Meridian Engineering Company v. United States , 885 F.3d 1351 ( 2018 )


Menu:
  •   United States Court of Appeals
    for the Federal Circuit
    ______________________
    MERIDIAN ENGINEERING COMPANY,
    Plaintiff-Appellant
    v.
    UNITED STATES,
    Defendant-Appellee
    ______________________
    2017-1584
    ______________________
    Appeal from the United States Court of Federal
    Claims in No. 1:11-cv-00492-SGB, Chief Judge Susan G.
    Braden.
    ______________________
    Decided: March 20, 2018
    ______________________
    MARIA L. PANICHELLI, Cohen Seglias Pallas Greenhall
    & Furman PC, Philadelphia, PA, argued for plaintiff-
    appellant. Also represented by MICHAEL H. PAYNE.
    ERIC LAUFGRABEN, Commercial Litigation Branch,
    Civil Division, United States Department of Justice,
    Washington, DC, argued for defendant-appellee. Also
    represented by CHAD A. READLER, ROBERT E. KIRSCHMAN,
    JR., ALLISON KIDD-MILLER; JOHN FRANCIS BAZAN, SR.,
    United States Army Corps of Engineers, Los Angeles, CA.
    ______________________
    2                      MERIDIAN ENG’G CO.   v. UNITED STATES
    Before PROST, Chief Judge, REYNA and WALLACH, Circuit
    Judges.
    WALLACH, Circuit Judge.
    Meridian Engineering Company (“Meridian”) appeals
    two final decisions of the U.S. Court of Federal Claims
    determining, inter alia, that (1) Meridian did not meet
    standards of proof to show that the United States (“Gov-
    ernment”) breached certain contractual obligations and
    its duty of good faith and fair dealing in a dispute under
    the Contract Disputes Act, 41 U.S.C. §§ 601−613 (2006)
    (“CDA”) related to the construction of a flood control
    project in Nogales, Arizona, see Meridian Eng’g Co. v.
    United States (Meridian I), 
    122 Fed. Cl. 381
    , 384, 400
    n.25, 426 (2015); J.A. 3000−53 (Second Amended Com-
    plaint), and (2) Meridian was owed certain monies for
    equitable adjustment and interest on the payments
    running from the date Meridian submitted its claim,
    January 7, 2014, see Meridian Eng’g Co. v. United States
    (Meridian II), 
    130 Fed. Cl. 147
    , 172 (2016). We have
    jurisdiction pursuant to 28 U.S.C. § 1295(a)(3) (2012). We
    affirm-in-part, vacate-in-part, reverse-in-part, and re-
    mand.
    BACKGROUND 1
    In 2007, Meridian entered into a contract with the
    Government to construct flood control structures, referred
    to as the Chula Vista Project. Meridian 
    I, 122 Fed. Cl. at 385
    −86. The Project contemplated construction of several
    concrete channels, relocation of a sewer line, and dewater-
    ing and water diversion. See J.A. 1044−627 (Contract).
    1   The undisputed facts and procedural history of
    this case are extensive and are described in full in Merid-
    ian I. 
    See 122 Fed. Cl. at 385
    −97. We provide here only a
    brief summary of the relevant facts and procedural histo-
    ry necessary to resolve this appeal.
    MERIDIAN ENG’G CO.   v. UNITED STATES                    3
    After commencing the Project, Meridian encountered a
    series of problems relating primarily to what it deemed
    “subsurface organic/unsuitable material,” specifically, “a
    layer of dripping saturated dark clay material under
    which a clean layer of sand is producing water” that had
    “the potential for serious structural damage.” J.A. 1810;
    see Meridian 
    I, 122 Fed. Cl. at 388
    (describing “softer-
    than-anticipated soils”), 390−92 (describing modifications
    pursuant to discovery of “saturated soils”). Meridian
    notified the Government about these problems, and the
    Government issued several Contract modifications in
    response. See Meridian 
    I, 122 Fed. Cl. at 388
    −90 (describ-
    ing modifications for increase in allotted funds for larger
    pipe size, addition of a reinforced concrete access ramp,
    investigation of soil properties, remediation of saturated
    soils, and additional sheet piling). Eventually, the Gov-
    ernment directed Meridian to suspend work on the Pro-
    ject in January 2009 following a series of structural
    failures, see J.A. 3127−28, and, while minor work contin-
    ued, the Government ultimately terminated the Project
    following a September 2009 final inspection of the Project
    site, see Meridian 
    I, 122 Fed. Cl. at 394
    −96.
    Following the parties’ disagreements over payment
    owed to Meridian, Meridian filed suit in the Court of
    Federal Claims for breach of contract, breach of the duty
    of good faith and fair dealing, and a violation of the CDA.
    See J.A. 127, 3000−53. The Government conceded liabil-
    ity for costs relating to three counts of Meridian’s Second
    Amended Complaint (Counts VII−IX), which were the
    subject of a separate damages trial. See J.A. 3032−36
    (Count VII (Suspension of Work), Count VIII (Channel
    Fill), Count IX (Interim Protection)). See generally Merid-
    ian II, 
    130 Fed. Cl. 147
    . Because the Government now
    4                      MERIDIAN ENG’G CO.   v. UNITED STATES
    concedes the only issue with respect to Meridian II, 2 the
    remainder of this opinion addresses determinations from
    Meridian I.
    DISCUSSION
    I. Standard of Review
    We review the Court of Federal Claims’ legal conclu-
    sions de novo and its factual findings for clear error. See
    John R. Sand & Gravel Co. v. United States, 
    457 F.3d 1345
    , 1353 (Fed. Cir. 2006), aff’d 
    552 U.S. 130
    (2008). “A
    finding may be held clearly erroneous when the appellate
    court is left with a definite and firm conviction that a
    mistake has been committed.” Ind. Mich. Power Co. v.
    United States, 
    422 F.3d 1369
    , 1373 (Fed. Cir. 2005) (in-
    ternal quotation marks, ellipsis, and citation omitted).
    II. CDA Claims
    Meridian asserts that the Court of Federal Claims
    erred when it “reasoned that only Meridian’s breach of
    contract and breach of good faith and fair dealing claims
    2   Both parties agree that the Court of Federal
    Claims erred in setting the date from which interest
    accrued at January 7, 2014. See Appellant’s Br. 61−62;
    Appellee’s Br. 60. Interest accrues from the date that the
    contracting officer (“CO”) receives a claim. See 41 U.S.C.
    § 7109(a)(1) (2012) (“Interest on an amount found due a
    contractor on a claim shall be paid to the contractor for
    the period beginning with the date the [CO] receives the
    contractor’s claim . . . until the date of payment of the
    claim.”). Here, accrual commenced on January 7, 2011.
    See J.A. 2511. We reverse Meridian II with respect to the
    date of interest accrual with instructions for the court to
    enter the correct accrual date as January 7, 2011, and
    recalculate the amount of interest in accordance with the
    correct accrual date.
    MERIDIAN ENG’G CO.   v. UNITED STATES                     5
    presented a viable cause of action,” because “Meridian’s
    CDA claims should have been analyzed under the frame-
    work contemplated by the CDA, and not under the rubric
    of a ‘breach’ claim.” Appellant’s Br. 23, 24 (capitalization
    modified). However, Meridian does not explain the alter-
    nate CDA framework to which it refers, nor does it state
    how analysis under a different hypothetical framework
    would result in a finding in its favor. See 
    id. at 22−25
    (stating only that the use of the breach of contract stand-
    ard “skewed” the Court of Federal Claims’ analysis).
    “The[] requirements of the CDA are jurisdictional pre-
    requisites to any appeal.” M. Maropakis Carpentry, Inc.
    v. United States, 
    609 F.3d 1323
    , 1328 (Fed. Cir. 2010)
    (citation omitted); see K-Con Bldg. Sys., Inc. v. United
    States, 
    778 F.3d 1000
    , 1004 (Fed. Cir. 2015) (reviewing de
    novo whether the Court of Federal Claims had jurisdic-
    tion under the CDA). Pursuant to the CDA, a party must
    submit a “valid claim,” which is defined by regulation as a
    demand seeking “as a matter of right, the payment of
    money in a sum certain, the adjustment or interpretation
    of contract terms, or other relief arising under or relating
    to the contract.” M. 
    Maropakis, 609 F.3d at 1327
    (quoting
    48 C.F.R. § 33.201 3). Thus, the CDA itself does not pro-
    vide a cause of action to which money damages may
    accrue; it is the claim asserted pursuant to the CDA that
    is the source of potential damages and review by the trier
    of fact. See Northrop Grumman Computing Sys., Inc. v.
    United States, 
    709 F.3d 1107
    , 1112 (Fed. Cir. 2013) (ex-
    plaining the prerequisites for a valid claim brought under
    the CDA, which is a jurisdictional requirement to obtain
    relief). Therefore, the Court of Federal Claims did not err
    3    Recodified at Federal Acquisition Regulation
    (“FAR”) 2.101 (2002); see Federal Acquisition Regulation;
    Definition of ‘Claim’ and Terms Relating to Termination,
    67 Fed. Reg. 43,513, 43,513 (June 27, 2002).
    6                       MERIDIAN ENG’G CO.   v. UNITED STATES
    in finding it had jurisdiction under the CDA to evaluate
    Meridian’s breach of contract claims.
    III. The Court of Federal Claims Did Not Err in Its Differ-
    ing Site Conditions Analysis (Counts II and V)
    The Court of Federal Claims found that Meridian did
    not offer sufficient evidence to satisfy its Type I differing
    site condition (“DSC”) claim alleging that in the channel
    and sewer line areas of the project the unexpected condi-
    tions of “soupy” soil caused delays and imposed unantici-
    pated costs. 4 Meridian 
    I, 122 Fed. Cl. at 403
    ; see 
    id. at 408−09.
    Meridian posits several errors in the Court of
    Federal Claims’ analysis. 5 See Appellant’s Br. 27−40.
    After articulating the applicable legal standard, we ad-
    dress each argument in turn.
    4   Meridian’s DSC claim originates from the stand-
    ard “differing site conditions” clause located in the Con-
    tract pursuant to FAR 52.236-2(a) (2017).                See
    J.A. 1150−51.
    5   For example, Meridian argues that the Court of
    Federal Claims only addressed Count V’s DSC claim with
    respect to the sewer relocation work but “wholly failed to
    address Meridian’s Count II [DSC] claim” related to the
    area of construction around the concrete channels. Appel-
    lant’s Br. 40 (capitalization modified). Meridian is incor-
    rect. The Court of Federal Claims noted at the start of its
    DSC analysis that, “because the parties’ briefs jointly
    discuss [DSC] and sewer relocation, the court addresses
    Counts [II] and [V] together.” Meridian 
    I, 122 Fed. Cl. at 402
    n.27; see 
    id. at 402
    (discussing Counts II and V jointly
    under a common heading “Whether Meridian Is Entitled
    to Costs for [DSC] in the Channel and at the Sewer Line”
    (capitalization modified)).
    MERIDIAN ENG’G CO.   v. UNITED STATES                      7
    A. Legal Standard
    “A Type I [DSC claim] arises when the conditions en-
    countered differ from what was indicated in the contract
    documents.” Renda Marine, Inc. v. United States, 
    509 F.3d 1372
    , 1376 (Fed. Cir. 2007); see FAR 52.236-2(a)−(b)
    (“The Contractor shall promptly . . . give a written notice
    to the [CO] of (1) subsurface or latent physical conditions
    at the site which differ materially from those indicated in
    this contract. . . . The [CO] shall investigate the site
    conditions promptly after receiving the notice. If the
    conditions do materially so differ and cause an increase or
    decrease in the Contractor’s cost of, or the time required
    for, performing any part of the work under this contract,
    whether or not changed as a result of the conditions, an
    equitable adjustment shall be made under this
    clause . . . .”). 6 To prevail on a Type I DSC claim, a con-
    tractor must prove that: (1) “a reasonable contractor
    reading the contract documents as a whole would inter-
    pret them as making a representation as to the site
    conditions”; (2) “the actual site conditions were not rea-
    sonably foreseeable to the contractor, with the infor-
    mation available to the particular contractor outside the
    contract documents” (i.e., reasonable foreseeability);
    (3) “the particular contractor in fact relied on the contract
    representation”; and (4) “the conditions differed material-
    ly from those represented and . . . the contractor suffered
    damages as a result.” Int’l Tech. Corp. v. Winter, 
    523 F.3d 1341
    , 1348−49 (Fed. Cir. 2008). “Determining whether a
    contract contained indications of a particular site condi-
    6   It “is distinguished from a Type II [DSC claim],
    which arises when the conditions encountered are of an
    unusual nature and differ materially from those normally
    encountered in the kind of work contemplated by the
    contract.”    Renda 
    Marine, 509 F.3d at 1376
    (citing
    FAR 52.236-2(a)−(b)).
    8                       MERIDIAN ENG’G CO.   v. UNITED STATES
    tion is a matter of contract interpretation” that we review
    de novo. 
    Id. at 1350
    (internal quotation marks and cita-
    tion omitted).
    B. Meridian Has Not Shown a Type I Differing Site Con-
    dition
    The Court of Federal Claims found in relevant part
    that Meridian’s interpretation of the Contract was not
    reasonable, and that the existence of subsurface saturated
    soil conditions was “reasonably foreseeable.” Meridian 
    I, 122 Fed. Cl. at 409
    ; see 
    id. at 408−09.
    Specifically, the
    Court of Federal Claims first found that the specification
    stated that “[w]ater in varying quantities may be flowing
    in natural washes throughout the length of the project,”
    and “[t]he work site may be inundated because of [water]
    runoff,” 
    id. (quoting J.A.
    1629, 1630), such that “a reason-
    able contractor would interpret the Specification as repre-
    senting water as a site condition,” id at 409. As for the
    second element of reasonable foreseeability, the Court of
    Federal Claims found that the original drawings in the
    Contract showed saturated soil and that the worksite was
    located on a floodplain, and a reasonable contractor would
    have conducted a site visit which would have alerted the
    contractor to the subsurface saturated soil conditions,
    such that “the actual conditions at the site were reasona-
    bly foreseeable.” 
    Id. (citing J.A.
    1664, 1725−26, 1729).
    We see no error in the Court of Federals Claims’ find-
    ings with respect to the first two elements of a Type I
    DSC claim. 7 As noted by the Court of Federal Claims,
    7   Meridian’s arguments related to the third and
    fourth elements of the Type I DSC claim―reliance in fact
    and material differences―are “premised on the [Court of
    Federal Claims’] erroneous conclusions regarding [the
    second element of reasonable foreseeability].” Appellant’s
    Br. 39 (capitalization modified). We may affirm the Court
    MERIDIAN ENG’G CO.   v. UNITED STATES                     9
    several instances in the Specification and accompanying
    drawings indicate the potential presence of water and
    saturated soil. See, e.g., J.A. 1664, 1725−26; see also
    J.A. 1729, 3274−76, 3286, 3367−68. Boring logs that
    accompanied the Contract also recorded sub-surface
    conditions near the boring holes that were “silty clay, with
    sand, black, wet, medium to high plasticity, [and] soft.”
    J.A. 1652; see J.A. 1653−63 (recording similar descriptions
    in additional boring hole logs). Further, the boring hole
    logs stated that “variations may exist in the subsurface
    between boring locations,” J.A. 1736, and that the logs,
    which recorded boring log data from nearly two decades
    prior, “should not be construed as . . . defining construc-
    tion conditions,” J.A. 1651; see, e.g., J.A. 1664 (dating
    boring excavations to 1989). Therefore, even though the
    Contract indicated “hard unyielding material” found at
    parts of the site, J.A. 1737, a “reasonable and prudent
    contractor would not have understood the [C]ontract
    documents as providing an affirmative indication of the
    subsurface conditions” to be non-saturated at the site,
    H.B. Mac, Inc. v. United States, 
    153 F.3d 1338
    , 1347 (Fed.
    Cir. 1998); see 
    id. at 1346−47
    (finding no representation
    as to site conditions where both parties acknowledged the
    of Federal Claims’ holding that Meridian has not proven a
    DSC based on the failure of a single element of the DSC
    claim. See Renda 
    Marine, 509 F.3d at 1378
    (affirming
    denial of a DSC claim when contractor failed to establish
    the first two elements of its claim); see also Int’l Tech.
    
    Corp., 523 F.3d at 1353
    (affirming denial of a DSC claim
    based on failure to establish the first element “and, alter-
    natively,” failure to establish the second element). How-
    ever, even if we were to review the third and fourth
    elements, because we affirm the Court of Federal Claims’
    determination with regard to the first and second ele-
    ments, we would find that Meridian’s conditional argu-
    ments on the third and fourth elements fail.
    10                     MERIDIAN ENG’G CO.   v. UNITED STATES
    site contained highly variable subsurface conditions and
    finding boring holes taken in proximity to site but not
    directly in work zone that indicated certain conditions
    could not be representative of entire site); see also Renda
    
    Marine, 509 F.3d at 1378
    (similar).
    A reasonable and prudent contractor would have fore-
    seen the saturated soil condition, based on the Contract
    documents and the fact that the actual conditions at the
    site indicated such conditions. See H.B. 
    Mac, 153 F.3d at 1346
    (“It is well-settled that a contractor is charged with
    knowledge of the conditions that a pre-bid site visit would
    have revealed.” (citation omitted)); Meridian I, 122 Fed.
    Cl. at 409 (relying on testimony from the Government’s
    expert). The Government’s expert stated not only that
    “[s]oft saturated soils with challenging groundwater
    conditions can be, and typically are, encountered when
    excavating in an active flood channel,” J.A. 442, but also
    that a large presence of saturated soil was located “100
    f[ee]t or so” away from where Meridian worked, J.A. 583.
    Meridian’s President, Mark Sutton, acknowledged that he
    reviewed the boring logs and understood that certain
    dewatering efforts would need to take place before con-
    struction began. See, e.g., J.A. 259–62. Moreover, Merid-
    ian presents nothing but unsworn attorney argument to
    rebut the Government’s testimony that a site visit would
    have made a reasonable contractor aware of the saturated
    soil conditions, see Reply Br. 17; that is not evidence and
    cannot rebut the Government’s admitted evidence, see
    Gemtron Corp. v. Saint-Gobain Corp., 
    572 F.3d 1371
    ,
    1380 (Fed. Cir. 2009). Therefore, we find the Court of
    Federal Claims did not err in finding no DSC with respect
    to the channel and sewer relocation area.
    C. Meridian’s Counterarguments on Its Type I DSC Claim
    Are Unpersuasive
    Meridian makes four primary arguments why we
    should find the Court of Federal Claims erred in finding
    MERIDIAN ENG’G CO.   v. UNITED STATES                   11
    that “the actual conditions at the site were reasonably
    foreseeable,” 8 Meridian 
    I, 122 Fed. Cl. at 409
    ; see Appel-
    lant’s Br. 26–39, all of which are unavailing.
    First, Meridian contends that the Court of Federal
    Claims’ review “was based on an improper interpretation
    of the Contract documents, which failed to give proper
    weight to [certain] geotechnical information.” Appellant’s
    Br. 29; see 
    id. at 29−39.
    Specifically, Meridian alleges
    that the geotechnical information provided in the solicita-
    tion “indicated that there would be hard, unyielding
    materials in the excavation areas” rather than the discov-
    ered groundwater and clay materials. 
    Id. at 31;
    see, e.g.,
    J.A. 1737 (providing Section 3.2 of the Specification
    stating certain areas of the Project contained “hard un-
    yielding material”).
    Despite Section 3.2’s language, the Court of Federal
    Claims noted several other portions of the Contract that
    indicated areas of the site contained saturated soil. See
    Meridian 
    I, 122 Fed. Cl. at 409
    (citing J.A. 1664, 1725−26
    (portions of boring logs)). As discussed above, the boring
    logs reviewed by the Court of Federal Claims also re-
    vealed conditions of “silty clay, with sand, black, wet,
    8    Meridian also contends that the Court of Federal
    Claims erred by determining “what specific representa-
    tions the contract made” under the first element of the
    Type I DSC claim, i.e., what representations were made to
    a reasonable contractor, when that determination should
    have been made under the second element of the Type I
    DSC claim. See Appellant’s Br. 27. However, Meridian
    does not allege this error would affect the disposition of
    the Court of Federal Claims’ holding, nor does Meridian
    present any evidence in support of its argument. Accord-
    ingly, we find Meridian waived this undeveloped argu-
    ment. See SmithKline Beecham Corp. v. Apotex Corp.,
    
    439 F.3d 1312
    , 1320 (Fed. Cir. 2006).
    12                      MERIDIAN ENG’G CO.   v. UNITED STATES
    medium to high plasticity, [and] soft.” J.A. 1652; see J.A.
    1653−63 (recording similar descriptions in additional
    boring hole logs); see also H.B. 
    Mac, 153 F.3d at 1346
    (considering boring log data on a case-by-case factual
    basis as part of the DSC analysis). Finally, Section 3.2,
    which is the same portion of the Specification that Merid-
    ian cites for the proposition that certain areas would
    contain hard, unyielding material, instructs that the
    contractor may encounter in certain areas “unstable
    material,” J.A. 1739, defined as “materials too wet to
    properly support the utility pipe, conduit, or appurtenant
    structure,” J.A. 1735. We cannot say that the Court of
    Federal Claims clearly erred in its determination that the
    subsurface soil conditions were reasonably foreseeable
    based on the Contract.
    Second, Meridian contends that the Court of Federal
    Claims erred in not giving sufficient weight to Meridian’s
    expert and witness testimony, which explained that
    Meridian relied on certain statements in the Specification
    in making its assessment. See Appellant’s Br. 32−34
    (describing reliance on Meridian’s president, Mr. Sutton),
    34–36 (asserting the findings of Meridian’s expert, Dr.
    James W. Mahar, which it deems consistent with Mr.
    Sutton’s conclusions that it was reasonable not to expect
    groundwater flows or clay materials at the site). We do
    not find clear error in the Court of Federal Claims’ con-
    sideration of the expert and witness testimony. We have
    stated that “weighing of conflicting evidence is a task
    within the special province of the trial judge who, having
    heard the evidence, is in a better position than we to
    evaluate it.” Pac. Gas & Elec. Co. v. United States, 
    668 F.3d 1346
    , 1353 (Fed. Cir. 2012) (internal quotation
    marks and citations omitted). Where “a trial judge’s
    finding is based on his decision to credit the testimony of
    one of two or more witnesses, each of whom has told a
    coherent and facially plausible story that is not contra-
    dicted by extrinsic evidence, that finding, if not internally
    MERIDIAN ENG’G CO.   v. UNITED STATES                   13
    inconsistent, can virtually never be clear error.” 
    Id. (quoting Anderson
    v. City of Bessemer, 
    470 U.S. 564
    , 575
    (1985)). Here, the Court of Federal Claims reviewed
    testimony submitted by both parties. See, e.g., Meridian
    
    I, 122 Fed. Cl. at 403
    (reviewing parties’ arguments with
    respect to testimony of Dr. Mahar), 409 (reviewing testi-
    mony of Mr. Sutton and the Government’s expert Mr.
    Stephen G. Chickey). 9 It found the Government’s prof-
    fered testimony to be more persuasive, and found that Mr.
    Sutton’s testimony also demonstrated that Meridian had
    reviewed the boring log data that showed the boring holes
    had no bearing capacity due to saturated soils. 
    Id. (citing J.A.
    281−83). Meridian’s argument that its proffered
    testimony should be more persuasive does not leave us
    with a “definite and firm conviction” that the Court of
    Federal Claims made a clear error in its judgment here.
    Ind. Mich. Power 
    Co., 422 F.3d at 1373
    (internal quota-
    tion marks and citation omitted); see PGBA, LLC v.
    United States, 
    389 F.3d 1219
    , 1232 (Fed. Cir. 2004) (find-
    ing no clear error where the Court of Federal Claims’
    denial of injunctive relief was supported by record evi-
    dence and appellant merely asked us “to reweigh the
    relative harms . . . and find in its favor”).
    Third, Meridian contends that the Court of Federal
    Claims erred because its conclusion was based on an
    9    Meridian separately alleges that Mr. Chickey
    “was not accepted by the [Court of Federal Claims] as an
    expert,” such that his testimony should not be relied
    upon. Appellant’s Br. 36. The Court of Federal Claims
    commented in a supplemental hearing during trial, at
    which Mr. Chickey testified, that Mr. Chickey was consid-
    ered an “expert[].” J.A. 3411. Because Meridian does not
    challenge that finding on appeal, we accept the Court of
    Federal Claims’ determination and may rely on Mr.
    Chickey’s testimony.
    14                       MERIDIAN ENG’G CO.   v. UNITED STATES
    improper finding that “a reasonable contractor would
    have conducted an independent soils investigation.”
    Appellant’s Br. 29. Meridian incorrectly summarizes the
    Court of Federal Claims’ findings. The Court of Federal
    Claims did not state that a reasonable contractor would
    make an independent soils investigation. It stated that “a
    reasonable contractor would want to investigate whether
    there were unstable, saturated conditions upstream”
    because the work site was in a floodplain and the plan
    drawings showed saturated soil with no bearing capacity
    as needed for the project, and “[a] site visit also would
    have made these conditions known, because large por-
    tions of saturated, alluvial soil were located ‘100 feet or so’
    away from” the proposed worksite. Meridian I, 122 Fed.
    Cl. at 409. The underlying contractual information avail-
    able to Meridian, along with its ability to visit the site and
    visually assess the ground conditions, support the Court
    of Federal Claims’ finding that, based on the Contract and
    “all information available,” Int’l Tech. 
    Corp., 523 F.3d at 1349
    (internal quotation marks and citation omitted), the
    ground conditions would have been reasonably foreseea-
    ble. Indeed, here, Meridian was aware that “[m]onsoons
    are a common occurrence at the project site during the
    summer months.” Meridian 
    I, 122 Fed. Cl. at 391
    n.13
    (citing Mr. Sutton’s testimony). The Court of Federal
    Claims did not impose an improper requirement for
    investigation of the site conditions beyond what a reason-
    able contractor would undertake here.
    Fourth, Meridian argues that the Government’s “vari-
    ous modifications to address the soils issues” by the CO
    acts as an admission that a Type I DSC claim exists.
    Appellant’s Br. 38; see 
    id. at 38−39.
    However, we have
    stated that “in court litigation, a contractor is not entitled
    to the benefit of any presumption arising from the [CO]’s
    decision. De novo review precludes reliance upon the
    presumed correctness of the decision.” Wilner v. United
    States, 
    24 F.3d 1397
    , 1401 (Fed. Cir. 1994); see Renda
    MERIDIAN ENG’G CO.   v. UNITED STATES                     15
    
    Marine, 509 F.3d at 1378
    n.1 (citing Wilner for the propo-
    sition that “a CO’s decision to award additional compen-
    sation is not binding upon the agency in subsequent CDA
    litigation”). While the CO issued several contract modifi-
    cations following the award of the Contract to Meridian,
    see Meridian 
    I, 122 Fed. Cl. at 387
    −90, the Court of Fed-
    eral Claims explained that Meridian failed to show “by a
    preponderance of the evidence” that all four elements of
    the DSC claim were met, and gave sufficient reasoning for
    its finding, 
    id. at 409;
    see 
    id. at 406−09.
    We conclude the
    Court of Federal Claims did not err in its analysis of the
    second element of the Type I DSC claim.
    D. Meridian’s Defective Pipe and Dewatering Specifica-
    tion Claims
    The Court of Federal Claims found that Meridian’s
    defective pipe and dewatering specification claims were so
    intertwined with its DSC claim that they constituted a
    single claim. 
    Id. at 405.
    Meridian contends that analyz-
    ing its defective pipe and dewatering specification claims
    as part of the DSC analysis was error. Appellant’s
    Br. 40−49. We address each claim in turn.
    1. The Defective Pipe Specification Claim
    Meridian alleges that “[e]ven if Meridian had not en-
    countered a [DSC], it is entirely possible that Meridian
    would be entitled to recover damages incurred as a result
    of the defective pipe specification alone.” 
    Id. at 46.
    We
    disagree with Meridian.
    We have previously stated:
    Although [DSC] and defective specifications
    claims are distinct in theory, they collapse into a
    single claim . . . where the alleged defect in the
    specification is the failure to disclose the alleged
    [DSC]. Where the [DSC] claim and the defective
    specifications claim are so intertwined as to con-
    stitute a single claim, that claim will be governed
    16                       MERIDIAN ENG’G CO.   v. UNITED STATES
    by the specific [DSC] clause and the cases under
    that clause.
    Comtrol, Inc. v. United States, 
    294 F.3d 1357
    , 1362 (Fed.
    Cir. 2002).
    The Specification called for Class IV unlined pipe to
    be used in the sewer relocation project. J.A. 1449; see
    J.A. 1446−47. Upon installation, the Class IV pipe bowed
    and Meridian had to “remove and reinstall” the pipe with
    stronger Class V pipe. J.A. 357. Meridian admits that
    the bowing of the pipe “was undoubtedly exacerbated” by
    the purported DSC, “i.e., the unanticipated subsurface
    soil conditions.” Appellant’s Br. 45 n.7. However, it
    incorrectly states that the “problems . . . were certainly in
    part attributable to the defective specifications,” 
    id., because all
    of the discussions on the inadequacy of the
    Class IV pipe stem from the discovery of the soft subsur-
    face conditions that also form the basis for Meridian’s
    DSC claim, see J.A. 357−58 (providing admission by
    Meridian that the “amount of water coming down”
    through the soil contributed to pipe bowing), 646 (provid-
    ing statement by Meridian’s witness that bowing was
    caused by water coming through “voids of larger grain
    materials” in the soil to “complete[] the liquification of the
    crazy soft material adjacent to the pipe”); see also Appel-
    lant’s Br. 14−15 (citing J.A. 2498 (stating, in Govern-
    ment’s After Action Review, that the “[w]rong [c]lass of
    pipe [was] specified” because it was “not adapted to site
    constraints”)). Therefore, we agree with the Court of
    Federal Claims that Meridian’s defective pipe specifica-
    tion claim is “so intertwined” with its DSC claim as to
    constitute a single claim. 
    Comtrol, 294 F.3d at 1362
    .
    Meridian’s counterarguments are unpersuasive. To
    the extent Meridian argues that the Specification was
    defective because it should have required a contractor to
    provide Class V pipe, see Appellant’s Br. 43 (stating that
    the Arizona Department of Environmental Quality
    MERIDIAN ENG’G CO.   v. UNITED STATES                    17
    (“ADEQ”) “required Class V pipe”), we do not find suffi-
    cient evidence in the record to support this claim. The
    Government’s witness stated that Class IV was “right on
    the line of being adequate,” J.A. 567, and that Class IV
    was not “the wrong pipe” because alterations could have
    been made to compensate for the later-discovered issues
    and satisfy ADEQ requirements, J.A. 496. Meridian has
    not presented evidence that, given the information in the
    Specification, Class V was required. Rather, it claims
    that the purported DSC caused Class IV pipes to be
    inadequate.
    Meridian also contends that the Specification was de-
    fective because the design drawings called for Class V
    pipe, J.A. 1725, such that the discrepancy itself consti-
    tutes error, see Appellant’s Br. 43. This argument is
    without merit. The Contract states that “[i]n case of
    difference between drawings and specifications, the
    specifications shall govern.” J.A. 1156. Meridian does not
    challenge this unambiguous contract language.           See
    generally Appellant’s Br. Moreover, if the documents
    were on their face ambiguous, as Meridian alleges, Merid-
    ian “ha[d] a duty to seek clarification of a patent ambigui-
    ty” on this basis. 
    Comtrol, 294 F.3d at 1365
    (citations
    omitted). It is undisputed that Meridian failed to inquire
    about the discrepancy before bidding. See J.A. 1760
    (providing evidence that Meridian asked for clarification
    post-award of Contract). Therefore, Meridian cannot
    establish the discrepancy as a basis for its DSC claim.
    2. The Defective Dewatering Specification Claim
    In a footnote, the Court of Federal Claims found that
    the dewatering requirements in the Specification were
    performance requirements, rather than design require-
    ments. Meridian 
    I, 122 Fed. Cl. at 406
    −07 n.30; see Blake
    Constr. Co. v. United States, 
    987 F.2d 743
    , 745 (Fed. Cir.
    1993) (detailing differences between design and perfor-
    mance specifications). Therefore, the Court of Federal
    18                      MERIDIAN ENG’G CO.   v. UNITED STATES
    Claims reasoned that Meridian had “discretion to deviate
    from the specifications,” and any deviation from the
    representations in the dewatering specification would not
    be cause for a defective specification claim. Meridian 
    I, 122 Fed. Cl. at 406
    n.30.
    Meridian argues that the dewatering specification is a
    design specification, not a performance specification, and
    therefore the Court of Federal Claims was required to
    consider it separately from a DSC analysis. Appellant’s
    Br. 46−49; see J.A. 1628−31. However, Meridian does not
    contest that the underlying allegations related to the
    purported defective dewatering specification are so inter-
    twined with the DSC claim as to constitute a single claim.
    See generally Appellant’s Br. Nor does Meridian argue
    that Comtrol’s instruction to treat DSC and defective
    specification claims as a single claim would not apply to
    its dewatering specification claim, regardless of whether
    the dewatering specification is categorized as a perfor-
    mance or design specification. See generally 
    id. There- fore,
    we reject the argument that the Court of Federal
    Claims erred in determining that Meridian’s defective
    dewatering specification claim fails under the DSC analy-
    sis. 10
    10  Even if we were to review the dewatering specifi-
    cation’s classification, we would not find that the Court of
    Federal Claims erred.        The dewatering specification
    unequivocally states that “[a]ll permanent construction
    shall be carried on in areas free from water.” J.A. 1629.
    However, it leaves the means by which to accomplish this
    objective to the discretion of the contractor. See J.A. 1629
    (ordering the contractor to submit a proposal “showing the
    method that he proposes to use to divert water” (emphasis
    added)), 1629 (ordering contractor to, in its plans “de-
    scrib[e] the proposed methods to protect each construction
    work area[] from storm runoff” (emphasis added)), 1630
    MERIDIAN ENG’G CO.   v. UNITED STATES                     19
    IV. The Court of Federal Claims Provided Insufficient
    Analysis for Meridian’s Flood Event Claim (Count IV)
    Meridian sought additional damages below that it
    purportedly accrued “due to the [Government’s] modifica-
    tions and specification defects” that caused delay and
    forced Meridian to work in “inclement weather” condi-
    tions. Meridian 
    I, 122 Fed. Cl. at 410
    (internal quotation
    marks and citation omitted); see J.A. 3015−21 (Count IV).
    The Court of Federal Claims denied the claim, finding
    that “the doctrine of accord and satisfaction bars Meridi-
    an’s claims that the [Government] is responsible for costs
    incurred for delays caused by flood events.” Meridian 
    I, 122 Fed. Cl. at 412
    . The Court of Federal Claims based
    its analysis on the accord and satisfaction standard
    discussed in Community Heating & Plumbing Co. v.
    Kelso, which states that:
    Discharge of a claim by accord and satisfaction oc-
    curs when some performance different from that
    which was claimed as due is rendered and such
    substituted performance is accepted by the claim-
    ant as full satisfaction of his claim. However,
    courts may refuse to bar a claim based upon the
    defense of accord and satisfaction where the par-
    ties continue to consider the claim after the execu-
    tion of a release.
    
    987 F.2d 1575
    , 1581 (Fed. Cir. 1993) (citations omitted).
    The Court of Federal Claims found that two bilateral
    contract modifications executed in September 2008, which
    (“The Contractor shall submit the method of dewatering to
    [CO] for his approval.” (emphases added)). Because the
    Specification does not “describe in precise detail the
    materials to be employed and the manner in which the
    work is to be performed,” it is properly considered a
    performance specification. Blake 
    Constr., 987 F.2d at 745
    .
    20                      MERIDIAN ENG’G CO.   v. UNITED STATES
    claimed that the modifications “reflect[] all credits due the
    Government and all debits due the Contractor . . . for all
    costs and markups directly or indirectly attributable for
    the change ordered,” J.A. 3122, 3151, constituted accord
    and satisfaction with respect to the flood events claim,
    Meridian 
    I, 122 Fed. Cl. at 411
    −12. As part of its analy-
    sis, it further found that the Government’s “draft modifi-
    cation,” dated August 2009, which considered additional
    estimates for flood damage, did not negate the findings of
    satisfaction because Meridian did not allege that the
    “internal memorandum was known by Meridian prior to
    discovery,” such that the memorandum could not be
    evidence that “the parties” continued to negotiate the
    claims. 
    Id. at 412.
        Meridian asserts that the defense of accord and satis-
    faction for Count IV 11 should be barred because the
    parties continued to consider the claim after the bilateral
    modifications, and the Court of Federal Claims’ finding to
    11 Meridian also contests the Court of Federal
    Claims’ determination that Count V (Differing Site Condi-
    tions) of Meridian’s Second Amended Complaint was
    barred by accord and satisfaction. See Appellant’s Br.
    54−57. Because we affirm the Court of Federal Claims’
    determinations that Count V fails on its merits, see supra
    Section III, we need not consider the Court of Federal
    Claims’ alternative holdings with respect to the affirma-
    tive defense of accord and satisfaction for Count V, see
    Meridian 
    I, 122 Fed. Cl. at 410
    (holding that “even if,
    arguendo, the sewer line were a [DSC],” certain modifica-
    tions “constituted accord and satisfaction”); see also
    Holland v. United States, 
    621 F.3d 1366
    , 1382 (Fed. Cir.
    2010) (concluding accord and satisfaction barred appel-
    lants’ breach of contract claims “[i]n the alternative” after
    affirming that appellants failed to satisfy elements for
    breach of contract).
    MERIDIAN ENG’G CO.   v. UNITED STATES                   21
    the contrary is clearly erroneous.         See Appellant’s
    Br. 52−53. Meridian contends that the continued drafting
    of Government estimates for flood damage, “even absent
    any ‘negotiations’ with Meridian[,]” indicates that the
    Government “did not believe there had been a release or
    abandonment [of] Meridian’s claims.” 
    Id. at 53.
    Meridian
    further argues the Court of Federal Claims erred because
    it did not use the four-part standard for accord and satis-
    faction as articulated in Holland. See 
    id. at 48−51;
    see
    
    also 621 F.3d at 1382
    . We find the Court of Federal
    Claims provided insufficient analysis of this defense.
    Accord and satisfaction has been “aptly described” as
    a four-part test of “proper subject matter, competent
    parties, meeting of the minds of the parties, and consider-
    ation.” Brock & Blevins Co. v. United States, 
    343 F.2d 951
    , 955 (Ct. Cl. 1965) (internal quotation marks and
    citation omitted); see 
    Holland, 621 F.3d at 1382
    (citing to
    O’Connor v. United States, 
    308 F.3d 1233
    , 1240 (Fed. Cir.
    2002) for the same proposition, which in turn cites to
    Brock & 
    Blevins, 343 F.2d at 955
    ). While Community
    Heating does not use the term “meeting of the minds,” see
    generally 
    987 F.2d 1575
    , its discussion of parties’ contin-
    ued consideration of a claim after execution of a release
    forms part of this inquiry for purposes of the accord and
    satisfaction doctrine, see 
    id. at 1581
    (citing Brock &
    
    Blevins, 343 F.2d at 955
    ). The Court of Federal Claims
    erred in its analysis of the meeting of the minds part of
    the accord and satisfaction claim when it analyzed
    whether the parties “continue[d] to consider the claim
    after execution of a release.” 
    Id. at 1581
    (citation omit-
    ted). 12
    12   The Court of Federal Claims further erred by not
    reviewing the other challenged element of the accord and
    satisfaction claim. See 
    Holland, 621 F.3d at 1382
    . Merid-
    ian contested the elements of “meeting of the minds” and
    22                      MERIDIAN ENG’G CO.   v. UNITED STATES
    The Court of Federal Claims solely considered wheth-
    er Meridian knew of the August 10, 2009 Government
    draft modification in determining whether the parties
    continued to consider the flood events claim. See Meridi-
    an 
    I, 122 Fed. Cl. at 412
    (stating Meridian does not allege
    and the record does not support finding that the Govern-
    ment’s “internal memorandum was known by Meridian
    prior to discovery”). It failed to consider additional evi-
    dence on record showing that the Government directed
    Meridian to submit revised estimates for the flood claim
    on multiple occasions after the execution of the bilateral
    modifications, see J.A. 2486, 2491−93, to which Meridian
    did not respond, see, e.g., J.A. 2492−93 (stating, in a price
    negotiation memorandum on flood event damage dated
    September 2009, that “[n]egotiations could not be entered
    into because the Contractor failed to respond to the re-
    quest for data” such that “[t]he modification will be issued
    unilaterally”). It also did not consider the content of the
    Government’s draft modification and supporting docu-
    mentation to determine the Government’s intent in draft-
    “proper subject matter” below, J.A. 901−02; see King
    Fisher Marine Serv., Inc. v. United States, 
    16 Cl. Ct. 231
    ,
    236−37 (1989) (stating “proper subject matter” requires
    showing the subject matter of the modification is the
    same as that of the disputed claim), and we agree that the
    other two elements have been satisfied, see Mil-Spec
    Contractors, Inc. v. United States, 
    835 F.2d 865
    , 867 (Fed.
    Cir. 1987) (defining the element of “competent parties” to
    require that the officials with whom an agreement is
    made had “authority to bind the Government”); Bogley’s
    Estate v. United States, 
    514 F.2d 1027
    , 1033 (Ct. Cl. 1975)
    (defining the element of “consideration” as “detriment
    incurred by the promisee, or a benefit received by the
    promisor” (citation omitted)). On remand, the Court of
    Federal Claims shall consider meeting of the minds and
    proper subject matter.
    MERIDIAN ENG’G CO.   v. UNITED STATES                    23
    ing the revisions, see J.A. 2484−93, or evidence that
    Meridian submitted additional requests for equitable
    adjustment after the 2008 releases that included adjust-
    ments on the flood events claim, and that the Government
    acknowledged receipt and planned review of those sub-
    mitted adjustments in 2010, see J.A. 2510.
    In our precedent on accord and satisfaction, we have
    never held that the affirmative defense of accord and
    satisfaction may only be barred with evidence of formal
    draft modifications negotiated between parties after a
    release’s execution. Indeed, in several cases, we have
    found accord and satisfaction barred when a contractor
    submitted a proposed claim before the execution of a
    release, and only one party, the Government, responded
    in some fashion after execution. See, e.g., England v.
    Sherman R. Smoot Corp., 
    388 F.3d 844
    , 850 (Fed. Cir.
    2004); Winn-Senter Constr. Co. v. United States, 110 Ct.
    Cl. 34, 65−66 (1948). The predecessor to the Court of
    Federal Claims has also reviewed testimony by one or
    more parties to determine intent with respect to a release
    or considerations of a claim subsequent to a release. See,
    e.g., A & K Plumbing & Mechanical, Inc. v. United States,
    
    1 Cl. Ct. 716
    , 723 (1983), aff’d, 
    795 F.2d 1011
    (Tbl.) (Fed.
    Cir. 1986).
    Thus, the Court of Federal Claims’ assumption that
    Meridian had to have known of the proposed draft modifi-
    cation for the meeting of the minds requirement improp-
    erly applied the law on accord and satisfaction. Our
    precedent on the meeting of the minds inquiry accepts a
    wide range of evidence in its fact-specific consideration.
    Accordingly, we remand for the Court of Federal Claims
    to consider whether the parties reached a meeting of the
    minds on the flood event claims in light of all of the evi-
    dence. See Yankee Atomic Elec. Co. v. United States, 
    536 F.3d 1268
    , 1274 (Fed. Cir. 2008) (remanding for Court of
    Federal Claims to apply a proper legal analysis); Cienega
    Gardens v. United States, 
    503 F.3d 1266
    , 1291 (Fed. Cir.
    24                     MERIDIAN ENG’G CO.   v. UNITED STATES
    2007) (similar). The Court of Federal Claims may con-
    clude that the claims are barred by accord and satisfac-
    tion on remand, but we are unwilling to say, based on the
    Court of Federal Claims’ reasoning, that this is so without
    further review.
    V. The Court of Federal Claims Erred When It Denied
    Meridian’s Unpaid Contract Quantities Claim (Count VI)
    Meridian sought damages for “unpaid contract quan-
    tities” of certain items purchased in excess of original
    contract estimates in the amount of $358,913.63. Meridi-
    an 
    I, 122 Fed. Cl. at 412
    −13; see J.A. 2301. The Court of
    Federal Claims found that Meridian was entitled to
    “payment for items used” but was not entitled to payment
    beyond what the Government had already made because
    the Government “[wa]s entitled to withhold payment.”
    Meridian 
    I, 122 Fed. Cl. at 413
    (quoting FAR 52.232-5
    (Payments Under Fixed-Price Construction Contracts)
    (“[I]f satisfactory progress has not been made, the [CO]
    may retain a maximum of 10 percent of the amount of the
    payment until satisfactory progress is achieved.”)). Me-
    ridian argues that the Court of Federal Claims “erred
    when denying Meridian’s unpaid contract quantities
    claim” because, inter alia, here, “there has been no asser-
    tion of unsatisfactory progress.” Appellant’s Br. 58, 60
    (capitalization modified). It further argues that the
    Government cannot claim its right to set off in withhold-
    ing the unpaid contract quantities because the Court of
    Federal Claims did not properly analyze the amount
    allegedly owed to Meridian in relation to the Govern-
    ment’s proposed set off. See Reply Br. 27−28. We agree
    with Meridian.
    First, the Court of Federal Claims found the Govern-
    ment was entitled to withhold up to 10% of payment
    based on FAR 52.232-5. Meridian 
    I, 122 Fed. Cl. at 413
    .
    However, this FAR provision, while incorporated into the
    Contract, only applies to periods with “progress payment,”
    MERIDIAN ENG’G CO.   v. UNITED STATES                    25
    J.A. 1137, which is not applicable to the unpaid contract
    quantities identified by Meridian, see FAR 52.232-16
    (“The Government will make progress payments to the
    Contractor when requested as work progresses . . . .”); J.A.
    183 (Court of Federal Claims: “[T]he requirements of
    complying with the outline [of payment] as applied to
    progress payments don’t apply.” Government: “Sure.”),
    214 (Court of Federal Claims: “[A]bsent any other indica-
    tion incorporating those payment provisions involving
    estimates of work done, we don’t have an indication in the
    contract to the contractor that the progress payment
    provisions will apply.”). Indeed, the Government aban-
    doned its arguments related to the progress payment
    provisions with respect to the unpaid contract quantities
    after the partial summary judgment phase of the trial.
    Compare J.A. 166−214 (setting forth the Government’s
    arguments on progress payments at the hearing on mo-
    tion for summary judgment), with Def.’s Trial Br. at 82,
    Meridian v. United States, No. 1:11-cv-00492-SGB (Fed.
    Cl. Sept. 18, 2014), ECF No. 122 (hereinafter “Gov’t’s
    Post-Trial Br.”). Moreover, withholding is only allowable
    if “satisfactory progress has not been made” on a contract,
    FAR 52.232-5, but the Government has conceded that
    “unit priced quantity work was generally done” and there
    was no allegation of unsatisfactory performance that
    would merit withholding, Meridian 
    I, 122 Fed. Cl. at 413
    (internal quotation marks and citation omitted); see
    Appellee’s Br. 54 (“[T]he Government acknowledged that
    Meridian was entitled to a small amount of additional
    funds for unpaid quantities associated with channel
    improvements . . . .”). 13
    13   For the same reasoning, the Court of Federal
    Claims’ citation to M.C. & D. Capital Corp. v. United
    States, which applies the provisions of FAR 52.232-5,
    would not apply here, see Meridian 
    I, 122 Fed. Cl. at 413
    26                      MERIDIAN ENG’G CO.   v. UNITED STATES
    The Court of Federal Claims also cited in part to
    Johnson v. All-State Construction, Inc. to support its
    holding supporting the Government’s refusal to pay any of
    the alleged unpaid contract quantities.        Meridian 
    I, 122 Fed. Cl. at 413
    (citing 
    329 F.3d 848
    , 854 (Fed. Cir.
    2003)). The Government on appeal relies on Johnson to
    argue that it “was entitled to set off overpayments.”
    Appellee’s Br. 55. In Johnson, we affirmed the Govern-
    ment’s withholding of certain payments based on the
    Supreme Court’s directive that “[t]he [G]overnment has
    the same right [of set off] which belongs to every creditor,
    to apply the unappropriated moneys of his debtor, in his
    hands, in extinguishment of the debts due to 
    him.” 329 F.3d at 852
    (quoting United States v. Munsey Tr. Co., 
    332 U.S. 234
    , 239 (1947)).
    Meridian does not contest that the Government has a
    common law right to a set off, rather, it argues that “the
    amount of any potential set[]off” was not established by
    the Government at trial because the issue was not ad-
    dressed in the quantum phase. Reply Br. 27. The Gov-
    ernment, which also argued before the Court of Federal
    Claims that the issue would be “resolved at the damages
    portion of trial,” Gov’t’s Post-Trial Br. 82, presented
    evidence in the form of its expert Mr. Stephen Weathers’s
    report that the Government overpaid Meridian for con-
    tract items by $326,642.32, J.A. 3239; see J.A. 3227−39.
    Meridian claimed in detail damages for unpaid contract
    quantities in the amount of $358,913.63. J.A. 3030−32
    (Second Amended Complaint); see J.A. 2301–13 (detailing
    alleged unpaid quantities).
    The Court of Federal Claims did not provide any
    analysis of the parties’ varying cost estimates to explain
    why it found that Meridian had not shown by a prepon-
    (citing 
    948 F.2d 1251
    , 1257 (Fed. Cir. 1991)), because
    satisfactory progress has been made.
    MERIDIAN ENG’G CO.   v. UNITED STATES                    27
    derance of the evidence it was entitled to the amount
    claimed. See Meridian 
    I, 122 Fed. Cl. at 413
    (stating, in a
    conclusory fashion after discussing legal standards for set
    off, “[f]or these reasons, the court has determined that the
    Government did not breach the September 21, 2007
    Contract based on alleged unpaid contract quantities”).
    We are not inclined to resolve facts in the first instance.
    See Cutter v. Wilkinson, 
    544 U.S. 709
    , 718 n.7 (2005)
    (“[W]e are a court of review, not of first view.”). There-
    fore, we find the Court of Federal Claims clearly erred in
    dismissing Meridian’s unpaid contract quantities claim, in
    light of the conflicting information contained in the Sec-
    ond Amended Complaint and Mr. Weathers’s testimony.
    See Dairyland Power Coop. v. United States, 
    645 F.3d 1363
    , 1376 (Fed. Cir. 2011) (remanding damages award
    where Court of Federal Claims erroneously “concluded
    that it was not required to apply” a “detailed inquiry” to a
    factual question it should have decided in the first in-
    stance). Count VI is therefore remanded to the Court of
    Federal Claims for further review.
    CONCLUSION
    We have considered Meridian’s remaining arguments
    and find them unpersuasive. 14 We vacate and remand the
    Court of Federal Claims’ findings in Meridian I on Counts
    IV and VI, reverse and remand the Court of Federal
    14    Meridian states in a conclusory manner that be-
    cause “[i]t is now clear that the [Government] did, indeed,
    fail to pay Meridian even those sums that it agreed Me-
    ridian was owed,” the Court of Federal Claims “erred in
    denying Meridian’s good faith and fair dealing claim
    [(Count XIV)].” Appellant’s Br. 62. “[M]ere statements of
    disagreement with the [trial] court as to the existence of
    factual disputes do not amount to a developed argument.”
    SmithKline 
    Beecham, 439 F.3d at 1320
    . Accordingly, we
    find this argument waived.
    28                       MERIDIAN ENG’G CO.   v. UNITED STATES
    Claims’ interest calculation in Meridian II, and affirm the
    remainder of the decisions. Accordingly, the Final Deci-
    sions of the U.S. Court of Federal Claims are
    AFFIRMED-IN-PART, VACATED-IN-PART,
    REVERSED-IN-PART, AND REMANDED
    COSTS
    Each party shall bear its own costs.
    

Document Info

Docket Number: 2017-1584

Citation Numbers: 885 F.3d 1351

Judges: Prost, Reyna, Wallach

Filed Date: 3/20/2018

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (24)

H.B. Mac, Inc. v. United States , 153 F.3d 1338 ( 1998 )

Cutter v. Wilkinson , 125 S. Ct. 2113 ( 2005 )

United States v. Munsey Trust Co. , 332 U.S. 234 ( 1947 )

Cienega Gardens v. United States , 503 F.3d 1266 ( 2007 )

Holland v. United States , 621 F.3d 1366 ( 2010 )

Dairyland Power Cooperative v. United States , 645 F.3d 1363 ( 2011 )

Pacific Gas & Electric Co. v. United States , 668 F.3d 1346 ( 2012 )

Pgba, LLC v. United States, and Wisconsin Physicians ... , 389 F.3d 1219 ( 2004 )

H.T. Johnson, Acting Secretary of the Navy v. All-State ... , 329 F.3d 848 ( 2003 )

Blake Construction Company, Inc. v. The United States , 987 F.2d 743 ( 1993 )

Gemtron Corp. v. Saint-Gobain Corp. , 572 F.3d 1371 ( 2009 )

Community Heating & Plumbing Company, Inc. v. Admiral Frank ... , 987 F.2d 1575 ( 1993 )

Renda Marine, Inc. v. United States , 509 F.3d 1372 ( 2007 )

Mil-Spec Contractors, Inc. v. The United States , 835 F.2d 865 ( 1987 )

donald-oconnor-and-benjamin-m-aban-donald-n-adaniya-rolando-r , 308 F.3d 1233 ( 2002 )

Brock & Blevins Company, Inc. v. The United States , 343 F.2d 951 ( 1965 )

A & K Plumbing & Mechanical v. United States , 795 F.2d 1011 ( 1986 )

Gordon R. England, Secretary of the Navy v. The Sherman R. ... , 388 F.3d 844 ( 2004 )

Yankee Atomic Electric Co. v. United States , 536 F.3d 1268 ( 2008 )

Indiana Michigan Power Company v. United States , 422 F.3d 1369 ( 2005 )

View All Authorities »