Moore v. Goran, LLC , 388 Mont. 340 ( 2017 )


Menu:
  •                                                                                                08/22/2017
    DA 17-0032
    Case Number: DA 17-0032
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    
    2017 MT 208
    MARK MOORE,
    Plaintiff and Appellee,
    v.
    GORAN, LLC and JOHN DOES 1-5,
    Defendants and Appellants.
    APPEAL FROM:            District Court of the Twenty-Second Judicial District,
    In and For the County of Carbon, Cause No. DV-16-27
    Honorable Blair Jones, Presiding Judge
    COUNSEL OF RECORD:
    For Appellants:
    W. Scott Mitchell, Brianne C. McClafferty, Holland & Hart LLP,
    Billings, Montana
    For Appellee:
    James R. Halverson, John L. Wright, Halverson, Mahlen & Wright, P.C.,
    Billings, Montana
    Submitted on Briefs: June 28, 2017
    Decided: August 22, 2017
    Filed:
    __________________________________________
    Clerk
    Chief Justice Mike McGrath delivered the Opinion of the Court.
    ¶1     This appeal comes from the District Court’s grant of a summary judgment motion
    in favor of Mark Moore.
    ¶2     We restate the issue on appeal as follows:
    Did the District Court err when it granted summary judgment to Moore?
    FACTUAL AND PROCEDURAL BACKGROUND
    ¶3     Mark Moore (Moore) is the owner of the Moore gravel pit (Moore Pit) north of
    Red Lodge, Montana.       Goran, LLC (Goran) is a Utah Limited Liability Company
    contracted by the Montana Department of Transportation (MDT) to build the Red Lodge
    Tied Projects. Moore and Goran entered into a contract (Contract) in which Moore
    agreed to provide Goran crushed aggregate material. Goran’s form contract was used.
    ¶4     Moore loaded crushed aggregate onto Goran’s trucks at the Moore Pit, where it
    was weighed and the driver of Goran’s truck would sign for and receive a weight ticket.
    Each week Moore would send an invoice to Goran for the crushed aggregate, measured
    by the ton at the Moore Pit; Goran paid the invoices. Once Goran had removed all of the
    materials from the Moore Pit it needed, Goran refused to pay the final invoices. Moore
    sued for breach of contract, violation of the Montana Prompt Payment Act, and unjust
    enrichment. Goran filed a counterclaim for breach of contract, breach of duty of good
    faith and fair dealing, and unjust enrichment.
    ¶5     In the District Court, Goran argued it overpaid Moore for the materials it took
    from the Moore Pit. Moore disagreed, arguing that Goran clearly took material from the
    2
    Moore Pit and then refused to pay. Goran argued the Contract did not specify how the
    parties would measure the amount of material taken from the Moore Pit and that the
    materials should be measured by volume by MDT at the Red Lodge Tied Projects.1
    Moore argues the Contract requires measurement of the material by weight and that the
    only evidence of the material Goran took possession of was the measurements in tons at
    the Moore Pit scales.
    ¶6     Moore moved for summary judgment, arguing that the Contract unambiguously
    required Goran to base payment on the tonnage of crushed aggregate weighed by
    Moore’s scales. The District Court agreed with Moore and granted his motion. The
    District Court determined Goran breached the Contract by refusing to pay for the crushed
    aggregate material. The District Court determined that Goran was unjustly enriched and
    owes Moore $66,269.952 for the crushed aggregate it removed, as measured by the
    Moore Pit scale. The District Court granted attorney’s fees to Moore, as the prevailing
    party. Goran appeals.
    STANDARD OF REVIEW
    ¶7     We review de novo a district court’s grant or denial of summary judgment,
    applying the same criteria of M. R. Civ. P. 56 as a district court. Pilgeram v. GreenPoint
    Mortg. Funding, Inc., 
    2013 MT 354
    , ¶ 9, 
    373 Mont. 1
    , 
    313 P.3d 839
    . The construction
    and interpretation of a written agreement are questions of law that we review for
    1
    Goran asserts MDT measured the crushed aggregate material in cubic yards at the Red
    Lodge Tied Projects daily.
    2
    Moore asserts Goran owes a total of $188,486.82, has paid $122,216.87, and
    $66,269.95 is the amount still owed.
    3
    correctness. Ophus v. Fritz, 
    2000 MT 251
    , ¶ 19, 
    301 Mont. 447
    , 
    11 P.3d 1192
    ; Mary J.
    Baker Revocable Trust v. Cenex Harvest States, Coops., Inc., 
    2007 MT 159
    , ¶ 19, 
    338 Mont. 41
    , 
    164 P.3d 851
    . If the Supreme Court reaches the same conclusion as the
    District Court, but on different grounds, it may affirm the district court’s judgment.
    Johnson Farms, Inc. v. Halland, 
    2012 MT 215
    , ¶ 11, 
    366 Mont. 299
    , 
    291 P.3d 1096
    .
    DISCUSSION
    ¶8    Did the District Court err when it granted summary judgment to Moore?
    ¶9    Goran argues the District Court erred when it granted summary judgment to
    Moore; the District Court was presented with conflicting evidence regarding the amount
    of crushed aggregate removed from the Moore Pit, which created an issue of material
    fact. Goran asserts the District Court resolved this issue of material fact by improperly
    interpreting the Contract.   Specifically, Goran asserts the District Court ignored the
    payment terms of Paragraph 3 and created its own definition of the term “project,” in the
    Contract.
    ¶10   The District Court determined that, based on the language of the Contract that
    “delivery to the project” occurred when the crushed aggregate was loaded onto Goran’s
    trucks at the Moore Pit. Goran argues the District Court’s interpretation of the Contract
    language “delivered to the project” was incorrect.
    ¶11   A contract is to be taken together, as a whole, to give effect to every part if
    reasonably practicable, each clause helping to interpret the other. Section 28-3-202,
    MCA. When interpreting a written contract, the court should determine the intention of
    the parties from the writing alone if possible. Section 28-3-303, MCA. A court’s duty is
    4
    to enforce contracts as they are written, not to make new ones for the parties. Hein v.
    Fox, 
    126 Mont. 514
    , 521, 
    254 P.2d 1076
    , 1080 (1953). The interpretation of a contract is
    a question of law. Ophus, ¶ 19.
    ¶12    Initially we note that while Goran asserts MDT measurement by volume can be
    used to determine the amount of material removed from the pit, the Contract clearly
    indicates that the crushed aggregate material was to be bought and sold by the ton. As
    such, the MDT measurements by volume were not contemplated in the Contract between
    Moore and Goran.      The only measurement available to the parties of the crushed
    aggregate in tons was the Moore Pit scales. The Contract requires the material to be
    weighed at the Moore Pit scales by the ton and the parties practice was for Goran to be
    invoiced based on those weights.
    ¶13    Goran argues that based on the Contract it owes Moore for material actually
    delivered to the project, that the term project was defined in the Contract as the “RED
    LODGE TIED PROJECTS,” and therefore delivery could take place nowhere else.
    ¶14    However, Goran inserts language into the Contract by giving “project” a different
    meaning that the one actually used in the Contract. The contract specifically defines
    “project” within the general terms section. It is defined as “the construction project for
    which GORAN is arranging with SUPPLIER to purchase goods and/or services
    hereunder.”   As defined in the contract the term is not used to denote a particular
    location, but rather refers to the construction project as a whole—the purpose of the
    contract.
    5
    ¶15    For our purposes here, the pertinent part of the Contract states “[V]endor agrees to
    furnish F.O.B. Moore Pit an estimated quantity of all material as listed below. . . .”
    Moore Pit is the location where delivery to the project occurred.
    ¶16    Montana has adopted the Uniform Commercial Code (UCC) and it is codified in
    Montana statute. Section 30-1-102, MCA, et seq. The UCC is designed to simplify,
    clarify, and modernize the law governing commercial transactions.                   Section
    30-1-102(1)(a), MCA.
    ¶17    Montana’s Uniform Commercial Code controls agreements to sell goods. Section
    30-2-102, MCA; Webcor Elecs. v. Home Elecs., 
    231 Mont. 377
    , 383, 
    754 P.2d 491
    , 494
    (1988). Section 30-2-105, MCA, defines “goods” to mean all things movable at the time
    of the contract for sale. Rothing v. Kallestad, 
    2007 MT 109
    , ¶ 27, 
    337 Mont. 193
    , 
    159 P.3d 222
    . Crushed aggregate is a good as it was movable at the time of the contract. The
    UCC controls the interpretation of this Contract.
    ¶18    Under the UCC it is the obligation of the seller to transfer and deliver, and that of
    the buyer to accept and pay, in accordance with the contract. Section 30-2-301, MCA.
    Here, the Contract stated that Moore would “[F]urnish F.O.B. Moore Pit an estimated
    quantity of materials. . . .” The F.O.B. language is a term of art under the UCC and
    means “free on board.” Section 30-2-319, MCA; Litecubes, LLC v. N. Light Prods., 
    523 F.3d 1353
    , 1358 n.1 (Fed. Cir. 2008); N. Am. Philips Corp. v. Am. Vending Sales, Inc., 
    35 F.3d 1576
    , 1578 n.2 (Fed. Cir. 1994). F.O.B. is followed by a location, usually the place
    of shipment (where the goods are shipped from) or a place of destination (where the
    buyer takes possession of the goods). Section 30-2-319, MCA. Contracting parties use
    6
    F.O.B. terms to designate where delivery would take place and where risk of loss would
    transfer from seller to buyer. 
    Litecubes, 523 F.3d at 1358
    n.1 (Fed. Cir. 2008); MEMC
    Elec. Materials, Inc. v. Mitsubishi Materials Silicon Corp., 
    420 F.3d 1369
    , 1374 n.3 (Fed.
    Cir. 2005); § 30-2-509, MCA.
    ¶19    If the language following F.O.B. is the place of shipment, the seller must move the
    goods at its expense and maintain control of and the risk of loss of the goods until the
    seller places the goods with a carrier. Section 30-2-319(1)(a), MCA, provides “[W]hen
    the term is F.O.B. the place of shipment, the seller must at that place ship the goods in the
    manner provided in this chapter (30-2-504) and bear the expense and risk of putting them
    into the possession of the carrier.” The risk of loss will transfer from seller to buyer
    when the seller places the goods in the hands of a carrier. Section 30-2-509, MCA;
    United States use of Gaunt v. Carl M. Geupal Constr. Co., 
    423 F.2d 818
    , 820 (7th Cir.
    1970) (interpreting the Indiana UCC statute identical to Montana’s UCC statute). In a
    shipment contract, title passes to the buyer at the time and place of shipment. Section
    30-2-401(2), MCA. Title passes to the buyer at the time and place at which the seller
    completes performance with reference to the delivery of the goods. Section 30-2-401(2),
    MCA.
    ¶20    In the instant case, the Contract required Moore to deliver the goods “F.O.B.
    Moore Pit.” The F.O.B. term creates a shipment contract, as the language following
    F.O.B. is Moore Pit, the location from where Moore would ship the goods. In this F.O.B.
    place of shipment contract, the risk of loss, injury, or destruction of the crushed aggregate
    would be borne by Moore until the crushed aggregate material had been loaded for
    7
    shipment. Possession, title, and risk of loss passed to Goran at the Moore Pit when
    Moore delivered the crushed aggregate directly to Goran. This Contract provides that
    delivery to the project occurred at the Moore Pit.
    ¶21    The Moore Pit scale is the only location where the material could have been
    measured per the Contract. Goran argues that the MDT measurements taken at the Red
    Lodge Tied Projects should be used to determine the amount of material it obtained. This
    interpretation would in effect impose risk of loss of material on Moore after delivery took
    place and potentially not until the Red Lodge Tied Projects were completed.           This
    interpretation is contrary to the UCC as noted above. Unless otherwise explicitly agreed
    title passes to the buyer at the time and place at which the seller completes performance
    with reference to the delivery of the goods. Section 30-2-401(2), MCA.
    ¶22    The Contract required Moore to deliver the crushed aggregate to Goran at the
    Moore Pit.    Title and risk of loss transferred at the Moore Pit, when Goran took
    possession. The contract required material to be sold by the ton and payment would be
    based on the measurements taken at the pit.
    ¶23    On appeal, Goran contends that the amount of material it received from Moore
    was in dispute, thus creating a genuine issue of material fact; therefore summary
    judgment was inappropriate. The District Court determined both that the amount of
    material was not in dispute and that Goran had failed to submit admissible evidence
    disputing the amount of material actually removed.
    ¶24    After a thorough review of the pleadings and record as well as the arguments made
    on appeal, we conclude Goran failed to provide the trial court with substantial evidence
    8
    indicating there was a discrepancy in the amount of materials it took from the Moore Pit.
    Evidence sufficient to raise a genuine issue of material fact “must be in proper form and
    conclusions of law will not suffice; the proffered evidence must be material and of a
    substantial nature, not fanciful, frivolous, gauzy or merely suspicious.” Elk v. Healthy
    Mothers, Healthy Babies, Inc., 
    2003 MT 167
    , ¶ 16, 
    316 Mont. 320
    , 
    73 P.3d 795
    . Goran
    cites Mary J. Baker Revoc. Trust, ¶ 17, noting that it is entitled to all reasonable
    inferences which may be drawn from its offered proof in defeating summary judgment.
    While we agree with the cited rule, the fact is that Goran has simply failed to offer proof
    of a material factual dispute that would support an inference in its favor.
    ¶25    The evidence provided by Goran is the affidavit of Todd Cusick and MDT
    measurement documents. The documents purporting to be MDT measurements were
    never authenticated. The documents seem to be pages taken at random from a larger
    document.    The affiant, Cusick, does not have, and doesn’t purport to have, direct
    personal knowledge of the measurements taken by MDT.
    ¶26    Under M. R. Civ. P. 56(e)(2), the party opposing a motion for summary judgment
    cannot rely on speculation or conclusory statements. Baumgart v. State, 
    2014 MT 194
    ,
    ¶ 14, 
    376 Mont. 1
    , 
    332 P.3d 225
    . For any document to be considered with an affidavit,
    the exhibits must have proper foundation laid by an affiant with personal knowledge of
    the document’s authenticity and genuineness as well as the basis for hearsay exclusion.
    Alfson v. Allstate Property and Cas. Ins. Co., 
    2013 MT 326
    , ¶ 13, 
    372 Mont. 363
    , 
    313 P.3d 107
    . Unauthenticated documents cannot be considered on a motion for summary
    judgment. Alfson, ¶ 13.
    9
    ¶27    Goran has failed to present sufficient admissible evidence to establish a genuine
    issue of material fact. The District Court properly granted summary judgment to Moore.
    CONCLUSION
    ¶28    The Contract designated that the material was to be sold by weight, in this case
    tons. The Moore Pit scales were the only place to weigh the material by the ton. Moore
    would base Goran’s invoices on that measurement. Further, the Contract specified that
    the vendor agreed to furnish the material to Goran F.O.B. Moore Pit and thus the point of
    delivery was, and the title as well as the risk of loss were transferred at, the Moore Pit.
    The District Court properly granted summary judgment to Moore as Goran failed to
    present sufficient evidence to establish that an issue of material fact existed regarding the
    amount of material Goran removed from the Moore Pit. Moore is entitled to reasonable
    attorney’s fees and costs for both trial and appeal in this case under § 28-2-2105, MCA.
    We remand to the District Court for determination of fees and costs.
    ¶29    Affirmed.
    /S/ MIKE McGRATH
    We Concur:
    /S/ LAURIE McKINNON
    /S/ DIRK M. SANDEFUR
    /S/ BETH BAKER
    /S/ MICHAEL E WHEAT
    10