Horsfield Materials, Inc. v. City of Dyersville , 2013 Iowa Sup. LEXIS 83 ( 2013 )


Menu:
  •               IN THE SUPREME COURT OF IOWA
    No. 12–0491
    Filed July 5, 2013
    HORSFIELD MATERIALS, INC.,
    Appellant,
    vs.
    CITY OF DYERSVILLE,
    Appellee.
    Appeal from the Iowa District Court for Dubuque County,
    Andrea J. Dryer (trial) and Lawrence H. Fautsch (motion to compel
    discovery), Judges.
    A materials supplier appeals from the district court’s denial of
    declaratory and injunctive relief in an action against a municipality for
    alleged violations of Iowa’s public bidding and open records laws.
    DISTRICT COURT JUDGMENT AFFIRMED IN PART AND REVERSED
    IN PART, AND CASE REMANDED.
    Vernon P. Squires of Bradley & Riley, PC, Cedar Rapids, for
    appellant.
    Douglas M. Henry and P. Christopher Williams of Fuerste, Carew,
    Juergens & Sudmeier, P.C., Dubuque, for appellee.
    2
    MANSFIELD, Justice.
    In this case, we must decide whether an entity excluded from a
    city’s list of preapproved material suppliers on a public construction
    project can obtain a declaratory judgment that such a preapproval
    process violated Iowa’s public bidding statute and constitutional
    guarantees of equal protection and due process. Additionally, we must
    decide whether the same entity should have been granted relief under
    Iowa’s open records law based on the city’s delay in responding to an
    open records request.
    We conclude the supplier lacked standing to challenge the
    preapproval process under Iowa’s public bidding statute.      We find the
    supplier did have standing to assert its constitutional claims but reject
    those claims on the merits. Finally, we hold the city’s substantial and
    inadequately explained delay in responding to the supplier’s open records
    request violated the law.    For these reasons, we affirm the judgment
    entered by the district court dismissing the plaintiff’s public bidding and
    constitutional claims, but reverse in part the district court’s ruling that
    denied the plaintiff relief under the open records law.
    I. Facts and Procedural Background.
    Plaintiff Horsfield Materials, Inc. (Horsfield) is a construction
    supply business based in Epworth, about ten miles east of Dyersville.
    Horsfield produces and sells construction materials including aggregate
    (e.g., crushed stone, sand, and gravel) and ready-mix concrete. Horsfield
    supplies a variety of customers such as individuals, large concrete
    contractors, government bodies, and developers.
    Horsfield has a sister company, Horsfield Construction, Inc., that
    does business as a construction contractor.      Matthew Horsfield is the
    president of both firms.      In 2005, Horsfield Construction became
    3
    embroiled in litigation with Dyersville over a downtown pavement,
    sidewalk, and streetlight replacement project that Horsfield Construction
    had agreed to perform for the City.
    This litigation concerns the Wastewater Treatment Facility Phase II
    Improvements, which consisted of modifications and upgrades to
    Dyersville’s existing wastewater treatment facility. The estimated cost of
    the project was approximately $1.2 million.        The project was largely
    funded as an Iowa Green Initiative through the Iowa Revolving Loan
    Fund, but $300,000 of federal stimulus money was available. To qualify
    for these funds, the City had to issue a notice to proceed by mid-
    February 2010.
    Because the estimated cost of the project exceeded $100,000, the
    project fell under the requirements of Iowa’s public construction bidding
    statute. See Iowa Code §§ 26.1–.15 (2009). Chapter 26 imposes certain
    requirements     on   the   bidding   and   selection   process   for   public
    construction projects, including notice, public hearing, and selection of
    the “lowest responsive, responsible bidder.” Id. § 26.9.
    Gary Sejkora, a licensed professional engineer retained by the City,
    finalized the proposed plans and specifications for the wastewater project
    on December 3, 2009. These stated that a public hearing would be held
    on the plans and specifications on December 21, 2009, and that the
    deadline for submitting bids on the project would be January 7, 2010.
    Two special conditions in the specifications limited the aggregate
    and concrete suppliers that could be used on the project to three named
    companies. The relevant language stated as follows:
    27. AGGREGATE SUPPLIERS: Bard Concrete, River City
    Stone, and Kuhlman Quarries are approved aggregate
    suppliers subject to compliance with material specifications.
    4
    Other aggregate suppliers must obtain approval from the
    City and Engineer prior to bidding.
    28. CONCRETE        SUPPLIERS:     Bard   Concrete,     Apex
    Concrete, and Flynn Ready-Mix are approved concrete
    suppliers subject to compliance with material specifications.
    Other concrete suppliers must obtain approval from the City
    and Engineer prior to bidding.
    This was not the first time Horsfield had been excluded from a list
    of preapproved suppliers. Another city project in the summer of 2009
    had similarly limited suppliers to specific companies other than
    Horsfield. Horsfield suspected that it was being “blackball[ed]” because
    of its sister company’s involvement in litigation with the City.
    Under the public hearing requirement, a city may not enter into a
    contract for a public improvement project “until the governmental entity
    has held a public hearing and has approved the proposed plans,
    specifications, and form of contract, and estimated total cost of the
    public improvement.” Id. § 26.12.
    On the day of the December 21 hearing, Horsfield’s attorney faxed
    a letter to Sejkora and to the city clerk, asking for an explanation as to
    why other suppliers, and not Horsfield, had been preapproved. Horsfield
    also asked what steps it could take to become an approved supplier for
    the wastewater project. Additionally, the letter contained Horsfield’s first
    open records request to Dyersville. Horsfield requested
    all records that relate to, reference, or concern in any way
    the procedures, guidelines, publications, standards,
    processes, and notifications used in: 1) determining the
    “approved” suppliers in paragraphs 27 and 28 of the
    contract specifications; 2) determining that Horsfield
    Materials, Inc. was not an “approved” supplier, and
    3) determining “approved” and “not approved” suppliers or
    contractors generally by the City of Dyersville, or its agents,
    on this and other publicly bid projects. The request includes
    a list of all suppliers and contractors currently “approved”
    and “not approved” by the City of Dyersville. This request
    also includes, without limitation, all communications with
    any supplier or contractor concerning the approval process
    5
    and designation as an “approved” supplier. It also includes,
    without limitation, all records containing any reference or
    mention of Horsfield Materials, Inc., Horsfield Construction,
    Inc., or their agents, to the extent the records relate in any
    way to approval or exclusion as a supplier or contractor for
    this or any other project for the City of Dyersville.
    Matthew Horsfield spoke at the hearing that evening, requesting
    that his company be named an additional preapproved supplier. The city
    council did not grant his request and instead, approved the plans and
    specifications with the existing versions of paragraphs 27 and 28.
    The following day, December 22, Horsfield’s attorney faxed another
    letter to the City, renewing the company’s request to become a
    preapproved supplier of aggregate and concrete. Horsfield also clarified
    that its records request included electronic information and documents
    in possession of any city employee, any city council member, or the
    mayor.
    On December 30, Matthew Horsfield emailed Sejkora, again asking
    to become a preapproved supplier for the wastewater project.           Sejkora
    declined to preapprove Horsfield because “[w]e do not have any
    experience working with Horsfield Materials on projects comparable to
    the Dyersville Wastewater Treatment Facility Phase II project. Therefore,
    we require documentation prior to considering approval.” Sejkora then
    referred Horsfield to an addendum issued that day that contained a new
    Special Condition 29.      This condition allowed a general contractor to
    request approval of an alternative supplier for aggregate or concrete
    within thirty days after being awarded the contract.
    Under Special Condition 29, the request for approval was required
    to be in writing and to include details about the proposed supplier’s
    business such as contact information, history of the business and
    production   facilities,   and   resumes   of   “key   individuals   involved.”
    6
    Additionally, a number of quality test results from the Iowa Department
    of Transportation (DOT) were required, as well as a minimum of three
    references from engineers, contractors, and owners that had used the
    supplier’s products before.
    Preapproved suppliers of course did not need to provide this
    information, but Sejkora later testified that these requirements reflected
    the underlying criteria for preapproval.      Yet Sejkora could not recall
    when any of the preapproved suppliers had last submitted the aggregate
    or   concrete   quality   control   reports   that   Special   Condition   29
    contemplated.
    Horsfield’s aggregate and concrete have never been deemed
    unacceptable by the DOT, which certifies aggregate and concrete
    sources.   Horsfield also maintained that the City’s offer in Special
    Condition 29 to approve a new supplier after the contract award was not
    a realistic option.   A general contractor would be very reluctant to
    antagonize the supplier whose bid it had used to gain the contract by
    later trying to substitute a new supplier.
    That same day, December 30, Horsfield submitted an additional
    open records request to Dyersville, seeking “all documents and records
    relating in any way to Addendum No. 2 to the Contract and/or any other
    documents and records relating to an alternative suppliers approval
    process.” The following day, the City provided Horsfield with thirty-nine
    pages of records in response to the outstanding requests.
    Horsfield’s attorney openly questioned whether the thirty-nine
    pages amounted to all the responsive documents. On January 7, 2010,
    the day bidding closed on the wastewater project, Horsfield again
    clarified the scope of its requests, pointing out that they included
    documents in the possession of Sejkora, even though he was not an
    7
    employee of the city.     Horsfield took the position that Sejkora, as
    engineer on this project, was the City’s agent.
    On January 11, 2010, the city council awarded the project to
    Portzen   Construction,   having   concluded      that   it   was   the   lowest
    responsible, responsive bidder.       Portzen’s bid totaled $1,323,537,
    approximately nine percent above the engineer’s estimate.             Horsfield
    never submitted information under Special Condition 29, and Horsfield
    Construction never bid on the wastewater project.
    That same day, Horsfield submitted its final open records request
    relevant to this case. This request sought:
    1. All records that concern, reference, or relate in any
    way to the proposed wastewater treatment facility
    improvements referenced above.
    2. All records that concern, reference or relate in any
    way to Matt Horsfield, Horsfield Construction, Inc., or
    Horsfield Materials, Inc.
    One day after receiving this request, Dyersville’s attorney responded that
    because of Horsfield Construction’s prior legal dispute with the City, the
    volume of responsive documents would be very large. He suggested that
    Horsfield narrow its requests to exclude documents produced in the
    litigation or created over twelve months ago. By email dated January 21,
    2010, Horsfield’s attorney agreed to these two limitations. On January
    25, Dyersville’s attorney wrote to Horsfield’s attorney, explaining the
    reimbursement that the City would expect for its costs associated with
    retrieving the records and stating that the City would begin working on
    Horsfield’s request.
    On January 26, Dyersville’s attorney sent Horsfield’s attorney a
    privilege log for five emails relating to Special Condition 29 that the City
    considered protected by the attorney–client privilege.        On February 7,
    8
    having not received any documents in response to its January 11 request
    (as modified on January 21), Horsfield’s attorney emailed Dyersville’s
    attorney requesting a status update.        A few days later, the city
    administrator Mick Michel sent an internal email to the City’s attorney,
    indicating that progress was slow on the document production. One of
    the problems was that the potentially responsive “documents” included
    forty-two hours of video of city council meetings and other public
    hearings, which the City believed needed to be screened to determine
    whether they were responsive to the request.
    On March 18, 2010, Horsfield brought the present lawsuit in two
    counts. The first count sought relief under the Open Records Act; the
    second count asserted a claim that the City’s practice of preapproving
    suppliers violated Iowa’s public bidding statute, as well as federal and
    state due process and equal protection guarantees.
    Meanwhile, the parties’ dealings on the January 11 open records
    request continued. On March 25, Dyersville’s attorney wrote Horsfield’s
    attorney, updating him on the status of the open records request. He
    informed Horsfield’s attorney that forty-two hours of video of city council
    meetings and other public hearings still needed to be reviewed and
    sought Horsfield’s input.    The City’s counsel indicated that Horsfield
    could provide a hard drive onto which the City would copy the entire
    forty-two hours for Horsfield’s review.
    On April 5, the attorneys for Horsfield and the City exchanged
    emails about records other than the video recordings.       The next day,
    April 6, Dyersville produced 617 pages of documents in response to the
    January 11 request.      Two days later, the City’s attorney provided a
    privilege log for eight emails the City had withheld. He also indicated
    that he was still awaiting instructions concerning the video.
    9
    On June 2, Horsfield filed a motion to compel discovery.
    Horsfield’s principal argument was that the City had wrongfully withheld
    emails exchanged between Sejkora (who was not a city employee) and the
    City’s attorney.   The district court denied the motion, citing Tausz v.
    Clarion-Goldfield Community School District, 
    569 N.W.2d 125
    , 127 (Iowa
    1997). However, the City subsequently elected to produce the emails and
    used them at trial.
    During the two-day trial to the court that took place on July 28–
    29, 2011, Matt Horsfield testified that Horsfield Materials has sources for
    materials in Dubuque County, has supplied most of the major concrete
    contractors in the area, has supplied the county and the Iowa DOT, and
    wanted to supply materials for Dyersville jobs. He also testified that in
    two additional public works projects in 2011, Dyersville has continued to
    use a list of preapproved suppliers that excludes Horsfield.
    Following trial, the district court entered findings of fact and
    conclusions of law that rejected each of Horsfield’s claims. Concerning
    Horsfield’s challenge to the City’s preapproval process, the court found
    that Horsfield lacked standing:
    If an unsuccessful bidder on a public construction
    contract lacks standing to challenge the legality of bidding
    procedures, then an aggregate and concrete supplier
    desirous of selling its products to a bidder, and perhaps
    ultimately to the governmental entity if the bid is successful,
    also lacks standing to challenge a portion of the bidding
    procedures.
    Regarding Horsfield’s open records claim, the district court concluded no
    violation had occurred:
    Under the circumstances, the delay in making the city’s
    records that were responsive to the January request
    available did not amount to a refusal to make the records
    available. The city made good faith efforts to comply, and
    did substantially comply, with Chapter 22 requirements.
    10
    Horsfield filed a motion to enlarge under Iowa Rule of Civil
    Procedure 1.904(2), requesting the district court to separately address
    and analyze its constitutional claims.     It argued that Horsfield had
    standing to bring its constitutional claims regardless of any lack of
    standing under the public bidding statute. The district court denied the
    motion. Horsfield now appeals.
    II. Standard of Review.
    Horsfield filed the present petition in equity seeking injunctive and
    declaratory relief. In their briefing, the parties agree that the scope of
    review is de novo. However, “[t]he fact the action was filed on the equity
    docket does not control our review.”     City of Riverdale v. Diercks, 
    806 N.W.2d 643
    , 651 (Iowa 2011). Rather, the manner in which the district
    court actually tried the action determines our standard of review. Id. at
    651–52. Here, the district court ruled on evidentiary objections, but any
    rulings excluding evidence were “minor and did not have a significant
    effect on the proceedings.” Passehl Estate v. Passehl, 
    712 N.W.2d 408
    ,
    414 (Iowa 2006).       Accordingly, we will apply a de novo standard of
    review.   This means that the district court’s findings of fact are not
    binding, but we will “give deference to those findings because the district
    court had the opportunity to assess the credibility of the witnesses.”
    Hensler v. City of Davenport, 
    790 N.W.2d 569
    , 578 (Iowa 2010).
    III. Analysis.
    A. Standing Under Iowa Code Section 26.9.          Horsfield alleges
    that Dyersville’s ongoing use of preapproved suppliers for public
    contracts violates Iowa’s public bidding statute.   Specifically, Horsfield
    contends that the practice violates Iowa Code section 26.9, which
    provides, “The contract for the public improvement must be awarded to
    the lowest responsive, responsible bidder.”       In Horsfield’s view, by
    11
    limiting the universe of potential aggregate and concrete suppliers, the
    City undermines the legal requirement in section 26.9 that it get the best
    deal for its taxpayers. See, e.g., Philip L. Bruner & Patrick J. O’Connor,
    Jr., 1 Bruner & O’Connor on Construction Law § 2:45 (2012) (“Limitation
    of competition through the use of unjustifiably restrictive product
    specifications violates the objectives of competitive sealed bidding.”); see
    also Kratz v. City of Allentown, 
    155 A. 116
    , 117 (Pa. 1931) (“The city had
    the right to call for stone of a particular quality and fitness, but not from
    a particular quarry.     To do the latter might create a monopoly and
    prevent competitive bidding.”). The initial question we must answer is
    whether Horsfield has standing to raise this claim.
    Our self-imposed standing inquiry has two distinct prongs, each of
    which a plaintiff must satisfy to proceed with a claim. “Our cases have
    determined that a complaining party must (1) have a specific personal or
    legal interest in the litigation and (2) be injuriously affected.” Citizens for
    Responsible Choices v. City of Shenandoah, 
    686 N.W.2d 470
    , 475 (Iowa
    2004); see also Alons v. Iowa Dist. Ct., 
    698 N.W.2d 858
    , 869 (Iowa 2005).
    This inquiry is separate from, and precedes, the merits of a case. See
    Alons, 698 N.W.2d at 864 (“Even if the claim could be meritorious, the
    court will not hear the claim if the party bringing it lacks standing.”).
    We have previously considered our standing doctrine as it applies
    to unsuccessful bidders on public construction projects.             We have
    consistently held that our public bidding statute seeks “ ‘to secure by
    competition among bidders, the best results at the lowest price, and to
    forestall fraud, favoritism and corruption in the making of contracts.’
    Such statutes were enacted for the benefit of the taxpayers, not the
    bidders.” Elview Constr. Co. v. N. Scott Cmty. Sch. Dist., 
    373 N.W.2d 138
    ,
    141 (Iowa 1985) (quoting Istari Constr., Inc. v. City of Muscatine, 330
    
    12 N.W.2d 798
    , 800 (Iowa 1983)) (holding that an unsuccessful bidder does
    not have standing in an equity action to void public project contracts).
    As a result, we have denied standing to unsuccessful bidders that
    seek to void a municipality’s contract with a successful bidder or seek
    damages for lost profits. See Garling Constr., Inc. v. City of Shellsburg,
    
    641 N.W.2d 522
    , 524 (Iowa 2002). In Garling, a general contractor was
    unsuccessful in bidding on a municipal building project even though it
    made the lowest bid and the city made no finding that it was not
    responsible.   Id. at 522–23.     The evidence suggested that the city
    preferred another, costlier, bidder because it was local. Id. at 523. The
    unsuccessful bidder petitioned for writ of certiorari, demanding damages.
    Id. Despite an apparent violation of the public bidding statue, we held
    that the unsuccessful bidder lacked standing to collect damages. Id. at
    524–25. We reasoned that it
    “would be contrary to the public interest the bidding laws
    were designed to protect, since it would twice penalize
    taxpayers by compelling them to pay not only the excess over
    what they would have paid if the contract were properly
    awarded, but also the amount of profit lost by the contractor
    whose bid was wrongfully rejected.”
    Id. (quoting James L. Isham, Annotation, Public Contracts: Low Bidder’s
    Monetary Relief Against State or Local Agency for Nonaward of Contract,
    
    65 A.L.R. 4th 93
    , 111 (1988) [hereinafter Isham]).        “The paramount
    purpose of the competitive bidding statute is to protect the public as
    taxpayers, and that purpose must not be impaired in interpreting the
    statute.” Master Builders of Iowa, Inc. v. Polk County, 
    653 N.W.2d 382
    ,
    394 (Iowa 2002) (holding that Iowa’s competitive bidding statute does not
    bar project labor agreements, whereby bidders agree on collective
    bargaining terms before bidding, and only parties to the agreement will
    be chosen for the contract).
    13
    In both Garling and Elview, we used “standing” terminology to
    explain our decisions.          641 N.W.2d at 523–24; 373 N.W.2d at 141.
    Related to standing, but generally distinguished from it, is the question
    whether the plaintiff has a “cause of action” under the statute in
    question. Bond v. United States, __ U.S. __, __, 
    131 S. Ct. 2355
    , 2362–
    63, 
    180 L. Ed. 2d 269
    , 277–78 (2011) (discussing the distinction between
    the two concepts). Arguably, we could have said in Elview and Garling
    that the unsuccessful bidder did not have a cause of action, because the
    issue was not whether it had allegedly suffered a cognizable injury, but
    whether it could bring the claim in question over that alleged injury. But
    having gone down the standing path in these two prior cases, we will
    remain there for the present case.
    We have, however, left open the possibility that unsuccessful
    bidders may have standing in actions for injunction, mandamus, or
    declaratory judgment.           Garling, 641 N.W.2d at 524–25.                “Denial of
    standing to an unsuccessful bidder does not mean violation of a bidding
    statute will necessarily go unchallenged.                     An injunction action,
    mandamus, or declaratory judgment might still be available.” Id. at 524.
    In fact, many other states have conferred standing on an unsuccessful
    bidder in these circumstances.1
    1See, e.g., Ala. Mun. & Envtl. Eng’rs, Inc. v. Slaughter Constr. Co., 
    961 So. 2d 889
    ,
    894 (Ala. Civ. App. 2007) (declining to allow unsuccessful bidder to seek monetary
    damages from violation of competitive bidding statute and noting that remedy is limited
    to injunction as provided for in the statute); City of Phoenix v. Wittman Contracting Co.,
    
    509 P.2d 1038
    , 1040 (Ariz. Ct. App. 1973) (“[A]n unsuccessful bidder, arbitrarily and
    capriciously refused award of a public contract, is a ‘party beneficially interested’ with
    sufficient standing to seek mandamus relief.”); Walt Bennett Ford, Inc. v. Pulaski Cnty.
    Special Sch. Dist., 
    624 S.W.2d 426
    , 428 (Ark. 1981) (holding that an unsuccessful
    bidder which alleged it was the lowest qualified bidder had standing to sue to void an
    allegedly improper public project contract); Kajima/Ray Wilson v. L.A. Cnty. Metro.
    Transp. Auth., 
    1 P.3d 63
    , 68 (Cal. 2000) (“California courts long ago authorized a
    disappointed bidder to seek a writ of mandate to have a contract set aside.”); Lawrence
    Brunoli, Inc. v. Town of Branford, 
    722 A.2d 271
    , 273–74 (Conn. 1999) (“Providing
    unsuccessful bidders with an equitable remedy alone is consistent with the policies that
    14
    ______________________
    we previously have identified as underlying the municipal bidding statutes.”); Mid-Am.
    Waste Sys. of Fla., Inc. v. City of Jacksonville, 
    596 So. 2d 1187
    , 1188–89 (Fla. Dist. Ct.
    App. 1992) (holding that second most responsible bidder has standing to seek
    injunctive and declaratory relief against awarding contract to sister corporation of waste
    hauler that had been convicted of price fixing); Hilton Constr. Co. v. Rockdale Cnty. Bd.
    of Ed., 
    266 S.E.2d 157
    , 161 (Ga. 1980) (allowing low bidder to seek mandamus and
    injunctive relief for alleged violation of public bidding law); Arakaki v. States, 
    952 P.2d 1210
    , 1214 (Haw. 1998) (noting that unsuccessful bidder may seek to have an agency
    order a “remand and reconsideration” by government body awarding contract); Scott v.
    Buhl Joint Sch. Dist. No. 412, 
    852 P.2d 1376
    , 1382–83 (Idaho 1993) (holding
    disappointed bidders had standing to bring suit seeking declaratory judgment,
    mandamus, and injunction); Ct. St. Steak House, Inc. v. County of Tazewell, 
    643 N.E.2d 781
    , 784 (Ill. 1994) (reaching the merits of a mandamus action challenging a county’s
    exercise of discretion under a public bidding statute); Shook Heavy & Envtl. Constr. Grp.
    v. City of Kokomo, 
    632 N.E.2d 355
    , 358 & n.7 (Ind. 1994) (noting that unsuccessful
    bidders may challenge contract award if it alleges fraud or collusion); Sutter Bros.
    Constr. Co. v. City of Leavenworth, 
    708 P.2d 190
    , 196 (Kan. 1985) (“An unsuccessful
    bidder’s remedy is to seek injunctive relief preventing the award of the contract to one
    not legally entitled thereto.”); Pendleton Bros. Vending, Inc. v. Commonwealth Fin. &
    Admin. Cabinet, 
    758 S.W.2d 24
    , 28 (Ky. 1988) (noting that procurement statute confers
    standing to unsuccessful bidders to challenge award of contract in violation of the
    statute); Airline Constr. Co. v. Ascension Parish Sch. Bd., 
    568 So. 2d 1029
    , 1032 (La.
    1990) (noting that under Louisiana’s public bidding statute, which requires awarding
    contracts to the lowest responsible bidder, “an unsuccessful bidder may sue to enjoin
    the public body from executing the contract or to set aside the award of the contract to
    another bidder when the public body acted arbitrarily in selecting the successful
    bidder”); Associated Subcontractors of Mass., Inc. v. Univ. of Mass. Bldg. Auth., 
    810 N.E.2d 1214
    , 1218 (Mass. 2004) (holding that “subcontractors[] have standing to bring
    this suit” because, among other things, “the claim is one for declaratory judgment”);
    Groves v. Dep’t of Corr., 
    811 N.W.2d 563
    , 568 (Mich. Ct. App. 2011) (noting that, when
    unsuccessful bidder alleges fraud, abuse, or illegality, it may seek injunctive relief
    against municipality for competitive bidding violations); Tel. Assocs., Inc. v. St. Louis
    Cnty. Bd., 
    364 N.W.2d 378
    , 382 (Minn. 1985) (“While it is true that an unsuccessful
    bidder has standing to maintain a proceeding to review the award of a contract in
    violation of [competitive bidding law], this procedure is sanctioned merely to ensure
    enforcement of the statute.”) (citation and internal quotation marks omitted); Gulf Oil
    Corp. v. Clark County, 
    575 P.2d 1332
    , 1333–34 (Nev. 1978) (“A timely challenge is
    compatible with the public interest since it serves to force compliance with the purpose
    of the bidding procedure.”); Jerkens Truck & Equip., Inc. v. City of Yonkers, 
    579 N.Y.S.2d 417
    , 422 (App. Div. 1992) (holding an unsuccessful lowest bidder had standing to bring
    writ of prohibition claim to prevent city from awarding public contract to the successful
    bidder); Cementech, Inc. v. City of Fairlawn, 
    849 N.E.2d 24
    , 27 (Ohio 2006) (noting that
    a rejected bidder’s remedy is limited to injunctive relief); Associated Builders &
    Contractors of R.I., Inc. v. Dep’t of Admin., 
    787 A.2d 1179
    , 1186 (R.I. 2002) (holding that
    general contractors disqualified from bidding had standing to seek injunctive relief
    challenging project labor agreement requirement under the competitive bidding statute);
    Sloan v. Dep’t of Transp., 
    618 S.E.2d 876
    , 878–79 (S.C. 2005) (recognizing a “public
    importance” exception to the standing rule in the public bidding context); H & W
    Contracting, LLC v. City of Watertown, 
    633 N.W.2d 167
    , 172–73 (S.D. 2001) (“Because a
    disappointed bidder’s standing is based on the protection of public interests, it extends
    only to suits for declaratory or equitable relief seeking to compel compliance with the
    15
    Horsfield argues that its declaratory judgment claim fits into the
    class of claims that most other states allow and as to which Garling left
    the door open.         But there is a key difference.              Horsfield is not an
    unsuccessful bidder. It is a prospective supplier.
    Because Horsfield is a supplier rather than a contractor, it is more
    distant from chapter 26’s paramount purpose of protecting the taxpayer.
    A contractor that claims to have been the low bidder can argue that if the
    contract were awarded to it, taxpayers would directly benefit. But the
    relationship between relief to Horsfield and relief for Dyersville taxpayers
    is more tenuous. Horsfield’s argument has to run that if the City did not
    have a defined list of preapproved suppliers, the resulting bids would on
    balance be lower and better for the City. Whatever the possible merits of
    this argument, it is a more indirect one than a disappointed bidder might
    assert.
    In challenges to administrative agency actions, the standing
    inquiry has required “ ‘the interest sought to be protected by the
    complainant to be arguably within the zone of interests to be protected or
    ______________________
    competitive bid laws.”); Metro. Air Research Testing Auth., Inc. v. Metro. Gov’t of Nashville
    & Davidson Cnty., 
    842 S.W.2d 611
    , 617 (Tenn. Ct. App. 1992) (noting “in the absence of
    a statute, an unsuccessful bidder’s standing extends only to equitable or declaratory
    relief to ensure enforcement of required competitive bidding procedures”); Peerless Food
    Prods., Inc. v. State, 
    835 P.2d 1012
    , 1015 (Wash. 1992) (“Although a public contractor
    whose low bid is wrongfully rejected by a government entity is often held to have
    standing to prosecute an action for injunction, mandamus, or declaratory judgment, it
    is less frequently held that there is a remedy for damages in such cases[.]”) (citation and
    internal quotation marks omitted); W. Va. Util. Contractors Ass’n v. Laidley Field Athletic
    & Recreational Ctr. Governing Bd., 
    260 S.E.2d 847
    , 850 (W. Va. 1979) (holding an
    association of utilities contractors, that were prevented from bidding on a public
    project, had standing to seek declaratory judgment); D.M.K., Inc. v. Town of Pittsfield,
    
    711 N.W.2d 672
    , 678 (Wis. Ct. App. 2006) (citing Aqua-Tech, Inc. v. Como Lake Prot. &
    Rehab. Dist., 
    239 N.W.2d 25
    , 31 (Wis. 1976)) (stating that an unsuccessful bidder’s
    remedy for competitive bidding violations is injunctive relief, not damages); see also
    Isham, 65 A.L.R. 4th at 103 (“Declaratory judgment appears to be a popular and viable
    method of challenging the validity of contracts awarded to other than the lowest
    responsible bidder.”).
    16
    regulated by the statute.’ ” Godfrey v. State, 
    752 N.W.2d 413
    , 419 (Iowa
    2008) (quoting Ass’n of Data Processing Serv. Orgs., Inc. v. Camp, 
    397 U.S. 150
    , 153, 
    90 S. Ct. 827
    , 830, 
    25 L. Ed. 2d 184
    , 188 (1970)). The
    circumstance here is somewhat analogous: Horsfield is challenging the
    action of a municipality under a statute regulating the municipality’s
    conduct; it is not asserting a constitutional claim here.           See id.
    (distinguishing standing to bring constitutional claims).
    Other     jurisdictions   have    generally   found   that   potential
    subcontractors, like Horsfield, are not proper parties to invoke remedies
    under the competitive bidding statutes.       For example, in Connecticut
    Associated Builders & Contractors v. City of Hartford, the Connecticut
    Supreme Court affirmed a trial court’s ruling that subcontractors lacked
    standing to challenge a project labor agreement.       
    740 A.2d 813
    , 822
    (Conn. 1999). The court reasoned that allowing subcontractor standing
    was less certain to vindicate the public interest in getting the lowest and
    best overall bids and more likely to complicate and delay the bidding
    process. As the court explained:
    The trial court determined that the subcontractors did
    not have standing because they did not have a legal stake in
    the bidding process. The court reasoned that a diminished
    possibility of potential work as subcontractors was too
    attenuated an interest to give the subcontractors a legal
    stake in the bidding process. . . .
    ....
    The problem with the plaintiffs’ arguments is that the
    limited standing we have granted to disappointed and
    excluded contractors to bring challenges based on
    competitive bidding laws is designed to protect the interests
    of the public, not those of the contractors. The plaintiffs do
    not dispute the fact that the subcontractors did not and
    could not have bid on the project. We can discern no reason
    for expanding the “private attorney general” standing granted
    to contractors that bid or were precluded from bidding on a
    public project. On the contrary, permitting legal challenges
    17
    from the numerous subcontractors that potentially could be
    affected by a particular bidding process would be likely to
    upset the balance in protecting the public’s dual interests in
    fair public bidding processes and in the efficient completion
    of public works projects.
    Id. at 822–23; see also Amtech Sys. Corp. v. Ill. State Toll Highway Auth.,
    
    637 N.E.2d 619
    , 625 (Ill. App. Ct. 1994) (holding that a supplier lacked
    standing    to   challenge   specifications   that   allegedly   required   any
    successful bidder to use another supplier’s product); Transactive Corp. v.
    N.Y. State Dep’t of Soc. Servs., 
    706 N.E.2d 1180
    , 1184 (N.Y. 1998)
    (holding that a subcontractor, whose bid was part of an unsuccessful
    general contractor’s bid, did not have standing to bring a competitive
    bidding challenge, because it was “not within the zone of interests
    protected by” the public bidding statute). We agree with the reasoning in
    those cases and adopt it here.
    We do not foreclose the possibility that a contractor bidding on a
    project could have standing to bring a claim under chapter 26 for
    mandamus, injunction, or declaratory relief asserting that it lost the bid
    because the city wrongfully disallowed a supplier it wanted to use. Nor
    do we endorse such a claim. We simply indicate that from a standing
    perspective, this kind of claim would appear to be a better mechanism for
    vindicating the interests of taxpayers and would present a more clear
    and direct injury.
    Horsfield cites our recent decision in Hawkeye Foodservice
    Distribution, Inc. v. Iowa Educators Corp. and urges that harm to a
    company’s “competitive interests” can satisfy the injury requirement for
    standing.    See 
    812 N.W.2d 600
     (Iowa 2012).              But the facts, the
    procedural posture, and the statutes involved in that case were different.
    In Hawkeye Foodservice, the plaintiff food service company filed a
    petition alleging that the defendant government agencies had, in violation
    18
    of Iowa law, established an unlawful entity (also named as a defendant)
    that “award[ed] Hawkeye’s competitor a prime vendor contract,” thereby
    “taking business away from Hawkeye.” Id. at 606. In other words, the
    plaintiff (unlike Horsfield) was like an unsuccessful bidder that would
    have received a contract but for the defendants’ allegedly illegal conduct.
    Also noteworthy is that the case had been dismissed on the pleadings by
    the district court.       Id. at 604.       Thus, we concluded the plaintiff’s
    allegation that “it has lost and continues to lose business based on the
    AEAs’ illegal actions” was sufficient for that stage of the proceedings. Id.
    at 607.      Additionally, the plaintiff in Hawkeye Foodservice, a private
    company, was suing under laws designed to circumscribe the authority
    of the defendants to engage in private-type activities.               Id. at 610–13.
    Here Horsfield is bringing suit under bidding statutes intended to protect
    taxpayers, not companies like Horsfield. Accordingly, we do not believe
    that Hawkeye Foodservice affects the standing analysis in this case
    under chapter 26.2
    B. Horsfield’s Constitutional Claims.                Horsfield alleges that
    Dyersville’s ongoing exclusion of Horsfield from its list of preapproved
    suppliers for public contracts violates federal and state due process and
    equal protection guarantees. We agree with Horsfield that the standing
    analysis for these claims differs from that for the claims under the
    bidding statute.        See Godfrey, 752 N.W.2d at 419–20 (discussing
    constitutional standing). In cases involving “public rights,” we “no longer
    require the litigant to allege a violation of a private right and do not
    2As   the district court found, there is no issue of taxpayer standing here. See,
    e.g., Miller v. City of Des Moines, 
    143 Iowa 409
    , 423–24, 
    122 N.W. 226
    , 231–32 (1909)
    (finding that taxpayers had standing to maintain an action to enjoin the performance of
    a contract entered into by the city). The record is undisputed that Horsfield does not
    own property within Dyersville. Horsfield does not maintain on appeal that it has
    standing as a taxpayer.
    19
    require traditional damages to be suffered.        Instead, we require the
    litigant to allege some type of injury different from the population in
    general.” Id. at 420.
    Horsfield has demonstrated that a government practice has put it
    in a separate category from certain other suppliers and thereby
    disadvantaged it. Three companies are approved to supply aggregate and
    concrete; Horsfield, which presented proof that it is equally qualified,
    remains on the outside looking in.         Horsfield also has shown that it
    regularly supplies numerous contractors in Dubuque County with
    aggregate and concrete and is being prevented from doing so on
    Dyersville projects due to its ongoing exclusion from the preapproved
    supplier list. True, Horsfield has not established that its exclusion from
    the City’s list has caused it to lose the profits associated with a particular
    project.   However, it has proved a negative, i.e., that its ongoing
    exclusion from the preapproved supplier list and the practical obstacles
    associated with postaward approval make it unlikely it will be able to get
    work on city projects—far less likely than the privileged three. This is
    certainly an “injury different from the population in general” and more
    than an “abstract claim.”       Godfrey, 752 N.W.2d at 420–21 (internal
    quotation marks omitted). We should look at the question this way: If
    hypothetically   the    City   intentionally   included   only   white-owned
    companies on its preapproved list, would a minority-owned company on
    these facts have standing to sue for an equal protection violation? We
    believe the answer is clearly yes.
    Thus, for its constitutional claims, Horsfield has met the “injury in
    fact” element of standing. See Godfrey, 752 N.W.2d at 421 (quoting the
    Supreme Court, in Lujan v. Defenders of Wildlife, 
    504 U.S. 555
    , 560–61,
    
    112 S. Ct. 2130
    , 2136, 
    119 L. Ed. 2d 351
    , 364 (1992), as requiring that a
    20
    “plaintiff must establish a causal connection between the injury and the
    conduct complained of and that the injury is likely, as opposed to merely
    speculative, to be redressed by a favorable decision” (citation and
    internal quotation marks omitted)).
    An entity “need not demonstrate that it has been, or will be, the
    low bidder on a Government contract. The injury in cases of this kind is
    that   a   ‘discriminatory   classification   prevent[s]   the   plaintiff   from
    competing on an equal footing.’ ” Adarand Constructors, Inc. v. Pena, 
    515 U.S. 200
    , 211, 
    115 S. Ct. 2097
    , 2105, 
    132 L. Ed. 2d 158
    , 171 (1995)
    (quoting Ne. Fla. Chapter of Associated Gen. Contractors of Am. v.
    Jacksonville, 
    508 U.S. 656
    , 667, 
    113 S. Ct. 2297
    , 2304, 
    124 L. Ed. 2d 586
    , 598 (1993)) (finding that a subcontractor had standing to proceed
    with an equal protection challenge).
    When the government erects a barrier that makes it more
    difficult for members of one group to obtain a benefit than it
    is for members of another group, a member of the former
    group seeking to challenge the barrier need not allege that
    he would have obtained the benefit but for the barrier in
    order to establish standing. The “injury in fact” in an equal
    protection case of this variety is the denial of equal treatment
    resulting from the imposition of the barrier, not the ultimate
    inability to obtain the benefit.
    Ne. Fla. Chapter, 508 U.S. at 666, 113 S. Ct. at 2303, 124 L. Ed. 2d at
    597.
    However, we agree with the City that Horsefield’s constitutional
    claims fail on their merits.    Because no suspect class or fundamental
    right is at issue, we apply the rational basis test.       King v. State, 
    818 N.W.2d 1
    , 25, 31 (Iowa 2012); see also Master Builders, 653 N.W.2d at
    398 (finding that an equal protection challenge to the inclusion of a
    project labor agreement in competitive bids should be evaluated under
    21
    the rational basis test).3           The rational basis test is a “deferential
    standard.” Ames Rental Prop. Ass’n v. City of Ames, 
    736 N.W.2d 255
    ,
    259 (Iowa 2007). For equal protection purposes, we must determine only
    whether     the     classification      is    “rationally   related   to   a   legitimate
    governmental interest.”           Id.        “A statute or ordinance is presumed
    constitutional and the challenging party has the burden to ‘negat[e] every
    reasonable basis that might support the disparate treatment.’ ”                         Id.
    (citation omitted).      “The City is not required or expected to produce
    evidence to justify its legislative action.” Id. Still, for state constitutional
    purposes, the government interest must be “ ‘realistically conceivable.’ ”
    Qwest Corp. v. Iowa State Bd. of Tax Review, 
    829 N.W.2d 550
    , 560 (Iowa
    2013) (citation and emphasis omitted); King, 818 N.W.2d at 30; Racing
    Ass’n of Cent. Iowa v. Fitzgerald, 
    675 N.W.2d 1
    , 7–8 (Iowa 2004). And in
    the equal protection context, the means chosen to advance that interest
    cannot be “so overinclusive and underinclusive as to be irrational.” State
    v. Mitchell, 
    757 N.W.2d 431
    , 439 (Iowa 2009); see also Racing Ass’n of
    Cent. Iowa, 675 N.W.2d at 10.
    3Horsfield   argues that “a fundamental right applies, namely its liberty interest in
    the right to contract.” However, to support that contention, it cites a case, Koster v.
    City of Davenport, which involved an alleged state impairment of an existing contract in
    violation of United States Constitution article I, section 10. See 
    183 F.3d 762
    , 766 (8th
    Cir. 1999). On the due process claim, the Koster court applied the rational basis test.
    Id. at 768–69. The United States Supreme Court has held for the better part of a
    century that the right to contract is not fundamental under the United States
    Constitution. See W. Coast Hotel Co. v. Parrish, 
    300 U.S. 379
    , 391, 
    57 S. Ct. 578
    , 581–
    82, 
    81 L. Ed. 703
    , 708 (1937) (“The Constitution does not speak of freedom of
    contract. . . . [R]egulation which is reasonable in relation to its subject and is adopted
    in the interests of the community is due process.”). Nor have we held in the past that
    the right to contract is a fundamental right triggering strict scrutiny under the Iowa
    Constitution. See State v. Willard, 
    756 N.W.2d 207
    , 213 (Iowa 2008) (applying a
    rational basis test to sex offender residency restrictions notwithstanding the defendant’s
    argument that they affected his right to contract). Horsfield is not asserting any claim
    under article I, section 6 of the Iowa Constitution apart from traditional equal
    protection, and we have no occasion to consider whether another type of claim would be
    available.
    22
    Dyersville’s preapproval process serves a realistically conceivable
    governmental interest in quality control. As Sejkora testified, “The effort
    was for quality control to make sure that we were able to obtain
    materials from . . . suppliers we knew through our experience to be
    capable of providing materials that complied with the specification
    technical requirements.”     And there is a reasonable fit between the
    means chosen and the goal. Sejkora explained that the City had twenty
    to thirty years of positive experience with each of the suppliers on the
    preapproved lists: “We’ve had a working relationship with the three
    identified and prior approved suppliers and over the years have seen this
    material come in.” There is no indication the City excluded any suppliers
    from its preapproved lists that had a similar track record. While there
    are certainly other, perhaps better, ways to assure a quality supply of
    concrete and aggregate at a competitive price, we cannot say the City’s
    process is so arbitrary as to violate equal protection or substantive due
    process.      Accordingly, we reject Horsfield’s equal protection and
    substantive due process claims.
    Horsfield also contends that the City violated its procedural due
    process rights.      “Under procedural due process, notice and an
    opportunity to be heard are required when a person’s property interests
    are at stake.”     Lewis v. Jaeger, 
    818 N.W.2d 1
    65, 181 (Iowa 2012).
    “Procedural due process requires that certain procedures be afforded
    (e.g., notice and an opportunity to be heard) before the government
    deprives a citizen of a liberty or property interest.” King, 818 N.W.2d at
    33 n.25.      However, “[o]ur first inquiry in a procedural due process
    analysis is whether a protected liberty or property interest is involved.”
    Bowers v. Polk Cnty. Bd. of Supervisors, 
    638 N.W.2d 682
    , 691 (Iowa
    2002).     The problem here is that Horsfield has no protected liberty or
    23
    property interest at stake, merely an unfulfilled desire to enter into
    contracts to supply materials for Dyersville public improvements. See,
    e.g., Greenwood Manor v. Iowa Dep’t of Pub. Health, 
    641 N.W.2d 823
    ,
    837–38 (Iowa 2002) (holding that nursing homes do not have a protected
    property interest in a competitor’s not receiving a certificate of need).
    Hence, no procedural due process violation occurred here. A different
    question might be presented if we were talking about a broad or
    stigmatizing debarment by the federal government. See Trifax Corp. v.
    District of Columbia, 
    314 F.3d 641
    , 643–44 (D.C. Cir. 2003).          Here,
    however, Horsfield’s complaint is merely that it is unable to get on one
    municipality’s approved supplier list. This does not implicate a liberty
    interest.
    C. Horsfield’s Open Records Act Claim.         Horsfield also argues
    the district court erred in finding that Dyersville did not violate Iowa’s
    Open Records Act. That Act provides that “[e]very person shall have the
    right to examine and copy a public record and to publish or otherwise
    disseminate a public record or the information contained in a public
    record.” Iowa Code § 22.2.
    “ ‘The purpose of the statute is to open the doors of government to
    public scrutiny [and] to prevent government from secreting its decision-
    making activities from the public, on whose behalf it is its duty to act.’ ”
    Diercks, 806 N.W.2d at 652 (quoting Rathmann v. Bd. of Dirs., 
    580 N.W.2d 773
    , 777 (Iowa 1998)). “ ‘Accordingly, there is a presumption of
    openness and disclosure under this chapter.’ ” Id. (quoting Gabrilson v.
    Flynn, 
    554 N.W.2d 267
    , 271 (Iowa 1996)).
    Civil enforcement of Iowa’s Open Records Act initially places the
    burden of showing three things on the party seeking enforcement
    (Horsfield).   That party must “demonstrate[] to the court that the
    24
    defendant is subject to the requirements of this chapter, that the records
    in question are government records, and that the defendant refused to
    make those government records available for examination and copying by
    the plaintiff.”   Iowa Code § 22.10(2).      Once a party makes these
    showings, the defendant has the burden to show compliance, and the
    court must issue an injunction if it finds the defendant has not complied
    by a preponderance of the evidence. Id. § 22.10(3)(a); see also Diercks,
    806 N.W.2d at 653 (“Once the citizen shows the city denied his or her
    request to access government records, the burden shifts to the city to
    demonstrate it complied with the chapter’s requirements.”).
    Horsfield makes two arguments on appeal, both of which relate to
    the timeliness rather than the completeness of production.              First,
    Horsfield contends the City violated the law by not making its 617-page
    production until April 2010. This was approximately seventy days after
    the parties confirmed Horsfield’s modified request for these documents
    and, in Horsfield’s view, exceeded the twenty-day deadline set forth in
    Iowa Code section 22.8(4)(d). Second, Horsfield argues that Dyersville’s
    claim of privilege on certain emails, followed by its belated April 2011
    eve-of-trial waiver of that privilege and production of the emails, amounts
    to an admission that the City had “no defense to its failure to produce
    relevant and responsive documents.”
    There is no explicit time deadline in chapter 22 for the production
    of public records when requested. However, Horsfield argues that there
    is an implicit time limit of twenty days based on the following language in
    section 22.8:
    4. Good-faith, reasonable delay by a lawful custodian
    in permitting the examination and copying of a government
    record is not a violation of this chapter if the purpose of the
    delay is any of the following:
    25
    a. To seek an injunction under this section.
    b. To determine whether the lawful custodian is
    entitled to seek such an injunction or should seek such an
    injunction.
    c. To determine whether the government record in
    question is a public record, or confidential record.
    d. To determine whether a confidential record should
    be available for inspection and copying to the person
    requesting the right to do so. A reasonable delay for this
    purpose shall not exceed twenty calendar days and ordinarily
    should not exceed ten business days.
    Id. § 22.8(4)(a)–(d) (emphasis added). Yet the twenty-day time limit is not
    a blanket rule; rather, it is limited to the circumstance in which the
    custodian needs to determine whether an otherwise confidential record
    should be made available to a person who claims the right to view it.
    That is not the situation here.
    On the other hand, the fact that section 22.8(4) lists certain
    grounds for “[g]ood faith, reasonable delay” might lead to an inference
    that those grounds are exclusive.           See Kucera v. Baldazo, 
    745 N.W.2d 481
    , 487 (Iowa 2008) (discussing the rule of expressio unius est exclusio
    alterious).   But see State v. Meyers, 
    799 N.W.2d 132
    , 142 (Iowa 2011)
    (noting limits on this principle).4 And section 22.4 of the Open Records
    Act, by stating that “[t]he rights of persons under this chapter may be
    exercised at any time during the customary office hours of the lawful
    custodian of the records,” suggests that our legislature contemplated
    immediate access to public records.
    4One might also argue that because section 22.10(3)(b)(2) gives a defense to any
    person who “[h]ad good reason to believe and in good faith believed facts which, if true,
    would have indicated compliance with the requirements of this chapter,” there should
    not be an another “good faith” test layered on top of that to determine whether
    compliance with the Open Records Act has occurred.
    26
    Based on our review of section 22.8(4)(d), we believe it is not
    intended to impose an absolute twenty-day deadline on a government
    entity to find and produce requested public records, no matter how
    voluminous the request. Rather, it imposes an outside deadline for the
    government entity to determine “whether a confidential record should be
    available for inspection and copying to the person requesting the right to
    do so.”   We do not think we should extrapolate section 22.8(4)(d)’s
    twenty-day deadline to other contexts, when the legislature chose not
    even to include that deadline in the other portions of section 22.8(4).
    According to a longstanding administrative interpretation of
    chapter 22:
    Access to an open record shall be provided promptly upon
    request unless the size or nature of the request makes
    prompt access infeasible. If the size or nature of the request
    for access to an open record requires time for compliance,
    the custodian shall comply with the request as soon as
    feasible.
    See Iowa Uniform Rules on Agency Procedure, Fair Information Practices,
    Agency    No.—X.3(17A,22),    [hereinafter   Fair   Information    Practices]
    available at https://www.legis.iowa.gov/DOCS/Rules/Current/Uniform
    Rules.pdf (emphasis added); see also Griffin Pipe Prods. Co. v. Bd. of
    Review, 
    789 N.W.2d 769
    , 775 (Iowa 2010) (“Longstanding administrative
    interpretations are entitled to some weight in statutory construction.”).
    The State’s Uniform Rules on Agency Procedure, from which the above
    quotation is taken, were drafted by a nine-member task force chaired by
    University of Iowa Law School Professor Arthur Bonfield; they were
    adopted in 1985.       Fair Information Practices at 1.           Under this
    interpretation, practical considerations can enter into the time required
    for responding to an open records request, including “the size or nature
    27
    of the request.” But the records must be provided promptly, unless the
    size or nature of the request makes that infeasible.5
    In Wings v. Dunlap, our court of appeals reversed a district court’s
    determination that a records custodian had violated chapter 22 when it
    took from March 28, 1991, to April 22, 1991, for him to make certain
    public records available for examination. 
    527 N.W.2d 407
    , 410–11 (Iowa
    Ct. App. 1994). That court observed, “Chapter 22 cannot be interpreted
    and applied in a vacuum.”           Id. at 410.      That court also held that a
    “substantial compliance” standard should apply to alleged violations of
    chapter 22, analogizing to a case where we applied a substantial
    compliance rule in the context of Iowa’s open meetings law, Iowa Code
    chapter 21.      See id. (citing KCOB/KLVN, Inc. v. Jasper Cnty. Bd. of
    Supervisors, 
    473 N.W.2d 171
    , 176 (Iowa 1991)).                    The court found
    substantial compliance notwithstanding the admission by the city
    attorney that she had “dropped the ball.” Id. at 409.
    In this case we need not decide whether a substantial compliance
    standard applies to claimed violations of the Open Records Act.                    The
    district court followed such a standard and Horsfield does not argue on
    appeal for something different. In light of this concession, we will utilize
    substantial compliance here, assuming without deciding that it is the
    appropriate test. See Brown v. John Deere Waterloo Tractor Works, 
    423 N.W.2d 193
    , 194 (Iowa 1988) (indicating that substantial compliance is a
    fact-specific inquiry depending on whether “the purpose of the statute is
    shown to have been served” (citation and internal quotation marks
    omitted)).
    5Under federal law, which expressly requires the requested records to be made
    “promptly available,” 5 U.S.C. § 552(a)(3)(A) (2006), it has been considered whether the
    agency “unreasonably delayed” and whether the requester was “prejudiced” by the
    delay. Strout v. U.S. Parole Comm’n, 
    40 F.3d 136
    , 138 (6th Cir. 1994).
    28
    Although it is a close question, on our de novo review we are not
    persuaded that the City’s production of the documents requested in
    January 2010 substantially complied with its legal obligation to produce
    public records promptly, subject to the size and nature of the request.
    The City took from approximately January 25, 2010, to April 6, 2010, to
    produce these 617 pages.        The City did not produce any of the
    documents until after Horsfield went to court on March 18, 2010.        A
    hiatus in communication occurred from February 12, 2010, when
    Horsfield’s attorney asked for a status report, until March 25, 2010,
    when the City’s attorney informed Horsfield’s attorney that the records
    were essentially ready for production, except that the City “had been
    looking for time to review 42 hours of video.”
    Most troubling, it appears that the video recordings of public
    proceedings became a stumbling block to the production of the hard copy
    documents. That should not have occurred. From the beginning, the
    City could have offered Horsfield the opportunity to review or copy the
    video on its own, as it ultimately did.          In any event, any issues
    surrounding the video should not have held up the production of the
    hardcopy documents once they were located.
    The City’s position in this case is not without support. The city
    administrator Michel testified that he had to go through individual
    employee email accounts. He had to figure out how to get administrative
    rights and run an appropriate email search. Additionally, “we also had a
    lot of papers that were not digitized or nonsearchable, so we actually had
    to go through those documents to make sure that it didn’t have those
    reference points.” Michel was dealing with other urgent matters at that
    time, including the budget, development agreements, the implementation
    of a loan within a tight time frame, and getting approval for buyouts from
    29
    the 2008 floods.        This was in addition to his work on regular city
    business. Michel was devoting fifty to seventy hours a week to his job.
    Furthermore, none of the 617 pages (nor the video) were actually used at
    the trial on Horsfield’s underlying claim challenging the City’s use of
    preapproved supplier lists.
    Still, we have two problems with Michel’s testimony.                   First, his
    explanations did not include any dates or other time frames. Thus, while
    he gave plausible explanations for the City’s delay that might have
    carried the day in other circumstances, it is impossible to know how
    much time it really took city officials to work on Horsfield’s request,
    relative to other demands on city officials’ time. The City had the burden
    of going forward to demonstrate compliance with the Act. See Iowa Code
    § 22.10(2).6 In addition, as we have already discussed, the handling of
    the video was unsatisfactory.
    We disagree with Horsfield’s other contention with respect to
    claimed violations of the Open Records Act.                In our view, the City’s
    tactical decision to waive the attorney–client privilege in April 2011 with
    respect to the eight emails does not establish that the City violated the
    Act when it initially withheld them.           The Act allows public entities to
    6Under   section 22.10(2), once a party seeking judicial enforcement
    demonstrates to the court that the defendant is subject to the
    requirements of this chapter, that the records in question are
    government records, and that the defendant refused to make those
    government records available for examination and copying by the
    plaintiff, the burden of going forward shall be on the defendant to
    demonstrate compliance with the requirements of this chapter.
    The plaintiff must still prove “by a preponderance of the evidence that a lawful
    custodian has violated” the Act. Id. § 22.10(3). Although section 22.10(2) speaks in
    terms of a refusal rather than a delay in production, we think a refusal to produce
    encompasses the situation where, as here, a substantial amount of time has elapsed
    since the records were requested and the records have not been produced at the time
    the requesting party files suit under the Act.
    30
    withhold “[r]ecords which represent and constitute the work product of
    an attorney, which are related to litigation or claim made by or against a
    public body.” Id. § 22.7(4). Also, the Act does not affect other specific
    statutory privileges recognized by the legislature, such as the attorney–
    client privilege. See Burton v. Univ. of Iowa Hosps. & Clinics, 
    566 N.W.2d 182
    , 186–89 (Iowa 1997); see also Iowa Code § 622.10(1). Thus, the City
    had a right to withhold the emails. While there may be circumstances
    when it is unfair for a litigant that has properly asserted the attorney–
    client privilege later to waive that privilege, this is a procedural matter
    and not a violation of the Open Records Act.
    IV. Conclusion.
    For the foregoing reasons, we affirm the carefully reasoned
    judgment of the district court in all respects, except we find that the City
    violated the Open Records Act when it did not produce the public records
    requested in January 2010 until April 2010. We reverse the judgment on
    this point only and remand for further proceedings consistent with this
    opinion.
    DISTRICT     COURT     JUDGMENT       AFFIRMED      IN   PART    AND
    REVERSED IN PART, AND CASE REMANDED.
    

Document Info

Docket Number: 12–0491

Citation Numbers: 834 N.W.2d 444, 2013 Iowa Sup. LEXIS 83, 2013 WL 3378316

Judges: Mansfield

Filed Date: 7/5/2013

Precedential Status: Precedential

Modified Date: 11/12/2024

Authorities (48)

Airline Const. v. Ascension Parish School Board , 1990 La. LEXIS 2373 ( 1990 )

Kratz v. Allentown , 304 Pa. 51 ( 1931 )

Sloan v. Department of Transportation , 365 S.C. 299 ( 2005 )

Wings v. Dunlap , 1994 Iowa App. LEXIS 149 ( 1994 )

Burton v. University of Iowa Hospitals & Clinics , 1997 Iowa Sup. LEXIS 199 ( 1997 )

Garling Construction, Inc. v. City of Shellsburg , 2002 Iowa Sup. LEXIS 7 ( 2002 )

Sutter Bros. Construction Co. v. City of Leavenworth , 238 Kan. 85 ( 1985 )

Master Builders of Iowa, Inc. v. Polk County , 653 N.W.2d 382 ( 2002 )

Kucera v. Baldazo , 2008 Iowa Sup. LEXIS 34 ( 2008 )

Peerless Food Products, Inc. v. State , 119 Wash. 2d 584 ( 1992 )

Citizens for Responsible Choices v. City of Shenandoah , 2004 Iowa Sup. LEXIS 236 ( 2004 )

Telephone Associates, Inc. v. St. Louis County Board , 1985 Minn. LEXIS 1014 ( 1985 )

Associated Builders & Contractors of Rhode Island, Inc. v. ... , 2002 R.I. LEXIS 1 ( 2002 )

Bond v. United States , 131 S. Ct. 2355 ( 2011 )

Wilson v. Los Angeles County Metropolitan Transportation ... , 96 Cal. Rptr. 2d 747 ( 2000 )

Clifford L. Strout v. U.S. Parole Commission , 40 F.3d 136 ( 1994 )

Brown v. John Deere Waterloo Tractor Works , 1988 Iowa Sup. LEXIS 136 ( 1988 )

Rathmann v. Board of Directors of the Davenport Community ... , 1998 Iowa Sup. LEXIS 137 ( 1998 )

West Coast Hotel Co. v. Parrish , 57 S. Ct. 578 ( 1937 )

Northeastern Florida Chapter of the Associated General ... , 113 S. Ct. 2297 ( 1993 )

View All Authorities »