MEDFORD TOWNSHIP SCHOOL DISTRICT VS. SCHNEIDER ELECTRIC BUILDINGS AMERICAS, INC. (L-0787-18, BURLINGTON COUNTY AND STATEWIDE) , 459 N.J. Super. 1 ( 2019 )


Menu:
  •                 NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-5798-17T4
    MEDFORD TOWNSHIP
    SCHOOL DISTRICT,
    APPROVED FOR PUBLICATION
    Plaintiff-Respondent,                       April 26, 2019
    APPELLATE DIVISION
    v.
    SCHNEIDER ELECTRIC
    BUILDINGS AMERICAS, INC.,
    Defendant-Appellant.
    Argued April 1, 2019 – Decided April 26, 2019
    Before Judges Messano, Fasciale and Rose.
    On appeal from Superior Court of New Jersey, Law
    Division, Burlington County, Docket No. L-0787-18.
    Mark A. Rosen argued the cause for appellant
    (McElroy, Deutsch, Mulvaney & Carpenter, LLP,
    attorneys; Mark A. Rosen, of counsel and on the
    briefs).
    Richard W. Hunt argued the cause for respondent
    (Parker McCay PA, attorneys; Richard W. Hunt and
    John Neckonchuk, on the brief).
    The opinion of the court was delivered by
    ROSE, J.A.D.
    Defendant Schneider Electric Buildings Americas, Inc. (Schneider)
    appeals from a July 3, 2018 Law Division order enjoining and dismissing
    arbitration proceedings filed against plaintiff Medford Township School
    District (District). 1 We affirm.
    I.
    The dispute arises from the implementation of an energy savings
    improvement program (ESIP), N.J.S.A. 18A:18A-4.6, under which the District
    contracted with Schneider to design and implement upgrades to several of the
    District's schools and its transportation and operations center. Initially, the
    parties executed the Performance Assurance Support Services Agreement
    (PASS Agreement), requiring the District to monitor the ESIP's actual energy
    savings and guaranteeing the District a certain level of monetary savings. The
    PASS Agreement did not contain an arbitration provision.              Instead, its
    governing law clause provided, in pertinent part (emphasis added):
    This PASS Agreement will be governed,
    interpreted and construed by, under and in accordance
    with the laws, statutes and decisions of the state in
    which the [s]ervices are to be performed, without
    regard to its choice of law provisions. Venue shall be
    in the federal, state or municipal courts serving the
    county in which the [s]ervices are performed.
    1
    See R. 2:2-3(a)(3) (deeming an order compelling or denying arbitration "a
    final judgment of the court for appeal purposes").
    A-5798-17T4
    2
    Thereafter, the District issued a request for proposals (RFP), seeking a
    qualified energy services company (ESC) to perform the services of a general
    contractor for its ESIP. Among other things, the RFP outlined the terms of the
    ESIP Agreement, including development and implementation of an energy
    savings plan. Paragraph 30 of the RFP contained a governing law clause,
    which stated verbatim (emphasis added):
    The ESIP Agreement shall be governed by the
    laws of the State of New Jersey. The successful
    [ESC] shall agree that any action or proceeding that
    arises in any manner out of performance of the RFP or
    ESIP Agreement, shall be litigated in the Superior
    Court of New Jersey, Burlington County, State of New
    Jersey, and the [ESC] shall consent and submit to the
    jurisdiction of the Superior Court.
    After Schneider was awarded the project, the parties executed the
    Energy Services Construction Contract (ESCC). 2        Under the terms of the
    ESCC, the parties agreed that Schneider would be paid $2,494,575 for
    performing energy conservation measures, including lighting upgrades and
    building automation systems throughout the District.
    Article 5 of the ESCC contained a dispute resolution provision, which
    2
    The parties do not dispute that although the PASS Agreement predated the
    ESCC, which was executed in June 2015, and the RFP, which was issued in
    June 2014, the PASS Agreement applied to the project and Schneider's
    obligations. Inexplicably, however, the PASS Agreement was signed by the
    District's business administrator in January 2010 and Schneider's regional
    director in February 2012.
    A-5798-17T4
    3
    stated (emphasis added):
    5.1 To the extent allowed by applicable law, any
    controversy or claim arising out of or relating to this
    [c]ontract, or [c]ontract [d]ocuments, or any breach
    thereof, may be settled by binding arbitration in
    accordance with the Construction Industry Arbitration
    Rules of the American Arbitration Association
    [(AAA)], and judgment upon the award rendered by
    the arbitrator(s) may be entered in any court having
    jurisdiction thereof.
    5.2 The arbitration proceeding location shall be in
    the county in which the [p]roject is located.
    Schneider alleged it completed its scope of work under the ESCC in
    January 2017 but the District withheld $462,269, claiming the work was
    unsatisfactory. On March 14, 2018, Schneider filed a demand for arbitration
    with the AAA pursuant to the arbitration provision set forth in Article 5.1 of
    the ESCC.
    One month later, the District filed a verified complaint and an order to
    show cause (OTSC) in the Law Division, seeking to enjoin and dismiss
    Schneider's arbitration action.   The complaint also alleged breaches of the
    ESCC and PASS Agreement and other causes of action related to Schneider's
    performance of work on the project. The District claimed all of the contract
    disputes should be litigated in the Law Division.
    Schneider filed its answer to the complaint and opposition to the OTSC,
    countering the ESCC's arbitration provision was valid and enforceable.
    A-5798-17T4
    4
    Schneider further argued the District's "allegations of defective work under the
    [ESCC] are inextricably intertwined with Schneider's claim for payment and
    should be resolved in the [a]rbitration proceeding . . . ."
    On the return date of the OTSC, the trial judge rendered a tentative
    written decision granting the District's requested relief, but afforded the parties
    an opportunity to be heard.       Thereafter, the judge issued a well-reasoned
    amplified statement of reasons, 3 thoroughly addressing the parties' arguments
    and applying the relevant law.
    The trial judge acknowledged the validity of the arbitration provision,
    finding "no indication that [it] was included without negotiation or that it was
    an inconspicuous part of the [ESCC]." However, the judge further found by
    using the term, "may," the provision was permissive and not mandatory.
    Comparing the plain terms of the arbitration provision to other terms in the
    ESCC, the judge observed "the parties specifically used the word 'shall' when
    the terms were intended as mandatory."          For example, "mandatory 'shall'
    language r[an] throughout the entirety of Article 2 [pertaining to payments],
    except for where '[p]ayments may [have been] withheld.'"
    The trial judge found additional support for his conclusion in the
    governing law provision of the RFP, which "distinctly g[ave] the Burlington
    3
    See R. 2:5-1(b).
    A-5798-17T4
    5
    Vicinage of the Superior Court . . . jurisdiction over disputes arising from the
    implementation of the District's ESIP." As such, the judge reasoned the RFP,
    which preceded the ESCC, "serve[d] as extrinsic evidence for the ESCC – an
    agreement made to satisfy ESIP requirements – and help[ed] to uncover the
    actual meaning of the arbitration clause in the ESCC."
    In sum, the trial judge concluded:
    the permissive, "may" in the ESCC arbitration clause
    ma[d]e[] arbitration optional. In order for the ESCC
    arbitration clause to require arbitration, the clause
    needed to include mandatory language that waived the
    right to adjudicate in the courts or there needed to be
    mutual consent by the parties. As neither of [those]
    scenarios exist[ed] here, . . . the District's injunction
    request to restrain arbitration [is granted].
    This appeal followed.
    Schneider maintains the plain terms of the ESCC permit either party to
    select binding arbitration as a means for dispute resolution, which then
    compels the other party to arbitrate. In essence, Schneider claims the judge's
    interpretation of the arbitration provision renders the clause "superfluous"
    because a dispute resolution provision is unnecessary when both parties agree
    to arbitrate. Schneider further argues the judge erred in considering parol
    evidence because the ESCC contains a merger clause. We disagree.
    A-5798-17T4
    6
    II.
    Well-established legal principles guide our review. Because the validity
    of an arbitration agreement is a question of law, we review the order enjoining
    arbitration de novo. Barr v. Bishop Rosen & Co., 
    442 N.J. Super. 599
    , 605
    (App. Div. 2015) (citing Hirsch v. Amper Fin. Servs., LLC, 
    215 N.J. 174
    , 186
    (2013)); see also Kernahan v. Home Warranty Admin. of Fla., Inc., 
    236 N.J. 301
    , 316 (2019) ("Whether a contractual arbitration provision is enforceable is
    a question of law," accordingly we need not defer to the trial court's
    "interpretative analysis" unless it is "persuasive.").
    Our jurisprudence and public policy favor alternative dispute resolution
    and are consistent with our view that "[l]itigation ought to be a last resort, not
    a first one." Billig v. Buckingham Towers Condo. Ass'n, 
    287 N.J. Super. 551
    ,
    564 (App. Div. 1996); see also Cole v. Jersey City Med. Ctr., 
    215 N.J. 265
    ,
    276 (2013). Consequently, an "agreement to arbitrate should be read liberally
    in favor of arbitration." Angrisani v. Fin. Tech. Ventures, LP, 
    402 N.J. Super. 138
    , 148 (App. Div. 2008) (quoting Marchak v. Claridge Commons, Inc., 
    134 N.J. 275
    , 282 (1993)).
    Nonetheless, the policy favoring arbitration "is not without limits."
    Garfinkel v. Morristown Obstetrics & Gynecology Assocs., 
    168 N.J. 124
    , 132
    (2001).    Recently, our Supreme Court reiterated that "[a]n arbitration
    A-5798-17T4
    7
    agreement is valid only if the parties intended to arbitrate because parties are
    not required 'to arbitrate when they have not agreed to do so.'" Kernahan, 236
    N.J. at 317 (quoting Volt Info. Scis., Inc. v. Bd. of Trs. of Leland Stanford
    Junior Univ., 
    489 U.S. 468
    , 478 (1989)). The Court elaborated:
    In this state, when called on to enforce an
    arbitration agreement, a court's initial inquiry must be
    -- just as it is for any other contract -- whether the
    agreement to arbitrate all, or any portion, of a dispute
    is "the product of mutual assent, as determined under
    customary principles of contract law."
    [Id. at 319 (quoting Atalese v. U.S. Legal Servs. Grp.,
    LP, 
    219 N.J. 430
    , 442 (2014)).]
    In Atalese, the Court found, in the context of a consumer contract for
    debt-adjustment services, that "because arbitration involves a waiver of the
    right to pursue a case in a judicial forum, 'courts take particular care in
    assuring the knowing assent of both parties to arbitrate, and a clear mutual
    understanding of the ramifications of that assent.'" 219 N.J. at 442-43 (quoting
    NAACP of Camden Cty. E. v. Foulke Mgmt. Corp., 
    421 N.J. Super. 404
    , 425
    (App. Div. 2011)). Consequentially, when a contract contains a waiver of a
    right to pursue a statutory remedy in court, that waiver "must be clearly and
    unmistakably established." Garfinkel, 
    168 N.J. at 132
    . Accordingly, a "court
    may not rewrite a contract to broaden the scope of arbitration." 
    Ibid.
     (quoting
    A-5798-17T4
    8
    Yale Materials Handling Corp. v. White Storage & Retrieval Sys., Inc. , 
    240 N.J. Super. 370
    , 374 (App. Div. 1990)).
    As with other contractual provisions, courts look to the plain language
    the parties used in the arbitration provision. Id. at 135; see also Kernahan, 236
    N.J. at 321 ("A basic tenet of contract interpretation is that contract terms
    should be given their plain and ordinary meaning."); Quigley v. KPMG Peat
    Marwick, LLP, 
    330 N.J. Super. 252
    , 270 (App. Div. 2000) (in construing an
    arbitration clause, courts must honor the intentions of the parties as set forth in
    the language).
    At issue here is whether the terms of the arbitration clause permit or
    mandate arbitration. In certain contexts, we have recognized that where a
    provision permits the parties to select arbitration to resolve a dispute under the
    contract, but does not mandate arbitration, the provision is optional. Riverside
    Chiropractic Grp. v. Mercury Ins. Co., 
    404 N.J. Super. 228
    , 237-38 (App. Div.
    2008).
    In Riverside, we considered an arbitration clause in an automobile
    insurance contract, which permitted an injured party, the insured, and the
    assignee of the insured's provider to submit a claim to dispute resolution. 
    Id. at 233
    .   However, "the applicable insurance contract d[id] not entitle the
    insurer to elect arbitration over the wishes of the insured."         
    Id. at 238
    .
    A-5798-17T4
    9
    Pursuant to the plain language of the arbitration clause, we determined the use
    of the word "may" did not mandate arbitration. 
    Id. at 237
    . Instead, it afforded
    the provider-assignee of the insured "the option of filing for arbitration, but
    d[id] not require it to do so." 
    Ibid.
     We thus determined "had plaintiff opted to
    file its claim . . . initially in the trial court, nothing in the contract language
    would have forbidden the suit from going forward." 
    Ibid.
    Significantly, in Riverside, the policy at issue did not provide "[e]ither
    party may make a written demand for arbitration." 
    Id. at 238
     (alteration in
    original). Had the policy contained that language, we recognized it "could
    [have] be[en] construed as making arbitration mandatory, because if the
    insured elect[ed] to sue, the insurer c[ould] simply make a written demand for
    arbitration, which must then be honored."              
    Ibid.
     (emphasis added).
    Accordingly, when an arbitration provision specifically permits either party to
    select arbitration, once invoked, the other party may be bound to arbitrate the
    dispute. See e.g., Local 771, I.A.T.S.E. v. RKO Gen., Inc., 
    546 F.2d 1107
    ,
    1115-16 (2d Cir. 1977) (recognizing a contract that provides "[t]he parties may
    submit to arbitration" triggers mandatory arbitration and that "[n]either the
    word 'may' nor any other language used in the [a]greement implies that the
    parties had the option of invoking some remedy other than arbitration").
    A-5798-17T4
    10
    Against that legal backdrop, we begin our analysis by reiterating the
    arbitration clause at issue did not provide that either party may resolve
    disputes under the ESCC by binding arbitration. Rather, the clause generally
    provides "any controversy or claim arising out of or relating to [the ESCC], or
    [c]ontract [d]ocuments, or any breach thereof, may be settled by binding
    arbitration."   Nonetheless, Schneider urges us to interpret the provision as
    mandatory where, as here, it invoked arbitration and the parties to the contract
    are "two sophisticated entities."
    Notably, the District is not "an average member of the public[,]" nor is
    the ESCC a consumer contract. Cf. Atalese, 219 N.J. at 442-43. Indeed, the
    District is a public entity and was sophisticated enough to draft a fifty-five
    page RFP to solicit bids for a multi-million dollar project. Nor is the ESCC a
    contract of adhesion. As the judge aptly recognized, "[t]here is no indication
    that the arbitration provision was included without negotiation or that it was an
    inconspicuous part of the [ESSC]." We also agree with the trial judge that the
    arbitration provision is prominently "identifiable" on the fifth page of the
    nineteen-page ESCC.
    Pursuant to its plain terms, under certain circumstances the arbitration
    provision, standing alone, might support Schneider's argument that it is
    mandatory because the term, "may" permitted either of the two "sophisticated"
    A-5798-17T4
    11
    parties to invoke arbitration. Schneider contends interpreting the provision as
    permissive renders it superfluous because, even absent an arbitration clause,
    the parties to a contract can always submit a dispute to arbitration if the other
    consents. Without any related conflicting agreements executed between the
    parties mandating litigation, we might agree with Schneider's position. Such is
    not the case here, however.
    Rather, the terms of the arbitration clause, when read in pari materia
    with the mandatory provisions of the two governing law provisions in the RFP
    and PASS Agreement, both of which preceded the ESCC, mandate litigation
    and do not evince a clear intent to waive the right to sue in court. Contrary to
    Schneider's argument, the arbitration clause is not superfluous because the
    governing law provision of the RFP specifically required the successful bidder
    of the project to "agree" to "litigate[]" any disputes "aris[ing] in any manner
    out of performance of the RFP or ESIP Agreement" in the Burlington
    Vicinage. Likewise, interpretation and construction of the PASS Agreement
    was required to be resolved in "federal, state or municipal courts serving the
    county in which the [s]ervices [we]re . . . performed." Thus, the arbitration
    provision in the ensuing ESCC permitted the parties to choose a forum not
    previously agreed to, or permitted, under the mandatory governing law
    provisions of the PASS Agreement and RFP. Because the ESCC's dispute
    A-5798-17T4
    12
    resolution clause permitted arbitration when the parties previously did not have
    that option, the clause was not superfluous.
    Put another way, had the District consented to arbitration after that
    forum was invoked by Schneider, the parties would not have violated the
    governing law provisions of the PASS Agreement and RFP.             Reading the
    arbitration provision as a whole, however, the use of the permissive term,
    "may" without a clear indication that the parties intended to waive litigation
    cannot be harmonized with the PASS Agreement and RFP, both of which
    clearly require resolution of disputes under the ESIP in a court of law.
    We are likewise unpersuaded by Schneider's argument that the ESCC's
    merger clause prohibits the introduction of extrinsic evidence under the parol
    evidence rule.   As the trial court recognized, "[t]he ESCC and the PASS
    Agreement are in conflict regarding which contract's terms supersede if there
    are varying terms and conditions related to the same subject matter."
    Specifically, Article 13.5, the final article of the ESCC provides, in
    pertinent part: "[The ESCC] sets forth the entire understanding between the
    parties and supersedes all prior oral or written understandings related to the
    subject matter herein." Conversely, the second sentence on the first page of
    the PASS Agreement provides, "To the extent that the terms and conditions in
    this PASS Agreement conflict with the terms and conditions in the Energy
    A-5798-17T4
    13
    Services Contract, 4 the terms and conditions of this PASS Agreement shall
    control."
    Although the PASS Agreement and the ESCC apparently conflict
    regarding merger, the trial judge properly considered extrinsic evidence to
    support his decision that the arbitration clause was permissive. Our Supreme
    Court has long recognized, "[e]vidence of the circumstances is always
    admissible in aid of the interpretation of an integrated agreement. This is so
    even when the contract on its face is free from ambiguity." Conway v. 287
    Corp. Ctr. Assocs., 
    187 N.J. 259
    , 269 (2006) (alteration in original) (quoting
    Atlantic Northern Airlines, Inc. v. Schwimmer, 
    12 N.J. 293
    , 301 (1953)); see
    also Manahawkin Convalescent v. O'Neill, 
    217 N.J. 99
    , 118 (2014). Thus,
    notwithstanding the ESCC's merger clause, interpretation of the arbitration
    provision is not precluded by consideration of extrinsic evidence.
    Based on our de novo review of the record, when viewed in conjunction
    with the parties' related agreements, we agree with the trial judge that the
    ESCC's arbitration provision was permissive and not mandatory. As the judge
    correctly observed, the parties specifically used the term, "shall" when they
    intended certain provisions of the ESCC to be mandatory. Had the District and
    4
    It is not entirely clear from the record whether the "Energy Services
    Contract" is another term for the ESCC, which was not executed until June
    2015.
    A-5798-17T4
    14
    Schneider intended to resolve their disputes by mandatory arbitration, the
    ESCC should have explicitly so stated. Instead, use of the permissive term,
    "may" underscored their intention that the arbitration provision was
    permissive.   Further, Schneider drafted the agreement and, as such, to the
    extent there exists any ambiguity in the arbitration provision, that ambiguity
    should be construed against Schneider. See e.g., Roach v. BM Motoring, LLC,
    
    228 N.J. 163
    , 174 (2017).
    In sum, a permissive interpretation of the arbitration provision in the
    ESCC is consistent with the parties' prior intentions that disputes between
    them would be litigated in court, as expressed in both the PASS Agreement
    and RFP. Thus, we conclude under the facts presented that, absent its consent,
    the District was not bound to arbitrate its alleged breaches of the ESCC, nor
    Schneider's alleged breaches of the ESCC and PASS Agreement and other
    causes of action related to Schneider's performance of work on the project.
    Affirmed.
    A-5798-17T4
    15