Cincinnati Fluid Power, Inc. v. Rexnord, Inc. , 773 F.2d 92 ( 1985 )


Menu:
  • PER CURIAM.

    Defendant Rexnord, Inc. (Racine) appeals from a jury verdict in favor of Plaintiff Cincinnati Fluid Power, Inc. (Fluid Power) in this diversity suit. Fluid Power relied upon Ohio’s promissory estoppel doctrine in seeking damages for denial of an allegedly promised distributorship. Defendant Racine assigns error in the trial court’s failure to give requested jury instructions, challenges evidentiary rulings, and alleges an absence of evidence supporting the damages awarded to Fluid Power. Upon corn sideration of all issues raised on appeal, we affirm.

    Fluid Power is an Ohio corporation that served as an authorized distributor for hydraulic and pneumatic component manufacturers. Racine Fluid Power Division, located in Racine, Wisconsin, was an operating division of Rexnord. Racine manufactured hydraulic pumps, valves, and systems that it sold to independent authorized distributorships. In November, 1981, Fluid Power’s president, Daniel Kallmyer, contacted Racine vice-president William Watson to learn whether Fluid Power could become a Racine distributor. Kallmyer learned that Racine was unhappy with its exclusive authorized distributor for southwest Ohio, Dynamic Technology, Inc. and that Racine planned to make “some changes” in the region. In early December, 1981, Kallmyer met with Watson and Racine’s distributor sales manager, Donald Spaulding, at Racine’s Wisconsin offices. During this meeting, the parties exchanged information about the companies, discussed Racine’s expectations of its distributors, and discussed the written agreements upon which such relationships were based.

    Following the December meeting, Kall-myer sought counsel at First National Bank of Cincinnati regarding financing of the additional inventory and expenses that Fluid Power would incur if it became a Racine distributor. On the advice of a bank vice-president, Kallmyer began to compile documents that would support an application for a Small Business Administration loan.

    During the first three months of 1982, Watson and Spaulding were “shopping” to determine which of several possible replacements for Dynamic Technology would best serve Racine’s interests in southwestern Ohio. They told Kallmyer that they planned to decide on their preferred distributor by March 23, 1982. As part of this process, Watson and Spaulding visited Fluid Power’s Cincinnati facility in mid-February. Kallmyer testified that during this meeting he told Watson and Spaulding that if he were to increase his staff from three to seven persons to satisfy Racine, Fluid Powers would have to move to larger facilities. Kallmyer showed Watson and Spaulding the proposed new quarters for Fluid Power and received what he understood as their expressions of approval. At this time, Fluid Power had neither committed for the new space nor terminated the lease on its then current space, both of which were owned by the same company. There was testimony, however, that Kall-myer had told Racine in December that he planned to move to larger quarters to accommodate Fluid Power’s current business.

    On March 22, 1982, Kallmyer met with Watson and Spaulding in Wisconsin. Kall-myer testified that Spaulding told him, “We have made the decision that we want you to be our distributor in Southwestern Ohio.” Watson and Spaulding reportedly told Kallmyer, “Don’t go racing back to Cincinnati to announce this to the world. We will be terminating our distributor down there. They should hear it from Racine. They shouldn’t hear it from someone *95else.” Although no written distribution agreement was executed during this meeting, Kallmyer testified that Watson and Spaulding told him Racine’s decision was “solid.” They reportedly also said, “You can take it to the bank,” which Kallmyer testified he understood as “a phrase that meant you can depend on it.” Finally, Kallmyer testified that the Racine representatives told him he could go ahead with the new lease in response to his report that the building’s owner was anxious for him to decide about the space.

    On March 23, Watson sent Kallmyer a letter intended to facilitate Fluid Power’s application for a Small Business Administration loan. It read in part:

    Per our conversation of March 22, 1982, I would like to confirm our intentions to appoint Cincinnati Fluid Power as our distributor in Southwestern Ohio, as soon as we can clear up some administrative details.

    Racine maintains that these “administrative details” were the termination of its relationship with Dynamic Technology and execution of a written agreement with Fluid Power.

    Kallmyer returned to Cincinnati and informed his landlord that Fluid Power wanted to lease the new, larger space. Soon, Fluid Power moved into the new facility and executed a lease that ran for 75 months beginning April 1, 1982. This lease and accompanying telephone and utility charges are the primary sources of Fluid Power’s alleged reliance damages.

    In early April 1982, Spaulding informed Ted Theiman, owner of Dynamic Technology, that Racine had determined to terminate its relationship with Dynamic Technology. Theiman responded by threatening litigation and demanding a meeting with senior executives of Racine. Despite lengthy discussions between Theiman and Racine representatives and an attempt by Kallmyer to purchase Dynamic Technology, that company continued as Racine’s exclusive distributor in southwestern Ohio. Racine never executed a distribution agreement with Fluid Power. There was evidence before the jury from which it could conclude either that Kallmyer learned of Theiman’s objections before he executed the lease for the new space or that he only learned of Racine’s difficulties after he was committed to the new, larger space. The jury also could find either that Kallmyer would have moved Fluid Power regardless of any promises by Racine or that the move was in reliance upon the March 22 representations. The jury returned a verdict in favor of Fluid Power and assessed $47,500 in damages.

    Two of Racine’s allegations of error on appeal challenge the trial court’s rejection of jury instructions requested by Racine. This Court reviews the adequacy of jury instructions taken as a whole. DSG Corp. v. Anderson, 754 F.2d 678, 682 (6th Cir.1985). Jury instructions are not prejudicial if they “adequately inform the jury of the relevant considerations and provide a basis in law for aiding the jury in reaching its determination.” Blackwell v. Sun Electric Corp., 696 F.2d 1176, 1181 (6th Cir.1983). If the instructions fairly and adequately cover material issues, it is not error to refuse to give other requested instructions, even though they correctly state the law. Carruba v. Transit Casualty Co., 443 F.2d 260, 264 (6th Cir.1971).

    Fluid Power went to the jury on a theory of promissory estoppel that was factually based upon the statements of Watson and Spaulding to Kallmyer during the March 22, 1982 meeting. Restatement of Contracts 2d, § 90, as recognized by the Ohio Supreme Court in McCroskey v. State, 8 Ohio St.3d 29, 456 N.E.2d 1204 (1983), provided the legal authority for Fluid Power’s theory of Racine’s liability. Fluid Power maintained that it had reasonably relied to its detriment upon a promise by Racine to establish it as a Racine distributor. Racine defended on two grounds, arguing first that its representatives had made no “promise” to Fluid Power but had merely expressed intentions, desires, or plans. In the alternative, Racine argued that it had made only a conditional promise to Fluid Power that was conditioned upon both ter*96mination of Racine’s relationship with Dynamic Technology and execution of a written agreement with Fluid Power.

    The trial court thoroughly and properly instructed the jury regarding the elements of estoppel. Estoppel requires a clear and unambiguous promise that reasonably and foreseeably induces reliance causing injury to the party bringing suit. See Talley v. Teamsters Local No. 377, 48 Ohio St.2d 142, 357 N.E.2d 44 (1976). Additionally, Racine offered an instruction based upon Restatement of Contracts 2d, § 91, which provides that performance of a conditional promise “becomes due only upon the occurrence of the condition or upon the arrival of the specified date.” The requested instruction accurately expresses the content of Restatement § 91 in the context of the events of this case. The trial court, however, declined to give this instruction and stated that he feared confusing the jury.

    Although the requested instruction accurately stated the law, the trial court did not necessarily commit reversible error by refusing to present it to the jury. Carruba, 443 F.2d at 264. The trial court did instruct the jury that Racine would only be liable if any promise it made to Fluid Power had “reasonably and forseeably induced reliance” by the plaintiff. Racine’s alleged liability arose from actions Fluid Power claimed to have taken in reliance upon the March 22 discussions both without confirming that Racine had cancelled Dynamic Technology, and without executing its own distribution agreement with Racine. If the jury had accepted Racine’s version of the March 22 discussions, this instruction would necessarily have resulted in a finding that Fluid Power’s reliance was not reasonable or foreseeable because Dynamic Technology was not cancelled and Fluid Power had not contracted with Racine. Racine had advanced no reason in this case for us not to apply the normal presumption that the jury followed the instructions correctly as given. See Pittman v. Littlefield, 438 F.2d 659, 662 (1st Cir.1971). See also Wright & Miller, Federal Practice and Procedure § 2258.

    We do not agree with the trial court that an instruction expressly concerning conditional promises would have confused the jury. The instructions that the trial court did give the jury regarding liability, however, when read as a whole, fairly and adequately informed the jury of the proper considerations by which to evaluate the central factual dispute on which Racine’s defense turned. Consequently, under the facts of this case, the trial court’s refusal to give such an instruction was harmless error at most. See Fed.R.Civ.P. 61.

    The second issue concerns the trial court’s refusal to give one of two requested instructions limiting the extent of Fluid Power’s reliance damages. The proposed, but unexecuted, written contract between Fluid Power and Racine would have expired on June 30, 1983, approximately fourteen months after Racine’s alleged promise to establish Fluid Power as its distributor. Allegedly in reliance on Racine’s promise, Fluid Power entered into a 75-month lease for larger premises. That lease extended five years past the proposed termination date of the unexecuted contract. Racine maintains that it was entitled to one of two instructions; either an instruction that Fluid Power’s damages for increased rental expenses could not extend beyond the term of the contemplated contract, or an instruction that the jury could award Fluid Power less than its reasonable reliance expenses if justice required.

    The trial court did not reversibly err by declining to limit Fluid Power’s recovery to the period of the contemplated contract. As a general matter, it is established that plaintiffs who recover damages in promissory estoppel actions should not be “placed in a better position for the alleged breach than they may have been had the promise been kept.” Gruen Industries, Inc. v. Biller, 608 F.2d 274, 281 (7th Cir.1979). In the present case, however, the nature and terms of any promise by Racine were properly questions for the jury to determine upon a review of all the *97evidence. The proposed contract did not establish the terms of the non-contractual promise on which Fluid Power sued; the proposed contract was neither fully negotiated nor executed by the parties. Nor did Fluid Power merely seek damages for Racine’s failure to execute the proposed contract as written. There was competent evidence before the jury that Racine established firm, long-term relationships with its distributors, which it was reluctant to sever. The jury could have concluded that Racine’s alleged promise to establish Fluid Power as its distributor involved a commitment far exceeding fourteen months. Therefore, the trial court properly declined to limit Fluid Power’s damages to the period of the contract.

    Racine’s alternative requested instruction limiting damages was based upon Restatement of Contracts 2d, § 90, which provides that, “The remedy granted for breach may be limited as justice requires.” The trial court satisfied this request by extensively instructing the jury that Fluid Power could only receive reasonable reliance damages that it could not have mitigated. The trial court instructed the jury that “the plaintiff is never given judgment for losses that he could have avoided by reasonable effort without risk of other substantial loss.” Additionally, the jury was told that Fluid Power’s damages “cannot exceed” the amount lost “because of reasonable or foreseeable reliance on a promise or an amount which was within the contemplation of the parties at the time the promise was made.” In sum, when read as a whole, the jury instructions fairly and adequately informed the jury of the proper considerations for determining both liability and damages in this case.

    Finally, Racine maintains that the jury’s award of $47,500 in damages to Fluid Power was not supported by competent and substantial evidence. A damage award must be supported by evidence from which the alleged loss may be reasonably calculated. Agricultural Services Association, Inc. v. Ferry-Morse Seed Co., 551 F.2d 1057, 1072 (6th Cir.1977). Fluid Power’s damage claims were based upon expenses associated with its move to larger facilities in order to accommodate the requirements for Racine distributors. The damage claims for increased utility and telephone expenses were supported by competent evidence in the form of both Kall-myer’s testimony from his personal knowledge as Fluid Power’s president and Fluid Power’s utility bills. Fluid Power’s accounting expenses associated with the move were similarly documented.

    The primary challenge on appeal to the damage award concerns evidence supporting Fluid Power’s claim for increased rent expenses. The total rent expenses under the new lease were $76,000; the lease itself was entered into evidence and supported this finding. Kallmyer testified that this would exceed Fluid Power’s lease expenses on its old quarters by $42,732. His testimony was based upon negotiations with his landlord for renewal of the lease for the old, smaller space. Racine objected to this testimony as hearsay, but was overruled. Racine maintains that there is no competent evidence of Fluid Power’s increased lease expenses because Kallmyer’s testimony was hearsay reporting the out-of-court declarations of his landlord.

    Kallmyer’s testimony concerning the price at which his landlord intended to renew Fluid Power’s lease was hearsay; it was testimony regarding the out-of-court statements of his landlord, offered to prove the truth of the matter asserted. See F.R.E. 801(c). Kallmyer’s testimony, however, was properly admitted into evidence under the hearsay exception established in F.R.E. 803(3). This provision allows admission of testimony regarding out-of-court statements of future intent and plans by declarants such as the landlord, although it generally does not allow admission of testimony concerning the declarant’s statements of memory or belief about his past intents or plans.

    The intent of Kallmyer’s landlord to renew Fluid Power’s lease at a certain price was at issue. Kallmyer testified regarding his landlord’s statements that expressed *98his then-future intent and the terms of his plan to renew Fluid Power’s lease at a certain price. This Court has previously approved admission under F.R.E. 803(3) of testimony regarding similar out-of-court statements of future intent. United States v. Williams, 704 F.2d 315, 321-22 (6th Cir.), cert. denied, — U.S.-, 104 S.Ct. 481, 78 L.Ed.2d 679 (1983) (testimony regarding statements of intent to use large sums of cash for certain legal purposes rather than for the purchase of cocaine); Detroit Police Officers’ Association v. Young, 608 F.2d 671, 693-94 (6th Cir.1979), cert. denied, 452 U.S. 938, 101 S.Ct. 3079, 69 L.Ed.2d 951 (1981) (testimony regarding statements of intent to discriminate racially). See also United States v. Harris, 733 F.2d 994, 1004 (2d Cir.1984); United States v. DiMaria, 727 F.2d 265, 270-71 (2d Cir.1984). F.R.E. 803(3) operates even where, as here, the declarant is available to testify. Detroit Police Officers’ Association, 608 F.2d at 694. Nor does Data General Corp. v. Scientific Information Management, Inc., 745 F.2d 56 (6th Cir.1984), control the present case. Data General is an unpublished opinion that does hot consider F.R.E. 803(3).

    For the foregoing reasons, the jury verdict and award of damages are Affirmed.

Document Info

Docket Number: 84-3326

Citation Numbers: 773 F.2d 92, 19 Fed. R. Serv. 272, 1985 U.S. App. LEXIS 23212

Judges: Jones, Krupansky, Per Curiam, Phillips

Filed Date: 9/19/1985

Precedential Status: Precedential

Modified Date: 10/19/2024