Clay Ammerman and Erin Ammernman v. the Ranches of Clear Creek Community Association, Inc. and the Ranches Od Clear Creek Architectural Review Committee ( 2018 )


Menu:
  • Opinion issued August 30, 2018
    In The
    Court of Appeals
    For The
    First District of Texas
    ————————————
    NOs. 01-17-00015-CV &
    01-17-00448-CV
    ———————————
    CLAY AMMERMAN AND ERIN AMMERMAN, Appellants
    V.
    THE RANCHES OF CLEAR CREEK COMMUNITY ASSOCIATION, INC.
    AND THE RANCHES OD CLEAR CREEK ARCHITECTURAL REVIEW
    COMMITTEE, Appellees
    On Appeal from the 506th District Court
    Waller County, Texas
    Trial Court Case Nos. 16-01-23529-A & 16-01-23529
    OPINION
    Appellants, Clay and Erin Ammerman, sued appellees, the Ranches of Clear
    Creek Community Association, Inc., the Ranches of Clear Creek Architectural
    Review Committee (collectively, “the Association”), and Johnny and Angela
    Wilson, for breach of contract and other causes of action alleging that the
    Association and the Wilsons violated applicable restrictive covenants.         The
    Wilsons then filed counter-claims against the Ammermans, asserting that the
    Ammermans also violated applicable deed restrictions. The trial court rendered
    summary judgment in favor of the Association and the Wilsons on all claims.1 On
    appeal, the Ammermans argue: (1) the trial court erred in granting summary
    judgment dismissing the Ammermans’ claims on statute of limitations grounds
    because the Ammermans presented some evidence raising a fact issue regarding
    when their cause of action for breach of the Covenants and a declaratory judgment
    against the Wilsons and the Association accrued and when they could have
    discovered their cause of action; and (2) the trial court erred in granting summary
    judgment dismissing their claims on the ground that the Association and the
    Wilsons had conclusively proved that they did not violate the relevant restrictive
    covenants because they presented some evidence that the Association acted
    arbitrarily and capriciously in approving the Wilsons’ building plans; and (3) the
    trial court erred in granting summary judgment in favor of the Wilsons on their
    claim that the Ammermans breached the restrictive covenants in making changes
    1
    The Ammermans’ claims against the Wilsons were addressed in cause number 16-
    01-23529 and resulted in appellate cause number 01-17-00448-CV. The
    Ammermans’ claims against the Association were severed into trial court cause
    number 16-01-23529-A and resulted in appellate cause number 01-17-00015-CV.
    2
    to the buildings on their own property because the alleged violations were barred
    by the statute of limitations.
    We affirm the trial court’s summary judgment dismissing the Ammermans’
    claims against both the Wilsons and the Association. We reverse the trial court’s
    grant of summary judgment in favor of the Wilsons on their counterclaims against
    the Ammermans and remand for further proceedings consistent with this opinion.
    Background
    The Ranches of Clear Creek (the Community) is a gated community in
    Waller County, Texas. The Declaration of Covenants and Restrictions for the
    Ranches of Clear Creek (the Covenants) that were filed with Waller County
    require, among other things, in Article VI, section 3, that all improvements or
    alterations to improvements must be approved in writing by the Architectural
    Review Committee (ARC) after the submission of certain required documentation.
    The Covenants further provide that all improvements to property must be made
    within the designated predetermined “Building Envelope,” which is defined as
    “that certain contiguous and regularly shaped three (3) acre portion of each Lot to
    be designated by each Owner and approved by the Residential Review Committee
    prior to the commencement of any construction upon any Lot.” Article VI, Section
    9 of the Covenants states:
    The Building Envelope of each lot shall be located so that same is as
    far as reasonably possible from the Building Envelope on all other
    3
    contiguous Lots. In the event that a Building Envelop has not been
    established on all contiguous tracts then the Building Envelope shall
    be located as follows: (i) in a manner that will maintain the integrity
    of a rural ranch setting; (ii) be set back from any abutting Street a
    minimum of 100 feet; (iii) have a side yard set back a minimum of
    100 feet; and (iv) have a rear yard set back a minimum of 100 fee.
    Once established, the Building Envelope shall not be modified nor
    changed without Residential ARC approval.
    The Covenants give the Association’s Architectural Review Committee (the ARC)
    “exclusive jurisdiction over all original construction on the Lots.”
    The Covenants also govern the types of structures that may be built. Article
    VII, section 3 provides, in part, that “[n]o detached garage or accessory building
    shall exceed one story in height without the written consent of the Residential
    ARC.” Article VII, section 4 governs garages, driveways, and sidewalks. It
    provides:
    Each Single Family Residence must have an attached or detached
    garage for a minimum of two (2) full size automobiles. Each Owner
    shall construct and maintain at his own expense a driveway from the
    garage of his or her residence to the abutting Street, including the
    portion of the driveway in the street easement, and the Owner shall
    repair at his expense any damage to the Street or drainage ditches
    occasioned by connecting the driveway thereto.
    Article VII, section 19 addressed requirements of outbuildings:
    No outbuilding or structure shall be permitted outside of the Building
    Envelope without prior written approval of the Residential ARC and
    must be located in such a manner as to be no nearer any street, or
    common area, than the rear of the primary residence. No more than
    three (3) outbuildings or other structures, temporary or permanent,
    will be allowed without approval of the Residential ARC.
    4
    The Covenants further state that the purpose of the Association is to, among
    other things, “providing for the maintenance and preservation of the Area of
    Common Responsibility and the facilities of the Association and architectural
    control of the Lots.” The Covenants vested the Association’s Board with rule-
    making authority to “exercise business judgment and reasonableness on behalf of
    the Association” in adopting, amending, repealing, and enforcing the rules and
    regulations necessary to implement the Covenants.
    The Ammermans purchased Lot 28, a 30.6-acre parcel, in May 2006. The
    Wilsons purchased lot 29, a 16.8-acre parcel of land, several months later. Lots 28
    and 29 are contiguous. Each lot had a predetermined Building Envelope within
    which the owner was permitted to construct a residence and other buildings. The
    Ammermans began to develop their property, Lot 28, immediately after they
    purchased it. In 2007, their barndominium was approved by the ARC with a
    changed Building Envelope, and the residence was completed in November of
    2008. In June and July 2012, the Ammermans constructed a shed outside of Lot
    28’s building envelope and, in January 2014, they added onto their shed outside
    Lot 28 in front of their barndominium.
    Subsequently, in 2015, the Wilsons began the process of building their
    retirement home on Lot 29, with ARC approval. The Ammermans investigated the
    proposed building location and came to believe that the Wilsons residence violated
    5
    the restrictive covenants governing the Community. Specifically, they alleged, but
    have not shown, that the Wilson’s building plan is not within the 2006
    predetermined Building Envelope.
    A.    The Ammermans’ Suit Against the Association and the Wilsons and
    Request for a Declaratory Judgment and Temporary Injunction
    On January 11, 2016, the Ammermans filed suit against the Association and
    the Wilsons. They alleged causes of action for breach of contract and declaratory
    judgment, asserting that the Association and the Wilsons had violated Article VI,
    Section 9 of the Covenants regarding the location of the building envelope for the
    Wilson’s lot. The Ammermans sought a declaratory judgment “regarding the
    construction and validity of the Covenants in order to determine the rights, status,
    and legal relations of the Ammermans and Defendants.” The Ammermans also
    sought a temporary injunction to prevent the Wilsons from building their proposed
    residence while litigation proceeded. The Ammermans’ subsequently amended
    their petition to add a cause of action against the Association for failing “to comply
    with their duties” and “by exercising their discretionary authority in an arbitrary
    and capricious manner.”
    The Association and the Wilsons answered, denying all of the Ammermans’
    claims and asserting various affirmative defenses, including that the Ammermans’
    claims were barred by the statute of limitations.
    6
    The trial court held a hearing on the Ammermans’ request for a temporary
    injunction. Clay Ammerman testified that he and his wife were among the first
    residents to purchase lots in the community, that they had purchased Lot 28
    because of its unique location and secluded nature, and that they immediately
    began construction of their primary residence. Ammerman acknowledged that he
    was aware at the time he purchased his lot of potential locations where his
    neighbors, the Wilsons, could build a residence on Lot 29. However, he testified
    that their proposed building location, or building envelope, violated the Covenants
    because their approved building site was not as far as reasonably possible from his
    residence and would affect the resale value of his home. Clay Ammerman also
    acknowledged that he had sought and obtained approval to move his own building
    envelope when building his home in 2007.
    On February 9, 2016, the trial court denied the request for injunctive relief.
    B.    The Wilsons’ April 28, 2016 Counterclaim and the Ammermans’ April
    29, 2016 Amended Petition and Application for Permanent Injunction
    On April 28, 2016, the Wilsons filed a counterclaim against the Ammermans
    for breach of contract and for a declaratory judgment, asserting that the
    Ammermans had breached the Covenants “by constructing their shed [and by]
    constructing a car-port and failing to construct a garage.”2 The Wilsons asked that
    2
    The Wilsons referred to the requirements of the Covenants generally in the
    original counterclaim but did not identify the particular provisions by number.
    7
    the trial court declare their rights with respect the Covenants and find that the
    Ammermans had breached them.
    The Ammermans did not file an answer to the Wilsons’ counter-petition.
    However, the next day, April 29, 2016, they filed an amended petition and an
    application for permanent injunction containing additional information regarding
    the parties. The Ammermans continued to assert that the Wilsons and the
    Association had violated Article VI, Section 9 of the Covenants, specifically the
    part stating that “[t]he Building Envelope of each lot shall be located so that same
    is as far as reasonably possible from the Building Envelope on all other contiguous
    lots.”
    C.       The Association’s and the Wilsons’ May 9, 2016 Joint Motion for
    Summary Judgment
    On May 9, 2016, the Association and the Wilsons filed a joint traditional
    motion for summary judgment on the Ammermans’ claim that they had both
    breached Article VI, Section 9 of the Covenants. They argued that when the
    Ammermans and the Wilsons purchased their lots in 2006, the Wilsons’ lot, Lot
    29, “already had a pre-determined Building Envelope that was set by the
    [Association] and the developer of the subdivision.” They argued: “Despite the
    Their complaints relate to Article VII, section 4’s requirement that each residence
    have a garage; Article VII, section 19’s requirement that outbuildings be placed
    behind the primary residence; Article VI, section 3’s requirement that an owner
    obtain written approval from the ARC for all improvements; and Article VI,
    section 9’s provisions regarding the building envelope.
    8
    undisputed fact that the Ammermans were aware of the location of Lot 29’s
    Building Envelope in 2006, they have waited nearly a decade and until the eve of
    the construction of the Wilsons’ home to file a frivolous suit complaining about
    information they have been in possession of since at least May 2006.” They
    asserted that the Ammerman’s claims were barred by the statute of limitations.
    In the alternative, the Association and the Wilsons argued in their traditional
    motion for summary judgment that the “governing documents give the
    [Association] and [ARC] discretion to determine the placement of all Building
    Envelopes as well as the placement of structures within the Building Envelopes,”
    and thus the Ammermans could not raise a genuine issue of material fact on their
    claims that either the Association or the Wilsons had breached Article VI, section 9
    of the Covenants.
    The Association and the Wilsons supported this motion for summary
    judgment with the affidavit of Jack Owen, the president of the Association and the
    custodian of the Association’s records. He averred, in relevant part, that the
    Ammermans purchased Lot 28 in May 2006, that the Wilsons purchased Lot 29 in
    September 2006, and that “[a]s of January 3, 2016, the Wilsons were given
    approval to begin construction of their home.” Owen stated, “When determining
    approval for the Wilsons, the [Association] and ARC determined that the Wilsons’
    9
    Building Envelope is as far as reasonably possible from all other contiguous
    owners in the [Community].”
    The Association and the Wilsons also included the transcript from the
    temporary injunction hearing as support for the motion for summary judgment.
    They cited Clay Ammerman’s testimony that he was aware of the potential
    building sites for the Wilsons’ home when he purchased his lot in 2006, his
    acknowledgment that the previously proposed building cite for the Wilsons’ home
    was “closer to [his] primary residence . . . than the envelope where the Wilsons”
    had been approved to build their home in 2016, and that Clay Ammerman was
    aware that people had to build within their designated building envelope when he
    purchased his lot in 2006.
    The motion for summary judgment was also accompanied by the declaration
    of Johnny Wilson, in which he stated that “each individual lot was listed for sale
    with a Building Envelope that was predetermined by the HOA [the Association]
    and the ARC,” and, thus, when he and his wife purchased their lot in September
    2006, “the Building Envelopes for all of the lots, including Lot 29, were already
    set. As such, we were not only aware of Lot 29’s Building Envelope, but also our
    neighbor’s, Clay and Erin Ammerman’s . . . Building Envelope.” He went on to
    state that “one of the reasons we ultimately decided to purchase Lot 29 was
    because of the Building Envelope.” He stated that he and his wife had owned Lot
    10
    29 for nearly ten years before deciding to build a retirement home, and the plans
    and specifications for the home that were approved by the Association and ARC
    “showed that the home would be located inside of our Building Envelope.” He
    stated, “Notably, we have not ever requested that our Building Envelope be
    modified or changed and so, it has remained in its original location for ten years.”
    The Association and the Wilsons also presented the trial court with a copy of
    the Covenants and other documents governing the Community, a copy of the letter
    from the ARC approving the Wilsons’ building plans, and a copy of a letter from
    the ARC to the Ammermans explaining its decision to approve the location of the
    Wilsons’ home. The letter to the Ammermans stated, in part, “Regarding the ARC
    decision to approve the location of the Wilson’s home site on Lot 29 the ARC has
    placed considerable effort to address your concerns as well as the effect on the
    Wilsons of moving their building envelope as you have suggested.” The ARC
    specifically noted that “the Wilsons’ requested home site on Lot 29 is within the
    ‘as reasonably possible’ distance required by our [Covenants]” and that the original
    building site “was closer to the cul-de-sac than the Wilsons have requested, [and]
    therefore the building envelope has already been set back.”
    In their response to the motion for summary judgment, the Ammermans
    asserted generally that after they became aware of the Wilsons’ building location
    in January 2016, they investigated and discovered “that the Wilsons were building
    11
    their residence in a location different than what was originally platted by the
    developer,” referring apparently to the fact that the Wilsons had chosen a site for
    their home within their building envelope that was different from the building site
    originally noted by the developer. The Ammermans contended, however, that the
    Wilsons’ “building envelope was changed and/or modified based on the December
    16, 2015 building plans submitted by the Wilsons,” citing the letters from the ARC
    approving the Wilsons’ building and explaining its decision to the Ammermans as
    evidence to support their contention. The Ammermans did not dispute that a four-
    year statute of limitations applied to their claims for breach of contract and
    declaratory judgment, but they argued that their limitations period did not begin to
    run until January 2016 when they first received notice from the ARC that it had
    approved “a new build location in breach of the Covenants[.]” The Ammermans
    also asserted that the discovery rule applied to their claims because their injury was
    inherently undiscoverable until the Wilsons began to develop their property.
    The Ammermans supported their response with, among other documents, the
    affidavit of Clay Ammerman, in which he provided details of the building of his
    own residence. He stated, “During the development of our Lot, we were required
    by the then existing ARC to incur substantial expenses planting foliage to screen
    off our property from the then platted build location on Lot 29.” He further averred
    that, based on the details of the Wilsons’ construction, the “recently approved build
    12
    location renders the foliage we were required to plant useless, as it does not
    provide any screening where the Wilsons are now approved to build.” He stated
    that the Wilsons’ home would be visible from the entrance to his home and that the
    build site “is a mere 100 yards from our property line, resulting in the Wilsons’
    newly approved building location being not as far as reasonably possible from our
    building envelope.”
    D.    The Ammermans’ June 1, 2016 Amended Petition and June 14, 2016
    Motion for Summary Judgment on the Wilsons’ Counterclaim
    On June 1, 2016, while the Association’s and the Wilson’s joint traditional
    motion for summary judgment was still pending, and before the trial court ruled on
    their original claims regarding Article VI, Section 9 of the Covenants, the
    Ammermans filed a second amended petition, asserting new claims for breach of
    contract and declaratory judgment against the Association.        In their amended
    petition, the Ammermans contended again that the Association and the Wilsons
    had breached Article VI, Section 9 of the Covenants, and they added claims that
    the Association breached Article II, Sections 1 and 4, Article VI sections 3, and
    Article VII, section 3 in connection the approval of the Wilsons’ building site. The
    Ammermans asked the trial court to declare their rights with respect to the
    additional covenants as well as with respect to Article VI, Section 9 pursuant to the
    Declaratory Judgments Act, Texas Civil Practice and Remedies Code section
    37.004(a).
    13
    The Ammermans also asserted that the Association had violated Property
    Code sections 202.004 and 215.009 by approving the Wilson’s building plans.
    Section 202.004 provides, in relevant part:
    (a) An exercise of discretionary authority by a property owners’
    association or other representative designated by an owner of real
    property concerning a restrictive covenant is presumed reasonable
    unless the court decides by a preponderance of the evidence that the
    exercise of discretionary authority was arbitrary, capricious, or
    discriminatory.
    TEX. PROP. CODE ANN. § 202.004 (West 2014). Likewise, section 215.009 provides
    that “[a] property owners’ association may enforce its restrictive covenants . . . by
    exercising discretionary authority relating to a restrictive covenant unless a court
    has determined by a preponderance of the evidence that the exercise of
    discretionary authority was arbitrary, capricious, or discriminatory. . . .”      
    Id. § 215.009
    (West 2014).
    On June 14, 2016, the Ammermans filed their own motion for summary
    judgment asserting that the Wilsons’ counterclaims were barred by the statute of
    limitations and laches. The Wilsons responded, asserting that they had no way to
    know that the Ammermans had not complied with the Covenants until Ammerman
    testified at the temporary injunction hearing regarding their lack of written
    approval by ARC for their improvements and other deviations from the Covenants.
    14
    E.    The Trial Court’s July 6, 2016 Order on the Association’s and the
    Wilsons’ Traditional Motion for Summary Judgment
    On July 6, 2016, the trial court granted in its entirety the Association’s and
    the Wilsons’ joint traditional motion for summary judgment on the Ammermans’
    claims that the Wilsons and the Association had breached Article VI, section 9 of
    the Covenants. It specifically ruled that the Association and the Wilsons had
    established both that the statute of limitations barred the Ammermans’ breach of
    contract and declaratory judgment claims and that the Association and the Wilsons
    had established as a matter of law that neither had violated Article VI, Section 9 of
    the Covenants. The trial court also awarded reasonable and necessary attorneys’
    fees to the Wilsons and the Association in an amount to be determined.
    F.    The Trial Court’s July 18, 2016 Order on the Ammermans’ Motion for
    Summary Judgment
    On July 18, 2016, the trial court granted the Ammermans’ motion for
    summary judgment on the Wilsons’ counterclaims on limitations grounds in part
    and denied it in part. The trial court ruled that the Ammermans’ “claim in the
    Motion that the statute of limitations has passed on [the Wilsons’] [counter-claims]
    for breach of contract on the construction of the Barndominium is hereby
    GRANTED.” The trial court denied summary judgment on the Wilsons’ remaining
    breach of contract counterclaims, specifically denying the portion of the
    Ammermans’ motion arguing that claims involving construction and modification
    15
    of the equipment building and the declaratory judgment claims were barred by the
    statute of limitations. These claims, therefore, continued to go forward.
    G.    The Association’s August 10, 2016 Second Traditional Motion for
    Summary Judgment
    On August 10, 2016, the Association filed a second traditional motion for
    summary judgment to address the additional claims raised by the Ammermans in
    their June 1, 2016 amended petition, before the July 6, 2016 summary judgment
    was entered, regarding discovery of the Association’s and the Wilsons’ alleged
    breaches of the Covenants, and also regarding the Association’s alleged breach of
    Property Code sections 202.004 and 202.009. The Association sought dismissal of
    all of the Ammermans’ claims against it, including both the Ammermans’ claims
    related to discovery of the Wilsons’ alleged breaches of the Covenants within the
    statute of limitations, on which the trial court had already ruled, and the
    Ammermans’ new claims under the Property Code.             The Association set out
    detailed arguments asserting that it had not breached any provisions of the
    Covenants. And it asserted that the Ammermans’ related declaratory judgment
    claims failed for the same reasons as their breach of contract claims.
    The Association argued, again, that, as decided by the trial court’s July 6,
    2016 summary judgment order, the Ammermans were aware of the location of the
    pre-determined Building Envelope on the Wilsons’ property in 2006. Thus, any
    complaints that the Association violated Article VI, Section 9 or any other
    16
    provisions of the Covenants in determining or approving the location of the
    Wilson’s Building Envelope were barred by the statute of limitations for breach of
    contract. The Association further argued that the discovery rule did not apply
    because the summary judgment evidence established that Clay Ammerman was
    aware of the Wilsons’ potential building locations in 2006 and that he was aware
    that owners could build their home anywhere within the predetermined building
    envelope that was designated prior the Ammermans’ and Wilsons’ purchase of
    their respective lots in 2006. In the alternative, the Association argued in its
    second motion for traditional summary judgment that it did not breach any of the
    provisions asserted by the Ammermans in their June 1 amended petition.
    Finally, the Association moved for summary judgment on the Ammermans’
    claim that the Association had violated Property Code sections 202.004 and
    202.009. It argued that section 215.009 was not applicable in this case. The
    Association further argued in its motion for summary judgment that it did not
    violate the Property Code by acting arbitrarily or capriciously, in violation of
    section 202.004, when it approved the Wilsons’ building plans under Article VI,
    Section 9. The Association cited Property Code section 202.004(a), creating a
    presumption that a property owners’ association’s exercise of discretion “is
    presumed reasonable unless the court decides by a preponderance of the evidence
    that the exercise of discretionary authority was arbitrary, capricious, or
    17
    discriminatory.” See TEX. PROP. CODE ANN. § 202.004(a). The Association argued
    that the Ammermans had failed to rebut this presumption.
    H.    The Trial Court’s November 21, 2016 Order on the Association’s
    Second Traditional Motion for Summary Judgment
    On November 21, 2016, the trial court granted summary judgment against
    the Ammermans and dismissed all their claims against the Association in response
    the Association’s second traditional motion for summary judgment.3
    I.    The Trial Court’s December 13, 2016 Order Severing the Cases and the
    Association’s December 29 Notice of Appeal in Cause No. 16-01-23529-
    A, Resulting in Appellate Cause No. 01-17-00015-CV
    On December 13, 2016, the trial court severed all of the Ammermans’
    claims against the Association into a separate cause of action, stating “that all
    claims and causes of action asserted by [the Ammermans] against [the Association]
    are hereby severed into a separate cause under a new cause number[,]” namely
    cause number 16-01-23529-A.       This severance order, combined with the trial
    court’s July 6, 2016 order, granting the Association’s and the Wilsons’ joint
    motion for summary judgment, and the November 21, 2016 order, granting the
    Association’s second traditional motion for summary judgment, constituted a final
    ruling of the trial court with respect to the Association. It left pending only the
    Wilsons’ counterclaim for declaratory judgment and breach of the Covenants
    3
    The Ammermans do not challenge the trial court’s ruling dismissing their claims
    under Property Code Section 215.009 on appeal.
    18
    against the Ammermans insofar as the counterclaim regarded later improvements
    made to the Ammermans’ property.
    Accordingly, the trial court’s summary judgments in favor of the
    Association on the Ammermans’ claims against it became the trial court’s final
    judgment with respect to the Association.
    On December 29, 2016, the Ammermans filed a notice of appeal in the
    severed case, trial court cause number 16-01-23529-A, resulting in appellate cause
    number 01-17-00015-CV. The notice of appeal challenged both the July 6, 2016
    order granting the Joint Motion for Summary Judgment and the November 21,
    2016 order granting the Association’s second Motion for Summary Judgment, and
    it noted that those judgment were made final as to the Association when the claims
    against the Association were severed from those of the Wilsons.
    J.    The Wilsons’ December 27, 2016 Amended Counterclaim Against the
    Ammermans; the Wilsons’ March 10, 2017 Traditional Motion for
    Summary Judgment on Their Counterclaim; and the Ammermans’
    April 4, 2017 Response
    On December 27, 2016, the Wilsons filed an amended counterclaim
    asserting claims for breach of contract and declaratory judgment against the
    Ammermans, again based on allegations that the Ammermans breached the
    Covenants by failing to get written approval for their improvements, constructing
    their shed in a location that violated the restrictions, constructing a car-port, and
    failing to construct a garage.
    19
    On March 10, 2017, the Wilsons filed a traditional motion for summary
    judgment on their counterclaim seeking a declaratory judgment that the
    Ammermans had violated Article VI, sections 3 and 9, and Article VII, sections 4
    and 19 of the Covenants by failing to include a garage as part of their primary
    residence and by building the equipment shed without written ARC approval
    outside their building envelope and placing it somewhere besides the rear of the
    property. The Wilsons sought reasonable and necessary attorneys’ fees pursuant to
    the Declaratory Judgments Act.
    As summary judgment evidence, the Wilsons included a transcript of Clay
    Ammerman’s testimony at the temporary injunction hearing. The Wilsons
    contended that Clay Ammerman admitted at the hearing that his residence lacked a
    two-car garage; that he had built a shed on his property without obtaining written
    approval from the Association and that the shed was built in front, rather than
    behind, the primary residence; and that the shed is located outside the
    Ammermans’ building envelope and was located less the one-hundred feet from
    the property line. Specifically, the Wilsons cited Clay Ammerman’s testimony that
    his home had a “porte cochere” and his statement, “I don’t need a garage. It is not
    visible from any street or common area or adjoining property.” They also point to
    Clay Ammerman’s testimony that he got verbal approval to build his shed and his
    testimony that he built the shed in the only location that he could have built it,
    20
    which he acknowledged was not in his rear yard. The Wilsons also provided a
    survey showing that the shed is less than 100 feet from the Wilson-Ammerman
    property line and thus was placed inside the 100-foot setback required by the
    Covenants.
    The Wilsons asserted that all of these conditions constituted violations of the
    Covenants, and because Ammerman admitted to the violations, no genuine issues
    of material fact existed and the Wilsons were entitled to summary judgment.
    In their Response to the Wilson’s Motion for Summary Judgment on their
    counterclaim, filed April 4, 2017, the Ammermans asserted that the evidence,
    including Clay Ammermans’ testimony, established that their residence contained
    “garage space far larger than the 600 square feet required by the [Covenants]” and
    pointed to garage space included on their property as containing “both an [eight
    foot] roll-up metal door and a [fourteen foot] set of double cedar plank doors for
    larger vehicles.” They also pointed to the fact that their residence included a porte-
    cochere that satisfied the Covenant’s requirement that each residence include a
    garage. The Ammermans also cited to the fact that they obtained written approval
    for the residential building.
    Regarding the Wilsons’ claims that the Ammermans built the shed without
    written approval, the Ammermans pointed to e-mail correspondence from
    members of the ARC approving the construction of the shed. They argued that, at a
    21
    minimum, the e-mails raised a fact question regarding whether the Ammermans
    obtained proper written approval to build the shed. They also argued that, although
    the Covenants generally require that sheds and other storage buildings should be
    placed behind the primary residence, the Covenants have a specific condition that
    lake-front properties—like the Ammermans’—may not have storage buildings
    placed in the rear yard. They also argued that, to the extent their property varied
    from the requirements of the Covenants, the e-mails approving the construction of
    the shed raised at least a fact question that they were granted a variance by the
    Association and, thus, were not in violation of the Covenants.
    In addition to floor plans showing the presence of a garage and a porte-
    cochere in the Ammermans’ residence, the Ammermans provided written
    documentation and emails showing approval of their building plans and affidavits
    of other Community residents who stated that building approvals were done
    verbally or by email, as had occurred in the Ammermans’ case.
    K.    The Trial Court’s May 16, 2017 Final Judgment and the Wilsons’ June
    14, 2017 Notice of Appeal in Cause Number 16-01-23539, Resulting in
    Appellate Cause Number 01-17-00448-CV
    In an order signed May 16, 2017, the trial court granted the Wilsons’ motion
    for summary jdgment, declaring that the Ammermans were in violation of Article
    VI, sections 3 and 9, and Article VII, sections 4 and 19 of the Covenants due to
    their lack of a garage and the construction of the equipment shed. The trial court
    22
    awarded the Wilsons reasonable and necessary attorney’s fees, thereby disposing
    of all of the Wilsons’ remaining claims against the Ammermans. The trial court’s
    May 16, 2017 order in cause number 16-01-23529 thereby became the court’s final
    judgment on all of the Wilsons’ claims against the Ammermans and all of the
    Ammermans’ claims against the Wilsons.
    On June 14, 2017, the Ammermans filed a Notice of Appeal against the
    Wilsons, resulting in appellate cause number 01-17-00448-CV. In this notice of
    appeal, the Ammermans again listed the trial court’s November 21, 2016 order
    granting the Association’s second motion for summary judgment, which was also
    included in the then-pending appeal in appellate cause number 01-17-00015-CV,
    and they listed the trial court’s May 16, 2017 final order granting the Wilsons’
    motion for summary judgment on their declaratory judgment counter-claim against
    the Ammermans.
    Summary Judgment on the Ammermans’ Claims
    In their first and second issues, the Ammermans argue that (1) the trial court
    erred in granting summary judgment dismissing their claims on statute of
    limitations grounds because they presented some evidence raising a fact issue
    regarding when their cause of action for breach of the Covenants and for a
    declaratory judgment against the Wilsons and the Association accrued and when
    they could have discovered their cause of action; and (2) the trial court erred in
    23
    granting summary judgment dismissing their claims on the ground that the
    Association and the Wilsons had conclusively proved that they did not violate the
    relevant restrictive covenants because they presented some evidence that the
    Association acted arbitrarily and capriciously in approving the Wilsons’ building
    plans. We address these issues together.
    A.    Standard of Review
    We review summary judgments de novo. City of Richardson v. Oncor Elec.
    Delivery Co., 
    539 S.W.3d 252
    , 258 (Tex. 2018). The movant must show that no
    genuine issue of material fact exists and that the trial court should grant judgment
    as a matter of law. TEX. R. CIV. P. 166a(c); Oncor 
    Elec., 539 S.W.3d at 258
    –59. A
    defendant is entitled to a traditional summary judgment if the defendant
    conclusively negates at least one essential element of each cause of action or
    conclusively proves all elements of an affirmative defense. KCM Fin. LLC v.
    Bradshaw, 
    457 S.W.3d 70
    , 79 (Tex. 2015). If the movant meets its burden, the
    burden then shifts to the nonmovant to raise a genuine issue of material fact to
    preclude summary judgment. Katy Venture, Ltd. v. Cremona Bistro Corp., 
    469 S.W.3d 160
    , 163 (Tex. 2015) (per curiam); see also First United Pentecostal
    Church of Beaumont v. Parker, 
    514 S.W.3d 214
    , 220 (Tex. 2017) (stating that fact
    question exists if evidence rises to level that would enable reasonable and fair-
    minded people differ in their conclusions).
    24
    In reviewing the grounds for summary judgment, we take as true all
    evidence favorable to the nonmovant and indulge every reasonable inference and
    resolve any doubts in the nonmovant’s favor. Sommers for Ala. & Dunlavy, Ltd. v.
    Sandcastle Homes, Inc., 
    521 S.W.3d 749
    , 754 (Tex. 2017). Here, because the trial
    court granted the challenged motions for summary judgment in their entirety, we
    must affirm a summary judgment if it is correct on any of the grounds asserted in
    the motions. See Provident Life & Accident Ins. Co. v. Knott, 
    128 S.W.3d 211
    , 216
    (Tex. 2003).
    Here, the Wilsons and the Association sought summary judgment on claims
    alleging breach of the Covenants. “[A]ny person entitled to benefit under the terms
    of a restrictive covenant may enforce it.” Moseley v. Arnold, 
    486 S.W.3d 656
    , 662
    (Tex. App.—Texarkana 2016, no pet.) (quoting Girsh v. St. John, 
    218 S.W.3d 921
    ,
    923 (Tex. App.—Beaumont 2007, no pet.); see also Oyoque v. Henning, No. 09-
    17-00018-CV, 
    2018 WL 1527892
    , at *3 (Tex. App.—Beaumont Mar. 29, 2018, no
    pet.) (mem. op.) (discussing standing to sue for violation of restrictive covenants).
    Restrictive covenants are construed using the general rules of contract
    construction. 
    Moseley, 486 S.W.3d at 662
    (citing Pilarcik v. Emmons, 
    966 S.W.2d 474
    , 478 (Tex. 1998)). “Courts must examine the covenants as a whole in light of
    the circumstances present when the parties entered the agreement.” 
    Pilarcik, 966 S.W.2d at 478
    (citing Grain Dealers Mut. Ins Co. v. McKee, 
    943 S.W.2d 455
    , 458
    25
    (Tex. 1997)); see Columbia Gas Transmission Corp. v. New Ulm Gas, Ltd., 
    940 S.W.2d 587
    , 589 (Tex. 1996). Restrictive covenants are “unambiguous as a matter
    of law if [they] can be given a definite or certain legal meaning.” 
    Pilarcik, 966 S.W.2d at 478
    (quoting Grain 
    Dealers, 943 S.W.2d at 458
    ).
    B.    Statute of Limitations
    The Association and the Wilsons sought summary judgment in part on the
    ground that the Ammermans’ suit was barred by the statute of limitations. The
    statute of limitations is an affirmative defense. TEX. R. CIV. P. 94. A defendant
    seeking summary judgment on the basis of an affirmative defense, such as
    limitations, bears the burden to conclusively establish that defense, including the
    accrual date of the cause of action. Diversicare Gen. Partner, Inc. v. Rubio, 
    185 S.W.3d 842
    , 846 (Tex. 2005); KPMG Peat Marwick v. Harrison Cty. Hous. Fin.
    Corp., 
    988 S.W.2d 746
    , 748 (Tex. 1999). When a cause of action accrues is a
    question of law. Holy Cross Church of God in Christ v. Wolf, 
    44 S.W.3d 562
    , 567
    (Tex. 2011). If the summary judgment movant establishes that the statute of
    limitations bars the action, the nonmovant must adduce proof raising a fact issue in
    avoidance of the statute of limitations. KPMG Peat 
    Marwick, 988 S.W.2d at 748
    .
    Breach of contract claims are subject to a four-year statute of limitations.
    See Exxon Corp. v. Emerald Oil & Gas Co., 
    348 S.W.3d 194
    , 203 (Tex. 2011).
    Because a declaratory judgment action is a procedural device used to determine
    26
    substantive rights, we must look to the legal remedy underlying the cause of action
    to determine the applicable limitations period. Nw. Austin Mun. Util. Dist. No. 1 v.
    City of Austin, 
    274 S.W.3d 820
    , 836 (Tex. App.—Austin 2008, pet. denied). Here,
    the Ammermans sought a declaratory judgment that the Association and the
    Wilsons violated the Covenants—the same basis as their breach of contract
    claim—and thus the statute of limitations is likewise four years. See 
    id. Generally, a
    cause of action accrues when facts come into existence that
    authorize a claimant to seek a judicial remedy, when a wrongful act causes some
    legal injury, or whenever one person may sue another. Am. Star Energy &
    Minerals Corp. v. Stowers, 
    457 S.W.3d 427
    , 430 (Tex. 2015); B. Mahler Interests,
    L.P. v. DMAC Constr., Inc., 
    503 S.W.3d 43
    , 49 (Tex. App.—Houston [14th Dist.]
    2016, no pet.). A breach of contract claim accrues when the contract is breached.
    Cosgrove v. Cade, 
    468 S.W.3d 32
    , 39 (Tex. 2015); B. Mahler 
    Interests, 503 S.W.3d at 49
    . A cause of action under the Declaratory Judgment Act accrues when
    there is an actual controversy between the parties. In re Estate of Denman, 
    362 S.W.3d 134
    , 144 (Tex. App.—San Antonio 2011, no pet.).
    The Ammermans asserted that the discovery rule applies in this case. The
    discovery rule defers accrual of a claim until the injured party learned of, or in the
    exercise or reasonable diligence should have learned of, the wrongful act causing
    the injury. 
    Cosgrove, 468 S.W.3d at 36
    . The discovery rule is limited to
    27
    “circumstances where ‘the nature of the injury incurred is inherently
    undiscoverable and the evidence of injury is objectively verifiable.’” 
    Id. (quoting Comput.
    Assocs. Int’l, Inc. v. Altai, Inc., 
    918 S.W.2d 453
    , 456 (Tex. 1996)). An
    injury is not inherently undiscoverable when it is the type of injury that could be
    discovered through the exercise of reasonable diligence. BP Am. Prod. Co. v.
    Marshall, 
    342 S.W.3d 59
    , 66 (Tex. 2011).
    It is the discovery of the injury and its general cause, not discovery of the
    exact cause in fact, that starts the running of the limitations period. Bayou Bend
    Towers Council of Co–Owners v. Manhattan Constr. Co., 
    866 S.W.2d 740
    , 743
    (Tex. App.—Houston [14th Dist.] 1993, writ denied). “Knowledge of injury
    initiates the accrual of the cause of action and triggers the putative claimant’s duty
    to exercise reasonable diligence to investigate the problem, even if the claimant
    does not know the specific cause of the injury or the full extent of it.” Exxon 
    Corp., 348 S.W.3d at 209
    .
    C.    Statute of Limitations on the Ammermans’ Claims that the Association
    and the Wilsons Breached the Covenants
    The Association and the Wilsons asserted, in their joint motion for summary
    judgment, that the Ammermans’ breach of contract claim arising from the
    Wilsons’ and the Association’s alleged breach of Article VI, Section 9 of the
    Covenants with regard to the location of the Wilsons’ building envelope was
    barred by the statute of limitations. The Association asserted an identical argument
    28
    in its second motion for summary judgment regarding the amended claims filed
    against it by the Ammermans. Thus, they bore the burden of establishing when the
    cause of action accrued. See 
    Rubio, 185 S.W.3d at 846
    .
    The Association and the Wilsons argued that the building envelopes were
    established by the Association and the developer prior to the sale of the lots, and
    thus the Ammermans knew of the location of the Wilsons’ building envelope at the
    time both parties bought their lots in 2006; therefore, the Ammermans’ claims for
    breach of Article 6, Section 9 of the Covenants are time-barred.
    The Association and the Wilsons presented Johnny Wilsons’ declaration
    indicating that the location of the Wilsons’ building envelope—the three-acre
    parcel in which they are permitted to build any improvements to the lot—was set
    by the developer in 2006 and that this information was available to the
    Ammermans in May 2006 when they selected and purchased their own lot. Wilson
    also declared that he and his wife had never sought or obtained a modification of
    their building envelope. He declared that the building site approved by the
    Association was located within the building envelope set in 2006. The Association
    and the Wilsons also presented evidence, in the form of Clay Ammerman’s
    testimony at the temporary injunction hearing, that Ammerman was aware of the
    Wilsons’ potential building locations and that he also knew that each lot had a
    building envelope in which all improvements were to be constructed.
    29
    The Ammermans claims against both the Wilsons and the Association all
    arise from alleged facts surrounding the Associations’ approval of the Wilsons’
    building site. The Ammermans claim that both the Wilsons and the Association
    violated Article VI, Section 9 of the Covenants in determining the Wilsons’
    building site. Artice VI, Section 9, which has three relevant provisions, states:
    [1] The Building Envelope of each lot shall be located so that same is
    as far as reasonably possible from the Building Envelope on all other
    contiguous Lots. [2] In the event that a Building Envelop has not been
    established on all contiguous tracts then the Building Envelope shall
    be located as follows: (i) in a manner that will maintain the integrity
    of a rural ranch setting; (ii) be set back from any abutting Street a
    minimum of 100 feet; (iii) have a side yard set back a minimum of
    100 feet; and (iv) have a rear yard set back a minimum of 100 fee.
    [3] Once established, the Building Envelope shall not be modified nor
    changed without Residential ARC approval.
    Article VI, section 9.     The Ammermans also asserted that the Associations’
    approval of the building site violated various other provisions in the Covenants
    requiring that the Association enforce the Covenants and maintain “architectural
    control of the Lots” (Article II, section 1), that the Associations’ Board make and
    enforce such rules and regulations as are necessary to enforce the Covenants
    (Article II, section 4), that the ARC properly approve all building plans to meet
    certain construction standards (Article VI, section 3 and Article VII, section 3).
    The Wilsons and the Association presented evidence that a building
    envelope was established on both Lot 28 and Lot 29 before the Ammermans
    purchased Lot 28 and the Wilsons purchased the contiguous Lot 29 in 2006. See
    30
    
    Pilarcik, 966 S.W.2d at 478
    (“Courts must examine the covenants as a whole in
    light of the circumstances present when the parties entered the agreement.”). Thus,
    the Association and the Wilsons established that any alleged breach of the
    Covenants committed in determining the location of the Wilsons’ building
    envelope accrued when the building envelope was designated in 2006 before they
    purchased their contiguous lots. See 
    Stowers, 457 S.W.3d at 430
    (cause of action
    accrues when facts come into existence that authorize claimant to seek judicial
    remedy); 
    Cosgrove, 468 S.W.3d at 39
    (breach of contract claim accrues when
    contract is breached).
    Furthermore, the Association and the Wilsons established that any injury
    caused by the allegedly improper location of the Building Envelope as determined
    in 2006 was discoverable by the Ammermans in May 2006, when the Ammermans
    purchased their lot knowing the location of both their own building envelope and
    those of the other contiguous lots. See 
    Marshall, 342 S.W.3d at 66
    (holding that
    injury is not inherently undiscoverable when it could be discovered through
    exercise of reasonable diligence). Likewise, the claim for declaratory judgment
    seeking a declaration that the Association and the Wilsons violated the Covenants
    in approving the Wilsons’ building envelope accrued in May 2006, when the
    Ammermans purchased the lot that gave them an interest in the designation of
    other building envelopes designated on nearby lots. See In re Estate of Denman,
    
    31 362 S.W.3d at 144
    . However, the Ammermans did not file their suit until 2016.
    Because the statute of limitations for both the breach of contract claim and
    declaratory judgment claim is four years, the Ammermans’ suit was time-barred.
    See Exxon 
    Corp., 348 S.W.3d at 203
    ; Nw. Austin Mun. Util. Dist. No. 
    1, 274 S.W.3d at 836
    .
    The Ammermans argue that the ARC approved a new building envelope
    sometime between 2006 and January 2016 and, thus, the cause of action did not
    accrue until January 2016, when the Wilsons marked the construction location for
    their home. Alternatively, the Ammermans argue that the discovery rule deferred
    accrual of their claim until they could have discovered that the building envelope
    had been relocated. See 
    Cosgrove, 468 S.W.3d at 36
    . The Ammermans further
    argue that they raised a fact question regarding whether their cause of action was
    discoverable.4
    The Ammermans support their arguments with evidence concerning the
    particular location of the Wilsons’ proposed home site, such as portions of the
    testimony adduced at the temporary injunction hearing and admitted as part of the
    summary judgment record. They also cite the letter from the ARC explaining the
    4
    The Ammermans also argue that they were prevented from obtaining discovery
    proving that the building envelope had been moved; however, they did not raise
    this as a ground for error or otherwise provide citations to the record or authorities
    to support their complaint. Thus any complaint of this nature is waived for failure
    to adequately brief it. See TEX. R. APP. P. 38.1(i).
    32
    reasons for approving the Wilsons’ building site, noting that the current building
    location was “already set back” as compared to the previous site. The Ammermans
    argue that this was some evidence that the proposed location of the home site was
    changed sometime between 2006 and 2016. However, none of this evidence
    contradicts the evidence that the parties were aware of possible building locations
    in 2006, at the time they purchased their lots. And none of this evidence
    contradicts Johnny Wilsons’ declaration that the approved building site was within
    the original building envelope. It does not indicate that the three-acre building
    envelope moved, nor does it indicate that the Wilsons’ approved building site falls
    outside the building envelope established in 2006.
    Critically, the Ammermans’ argument misconstrues Article VI, section 9’s
    second provision, which states, “In the event that a Building Envelop has not been
    established on all contiguous tracts then the Building Envelope shall be located as
    follows: (i) in a manner that will maintain the integrity of a rural ranch setting;
    (ii) be set back from any abutting Street a minimum of 100 feet; (iii) have a side
    yard set back a minimum of 100 feet; and (iv) have a rear yard set back a minimum
    of 100 fee.” Here, the Building Envelope was established when the Ammermans
    and the Wilsons purchased their lots; therefore, by its plain language, this
    provision is inapplicable to the Ammermans’ claims.
    33
    Instead, the third provision in Article VI, Section 9 applies to any changes
    made in the original envelope, namely, “Once established, the Building Envelope
    shall not be modified nor changed without Residential ARC approval.”             The
    Ammermans argue that the Wilsons and the Association improperly modified or
    changed the Wilsons’ building envelope that was set in 2006, but they have failed
    to present any evidence to support their contention.
    We conclude that the Wilsons and the Association established that they were
    entitled to summary judgment on limitations grounds with respect to the
    Ammermans’ claims that they violated the Covenants. The Ammermans failed to
    raise a genuine issue of material fact regarding when their cause of action for
    breach of the Covenants accrued or on the application of the discovery rule.
    Accordingly, the grant of summary judgment on this ground was proper.5
    We overrule the Ammermans’ first issue.
    5
    Because we affirm the trial court’s grant of summary judgment on limitations
    grounds, we need not address the alternative grounds asserted by the Wilsons and
    the Association in their motions for summary judgment on these claims. See
    Provident Life & Accident Ins. Co. v. Knott, 
    128 S.W.3d 211
    , 216 (Tex. 2003).
    34
    D.    Summary Judgment on the Ammermans’ Claim that the Association
    Violated Property Code section 202.004
    In their second issue, the Ammermans’ claim that the Association’s
    construction and application of the Covenants was arbitrary and capricious in
    violation of Property Code section 202.004.6
    Section 202.004 provides:
    (a) An exercise of discretionary authority by a property owners’
    association or other representative designated by an owner of real
    property concerning a restrictive covenant is presumed reasonable
    unless the court determines by a preponderance of the evidence that
    the exercise of discretionary authority was arbitrary, capricious, or
    discriminatory.
    (b) A property owners’ association or other representative designated
    by an owner of real property may initiate, defend, or intervene in
    litigation or an administrative proceeding affecting the enforcement of
    a restrictive covenant or the protection, preservation, or operation of
    the property covered by the dedicatory instrument.
    (c) A court may assess civil damages for the violation of a restrictive
    covenant in an amount not to exceed $200 for each day of the
    violation.
    TEX. PROP. CODE ANN. § 202.004. This statute establishes a cause of action by “a
    property owners’ association or other representative designated by an owner of real
    property,” allowing such an entity to “initiate, defend, or intervene” in a suit
    affecting the enforcement of a restrictive covenant. See 
    id. § 202.004(b);
    Sierra
    6
    To the extent that the Ammermans’ second issue on appeal also addresses the
    Association’s purported breach of the Covenants, those claims were resolved on
    statute of limitations grounds, as discussed above. The Ammermans do not
    challenge the trial court’s ruling dismissing their claims under Property Code
    section 215.009 on appeal.
    35
    Crest Homeowners Ass’n, Inc. v. Villalobos, 
    527 S.W.3d 235
    , 239 (Tex. App.—El
    Paso 2016, no pet.); KBG Invs., LLC v. Greenspoint Property Owners’ Ass’n, Inc.,
    
    478 S.W.3d 111
    , 119 (Tex. App.—Houston [14th Dist.] 2015, no pet.).
    “Subsection (a) ‘creates a rebuttable presumption that a property owners’
    association or other representative acts reasonably in exercising its discretionary
    authority.’” 
    Villalobos, 527 S.W.3d at 239
    (quoting La Ventana Ranch Owners’
    Ass’n, Inc. v. Davis, 
    363 S.W.3d 632
    , 647 (Tex. App.––Austin 2011, pet. denied)).
    We first observe that nothing in the statutory language of section 202.004
    indicates an intent by the legislature to create a cause of action by a homeowner
    against a homeowners’ association, such as the one filed by the Ammermans here.
    See TEX. PROP. CODE ANN. § 202.004(b); 
    Villalobos, 527 S.W.3d at 239
    .
    Furthermore, in its second motion for summary judgment, the Association argued
    that the Ammermans failed to present any evidence rebutting the statutory
    presumption created by section 202.004(a) that its exercise of discretion in
    approving the building envelope was reasonable.
    The Ammermans argue that they raised a fact question as to whether the
    ARC’s decisions allowing changes to the Wilsons’ Building Envelope in violation
    of the Covenants were arbitrary and capricious. However, as discussed above, the
    Ammermans have presented no evidence that the building envelope was changed.
    Johnny Wilson declared that the approved building site is located within the
    36
    building envelope set by the developer in 2006, and the Ammermans have
    provided no controverting evidence.
    We conclude that the Ammermans have failed to present any evidence that
    the Association ever approved a change to the Wilsons’ envelope. They likewise
    failed to present any evidence rebutting the presumption that any exercise of
    discretion by the Association was reasonable. See TEX. PROP. CODE ANN.
    § 202.004(a).
    We overrule the Ammermans’ second issue.
    Summary Judgment on the Wilsons’ Counterclaim Against the Ammermans
    for Violations of the Covenants
    In their third issue, the Ammermans argue that the trial court erred in
    granting summary judgment in favor of the Wilsons on their counterclaims for
    declaratory judgment, in which the Wilsons asserted that the Ammermans violated
    the Covenants.
    A.    Review of the November 21, 2016 Order in the Context of the Appeal
    Between the Ammermans and the Wilsons
    As a preliminary matter, the Wilsons argue that the Ammermans’ “notice of
    appeal attempts to appeal the November 21, 2016 order,” noting that “the
    Ammermans [have] already appealed this order in [the appeal between the
    Ammermans and the Association].” The Wilsons also argue that the Ammermans’
    notice of appeal filed in appellate cause number 01-17-00448-CV was untimely as
    37
    to the November 21, 2016 order. The Wilsons misconstrue the procedural posture
    of the case.
    The trial court’s November 21, 2016 order granted the Association’s second
    traditional motion for summary judgment and dismissed the Ammermans’
    remaining claims against the Association. Neither the Association’s second
    traditional motion for summary judgment nor the trial court’s November 21, 2016
    order granting that motion addressed any claims between the Ammermans and the
    Wilsons.
    Subsequently, on December 13, 2016, the trial court severed all of the
    Ammermans’ claims against the Association into a separate cause of action,
    making the trial court’s orders regarding the claims against the Association final
    and appealable. See Harris Cty. Flood Control Dist. v. Adam, 
    66 S.W.3d 265
    , 266
    (Tex. 2001) (per curiam) (judgment in severed cause that disposed of all claims
    between parties to appeal was final and appealable). The Ammermans filed a
    timely notice of appeal in the severed case against the Association on December
    29, 2016, asserting that they were appealing the trial court’s summary judgment
    rulings against them, including in the November 21, 2016 order. See TEX. R. APP.
    P. 26.1 (setting out time to file notice of appeal).
    The claims between the Ammermans and the Wilsons remained pending in
    the trial court. On May 16, 2017, the trial court granted the Wilsons’ motion for
    38
    summary judgment, rendering a declaratory judgment in their favor on their
    counterclaims against the Ammermans. This finally resolved all claims between
    the Ammermans and the Wilsons, and the Ammermans filed their notice of appeal
    twenty-nine days later on June 14, 2017. See 
    id. In this
    notice of appeal, the
    Ammermans again listed the trial court’s November 21, 2016 order as an order that
    they would be challenging on appeal. The Ammermans then filed an identical brief
    in both of their appeals.
    The Wilsons assert that the Ammermans “now attempt to get a second bite at
    the apple by briefing the issues of the November 21, 2016 order that have nothing
    to do with the Wilsons.” They argue, “Because the claims between the
    Ammermans and the Wilsons are not adjudicated in the November 21, 2016 order,
    review of that order is improper as the Wilsons are not subject to the November 21,
    2016 order.” The Wilsons further argue that “[e]ven if the Ammermans could file a
    notice of appeal as to an order related to different parties in a different appeal, the
    Ammermans’ notice of appeal as to the November 21, 2016 order was untimely.”
    The Wilsons assert that the November 21, 2016 order became final when the trial
    court severed the claims against the Association from the claims between the
    Ammermans and the Wilsons on December 13, 2016, and they further assert that
    the Ammermans’ notice of appeal in the case against the Wilsons was not filed
    until June 14, 2017.
    39
    We agree that the November 21, 2016 order did not adjudicate any claims
    between the Ammermans and the Wilsons. We reviewed the propriety of the trial
    court’s November 21, 2016 order in the context of the appeal in cause number 01-
    17-00015-CV between the Ammermans and the Association. Furthermore, the
    notice of appeal in the 01-17-00015-CV case was timely. The November 21, 2016
    order became final on December 13, 2016, and the Ammermans’ notice of appeal
    in that case, specifically including the November 21, 2016 order, was timely filed
    on December 29, 2016.
    In the context of cause number 01-17-00448-CV, between the Wilsons and
    the Ammermans, the November 21, 2016 order is irrelevant because it did not
    adjudicate any claims between those parties, and we need not review that order to
    resolve any issues between the Ammermans and the Wilsons. Moreover, even if
    the Ammermans erred in listing the November 21, 2016 order in their notice of
    appeal for cause number 01-17-00448-CV, such an error would not deprive this
    Court of jurisdiction to consider the case because the Ammermans nevertheless
    filed a timely notice of appeal with the contents necessary to invoke the
    jurisdiction of this Court over the claims between the Wilsons and the
    Ammermans. See TEX. R. APP. P. 25.1(a) (providing that appeal is perfected when
    written notice of appeal is filed with trial court clerk), (b) (providing that filing of
    notice of appeal by any party invokes appellate court’s jurisdiction over all parties
    40
    to trial court’s judgment), (d) (providing that notice of appeal must contain, among
    other things, “the date of the judgment or order appealed from”).
    The trial court’s various orders granting summary judgment in favor of the
    Wilsons became final on May 16, 2017, when the trial court rendered its order
    granting summary judgment in favor of the Wilsons on their counterclaims against
    the Ammermans, finally resolving all of the claims between the parties. See
    Lehmann v. Har-Con Corp., 
    39 S.W.3d 191
    , 200 (Tex. 2001) (“[I]f a court has
    dismissed all of the claims in a case but one, an order determining the last claim is
    final.”);   Webb      v.    Jorns,     
    488 S.W.2d 407
    ,     408–09     (Tex.
    1972)https://1.next.westlaw.com/Link/Document/FullText?findType=Y&serNum=1972133193
    &pubNum=0000713&originatingDoc=Id50e0d70199c11e7afe7804507f6db3f&refType=RP&fi=
    co_pp_sp_713_409&originationContext=document&transitionType=DocumentItem&contextDa
    ta=(sc.Search) - co_pp_sp_713_409 (recognizing that interlocutory order becomes final
    for purposes of appeal when it merges into final judgment disposing of whole
    case). The Ammermans filed their notice of appeal twenty-nine days later on June
    14, 2017. See TEX. R. APP. P. 26.1. The Ammermans’ June 14, 2017 notice of
    appeal listed the orders about which they complain on appeal, and, thus, this is not
    a case in which a party is seeking review of an order or judgment not listed in the
    notice of appeal. See TEX. R. APP. P. 25.1(d) (requiring that notice of appeal
    identify order or judgment complained of). Rather, the Ammermans listed an
    41
    interlocutory order rendered by the trial court earlier in the litigation, but with
    respect to a later-severed party. The Wilsons point to no authority, nor could we
    find any, indicating that the inclusion in an appellant’s notice of appeal of an order
    that would ultimately provide no relief to the appellant deprives an appellate court
    of jurisdiction over a timely-filed appeal. Moreover, we note that the matters that
    are irrelevant to the claims between the Ammermans and the Wilsons were also
    raised and addressed in the timely-filed appeal of the Ammermans’ claims against
    the Association.
    Accordingly, we hold that we have appellate jurisdiction to consider the
    Ammermans’ third issue complaining that the trial court erred in granting summary
    judgment in favor of the Wilsons on their counterclaims for declaratory judgment.
    And we overrule the Wilsons’ preliminary argument to the extent they argue that
    the Ammermans’ notice of appeal against them was untimely.
    B.    Statute of Limitations
    The Ammermans argue, in their third issue, that the statute of limitations
    bars the Wilsons’ claims that the Ammermans violated the Covenants. However,
    the Ammermans never pleaded the affirmative defense of limitations.
    Statute of limitations is an affirmative defense, and Texas Rule of Civil
    Procedure 94 requires a party to plead all affirmative defenses. TEX. R. CIV. P. 94;
    Hassell Constr. Co. v. Stature Commercial Co., 
    162 S.W.3d 664
    , 667 (Tex.
    42
    App.—Houston [14th Dist.] 2005, no pet.).          Because the Ammermans never
    pleaded this affirmative defense, the trial court did not err in failing to dismiss the
    counterclaims on this ground. See Roark v. Stallworth Oil & Gas, Inc., 
    813 S.W.2d 492
    , 494 (Tex. 1991) (generally, summary judgment cannot be granted on
    unpleaded affirmative defense unless raised in motion for summary judgment and
    opposing party does not object to lack of pleading).
    C.    Genuine Issue of Material Fact
    The Ammermans also argue in their third issue that “substantial questions of
    material fact persisted” with regard to the Wilsons’ counterclaims, and, thus, “the
    granting of summary judgment in this matter was improper.” See Katy Venture,
    
    Ltd., 469 S.W.3d at 163
    (holding that if movant meets its summary judgment
    burden, nonmovant then bears burden to raise genuine issue of material fact
    precluding summary judgment).
    In their motion for traditional summary judgment, the Wilsons argued that
    they were entitled as a matter of law to a declaration that the Ammermans violated
    the Covenants by building a residence without a garage and by building a shed
    outside their building envelope and without proper written approval. They argued
    that Clay Ammerman admitted to the violations of the Covenants in his testimony
    at the temporary injunction hearing. The trial court ultimately found that the
    Ammermans’ breached the Covenants as a matter of law because (1) their primary
    43
    residence lacked a two-car garage; (2) they constructed an equipment shed on Lot
    28 without written approval of the ARC; (3) the equipment shed on Lot 28 was not
    located behind the primary residence; and (4) the equipment shed on Lot 28 was
    located outside the Building Envelope and within the 100-foot setback at the
    property line.However, the Ammermans cited other portions of that same record
    indicating that the Ammermans believed they had acted within the scope of the
    Covenants at all times. For example, Clay Ammerman testified that he had a “porte
    cochere” and that he did not need a garage, but he did not affirmatively testify that
    his property lacked a garage in violation of the Covenants. The Ammermans also
    presented summary judgment evidence that their home had garage space and that
    their primary residence was approved by the ARC in writing.
    Regarding the alleged violations for the building of the shed, Clay
    Ammerman testified at the temporary injunction hearing that he got verbal
    approval to build his shed and that he built the shed in the only location that he
    could have built it, which he acknowledged was not in his rear yard.            This
    testimony does not constitute an admission that the Ammermans failed to get
    written approval, as the Wilsons claim. Furthermore, the Ammermans submitted
    summary judgment evidence in the form of emails from ARC members approving
    the building of the shed—including its location as being outside the original
    Building Envelope, within the 100-foot setback, and not being located behind the
    44
    primary residence. The Ammermans presented affidavits from other homeowners
    averring that the Association’s practice was to provide the required approvals
    either verbally or through emails such as those provided to the Ammermans here.
    The Ammermans also pointed to the copies of the Covenants themselves,
    which provided exceptions to the general rule that utility buildings must be located
    behind the primary residence by stating that lake-front properties—like the
    Ammermans’—may not have storage buildings placed in the rear yard. The
    Ammermans also argued that, to the extent their property varied from the
    requirements of the Covenants, the ARC was authorized to approve construction
    that otherwise violated the covenants and that the e-mails approving the
    construction of the shed raised at least a fact question that they were granted a
    variance by the Association and, thus, were not in violation of the Covenants.
    Thus, although the trial court concluded that the Ammermans were in
    violation of the Covenants because their primary residence lacked a two-car
    garage, the Ammermans provided more than a scintilla of evidence indicating that
    their primary residence contained an appropriate garage or the equivalent of a
    garage, in the form of a porte cochere, that was approved by the ARC in writing.
    The Ammermans also provided emails raising, at the least, a fact question
    regarding whether they had obtained written approval from the ARC to construct
    their shed. The e-mails indicated that ARC committee members approved the
    45
    shed—including its location—prior to the Ammermans’ beginning construction.
    Furthermore, the Covenants themselves indicated that lake-front properties may
    not have storage buildings in the rear yard and that the ARC had authority to
    approve building plans even if they varied from the requirements of the Covenants.
    We conclude that the Ammermans presented more than a scintilla of
    evidence raising a fact-issue regarding whether their primary residence and shed
    violated the Covenants. Accordingly, the trial court erroneously granted summary
    judgment on the Wilsons’ counterclaims against the Ammermans. See TEX. R. CIV.
    P. 166a(c); Oncor 
    Elec., 539 S.W.3d at 258
    –59.
    We sustain the Ammermans’ third issue.
    Conclusion
    We affirm the judgment of the trial court in appellate cause number 01-17-
    00015-CV, dismissing the Ammermans’ claims against the Association. We
    further affirm the portion of the trial court’s judgment dismissing the Ammermans’
    claims against the Wilsons in appellate cause number 01-17-00448-CV. We
    reverse the portion of the trial court’s judgment granting summary judgment on the
    Wilsons’ counterclaims against the Ammermans and remand for further
    proceedings consistent with this opinion.
    46
    Evelyn V. Keyes
    Justice
    Panel consists of Justices Keyes, Bland, and Massengale.
    47