Clean Air Council, M.M. deMarteleire and M.S. Bomstein v. Sunoco Pipeline, L.P. , 185 A.3d 478 ( 2018 )


Menu:
  •         IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Clean Air Council,                       :
    Margaret M. deMarteleire, and            :
    Michael S. Bomstein                      :
    :
    v.                           :   No. 1112 C.D. 2017
    :   Argued: February 7, 2018
    Sunoco Pipeline L.P.,                    :
    Appellant       :
    BEFORE: HONORABLE MARY HANNAH LEAVITT, President Judge
    HONORABLE RENÉE COHN JUBELIRER, Judge
    HONORABLE P. KEVIN BROBSON, Judge
    HONORABLE PATRICIA A. McCULLOUGH, Judge
    HONORABLE ANNE E. COVEY, Judge
    HONORABLE MICHAEL H. WOJCIK, Judge
    HONORABLE ELLEN CEISLER, Judge
    OPINION
    BY JUDGE BROBSON                         FILED: April 30, 2018
    I. INTRODUCTION
    This appeal arises out of an action for declaratory and injunctive relief
    brought by Clean Air Council and two of its members, Margaret M. deMarteleire
    and Michael S. Bomstein (collectively, Plaintiffs), in the Court of Common Pleas of
    Philadelphia County (trial court) against Sunoco Pipeline L.P. (Sunoco). By Order
    dated May 25, 2017, the trial court, by the Honorable Linda S. Carpenter, denied
    Sunoco’s motion for summary judgment. The trial court, by the Honorable Mary D.
    Colins, issued an amending order on July 13, 2017, pursuant to Section 702(b) of
    the Judicial Code, 42 Pa. C.S. § 702(b),1 certifying the following controlling
    questions of law for immediate appellate review:
    (a) Are Plaintiffs’ claims outside the subject matter
    jurisdiction of the [trial court] or otherwise
    non-justiciable as collateral attacks on the Public
    Utility Commission’s (PUC) determinations?
    (b) Are Plaintiffs’ claims based upon Pennsylvania
    Constitution Article I, Section 27 also outside the
    subject matter jurisdiction of the [trial court] or
    otherwise non-justiciable as collateral attacks on the
    Department of Environmental Protection’s issuance of
    environmental permits to [Sunoco] for the pipelines?
    (c) Do Plaintiffs, as non-condemnees, lack standing to
    pursue their claims?
    (d) Are Plaintiffs’ due process claims legally insufficient
    because the procedural provisions of the Eminent
    Domain Code[2] and remedies provided by the Public
    Utility Code[3] satisfy any due process requirements?
    Sunoco thereafter filed a petition for permission to appeal pursuant to
    Rule 1311(b) of the Pennsylvania Rules of Appellate Procedure, which this Court
    granted by its Order of September 27, 2017. In so doing, we indicated that we would
    consider the above questions certified by the trial court, along with the question of
    1
    Section 702(b) of the Judicial Code provides:
    When a court . . . , in making an interlocutory order in a matter in which its final
    order would be within the jurisdiction of an appellate court, shall be of the opinion
    that such order involves a controlling question of law as to which there is substantial
    ground for difference of opinion and that an immediate appeal from the order may
    materially advance the ultimate termination of the matter, it shall so state in such
    order. The appellate court may thereupon, in its discretion, permit an appeal to be
    taken from such interlocutory order.
    2
    26 Pa. C.S. §§ 101-1106.
    3
    66 Pa. C.S. §§ 101-3316.
    2
    whether Sunoco is “the Commonwealth,” such that it can be sued for violating the
    duties of the “trustee” under Article I, Section 27 of the Pennsylvania Constitution.4
    II. BACKGROUND
    Plaintiffs commenced this action in the trial court by Complaint filed
    on August 27, 2015. (Reproduced Record (R.R.) 59a-398a.) In their eight-count
    Complaint,5 Plaintiffs challenge the right, authority, and entitlement of Sunoco to
    exercise the power of eminent domain in order to construct two natural gas liquid
    (NGL) pipelines, known as Mariner East 1 (ME1) and Mariner East 2 (ME2), across
    the Commonwealth of Pennsylvania as part of Sunoco’s Mariner East Project.
    Ms. deMarteleire and Mr. Bomstein are husband and wife, jointly residing at their
    home in Media, Delaware County, Pennsylvania. (Compl. ¶ 2.) Both are members
    of Clean Air Council. Clean Air Council is a nonprofit corporation with a place of
    business in Philadelphia, Pennsylvania. (Id. ¶ 1.) Clean Air Council’s mission is to
    protect everyone’s right to breathe clean air.
    Plaintiffs’ Complaint includes a lengthy and detailed history of the
    Mariner East Project, with which this Court is very familiar. Briefly stated, the
    Mariner East Project is an effort by Sunoco to construct and operate an integrated
    pipeline system to transport petroleum products and NGLs (e.g., propane, ethane,
    and butane) from the Marcellus and Utica Shale formations in Pennsylvania, Ohio,
    4
    Article I, Section 27 of the Pennsylvania Constitution, otherwise known as the
    Environmental Rights Amendment, provides:
    The people have a right to clean air, pure water, and to the preservation of
    the natural, scenic, historic and esthetic values of the environment. Pennsylvania’s
    public natural resources are the common property of all the people, including
    generations yet to come. As trustee of these resources, the Commonwealth shall
    conserve and maintain them for the benefit of all the people.
    5
    By order dated February 5, 2016, the trial court struck Count IX of the Complaint.
    3
    and West Virginia, through the Commonwealth of Pennsylvania, with a terminus at
    Sunoco’s Marcus Hook Industrial Complex in Delaware County, Pennsylvania. See
    In re Condemnation by Sunoco Pipeline L.P., 
    143 A.3d 1000
    , 1008 (Pa. Cmwlth.)
    (en banc) (Martin), appeal denied, 
    164 A.3d 485
    (Pa. 2016). The project consists of
    two phases—ME1 (combination of new and existing pipelines) and ME2 (entirely
    new pipeline). 
    Id. As Plaintiffs
    note in paragraph 56 of their Complaint, efforts by Sunoco
    to acquire easements over private property to construct ME2 have met resistance,
    spawning litigation across the Commonwealth under the Eminent Domain Code,
    some of which has reached this Court. The lead case is Martin. Martin involved
    litigation over declarations of taking that Sunoco filed in the Court of Common Pleas
    of Cumberland County pursuant to Section 302 of the Eminent Domain Code,6
    26 Pa. C.S. § 302, condemning private property for purposes of constructing ME2.7
    The property owners filed preliminary objections, contesting the declarations. In
    doing so, they raised some of the legal challenges that Plaintiffs raise in their
    Complaint.
    Specifically, the property owners in Martin contended that ME2 was an
    interstate pipeline regulated by the Federal Energy Regulatory Commission (FERC)
    and not an intrastate pipeline regulated by the PUC as a public utility. As a
    consequence, Sunoco could not use its eminent domain power as a public utility to
    6
    The Eminent Domain Code provides that the power of condemnation can only be
    exercised by the filing of a declaration of taking in the court of common pleas of the county in
    which the real property is located. 26 Pa. C.S. §§ 301, 302.
    7
    In Martin, this Court observed that ME1 “has been completed.”                  
    Martin, 143 A.3d at 1008
    .
    4
    construct ME2.8 
    Martin, 143 A.3d at 1015-16
    ; (Compl. Ct. I). The property owners
    in Martin also contended that Sunoco lacked certificates of public convenience
    (CPC) from the PUC to construct ME1 and ME2, which, under the Public Utility
    Code, Sunoco must possess in order to exercise its eminent domain power as a public
    utility.9 
    Martin, 143 A.3d at 1016-17
    ; (Compl. Ct. II). They also contended that
    Sunoco failed to demonstrate a public need served by the taking.                          
    Martin, 143 A.3d at 1017-18
    .
    Ultimately, a divided en banc panel of this Court rejected the property
    owners’ contentions and allowed the takings to proceed:
    For these reasons, we conclude that common pleas
    did not err when it overruled Condemnees’ Preliminary
    Objections to Sunoco’s Declarations of Taking. We
    further conclude that Sunoco is regulated as a public utility
    by the PUC and is a public utility corporation, and Mariner
    East interstate service is a public utility service rendered
    by Sunoco within the meaning of the BCL.[10]
    
    Martin, 143 A.3d at 1020
    (citation omitted).11 In so doing, the Court expressly held
    that Sunoco possesses the requisite approvals from the PUC to construct ME2 to
    provide intrastate service. 
    Id. at 1015-16.
    Since Martin, other property owners
    across the Commonwealth have fought against Sunoco’s efforts to take their
    property by eminent domain, with similar results. See, e.g., In re Condemnation by
    Sunoco Pipeline L.P., 
    165 A.3d 1044
    (Pa. Cmwlth. 2017) (Katz), appeal denied,
    8
    Under Section 1511(a)(2) of the Business Corporation Law of 1988 (BCL),
    15 Pa. C.S. § 1511(a)(2), a public utility corporation may acquire private property through eminent
    domain for certain “principal purposes,” among which is the transportation of natural gas “for the
    public.”
    9
    See 66 Pa. C.S. §§ 1101, 1104.
    10
    15 Pa. C.S. §§ 1101-4146.
    11
    The undersigned and Judge Patricia McCullough each filed a dissenting opinion.
    5
    (Pa., No. 507 MAL 2017, filed Jan. 22, 2018); In re Condemnation by Sunoco
    Pipeline L.P. (Pa. Cmwlth., No. 1780 C.D. 2016, filed Oct. 24, 2017) (Andover
    Homeowners’ Assoc., Inc.), petition for allowance of appeal pending, (Pa., No. 814
    MAL 2017, filed Nov. 27, 2017); In re Condemnation by Sunoco Pipeline L.P. (Pa.
    Cmwlth., No. 2030 C.D. 2016, filed June 29, 2017) (Perkins), appeal denied, (Pa.,
    No. 501 MAL 2017, filed Jan. 22, 2018); In re Condemnation by Sunoco Pipeline
    L.P. (Pa. Cmwlth., No. 1306 C.D. 2016, filed May 26, 2017) (Blume), appeal denied,
    (Pa., No. 434 MAL 2017, filed Jan. 22, 2018); In re Condemnation by Sunoco
    Pipeline L.P. (Pa. Cmwlth., No. 565 C.D. 2016, filed May 24, 2017) (Homes for
    Am.), appeal denied, (Pa., No. 429 MAL 2017, filed Jan. 22, 2018); In re
    Condemnation by Sunoco Pipeline L.P. (Pa. Cmwlth., No. 220 C.D. 2016, filed
    May 15, 2017) (Gerhart), appeal denied, (Pa., No. 400 MAL 2017, filed
    Jan. 22, 2018).
    In their Complaint, Plaintiffs attempt to open up a new front in the battle
    to stop Sunoco from exercising the power of eminent domain to construct ME1 and
    ME2.12 They commenced their assault in the trial court, although it is undisputed
    that neither ME1 nor ME2 enters Philadelphia County. Moreover, unlike the
    property owners in the cases cited above, Plaintiffs do not allege to be
    “condemnees”—i.e., owners of real property subject to filed declarations of taking
    under the Eminent Domain Code.                 See 26 Pa. C.S. § 103 (definition of
    “condemnee”). Instead, Ms. deMarteleire and Mr. Bomstein allege that their home
    in Delaware County was, at the time they filed their Complaint, on the proposed
    route of ME2. (Compl. ¶ 108.)
    12
    As previously noted, ME1 “has been completed.” 
    Martin, 143 A.3d at 1008
    .
    6
    As for its interest, Clean Air Council also identifies as a member Eric
    Friedman, a resident of the Andover Development in Thornberry Township,
    Delaware County, and President of the Andover Homeowners’ Association
    (Andover HOA). (Compl. ¶¶ 118-19.) Plaintiffs allege that the path of ME2 would
    run through open space in the Andover Development and that the Andover HOA and
    Mr.    Friedman      oppose      any    easement      to    Sunoco     to    construct     ME2.
    (Compl. ¶¶ 120-25.) Indeed, Sunoco proceeded under the Eminent Domain Code
    by filing a declaration of taking in the Court of Common Pleas of Delaware County
    for purposes of securing an easement to construct a portion of ME2 within the
    Andover HOA open space.              The Andover HOA filed preliminary objections,
    challenging the declaration. The Delaware County court overruled the preliminary
    objections, thereby allowing the taking.                This Court affirmed.            Andover
    Homeowners’ Assoc., Inc., slip. op. at 11.13
    Clean Air Council also points to one of its members, Thomas Casey of
    Chester County. According to the Complaint, Sunoco “initially expressed intent” to
    take Mr. Casey’s land for purposes of ME2, but it ultimately chose not to do so.
    (Compl. ¶ 129.) Clean Air Council also alleges generally that it “has members
    throughout Pennsylvania, including along the route of” ME2 who do not wish to
    give or sell an easement to Sunoco for ME2. (Compl. ¶¶ 116, 235.) Clean Air
    Council, however, does not identify any of these members, nor does it allege that
    any of them face an imminent taking of their property by Sunoco.
    As noted above, Counts I and II of the Complaint include claims that
    are identical in all material respects to challenges that this Court addressed in Martin.
    13
    In our decision, we vacated and remanded only that portion of the Delaware County
    court’s order relating to the amount of the bond filed by Sunoco. Andover HOA has filed a petition
    for allowance of appeal with the Pennsylvania Supreme Court, docketed at 814 MAL 2017.
    7
    With respect to relief, Plaintiffs seek a judicial declaration that Sunoco “may not
    exercise the right of eminent domain against” Ms. deMarteleire and Mr. Bomstein
    and other Clean Air Council members. (R.R. 98a, 100a.) In Counts III and IV,
    Plaintiffs seek a judicial declaration that Sunoco’s condemnations to construct the
    Mariner East Project violate Plaintiffs’ property rights secured by the Takings
    Clause of the Fifth Amendment to the United States Constitution14 and Article X,
    Section 4 of the Pennsylvania Constitution15 and that, as a result, Sunoco “may not
    exercise the right of eminent domain against” Ms. deMarteleire and Mr. Bomstein
    and other Clean Air Council members. (Compl. Cts. III, IV.) In this regard,
    Plaintiffs specifically allege that Sunoco is using its eminent domain power to effect
    a “private taking” for a “private purpose.”
    In Counts V and VI, Plaintiffs purport to raise a procedural due process
    challenge under the Fourteenth Amendment to the United States Constitution and
    Article I, Section 1 of the Pennsylvania Constitution.16 (R.R. 103a.) Specifically,
    14
    The Fifth Amendment to the United States Constitution, made applicable to the States
    through the Fourteenth Amendment to the United States Constitution, prohibits the taking of
    private property for “public use” without just compensation. The Pennsylvania Constitution
    includes a similar takings clause in Article I, Section 10, which prohibits the taking of private
    property for “public use” without legal authority and just compensation. Plaintiffs, however, do
    not specifically allege a violation of Article I, Section 10 in their Complaint.
    15
    Article X, Section 4 of the Pennsylvania Constitution requires municipal and other
    corporations, when exercising the power of eminent domain, to make just compensation for the
    property taken for “public use.”
    16
    The Due Process Clause of the Fourteenth Amendment provides that no State shall
    “deprive any person of life, liberty, or property, without due process of law.” U.S. Const.
    amend. XIV, § 1. Though not explicitly found in the text, the Pennsylvania Supreme Court has
    held that the guarantee of due process of law in Pennsylvania jurisprudence emanates from
    Article I, Sections 1, 9, and 11 of the Pennsylvania Constitution. Lyness v. State Bd. of Med.,
    
    605 A.2d 1204
    , 1207 (Pa. 1992). The due process standards of the United States and Pennsylvania
    Constitutions are, however, essentially the same. Muscarella v. Commonwealth, 
    87 A.3d 966
    , 973
    (Pa. Cmwlth. 2014).
    8
    Plaintiffs aver that they did not receive adequate notice of any PUC authorizations
    granted to Sunoco to construct ME1 or ME2. Had they received such notices,
    Plaintiffs allege that they would have appeared before the PUC to oppose such
    authorizations.   As for relief, Plaintiffs seek a “hearing to determine whether
    [Sunoco] is entitled to exercise eminent domain rights over” Ms. deMarteleire’s and
    Mr. Bomstein’s property and other Clean Air Council members’ properties. (Id.)
    In Count VII of the Complaint, Plaintiffs allege that Sunoco has
    fiduciary duties as a trustee under the Environmental Rights Amendment to consider
    the impact its construction of the Mariner East Project would have on Pennsylvania’s
    public natural resources. Plaintiffs further allege that Sunoco has failed to perform
    this assessment. Accordingly, Plaintiffs seek a declaration that Sunoco may not
    pursue eminent domain with respect to either ME1 or ME2 “until it demonstrates to
    the PUC that its pipeline project comports with the Environmental Rights
    Amendment.” (R.R. 104a (emphasis added).) Finally, in Count VIII, Plaintiffs seek
    preliminary and final injunctive relief, barring Sunoco from using eminent domain
    to acquire easements to construct ME1 and ME2 based on the substantive claims in
    the Complaint. (R.R. 107a.)
    In its Opinion in support of its order denying Sunoco’s motion for
    summary judgment, the trial court rejected Sunoco’s contention that this Court’s
    decisions in Martin and subsequent eminent domain cases related to the Mariner
    East Project compelled the trial court to enter judgment in Sunoco’s favor as a matter
    of law on Plaintiffs’ claims. (Trial Ct. Op. at 6-10.) With respect to Counts I and II,
    the trial court noted that discovery is ongoing and factual issues remain that preclude
    the entry of summary judgment. With respect to the remaining substantive counts
    (Counts III-VII), the trial court noted that these constitutional claims are outside of
    9
    the ambit of the Eminent Domain Code and the adjudicative authority of the PUC.
    Accordingly, they were not raised nor could they have been raised in the
    condemnation cases previously addressed by this Court. Finally, the trial court noted
    that because summary judgment would be denied with respect to the substantive
    counts of the Complaint, Count VIII, which derivatively seeks injunctive relief,
    should also proceed.
    III. ANALYSIS
    A. Standard of Review
    Our standard of review on appeal from the grant or denial of summary
    judgment is de novo, and our scope of review is plenary. Pentlong Corp. v. GLS
    Capital, Inc., 
    72 A.3d 818
    , 823 n.6 (Pa. Cmwlth. 2013). Our review is limited to
    determining whether the trial court committed an error of law or abuse of
    discretion. Wolfe v. Stroudsburg Area Sch. Dist., 
    688 A.2d 1245
    , 1247 (Pa.
    Cmwlth. 1997). Summary judgment is only appropriate where, upon examination
    of the record in the light most favorable to the nonmoving party, no genuine issue of
    material fact exists and the moving party is clearly entitled to a judgment as a matter
    of law. Dwight v. Girard Med. Ctr., 
    623 A.2d 913
    , 915 (Pa. Cmwlth. 1993).
    In their brief, Plaintiffs raise several concerns about issue preservation,
    suggesting that Sunoco did not raise or preserve below the questions currently on
    appeal with respect to some or all of the counts of the Complaint. In response, we
    note that it is the trial court, not Sunoco, that has certified questions to this Court as
    “controlling questions of law” and has amended its prior order, denying summary
    judgment, to indicate that its ruling denying Sunoco’s motion for summary judgment
    “involves” the four questions that the trial court certified in its amending order
    pursuant to Section 702(b) of the Judicial Code. Moreover, in their Answer to
    10
    Petition for Permission to Appeal Under Pa. R.A.P. 1311 filed with the Court in this
    matter, Plaintiffs concede that Sunoco raised the issues currently before this Court
    in several filings before the trial court, most recently its motion for summary
    judgment. (Pls.’ Answer at 1-2.) For these reasons, we will proceed to address the
    issues certified by the trial court consistent with the standard and scope of review set
    forth above.
    B. Question 1: Are Plaintiffs’ Claims Outside the Subject Matter
    Jurisdiction of the [Trial Court] or Otherwise Non-Justiciable
    Collateral Attacks on the Public Utility Commission’s
    Determinations?17
    1. Count I (Interstate/Intrastate) and Count II (Lack of CPCs)
    The essence of Plaintiffs’ Contention in Count I of the Complaint is that
    ME1 and ME2 are interstate pipelines regulated by the FERC, not the PUC. Sunoco,
    therefore, lacks the authority to condemn property to construct ME1 and ME2
    afforded under the BCL to public utilities regulated by the PUC. In Count II,
    Plaintiffs contend that even if the Mariner East Project is intrastate in nature, the
    PUC has not issued the required CPCs for the pipelines. Sunoco essentially argues
    that in Martin, the issues raised by Plaintiffs in Counts I and II of the Complaint
    have already been decided. Sunoco contends that Plaintiffs’ effort to press the issues
    in the trial court amount to collateral attacks on the CPCs issued by the PUC to
    Sunoco.
    In response, Plaintiffs claim that common pleas courts, and not the
    PUC, have “jurisdiction over claims as to the validity of a utility’s taking.” (Pls.’
    Br. at 16.) In support, Plaintiffs cite to this Court’s opinion in Southeastern
    17
    A court’s lack of subject matter jurisdiction is a nonwaivable issue that can be raised at
    any stage of the proceeding, even by an appellate court sua sponte. See, e.g., LeFlar v. Gulf Creek
    Indus. Park No. 2, 
    515 A.2d 875
    , 879 (Pa. 1986).
    11
    Pennsylvania     Transportation     Authority   v.   Public    Utility   Commission,
    
    991 A.2d 1021
    (Pa. Cmwlth. 2010) (SEPTA). In that case, SEPTA appealed the
    PUC’s approval of an application to site and construct a high voltage power line. On
    appeal, SEPTA contended that the PUC should have denied the application, because
    the utility could not justify condemnation of the property to construct the power line.
    Agreeing with the PUC, this Court held that whether a public utility may exercise
    the power of eminent domain is not an issue that the PUC considers when reviewing
    an application for a CPC:
    [T]he only role of the PUC is to consider if the project is
    necessary or proper for the benefit of the public, and it is
    expressly barred from considering the power of the utility
    to condemn. After the PUC authorizes a utility to exercise
    the power of eminent domain, a condemnation is far from
    final, as 15 Pa. C.S. § 1511(g) makes clear that before
    taking the land, the utility must prevail in a condemnation
    action at the Court of Common Pleas. As our Supreme
    Court held, in interpreting an earlier but substantially
    similar version of the statute: “Once there has been a
    determination by the PUC that the proposed service is
    necessary and proper, the issues of scope and validity and
    damages must be determined by a Court of Common Pleas
    exercising equity jurisdiction.”
    
    SEPTA, 991 A.2d at 1023
    (quoting Fairview Water Co. v. Pa. Pub. Util.
    Comm’n, 
    502 A.2d 162
    , 167 (Pa. 1985)).
    We agree with Plaintiffs in their assessment of the law but only to a
    point. We do not read Counts I and II of the Complaint as challenging orders or
    CPCs issued by the PUC to Sunoco. Rather, Plaintiffs challenge the power of
    Sunoco to condemn property by eminent domain. As we noted in SEPTA, in order
    to exercise the power of eminent domain conferred by the BCL, a public utility must
    12
    first obtain a CPC from the PUC.18 In evaluating a request for a CPC, the PUC only
    considers whether the proposed service is “necessary or proper for the service,
    accommodation, convenience, or safety of the public.” 66 Pa. C.S. § 1103(a). There
    is no provision in either the Public Utility Code or the BCL that also authorizes the
    PUC, in the context of a CPC administrative proceeding, to consider whether the
    public utility may exercise the power of eminent domain to effect a taking in
    furtherance of the authorized service. Indeed, as this Court observed in SEPTA,
    although the issuance of the CPC allows the public utility to commence proceedings
    under the Eminent Domain Code, success in the common pleas court is not
    guaranteed. To effect a condemnation, the public utility must proceed and succeed
    in the common pleas court under the Eminent Domain Code. 15 Pa. C.S. § 1511(g)
    (requiring all condemnation and taking of property authorized by section to follow
    procedures under Eminent Domain Code); see also 
    Martin, 143 A.3d at 1019
    (discussing separate roles of PUC and common pleas courts).
    In Counts I and II, like the condemnees in Martin, Plaintiffs challenge
    the power of Sunoco to exercise eminent domain on two grounds: (1) Sunoco is not
    a public utility for purposes of the Mariner East Project because the project is purely
    interstate in nature and not regulated by the PUC; and (2) if intrastate, Sunoco has
    not secured the required CPCs from the PUC. Neither claim amounts to a collateral
    attack of the CPCs that the PUC has issued to Sunoco or a challenge to the PUC’s
    determination of “public need” set forth in those CPCs. There remains, however,
    the question of the trial court’s subject matter jurisdiction.
    18
    For purposes of Sunoco’s ME1 and ME2 pipelines, that requirement is found in
    Section 1104 of the Public Utility Code, 66 Pa. C.S. § 1104, which provides: “Unless its power
    of eminent domain existed under prior law, no domestic public utility . . . shall exercise any power
    of eminent domain within this Commonwealth until it shall have received the certificate of public
    convenience required by section 1101.”
    13
    The Pennsylvania Supreme Court has observed: “Subject matter
    jurisdiction relates to the competency of a court to hear and decide the type of
    controversy presented. Jurisdiction is a matter of substantive law.” Commonwealth
    v. Bethea, 
    828 A.2d 1066
    , 1074 (Pa. 2003), cert. denied, 
    540 U.S. 1118
    (2004). As
    for jurisdiction of the courts of common pleas, Section 931(a) of the Judicial Code,
    42 Pa. C.S. § 931(a), provides:
    Except where exclusive original jurisdiction of an action
    or proceeding is by statute or by general rule adopted
    pursuant to section 503 (relating to assignment of matters)
    vested in another court of this Commonwealth, the courts
    of common pleas shall have unlimited original jurisdiction
    of all actions and proceedings, including all actions and
    proceedings heretofore cognizable by law or usage in the
    courts of common pleas.
    (Emphasis added.) The test for determining whether a court has subject matter
    jurisdiction is whether the court has “‘the power to enter upon the inquiry, not
    whether it might ultimately decide that it was unable to grant the relief sought in the
    particular case.’” Heath v. Workers’ Comp. Appeal Bd. (Pa. Bd. of Prob. and
    Parole), 
    860 A.2d 25
    , 29 (Pa. 2004) (quoting Strank v. Mercy Hosp. of
    Johnstown, 
    102 A.2d 170
    , 172 (Pa. 1954)).
    Applying this test, we hold that the trial court’s general jurisdiction
    under Section 931(a) of the Judicial Code does not extend to claims seeking to
    adjudicate the power and right of a public utility to condemn property. As noted
    above, the substantive law of this Commonwealth requires that public utilities
    wishing to condemn private property abide by the procedures set forth in the Eminent
    Domain Code. The Eminent Domain Code “provides a complete and exclusive
    procedure and law to govern all condemnations of property for public purposes and
    the assessment of damages.”       26 Pa. C.S. § 102.     To condemn property, the
    14
    condemnor must commence an action “in the court of the county in which the
    property is located or, if the property is located in two or more counties, in the court
    of any one of the counties.” 26 Pa. C.S. § 301 (emphasis added). The condemnor
    does so by, inter alia, filing in court a declaration of taking and providing notice to
    the condemnee. 26 Pa. C.S. §§ 302-305. Thereafter, the condemnee may file
    preliminary objections, challenging the condemnation on certain grounds:
    Preliminary objections shall be limited to and shall
    be the exclusive method of challenging:
    (i) The power or right of the condemnor to
    appropriate the condemned property unless it has been
    previously adjudicated.
    (ii) The sufficiency of the security.
    (iii) The declaration of taking.
    (iv) Any other procedure followed by the
    condemnor.
    26 Pa. C.S. § 306(a)(3) (emphasis added).
    In Vartan v. Reed, 
    514 A.2d 646
    (Pa. Cmwlth. 1986), appeal denied,
    
    536 A.2d 1335
    (Pa. 1987), the owner of property in the City of Harrisburg was
    advised that a local redevelopment authority planned to acquire the property by
    condemnation. Rather than wait for this to occur, the property owner commenced
    an action in common pleas court, seeking an order enjoining the authority from
    attempting to acquire the property by eminent domain. The common pleas court
    granted the injunction, and the authority appealed. This Court reversed, finding that
    the common pleas court lacked subject matter jurisdiction over the case: “It has
    uniformly been held that equity does not have jurisdiction to enjoin a condemnation,
    whether or not a declaration of taking has been filed; and that preliminary objections
    15
    shall be the exclusive method of challenging the right or power to condemn.”
    
    Vartan, 514 A.2d at 648
    (emphasis added).19
    Whether Sunoco is a public utility for purposes of the Mariner East
    Project (Count I) and, if it is, whether it has secured the required CPCs to proceed
    therewith (Count II) are questions that go to the “power and right” of Sunoco to
    condemn land by eminent domain under the BCL. Under the substantive law of this
    Commonwealth, the exclusive method for raising these questions is through
    preliminary objections filed (1) by the condemnee, (2) after the filing of a declaration
    of taking, and (3) in the court of common pleas where the property is located. As
    Plaintiffs’ action below does not meet any of these parameters, the trial court lacks
    subject matter jurisdiction over Counts I and II of the Complaint.
    2. Counts III and IV (Unconstitutional Takings)
    As noted above, in Counts III and IV of the Complaint, Plaintiffs’ claim
    that Sunoco’s condemnations of property for the Mariner East Project violate the
    Takings Clause of the Fifth Amendment and Article X, Section 4 of the Pennsylvania
    Constitution.     To properly exercise eminent domain under these provisions,
    Plaintiffs contend, the condemnations in question must be for a public purpose.
    Citing, inter alia, the Pennsylvania Supreme Court’s decision in Middletown
    Township v. Lands of Stone, 
    939 A.2d 331
    (Pa. 2007), Plaintiffs contend that the test
    for determining whether a condemnation is for a “public purpose” is whether the
    19
    In Vartan, the Court addressed the exclusiveness of the remedy under Section 406(a) of
    the 1964 Eminent Domain Code (Former Code). See Act of June 22, 1964, Special Sess.,
    P.L. 84, as amended, formerly 26 P.S. § 1 406(a), repealed by Section 5 of the Act of May 4, 2006,
    P.L. 112. Under Section 306(a) of the current Eminent Domain Code, 26 Pa. C.S. § 306(a),
    “preliminary objections are still the exclusive method of challenging the condemnor’s right to
    take, the declaration of taking itself, and any procedural irregularities by the condemnor.” Lang
    v. Dep’t of Transp., 
    13 A.3d 1043
    , 1049 (Pa. Cmwlth. 2011).
    16
    public is “the primary and paramount beneficiary.”               Lands of 
    Stone, 939 A.2d at 337-38
    . Plaintiffs seek the opportunity to establish below that although
    a public need may be served by the Mariner East Project, for purposes of triggering
    the power to condemn under the BCL, the condemnations do not satisfy the “primary
    and paramount beneficiary test.”
    Counts III and IV of the Complaint raise questions that go to the “power
    and right” of Sunoco to condemn land by eminent domain under the United States
    and Pennsylvania Constitutions. Indeed, Lands of Stone, the opinion on which
    Plaintiffs rely, arose under the Eminent Domain Code. The township in that case
    filed a declaration of taking to condemn property for preservation of open space.
    The condemnee filed preliminary objections, challenging, inter alia, the power of
    the township to take his property. The Pennsylvania Supreme Court held that
    although the township had the statutory power to condemn the property for open
    space (recreational purposes), the record was inadequate to determine whether the
    condemnation violated the Takings Clause of the Fifth Amendment to the United
    States Constitution.   Accordingly, it remanded the matter to common pleas
    (proceeding under the Eminent Domain Code) to develop a record and consider the
    question. Lands of 
    Stone, 939 A.2d at 337-40
    .
    The trial court concluded that it could exercise jurisdiction over these
    claims, citing the Pennsylvania Supreme Court’s decision in Robinson Township v.
    Commonwealth, 
    83 A.3d 901
    (Pa. 2013) (Robinson Twp.). That case, however,
    involved a facial validity challenge to a statute enacted by the General Assembly,
    which authorized certain private entities in the oil and gas industry to condemn
    property through eminent domain. The plaintiffs claimed that the statute was
    unconstitutional because it authorized private takings in violation of the
    17
    Pennsylvania and United States Constitutions. In rebuffing the Commonwealth’s
    contention that the plaintiffs could not bring their challenge until a company
    attempted to exercise that authority by filing a declaration of taking under the
    Eminent Domain Code and then raise it by preliminary objection, the Supreme Court
    explained:
    Waiting for a test case implicating a taking under
    [the statute]—and subject to the Eminent Domain Code’s
    exclusive procedures—is certainly an available avenue for
    testing the constitutionality of the provision. But, as a
    facial challenge to the validity of a statutory provision and
    pure question of law, the citizens’ claim is also generally
    appropriate for pre-enforcement review in a declaratory
    judgment action.
    Robinson 
    Twp., 83 A.3d at 990
    (emphasis added).
    By analogy, this case would be similar to Robinson Twp. if Plaintiffs
    were challenging the constitutionality of Section 1511(a)(2) of the BCL, which
    provides public utilities with the power to condemn private property.
    Counts III and IV, however, do not raise facial challenges to the constitutionality of
    a statute; rather, they call into question the public purpose of particular takings across
    the Commonwealth. Moreover, the claims do not involve pure questions of law, as
    Plaintiffs contend at several points in their appellate brief. (See, e.g., Pls.’ Br. at 35.)
    The trial court’s reliance on Robinson Twp., therefore, was misplaced.
    For these reasons, the Eminent Domain Code provides the exclusive
    procedure for challenging the power and right of Sunoco to condemn under the
    United States and Pennsylvania Constitutions. The trial court, therefore, lacks
    subject matter jurisdiction over Counts III and IV of the Complaint.
    18
    3. Counts V and VI (Due Process)
    In Counts V and VI, under the guise of due process claims, Plaintiffs
    aver that the CPCs Sunoco received from the PUC affected the property rights of the
    Plaintiffs as well as other Clean Air Council members, as Sunoco has relied on them
    to support its exercise of eminent domain to obtain easements for the construction
    of the Mariner East Project. Plaintiffs allege that Sunoco should have been required
    under Pennsylvania recording laws to index the CPCs in county records as
    encumbrances. (Compl. ¶¶ 207, 210.) Sunoco did not record the CPCs in the
    Delaware County property records relating to Ms. deMarteleire’s and Mr.
    Bomstein’s property. (Compl. ¶ 207.) As a result, neither Ms. deMarteleire nor Mr.
    Bomstein ever had actual or constructive notice that Sunoco “was planning to
    construct a pipeline in their backyard.” (Compl. ¶ 208.) Further, Plaintiffs posit that
    if Sunoco were to apply to the PUC for approval to build ME1 and ME2 and had
    notified Plaintiffs of its application, Plaintiffs would have appeared to oppose any
    such application. (Compl. ¶ 212.)
    Sunoco contends that Plaintiffs’ due process claims are collateral
    attacks on the process the PUC followed to issue the CPCs to Sunoco that relate to
    the Mariner East Project and the validity and enforceability of those CPCs.
    It contends that such issues fall within the PUC’s exclusive jurisdiction. Sunoco
    does not cite any authority to support its position. Plaintiffs respond, however, that
    claims that a condemnor failed to afford due process is “collateral” to an eminent
    domain proceeding and, therefore, can be raised before a common pleas court sitting
    in equity. In support, Plaintiffs cite to cases from this Court, one of which addresses
    due process claims.
    19
    In Condemnation of Legislative Route 201, 
    349 A.2d 819
    (Pa.
    Cmwlth. 1975) (en banc) (Becker), the Pennsylvania Department of Transportation
    (PennDOT) initiated condemnation proceedings under the Former Code to acquire
    private property for purposes of a road-widening project.           Before initiating
    condemnation proceedings and during the design phase of the project, then-existing
    state and federal law required PennDOT to provide notice of the project to the public
    with an opportunity to be heard with respect to, inter alia, the environmental impacts
    of the design. 
    Becker, 349 A.2d at 819-20
    . After PennDOT completed the design
    phase and initiated proceedings under the Former Code to condemn property in
    Chester County, the condemnees filed preliminary objections, which included an
    objection under the Environmental Rights Amendment. The common pleas court
    dismissed the preliminary objections, and the condemnees appealed. 
    Id. at 820.
                 On appeal to this Court, the condemnees argued that PennDOT violated
    their due process rights by failing to give them personal notice of and an opportunity
    for hearing as to the environmental impacts of the project: “This, they argue, makes
    the condemnation proceedings a nullity.”       
    Id. Initially, this
    Court considered
    whether the procedural due process challenge fell within the scope of the four
    authorized preliminary objections under the Former Code, which are materially
    identical to the four grounds set forth in Section 306(a)(3) of the Eminent Domain
    Code. The Court first held that the challenge did not go to PennDOT’s “power or
    right” to condemn, which is provided for in a statute separate and apart from the
    procedures that govern planning for highway projects. 
    Id. at 821.
    Noting that the
    condemnees did not challenge the sufficiency of the security or the declaration of
    the taking itself, the Court considered whether the condemnees’ due process
    challenge could be considered an objection to “any other procedure followed by the
    20
    condemnor.” 
    Id. The Court
    concluded that it did not, noting that this preliminary
    objection is confined to other procedures set forth in the Former Code directly related
    to the filing of a declaration of taking. 
    Id. (citing Simco
    Stores, Inc. v. Phila.
    Redevelopment Auth., 
    302 A.2d 907
    (Pa. Cmwlth. 1973), aff’d, 
    317 A.2d 610
    (1974)).
    The Court concluded that the appeal was analogous to the Court’s
    earlier decision in Simco:
    The instant appeal is analogous to Simco, wherein a
    local ordinance protected businesses from eviction for one
    year subsequent to the declaration of taking. The
    condemnor attempted such an eviction, and the
    condemnee raised preliminary objections based on the
    ordinance. We found such an objection to be improper,
    because even though the conduct was improper under the
    ordinance, the power to take was still effective.
    
    Id. (emphasis added).
    Concluding, then, that the condemnees’ due process challenge
    could not be raised by preliminary objection under the Former Code, the Court held:
    Even if one assumes that failure to give personal
    notice to [the condemnees] of the highway project hearing
    here involved constituted legal error, preliminary
    objections to the declaration of taking is not the proper
    vehicle to challenge such procedures. Here the challenge
    goes to a matter that is primarily of a planning nature and
    collateral to the condemnation proceeding.
    
    Id. at 821-22
    (emphasis added).
    Although Sunoco has not persuaded the Court that Plaintiffs’ due
    process challenge lies in the exclusive jurisdiction of the PUC, we are also
    unpersuaded by Plaintiffs’ arguments that their due process challenges in
    Counts V and VI of the Complaint are akin to the collateral claims discussed in
    Becker and Simco. In Becker, PennDOT’s power to condemn was unaffected by its
    alleged failure to afford due process in the design phase of a highway project.
    21
    In Simco, the condemnor allegedly acted in contravention of a local ordinance after
    it filed the declaration of taking, not at all implicating the power to file the
    declaration of taking in the first place. Here, by contrast, Sunoco’s power and right
    to condemn property by Eminent Domain depends on the existence and validity of
    CPCs issued by the PUC to Sunoco. See 66 Pa. C.S. § 1104. Counts V and VI
    plainly level a due process challenge to the validity and enforceability of the CPCs.
    As such, although couched in terms of due process, the claims are similar in kind to
    Counts I through IV of the Complaint in that they call into question the “power and
    right” of Sunoco to condemn land by eminent domain under the BCL.
    Accordingly, for the reasons set forth above with respect to
    Counts I through IV, the claims set forth in Counts V and VI of the Complaint must
    be raised in the context of proceedings under the Eminent Domain Code.20 The trial
    court, therefore, erred in concluding that Plaintiffs could invoke the trial court’s
    general jurisdiction under Section 931(a) of the Judicial Code to address their due
    process claims.
    C. Question 2: Are Plaintiffs’ Claims Based Upon Pennsylvania
    Constitution Article I, Section 27 Also Outside the Subject Matter
    Jurisdiction of the [Trial Court] or Otherwise Non-Justiciable
    Collateral Attacks on the Department of Environmental
    Protection’s Issuance of Environmental
    Permits to [Sunoco] for the Pipelines?
    In Count VII of the Complaint, Plaintiffs seek a declaratory judgment
    that Sunoco violated its fiduciary duties as a trustee under the Environmental Rights
    Amendment by failing to consider the environmental impacts of the Mariner East
    Project before moving forward. They seek a declaration that Sunoco may not
    20
    In light of this ruling, we need not consider the fourth question that the trial court certified
    for appeal, relating to the legal sufficiency of Plaintiffs’ due process claims.
    22
    acquire property by eminent domain for the Mariner East Project until Sunoco
    demonstrates “to the PUC” that the project “comports with the Environmental Rights
    Amendment.” (R.R. 104a (emphasis added).)
    As noted above, in ascertaining whether the trial court has subject
    matter jurisdiction over this claim, we concern ourselves with the power of the trial
    court to enter upon the inquiry, not whether it might be able to issue the relief
    Plaintiffs seek. The inquiry prompted by the Complaint is whether Sunoco has
    violated the Environmental Rights Amendment with respect to the construction of
    the Mariner East Project. In support of its jurisdictional challenge, Sunoco claims
    that Count VII is nothing more than a collateral attack on the decisions by the PUC
    and the Department of Environmental Protection approving the project. Instead,
    Sunoco contends, Plaintiffs should have raised any Environmental Rights
    Amendment concerns in appeals from the determinations of those agencies relating
    to the Mariner East Project. In response, Plaintiffs raise several points, none of
    which appear to address directly the question of the trial court’s jurisdiction.
    Our review of the Complaint, particularly Count VII, convinces us that
    Plaintiffs are not seeking to attack collaterally PUC or Department of Environmental
    Protection approvals relating to the Mariner East Project. Instead, Plaintiffs’ legal
    claim is that Sunoco, and Sunoco alone, has violated the Environmental Rights
    Amendment in choosing to proceed with the project. Whether Sunoco has secured
    necessary regulatory approvals may have some relevance to its defense to Plaintiffs’
    claim,21 but anticipated defenses do not dictate our analysis of the trial court’s
    subject matter jurisdiction.
    21
    Until the Pennsylvania Supreme Court’s decision in Pennsylvania Environmental
    Defense Foundation v. Commonwealth, 
    161 A.3d 911
    (Pa. 2017) (PEDF), one of the factors that
    23
    When we accepted this interlocutory appeal, we agreed to consider the
    four issues that the trial court certified, along with the question of whether Sunoco
    is “the Commonwealth,” such that it can be sued for violating the duties of the
    “trustee” under the Environmental Rights Amendment. We requested that the
    parties address this question in their briefs. Both parties did so. Plaintiffs, in
    addition, argued that because Sunoco did not raise this question below, the question
    was not properly before the Court: “[T]he question may not be considered on appeal,
    sua sponte or otherwise.” (Pls.’ Br. at 42.) It is apparent that Plaintiffs do not
    appreciate the purpose behind the Court’s question.
    In PEDF, the Pennsylvania Supreme Court explained the scope of
    protections afforded under the Environmental Rights Amendment:
    [The Environmental Rights Amendment] grants two
    separate rights to the people of this Commonwealth. The
    first right is contained in the first sentence, which is a
    prohibitory clause declaring the right of citizens to clean
    air and pure water, and to the preservation of natural,
    scenic, historic and aesthetic values of the environment.
    This clause places a limitation on the state’s power to act
    contrary to this right, and while the subject of this right
    may be amenable to regulation, any laws that
    unreasonably impair the right are unconstitutional.
    The second right reserved by Section 27, set forth in
    its second sentence, is the common ownership by the
    people, including future generations, of Pennsylvania’s
    public natural resources. . . .
    this Court considered when evaluating a challenge under the Environmental Rights Amendment
    was whether the challenged action complied with all applicable statutes and regulations relating to
    the protection of the Commonwealth’s public natural resources. In PEDF, however, the Supreme
    Court rejected this Court’s three-part test, first articulated in Payne v. Kassab, 
    312 A.2d 86
    (1973),
    aff’d, 
    361 A.2d 263
    (Pa. 1976). 
    PEDF, 161 A.3d at 930
    . This does not necessarily mean, however,
    that compliance with statutes and regulations is irrelevant to the inquiry, even under the new
    standards adopted by the Pennsylvania Supreme Court in PEDF.
    24
    The third clause . . . establishes a public trust,
    pursuant to which the natural resources are the corpus of
    the trust, the Commonwealth is the trustee, and the people
    are the named beneficiaries.
    
    PEDF, 161 A.3d at 931-32
    (citations and footnote omitted) (emphasis added). In
    terms of the trustee’s obligation, the Supreme Court offered the following relevant
    elaboration:
    Trustee obligations are not vested exclusively in
    any single branch of Pennsylvania’s government, and
    instead all agencies and entities of the Commonwealth
    government, both statewide and local, have a fiduciary
    duty to act toward the corpus with prudence, loyalty, and
    impartiality.
    
    Id. at 931
    n.23.      Accordingly, in terms of actionable rights and duties, the
    Environmental Rights Amendment does two things: (1) it limits the power of “the
    state” to act in derogation of protected environmental interests; and (2) it obligates
    “the Commonwealth” to act as a trustee of Pennsylvania’s public natural resources.
    One of the questions that the trial court certified and this Court accepted
    goes to the trial court’s subject matter jurisdiction over Plaintiffs’ Environmental
    Rights Amendment claim. In light of the foregoing, the Environmental Rights
    Amendment does not impose duties or obligations on private parties. See Feudale
    v. Aqua Pa., Inc., 
    122 A.3d 462
    , 466 (Pa. Cmwlth. 2015) (“The plain language of
    the Environmental Rights Amendment charges the Commonwealth, as trustee, with
    the duty to conserve and maintain Pennsylvania’s public natural resources, and we
    are unaware of any case law applying this duty to non-Commonwealth entities.”),
    aff’d, 
    135 A.3d 580
    (Pa. 2016). Plaintiffs contend, however, that as a public utility
    exercising eminent domain powers, Sunoco is not acting purely as a private party.
    Instead, it is exerting “governmental powers.” (Pls.’ Br. at 44.) In essence, then,
    25
    Plaintiffs contend that Sunoco, acting under authority conferred by the PUC, is
    acting as “the Commonwealth government.”22
    With limited exceptions not applicable here, Section 761(a) of the
    Judicial Code, 42 Pa. C.S. § 761(a), vests within this Court exclusive original
    jurisdiction over all civil actions or proceedings “[a]gainst the Commonwealth
    government, including any officer thereof, acting in his official capacity.”
    42 Pa. C.S. § 761(a); see In re Condemnation of Legislative Route 58018,
    
    375 A.2d 1364
    , 1367-68 (Pa. Cmwlth. 1977) (en banc) (holding that question of
    whether PennDOT complied with Environmental Rights Amendment was collateral
    to eminent domain proceeding and is “properly raised only before this Court within
    our original jurisdiction”).          Accordingly, as Plaintiffs’ Environmental Rights
    Amendment claim hinges on the theory that Sunoco is exercising the powers of the
    Commonwealth government as a public utility, this Court, and not the trial court,
    has exclusive original jurisdiction over the claim, and the trial court, on remand,
    should transfer this matter to this Court’s original jurisdiction pursuant to
    Section 5103(a) of the Judicial Code, 42 Pa. C.S. § 5103(a) (relating to transfers of
    erroneously filed matters).23 This is not to say that the Court has accepted Plaintiffs’
    22
    Sunoco is clearly not acting on behalf of a local government agency. If Sunoco is not
    “the Commonwealth” for purposes of the Environmental Rights Amendment, Plaintiffs cannot
    prevail on their Environmental Rights Amendment claim.
    23
    Section 5103(a) of the Judicial Code provides:
    (a)      General rule.--If an appeal or other matter is taken to or brought in
    a court or magisterial district of this Commonwealth which does not have
    jurisdiction of the appeal or other matter, the court or magisterial district judge shall
    not quash such appeal or dismiss the matter, but shall transfer the record thereof
    to the proper tribunal of this Commonwealth, where the appeal or other matter shall
    be treated as if originally filed in the transferee tribunal on the date when the appeal
    26
    theory of liability.   Rather, we reserve for subsequent proceedings the merits
    question of whether a public utility, such as Sunoco, exercising the power of eminent
    domain, acts as the Commonwealth government and thus has independent duties or
    obligations to the people of Pennsylvania under the Environmental Rights
    Amendment.
    D. Question 3: Do Plaintiffs, as Non-Condemnees,
    Lack Standing to Pursue Their Claims?
    The final issue to be resolved is whether Plaintiffs, as non-condemnees,
    may pursue their claims against Sunoco. Through our dispositions of the above
    issues, we have essentially winnowed Plaintiffs’ Complaint down to a single count,
    alleging violations of the Environmental Rights Amendment by Sunoco in failing to
    consider the environmental impacts of the Mariner East Project before moving
    forward. We now consider the issue of whether Plaintiffs have standing to maintain
    this claim.
    On this point, Sunoco’s briefs are of little value. Boiled down to its
    essence, Sunoco’s contention is that only condemnees can challenge Sunoco’s
    exercise of eminent domain. Because neither Ms. deMarteleire nor Mr. Bomstein
    are condemnees with respect to the Mariner East Project, Sunoco claims that they
    lack standing to challenge Sunoco’s exercise of eminent domain. Because the
    individual Plaintiffs lack standing, Clean Air Council, relying on the individual
    Plaintiffs’ status as members, also lacks standing in Sunoco’s view. In short,
    Sunoco’s reasoning is premised entirely on its belief that Plaintiffs are challenging
    a particular condemnation of land. In Count VII of the Complaint, they are not.
    or other matter was first filed in a court or magisterial district of this
    Commonwealth.
    (Emphasis added.)
    27
    Whatever law may restrict who may lodge preliminary objections to a declaration of
    taking under the Eminent Domain Code does not necessarily limit who may
    challenge in this Court’s original jurisdiction a particular governmental decision for
    failure to comply with the Environmental Rights Amendment.
    On the question of standing to bring a claim under the Environmental
    Rights Amendment, we look to the Pennsylvania Supreme Court’s decision in
    Robinson Township v. Commonwealth, 
    83 A.3d 901
    (Pa. 2013) (Robinson Twp. II).
    There, the Pennsylvania Supreme Court held that property owners within a zoning
    district had standing to bring an Environmental Rights Amendment claim based
    upon “the serious risk of alteration in the physical nature of their respective political
    subdivisions and the components of their surrounding environment.” Robinson
    Twp. 
    II, 83 A.3d at 922
    .         Here, even if they are not actual condemnees,
    Ms. deMarteleire and Mr. Bomstein allege in the Complaint that the Mariner East
    Project is either on or in close proximity to their property. They assert that the
    project poses an increased risk of spills or explosions that would impair their
    property. (R.R. 87a.) Consistent with the Pennsylvania Supreme Court’s decision
    in Robinson Twp. II, this Court is satisfied that Ms. deMarteleire and Mr. Bomstein
    have asserted an interest sufficient to support their standing to assert their
    Environmental Rights Amendment claim against Sunoco. Concomitantly, Clean Air
    Council also has standing. Robinson Twp. 
    II, 83 A.3d at 922
    (“Under Pennsylvania
    law, an association has standing as representative of its members to bring a cause of
    action even in the absence of injury to itself, if the association alleges that at least
    one of its members is suffering immediate or threatened injury as a result of
    the action challenged.”).
    28
    IV. CONCLUSION
    For the reasons set forth above, the Eminent Domain Code provides the
    exclusive procedure to raise the claims set forth in Counts I through VI of the
    Complaint. In addition, because Plaintiffs contend that Sunoco, with respect to its
    exercise of eminent domain in furtherance of the Mariner East Project, is acting as
    “the Commonwealth,” this Court has exclusive original jurisdiction over Plaintiffs’
    Environmental Rights Amendment claim in Count VII of the Complaint.
    We, therefore, will reverse the trial court’s May 25, 2017 Order and remand with
    instruction that the trial court enter summary judgment in favor of Sunoco on
    Counts I through VI of the Complaint and transfer what remains to this Court
    pursuant to Section 5103(a) of the Judicial Code.
    P. KEVIN BROBSON, Judge
    29
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Clean Air Council,                       :
    Margaret M. deMarteleire, and            :
    Michael S. Bomstein                      :
    :
    v.                           :   No. 1112 C.D. 2017
    :
    Sunoco Pipeline L.P.,                    :
    Appellant       :
    ORDER
    AND NOW, this 30th day of April, 2018, it is hereby ORDERED that
    the Order of the Court of Common Pleas of Philadelphia County (trial court), dated
    May 25, 2017, as amended by Order dated July 13, 2017, is REVERSED, and the
    matter is REMANDED with instruction that the trial court enter summary judgment
    in favor of Appellant (Defendant below) Sunoco Pipeline L.P. as to Counts I through
    VI of the Complaint and transfer what remains to this Court’s original jurisdiction
    pursuant to Section 5103(a) of the Judicial Code, 42 Pa. C.S. § 5103(a).
    Jurisdiction relinquished.
    P. KEVIN BROBSON, Judge