Axia NetMedia Corp. v. Mass. Technology Park Corp. , 889 F.3d 1 ( 2018 )


Menu:
  •           United States Court of Appeals
    For the First Circuit
    No. 17-1607
    AXIA NETMEDIA CORPORATION,
    Plaintiff, Appellant,
    v.
    MASSACHUSETTS TECHNOLOGY PARK CORPORATION,
    d/b/a Massachusetts Technology Collaborative,
    Defendant, Appellee.
    APPEAL FROM THE UNITED STATES DISTRICT COURT
    FOR THE DISTRICT OF MASSACHUSETTS
    [Hon. Timothy S. Hillman, U.S. District Judge]
    Before
    Lynch, Circuit Judge,
    Souter, Associate Justice,*
    and Kayatta, Circuit Judge.
    Brian P. Voke, with whom Adam A. Larson and Campbell Campbell
    Edwards & Conroy PC were on brief, for appellant.
    Robert J. Kaler, with whom Edwin L. Hall and Holland & Knight
    LLP were on brief, for appellee.
    April 25, 2018
    *   Hon. David H. Souter, Associate Justice (Ret.) of the
    Supreme Court of the United States, sitting by designation.
    KAYATTA, Circuit Judge.        This appeal arises out of the
    efforts of the Massachusetts Technology Park Corporation ("MTC")
    to provide broadband network access in western and north central
    Massachusetts.        An   independent    public   instrumentality   of   the
    Commonwealth of Massachusetts, MTC entered into two contracts
    relevant to this appeal.          Under one contract, Axia NGNetworks
    U.S.A., which later changed its name to KCST, Inc. ("KCST"), agreed
    to operate the network that MTC would build.               Under a second
    contract,    KCST's    parent    company,    Axia    NetMedia   Corporation
    ("Axia"), guaranteed KCST's performance.             With the network now
    constructed and operating, MTC on the one hand and KCST and Axia
    on the other hand have lodged claims against each other, and KCST
    has filed for bankruptcy.       By the parties' agreement, those claims
    will be resolved, perhaps in the coming months, by arbitration.
    In the meantime, MTC secured from the United States District Court
    a preliminary injunction ordering Axia, as guarantor of KCST, to
    perform various obligations of KCST while the parties' substantive
    disputes remain unresolved.        Axia appeals and, for the following
    reasons, we affirm on all but one narrow issue, for which we
    remand.
    I.
    We begin with the contract between MTC and KCST pursuant
    to which MTC agreed to build and KCST agreed to operate the new
    - 2 -
    network.    We call this contract the "NOA" (for "network operator
    agreement").
    Under the NOA, KCST agreed to be "responsible for all
    aspects of the management, sales, monitoring, operations, support,
    and maintenance of the MTC network."       KCST also agreed to pay all
    costs of operating the network and an annual oversight fee to MTC.
    In return, KCST retained the network's revenue up to a defined
    threshold, above which it agreed to share the revenue with MTC.
    Article 11 of the NOA calls for binding arbitration of
    any disputes that the parties are unable to resolve on their own.
    Key to this appeal is the final provision of this article.          Titled
    "Continued Performance," Article 11.2 states:
    The Parties agree to continue performing their
    respective obligations under the Agreement
    (including the Wholesale Customer contracts
    and SLAs) while the dispute is being resolved
    unless   and   until  such   obligations   are
    terminated or expire in accordance with the
    provisions of this Agreement, or unless
    otherwise directed by MTC.
    On February 25, 2011, the same day that KCST and MTC
    inked the NOA, Axia and MTC entered into an agreement under which
    Axia guaranteed KCST's obligations in the NOA (we call this
    contract the "Guaranty").       In the Guaranty, Axia promised that,
    "should    Network   Operator   default   in   any   of   its   payment   or
    performance obligations under the Network Operator Agreement,"
    then Axia would "make all such payments and perform all such
    - 3 -
    obligations of the Network Operator," and "fully and punctually
    pay and discharge, as the same become due and payable, any and all
    costs, expenses and liabilities for or in connection with the
    Guaranteed Obligations."   That promise, though, is limited:   "This
    guaranty is limited to and capped at the amount of Four Million
    ($4,000,000) US Dollars, and should Guarantor advance to MTC funds
    up to said amount, Guarantor shall have no further obligation or
    liability under this Agreement."
    The Guaranty also addresses dispute resolution.      Under
    the heading "Governing Law, Jurisdiction, Venue and Forum," the
    Guaranty allows MTC, at its sole election, to file a demand for
    arbitration to resolve any dispute that the parties fail to resolve
    through mediation.   The Guaranty contains no express statement
    about what, if anything, Axia must do pending the resolution of
    any dispute.   It does, though, state:      "All other provisions
    relating to dispute resolution or arbitration contained in the
    Network Operator Agreement are herein incorporated by reference."
    MTC and KCST's relationship soured by the time MTC began
    turning over the network to KCST in late 2013.   KCST claimed that
    the network MTC delivered was not the one it had been promised.
    KCST's specific grievance was that the number of "Community Anchor
    Institutions," dubbed "CAIs," that had been built was too small.
    CAIs are facilities such as schools and municipal buildings that,
    according to Axia, are directly connected to the network, serve as
    - 4 -
    hubs of connectivity for extending the network to other customers,
    and are critical to the network's financial viability (and thus to
    KCST's net revenues).        As the dispute sharpened in July of 2014,
    KCST notified MTC that, pending the resolution of the dispute,
    KCST would be "withholding all fees and payments to or on behalf
    of MTC."   This notification led MTC to obtain an injunction from
    a Massachusetts state court requiring KCST, in accord with the
    NOA's continued performance provision, to continue performing its
    obligations     (including      making    payments)     during   the    dispute.
    During the following two years, the dispute simmered, but neither
    party pushed it toward resolution by arbitration.
    In 2016, a Swiss investment firm acquired a controlling
    position in Axia.     Because the Federal Communications Commission
    had granted authorization to KCST to operate the network, and this
    authorization    could    not    be   transferred     without    FCC   approval,
    KCST's operation of the network, as a wholly-owned subsidiary of
    Axia, apparently would have added a hurdle to the acquisition's
    regulatory approval.       Therefore, to facilitate the acquisition,
    Axia transferred the stock of KCST into a trust.              The FCC approved
    this transaction.        MTC, which had not participated in the FCC
    proceeding, filed for reconsideration, which the FCC denied.
    According to MTC, KCST then made a number of changes to
    the website KCST maintained for the broadband network.                 Claiming
    the   website   changes    to    be   a   breach   of   the   NOA's    continued
    - 5 -
    performance provision, MTC went to Massachusetts state court to
    enforce the previously issued preliminary injunction.                    The next
    day,   KCST    declared     bankruptcy.         Under   section 362(a)      of   the
    Bankruptcy Code, the filing of Chapter 11 bankruptcy stayed MTC's
    state court action.         See 
    11 U.S.C. § 362
    (a).
    KCST apparently continued to perform what it viewed as
    its operational obligations, but ceased to make many of the
    payments that it was obligated to make under the NOA. Anticipating
    a claim against it as guarantor, Axia preemptively filed suit in
    federal district court, seeking a declaratory judgment that MTC
    had materially breached the NOA by failing to build sufficient
    CAIs, and that, because of that breach, Axia had no responsibility
    under the Guaranty.          We will refer to this disagreement between
    MTC    and    Axia    as   "the    underlying    dispute."      MTC   has     since
    successfully demanded arbitration of the underlying dispute, to be
    held in the coming months.               MTC also filed in this lawsuit
    commenced by Axia a motion for a temporary restraining order and
    preliminary injunction requiring Axia as guarantor to perform
    KCST's obligations under the NOA while the arbitration of the
    underlying dispute is pending.          We will call this disagreement and
    its ancillary issues the "continued performance dispute."
    After    conducting     evidentiary       hearings   and    hearing
    argument      concerning     the    continued     performance      dispute,      the
    district court issued a preliminary injunction.                    In its order
    - 6 -
    implementing   the   preliminary    injunction,    the   district   court
    imposed a series of requirements on Axia.         It required Axia both
    to pay KCST's unmet payment obligations and to continue to provide,
    through Axia's affiliates, the "same level" of services to the
    network that those affiliates were currently providing.        The order
    also required Axia to provide assistance in transferring the
    services provided by Axia's affiliates to a new network operator,
    should MTC so request.    As part of this transfer assistance, the
    order required Axia to provide to MTC all information concerning
    the broadband network in Axia's control.     Axia opposed issuance of
    the order, and now asks that we set it aside in toto.
    II.
    The district court employed the familiar four-factor
    test for a preliminary injunction, analyzing the likelihood of
    success on the merits, the presence of irreparable harm absent
    relief, the balance of the equities, and the public interest.        See
    Arborjet, Inc. v. Rainbow Treecare Sci. Advancements, Inc., 
    794 F.3d 168
    , 171 (1st Cir. 2015).        Although we review the district
    court's decision to grant a preliminary injunction for abuse of
    discretion, we review its findings of fact for clear error and its
    conclusions of law de novo.    See OfficeMax, Inc. v. Levesque, 
    658 F.3d 94
    , 97 (1st Cir. 2011).
    - 7 -
    A.
    1.
    Axia's lead argument on appeal is that the district court
    focused on the wrong dispute in assessing the likelihood of success
    on the merits.         In evaluating this first prong of the test for
    preliminary injunctive relief, the district court trained its
    focus on whether MTC was likely to succeed in its argument that
    the Guaranty imposed an obligation on Axia to continue performing
    during the dispute resolution process.            In other words, the court
    assessed the likely outcome of the continued performance dispute.
    Axia    contends    that      the   district   court    should      have    instead
    determined whether MTC was likely to succeed in the parties'
    underlying dispute about whether MTC's alleged breaches of the NOA
    freed Axia of any obligations under the Guaranty.
    Axia's   argument     misapprehends      the    substance     of     the
    contractual undertaking that MTC seeks to enforce.                    MTC alleges
    that Axia promised to continue performance under the Guaranty even
    while a dispute exists as to whether MTC has breached the NOA.                     In
    the    face   of   such   a   claim,   MTC's    success      does   not    hinge    on
    establishing that it will prevail in the underlying dispute.
    Rather, to succeed, it need prevail in establishing that Axia bound
    itself to perform pendente lite.               The district court therefore
    quite properly focused its likelihood of success analysis upon the
    likelihood that MTC would succeed in the continued performance
    - 8 -
    dispute, i.e., on its claim that Axia must perform until the
    underlying dispute is resolved, however it might be resolved.        See
    Guinness-Harp Corp. v. Jos. Schlitz Brewing Co., 
    613 F.2d 468
    , 471
    n.1 (2d Cir. 1980) (noting the "adverse consequences [that] would
    occur" should, "for the purpose of assessing probable success on
    the merits, the merits were incorrectly considered to be the
    ultimate issue of contract termination," when that issue was
    subject to arbitration (internal citation omitted)); see also
    Peabody Coalsales Co. v. Tampa Elec. Co., 
    36 F.3d 46
    , 47-48 (8th
    Cir. 1994) (granting injunctive relief pending the resolution of
    a dispute in arbitration based on a similar contractual provision).
    To conclude otherwise would be to turn a promise to perform while
    a dispute is pending into a lesser promise, specifically, one to
    perform while a dispute is pending only if the promisor is likely
    to lose the dispute.      And in this case, it would require the
    district court to opine on the merits of a dispute that will be
    decided by an arbitrator.
    Of course, one can imagine a case in which the line
    between deciding whether a party has promised to perform and
    deciding the merits of the parties' underlying dispute might not
    be so sharp.    When a court orders a party to perform, it must
    define "performance."    In so doing, it might run into a dispute
    about what performance is.      In this very case, for example, we
    address,   infra,   whether   performance   by   Axia   includes   making
    - 9 -
    expenditures in excess of $4 million.      As we will explain, we
    accept Axia's argument that any order to spend in excess of that
    amount does indeed need to be justified (and is not) by an analysis
    of the underlying merits of the parties' positions on that issue.
    But that issue is ancillary to the merits of the parties' pending
    arbitration and, as became clear at oral argument, the parties do
    not dispute the meaning of the $4 million cap.   We therefore need
    not -- and do not -- decide how a court asked to enforce a promise
    to perform pending arbitration should proceed in assessing the
    likelihood of success on the merits if presented with a material
    dispute concerning what performance in ordinary course entails.
    Rather, we conclude more narrowly that, on the record in this case,
    the district court did not err by training its likelihood of
    success analysis on the question of whether Axia promised to
    continue performance until the arbitrator resolves the dispute.
    In so concluding, we do not overlook Axia's argument
    that we must assess the merits of the underlying dispute because
    Axia seeks rescission as a result of MTC's alleged breaches.
    Axia's reasoning seems to be that if its rescission claim is likely
    to prevail, then it is relieved of all its promises -- including
    any promise to perform pendente lite.   In rejecting this argument,
    we rely on the case law rejecting identical arguments aimed at
    avoiding promises to arbitrate. In brief, this case law recognizes
    that even claims for rescission based on fraud do not nullify an
    - 10 -
    agreement to arbitrate unless the arbitration agreement itself
    (rather than the contract as a whole) was procured by fraud.             See
    Farnsworth v. Towboat Nantucket Sound, Inc., 
    790 F.3d 90
    , 96 (1st
    Cir. 2015) (citing, among other cases, Prima Paint Corp. v. Flood
    & Conklin Mfg. Co., 
    388 U.S. 395
    , 402-04 (1967)); see also Rent-
    A-Ctr., W., Inc. v. Jackson, 
    561 U.S. 63
    , 71 (2010) ("[E]ven
    where . . . the alleged fraud that induced the whole contract
    equally induced the agreement to arbitrate[,] . . . we nonetheless
    require the basis of the challenge to be directed specifically to
    the agreement to arbitrate before the court will intervene.");
    Dialysis Access Ctr., LLC v. RMS Lifeline, Inc., 
    638 F.3d 367
    , 383
    (1st Cir. 2011) (affirming the district court's decision to compel
    arbitration because, "[a]lthough Appellants have challenged the
    validity of the [agreement] as a whole, they have not specifically
    challenged the validity of the Arbitration Clause itself").               In
    this contract, the promise to perform while arbitration proceeds
    qualifies easily as a term of the agreement that describes the
    manner in which the parties' dispute will proceed to arbitration.
    See Peabody Coalsales Co., 
    36 F.3d at
    48 (citing the Federal
    Arbitration Act's requirement that a court order the parties "to
    proceed   to   arbitration   in   accordance   with   the   terms   of   the
    agreement," 
    9 U.S.C. § 4
    ).        So, since there is no claim by Axia
    that its dispute resolution promise was itself obtained by fraud
    - 11 -
    or is otherwise invalid, the fact that Axia will ask the arbitrator
    to rescind the Guaranty is of no moment in this particular case.
    2.
    Having thus confirmed that the district court trained
    its "likelihood of success" assessment on the proper question, we
    turn next to the merits of that question.          But before doing so, we
    must address a threshold issue relevant to our review.
    Although   the   injunction      in   this   case    is   styled   as
    "preliminary," once arbitration is completed, any possible need to
    compel performance pendente lite disappears.              For that reason,
    some   appellate   courts   review   such    preliminary       injunctions    as
    either permanent injunctions or orders for specific performance.
    See Nemer Jeep-Eagle, Inc. v. Jeep-Eagle Sales Corp., 
    992 F.2d 430
    , 433-34 (2d Cir. 1993); Guinness-Harp Corp., 
    613 F.2d at 471
    .
    This can matter in some cases because a preliminary injunction
    rests on the reasonableness of a prediction concerning the final
    outcome while a permanent injunction, or order granting a request
    for specific performance, rests on the correctness of the final
    outcome.
    Nevertheless, in this particular case we need not decide
    whether the order should be treated as a permanent injunction.
    For one, no party raises or challenges the district court's
    decision to proceed with the motion as a request for a preliminary
    injunction.   More importantly, as we will explain, in this case
    - 12 -
    the pivotal question is a question of law, i.e., how to interpret
    a written contract concerning which neither party relies on any
    relevant extrinsic evidence.             See OfficeMax, Inc., 
    658 F.3d at 97
    .
    We decide that question of law de novo, even in reviewing a
    preliminary injunction.            
    Id.
       So, in short, our answer would not
    differ depending on whether we treat the injunction as preliminary
    or final.
    We therefore turn our attention to that question of law:
    Does the Guaranty require Axia to perform its obligations as
    guarantor while the underlying dispute is being resolved?                         The
    last sentence of the Guaranty incorporates by reference "[a]ll
    other provisions relating to dispute resolution or arbitration
    contained in the Network Operator Agreement."                   As we have noted,
    the NOA does indeed contain an article titled "Dispute Resolution."
    Article 11.1.1 states:            "Any dispute between the Parties either
    with       respect   to   the   interpretation     of    any   provision    of    the
    Agreement or with respect to the performance by Network Operator
    or    by    MTC   hereunder     shall    be   resolved   as    specified    in    this
    Article 11 . . . ."             Article 11.2 then clearly states that the
    "Parties agree to continue performing their respective obligations
    under the Agreement . . . while the dispute is being resolved."
    So,    a    straightforward      incorporation     of    Article 11.2      into   the
    Guaranty would seemingly mean that the "Parties" to the Guaranty
    (i.e., MTC and Axia) "agree to continue performing."
    - 13 -
    Axia nevertheless argues that Article 11.2 of the NOA
    only imposes a continued performance obligation on the "Network
    Operator,"    and     because    Axia    is     not    operating      the   network,
    incorporation of Article 11.2 does not impose any such obligation
    on Axia.     This argument makes no sense.              Article 11.2 imposes a
    continuing obligation requirement on the "Parties."                         In other
    words, like every other provision in the NOA (or in pretty much
    any contract), it imposes obligations on the parties to that
    contract.     By incorporating that provision of the NOA into the
    Guaranty, the drafters of the Guaranty effectively adopted the
    provision    as   their   own,    at    which    point       the   "Parties"   would
    obviously mean the parties to the Guaranty.                   For example, suppose
    the   NOA    stated    that     "the    parties       will     keep   any    dispute
    confidential,"      and   the    Guaranty       said     it    incorporated     this
    confidentiality clause.         As incorporated, such a clause would not
    simply state in the Guaranty what the parties to the NOA will do.
    Rather, it would become a promise of the parties to the Guaranty.
    Similarly, here, when the parties to the Guaranty agree that they
    incorporate a clause saying that the "Parties agree to perform
    their respective obligations under the Agreement . . . while a
    dispute is being resolved," then that incorporation plainly means
    that the parties to the incorporating contract (i.e., the Guaranty)
    agree to perform their obligations under that contract pending
    resolution of any dispute.         Otherwise, the incorporation would do
    - 14 -
    no work.    See McMahon v. Monarch Life Ins. Co., 
    186 N.E.2d 827
    ,
    830 (Mass. 1962) ("[A] contract is to be construed to give a
    reasonable effect to each of its provisions.").
    For the foregoing reasons, we find that the district
    court did not err in finding that MTC will likely prevail on its
    claim that Axia is obligated to continue performing its obligations
    as guarantor until the parties' underlying dispute is resolved.1
    B.
    In addition to challenging the decision to issue a
    preliminary injunction, Axia also presents a litany of challenges
    to the substance of the injunction.     We address each challenge in
    turn.
    1.
    Axia first contends that only KCST has FCC authorization
    to operate the network, hence the district court cannot order Axia
    to do so without violating FCC regulations.      The premise behind
    this argument does not fit the facts as the parties describe them.
    KCST, while in bankruptcy, has not rejected the NOA and continues
    as network operator.   Under a Transitional Services Agreement, two
    Axia affiliates, Axia SuperNet Ltd. and Axia Connect Ltd., provide
    essential services for operating the network.      That arrangement
    was itself disclosed to the FCC at the time FCC approval was
    1
    We address, below, the possibility that the district court
    may have overshot the mark on the $4 million cap.
    - 15 -
    obtained, when Axia told the FCC that KCST would "continue to use
    the technical, security, and customer support services currently
    provided to [KCST] by such affiliates of Axia."        The district
    court's order simply requires Axia to maintain this status quo by
    continuing "to provide, through its affiliates Axia SuperNet Ltd.
    and Axia Connect Ltd., the same level of service to MTC's Network
    that those affiliates are currently providing, including all the
    technical, administrative, and operational support services they
    are currently providing for the 123 Network."    The injunction also
    requires Axia as guarantor to make payments that KCST previously
    made under the NOA, but Axia makes no argument that the making of
    payments would constitute an activity prohibited by the FCC.     To
    the contrary, the payments would seem to facilitate maintenance -
    - rather than interruption -- of the FCC-approved arrangement while
    the underlying dispute is resolved.
    Axia posits that much of this might change if KCST were
    to stop performing at all as network operator.    Why this would be
    so is not readily apparent.    In any event, KCST apparently now
    continues to serve as network operator.   The bankruptcy court has
    also lifted the automatic stay of actions seeking relief involving
    KCST with regard to any action or order "as may be necessary to
    enforce the preliminary injunction and any related orders."     And
    any lack of funds that might otherwise keep KCST from continuing
    to serve as network operator would seem to be taken care of by the
    - 16 -
    compelled payments of Axia.            On such a record, we see no need to
    accept Axia's invitation to speculate about a hypothetical change
    to   the    status   quo   in    the   short    time   remaining    before      the
    arbitration is completed.         This is especially so where that change
    to the status quo could take many forms, the differences among
    which could be dispositive to our resolution.              And it is even more
    so where the parties point us to little substantive law that would
    govern our resolution of these hypothetical situations.
    We similarly see no merit in Axia's contention that the
    FCC's decision denying reconsideration sought by MTC precludes MTC
    "from      conducting    any    further      litigation    challenging       KCST's
    operation     of   MTC's   Network"     on   the   basis   of   issue   or    claim
    preclusion.        Issue preclusion would only apply in this case if
    Axia could show, among other things, that the two proceedings
    involved "the same issue of law or fact."                  See Vargas-Colón v.
    Fundación Damas, Inc., 
    864 F.3d 14
    , 26 (1st Cir. 2017) (quoting
    Robb Evans & Assocs. v. United States, 
    850 F.3d 24
    , 32 (1st Cir.
    2017)).       But the issues in the FCC's reconsideration -- the
    procedural propriety of MTC's motion and whether reconsideration
    of the FCC's prior decision "is required in the public interest"
    -- are squarely different than the issues in this appeal.                    And if
    Axia instead intends its argument to sound in claim preclusion, it
    fares no better.        MTC's motion for reconsideration before the FCC
    and its current attempt to enforce the Guaranty's contractual
    - 17 -
    provisions are not "causes of action . . . sufficiently identical
    or related for claim preclusion purposes."              Airframe Sys., Inc. v.
    Raytheon, Co., 
    601 F.3d 9
    , 15 (1st Cir. 2010).
    2.
    Axia    next    contends    that    the    district    court's   order
    imposes on it a greater financial burden than permitted by the
    Guaranty.      Axia's      liability    under   the     Guaranty    is   expressly
    "limited to and capped at" $4 million.                The Guaranty thus states
    that, "should [Axia] advance to MTC funds up to said amount, [Axia]
    shall   have   no    further     obligation      or     liability    under    this
    Agreement."    The parties appear to have no dispute concerning the
    meaning of this cap.           Rather, they disagree about whether the
    district court's order respects that cap.                 The order certainly
    acknowledges the cap by providing that, once Axia's payments under
    the Guaranty reach $4 million, the order's provisions requiring
    Axia to "pay all invoices" and provide affiliate services "shall
    no longer have effect."          But, the order also requires Axia to
    provide commercially reasonable transfer assistance, should MTC so
    request. And in connection with those services, the order requires
    Axia to provide MTC with all information concerning the network in
    Axia's possession.         These latter two requirements are not subject
    to the order's $4 million limitation.                 Rather, they are limited
    only in their duration. The order provides that Axia's obligations
    - 18 -
    under these two requirements will cease after providing transfer
    assistance for one year.
    Axia   contends   that    complying     with   the   order    could
    therefore require Axia to expend more than $4 million in total.
    This might occur, for example, should Axia hit the $4 million cap
    but have remaining transfer assistance obligations.
    We agree with Axia that, under certain circumstances,
    without any change to the status quo, the district court's order
    could subject Axia to burdens that exceed the cap.               MTC argues
    that the unlimited obligation to provide transfer assistance and
    information for a specific period of time is justified by the fact
    that the NOA so obligates KCST, and Axia as guarantor must perform
    KCST's   obligations.    But,   as    we   have    explained,   and     as    MTC
    acknowledges, the Guaranty comes with an express cap.            So, on this
    issue, the order modifies rather than merely enforces Axia's
    promise to perform during the dispute.
    Therefore,   we   remand    to    the    district    court        with
    instructions to amend the order so as to make clear that Axia's
    obligations terminate once it has properly expended $4 million in
    complying with the Guaranty.2        For the sake of clarity, we note
    that only Axia's net costs properly attributed to its performance
    2 We express no opinion on what application, if any, the cap
    would have to a liability arising from a source other than properly
    complying with the Guaranty.
    - 19 -
    under the Guaranty count toward the $4 million cap, but leave it
    to the district court to resolve, should the issue arise, the
    precise contours of this requirement.
    3.
    Axia also argues that the injunction fails to abide by
    the requirements imposed by Rule 65 of the Federal Rules of Civil
    Procedure.     Axia contends that the court both failed to order a
    sufficient bond under Rule 65(c), and failed to state the terms of
    the order "specifically," as required by Rule 65(d)(1)(B).
    Under   Rule 65(c),   a    court   may   issue   a    preliminary
    injunction "only if the movant gives security in an amount that
    the court considers proper to pay the costs and damages sustained
    by any party found to have been wrongfully enjoined."                 Fed. R.
    Civ. P. 65(c).       The purpose of such a bond is to ensure that the
    enjoined party may readily be compensated for the costs incurred
    as a result of the injunction should it later be determined that
    it was wrongfully enjoined.        See Global NAPs, Inc. v. Verizon New
    England, Inc., 
    489 F.3d 13
    , 20-21 (1st Cir. 2007).            The bond also
    serves to provide notice to the moving party as to the "maximum
    extent of its potential liability, since the amount of the bond
    'is the limit of the damages the [enjoined party] can obtain for
    a wrongful injunction.'"        
    Id. at 21
     (quoting Continuum Co. v.
    Incepts, Inc., 
    873 F.2d 801
    , 803 (5th Cir. 1989)).                By providing
    that the bond should be "in an amount that the court considers
    - 20 -
    proper,"   Fed.    R.    Civ.   P.   65(c),    the   Federal   Rules    of   Civil
    Procedure vest the district court with "wide discretion," Ferguson
    v. Tabah, 
    288 F.2d 665
    , 675 (2d Cir. 1961).3              In this case, after
    holding a hearing, the district court required MTC to post a $4
    million bond.
    Axia first argues that the district court abused its
    discretion because Axia could plausibly expend more than $4 million
    in complying with the order. But, because we remand on this aspect
    of the order, as explained above, this challenge is now moot.                  And
    even if it were not, Axia does not point us to any authority, nor
    are we aware of any, that establishes the proposition that it is
    not within the district court's discretion to require a bond for
    less than the upper bound of what the enjoined party could, in
    theory, expend.         We also note that the bond is only intended to
    protect the enjoined party pending the outcome of the underlying
    dispute.   See Global NAPs, Inc., 
    489 F.3d at 21-22
    .                   Thus, the
    district   court    need    only     require   "an   amount    that    the   court
    considers proper," Fed. R. Civ. P. 65(c), for the time between
    when it issues the injunction and when the arbitration will likely
    3  The Second Circuit in Ferguson considered a version of the
    rule that read, "in such sums as the court deems proper." The
    rule has been amended to now read, "in an amount that the court
    considers proper." We do not think that these minor changes alter
    the discretion granted to the district court.
    - 21 -
    conclude.      The sum is not intended to cover the enjoined party's
    contractual liability beyond the scope of the injunction.
    Axia further argues that it was an abuse of discretion
    for the district court not to account for the possibility that,
    after handing over the network passwords to MTC, as the district
    court later required, Axia could be liable should something happen
    to the network.      We do not think this argument gets off the ground.
    For one, Axia has not explained how it might incur liability as a
    result of giving the passwords to MTC beyond what it would risk as
    a result of KCST's normal operation of the network.                  And if Axia's
    argument is simply that it might incur liability from its own
    conduct, or that of KCST, we do not see how the court could
    plausibly be required to take such contentions into account in
    calculating     a    bond.        For    example,   should   a   court     require   a
    distributor     to    perform      its    distribution    obligations      during    a
    dispute, we do not think that the district court would be obligated
    to require the moving party to post a bond that covers the
    potential      liability          that    might     be   incurred     should       the
    distributor's drivers cause an accident on the job.
    Axia next contends that the order's requirement that
    Axia "continue to provide, through its affiliates . . . the same
    level of service that those affiliates are currently providing"
    runs   afoul    of    the    requirement       in    Rule 65(d)(1)(B)       that     an
    injunction     "state       its    terms     specifically."         Fed.    R.     Civ.
    - 22 -
    P. 65(d)(1)(B).     The order, Axia argues, is too vague to pass
    scrutiny under this standard, and renders Axia vulnerable to
    contempt proceedings.     We disagree.
    The "specificity requirements are not 'merely technical'
    but are 'designed to prevent uncertainty and confusion and to avoid
    basing   a    'contempt   citation   on   a   decree   too   vague   to   be
    understood.'"    NBA Props. v. Gold, 
    895 F.2d 30
    , 32 (1st Cir. 1990)
    (alterations omitted) (quoting Schmidt v. Lessard, 
    414 U.S. 473
    ,
    476 (1974)).     The purpose of the specificity requirement is to
    protect "the elementary due process requirement of notice."          Scott
    v. Schedler, 
    826 F.3d 207
    , 212 (5th Cir. 2016) (per curiam)
    (quoting U.S. Steel Corp. v. United Mine Workers of Am., 
    519 F.2d 1236
    , 1246 (5th Cir. 1975)).     An "injunction must simply be framed
    so that those enjoined will know what conduct the court has
    prohibited."    Meyer v. Brown & Root Constr. Co., 
    661 F.2d 369
    , 373
    (5th Cir. 1981) (citing Int'l Longshoremen's Ass'n v. Phila. Marine
    Trade Ass'n, 
    389 U.S. 64
    , 75 (1967)).              Thus, an order that
    "judgment . . . is entered in accordance" with an opinion that
    merely states that the plaintiff is "entitled to . . . injunctive
    relief," without more, fails the test.        Mass. Ass'n of Older Ams.
    v. Comm'r of Pub. Welfare, 
    803 F.2d 35
    , 40 (1st Cir. 1986)
    (alteration in original) (quoting Schmidt, 
    414 U.S. at 474
    ).          But,
    conversely, "elaborate detail is unnecessary."         Islander E. Rental
    - 23 -
    Program v. Barfield, 
    145 F.3d 359
    , 
    1998 WL 307564
    , at *4 (5th Cir.
    Mar. 24, 1998) (per curiam) (unpublished).
    This order passes muster.    We see no reason why Axia
    does not know, or could not readily discern, the precise level of
    services its affiliates had been providing.   Nor has Axia advanced
    any reason as to why it may be in the dark.   Further, we note that
    the affiliates' responsibilities to KCST are spelled out in a
    thirty-two page "Transitional Services Agreement."      And, to the
    degree that Axia's concern stems from a worry that its good faith
    attempts to comply with the order nevertheless render it vulnerable
    to contempt proceedings, our case law accounts for such concerns
    by cautioning courts against finding contempt when faced with
    genuine ambiguities about an order's scope.    See NBA Props., 
    895 F.2d at 32
     ("[W]e must read any 'ambiguities' or 'omissions' in
    such a court order as 'redound[ing] to the benefit of the person
    charged with contempt.'" (quoting Ford v. Kammerer, 
    450 F.2d 279
    ,
    280 (3d Cir. 1971) (per curiam))).
    4.
    Axia's remaining challenges fare no better.   Axia argued
    in its briefs that the order runs afoul of the automatic bankruptcy
    stay's prohibition on actions that "exercise control over property
    of the estate."    
    11 U.S.C. § 362
    (a)(3).     On January 18, 2018,
    however, the bankruptcy court lifted the stay to allow the district
    court to take any actions necessary to enforce the preliminary
    - 24 -
    injunction.      This    action     moots    Axia's   challenge   under      the
    bankruptcy stay.
    To the degree that Axia contends that the district court,
    in granting MTC's motion for a preliminary injunction, abused its
    discretion in finding irreparable harm to MTC or in its balance of
    equities analysis, Axia has simply pointed us to nothing that would
    cause us to conclude that the district court went beyond the bounds
    of its discretion.       The district court conducted several days of
    hearings   before      reaching   its   conclusions,     during      which   it
    considered many of the same arguments Axia now advances on appeal.
    We see no abuse of discretion in the district court's conclusions.
    We have considered the remaining arguable challenges
    sprinkled without any development through Axia's brief, and find
    them likely without merit, and certainly waived. See United States
    v. Zannino, 
    895 F.2d 1
    , 17 (1st Cir. 1990) ("[I]ssues adverted to
    in a perfunctory manner, unaccompanied by some effort at developed
    argumentation, are deemed waived.").
    III.
    For   the    foregoing    reasons,    we   affirm   the    district
    court's judgment as modified by this opinion, and remand to the
    district court for the limited purpose of amending the order to
    make clear that Axia's obligations terminate once Axia itself has
    properly expended $4 million in complying with the Guaranty.
    - 25 -