CNH Industrial America LLC v. Jones Lang LaSalle Americas , 882 F.3d 692 ( 2018 )


Menu:
  •                                In the
    United States Court of Appeals
    For the Seventh Circuit
    No. 16-3800
    CNH INDUSTRIAL AMERICA LLC,
    Plaintiff-Appellee,
    v.
    JONES LANG LASALLE AMERICAS, INC.,
    Defendant-Appellant.
    Appeal from the United States District Court for the
    Eastern District of Wisconsin.
    No. 2:15-cv-00981-JPS — J. P. Stadtmueller, Judge.
    ARGUED SEPTEMBER 13, 2017 — DECIDED FEBRUARY 15, 2018
    Before BAUER, ROVNER, and SYKES, Circuit Judges.
    ROVNER, Circuit Judge. CNH Industrial America LLC
    (“CNH”), which manufactures farming and construction
    machinery (including tractors, combines, backhoes, and the
    like) under the New Holland brand name, hired the global real
    estate services firm Jones Lang LaSalle America, Inc. (“JLL”) to
    manage a corporate re-branding program that involved the
    2                                                 No. 16-3800
    replacement of signage at each of CNH’s more than 1,400
    dealers in North America. The program ran into problems
    when it was discovered that the vinyl used in the new signs
    was defective, necessitating the re-manufacture and replace-
    ment of virtually all of the signs already installed. After the
    vinyl manufacturer walked away from its commitment to
    replace, at its own cost, the defective signs, CNH sued JLL for
    breach of the service agreement between the two firms. CNH
    alleged that JLL had failed to perform adequate quality control
    in the manufacturing of the signs, failed to negotiate the best
    possible warranty on the vinyl and the signs themselves, and
    failed to properly document and manage the warranties.
    Following a bench trial, the district court agreed that JLL had
    indeed breached its contractual obligations to CNH and that
    CNH had suffered damages in the amount of $5,482,735.
    Pursuant to the contract’s terms, the court reduced JLL’s
    liability to $3,026.361.60—the sum CNH had paid to JLL in
    project management fees—plus such other amounts as JLL
    might recover from third parties (including the vinyl manufac-
    turer and the sign fabricators) in the future. JLL appeals, and
    we affirm the judgment in all respects.
    I.
    In 2007, CNH’s global parent—the Italian automaker
    Fiat—decided that the New Holland brand needed updating.
    It commissioned a team to create a new logo and prototype
    dealer sign, and then it directed CNH to implement a re-
    branding program pursuant to which all of the signage at each
    of CNH’s 1,442 independent dealerships in North America
    would be replaced. The typical dealer would require a family
    of five signs, including a pylon sign mounted on a large pole,
    No. 16-3800                                                    3
    a dealership name sign, an outdoor wall-mounted logo sign, a
    “parts” sign, and a “service” sign. CNH was to hire one or
    more American sign manufacturers to adapt the prototype and
    build the dealer signs to American specifications. Given the
    logistics entailed in replacing the signs at over 1,400 dealers
    (including site surveys, landlord approval, obtaining the
    requisite permits from governmental entities, manufacturing
    and installing the new signs, and disposing of the old signs),
    CNH decided to hire another firm to manage the process.
    CNH chose JLL to manage the sign-replacement program.
    JLL is a commercial real estate services firm that offers a wide
    array of services to property owners and investors. JLL
    represented that it had precisely what CNH was looking for:
    experience with large-scale signage replacement programs and
    the ability to provide “turnkey” management of all aspects of
    the re-branding program. CNH and JLL entered into a Service
    Agreement in April 2008.
    JLL’s obligations under the agreement—set forth in a
    Statement of Work attached thereto—were comprehensive,
    consistent with its role as the manager of the re-branding
    program. It was to develop specifications for the signs, identify
    and recommend to CNH for approval a firm or firms to
    manufacture the new signs, do the same with respect to raw
    materials suppliers for the sign components, supervise the
    manufacturing process, coordinate the entire replacement
    process with dealers from beginning to end, and handle any
    complaints from dealers about installed signs. Four of the
    obligations that JLL expressly assumed under the Service
    Agreement are particularly relevant here: (1) the obligation to
    “negotiat[e] … the best possible Warranty Program for the
    4                                                   No. 16-3800
    Family of Signs manufactured and disclose all elements of [the]
    Warranty Program to CNH and Dealers”; (2) “research and
    document[ ] … warranty information for all raw materials and
    sub components”; (3) “provide ongoing Project Management
    services for Warranty within One[ ]Year from the date of
    installation” for each sign; and (4) take “direct control and
    responsibility of all manufacturing including quality control
    meeting all [JLL] and CNH expectations.” Ex. 1002 Attach. B
    § 1(B) ¶4; § 1(C) ¶1; § 2(C) ¶¶ 1, 2. CNH retained the authority
    to control the sign-replacement project and approve or reject
    JLL’s recommendations, but it is clear from the agreement that
    JLL was assuming the burden of managing the project. And the
    testimony of CNH’s witnesses leave no doubt that CNH,
    consistent with JLL’s presentation materials, viewed JLL as the
    expert in this area and deferred to it as such.
    In order to reduce shipping costs, three different sign
    manufacturers at diverse locations around the country were
    chosen to produce the new signs. JLL signed the manufactur-
    ing contracts on CNH’s behalf, so that the multitude of
    invoices on the manufactured signs would be directed to JLL
    and it could make payment and resolve any disputes that
    arose. The agreements took effect on June 17, 2008. The
    contracts were identical to one another and contained the same
    warranties on the manufactured signs: a one-year warranty on
    parts, labor, and workmanship. The one-year warranty period
    constituted a reduction from the three-year period originally
    proposed. CNH was keenly interested in “value engineering”
    that would reduce the costs of the re-branding program to
    itself and its dealers, and toward that end it accepted a shorter
    No. 16-3800                                                    5
    warranty period in exchange for lower costs on the new
    signage.
    CNH required its dealers to pay for three of the five new
    signs to be installed at each dealership; CNH paid for the
    remaining two. Dealers expressed displeasure about the cost of
    the new signs—$10,500 for the three dealer-owned signs. In
    response to those concerns, dealers were given the option to
    finance their sign purchases; they were also given the option to
    make their own arrangements to install their signs, which
    would reduce their cost to $7,000. However, self-installation
    would nullify the one-year warranty on the signs—a nullifica-
    tion that the district court understood to be limited to problems
    associated with the installation as opposed to defects in the
    components of the signs.
    Upon JLL’s recommendation, Arlon, Inc. (“Arlon”) was
    selected as the exclusive supplier of the vinyl used to manufac-
    ture the new signs. The design specifications called for the New
    Holland signs to be fabricated using two custom-formulated
    colors: blue and yellow. The presentation materials Arlon had
    submitted in support of its successful proposal to CNH and
    JLL included details about the warranties Arlon offered on its
    products. Arlon’s standard warranty provided for replacement
    of the vinyl only (as opposed to labor, shipping, and other
    costs) on a prorated basis for a period of seven years. Distinct
    warranty terms were specified for Arlon’s Flexface®FX vinyl
    substrate, a product that JLL and CNH rejected in favor of
    Arlon’s translucent vinyl, which the sign manufacturers would
    apply to acrylic, heat, and then mold to create the sign faces.
    Arlon’s materials compared its standard warranties to those of
    its leading competitor, 3M, to demonstrate that Arlon’s
    6                                                  No. 16-3800
    warranties were superior in all respects. Custom warranties
    were also available on Arlon’s products.
    JLL accepted the warranty terms that Arlon proposed
    without, so far as the record reveals, attempting to negotiate
    terms that were more favorable to CNH. (Arlon’s representa-
    tive would later testify that he was aware of no negotiations
    over the terms, and the JLL employee who was the project
    manager at the time believed he discussed the warranty with
    Arlon but could not recall any specifics.) As we will discuss
    below, there is some real question as to what the actual
    warranty terms were. The only evidence of the warranty that
    either party has been able to identify is a brief summary of the
    terms that was included in an exhibit attached to each of the
    sign-manufacturing contracts. Arlon has disclaimed authorship
    of that summary and has disputed its accuracy; for its part, JLL
    does not know who drafted it. The summary states in full:
    Arlon Vinyl Extended Warranty—7 year warranty
    on 1st surface. 2nd surface on exterior sign applica-
    tions is 9 years. These [sic] is no charge for
    parts/labor/shipping for 1-year from date of installa-
    tion.
    Ex. 52 & Ex. E-Warranty thereto. The reference to the one-year
    period during which there would be no charge for parts, labor,
    or shipping evidently was a reference to the sign manufactur-
    ers’ warranty on the completed signs rather than the warranty
    on the Arlon vinyl. The reference to the Arlon warranty itself
    is incomplete. Arlon’s presentation materials indicated that it
    would replace defective vinyl on a pro-rated basis tied to the
    number of months remaining in the seven-year term; and JLL
    No. 16-3800                                                    7
    understands this to be a materials-only warranty that excluded
    coverage for labor and other costs. But, again, there is no
    document in the record that actually sets out the agreed-upon
    terms of the Arlon warranty.
    As manufacturing of the signs commenced late in 2008,
    problems soon emerged with the Arlon vinyl. In December
    2008, one of the sign fabricators reported that the yellow vinyl
    being used in the two-color CNH signs failed during the
    manufacturing process—the vinyl showed signs of bubbling
    and tearing. JLL reported the problem to CNH and worked
    with the sign manufacturers and Arlon to identify the source
    of the problem. The vinyl was determined to be defective, and
    Arlon agreed to replace the defective run of vinyl and reim-
    burse the sign manufacturers for their expenses. The replace-
    ment vinyl supplied by Arlon was stress-tested by the manu-
    facturers, and signs fabricated with the new vinyl came off the
    assembly line free of noticeable defects. JLL did not arrange for
    any independent testing of the vinyl to confirm that it was free
    of defects, nor did it demand that Arlon supplement its
    original warranty with any written assurance that it would
    take care of future problems with the vinyl at its expense.
    A second manufacturing problem occurred sometime after
    this incident and before 2010 as the result of a discrete run of
    vinyl that had not been properly cured. When the sign manu-
    facturers reported the problem, Arlon tested and reformulated
    the vinyl, and the problem appeared to be solved.
    The more serious problem with the vinyl—and the one that
    gave rise to this suit—first emerged in late 2010 or early 2011,
    as dealers began to report that blue vinyl on the signs which
    8                                                     No. 16-3800
    had been installed on their premises was showing signs of
    cracking and peeling. By the fall of 2011, some twenty-three
    installed signs had been reported as defective. That number
    would increase substantially through the remainder of the year
    and into 2012 as dealers continued to notice problems with the
    signs.
    In October 2011, Arlon agreed to cover the expense of
    replacing any and all signs that failed due to problems with its
    vinyl. This agreement significantly improved upon Arlon’s
    warranty, as it was not limited to replacing the defective vinyl
    but covered the full cost (including parts and labor) of manu-
    facturing and installing replacements for the defective signs. So
    far as the record reveals, however, Arlon never memorialized
    that agreement by way of an amended warranty or other
    formal instrument; and as problems with the vinyl continued
    to mount, Arlon would eventually walk away from its commit-
    ment to replace the defective signs.
    At no time did the parties undertake any form of audit or
    inventory to determine how many signs in the field might be
    failing; they instead chose to passively wait for dealers to
    notice and report failures to CNH and JLL and ask the sign
    manufacturers and Arlon to address them at that time. The
    parties agree that the possibility of such an audit was dis-
    cussed, but they disagree as to who proposed it and who was
    responsible for rejecting it. JLL insists that it suggested the
    possibility of both a field survey of all signs that were installed
    in 2008 and 2009 or, alternatively, a telephonic survey of
    dealers, but that CNH rejected both options in favor of what
    JLL labels the “break and fix” approach in order to keep the re-
    branding program on schedule. CNH disputes that account
    No. 16-3800                                                    9
    and contends that it raised the possibility of an audit, but that
    JLL assured CNH an audit was unnecessary given Arlon’s
    commitment to replace any and all defective signs.
    As time wore on, it became clear that the problems with
    Arlon’s vinyl were anything but isolated. Dealers continued to
    report problems with cracking and peeling signs, and JLL
    would in turn forward those reports to the sign manufacturers
    and Arlon so that replacements could be produced. A joint
    review of the reported vinyl failures by JLL and CNH in
    January 2014 revealed that approximately 46.7% of the 628 sites
    where signs had been installed in 2008 and 2009 had failed, and
    yet Arlon had been able to replace just over half (53.6%) of the
    defective signs. CNH complained about the delays, and JLL in
    turn spoke with Arlon about speeding up the replacement
    process.
    Unbeknownst to anyone else, Arlon had determined in
    early 2012, based on weatherometer testing, that there had
    been a failure in the formulation of all versions of the custom
    blue vinyl that it had produced for the CNH re-branding
    program to that date. Arlon thus had reason to foresee that
    signs manufactured using that vinyl would continue to fail at
    a substantial rate. Arlon kept this information to itself. Not
    until Arlon was required to disclose this information by
    subpoena in this litigation did the parties become aware of
    what Arlon had determined years earlier.
    Arlon Graphics LLC had acquired the operating assets of
    Arlon, Inc.’s vinyl manufacturing division late in 2011 and in
    connection with acquisition agreed to indemnify Arlon, Inc. for
    any warranty obligations stemming from defective vinyl
    10                                                           No. 16-3800
    products, including the custom vinyl produced for CNH. The
    new entity—which we shall continue to label “Arlon”—took
    over the replacement program for the failing New Holland
    signs.
    In 2013 and early 2014, Arlon began to chafe under the
    burdens of its commitment to replace the failing signs. In 2013,
    it complained about the prices that the sign manufacturers
    were charging for replacement signs. It also hired its own sign
    installer in an effort to reduce costs. Additionally, Arlon
    prevailed upon JLL and CNH to confine their replacement
    requests to no more than 10 per month in order to slow the
    pace of replacements.
    Following discussions with JLL in early 2014 about the need
    to expedite the replacement of defective signs, Arlon evidently
    decided it had had enough. In May 2014, Arlon informed JLL
    that it had been replacing signs pursuant to a three-year
    warranty (set forth in the 2008 presentation materials as the
    standard warranty on Arlon’s Flexface® FX/PSA combination
    vinyl products, which JLL and CNH had not selected) rather
    than a seven-year warranty, and that the three-year warranty
    period had expired. Arlon indicated that it was willing to
    contribute $3,000 per dealer site toward the ongoing replace-
    ment of defective signs, but no more. CNH responded by
    threatening legal action. In July 2014, Arlon declared that it
    would cease replacing signs altogether and would no longer
    communicate with JLL.1
    1
    CNH filed suit against Arlon in California state court in April 2015. That
    suit remains pending.
    No. 16-3800                                                  11
    When the bad news from Arlon was reported to CNH, the
    latter’s point person on the project emailed JLL accusing it of
    mismanaging the situation with Arlon.
    This is beyond disappointing. The process we
    followed was … put into place by JLL, Arlon &
    Priority [one of the three sign manufacturers] and
    was not the process that CNH requested. The order
    in which signs were repaired was not within CNH
    control either. There are signs that were reported in
    2011 that are still not repaired.
    CNH did not let dealers … self report, this was the
    process we were given to get the warranty covered.
    I have had numerous conversations over the last
    year with [the current JLL project manager] about
    sending a letter to our dealers and asking them [to]
    check their signs and report them, however, I was
    assured this was not necessary because Arlon was
    going to cover the signs via warranty. The informa-
    tion you have provided is the first time I am hearing
    that they are not willing to cover the replacement of
    the signs or that there is a limit on what they are
    going to cover.
    We pay JLL to manage our signs. I would have
    expected the management would include managing
    this problem and it appears it was not managed
    properly.
    Ex. 135A at 1. The two continued doing business as before,
    however, until JLL gave CNH notice in February 2016 (approx-
    imately six months after CNH commenced this litigation
    12                                                             No. 16-3800
    against JLL) that it was terminating the Service Agreement
    effective March 31, 2016. Thereafter, CNH made arrangements
    with one of the three sign manufacturers to replace the sign
    faces on all of the failed signs, and it engaged 3M to supply the
    vinyl for the additional replacement signs it required. 3M
    provided a warranty of up to 9 years on the new vinyl,
    depending on whether the signs would be installed in the
    American Southwest, illuminated, or fabricated with additional
    ultraviolet protection.
    CNH filed this suit against JLL in August 2015 alleging that
    JLL had breached its obligations under the Service Agreement.2
    After a one and one-half day bench trial, the district court
    found in CNH’s favor. The court, in sum, agreed with CNH
    that JLL had (1) failed to engage in any negotiations with Arlon
    over the terms of its warranty on the vinyl, thus breaching its
    obligation to negotiate the best possible warranty on the signs
    and sign components; (2) failed to research and document
    Arlon’s warranty terms and accurately inform CNH of those
    terms, instead relying on a warranty summary of unknown
    provenance and accuracy; (3) breached its duty to exert quality
    control over the manufacturing process by failing to engage in
    any sort of independent effort to identify the cause of the
    failing signs and confirm that Arlon had resolved it; and (4)
    breached its obligation to provide warranty management
    2
    JLL in turn filed a third-party complaint against the sign manufacturers,
    who are contractually responsible for enforcing Arlon’s warranty. The
    manufacturers invoked their right to arbitration and were dismissed from
    this litigation. The arbitration has been stayed pending the resolution of this
    appeal.
    No. 16-3800                                                   13
    services within one year of the date of installation of each sign
    by failing to ensure that warranty claims were presented in a
    timely manner. In reaching these conclusions, the court
    adopted CNH’s proposed facts where they conflicted with
    JLL’s, and necessarily discredited the testimony of JLL’s
    original project manager on the CNH job as to certain pro-
    active steps JLL had allegedly suggested to CNH to deal with
    the problem signs but that CNH had allegedly rejected. The
    court found that, owing to these contractual breaches, CNH
    had suffered damages totaling $5,482,735, a figure CNH’s
    damages expert arrived at based on the cost of replacing all
    defective signs. However, based on a limitation of liability
    provision in the agreement, the court reduced the damage
    award to $3,026,361.60, a sum equal to the total amount of fees
    CNH had paid to JLL over the life of the agreement, plus
    whatever additional amounts JLL might later recover from the
    individual sign manufacturers, Arlon, or its own insurance
    company.
    JLL has appealed from the adverse judgment, contesting
    the district court’s rationale in toto.
    II.
    A. Subject matter jurisdiction
    We begin our review by resolving a belated argument
    regarding jurisdiction. Subject matter jurisdiction in this case
    is premised on diversity of citizenship, 28 U.S.C. § 1332, and it
    is beyond dispute that there is complete diversity of citizenship
    as between the named parties: CNH is a limited liability
    company whose sole member, Case New Holland Industrial,
    Inc. is a Delaware corporation which maintains its principal
    14                                                  No. 16-3800
    place of business in Wisconsin; whereas JLL is a Maryland
    corporation whose principal place of business is in Illinois.
    And, of course, CNH’s claim for relief surpasses the statutory
    $75,000 threshold for diversity jurisdiction.
    But CNH’s suit is founded not only on its own injuries, but
    on those suffered by 260 Case New Holland dealers who
    assigned their individual claims to CNH. As we noted in our
    factual summary, ownership of the dealer signs is divided: the
    dealers each paid for and own three of the five signs installed
    at every dealership, and CNH paid for and owns the other two.
    Before bringing suit, CNH invited all of its 1,442 North
    American dealers to assign their claims regarding the defective
    signs to CNH so that it could pursue relief on behalf of the
    dealers as well as itself. Some 260 dealers did so.
    Under the terms of the assignment, each dealer surrendered
    to CNH “all rights and interest in and to any claims arising out
    of signs owned by the Dealer … which show cracking or
    checking in the blue vinyl fields.” The dealer acknowledged
    that, as a result of the assignments, it would “not be a party to
    negotiations or litigation …, and that counsel for [CNH] will
    not be acting as counsel for the Dealer.” CNH, in turn, under-
    took to “negotiate or litigate these claims as the owner of the
    assigned claims … .” It further agreed to pay for the cost of
    repairing or replacing defective signs “pending a successful
    resolution of these matters.” A successful resolution was
    defined as “a recovery or settlement value equal to or greater
    than $8,000 per dealer location.” R. 99-1 at 3.
    JLL was aware of the assignments below. They were
    mentioned in CNH’s unsuccessful motion for summary
    No. 16-3800                                                     15
    judgment, R. 83 at 17–18, and they were the subject of a motion
    in limine filed by JLL prior to trial, R. 153. Yet JLL neither
    raised an objection to the assignments nor took any action
    consistent with the view that the dealers were the real parties
    in interest with respect to the assigned claims. It did not, for
    example, seek to join the dealers as necessary parties pursuant
    to Federal Rule of Civil Procedure 19(a), nor did it move to
    dismiss the case pursuant to Rule 19(b) on the ground that the
    dealers were indispensable parties to the litigation.
    On appeal, however, JLL argues for the first time that the
    dealer assignments to CNH amount to a collusive effort to
    confer federal jurisdiction over the dealers’ claims. Some 16 of
    the 260 dealers that assigned their claims to CNH are citizens
    either of Maryland or Illinois and would thus share the same
    citizenship with JLL. And no dealer has a claim that satisfies
    the $75,000 threshold. Consequently, the dealers would be
    unable to sue JLL in federal court in their own right. Yet, in
    JLL’s view, the dealers are the real parties in interest with
    respect to the claims they have assigned to CNH. The assign-
    ments, JLL argues, are in effect a sham, serving the sole
    purpose of putting dealer claims before the district court
    despite the fact that those claims fall outside the limited subject
    matter jurisdiction of the federal courts. See 28 U.S.C. § 1359
    (“A district court shall not have jurisdiction of a civil action in
    which any party, by assignment or otherwise, has been
    improperly or collusively made or joined to invoke the
    jurisdiction of the court.”); Kramer v. Caribbean Mills, Inc., 
    394 U.S. 823
    , 
    89 S. Ct. 1487
    (1969) (deeming assignment to be
    collusive for purposes of § 1359 when made to attorney-
    assignee for $1 and assignee agreed to pay assignor 95 percent
    16                                                    No. 16-3800
    of net recovery “solely as a [b]onus”); Steele v. Hartford Fire Ins.
    Co., 
    788 F.2d 441
    , 444 (7th Cir. 1986) (“if getting into federal
    court was the sole purpose of the assignment, then even if the
    assignment was supported by consideration and was lawful
    under state law, one could question in just what sense the
    assignment was bona fide, and, more to the point, could ask
    whether it is not the precise purpose of section 1359 to discour-
    age people from using the device of assignment to get access to
    the federal courts”).
    Courts have cited a variety of factors as bearing on the
    determination whether the assignment of a claim amounts to
    collusion for purposes of section 1359. Among the factors
    courts have considered are:
    1. Whether the assignee of the claim lacked a prior
    connection to the litigation;
    2. Whether the assignor of the claim selected the
    assignee’s legal counsel and/or paid for the
    assignee’s litigation expenses;
    3. Whether the assignor retained control of the
    litigation;
    4. Whether the assignee agreed to share with the
    assignor any portion of the recovery;
    5. Whether the assignee provided meaningful
    consideration for the assignment;
    6. Whether the timing of the assignment is suspi-
    cious; and
    No. 16-3800                                                         17
    7. Whether the assignment was motivated by a
    desire to create diversity jurisdiction.
    YP Recovery Inc. v. Yellowparts Europe, SL, 
    2016 WL 4549109
    , at
    * 6 (N.D. Ill. Sept. 1, 2016) (St. Eve., J.) (citing, inter alia, Nat’l
    Fitness Holdings, Inc. v. Grand View Corp. Ctr., LLC, 
    749 F.3d 1202
    , 1205–06 (10th Cir. 2014) (setting out these same seven
    factors as among those court should consider in evaluating
    totality of circumstances); Branson Label, Inc. v. City of Branson,
    Mo., 
    793 F.3d 910
    , 916–17 & n.5 (8th Cir. 2015) (agreeing these
    factors are “a helpful guide” without adopting Tenth Circuit’s
    test); and Boyd v. Phoenix Funding Corp., 
    366 F.3d 524
    , 531–32
    (7th Cir. 2004) (remanding case removed from state to federal
    court for determination whether assignment of loans to
    assignee who filed notice of removal was bona fide assignment
    or instead designed to evade time limit on removal)). JLL
    concedes these factors cut both ways in this case but nonethe-
    less asserts that, on balance, they point to collusion. CNH
    naturally disagrees, emphasizing the factors (including CNH’s
    pre-existing and independent interest in this litigation and in
    protecting its goodwill by aggregating like claims for disposi-
    tion in one suit) which weigh against a finding of collusion. But
    we find it unnecessary to proceed down this multi-factor
    analysis in order to reject JLL’s contention that the dealer
    assignments amounted to a collusive effort to manufacture
    federal jurisdiction.
    In material respects, this case is on all fours with Grede v.
    Bank of New York Mellon, 
    598 F.3d 899
    , 900–01 (7th Cir. 2010).
    There, the trustee of a liquidation trust holding the assets of a
    bankrupt investment management firm, Sentinel Management
    18                                                   No. 16-3800
    Group, sued the Bank of New York Mellon, seeking to recover
    payments to the Bank that the trustee characterized as prefer-
    ential payments or fraudulent conveyances. There was
    complete diversity of citizenship as between the trustee (a
    citizen of Illinois) and the Bank and its parent (citizens of New
    York and Delaware). The trust was not solely pursuing its own
    claims in the litigation, however. Some 100 of Sentinel’s
    investors had assigned their own claims against the Bank to the
    liquidation trust for collection as permitted by the terms of the
    trust, and the trustee was also pursuing those claims in the suit.
    A number of those 100 investors were citizens of New York,
    and as such would not have been able to invoke the court’s
    diversity jurisdiction had they sued the Bank themselves; yet,
    in the Bank’s view, they were the real parties in interest as to
    the assigned claims. The Bank argued that the assignments to
    the trust were thus a collusive means of ushering the investors’
    claims into federal court. Invoking section 1359, the Bank
    argued that the case should have been dismissed for lack of
    jurisdiction.
    We dispatched the Bank’s argument, emphasizing both that
    diversity jurisdiction was present over the trust’s own claims
    against the Bank and that bringing the assigned dealer claims
    into the suit was a matter of efficient aggregation of similar
    claims rather than collusion to create federal jurisdiction where
    none existed in the first 
    instance. 598 F.3d at 901
    . Because our
    analysis in Grede bears directly on the facts of this case, we
    quote it in full:
    A collusive assignment is a genuine jurisdictional
    problem. We treat an assignment as collusive when
    its sole function is to shift litigation from state to
    No. 16-3800                                                     19
    federal court. Steele v. Hartford Fire Insurance Co., 
    788 F.2d 441
    , 444 (7th Cir. 1986); Hartford Accident &
    Indemnity Co. v. Sullivan, 
    846 F.2d 377
    , 382 (7th Cir.
    1988).
    Assignment to a trust could be designed to take
    advantage of the rule that a trust’s citizenship is that
    of the trustee, rather than the beneficiaries, for the
    purpose of 18 U.S.C. § 1332(a). See Navarro Savings
    Association v. Lee, 
    446 U.S. 458
    , 
    100 S. Ct. 1779
    , 64 L.
    Ed. 2d 425 (1980). Cf. Northern Trust Co. v. Bunge
    Corp., 
    899 F.2d 591
    (7th Cir. 1990) (a non-trustee
    holder of injured parties’ claims has the same citi-
    zenship as the claims’ owners). But it would not be
    sensible to put the assignments to the Sentinel
    Liquidation Trust in the collusive category.
    The Bank is a citizen of New York; many investors
    are not, and many individual claims exceed $75,000,
    so these investors could sue under the diversity
    jurisdiction in their own names. Or one investor
    could sue on behalf of a class; only the plaintiff’s
    citizenship would count, much as only a trustee’s
    citizenship counts. See Snyder v. Harris, 
    394 U.S. 332
    ,
    340, 
    89 S. Ct. 1053
    , 
    22 L. Ed. 2d 319
    (1969). What’s
    more, the Trust already is suing the Bank in federal
    court in its capacity as holder of Sentinel’s claims to
    recover preferential or fraudulent transfers; the
    investors’ claims could be added under the supple-
    mental jurisdiction. See 28 U.S.C. § 1367; Exxon Mobil
    Corp. v. Allapattah Services, Inc., 
    545 U.S. 546
    ,
    20                                                   No. 16-3800
    
    125 S. Ct. 2611
    , 
    162 L. Ed. 2d 502
    (2005). The assign-
    ments thus do not move litigation from state to
    federal court; instead they facilitate efficient aggre-
    gation of claims, just as Fed. R. Civ. P. 23 does.
    Subject-matter jurisdiction is secure.
    
    Grede, 598 F.3d at 900
    –01.
    Obviously this case does not involve a trust, but in all other
    respects the relevant circumstances are nearly identical to those
    at issue in Grede. CNH has its own contractual claims against
    JLL. Those claims lie at the center of the suit and indubitably
    fall within the diversity jurisdiction of the court. Of the 260
    assigned dealer claims, the vast majority involve dealers who
    are not citizens of either Maryland or Illinois. True, no dealer
    claim meets the $75,000 threshold, but given the diversity of
    citizenship, the dealers would qualify as pendent parties
    entitled to invoke supplemental jurisdiction of the court.
    § 1367; Exxon 
    Mobil, 545 U.S. at 558
    –567, 125 S. Ct. at 2620–25.
    As in Grede, then, the assignments of those claims to CNH did
    not serve the function of moving the litigation from state to
    federal court: CNH’s claims independently met the require-
    ments of section 1332; and most of the dealers’ claims could
    have been pursued via supplemental jurisdiction. The assign-
    ments serve the function of efficient aggregation rather than
    collusion to evade the requirements of diversity.
    In sum, we are not convinced that the 260 dealer assign-
    ments amounted to a collusive effort to create federal jurisdic-
    No. 16-3800                                                         21
    tion where it otherwise would not have existed. The district
    court properly exercised jurisdiction over the assigned claims.3
    B. Limitation on liability
    JLL’s opening argument on the merits of the case rests on
    the limitation of liability provisions found in Section 26 of the
    Service Agreement. JLL reads Section 26 to preclude CNH
    from recovering anything from JLL even if, as the district court
    found, JLL breached its contractual obligations to CNH.
    Section 26 of the contract provides:
    Notwithstanding anything else contained herein to
    the contrary, each party shall look solely to the
    assets of the other party for satisfaction of any
    liability or obligations relating to this engagement …
    and in no event shall [JLL’s] liability to CNH and the
    CNH Dealers collectively … exceed (i) in the case of
    performance by the Additional Service Providers,
    the amounts which [JLL] can recover from the
    Additional Service Providers and their insurers, and
    (ii) in any other case, the greater of the project
    management fees paid to [JLL] hereunder or One
    Million Dollars except for [JLL]’s liability under
    Section 9A above.
    Ex. 1002 § 26. In JLL’s view, subsection (i) is the one and only
    provision of Section 26 applicable to CNH’s claims. JLL reasons
    3
    In view of our conclusion as to collusion, we need not address CNH’s
    alternative argument that the assigned dealer claims could be dismissed
    pursuant to Federal Rule of Civil Procedure 21 in order to preserve the
    judgment as to CNH.
    22                                                   No. 16-3800
    that the harm underlying CNH’s complaint stems from the
    defective vinyl used to manufacture the dealer signs, and
    CNH’s recovery is tied to the cost of replacing those failed
    signs. JLL, by contrast, was hired to provide management
    services, not to fabricate the signs; and although it signed the
    manufacturing contracts on CNH’s behalf, those contracts
    make clear that its liability was limited to its role as manager
    and that it was not a guarantor as to the quality of the signs
    themselves. Ex. 52 § 17.012. Thus, CNH’s recovery is, in JLL’s
    view, limited by subsection (i) to whatever JLL might be able
    to recover from Arlon, the vinyl manufacturer. But CNH is
    already suing Arlon in California state court; for that purpose,
    CNH took assignment of all the sign manufacturers’ rights,
    title and interest in their claims against Arlon. So there is, in
    JLL’s view, nothing that JLL can recover from Arlon—and
    CNH can in turn take from JLL pursuant to section 26(i)—that
    CNH is not already seeking from Arlon directly. And as
    subsections (i) and (ii) of section 26 are mutually exclusive, JLL
    reasons, CNH cannot simultaneously invoke both (i) and (ii).
    In any event, JLL believes that subsection (ii) does not logically
    apply, as Arlon is the source of CNH’s injury. JLL—in its own
    view—did not commit any independent wrong that injured
    CNH.
    The threshold problem with this argument is that it was not
    raised below. This is a civil rather than a criminal case, which
    means that we typically will not entertain an argument raised
    for the first time on appeal, even for the limited purpose of
    ascertaining whether a plain error occurred. E.g., Packer v.
    Trustees of Indiana Sch. of Medicine, 
    800 F.3d 843
    , 849 (7th Cir.
    2015). Compounding the problem for JLL is that JLL did not
    No. 16-3800                                                        23
    simply overlook section 26 below but instead made an argu-
    ment directly contrary to the one it is making on appeal: JLL
    argued to the district court that subsection (ii) rather than
    subsection (i) of section 26 should apply to any recovery by
    CNH. R. 180 at 33; R. 182 at 44–45. Arguably, then, JLL did not
    simply forfeit, but deliberately waived, the argument it is
    making now. See generally United States v. Olano, 
    507 U.S. 725
    ,
    733, 
    113 S. Ct. 1770
    , 1777 (1993) (distinguishing waiver from
    forfeiture).
    JLL nonetheless contends that we should entertain its
    appellate argument because the proper construction of a
    contract presents a question of law, and as such we have the
    discretion to address it notwithstanding JLL’s failure to make
    (or its choice not to make) the argument below. See Hively v. Ivy
    Tech Cmty. Coll. of Indiana, 
    853 F.3d 339
    , 351 (7th Cir 2017) (en
    banc) (citing Amcast Indus. Corp v. Detrex Corp., 
    2 F.3d 746
    , 750
    (7th Cir. 1993)); see generally Singleton v. Wulff, 
    428 U.S. 106
    , 121,
    
    96 S. Ct. 2868
    , 2877 (1976) (“The matter of what questions may
    be taken up and resolved for the first time on appeal is one left
    primarily to the courts of appeals, to be exercised on the facts
    of individual cases.”)
    But we are not convinced that we should exercise our
    discretion to entertain the argument. See Allen v. City of Chicago,
    
    865 F.3d 936
    , 944 (7th Cir. 2017) (noting discretion to take up
    issues raised for first time on appeal in civil cases is one we
    exercise “rarely”). Although the proper construction of the
    Service Agreement may present a legal issue, that issue is not
    on par with a statutory-construction question that has the
    potential to affect large numbers of people beyond the parties
    24                                                    No. 16-3800
    to this case. Few beyond JLL and CNH will be affected by our
    interpretation of their private contract. Moreover, the district
    court’s understanding of the contract, and its application of
    both subsections (i) and (ii) of section 26, was not obviously
    wrong. Yes, the defective vinyl that Arlon manufactured
    certainly lies at the heart of this case, but it is JLL’s own breach
    of its contractual obligations to CNH for which the latter is
    seeking recovery. CNH’s theory of the case is that the defective
    vinyl ultimately would not have been a problem had JLL
    properly overseen the manufacturing process, secured the best
    possible warranty on the vinyl, properly documented the
    warranty issued, and proactively managed enforcement of the
    warranty. In this respect, it appears logical for JLL to have
    invoked subsection (ii) and, accordingly, for the district court,
    upon finding that JLL had breached its contractual obligations
    to CNH, to have awarded CNH the fees it had paid to JLL.
    At the same time, it is not clear to us that subsection (i) has
    no concurrent role to play in fashioning a recovery for CNH.
    JLL has assumed that Arlon constitutes an “Additional Service
    Provider” to which subsection (i) applies; but we are inclined
    to agree that it is the sign manufacturers rather than Arlon that
    are properly deemed Additional Service Providers for pur-
    poses of this provision. And just as CNH has sued Arlon, JLL
    sued the sign manufacturers for their own (purported) contri-
    bution to the sign fiasco. That issue will be resolved in arbitra-
    tion. 
    See supra
    n.2. Assuming that JLL might eventually recover
    something from the sign manufacturers in the arbitration, we
    see no reason why JLL may not be obligated to forward the
    proceeds to CNH pursuant to subsection (ii).
    No. 16-3800                                                    25
    To be clear, we are not reaching the merits of JLL’s argu-
    ment as to the limitation of its liability. We are, rather, citing
    the plausibility of the district court’s construction of the
    contract as a reason not to overlook JLL’s about-face and
    exercise our discretion to entertain the argument it presents for
    the first time on appeal.
    C. Breach of contract
    JLL next contends that the evidence does not support the
    district court’s findings that it breached its agreement with
    CNH in multiple respects. Even if a breach was established as
    to one or more of its contractual duties, JLL argues, CNH did
    not establish that its damages were the natural and foreseeable
    result of such breach. We take JLL’s various obligations in turn.
    1. Failure to document warranty
    Pursuant to the Statement of Work setting forth the
    “deliverables” JLL agreed to provide, it was JLL’s obligation to
    supply “[r]esearch and documentation of warranty informa-
    tion for all raw materials and sub components” and to
    “disclose all elements of [the] Warranty program to CNH and
    Dealers.” Ex. 1002 Attach. B § 1(B) ¶4; § 2(C) ¶1. CNH’s claim
    in this regard is that JLL never properly ascertained and
    documented the terms of Arlon’s warranty on the vinyl, such
    that all parties understood from the start what those terms
    actually were. JLL, on the other hand, contends that the terms
    of Arlon’s warranty were clear from the moment Arlon first
    submitted presentation materials to the parties in its ultimately
    successful quest to supply vinyl to the sign manufacturers; that
    CNH approved the selection of all vendors, including Arlon,
    and the contracts with those vendors; and that the terms of the
    26                                                  No. 16-3800
    Arlon warranty were documented in a summary attached to
    each of the sign manufacturing contracts. The district court was
    not persuaded. Judge Stadtmueller found that JLL had essen-
    tially paid little attention to the warranty terms and demon-
    strated a “complete abdication of responsibility” in ascertain-
    ing and documenting those terms. He was convinced that had
    JLL complied with its obligation to research and document the
    warranty terms, the instant lawsuit would never have oc-
    curred. R. 178 at 14.
    The record supports the district court’s finding that JLL
    breached its duty to CNH in this regard. We may assume for
    the moment that Arlon’s presentation materials left little doubt
    as to the warranty terms it was offering. But it is noteworthy
    that the sole evidence regarding the final warranty terms to
    which Arlon (purportedly) agreed is the abbreviated summary
    attached to each of the sign manufacturing agreements. That
    summary is all that was attached to the manufacturing
    contracts; it is all that was produced to CNH; and it is all that
    was produced at trial. But apart from the fact that this was only
    a summary rather than a full statement of the warranty terms,
    it is unknown who even prepared that summary—JLL itself
    did not. JLL’s first project manager attributed the duty to
    maintain custody of the warranty to the sign manufacturers.
    But the Service Agreement places the obligation to document
    the warranty terms on JLL. It is inconceivable that JLL did not
    obtain formal documentation of the terms from Arlon itself; if
    JLL did so, it was never able to produce a copy. Indeed, JLL’s
    project manager was not even sure whether the summary itself
    was accurate. The failure to obtain a copy of the actual war-
    ranty gave rise to doubt as to what Arlon’s obligations were,
    No. 16-3800                                                               27
    and that uncertainty made it easier for Arlon to contend, as it
    ultimately did in 2014, that its responsibilities to replace the
    defective vinyl were at an end.
    One might reasonably conclude that JLL breached its
    obligations to document the Arlon warranty for a second time
    when, in 2011, Arlon promised to replace any and all failing
    signs at its cost. Evidently, there was no memorialization of
    that promise, upon which Arlon of course later reneged when
    the extent of the problem with the defective vinyl, and the
    corresponding costs to Arlon in replacing the signs, became
    fully apparent. That JLL did not insist upon Arlon document-
    ing its 2011 commitment in a contract that would have effec-
    tively broadened and extended its warranty and bound Arlon
    to its promise reflects a second lapse in judgment on its part.4
    By this time, JLL knew that there were serious deficiencies in
    Arlon’s vinyl production that would necessitate the replace-
    ment of a significant number of installed signs, at substantial
    cost. The need for certainty as to Arlon’s obligations could not
    have been clearer by that point in time.
    2. Failure to negotiate best possible warranty
    Closely related to JLL’s obligation to research and docu-
    ment the terms of Arlon’s warranty was the obligation to
    negotiate the most favorable warranty on CNH’s behalf. In the
    4
    When asked about the failure to demand that Arlon put its promise in
    writing by modifying the warranty terms, JLL’s project manager simply
    stated, “No. I got results. It occurred.” R. 180 at 108. He seemed to believe
    that the warranty was “a one-time event.” R. 180 at 110. But we can see no
    reason why JLL could not have insisted that Arlon modify its warranty by
    placing its full-replacement commitment in writing.
    28                                                   No. 16-3800
    Warranty Assurance section of the Statement of Work, JLL
    “guarantee[d] negotiation of the best possible Warranty
    program for [the] Family of Signs manufactured … .” Ex. 1002
    Attach B § 2(C) ¶1. There is no dispute that this guarantee
    extends to the warranty on the sign components, including the
    vinyl supplied by Arlon, as well as the warranty on the signs
    themselves. Indeed, CNH has argued that JLL breached this
    obligation with respect to both warranties. But as we think
    JLL’s omissions with respect to the Arlon warranty are
    sufficient to establish that it breached this duty, we confine our
    analysis to that warranty alone.
    In the Program Specifications Arlon submitted to JLL in
    support of its successful endeavor to be selected as the vinyl
    manufacturer for the new signs, Arlon compared the warran-
    ties on its products with those of a leading competitor to
    demonstrate that its warranties (seven years or longer in most
    instances, depending on where the signs were installed) were
    more generous. JLL concedes that it would have been possible
    to obtain a longer and better warranty from Arlon than the one
    it provided, but it casts doubt on the notion that CNH would
    have been willing to pay the additional cost that an upgrade to
    the warranty terms likely would have entailed. JLL emphasizes
    that CNH accepted a reduction in the length of the warranty
    from the sign manufacturers on the completed signs from three
    years to one in order to cut costs and make the sign replace-
    ment program more palatable to the dealers. How then, JLL
    asks, can it be faulted for not seeking a longer warranty on the
    vinyl components of the signs?
    The important point, to our mind, is that the record reflects
    no effort at all by JLL to negotiate more favorable warranty
    No. 16-3800                                                     29
    terms on CNH’s behalf, or even to ascertain what the possibili-
    ties were. JLL’s project manager believed that he discussed the
    warranty with Arlon’s representative to confirm that the terms
    were commensurate with those offered by other manufactur-
    ers, but he could not recall any specifics. To be fair, as Judge
    Stadtmueller pointed out, the record indicates that none of the
    parties gave much thought to the warranty terms. But the
    obligation to do so was JLL’s, and so far as the record reveals,
    it simply accepted the terms as Arlon offered them—and as set
    forth above, did nothing whatsoever to document them. The
    dispute between Arlon and the other parties about the extent
    of Arlon’s obligation illustrates the significance of JLL’s failure
    in this respect. Certainly it is possible that CNH would not
    have agreed to pay for a better warranty on the vinyl; the
    record supports the inference that CNH was interested in the
    opportunity to reduce costs wherever possible. The fact that
    CNH accepted a shorter warranty on the completed signs is
    consistent with that possibility. Then again, it is also possible
    that CNH, in view of the shorter, one-year warranty on the
    signs themselves—the risk of which was aired in “many
    discussions,” according to JLL (R. 180 162)—might have chosen
    to pay for a longer warranty on a critical component of the
    signs. This is particularly so given that Arlon was formulating
    custom-colored vinyl with no history in the field to establish its
    viability. In any case, the obligation to present that option to
    CNH lay with JLL, which did nothing to explore the possibility
    of a stronger warranty and determine whether CNH was
    interested in such a warranty. There was no clear error in
    Judge Stadtmueller’s finding that JLL breached its obligation
    to CNH in this respect.
    30                                                    No. 16-3800
    3. Failure to manage warranty program
    An additional pledge that JLL made as part of its Warranty
    Assurance commitment was “to provide ongoing Project
    Management services for Warranty with One-Year from [the]
    date of installation.” Ex. 1002 Attach. B § 2(C) ¶2. The wording
    of this pledge is a bit stilted, but we take it that JLL agreed to
    manage any and all warranty matters that presented them-
    selves with respect to individual signs for a period of one year
    following the installation of the sign. In CNH’s view, JLL’s
    commitment in this respect entailed the obligations to
    (a) ascertain the terms of the warranties on the signs, and
    (b) ensure that any warranty claims were timely submitted to
    the sign manufacturers and the vendors who supplied the
    components of the signs, including Arlon in particular. Again,
    our focus here is on JLL’s actions and omissions with respect to
    Arlon.
    The evidence certainly supports the district court’s finding
    that JLL breached its obligations in this regard. We have
    already discussed JLL’s omission to document the terms of
    Arlon’s warranty on the vinyl, which fostered uncertainty as
    to the extent of Arlon’s obligation to replace defective signs.
    The critical failure insofar as this claim is concerned is JLL’s
    failure to pursue a more proactive, global approach to war-
    ranty management once it became clear that the vinyl on
    significant numbers of installed signs was failing in the field. It
    is true, as JLL takes pains to emphasize, that as the problem
    emerged, Arlon promised to replace any defective signs at its
    cost. JLL took Arlon at its word, and to an extent, that is
    understandable: Arlon had a reputational interest in fixing its
    mistakes and ensuring that a large customer like CNH was
    No. 16-3800                                                    31
    satisfied with the final product. But it is also reasonable to
    expect that JLL, a sophisticated party with extensive experience
    and expertise in the logistics of large-scale projects like CNH’s
    re-branding program, would anticipate and plan for the worst-
    case scenario. JLL understood that the manufacturers’ war-
    ranty on the signs themselves did not extend beyond one year,
    and that although Arlon’s warranty on the vinyl itself ex-
    tended beyond that period, its obligations as to related
    replacement costs (including labor) likewise dropped off after
    the one-year mark. Once it was clear that the issue with the
    vinyl was not isolated, it was JLL’s obligation to take all
    reasonable steps to ascertain the scope of the problem and to
    ensure that all failures were detected and remediated in a
    timely manner, so that its client would obtain the full benefit of
    the relevant warranties.
    The evidence supports the district court’s finding that JLL
    did not do this. There is, to be sure, a dispute in the testimony
    as to whether JLL suggested some form of audit of the installed
    signs and was turned down by CNH or whether it was the
    other way around. As the factfinder, the district judge was free
    to credit CNH’s testimony on this point. And having done so,
    Judge Stadtmueller plausibly concluded that JLL’s passive
    acceptance of Arlon’s assurances breached its obligation to
    manage the warranties on CNH’s behalf, with the result that
    CNH was left to deal on its own with a large number of
    defective signs when Arlon announced that its warranty
    obligations were at an end and it would no longer take
    responsibility for replacing any signs at its cost.
    32                                                  No. 16-3800
    4. Failure to exercise quality control
    Finally, in the Statement of Work, JLL agreed to assume
    “[d]irect control and responsibility of all manufacturing
    including quality control meeting all Provider and CNH
    expectations.” Ex. 1002 Attach. B § 1(C) ¶1. The district court
    found that the quality-control obligation extended to Arlon’s
    production of the vinyl, and we agree that this is a reasonable
    interpretation of the provision. As JLL points out, the agree-
    ment also gave it the power to delegate its duties, including
    this one, to the sign manufacturers. Ex. 1002 § 1(B). Even so, to
    the extent CNH was harmed by the failure to ensure that
    Arlon’s product was produced according to specifica-
    tions—which plainly it was—JLL may be faulted for not
    ensuring that the sign manufacturers themselves took appro-
    priate steps to identify and correct any failings in Arlon’s
    manufacturing process.
    Arlon, of course, bears the blame for its deliberate conceal-
    ment of the discovery in 2012 that all of the blue vinyl it had
    theretofore been producing for the signs was defective. But
    JLL’s contractual obligation to exercise control over the
    manufacturing process, including quality control, entailed an
    independent obligation to anticipate and rectify such problems.
    When sign after sign was reported to JLL as being defective,
    JLL arguably was obliged to look beyond what Arlon was
    telling it about the vinyl and to take steps to independently
    evaluate the nature of the problem.
    This JLL never did. As the district court pointed out, there
    were options available to JLL: it could have arranged for
    independent sampling and testing of the vinyl, and rather than
    No. 16-3800                                                                 33
    waiting to see how the completed and installed signs fared in
    the field over time it could have subjected vinyl samples to
    testing in a weatherometer. There is no real dispute that such
    steps would have made it possible to confirm that the vinyl
    Arlon was producing was defective. Indeed, according to
    Arlon’s internal emails, weatherometer testing is what led it to
    conclude in 2012 that all formulations of the blue vinyl used on
    the CNH signs to date were defective. Given these facts, no
    expert testimony was necessary to demonstrate what JLL could
    have done to expose the defective vinyl and why, given
    industry best practices, it should have done so. Particularly
    given the pattern of sign failures and the number of signs
    involved, JLL was on notice of the need to investigate the
    source and extent of the problem. The steps necessary to make
    those determinations might have been costly, but once it
    became clear that the failures were not an isolated problem,
    JLL became obligated to do something other than rely on
    Arlon’s assurances. If nothing else, it could have demanded to
    see Arlon’s own testing data, which would have involved no
    cost at all.5 Judge Stadtmueller found it “inconceivable” that
    JLL did not pursue any such avenues and simply accepted
    Arlon’s assurances. R. 178 at 15. There was no clear error in his
    finding.
    5
    JLL’s project manager testified that he did ask for Arlon’s testing data
    when the first failure occurred but conceded that he never got it, choosing
    instead to accept Arlon’s representation that it had identified and fixed the
    problem with the vinyl. “I wanted a full explanation. I did not get that. I did
    not get testing information. I had got resolution that it was solved.” R. 180
    at 90.
    34                                                   No. 16-3800
    D. Damages for breach
    The district court found that CNH had incurred a loss of
    $5,482,735 as a result of JLL’s contractual breaches, relying on
    the testimony of CNH’s expert as to the costs entailed in
    replacing the defective signs. JLL contends that the district
    court’s damages calculation is flawed in two respects.
    JLL’s initial contention is that the loss calculation signifi-
    cantly exceeds CNH’s actual sign-replacement costs, pointing
    out that not all installed signs failed, some signs were already
    replaced by Arlon, and some signs were self-installed by
    dealers, who agreed to a voiding of the warranties on the signs
    in exchange for the reduced costs of installing the signs
    themselves. But JLL stipulated below that a specified number
    of sign faces and other parts had failed, that CNH had con-
    tracted with another firm to replace the failed signs, and that
    CNH would incur specified costs to replace the defective signs.
    R. 174 ¶¶ 1–9. CNH’s expert relied on those stipulations in
    calculating his loss figure, not on any assumptions about what
    broader category of signs might fail in the future. R. 181 at 67.
    If JLL believed that these stipulated numbers were over-
    inclusive or inaccurate in some respect, it is not clear why it
    agreed to them. Indeed, JLL does not respond at all in its reply
    brief to CNH’s contention that JLL stipulated to the basis for its
    loss calculation. We need not explore this point further.
    CNH’s broader point is that the loss calculation essentially
    holds JLL to account for Arlon’s failures. In JLL’s view, the
    court, by using the cost to replace failed signs as the measure
    of CNH’s damages, essentially held JLL liable for Arlon’s poor
    workmanship and breach of warranty on the signs.
    No. 16-3800                                                   35
    But the district court’s findings make clear that JLL’s own
    failures with respect to quality control in the manufacturing
    process and with respect to the warranty on the vinyl made the
    defective-sign problem much worse for CNH than it otherwise
    would have been. As we have discussed, the evidence supports
    the court’s findings that had JLL taken the initiative to test
    Arlon’s vinyl once problems began to surface, the flaws in
    Arlon’s manufacturing process would have been exposed
    much sooner than they were and the number of completed and
    installed defective signs would have been much smaller than
    it turned out to be. Likewise, had JLL properly documented
    and managed the Arlon warranty on the vinyl, it would have
    been more aggressive in identifying defective signs and filing
    timely warranty claims to ensure that CNH had maximum
    coverage as to the signs.
    Consequently, we can find no clear error in the district
    court’s loss assessment. The basis for JLL’s liability certainly
    was distinct from Arlon’s, but the measure of the loss to CNH
    is essentially the same: the cost to replace the defective signs,
    the pool of which JLL might have limited to a much smaller
    group had it not breached its contractual duties to CNH.
    E. Waiver of right to object to JLL’s performance
    1. Waiver by conduct and duty to speak
    JLL contends that to the extent its performance fell short of
    standards specified by contract, CNH waived any shortcoming
    by virtue of its own conduct in accepting JLL’s performance in
    silence rather than voicing an objection. As JLL sees things,
    36                                                            No. 16-3800
    nothing about Arlon’s warranty or the number of failing signs6
    was a secret—CNH was involved from the start with the
    selection of Arlon as a vendor and on through the entire
    warranty claims process on the defective signs—and yet CNH
    never indicated that it wanted a better warranty than the one
    Arlon proposed, that it wanted outside testing on Arlon’s
    product once the first problems with the vinyl were noticed, or
    that it wanted JLL to handle the replacement of defective signs
    differently. Having sat back in silence for years while the
    problems with Arlon’s vinyl unfolded and JLL endeavored to
    address them, CNH cannot now claim that JLL should have
    negotiated a better warranty on the vinyl, taken the initiative
    to have outside testing done on the vinyl, and been more
    aggressive in making sure that faulty signs were identified,
    presented to Arlon, and replaced within the warranty period.
    JLL bears a significant burden on this line of argument, and
    the district court by no means clearly erred in rejecting it.
    Waiver entails the voluntary and intentional relinquishment of
    known right. See United States v. 
    Olano, supra
    , 507 U.S. at 
    733, 113 S. Ct. at 1777
    . So to establish waiver, JLL was required to
    show that CNH realized JLL’s performance did not satisfy its
    contractual obligations and chose nonetheless to accept JLL’s
    performance as it was.
    On the matters of quality control and warranty manage-
    ment, JLL stresses that CNH had the power, as it did with
    other aspects of the sign project, to approve and disapprove of
    6
    Arlon, of course, did conceal the scope of the problem with its vinyl, but
    it kept both JLL and CNH in the dark in this regard.
    No. 16-3800                                                   37
    particular proposals, and that although it regularly exercised
    that authority, it was silent with respect to JLL’s handling of
    the problems with the early runs of Arlon’s vinyl. But this
    assumes that CNH had a duty to speak up if it was concerned
    about something JLL was doing, at pain of waiving its contrac-
    tual rights if it did not.
    CNH did not have a duty to speak up. JLL concedes it “ran
    the program at the granular level.” JLL Brief at 41. Under the
    express terms of the contract, it was JLL’s obligation to monitor
    the manufacturing process and to deal with problems that
    emerged as it saw fit. JLL is effectively trying to transfer that
    duty to CNH by asserting that it was CNH’s duty to affirma-
    tively ask JLL to more aggressively manage the production
    process if that is what CNH expected and wanted. This is
    turning the contract on its head. CNH no doubt had the
    authority to sign off upon or object to any particular proposals
    that JLL presented to it. But the responsibility to oversee and
    correct the manufacturing process, as necessary, was JLL’s in
    the first instance. Taking the facts as the district judge found
    them, nothing suggests either that CNH had some unique
    knowledge that might have triggered a duty to speak on its
    part or that CNH stood in the way of JLL taking a more
    proactive approach with respect to Arlon and its problematic
    vinyl.
    As for the warranty on the vinyl: Although CNH may have
    accepted the warranty as presented to it, CNH cannot be
    charged with knowing and accepting the fact that JLL had
    failed to even ascertain what warranty options were available,
    let alone negotiate the best possible warranty. Nor is there any
    evidence showing that CNH knew that the only documenta-
    38                                                   No. 16-3800
    tion of the warranty in JLL’s possession was nothing more than
    an incomplete summary prepared by an unknown third party.
    Finally, with respect to JLL’s warranty management
    responsibilities, it is a fair inference from the record that CNH
    accepted JLL’s assurances as to what the term of Arlon’s
    warranty were and as to Arlon’s commitment to replace the
    defective signs. And certainly CNH participated in the claims
    submission process. But there is no evidence that CNH realized
    the extent to which JLL’s chosen course of action with respect
    to enforcement of the warranty placed CNH at risk of being
    left with a substantial number of defective signs if and when
    Arlon ceased cooperating, as it ultimately did. At worst, CNH
    deferred to JLL in handling the warranty matters, but that was
    wholly consistent with the contract between CNH and JLL. JLL
    in turn chose to place its trust in Arlon, which in retrospect was
    a mistake.
    2. Acceptance of “deliverables”
    JLL makes a second waiver argument that is rooted in the
    notice-and-opportunity-to-cure provisions of its contract with
    CNH. The Statement of Work describing JLL’s responsibilities
    under the Agreement identified the particular services JLL was
    to provide—which constitute what the Agreement refers to as
    “deliverables”—along with a set of supporting requirements
    (“acceptance criteria”) for each such service. Section 1(D) of the
    Service Agreement sets forth the parties’ respective responsi-
    bilities with respect to these “deliverables”: (1) JLL would
    furnish a deliverable; (2) CNH in turn would evaluate the
    deliverable to decide whether it satisfied the acceptance criteria
    in material respects and, if not, inform JLL of the shortcomings
    No. 16-3800                                                   39
    (and the necessary corrections) in writing; (3) JLL would then
    make its best efforts to fix the problem and resubmit the
    deliverable to CNH; and (4) if JLL was unable to remedy the
    non-conforming aspect of the deliverable, CNH would have
    the right to terminate the agreement. Ex. 1002 § 1(D). JLL’s
    point is that not until 2014, when Arlon announced that it was
    no longer willing to stand by its commitment to replace the
    defective signs at its cost, did CNH ever signal to JLL that it
    was dissatisfied with any aspect of JLL’s performance. Several
    of the service obligations that CNH faults JLL for mis-handling
    in this litigation constitute (or overlap with) deliverables that
    are identified in the Statement of Work—including negotiating
    the warranty terms, researching and documenting the war-
    ranty information, exercising quality control, and overseeing
    post-installation problems with the signs. By not registering
    timely written objections to JLL’s work in these areas and
    giving JLL the opportunity to cure the shortcomings, JLL
    argues, CNH failed to comply with the contractual provisions
    for non-conforming deliverables and thereby waived the
    objections it has pursued in this litigation.
    We reject this contractual argument for the same reasons
    that we rejected JLL’s generic waiver argument. Apart from the
    awkward fit between JLL’s undefined “deliverables” terminol-
    ogy and services that were, in many instances, ongoing in
    nature, the argument either presumes awareness on CNH’s
    part of the shortcomings in JLL’s performance or demands that
    CNH have regularly cross-examined JLL as to what steps it
    had or had not taken or considered in delivering services to
    CNH. For example, it presumes that when JLL advised CNH
    what the warranty terms were on the Arlon vinyl, CNH should
    40                                                No. 16-3800
    have asked JLL what the range of possible warranties was,
    what efforts JLL made to negotiate the warranty terms with
    Arlon, what the costs associated with each warranty option
    were, and why JLL chose or accepted the warranty terms it
    was relaying to CNH. Only in that way could CNH evaluate
    how effective JLL had been in negotiating the warranty terms.
    Likewise with quality control. If JLL’s point is that CNH
    should have alerted it to any dissatisfaction CNH had with its
    handling of the early reports of problems with the Arlon vinyl,
    for example, then one must presume that CNH knew what
    measures JLL had or had not taken with Arlon to confirm that
    the problems with the vinyl had indeed been corrected. That in
    turn would require either that JLL have briefed CNH thor-
    oughly on these points (which the evidence does not show) or
    that CNH took the initiative to interrogate JLL: What did Arlon
    tell you was the source of the problem? How can you be
    confident that the problem has been corrected? What if any
    testing data did Arlon provide you? What other options did
    you consider to verify that the problem has been addressed?
    And so on.
    But, again, imposing on CNH the duty to look behind JLL’s
    recommendations and services is inconsistent with the role that
    JLL assumed in managing the sign project. CNH wanted a firm
    that could provide turnkey management and that is what JLL
    undertook to provide CNH. Unless JLL can show that CNH
    was contemporaneously aware of the sorts of shortcomings
    Judge Stadtmueller found in JLL’s performance, then CNH
    cannot be faulted for failing to cite these failures to JLL and
    giving it the chance to remediate them. The evidence does not
    show this. Not until May of 2014, when Arlon essentially
    No. 16-3800                                                      41
    abandoned its commitment to replace the defective signs at its
    own expense could CNH have begun to appreciate the
    ramifications of JLL’s failures to negotiate a robust warranty on
    the vinyl, to properly verify and document the warranty terms,
    and to exercise more proactive quality-control oversight over
    the manufacturing process. True, CNH elected not to fire JLL
    immediately when this occurred. But insofar as the contractual
    obligations underlying the judgment are concerned, the ship
    had long since sailed. JLL has not convinced us that there was
    any correction it could have made in 2014 that would have
    materially reduced the damages that CNH already had
    incurred. (Nor has it undertaken to show what portion of the
    judgment might be attributable to the period of time after May
    2014.) There was no contractual waiver.
    F. Admission of parties’ pre-contractual conduct
    Finally, in its opening brief, JLL has made a cursory
    argument that the district court erred by admitting certain
    evidence as to the parties’ course of conduct prior to entering
    into their contract. In view of the integration clause in the
    agreement, JLL argues, such evidence was inadmissible.
    But not until its reply brief did JLL make any effort to
    explain what pre-contract evidence in particular was enter-
    tained and how it may have factored into the district court’s
    merits decision, thus depriving CNH of the opportunity to
    respond to the argument in a meaningful way. This is too late
    in the day. E.g., Bitsin v. Holder, 
    719 F.3d 619
    , 630 n.23 (7th Cir.
    2013). JLL waived the argument.
    42                                               No. 16-3800
    III.
    For all of the reasons discussed in this opinion, the judg-
    ment in favor of CNH is AFFIRMED.