Old Dominion Elec. Coop. v. Fed. Energy Regulatory Comm'n , 892 F.3d 1223 ( 2018 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued October 24, 2017               Decided June 15, 2018
    No. 16-1111
    OLD DOMINION ELECTRIC COOPERATIVE,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    DUKE ENERGY CORPORATION, ET AL.,
    INTERVENORS
    On Petition for Review of Orders of the
    Federal Energy Regulatory Commission
    Adrienne Elizabeth Clair argued the cause for petitioner.
    With her on the briefs was Dennis Lane.
    Susanna Y. Chu, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With her on the
    brief were Robert H. Solomon, Solicitor, and Elizabeth E.
    Rylander, Attorney.
    Joseph W. Mayes was on the brief for intervenor-movant
    Independent Market Monitor for PJM in support of respondent.
    Before: TATEL, GRIFFITH and MILLETT, Circuit Judges.
    2
    MILLETT, Circuit Judge: The weather conditions giving
    rise to this case may have been out of the ordinary, but the legal
    principles controlling its resolution are decidedly routine. In
    January 2014, a period of exceptionally cold temperatures,
    commonly referred to as a “Polar Vortex,” descended on the
    Eastern United States. As temperatures plunged, the demand
    for electricity soared. In working to help meet that demand,
    Old Dominion Electric Cooperative, an electricity generator
    and provider, found that its operational costs outstripped the
    amounts it could charge for electricity under the governing
    tariff.    Old Dominion then asked the Federal Energy
    Regulatory Commission to waive provisions of the governing
    tariff retroactively so that it could recover its costs. The
    Commission declined on the ground that such retroactive
    charges would violate the filed rate doctrine and the rule
    against retroactive ratemaking. The Commission was right to
    do so, and we accordingly deny Old Dominion’s petition for
    review. We also deny the motion of the Independent Market
    Monitor to intervene, but will accord it amicus curiae status.
    I
    A
    The Federal Power Act charges the Commission with
    ensuring that “[a]ll rates and charges made, demanded, or
    received by any public utility for or in connection with the
    transmission or sale of electric energy subject to the
    jurisdiction of the Commission * * * shall be just and
    reasonable.” 16 U.S.C. § 824d(a). To effectuate those goals,
    regulated utilities must file with the Commission and keep
    open for public inspection a schedule of the rates they intend to
    charge ratepayers. 
    Id. § 824d(c),
    (d). While the Act permits
    regulated utilities to set their filed rate unilaterally and record
    3
    it in a tariff, see 
    id. § 824d(c),
    the rates actually charged may
    not exceed those on file with the Commission, Towns of
    Concord, Norwood, and Wellesley Mass. v. FERC, 
    955 F.2d 67
    , 68 (D.C. Cir. 1992).
    The Act also empowers the Commission to fix or change
    rates and charges, but only prospectively. 16 U.S.C. § 824e(a).
    When a utility wishes to alter the rates it charges, it must
    provide sixty-days’ notice to the Commission and file new rate
    schedules “stating plainly the change or changes to be made in
    the schedule or schedules then in force and the time when the
    change or changes will go into effect.” 
    Id. § 824d(d).
    The
    Commission may waive the sixty-day notice requirement for
    good cause, but the Commission has no authority under the Act
    to allow retroactive change in the rates charged to consumers.
    See id.; Columbia Gas Transmission Corp. v. FERC, 
    895 F.2d 791
    , 795–796 (D.C. Cir. 1990) (Columbia III); see also
    Consolidated Edison Co. v. FERC, 
    958 F.2d 429
    , 434 (D.C.
    Cir. 1992).
    Those rules mandating the open and transparent filing of
    rates and broadly proscribing their retroactive adjustment are
    known collectively as the “filed rate doctrine.” At bottom, that
    doctrine means that “a regulated seller of [power]” is
    prohibited “from collecting a rate other than the one filed with
    the Commission,” and “the Commission itself” cannot
    retroactively “impos[e] a rate increase for [power] already
    sold.” Arkansas Louisiana Gas Co. v. Hall, 
    453 U.S. 571
    , 578
    (1981).
    In a similar vein, the rule against retroactive ratemaking
    “prohibits the Commission from adjusting current rates to
    make up for a utility’s over- or under-collection in prior
    periods.” Towns of 
    Concord, 955 F.2d at 71
    n.2. That
    otherwise categorical prohibition against retroactively
    4
    charging rates that differ from those that were on file during the
    relevant time period yields in only two limited circumstances:
    (i) when a court invalidates the set rate as unlawful, and (ii)
    when the filed rate takes the form not of a number but of a
    formula that varies as the incorporated factors change over
    time. See West Deptford Energy, LLC v. FERC, 
    766 F.3d 10
    ,
    22–23 (D.C. Cir. 2014) (compiling cases). Neither of those
    exceptions apply to this case. 1
    B
    PJM Interconnection, LLC (“PJM”) is a Regional
    Transmission Organization and Independent System Operator
    that exercises operational control over, but not ownership of,
    the electrical transmission facilities belonging to its
    participating members. See Midwest ISO Transmission
    Owners v. FERC, 
    373 F.3d 1361
    , 1364 (D.C. Cir. 2004). The
    Commission has tasked PJM, as a Regional Transmission
    Organization, with supervising and coordinating the movement
    of electricity throughout its market area, 18 C.F.R. § 35.34,
    which comprises thirteen states and the District of Columbia,
    see Hughes v. Talen Energy Mktg., LLC, 
    136 S. Ct. 1288
    ,
    1292–1293 (2016).
    1 The latter exception for formulaic rates is not really an
    exception at all. It just recognizes that sometimes a rate is set by a
    predetermined and concrete formula rather than a pre-set number.
    See, e.g., Public Utilities Comm’n v. FERC, 
    254 F.3d 250
    , 254 (D.C.
    Cir. 2001) (explaining that, because the charged rate is subject to
    change according to the formula’s fixed and predictable components,
    fluctuations in the overall cost to consumers under a true formula rate
    are not retroactive even though the ultimate charge to the customer
    may be unknown at the time of purchase).
    5
    One way that electricity is transferred throughout the PJM
    market is through competitive auctions. See Hughes, 136 S.
    Ct. at 1293. In same-day auctions, generators bid to provide
    the immediate delivery of electricity needed to slake sudden
    spikes in demand. In next-day auctions, generators bid to
    satisfy anticipated near-term demand. And in a “capacity
    auction,” generators make bids that, if accepted, bind them to
    providing needed electricity in the longer term. See 
    id. Old Dominion
    Electric Cooperative is a not-for-profit
    electrical generation and transmission utility that participates
    as both a generator and a load-serving entity (that is, a public
    utility) in the PJM market. This case involves three of Old
    Dominion’s natural-gas-fired electrical power plants in
    Maryland and Virginia: Marsh Run, Louisa, and Rock Springs.
    Each of those facilities is a “generation capacity resource,”
    which means that Old Dominion contractually committed itself
    to offer all of those units’ available generation capacity into
    PJM’s daily market and to generate electricity whenever called
    upon by PJM. Old Dominion Elec. Coop., 151 FERC ¶
    61,207 at P 2 n.2 (2015).
    PJM fulfills its oversight and market management
    responsibilities through rules prescribed in (1) the PJM Open
    Access Transmission Tariff and (2) the PJM Operating
    Agreement, to which participating generators like Old
    Dominion subscribe. Several provisions of those instruments
    bear on the dispute in this case.
    First, the Operating Agreement empowers PJM to take
    “measures appropriate to alleviate an Emergency, in order to
    preserve reliability” in the electricity market and to meet
    consumer need. Agreement § 1.6.2(vii). That authority
    includes directing generators “to start, shutdown, or change
    [the] output levels of [their] generations units[.]” Agreement
    6
    § 1.7.20(b).     According to Old Dominion, generators
    “understand[] PJM dispatch instructions to be determinations
    with which [they are] expected to comply” under the PJM
    Tariff § 1.8.2(a). J.A. 56 n.2.
    Second, generation capacity resources “must offer”
    capacity into the same-day and day-ahead auctions.
    Agreement § 1.10.1A(d). That “must offer” requirement
    commands generators to submit offers for all “available
    capacity” of any designated capacity generation facilities.
    Tariff § 1.10.1A(d).
    Third, the Tariff caps the prices at which generators may
    offer their capacity into the day-ahead market at
    $1,000/megawatt-hour. Tariff § 1.10.1A(d)(viii).
    Finally, Commission regulations require transmission
    organizations, like PJM, to self-monitor their markets and
    report any issues affecting their reliability, efficiency, and non-
    discriminatory operation. 18 C.F.R. § 35.34(k)(6). PJM
    retained a private company, Monitoring Analytics, LLC
    (“Monitor”) to act as its independent market monitor. Monitor
    has moved to intervene in this appeal.
    C
    In January 2014, a Polar Vortex brought extraordinarily
    cold temperatures for an unusually prolonged period of time to
    broad swaths of the continental United States, including the
    PJM market region. The plunging temperatures triggered a
    corresponding surge in the demand for electrical power to heat
    homes and businesses. Increased demand for power generation
    caused a regional spike in the price of natural gas, which is one
    of the primary fuels that generators like Old Dominion use to
    produce electricity.
    7
    Invoking market rules, PJM used its emergency authority
    to make sure that the electrical service needed to meet
    consumer demand was available and reliable. As part of those
    actions, beginning in early January, PJM repeatedly called on
    its generators to prepare for additional outputs of electricity.
    As relevant here, PJM tasked Old Dominion with ensuring that
    three of its generation capacity resources (Rock Springs,
    Louisa, and Marsh Run) would be able to fulfill their
    contractual commitments and run at full capacity during
    several anticipated acute spikes in energy demand: January 7–
    9, January 23, and January 28.
    To meet that need, Old Dominion had to purchase natural
    gas at inflated prices. In turn, Old Dominion’s marginal costs
    to    generate     electricity    spiked     to   approximately
    $1,200/megawatt-hour. PJM Interconnection, LLC, 146 FERC
    ¶ 61,041 at P 2 (2014). But the Tariff prohibited it from
    submitting bids for its electricity in the day-ahead auction that
    exceeded $1,000/megawatt-hour. In other words, runaway
    generation costs driven by extreme weather and market
    conditions ran headlong into the PJM Tariff’s pre-set rate cap.
    As a result, some generators, including Old Dominion, were
    forced temporarily to sell energy capacity at a loss. See also
    Duke Energy Corp. v. FERC, No. 16-1133 (D.C. Cir. June 15,
    2018).
    Old Dominion sought assurances from PJM that it would
    be able to recover those losses. On January 21, 2014, PJM
    posted a statement on its website that reiterated the generators’
    contractual obligation to offer full capacity into the day-ahead
    market at a price not to exceed $1,000/megawatt-hour,
    notwithstanding the unanticipated circumstances. PJM also
    expressed its intent to file with the Commission “as soon as
    practical” a “retroactive waiver” of the rate cap to compensate
    8
    those generation capacity resources whose costs for electricity
    generation had exceeded the Tariff’s rate cap. J.A. 137. PJM
    further stated that it would file a second waiver request seeking
    a temporary, prospective waiver of the rate cap provision.
    Two days later, PJM filed two concurrent waiver requests
    with the Commission. In one waiver, PJM requested
    immediate “make whole” relief—to be effective the next day
    (i.e., January 24, 2014)—that would allow generators to
    recover the difference between the actual costs of generating
    capacity and the Tariff’s rate cap for “must offer” bids
    submitted in the price auctions for forthcoming electricity
    generation.
    The second waiver sought to stop the financial
    hemorrhaging by waiving the filed Tariff’s rate cap “only
    prospectively.” J.A. 140. With that waiver, generation
    capacity resources that were contractually obligated to
    continue providing electricity could submit bids into the same-
    day and next-day auctions that exceeded the $1,000/megawatt-
    hour rate cap. That waiver would apply going forward until
    March 31, 2014.
    Notably, and contrary to PJM’s January 21 website post,
    neither waiver requested retroactive relief. The Commission
    promptly granted both waivers. PJM Interconnection, LLC,
    146 FERC ¶ 61,041, on reh’g, 149 FERC ¶ 61,059 (2014);
    PJM Interconnection, LLC, 146 FERC ¶ 61,078 (2014), on
    reh’g, 149 FERC ¶ 61,060 (2014).
    As it turned out, PJM had overestimated the amount of
    energy that would be required on several of the Polar Vortex’s
    coldest days. To correct its mistake, PJM reduced or cancelled
    some of its orders for generation services.
    9
    But that was too late to help the many generators that had
    purchased the expensive natural gas needed to supply the
    forecasted output and that had sunk start-up costs responding
    to now-cancelled or curtailed orders. Old Dominion had to
    resell some of its excess natural gas at a loss after the surge in
    demand had subsided and the market price had dropped. And
    it absorbed losses on the excess quantities it could not, or did
    not, resell. More specifically, the Polar Vortex and PJM’s call
    for generation capacity resources to meet the anticipated spike
    in demand caused Old Dominion to incur losses in the form of:
    (i) actual costs in excess of the $1,000/megawatt-hour rate that
    pre-dated the January 24, 2014 waiver; (ii) start-up costs
    arising from PJM’s cancelled requests for service; and (iii)
    costs that arose when units dispatched to generate for a certain
    period were instructed to cease operations earlier than
    anticipated.
    D
    Old Dominion requested that the Commission provide
    dual-faceted relief for its losses. First, Old Dominion sought
    to have the effective date of PJM’s “make whole” waiver
    extend back one additional day to cover losses it suffered on
    January 23, the date PJM filed its waiver request with the
    Commission. PJM Interconnection, LLC, 146 FERC ¶ 61,041
    (2014). Second, Old Dominion requested a waiver of
    provisions in the Tariff and PJM Agreement proscribing
    retroactive rate charges so that it could recover the start-up
    costs of its unused energy production that it incurred when PJM
    cancelled or cut back on prior orders for service. Combined,
    Old Dominion claimed nearly $15 million in costs attributable
    to PJM’s emergency measures during the Polar Vortex.
    The Commission denied Old Dominion’s request in all
    respects. The Commission agreed with Old Dominion’s
    10
    concession that the filed Tariff precluded its requested
    retroactive changes to the rates. The Commission also found
    that Old Dominion’s ratepayers lacked sufficient notice that the
    approved rate was subject to change. For those reasons, the
    Commission concluded that Old Dominion’s waiver was
    impermissible under the filed rate doctrine and the closely
    related rule against retroactive ratemaking.
    Old Dominion sought rehearing based entirely on grounds
    of fairness and equity. Specifically, it argued that the
    Commission has discretionary authority to “retroactively
    waive a tariff in order to authorize ‘actions other than those
    prescribed by the filed rate[]’” when “it concludes that the
    ‘tariff should not be applied under a particular out-of-the-
    ordinary set of facts[.]’” Old Dominion Elec. Coop., 154 FERC
    ¶ 61,155 at P 11 (2016).
    The Commission disagreed, explaining that Old
    Dominion’s requested waiver constituted “a classic example of
    a violation of the filed rate doctrine and the prohibition of
    retroactive ratemaking.” Old Dominion Elec. Coop., 154
    FERC ¶ 61,155 at P 9. The Commission also found that this
    court’s precedent stripped it of any power to disregard on
    equitable grounds either the filed rate doctrine or the rule
    against retroactive ratemaking, no matter how compelling the
    equities might be. 
    Id. at P
    17 (citing Columbia 
    III, 895 F.2d at 797
    ).
    II
    We review final orders of the Commission, 16 U.S.C.
    § 825l(b), under the Administrative Procedure Act’s familiar
    “arbitrary and capricious” standard, 5 U.S.C. § 706(2)(A); see
    FERC v. Electric Power Supply Ass’n, 
    136 S. Ct. 760
    , 782
    (2016). Under that standard, we defer to the Commission’s
    11
    reasonably explained decisions, Alcoa Inc. v. FERC, 
    564 F.3d 1342
    , 1347 (D.C. Cir. 2009), and to its interpretations of its
    own precedent, NSTAR Elec. & Gas Corp. v. FERC, 
    481 F.3d 794
    , 799 (D.C. Cir. 2007). Those same principles apply with
    equal force to our review of the Commission’s application of
    the filed rate doctrine, which is “Chevron-like in nature.” Old
    Dominion Elec. Coop. v. FERC, 
    518 F.3d 43
    , 48 (D.C. Cir.
    2008) (internal quotation marks omitted). Put simply, we
    afford the Commission’s interpretation of the filed Tariff and
    the PJM Operating Agreement “substantial deference” unless
    “the tariff language is unambiguous.” 
    Id. (internal quotation
    marks omitted).
    A
    The governing law is not in question here. The filed rate
    doctrine and the rule against retroactive ratemaking leave the
    Commission no discretion to waive the operation of a filed rate
    or to retroactively change or adjust a rate for good cause or for
    any other equitable considerations. Columbia 
    III, 895 F.2d at 794
    –797.       These corollary rules operate as a nearly
    impenetrable shield for consumers, ensuring rate predictability
    and preventing discriminatory or extortionate pricing. West
    
    Deptford, 766 F.3d at 12
    ; see Arkansas 
    La., 453 U.S. at 578
    (explaining that not even “the Commission itself” possesses the
    authority to contravene the prospective application of rates).
    Given those emphatic rules against retroactively changing
    filed rates and the absence of any equitable waiver authority in
    the Commission, the only question in this case is whether
    granting Old Dominion the waiver it sought would have
    violated one of those prohibitions. We agree with the
    Commission that either waiver would have run afoul of both.
    12
    To begin with, there is no dispute that the PJM Tariff’s
    filed rate did not allow the cost recovery that Old Dominion
    seeks. In fact, Old Dominion repeatedly conceded before the
    Commission and this court that the filed Tariff categorically
    precluded its compensation for losses caused by the rate cap.
    That would seem to be the end of the matter. But Old
    Dominion argues that recouping its losses would be consistent
    with the filed rate doctrine because ratepayers were on notice
    that the Tariff set a market rate for electricity, and the Polar
    Vortex altered that market rate.
    Close, but no cigar. Old Dominion is correct that no
    violation of the filed rate doctrine occurs when “buyers are on
    adequate [advance] notice that resolution of some specific issue
    may cause a later adjustment to the rate being collected at the
    time of service.” Natural Gas Clearinghouse v. FERC, 
    965 F.2d 1066
    , 1075 (D.C. Cir. 1992). When the very terms of the
    filed rate warn customers, at the time they contract for service,
    that the price charged will fluctuate based on an identified
    formula with specified cost drivers, then the rate is allowed to
    change when fluctuations in those cost drivers occur. That,
    after all, is how formulae work. And that comports with the
    filed rate doctrine because the rate changes are foreordained,
    not retroactive. See, e.g., Public Utilities 
    Comm’n, 254 F.3d at 254
    (explaining the well-established acceptability of formula
    rates that specify the cost components that form the basis of the
    rates a utility charges its customers); Transwestern Pipeline
    Co. v. FERC, 
    897 F.2d 570
    , 578 (D.C. Cir. 1990) (“The
    Commission need not confine rates to specific, absolute
    numbers but may approve a tariff containing a rate ‘formula’
    or a rate ‘rule’ * * *; it may not, however, simply announce
    some formula and later reveal that the formula was to govern
    from the date of announcement[.]”).
    13
    Old Dominion’s notice theory does not work in this case.
    Old Dominion has failed to identify any Tariff provisions that
    openly specify the type of market-variable cost components
    required for formula rates. Cf. Public Utilities 
    Comm’n, 254 F.3d at 255
    (citing, as an example, rate increases caused by new
    wage agreements where the utility agreed to a formula rate with
    a labor cost component); West 
    Deptford, 766 F.3d at 22
    (ratepayers have notice that rates determined by filed formulas
    will be determined according to the formula); 
    NSTAR, 481 F.3d at 801
    (rates may constantly change as long the changes are
    consistent with the formula on file with the Commission).
    Plus, if there were such variables, then they presumably
    would run in both directions. Yet tellingly, Old Dominion is
    unable to cite a single instance in which bull market conditions
    for utilities produced a refund to consumers of over-billed
    amounts.
    The coup de grace for Old Dominion’s theory is that the
    filed rate on its face assured customers that, however the
    market might change, charges would be capped at $1,000 per
    megawatt-hour.          Tariff, Attachment K, Appendix
    § 1.10.1A(d)(viii). Customers, in other words, were on explicit
    notice that, although market forces might cause some variation
    within a range, the rates charged would never exceed the
    agreed-upon rate cap. Old Dominion points to nothing in the
    Tariff’s terms that lifts that cap for the charges for which it
    seeks recoupment. To toss that cap aside after the fact just
    because it did exactly what a cap is supposed to do—serve as a
    firm ceiling on market prices—would retroactively rewrite the
    terms of the filed rate. The filed rate doctrine and rule against
    retroactive rulemaking flatly forbid such a result.
    Old Dominion argues alternatively that PJM’s January 21
    statement on its website, noting that it was seeking FERC’s
    14
    approval for certain generators to exceed the rate-cap, gave
    customers the required prospective notice that emergency
    retroactive rate increases could ensue. That argument fails at
    every step.
    First, the website statement was not filed with the
    Commission. That is required for all rate changes. 16 U.S.C.
    § 824d(d); see West 
    Deptford, 766 F.3d at 23
    –24; see also City
    of Piqua v. FERC, 
    610 F.2d 950
    , 954 (D.C. Cir. 1979). As a
    result, the statement did not provide the legally required notice
    to even first-line purchasers in the wholesale markets, such as
    load-serving entities, let alone to the downstream retail
    customers. See Columbia 
    III, 895 F.2d at 797
    (citing Columbia
    Gas Trans. Corp. v. FERC, 
    831 F.2d 1135
    , 1140–1141 (D.C.
    Cir. 1987), abrogated on other grounds by 
    Transwestern, 897 F.2d at 579
    ); cf. City of 
    Piqua, 610 F.2d at 954
    –955 (approving
    a seemingly retroactive rate because a pre-existing contractual
    agreement provided ratepayers prospective notice of the
    impending rate change from the date of the contract).
    Second, the website post was limited to retroactive “make
    whole” payments (which the actual waiver did not request), and
    to prospective relief allowing generators to submit cost-based
    offers into the day-ahead market above $1,000/megawatt-hour.
    On top of that, the website post reiterated that, unless and until
    the Commission granted the prospective waiver of the Tariff’s
    rate cap provision, the market rules remained in effect—
    including the $1,000 rate cap. To be sure, the Commission
    ultimately waived the sixty-day statutory notice period and
    granted PJM’s requested prospective relief effective January
    24, 2014. That just confirms that the Commission stuck to its
    prospective-only authority to adjust rates and that it left the past
    rates as it found them.
    15
    For all of those reasons, we uphold the Commission’s
    decision denying retroactive rate adjustments and deny Old
    Dominion’s petition for review.
    B
    Turning to Monitor’s pending motion to intervene, we
    hold that Monitor has no legally cognizable interest in this case,
    and thus lacks standing. Accordingly, its motion to intervene
    is denied.
    Intervenors become full-blown parties to litigation, and so
    all would-be intervenors must demonstrate Article III
    standing. 2 See Fund for Animals, Inc. v. Norton, 
    322 F.3d 728
    ,
    732-733 (D.C. Cir. 2003). To do so, the prospective intervenor
    must establish injury-in-fact to a legally protected interest,
    causation, and redressability. See Crossroads Grassroots
    Policy Strategies v. FEC, 
    788 F.3d 312
    , 316 (D.C. Cir. 2015).
    This court also looks to the timeliness of the motion to
    intervene and to whether the existing parties can be expected
    to vindicate the would-be intervenor’s interests. See Deutsche
    Bank Nat’l Trust Co. v. FDIC, 
    717 F.3d 189
    , 192 (D.C. Cir.
    2013). The Monitor, however, has failed to establish that the
    2 The Supreme Court recently held that an intervenor of right
    who seeks distinctive relief must demonstrate its own Article III
    standing. Town of Chester v. Laroe Estates, Inc., 
    137 S. Ct. 1645
    ,
    1651 (2017). But that decision had no occasion to consider whether
    all intervenors must do so. Town of Chester thus does not cast doubt
    upon, let alone eviscerate, our settled precedent that all intervenors
    must demonstrate Article III standing. Cf. Dellums v. United States
    Nuclear Regulatory Comm’n, 
    863 F.2d 968
    , 987 n.11 (D.C. Cir.
    1988) (intervening Supreme Court precedent must clearly dictate a
    departure from circuit law before a subsequent panel is free to
    discard an earlier panel’s holding).
    16
    litigation implicates any legally protected interest sufficient to
    confer Article III standing.
    The role of the Monitor is, as explained in the PJM
    Agreement, to “objectively monitor, investigate, evaluate and
    report on the PJM Markets, including, but not limited to,
    structural, design or operational flaws” that the markets might
    display. Monitor Br. A10–A11. 3 PJM retained the Monitor as
    an outside consultant to undertake those market-monitoring
    tasks.    The Monitor is charged with “mak[ing] such
    recommendations” to PJM “as [it] shall deem appropriate” to
    “address design flaws, structural problems, compliance” and
    other market anomalies that the Monitor detects. Monitor Br.
    A4.
    The Monitor’s role, however, is much in the nature of an
    auditor—it is largely confined to observing the market’s
    operations and then offering recommendations to PJM. The
    Monitor has no authority to enforce or to interpret the PJM
    Agreement or Tariff, to direct changes in the market’s
    operations, to alter market rules, or to police individual
    members’ compliance. Other than making some regulatory
    filings, all the Monitor can do is inform the Commission,
    authorized government agencies, or PJM’s participating
    members if it disagrees with PJM’s implementation of the
    market rules or operation of the PJM market. Beyond its
    contractually assigned tasks, the Monitor has no independent
    legal interest of its own in the PJM markets.
    That is not enough for Article III. The Monitor’s
    professional assignment to monitor the markets so that PJM
    and its members can promote the market’s efficient and
    3 We note that none of the relevant Agreement provisions,
    namely Attachment M, are in the record for this court’s inspection.
    17
    successful operation does not invest the Monitor with any
    legally cognizable rights concerning either how PJM addresses
    Old Dominion’s application for retroactive relief or how Old
    Dominion complies with the Tariff or Agreement. The
    Monitor is not a contractual party to either the Tariff or the
    Agreement, and it has no legal interests that are affected one
    way or the other by any parties’ non-compliance. It is, instead,
    an outside observer hired to study and report objectively on the
    market’s operations.
    The Monitor nonetheless asserts that its “responsibility to
    monitor the markets” under the Agreement would be impaired
    if Old Dominion prevails in this action. Monitor Br. A4. The
    Monitor adds that it was a “core participant,” not just a “mere
    observer,” in the Commission proceeding that led to the order
    on review. 
    Id. The Monitor
    further worries that, if the
    Commission’s order were reversed, then the competitive
    market design that the Monitor is “charged to protect” will need
    “repair,” requiring the Monitor to “redeploy its limited
    resources in an effort * * * to craft new rules that are harder to
    undermine.” Monitor Br. A6.
    We fail to see how this proceeding imperils any legally
    protected interest of the Monitor. Whether Old Dominion wins
    or loses, the Monitor’s ability to observe the market’s
    operations and to make recommendations or to inform
    potentially interested parties of its observations remains the
    same.
    Nor did the Commission’s order determine any legal rights
    belonging to the Monitor or benefit the Monitor in any
    discernable way. The Monitor thus has no “significant and
    direct interest” in defending the Commission’s denial of Old
    Dominion’s requested relief. 
    Crossroads, 788 F.3d at 318
    .
    The Monitor faces no “threatened loss” from this court’s
    18
    review, nor did it acquire any tangential benefit from the
    Commission’s order. Cf. Fund for 
    Animals, 322 F.3d at 733
    (allowing Mongolian entity to intervene where Secretary of
    Fish and Wildlife’s decision to not list argali sheep as
    endangered indirectly benefitted Mongolian tourism and
    conservation industries); Military Toxics Project v. EPA, 
    146 F.3d 948
    , 954 (D.C. Cir. 1998) (allowing manufacturers’
    association to intervene on the side of the EPA because some
    of its members indirectly benefitted from an EPA rule
    regarding munitions).
    The Monitor, for its part, identifies no law that vests it with
    independent legal rights. The Monitor is not a creature of
    statute and operates under no affirmative duty imposed by
    public law. Quite the contrary, even its existence is a matter
    entirely within PJM’s discretion. And its function is limited to
    monitoring, advising, encouraging compliance, and informing
    others through regulatory filings and other informal
    communications, none of which are at stake in this case. Cf.
    Sea-Land Serv., Inc. v. Department of Transp., 
    137 F.3d 640
    ,
    648 (D.C. Cir. 1998) (“[M]ere precedential effect within an
    agency is not, alone, enough to create Article III standing, no
    matter how foreseeable the future litigation.”).
    Because it lacks any legally cognizable interest or right in
    this proceeding, the Monitor lacks standing, and intervention is
    denied. We will, however, grant the Monitor amicus curiae
    status.
    *****
    For the foregoing reasons, we deny the petition for review
    and the motion to intervene, but we will allow the Monitor to
    participate as an amicus curiae.
    19
    So ordered.
    

Document Info

Docket Number: 16-1111

Citation Numbers: 892 F.3d 1223

Judges: Griffith, Millett, Tatel

Filed Date: 6/15/2018

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (17)

sea-land-service-inc-v-department-of-transportation-sea-land-service , 137 F.3d 640 ( 1998 )

columbia-gas-transmission-corporation-v-federal-energy-regulatory , 831 F.2d 1135 ( 1987 )

Fed. Energy Regulatory Comm'n v. Elec. Power Supply Ass'n , 136 S. Ct. 760 ( 2016 )

columbia-gas-transmission-corporation-v-federal-energy-regulatory , 895 F.2d 791 ( 1990 )

natural-gas-clearinghouse-v-federal-energy-regulatory-commission-anadarko , 965 F.2d 1066 ( 1992 )

consolidated-edison-company-of-new-york-inc-v-federal-energy-regulatory , 958 F.2d 429 ( 1992 )

Towns of Concord, Norwood, and Wellesley, Massachusetts v. ... , 955 F.2d 67 ( 1992 )

Fund for Animals, Inc. v. Norton , 322 F.3d 728 ( 2003 )

Alcoa Inc. v. Federal Energy Regulatory Commission , 564 F.3d 1342 ( 2009 )

Old Dominion Electric Cooperative, Inc. v. Federal Energy ... , 518 F.3d 43 ( 2008 )

Pub Util Cmsn St CA v. FERC , 254 F.3d 250 ( 2001 )

NSTAR Electric & Gas Corp. v. Federal Energy Regulatory ... , 481 F.3d 794 ( 2007 )

Military Toxics Project v. Environmental Protection Agency , 146 F.3d 948 ( 1998 )

transwestern-pipeline-company-v-federal-energy-regulatory-commission-the , 897 F.2d 570 ( 1990 )

The City of Piqua, Ohio v. Federal Energy Regulatory ... , 610 F.2d 950 ( 1979 )

Midwest Iso Transmission Owners v. Federal Energy ... , 373 F.3d 1361 ( 2004 )

Arkansas Louisiana Gas Co. v. Hall , 101 S. Ct. 2925 ( 1981 )

View All Authorities »