ordinances did not require installation of an automatic
    sprinkler system in a detached single-family residence.
    Thereafter, Cornell submitted construction drawings to Yerkes
    showing that the homes would be built with pre-engineered wood roof trusses and
    would not have automatic sprinklers. Third Amended Complaint ¶13; Reproduced
    Record at 1286a (R.R. ___). Yerkes reviewed and approved the drawings. The
    Borough then issued building permits for each residence. The permits, which did
    not mention sprinklers, were issued “subject to the provisions of the Borough
    Ordinances.” Id., Exhibit A; R.R. 1305a. Cornell paid the required fees associated
    with the permits and began construction.
    A representative from Yerkes visited the site regularly and inspected
    each stage of the construction. Third Amended Complaint ¶20; R.R. 1287a. At no
    time during these inspections did anyone from Yerkes inform Cornell that it was
    required to install automatic sprinklers.      Id., ¶21; R.R. 1287a.   After Cornell
    completed the Lot 1 residence, Yerkes did a final inspection and notified the
    Borough to issue a certificate of occupancy. Id., ¶23; R.R. 1287a.
    2
    The Borough refused to issue the certificate of occupancy because
    Cornell had not installed automatic sprinklers, which are required for homes
    constructed with pre-engineered wood roof trusses. By letter dated September 15,
    2010, Martin, the Borough manager, informed Cornell that the sprinkler systems
    were required under Ordinance No. 843, the Fire Prevention Code (Fire Code),
    which provides in pertinent part:
    (1) All new construction except single family detached and
    single family semi-detached dwellings located within the
    Borough will be equipped with full sprinkler systems.
    a. Exception: if a single family detached or
    single family semi-detached dwelling is
    constructed with wooden truss floors or roof
    supports the structure must be sprinklered.
    Third Amended Complaint, Exhibit B, at 1; R.R. 1311a.
    Martin’s letter further explained that “[a]lthough the Borough has
    adopted the Uniform Construction Code (“UCC”),[2] the provisions of the UCC do
    2
    
    34 Pa. Code §§401.1-405.42
    . By way of background, in 1999, the Pennsylvania General
    Assembly enacted the Pennsylvania Construction Code Act (Act), Act of November 10, 1999,
    P.L. 491, as amended, 35 P.S. §§7210.101-7210.1103, to establish uniform and modern
    construction standards throughout the Commonwealth. See Section 102 of the Act, 35 P.S.
    §7210.102. The Act authorized the Department of Labor and Industry (Department) to
    promulgate regulations, and the Department did so on April 12, 2002, and January 9, 2004. See
    Section 105 of the Act, 35 P.S. §7210.105. These regulations are known as the Uniform
    Construction Code (UCC).
    The Act required municipalities to adopt the UCC as their municipal building code within
    90 days after the promulgation of the UCC. Section 501(a) of the Act, 35 P.S. §7210.501(a).
    Further, the Act provides that the UCC preempts any construction standards established in local
    ordinances that are different from those in the UCC. Section 104(d) of the Act, 35 P.S.
    §7210.104(d). However, local ordinances, in certain circumstances, may supplement the rules in
    the UCC. Section 303(b) of the Act, 35 P.S. §7210.303(b) (“Municipal building code ordinances
    in effect on July 1, 1999 … which contain provisions which equal or exceed the specific
    (Footnote continued on the next page . . .)
    3
    not supersede ordinances in effect on July 1, 1999 with provisions which equal or
    exceed the specific requirements of the UCC.”                 Id.; R.R. 1311a.       The letter
    acknowledged that Cornell’s building permits were issued in error and stated that
    “[i]f the violation [of the Fire Code] is not corrected immediately, the Borough will
    consider all appropriate remedies available, including revocation of the previously
    issued building permits.” Id. at 2; R.R. 1312a.
    Yerkes refused to inspect the remaining residences in the subdivision
    until Cornell installed automatic sprinkler systems. As a result, the construction on
    Lots 2, 3, and 4 was halted, which “jeopardiz[ed] closings on the Lot 3 and 4
    [r]esidences.” Third Amended Complaint ¶35; R.R. 1289a. One couple “sold their
    home in reliance on being able to move into their completed [r]esidence and was
    thereafter forced to lease-back their prior residence.”               Id., ¶39; R.R. 1290a.
    Similarly, the Lot 1 purchaser had no place to live as a result of the Borough’s
    refusal to issue a certificate of occupancy for that residence. Id., ¶36; R.R. 1289a.
    Cornell alleges that as a result of the actions of the Borough and Yerkes, it “had no
    other option but to install the sprinkler systems in the [r]esidences, or face breach
    of its agreements with the [purchasers].” Id., ¶45; R.R. 1291a. Cornell alleges its
    damages include, but are not limited to, the costs of installing the sprinklers and
    relocating the purchasers of the residences to other housing units. Id., ¶48-50; R.R.
    1291a.
    (continued . . .)
    requirements of the regulations promulgated under this act shall remain in effect until such time
    as any such provisions fail to equal or exceed the minimum requirements of the regulations
    promulgated under this act….”). In 2004, the Borough of Narberth adopted the UCC as its
    municipal building code while retaining its ordinances in effect in 1999, including the Fire Code,
    that had stricter standards. Complaint, Exhibit D, at 2; R.R. 47a.
    4
    Cornell’s third amended complaint3 contained five counts: (1) breach
    of contract against the Borough and Yerkes; (2) promissory estoppel against the
    Borough and Yerkes; (3) negligent misrepresentation against Yerkes; (4) violation
    of the equal protection clause of the U.S. Constitution under 
    42 U.S.C. §1983
    against the Borough and Yerkes; and (5) violation of the equal protection clause of
    the Pennsylvania Constitution.4 Yerkes then filed a joinder complaint against C.
    O’Brien Architects, Inc., and its principal, Cheryl O’Brien, alleging negligent
    misrepresentation.
    The parties engaged in discovery, which included depositions of
    Martin, Loeper, and Frederick Hansell, the Borough’s Assistant Manager. At the
    conclusion of discovery, the Borough and Yerkes filed motions for summary
    judgment, on which the trial court heard oral argument.
    In support of its motion for summary judgment, the Borough argued
    that “despite being couched as contractual or quasi-contractual claims,” the
    allegations in Cornell’s complaint were “clearly based upon negligence” and, thus,
    barred by the Tort Claims Act. Borough Motion for Summary Judgment ¶33; R.R.
    2483a-84a. The Borough also argued that the complaint did not state an equal
    protection claim under 
    42 U.S.C. §1983
     because its assertion “is unproven at the
    end of discovery.” 
    Id., ¶35
    ; R.R. 2484a.
    3
    Initially, Cornell filed a complaint in mandamus and a petition seeking preliminary injunctive
    relief. During the course of the litigation, Cornell amended the complaint three times and elected
    to withdraw its request for mandamus relief.
    4
    In ruling on the Borough and Yerkes’ preliminary objections to Cornell’s complaint, the trial
    court dismissed Cornell’s equal protection claim under the Pennsylvania Constitution. That
    claim is no longer at issue.
    5
    Yerkes argued that it acted as the Borough’s employee in its capacity
    as the appointed building inspector; therefore, it was immune from liability under
    the Tort Claims Act. In support, Yerkes cited the deposition testimony of Martin,
    who testified:
    [Question]: From the time that Yerkes was appointed as the
    Narberth Borough code official prior to 2010, until the present
    they have always been acting in the capacity as the appointed
    Narberth Borough code official?
    [Martin]: Yes, they have.
    [Question]: And with respect to all of the services that they
    have provided in connection with the Cornell project that is at
    issue in this case, all of those services were provided in their
    capacity as the Narberth Borough building code official?
    [Martin]: Yes, they were.
    Martin Deposition at 110; R.R. 6291a.
    Cornell responded that the Tort Claims Act provides no immunity for
    non-tort claims such as breach of contract and promissory estoppel.        Cornell
    argued that the building permits constituted contracts between the parties and made
    no mention of sprinklers. By failing to issue the certificate of occupancy in
    accordance with the permits, Cornell argued, the Borough and Yerkes breached the
    contract.
    As to the promissory estoppel claim, Cornell explained that the
    Borough and Yerkes informed Cornell at the pre-construction meeting that
    automatic sprinklers were not required in the planned residences and affirmed that
    representation through their subsequent actions, i.e., reviewing and approving the
    construction drawings, issuing the building permits, inspecting the construction
    site, and allowing the construction to continue. Cornell argued that the promise
    6
    made by the Borough and Yerkes is enforceable because Cornell detrimentally
    relied on it.
    Cornell further argued that its negligent misrepresentation claim
    against Yerkes was not shielded by the Tort Claims Act. Cornell asserted that our
    Supreme Court has “created a cause of action to a third party ‘where information is
    negligently supplied by one in the business of supplying information, and where it
    is foreseeable that the information will be used and relied upon by third persons.’”
    
    Id. at 9
    ; R.R. 3604a.
    With respect to its equal protection claim under 
    42 U.S.C. §1983
    ,
    Cornell pointed to its letter of December 29, 2010, that it sent to the Borough and
    the Fire Marshal. The letter identified a number of residences and educational
    institutions within the Borough that should have been constructed with fire
    sprinklers but were not. The letter requested an investigation of each of those
    properties. However, the Borough chose not to require these properties to correct
    the violations with the installation of automatic sprinklers. In support, Cornell
    cited Martin’s deposition testimony:
    [Question]: We have marked a document … on Cornell Homes
    letterhead dated December 29, 2010, Mr. William Henderson,
    Jr., Narberth Fire Company President, signed by Mark
    McSorley … cc’d to the Narberth Borough Council Members
    and Thomas Grady, Mayor of Narberth. Have you seen this
    letter before?
    ***
    [Martin]: It was in the file, yes. I can’t recall when I saw it, no.
    ***
    7
    [Question]: So you didn’t do anything then with respect to
    following up with any of the properties that are identified here
    in Mr. McSorley’s letter?
    [Martin]: I did not, no.
    [Question]: Do you know if anybody in the Borough did?
    [Martin]: No, I don’t know that they did.
    Martin Deposition at 105-06; R.R. 6286a-87a. Cornell argued that the Borough’s
    inaction with respect to those other properties is inconsistent with “its claim that
    life safety issues were of such paramount concern.” Cornell’s Brief in Opposition
    to the Borough’s Motion for Summary Judgment at 19; R.R. 3326a. Cornell
    argued that there is no rational basis for the disparate treatment.
    The trial court granted the Borough’s and Yerkes’ motions for
    summary judgment. The trial court rejected Cornell’s contract claims for the stated
    reason that the “promise” made by the Borough and Yerkes was unenforceable.
    Relying on Section 403.63(f) of the UCC, which provides that a building code
    official may suspend or revoke a permit “when the permit is issued in error, on the
    basis of inaccurate or incomplete information or in violation of any act, regulation,
    ordinance or the [UCC],” 
    34 Pa. Code §403.63
    (f), the trial court concluded that
    “the permits were freely revocable and thus any ‘contract’ created between those
    parties was illusory.” Trial Court op., 8/25/2016, at 8.
    The trial court also dismissed Cornell’s promissory estoppel claim,
    concluding that it was in actuality a negligence claim barred by the Tort Claims
    Act. Citing this Court’s decisions in Peluso v. Kistner, 
    970 A.2d 530
     (Pa. Cmwlth.
    2009), and Gallagher v. Lynch, (Pa. Cmwlth., No. 2359 C.D. 2011, filed August
    21, 2012), the trial court noted that “the substance of a plaintiff’s allegations, rather
    than the label that a plaintiff has affixed to a particular cause of action,” determines
    8
    whether a claim is barred by governmental immunity. Trial Court op., 8/25/2016,
    at 11. The trial court concluded that “[e]ven though the pleadings [in the instant
    case] speak of promissory estoppel, negligence is the gist of the action.” Id. at 12.
    The trial court held that Cornell’s claim did not fall under any of the exceptions to
    immunity in Section 8542 of the Tort Claims Act, 42 Pa. C.S. §8542.
    Similarly,   the   trial   court   held   that   Cornell’s    negligent
    misrepresentation claim against Yerkes was barred by the Tort Claims Act.
    Finding that Yerkes acted as an employee of the Borough, the trial court reasoned:
    It is undisputed that Yerkes was the official building inspector
    for the Borough during the relevant times. When Yerkes
    performs building inspections, it acts on behalf of the Borough,
    its employer.      Therefore, it is immune from negligent
    representation liability under the [Tort Claims Act].
    Trial Court op., 8/25/2016, at 13.
    Finally, the trial court dismissed Cornell’s equal protection claim
    under 
    42 U.S.C. §1983
    , concluding that Cornell “failed to adduce sufficient
    evidence to survive summary judgment.” Trial Court op., 8/25/2016, at 15. The
    trial court found:
    [T]he only substantive evidence is a letter written by Cornell
    representatives to the Borough Fire Marshal and Borough
    Council referencing six permits that the Borough has allegedly
    granted in violation of Narberth Ordinance No. 843. Only two
    of those instances involve a property with wooden trusses, and
    only one involves roof trusses. The other four instances involve
    alleged violations of other provisions of the ordinance.
    
    Id.
     The trial court reasoned that the letter “is barely a scintilla of evidence and
    would clearly not survive trial on the merits.” 
    Id.
     Further, enforcement of the
    ordinance “may be relaxed at the discretion of the Borough.” 
    Id.
     Therefore, the
    9
    trial court concluded, summary judgment was appropriate. Cornell now appeals to
    this Court.5
    Appeal
    On appeal, Cornell raises four issues. First, it argues that the trial
    court erred in holding that the building permits did not create a “legally binding
    contract” between Cornell and the Borough and Yerkes. Cornell Brief at 18.
    Second, it argues that the trial court erred in ruling that its promissory estoppel
    claim is really a tort action that is barred by the Tort Claims Act. Third, Cornell
    argues that the trial court erred in dismissing its negligent misrepresentation claim
    against Yerkes, which, it asserts, is “an independent professional liability claim”
    that is “not subsumed by the Tort Claims Act.” 
    Id. at 45
    . Fourth, Cornell argues
    that the trial court erred in dismissing its equal protection claim under 
    42 U.S.C. §1983
     “in the face of clear, undisputed testimony from [the] Borough’s own
    employees that Cornell was treated as a class of one.” 
    Id. at 50
    .
    “A motion for summary judgment may be granted only where there is
    no genuine issue of material fact and the moving party is entitled to judgment as a
    matter of law.” Flood v. Silfies, 
    933 A.2d 1072
    , 1074 (Pa. Cmwlth. 2007). A fact
    is material if it directly affects the disposition or the outcome of a case.
    Department of Environmental Protection v. Delta Chemicals, Inc., 
    721 A.2d 411
    ,
    416 (Pa. Cmwlth. 1998). The moving party has the burden of proving that there is
    no genuine issue of material fact. Laich v. Bracey, 
    776 A.2d 1022
    , 1024 (Pa.
    5
    This Court’s scope of review of a trial court’s order granting summary judgment is plenary and
    we apply the same standard for summary judgment as does the trial court. Cochrane v. Kopko,
    
    975 A.2d 1203
    , 1205 (Pa. Cmwlth. 2009). We reverse a trial court’s order granting summary
    judgment only where it is established that the trial court committed an error of law or abused its
    discretion. 
    Id.
    10
    Cmwlth. 2001). The right to judgment must be clear and free from doubt. In
    considering the merits of a motion for summary judgment, a court must “view the
    record in the light most favorable to the non-moving party, and all doubts as to the
    existence of a genuine issue of material fact must be resolved against the moving
    party.” Flood, 
    933 A.2d at 1074
     (quotations omitted). We now consider the
    parties’ arguments in light of the above-referenced principles and this Court’s
    standard of review.
    Breach of Contract Claim
    Cornell argues that the building permits issued by the Borough and
    Yerkes to Cornell constitute an express contract. Specifically, Cornell asserts that
    it made an offer to the Borough and Yerkes to construct four homes in the Borough
    in accordance with the construction plans it submitted; that it paid permit fees in
    excess of $6,000 as consideration for the contract; and that the Borough and
    Yerkes accepted Cornell’s offer by issuing permits to Cornell for the construction
    of the homes based on the submitted and approved plans. Cornell Brief at 19.
    Alternatively, Cornell argues that “an implied-in-fact contract
    nevertheless exists,” which is evidenced by the parties’ actions. Cornell Brief at
    20-21. Contrary to the trial court’s finding that the building permits represent an
    illusory and unenforceable promise, Cornell argues that the permits are, “at the
    very least, voidable contracts.” Id. at 26. Cornell asserts that, “[i]n order for the
    [p]ermits to be unenforceable … the [p]ermits would have to have actually been
    revoked and evidence presented showing that the [p]ermits were validly
    revoked[.]” Id. at 24. Because the Borough and Yerkes did not revoke or suspend
    the permits, they “accept[ed] the benefits flowing from [the contract]” and,
    therefore, effectively ratified a voidable contract. Id. at 26. Cornell argues that it
    11
    has a vested right “to complete the work in accordance with the approved plans
    and issued permits,” id. at 28, and the Borough and Yerkes breached the contract
    by refusing to issue the certificates of occupancy.
    To establish a contract, all essential elements must exist, including
    consideration.     The requirement of consideration “is nothing more than a
    requirement that there be a bargained for exchange.”                        Department of
    Transportation v. First Pennsylvania Bank, 
    466 A.2d 753
    , 754 (Pa. Cmwlth.
    1983). “There can obviously be no such bargained for exchange if one of the
    parties is already legally bound to render the performance promised.” 
    Id.
     “A
    promise to do what the promisor is already bound to do cannot be a consideration,
    for if a person gets nothing in return for his promise but that to which he is already
    legally entitled, the consideration is unreal.” In re Commonwealth Trust Company
    of Pittsburgh, 
    54 A.2d 649
    , 651 (Pa. 1947).
    In First Pennsylvania Bank, a bank financed the purchase of a new
    automobile from Murphy Ford and acquired a first lien on the vehicle.               Murphy
    Ford then requested that the Department of Transportation record the lien pursuant
    to former Section 1133(c) of the Vehicle Code,6 which provided that the
    Department “shall endorse on the existing certificate of title, or on a new certificate
    which it then issues, the name and address of all secured parties and shall mail the
    certificate of title to the first lienholder named in the certificate.”                 First
    Pennsylvania Bank, 466 A.2d at 754 (quoting former 75 Pa. C.S. §1133). The
    Department, however, did not endorse the title and mailed the certificate to the
    6
    Section 1133 of the Vehicle Code was deleted by the Act of June 8, 2001, P.L. 123, effective
    July 1, 2001.
    12
    car’s owner, instead of the bank. The owner then sold the car, stopped making
    payments on his loan, and moved out of state.
    The bank requested the Department to pay the outstanding balance of
    the loan, alleging that it was a third-party beneficiary of a contract between the
    Department and Murphy Ford. The bank argued that the Department breached the
    contract by failing to record the lien and mail the title to the proper party. Holding
    that there was no contract between the Department and Murphy Ford, this Court
    found that the Department was legally required by former Section 1133(c) of the
    Vehicle Code to endorse the title and mail it to the first lienholder. “There was,
    therefore, no bargained for exchange between Murphy Ford and [the Department],
    and hence, no consideration.” Id.
    Likewise, here, the Borough is required by law to review and grant (or
    deny) building permits. Section 403.63(a) of the UCC, for example, provides that
    “[a] building code official shall grant or deny a permit application, in whole or in
    part, within 15 business days of the filing date or the application is deemed
    approved.”    
    34 Pa. Code §403.63
    (a) (emphasis added).            Similarly, Section
    403.63(b) provides that “[a] building code official shall examine the construction
    documents and shall determine whether the construction indicated and described is
    in accordance with the [UCC] and other pertinent laws or ordinances as part of the
    application process.”    
    34 Pa. Code §403.63
    (b) (emphasis added).             Section
    403.64(a) states that “[a] construction code official shall inspect all construction
    for which a permit was issued.”       
    34 Pa. Code §403.64
    (a) (emphasis added).
    Further, Section 403.65(b) states that “[a] building code official shall issue a
    certificate of occupancy after receipt of a final inspection report that indicates
    13
    compliance with the [UCC] and ordinance[.]” 
    34 Pa. Code §403.65
    (b) (emphasis
    added).
    The UCC also requires a developer to obtain building permits and pay
    any permit fees before commencing construction. Section 403.62(a) of the UCC
    provides that “[a]n owner or authorized agent who intends to construct ... a
    residential building … shall first apply to the building code official and obtain the
    required permits under §403.62a (relating to permit application).” 
    34 Pa. Code §403.62
    (a) (emphasis added). Section 403.63(k) provides that “[a] permit is not
    valid until the required fees are collected[.]” 
    34 Pa. Code §403.63
    (k).
    In short, the UCC required Cornell to obtain the building permits and
    pay the permit fees before constructing the Narberth Arbors homes. Similarly, it
    required the Borough and Yerkes to examine the construction documents; issue the
    building permits; inspect construction; and issue a certificate of occupancy.
    “Where a legal obligation exists, a cumulative promise to perform it, unless upon a
    new consideration, is a nullity. Such promise adds nothing to and takes nothing
    from the original obligation.” In re Commonwealth Trust Company of Pittsburgh,
    54 A.2d at 651 (internal quotations omitted). Because a promise to perform an
    obligation that the promisor is already legally bound to do cannot be consideration,
    we conclude that the building permits did not create a contractual relationship
    among Cornell, the Borough, and Yerkes.
    Further, our Supreme Court, in Commonwealth v. Devlin, observed:
    A “building permit” is not a contract; it is exactly what it says it
    is–a permit to erect a building according to the plans and
    specifications submitted with the application therefor. It does
    not require the property owner to erect such a building, but only
    permits him to do so. For any reason satisfactory to himself he
    may change his mind and not begin the construction, and his
    14
    decision in this respect will not be reviewable by the inspector
    or the city; or, having started, may stop before the building is
    completed, in which event no authority can compel him to go
    on.
    
    158 A. 161
    , 163 (Pa. 1932) (emphasis original). Based on the foregoing analysis,
    we conclude that the trial court did not err in granting summary judgment in favor
    of the Borough and Yerkes on Cornell’s breach of contract claim.
    Promissory Estoppel Claim
    Cornell argues, next, that the trial court erred in holding its
    promissory estoppel claim to be a “disguised” tort claim. Cornell asserts that a
    promissory estoppel claim “arise[s] from [an] implied contract[], and accordingly,
    sound[s] in contract not tort.” Cornell Brief at 41. Cornell sought damages under
    a theory of detrimental reliance, and the Tort Claims Act does not apply to such a
    claim.   Cornell argues that its detrimental reliance on the assurances by the
    Borough and Yerkes that the homes would not require sprinklers created “the
    consideration necessary for the formation of a contract, the breach of which
    becomes actionable.” 
    Id. at 41
    .
    We begin with a review of the principles of detrimental reliance,
    which this Court has explained “is another name for promissory estoppel.” Peluso
    v. Kistner, 
    970 A.2d 530
    , 532 (Pa. Cmwlth. 2009) (quoting Travers v. Cameron
    County School District, 
    544 A.2d 547
    , 550 (Pa. 1988)). Promissory estoppel
    provides an equitable remedy to enforce a “contract-like promise that would be
    otherwise unenforceable under contract law principles.”       
    Id.
       In promissory
    estoppel, the aggrieved party must show that “(1) the promisor made a promise that
    he should have reasonably expected to induce action or forbearance on the part of
    the promisee; (2) the promisee actually took action or refrained from taking action
    15
    in reliance on the promise; and (3) injustice can be avoided only by enforcing the
    promise.” Crouse v. Cyclops Industries, 
    745 A.2d 606
    , 610 (Pa. 2000). These
    factors are strictly enforced to guard against the “loose application” of promissory
    estoppel. Peluso, 
    970 A.2d at 533
    .
    Cornell argues that all of the promissory estoppel elements are present
    here. The Borough and Yerkes promised Cornell that it could build the Narberth
    Arbors homes without installing automatic sprinklers; in reliance Cornell built the
    homes without sprinklers; the Borough and Yerkes did not keep their promise
    because they later demanded the installation of sprinklers; and Cornell incurred
    substantial expenses to install them. Cornell argues that “[j]ustice will only be
    served if Cornell is compensated by [the] Borough and Yerkes for these
    unexpected substantial additional expenses.” Cornell Brief at 43.
    A plaintiff cannot defeat the defense of governmental immunity by
    couching a tort claim as a breach of contract claim. Matarazzo v. Millers Mutual
    Group, Inc., 
    927 A.2d 689
    , 693 (Pa. Cmwlth. 2007). Cornell’s claim lacks a
    necessary prerequisite for asserting promissory estoppel: a contract-like promise.
    The Borough and Yerkes promised, at most, to perform an obligation that they
    were legally bound to perform by the UCC.          A promise to perform a legal
    obligation is not a contract-like promise.
    The facts here are very similar to those in Gallagher v. Lynch, (Pa.
    Cmwlth., No. 2359 C.D. 2011, filed August 21, 2012). In Gallagher, the township
    issued landowners a permit for an on-lot sewage disposal system to serve the home
    they planned to build, and the landowners began construction. Months later, the
    Pennsylvania Department of Environmental Protection revoked the permit. The
    16
    landowners sued the sewage enforcement officer and the township for damages
    incurred as a result of their detrimental reliance on the permit.
    The trial court in Gallagher concluded that the landowners’ claim,
    labeled detrimental reliance or promissory estoppel, sounded in tort rather than
    contract. The landowners’ allegations set forth the elements of a negligence claim,
    i.e., a duty to conduct a site examination and to issue a permit in a competent, non-
    negligent manner; a breach of that duty of care; and damages resulting from such
    breach. The trial judge, therefore, dismissed the landowners’ claim under the
    immunity provisions of the Tort Claims Act. This Court adopted the trial court’s
    opinion with the above reasoning.
    Likewise, here, Cornell’s claim, although labeled as promissory
    estoppel, sounds in tort. The factual allegations in Cornell’s complaint set forth the
    elements of a negligent misrepresentation claim, which is “(1) a misrepresentation
    of a material fact; (2) made under circumstances in which the misrepresenter ought
    to have known its falsity; (3) with an intent to induce another to act on it; and (4)
    which results in injury to a party acting in justifiable reliance on the
    misrepresentation.” Bortz v. Noon, 
    729 A.2d 555
    , 561 (Pa. 1999). Accordingly,
    the trial court did not err in holding that Cornell’s promissory estoppel claim
    against the Borough is barred by the immunity provisions of the Tort Claims Act,
    42 Pa. C.S. §§8541-8542.
    Because the Borough and Yerkes did not make a contract-like promise
    and because the factual allegations in Cornell’s complaint set forth a negligent
    misrepresentation claim, we conclude that the trial court did not err in granting
    summary judgment to the Borough and Yerkes on Cornell’s promissory estoppel
    claim.
    17
    Negligent Misrepresentation Claim against Yerkes
    Cornell argues that the trial court erred by dismissing its negligent
    misrepresentation claim against Yerkes, which is “an independent professional
    liability claim … not subsumed by the Tort Claims Act.” Cornell Brief at 45.
    Yerkes responds that as the appointed building inspector, it is an employee of the
    Borough; therefore, “any action or inaction by Yerkes while acting in the official
    capacity of the Borough building inspector would be immune from suit under the
    [Tort Claims Act].” Yerkes Brief at 10.
    In support, Yerkes cites to this Court’s decision in Higby
    Development, LLC v. Sartor, 
    954 A.2d 77
     (Pa. Cmwlth. 2008).7 In that case, a real
    estate developer sued several township employees along with Yerkes Associates,
    Inc., which acted as the township’s code enforcement officer, and Russel Yerkes,
    the individual who performed the duties of the township’s code enforcement
    officer, alleging that they engaged in tortious conduct to impede its real estate
    development. Russel Yerkes countered that he was an employee of the township
    and, thus, immune from liability under the Tort Claims Act. The trial court ruled
    in favor of Russel Yerkes.
    Affirming the trial court, this Court examined Section 8501 of the
    Judicial Code, which defines the term “employee” as follows:
    Any person who is acting or who has acted on behalf of a
    government unit whether on a permanent or temporary basis,
    whether compensated or not and whether within or without the
    7
    In 2010, the Supreme Court vacated this Court’s order in Higby and remanded the matter to the
    trial court for further proceedings on the intentional tort claims. Higby Development, LLC v.
    Sartor, 
    991 A.2d 305
     (Pa. 2010). Notably, the Supreme Court did not reverse this Court’s
    holding that a third party who acts on behalf of a government unit in performing governmental
    functions is immune from liability under the Tort Claims Act.
    18
    territorial boundaries of the government unit, including any
    volunteer fireman and any elected or appointed officer, member
    of a governing body or other person designated to act for the
    government unit. Independent contractors under contract to the
    government unit and their employees and agents and persons
    performing tasks over which the government unit has no legal
    right of control are not employees of the government unit.
    42 Pa. C.S. §8501 (emphasis added). We found that the definition does not require
    a person to be “an employee in the traditional sense, but only that the employee is
    acting on behalf of the governmental entity.” Higby, 
    954 A.2d at 85
    . In support,
    this Court cited Walls v. Hazleton State Hospital, 
    629 A.2d 232
     (Pa. Cmwlth.
    1993). There, a patient brought a malpractice claim against a doctor, who was
    employed by a medical group retained as an independent contractor to provide
    medical services to a state hospital. The Walls court held that although the doctor
    was not a traditional employee, he was an “employee” of the Commonwealth
    because he was a person who “acted on behalf of a government unit whether on a
    permanent or temporary basis.” 
    Id.
     at 236-37 (citing 42 Pa. C.S. §8501). The
    Higby court therefore held:
    Because Yerkes was clearly acting as the Code Enforcement
    Officer on behalf of the Township in order to determine
    whether the next phase of construction could occur, and clearly
    did not make final decisions of Supervisors as he only
    recommended to them whether or not [Certificates of
    Occupancy] should be issued, Yerkes was an “employee” for
    purposes of the Tort Claims Act and was entitled to
    governmental immunity.
    Higby, 
    954 A.2d at 86
    .
    Likewise, here, Yerkes Associates was hired by the Borough as its
    official building inspector. Acting in that capacity, Yerkes examined and approved
    19
    construction drawings; recommended the issuance of building permits; and
    inspected the construction for which permits had been issued. Section 8501 of the
    Judicial Code defines “employee” as “any person who is acting or who has acted
    on behalf of a government unit[.]” 42 Pa. C.S. §8501. The definition does not
    require a person to be “an employee in the traditional sense, but only that the
    employee is acting on behalf of the governmental entity.” Higby, 
    954 A.2d at 85
    .
    Notably, Section 403.3(a) of the UCC requires that a building code official be
    appointed to enforce the Construction Code Act. 
    34 Pa. Code §403.3
    (a). Yerkes,
    in carrying out its responsibilities as a building code official, acted on behalf of the
    Borough. Consistent with our decision in Higby, we conclude that Yerkes acted as
    an “employee” of the Borough for purposes of the Tort Claims Act.
    Cornell argues that our Supreme Court’s decision in Bilt-Rite
    Contractors, Inc. v. The Architectural Studio, 
    866 A.2d 270
     (Pa. 2005), provides “a
    legal basis for [its] negligent misrepresentation claim against Yerkes.” Cornell
    Brief at 49. In that case, a school district hired an architectural firm to design a
    new school building. Relying on the architect’s drawings and plans, a construction
    company submitted a bid for general construction work on the project. The school
    district awarded the company the contract, and construction began. The company
    later found that the architect’s drawings and plans contained inaccurate
    information, which substantially increased construction costs. The company sued
    the architect for negligent misrepresentation under Section 552 of the Restatement
    (Second) of Torts (Restatement).8 The trial court dismissed the complaint, holding
    8
    Section 552 of the Restatement (Second) of Torts provides:
    (1) One who, in the course of his business, profession or employment, or in any
    other transaction in which he has a pecuniary interest, supplies false information
    (Footnote continued on the next page . . .)
    20
    that the architect owed no duty to the company. The Superior Court affirmed. The
    Supreme Court reversed, finding that “it is reasonable to hold [architects and other
    design] professionals to a traditional duty of care for foreseeable harm.” Bilt-Rite
    Contractors, 866 A.2d at 286. The Court recognized that Section 552 of the
    Restatement “sets forth the parameters of a duty owed when one supplies
    information to others, for one’s own pecuniary gain, where one intends or knows
    that the information will be used by others in the course of their own business
    activities.” Id. at 285-86.
    Cornell argues that under Bilt-Rite Contractors, Yerkes should be
    found liable because it “supplies information to others for personal gain,” and
    Cornell relied on Yerkes’ information “to its distinct detriment.” Cornell Brief at
    49. Cornell’s reliance on Bilt-Rite Contractors is misplaced. Unlike Bilt-Rite
    Contractors, the issue in the instant case is not whether Yerkes owed a duty of care
    (continued . . .)
    for the guidance of others in their business transactions, is subject to liability for
    pecuniary loss caused to them by their justifiable reliance upon the information, if
    he fails to exercise reasonable care or competence in obtaining or communicating
    the information.
    (2) Except as stated in Subsection (3), the liability stated in Subsection (1) is
    limited to loss suffered
    (a) by the person or one of a limited group of persons for whose
    benefit and guidance he intends to supply the information or knows
    that the recipient intends to supply it; and
    (b) through reliance upon it in a transaction that he intends the
    information to influence or knows that the recipient so intends or
    in a substantially similar transaction.
    (3) The liability of one who is under a public duty to give the information extends
    to loss suffered by any of the class of persons for whose benefit the duty is
    created, in any of the transactions in which it is intended to protect them.
    RESTATEMENT (SECOND) OF TORTS §522 (1977).
    21
    to Cornell or whether Cornell established a prima facie case of negligence. Rather,
    the trial court here granted summary judgment to Yerkes based on its affirmative
    defense of governmental immunity, which is separate from the merits of Cornell’s
    cause of action. An affirmative defense bars recovery even when the plaintiff has
    established a prima facie case.       Notably, the architectural firm in Bilt-Rite
    Contractors did not raise a defense of governmental immunity or claim it was an
    employee of the school district. Bilt-Rite Contractors, therefore, is inapposite.
    For all these reasons, we conclude that the trial court did not err in
    granting summary judgment in favor of Yerkes on Cornell’s negligent
    misrepresentation claim.
    Equal Protection Claim
    Finally, Cornell challenges the trial court’s conclusion that Cornell did
    not make a case on its equal protection claim under 
    42 U.S.C. §1983
    . Cornell
    asserts that the “undisputed facts and the admissions of [the] Borough” establish a
    violation of Cornell’s equal protection rights under the “class of one” theory.
    Cornell Brief at 52.
    Section 1983 provides, in pertinent part:
    Every person who, under color of any statute, ordinance,
    regulation, custom, or usage, of any State or Territory or the
    District of Columbia, subjects, or causes to be subjected, any
    citizen of the United States or other person within the
    jurisdiction thereof to the deprivation of any rights, privileges,
    or immunities secured by the Constitution and laws, shall be
    liable to the party injured in an action at law….
    
    42 U.S.C. §1983
    . To hold a state actor liable under Section 1983, “a plaintiff must
    prove a deprivation of a right guaranteed by the Constitution or the Laws of the
    United States by a defendant acting under the color of law.” Pettit v. Namie, 931
    
    22 A.2d 790
    , 801 (Pa. Cmwlth. 2007). “Section 1983 does not create substantive
    rights but, rather, is the vehicle for vindicating rights conferred in the United States
    Constitution or in federal statutes.” Jae v. Good, 
    946 A.2d 802
    , 809 (Pa. Cmwlth.
    2008).
    Cornell asserts that the Borough and Yerkes deprived it of its right to
    equal protection under the law guaranteed by the Fourteenth Amendment to the
    U.S. Constitution.9 Where the plaintiff does not allege membership in a protected
    class, he may assert an equal protection claim under the “class of one” theory.
    Village of Willowbrook v. Olech, 
    528 U.S. 562
    , 564 (2000). A plaintiff bringing a
    “class of one” claim must demonstrate that (1) the defendant treated him
    differently from others similarly situated; (2) the defendant did so intentionally;
    and (3) any differential treatment was without rational basis. Hill v. Borough of
    Kutztown, 
    455 F.3d 225
    , 239 (3d Cir. 2006). A “class of one” claim, like any
    equal protection claim evaluated under rational basis review, cannot succeed “if
    there is any reasonably conceivable state of facts that could provide a rational basis
    for the classification.”      Heller v. Doe, 
    509 U.S. 312
    , 320 (1993) (quotation
    omitted).
    Cornell argues that it presented sufficient evidence to support an equal
    protection claim under the “class of one” theory. Cornell points to the deposition
    testimony of Frederick Hansell, the Borough’s Assistant Manager, who testified in
    pertinent part:
    9
    The equal protection clause of the Fourteenth Amendment provides that “[n]o state shall …
    deny to any person within its jurisdiction the equal protection of the laws.” U.S. CONST. amend.
    XIV, §1.
    23
    [Question]: To your knowledge, the four lots of the Narberth
    Arbors project … are the only four residences where the
    borough has required fire sprinklers?
    [Hansell]: Yes.
    ***
    [Question]: Are you aware of any residential construction in the
    borough ever, other than these four lots, where the borough has
    required fire sprinklers?
    [Hansell]: No.
    Hansell Deposition at 123, 126; R.R. 5010a, 5013a.           Cornell asserts that the
    Borough “intentionally discriminated against Cornell by requiring Cornell, and
    only Cornell, to install automatic sprinklers in the Narberth Arbors homes.”
    Cornell Brief at 52.
    Cornell sent a letter to the Borough and the Fire Marshal that
    identified a number of properties within the Borough that are in violation of the
    Fire Code by not having sprinklers. In addition, Martin testified that he did not
    investigate those violations. Cornell argues this evidence demonstrated disparate
    treatment, which violated its right to equal protection of the laws.
    It is well established that “issue spotting without analysis or legal
    citation to support an assertion precludes our appellate review of [a] matter.”
    Boniella v. Commonwealth, 
    958 A.2d 1069
    , 1072 n.8 (Pa. Cmwlth. 2008). See
    also Pa. R.A.P. 2119(a) (requiring argument of issues to be “followed by such
    discussion and citation of authorities as are deemed pertinent.”). The evidence
    cited by Cornell relates to the Borough, but it has nothing to do with Yerkes.
    Cornell has not cited any evidence that Yerkes was involved in the alleged
    disparate treatment; its mere assertion of error does not suffice.
    24
    We consider, next, the trial court’s entry of summary judgment in
    favor of the Borough on Cornell’s equal protection claim. A municipality is a
    “person” that can be sued directly under Section 1983 and be held liable in certain
    circumstances. Arocho v. County of Lehigh, 
    922 A.2d 1010
    , 1021 (Pa. Cmwlth.
    2007) (citing Monell v. Department of Social Services of City of New York, 
    436 U.S. 658
    , 690 (1978)). A municipality cannot, however, be held liable under
    Section 1983 on a respondeat superior theory. 
    Id.
     (citing Monell, 
    436 U.S. at 691
    ). “Rather, liability will be imposed when the municipality implements an
    official policy that is either unconstitutional on its face or is the ‘moving force’
    behind the constitutional tort of one of its employees.” 
    Id.
     (citing Monell, 
    436 U.S. at 694
    ). “Policy is made when a ‘decisionmaker possess[ing] final authority
    to establish municipal policy with respect to the action’ issues an official
    proclamation, policy, or edict.” Andrews v. City of Philadelphia, 
    895 F.2d 1469
    ,
    1480 (3d Cir. 1990) (quoting Pembaur v. City of Cincinnati, 
    475 U.S. 469
    , 481
    (1986)). In the absence of an official policy, a municipality may also face liability
    under Section 1983 “for constitutional deprivations visited pursuant to
    governmental ‘custom’ even though such a custom has not received formal
    approval through the body’s official decisionmaking channels.” Monell, 
    436 U.S. at 690-91
    .
    This Court has held that “a municipality cannot be held liable in a
    Section 1983 action in the absence of a predicate unconstitutional act by the
    municipality’s employee.” Arocho, 
    922 A.2d at 1022
    . “Even if the municipality’s
    actions are arbitrary or even conscience shocking, in a constitutional sense the
    municipality cannot be held liable under Section 1983.” 
    Id.
     (internal quotations
    omitted).
    25
    Cornell argues that the Borough “has chosen not to require retroactive
    installation of automatic sprinklers on a number of similarly situated properties
    within the Borough, i.e. other buildings constructed with pre-engineered wood roof
    trusses.” Cornell Brief at 53-54. Cornell has not identified a custom or policy of
    the Borough “that is either unconstitutional on its face or is the ‘moving force’
    behind the constitutional tort of one of its employees.” Arocho, 
    922 A.2d at 1021
    .
    Section 403.65(d) of the UCC provides that “[a] building code official may
    suspend or revoke a certificate of occupancy when the certificate was issued in
    error….” 
    34 Pa. Code §403.65
    (d) (emphasis added). Similarly, Section 403.63(f)
    of the UCC provides that “[a] building code official may suspend or revoke a
    [building] permit issued under the [UCC] … when the permit is issued in error….”
    
    34 Pa. Code §403.63
    (f). Stated otherwise, the building code official may suspend
    or revoke a permit, but need not do so. That the Borough did not revoke or
    suspend the certificates issued for other similar properties does not mean the
    Borough acted deliberately to deprive Cornell of property rights. In any case,
    Cornell did not demonstrate a constitutional violation by a municipal actor; its
    equal protection claim against the Borough must fail as a matter of law. Arocho,
    
    922 A.2d at 1022
    .
    Further, this Court has observed that the “concept of equal protection
    does not require that [the administrative agency] attack a problem all at once or not
    at all.” UMCO Energy, Inc. v. Department of Environmental Protection, 
    938 A.2d 530
    , 540 (Pa. Cmwlth. 2007) (quoting Life Insurance Company of North America
    v. Insurance Department, 
    402 A.2d 297
    , 299 (Pa. Cmwlth. 1979)). An equal
    protection claim fails when a property owner merely alleges that state laws could
    have been applied against its predecessor in title but were not. Anselma Station,
    26
    Ltd. v. Pennoni Associates, Inc., 
    654 A.2d 608
    , 616 (Pa. Cmwlth. 1995). Cornell
    contends that the Borough should have taken action against other similarly situated
    properties not in compliance with the Fire Code. However, the Borough does not
    have to respond to every violation of the Fire Code in an identical fashion. The
    Equal Protection Clause of the Fourteenth Amendment does not require uniform
    enforcement of an ordinance. Ignelzi v. Zoning Board of Adjustment of the City of
    Pittsburgh, 
    495 A.2d 634
    , 636-37 (Pa. Cmwlth. 1985).
    Conclusion
    For the foregoing reasons, we affirm the trial court’s grant of
    summary judgment to Borough and Yerkes.
    ______________________________________
    MARY HANNAH LEAVITT, President Judge
    27
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Cornell Narberth, LLC,                   :
    Appellant             :
    :
    v.                           :   No. 1577 C.D. 2016
    :
    Borough of Narberth, Montgomery          :
    County, Pennsylvania and Yerkes          :
    Associates, Inc., C. O'Brien             :
    Architects, Inc. and Cheryl A. O'Brien   :
    ORDER
    AND NOW, this 14th day of July, 2017, the order of the Court of
    Common Pleas of Montgomery County, dated August 25, 2016, in the above-
    captioned matter is hereby AFFIRMED.
    ______________________________________
    MARY HANNAH LEAVITT, President Judge