Sierra Club v. U.S. Army Corps of Engineers , 905 F.3d 285 ( 2018 )


Menu:
  •                                                                FILED: October 2, 2018
    PUBLISHED
    UNITED STATES COURT OF APPEALS
    FOR THE FOURTH CIRCUIT
    No. 18-1173 (L)
    (LRH-2015-582-GBR)
    SIERRA CLUB; WEST VIRGINIA RIVERS COALITION; INDIAN CREEK
    WATERSHED ASSOCIATION; APPALACHIAN VOICES; CHESAPEAKE
    CLIMATE ACTION NETWORK
    Petitioners
    v.
    UNITED STATES ARMY CORPS OF ENGINEERS; MARK T. ESPER, in his
    official capacity as Secretary of the U.S. Army; TODD T. SEMONITE, in his official
    capacity as U.S. Army Chief of Engineers and commanding General of the U.S.
    Army Corps of Engineers; PHILIP M. SECRIST, in his official capacity as District
    Commander of the U.S. Army Corps of Engineers, Huntington District; MICHAEL
    E. HATTEN, in his official capacity as Chief, Regulatory Branch, U.S. Army Corps
    of Engineers, Huntington District
    Respondents
    MOUNTAIN VALLEY PIPELINE, LLC
    Intervenor
    ORDER
    PER CURIAM:
    Petitioners ask this Court to set aside Respondent U.S. Army Corps of Engineers’
    (the “Corps”) December 22, 2017, verification and July 3, 2018, reinstated verification that
    construction of the Mountain Valley Pipeline (the “Pipeline”) can proceed under the terms
    and conditions of Clean Water Act Nationwide Permit 12 (“NWP 12”), rather than an
    individual permit.    Among other arguments, Petitioners assert that, in issuing its
    verification, the Corps improperly imposed one condition—requiring use of a “dry cut”
    method for constructing four river crossings—“in lieu of” a special condition imposed by
    the State of West Virginia, J.A. 232—that “[i]ndividual stream crossings must be
    completed in a continuous, progressive manner within 72 hours,” J.A. 43—as part of its
    certification of NWP 12. Construction of each of the four river crossings using the “dry
    cut” method is expected to take four-to-six weeks to complete.
    Exercising jurisdiction pursuant to 15 U.S.C. § 717r(d)(1), we conclude, for reasons
    to be more fully explained in a forthcoming opinion, that the Corps lacked authority to
    substitute the “dry cut” requirement “in lieu of” West Virginia’s 72-hour temporal
    restriction. Accordingly, we VACATE, in its entirety, the Corps’ verification of the
    Pipeline’s compliance with NWP 12. See 5 U.S.C. § 706(2); 33 C.F.R. § 330.6(d)
    (explaining that if any part of a project requires an individual permit, then “the NWP does
    not apply and all portions of the project must be evaluated as part of the individual permit
    2
    process.”).   We reserve judgment on the parties’ remaining arguments until our
    forthcoming opinion.
    FOR THE COURT
    /s/ Patricia S. Connor
    Clerk
    3
    

Document Info

Docket Number: 18-1173 (L)

Citation Numbers: 905 F.3d 285

Judges: Per Curiam

Filed Date: 10/2/2018

Precedential Status: Precedential

Modified Date: 10/19/2024