Andrews v. Metropolitan Water Reclamation District of Greater Chicago ( 2021 )


Menu:
  •                                                                                Digitally signed
    by Reporter of
    Decisions
    Reason: I attest
    Illinois Official Reports                          to the accuracy
    and integrity of
    this document
    Supreme Court                               Date: 2021.01.29
    14:46:04 -06'00'
    Andrews v. Metropolitan Water Reclamation District of Greater Chicago,
    
    2019 IL 124283
    Caption in Supreme      BECKY ANDREWS et al., Appellees, v. THE METROPOLITAN
    Court:                  WATER RECLAMATION DISTRICT OF GREATER CHICAGO,
    Appellant.
    Docket No.              124283
    Filed                   December 19, 2019
    Decision Under          Appeal from the Appellate Court for the First District; heard in that
    Review                  court on appeal from the Circuit Court of Cook County, the Hon.
    William E. Gomolinski, Judge, presiding.
    Judgment                Appellate court judgment affirmed.
    Circuit court judgment reversed.
    Cause remanded.
    Counsel on              Michael Resis, of SmithAmundsen LLC, of Chicago, for appellant.
    Appeal
    Thomas A. Demetrio, Edward G. Willer, and Francis Patrick Murphy,
    of Corboy & Demetrio, P.C., of Chicago, for appellees.
    Robert E. Elworth, of HeplerBroom, LLC, of Chicago, for amicus
    curiae Illinois Association of Defense Trial Counsel.
    Kirsten M. Dunne, of GWC Injury Lawyers LLC, of Chicago, for
    amicus curiae Illinois Trial Lawyers Association.
    Justices                 CHIEF JUSTICE BURKE delivered the judgment of the court, with
    opinion.
    Justices Thomas, Kilbride, Theis, and Neville concurred in the
    judgment and opinion.
    Justice Karmeier dissented, with opinion, joined by Justice Garman.
    OPINION
    ¶1        At issue in this appeal is whether a water reclamation district is immune from liability
    pursuant to sections 2-109 and 2-201 of the Local Governmental and Governmental Employees
    Tort Immunity Act (Tort Immunity Act) (745 ILCS 10/2-109, 2-201 (West 2012)) for injuries
    suffered by the employee of a contractor. The circuit court of Cook County held defendant was
    entitled to immunity and entered summary judgment for defendant. The appellate court
    reversed the circuit court’s judgment. 
    2018 IL App (1st) 170336
    . We now affirm the judgment
    of the appellate court, reverse the judgment of the circuit court, and remand for further
    proceedings.
    ¶2                                           BACKGROUND
    ¶3         The Metropolitan Water Reclamation District of Greater Chicago (District) owns and
    operates the Calumet water reclamation plant located at 400 East 130th Street in Chicago. On
    July 10, 2008, the District entered into a contract with a joint venture, F.H. Paschen, S.N.
    Nielsen/IHC Construction (Joint Venture), for the “Primary Settling Tanks and Grit Removal
    Facilities” project to be carried out at the Calumet plant. The Joint Venture was the general
    contractor for the project.
    ¶4         According to the contract, it was the Joint Venture’s responsibility to determine the
    procedures and methods for the work and furnish all temporary structures and safety
    equipment. The Joint Venture was also responsible for the safety of all personnel on the work
    site, including its own employees and District personnel. The contract required the Joint
    Venture to submit plans for the work to the District’s engineer. The engineer then had the right
    to disapprove and reject any procedures and methods he deemed to be unsafe. The contract
    provided, however, that the engineer’s acceptance of the plans did not relieve the Joint Venture
    of its responsibility for safety, maintenance, and repairs on the project.
    ¶5         Jeffrey Andrews was an employee of F.H. Paschen, S.N. Nielsen & Associates, LLC, a
    member of the Joint Venture. On April 21, 2011, Andrews was assigned to work at the plant’s
    primary settling tank number 2402. According to the complaint in this case, prior to that date
    it had rained heavily, causing the area around the tank to be extremely muddy and the tank to
    -2-
    collect three feet of standing water. Andrews and a coworker, Luis Cuadrado, were assigned
    the job of applying grout to a gate at the bottom of a 29-foot effluent chamber.
    ¶6       In order to reach the bottom of the chamber, the workers used two ladders. First, they
    ascended a short, job-made wooden ladder to reach the top of the chamber. Then, they pivoted
    their bodies around the wooden ladder and onto a fiberglass extension ladder, which was set
    inside the chamber. The workers would then descend into the chamber using the fiberglass
    ladder. The two ladders were higher than the top of the chamber and were angled toward each
    other. There was no platform for workers to transition between the ladders. It was alleged that
    this two-ladder configuration had been used several times to reach the bottom of other tanks in
    the course of the construction project. While transitioning from the job-made ladder to the
    fiberglass ladder, Andrews fell approximately 30 feet and landed on Cuadrado, who had
    already descended to the bottom of the chamber. Both men were severely injured. Andrews
    suffered broken bones and severe, career-ending head injuries.
    ¶7       On January 3, 2012, Andrews’s wife, Becky Andrews, filed suit against the District, both
    individually and as plenary guardian of the person and estate of her husband. Plaintiff filed an
    amended complaint on January 3, 2013. The amended complaint contained four counts
    alleging construction negligence, loss of consortium for construction negligence, willful and
    wanton construction negligence, and loss of consortium for willful and wanton construction
    negligence. Defendant filed a combined motion to dismiss citing both sections 2-615 and 2-
    619 of the Code of Civil Procedure (735 ILCS 5/2-615, 2-619 (West 2012)). Defendant
    asserted it was immune from liability for the failure to supervise an activity on public property,
    pursuant to section 3-108 of the Tort Immunity Act. 745 ILCS 10/3-108 (West 2012). 1 This
    defense applied only to the negligence counts, since section 3-108 expressly excepts willful
    and wanton conduct from immunity. See 
    id.
     Defendant also argued that the amended complaint
    failed to state a cause of action for willful and wanton conduct.
    ¶8       On May 3, 2013, the trial court dismissed the two negligence counts with prejudice on the
    grounds that defendant was entitled to immunity under section 3-108. The court dismissed the
    willful and wanton counts without prejudice, allowing plaintiff to replead those counts. On
    October 10, 2013, plaintiff filed her second amended complaint, adding the Joint Venture as a
    defendant. 2 The second amended complaint alleged two counts of willful and wanton
    construction negligence against the District, one count on behalf of Jeffrey Andrews and one
    count for Becky Andrews’s loss of consortium. Both counts alleged that defendant
    “30. *** failed in one or more of the following respects with an utter indifference and
    a conscious disregard for plaintiff’s safety:
    a. allowed workers to work upon effluent chambers without the use of access
    platforms, when it had actual knowledge that employees were previously not using
    them;
    b. failed to supervise their employees on site when it knew of previous occasions
    when crews were working without fall protection;
    1
    As a “sanitary district,” the District is a local governmental body covered by the Act. See 70 ILCS
    2605/1 et seq. (West 2012); 745 ILCS 10/1-206 (West 2012).
    2
    The counts against the Joint Venture were later dismissed with prejudice based on the exclusive
    remedy provision of the Workers’ Compensation Act. 820 ILCS 305/5(a) (West 2012).
    -3-
    c. willfully failed to implement its fall protection plan by not providing supervision
    by a competent person;
    d. willfully failed to provide an offset platform or landing between the portable
    ladder and the 43’ fiberglass extension ladder, when it had actual knowledge that offset
    platforms were previously not being used;
    e. failed to implement a mandatory fall protection plan when it had actual
    knowledge of prior occasion [sic] when employees were not utilizing fall protection;
    f. failed to implement a safety plan when it had actual knowledge that employees
    were transitioning from makeshift ladders to extension ladders without access
    platforms;
    g. willfully failed to provide an adequate or suitable scaffold or ladder for Jeffrey
    Andrews to carry out his work when it knew Jeffrey Andrews was transitioning without
    an access platform;
    h. required the F.H. Paschen, S.N. Nielsen & Associates, LLC crew members to
    work around the subject settling tank when it knew it was extremely muddy and knew
    that the inside of the chamber contained excessive water;
    i. knowingly allowed Jeffrey Andrews to work in a confined work site in sloppy,
    rainy, muddy, and wet weather conditions;
    j. willfully failed to provide a wide enough opening so that the slope of the ladder
    could be adequately extended, allowing Jeffrey Andrews to work safely when it knew
    the opening was too small to allow for a proper slope of the ladder;
    k. willfully failed to provide fall restraints to Jeffrey Andrews when it knew Jeffrey
    Andrews did not have fall restraints during the transitioning stage;
    l. [the District’s] on-site engineer willfully failed to provide the necessary
    requirements for water site control, as per the contract;
    m. willfully failed to provide safe, suitable site-control to Jeffrey Andrews, as per
    the contract; and
    n. knowingly failed to properly monitor the work activities of the F.H. Paschen,
    S.N. Nielsen & Associates, LLC crew members.”
    ¶9         On March 4, 2014, defendant filed a motion to dismiss the second amended complaint
    pursuant to section 2-615 of the Code of Civil Procedure. 735 ILCS 5/2-615 (West 2012).
    Defendant argued that the complaint failed to state a cause of action for willful and wanton
    conduct because it did not allege that defendant had knowledge of any prior accidents or
    injuries. On April 23, 2014, the trial court granted in part and denied in part the motion to
    dismiss. The court found that plaintiff had failed to plead adequate causes of action for the
    willful and wanton failure to supervise. Accordingly, the court struck with prejudice the
    allegations of willful and wanton supervision set forth in paragraphs 30(b) and 30(c) of the two
    willful and wanton counts corresponding to Jeffrey and Becky Andrews in the complaint.
    ¶ 10       On October 22, 2014, defendant filed a motion to dismiss the second amended complaint
    pursuant to section 2-619(a)(9) of the Code of Civil Procedure. 
    Id.
     § 2-619(a)(9). Defendant
    argued that it owed no duty to plaintiff based on the general rule that one who employs an
    independent contractor is not liable for the acts or omissions of the independent contractor.
    Moreover, defendant argued that it did not retain sufficient control over the contractor’s work
    -4-
    to establish liability pursuant to the “retained control” exception set forth in section 414 of the
    Restatement (Second) of Torts. See Restatement (Second) of Torts § 414 (1965). The trial
    court denied the motion, finding an issue of fact precluded dismissal of the case.
    ¶ 11       Subsequently, on April 11, 2016, defendant filed a motion for summary judgment arguing
    that defendant was immune from liability under sections 2-109 and 2-201 of the Tort Immunity
    Act (745 ILCS 10/2-109, 2-201 (West 2012)). These sections immunize a local governmental
    entity from liability for injuries arising out of its employee’s acts or omissions while
    determining policy and exercising discretion. Id. However, defendant did not support its
    immunity defense with evidence that its employees made discretionary or policy decisions with
    respect to the two-ladder configuration that resulted in Andrews’s injuries. In fact, defendant
    referenced the deposition testimony of seven witnesses, all of whom testified that no District
    employees weighed in on worksite safety decisions.
    ¶ 12       For example, Greg Florek, a senior civil engineer for the District and the resident engineer
    assigned to the project, testified that the District had nothing to do with how the contractor
    performed its work or with safety aspects of the work. Florek admitted that he had no education
    or training in construction safety. He testified that he walked the job site once or twice a day
    in order to check the progress and confirm that the work was being done in compliance with
    the contract. Florek testified that he did not know when the two ladders were placed in the
    effluent chamber at the site of the accident, nor did he recall ever seeing that type of ladder
    configuration prior to the accident. He also stated that he never inspected the ladders involved
    in the occurrence or assessed whether they complied with any codes, rules, or regulations.
    ¶ 13       Defendant also cited the deposition testimony of John Lemon, defendant’s principal civil
    engineer, and Douglas Pelletier, an employee of the general contractor and the senior manager
    on the project. Lemon testified that defendant did not supervise the means and methods of the
    work performed by contractors and did not have a designated person responsible for project
    safety. He testified that the general contractor was solely responsible for safety. Pelletier
    testified that the contractor was responsible for stopping any unsafe work at the job site. He
    also testified that defendant did not enforce safety or tell the workers how to do their work.
    ¶ 14       Despite the lack of evidence showing that any safety decisions were made by its employees,
    defendant argued it was immune from liability based solely on its contract with the Joint
    Venture. The contract language specified that defendant’s engineer “may disapprove and
    reject” any “procedures, methods, structures or equipment *** which seem[ed] to him to be
    unsafe for the work hereunder.” Defendant argued that this language reserved its right to make
    decisions concerning safety. It argued that the reservation of the right to exercise discretion,
    standing alone, is sufficient to invoke discretionary immunity under the Tort Immunity Act,
    even if that right is never exercised. In addition, defendant argued, its “decision[s] on what
    contractor to hire, the contractor’s scope of work, the terms and conditions by which the work
    was to be performed, and decisions regarding delegation as to means and method and safety
    are all discretionary acts.”
    ¶ 15       The trial court agreed and entered summary judgment in defendant’s favor. The court ruled
    that “the [District] engineer had discretionary authority to make policy determinations under
    the terms of the contract between [the District] and subcontractor Paschen to enforce project
    safety.” Based on the contract language, the court concluded that defendant was entitled to
    -5-
    absolute immunity under sections 2-109 and 2-201. Plaintiff’s motion to reconsider was denied
    by the trial court.
    ¶ 16        Plaintiff appealed two of the trial court’s rulings: (1) the order dismissing the claims for
    willful and wanton supervision set forth in paragraphs 30(b) and 30(c) of two counts in the
    second amended complaint and (2) the order granting summary judgment for defendant on the
    remaining claims based on tort immunity. The appellate court reversed the trial court’s
    judgment on both issues and remanded for further proceedings. 
    2018 IL App (1st) 170336
    ,
    ¶¶ 32-33. On the first issue, the court held that the allegations of willful and wanton supervision
    were sufficient to defeat a motion to dismiss. Id. ¶ 17. On the second issue, the court held that
    defendant failed to prove its entitlement to immunity under section 2-201 and, thus, summary
    judgment was improper on the remaining willful and wanton claims. 3 Id. ¶¶ 18-28. The court
    held, “[i]n this case, even if Florek was in a position where he was entitled to make
    determinations of policy and exercise discretion, there is no evidence that he was making
    policy or exercising discretion with respect to the act or injury [sic] from which Andrews’s
    injury resulted.” Id. ¶ 21. “To the contrary, Florek testified and defendant has remained
    steadfast throughout the case that Florek did not know about the ladder configuration.” Id. The
    court concluded, “[j]ust because a party has a right to exercise discretion does not mean that it
    did exercise discretion.” Id. ¶ 28.
    ¶ 17        Defendant filed a petition for leave to appeal in this court, which we granted. Ill. S. Ct.
    R. 315(a) (eff. July 1, 2018). We also allowed the Illinois Association of Defense Trial Counsel
    to file an amicus curiae brief in support of defendant’s position and the Illinois Trial Lawyers’
    Association to file an amicus curiae brief in support of plaintiffs’ position. Ill. S. Ct. R. 345
    (eff. Sept. 20, 2010).
    ¶ 18                                              ANALYSIS
    ¶ 19       On appeal to this court, defendant asks that we reverse the appellate court’s judgment and
    affirm the trial court’s entry of summary judgment in its favor. Defendant challenges only the
    immunity portion of the appellate court’s judgment. Thus, the only issue in this appeal is
    whether defendant established its immunity defense pursuant to sections 2-109 and 2-201 of
    the Tort Immunity Act.
    ¶ 20       A party is entitled to summary judgment where “the pleadings, depositions, and admissions
    on file, together with the affidavits, if any, show that there is no genuine issue as to any material
    fact and that the moving party is entitled to a judgment as a matter of law.” 735 ILCS 5/2-
    1005(c) (West 2012). Because summary judgment is a drastic means of disposing of litigation,
    the trial court must construe the evidence in the record strictly against the movant. Adams v.
    Northern Illinois Gas Co., 
    211 Ill. 2d 32
    , 43 (2004). Furthermore, the court should grant
    summary judgment only if the movant’s right to a judgment is clear and free from doubt. 
    Id.
    On review of the trial court’s order granting summary judgment, this court must determine
    3
    We note that the appellate court incorrectly stated that summary judgment was entered as to
    “plaintiff’s claims based on simple negligence.” 
    2018 IL App (1st) 170336
    , ¶¶ 8, 18. In fact, the trial
    court had previously dismissed the negligence claims, and plaintiff did not appeal that dismissal order.
    Thus, the only claims at issue on summary judgment were those alleging willful and wanton conduct.
    We conclude that the appellate court’s mischaracterization of the claims did not affect its resolution of
    the tort immunity issue.
    -6-
    whether the existence of a genuine issue of material fact should have precluded the dismissal
    of the case or, absent such an issue of fact, whether summary judgment was proper as a matter
    of law. Kedzie & 103rd Currency Exchange, Inc. v. Hodge, 
    156 Ill. 2d 112
    , 116-17 (1993).
    ¶ 21       We review de novo the trial court’s order granting summary judgment. Barnett v. Zion Park
    District, 
    171 Ill. 2d 378
    , 385 (1996). This case involves statutory interpretation, an issue of
    law also subject to de novo review. Brunton v. Kruger, 
    2015 IL 117663
    , ¶ 24.
    ¶ 22                                           Tort Immunity Act
    ¶ 23        In 1959, this court abolished sovereign immunity from tort claims for local governmental
    entities. Molitor v. Kaneland Community Unit District No. 302, 
    18 Ill. 2d 11
    , 24-25 (1959). In
    response to that decision, in 1965, the General Assembly enacted the Tort Immunity Act.
    Zimmerman v. Village of Skokie, 
    183 Ill. 2d 30
    , 43 (1998); see also Ill. Const. 1970, art. XIII,
    § 4 (recognizing the abolition of sovereign immunity, “[e]xcept as the General Assembly may
    provide by law”). The Tort Immunity Act governs whether and under what circumstances local
    governmental entities are immune from liability in civil actions. Harinek v. 161 North Clark
    Street Ltd. Partnership, 
    181 Ill. 2d 335
    , 340 (1998). Unless a specific immunity provision
    applies, a public entity is liable in tort to the same extent as a private party. Barnett, 
    171 Ill. 2d at 386
    . Since the Tort Immunity Act is in derogation of the common law, it must be construed
    strictly against the public entity seeking immunity. Snyder v. Curran Township, 
    167 Ill. 2d 466
    , 477 (1995). In addition, the public entity or employee asserting an immunity defense bears
    the burden of proving it is entitled to that immunity. Van Meter v. Darien Park District, 
    207 Ill. 2d 359
    , 370 (2003).
    ¶ 24        In construing the provisions in the Tort Immunity Act, we bear in mind that the primary
    goal of statutory construction is to discern and effectuate the intent of the legislature. Home
    Star Bank & Financial Services v. Emergency Care & Health Organization, Ltd., 
    2014 IL 115526
    , ¶ 24. The best indicator of legislative intent is the language of the statute, given its
    plain and ordinary meaning. Ultsch v. Illinois Municipal Retirement Fund, 
    226 Ill. 2d 169
    , 181
    (2007). A reviewing court may not read into the statute any exceptions, conditions, or
    limitations that conflict with the clear legislative intent. Metropolitan Life Insurance Co. v.
    Hamer, 
    2013 IL 114234
    , ¶ 18. However, in interpreting the statutory language, we may
    consider the purpose and necessity for the law, the evils sought to be remedied, and the goals
    to be achieved. Crossroads Ford Truck Sales, Inc. v. Sterling Truck Corp., 
    2011 IL 111611
    ,
    ¶ 45.
    ¶ 25        Sections 2-109 and 2-201 of the Tort Immunity Act provide as follows:
    “A local public entity is not liable for an injury resulting from an act or omission of its
    employee where the employee is not liable.” 745 ILCS 10/2-109 (West 2012).
    “Except as otherwise provided by Statute, a public employee serving in a position
    involving the determination of policy or the exercise of discretion is not liable for an
    injury resulting from his act or omission in determining policy when acting in the
    exercise of such discretion even though abused.” 
    Id.
     § 2-201.
    ¶ 26        Read together, these sections shield a municipality from liability for the discretionary acts
    or omissions of its employees. Smith v. Waukegan Park District, 
    231 Ill. 2d 111
    , 118 (2008).
    Discretionary immunity for public officials is “premised upon the idea that such officials
    should be allowed to exercise their judgment in rendering decisions without fear that a good-
    -7-
    faith mistake might subject them to liability.” Harrison v. Hardin County Community Unit
    School District No. 1, 
    197 Ill. 2d 466
    , 472 (2001) (citing White v. Village of Homewood, 
    285 Ill. App. 3d 496
    , 502 (1996)). Section 2-201 provides absolute immunity for both negligence
    and willful and wanton conduct. In re Chicago Flood Litigation, 
    176 Ill. 2d 179
    , 195-96
    (1997). This court has recognized that the broad immunity in section 2-201 “offers the most
    significant protection afforded to public employees under the [Tort Immunity] Act.” Arteman
    v. Clinton Community Unit School District No. 15, 
    198 Ill. 2d 475
    , 484 (2002) (citing David
    C. Baum, Tort Liability of Local Governments and Their Employees: An Introduction to the
    Illinois Immunity Act, 1966 U. Ill. L.F. 981, 994).
    ¶ 27        By its plain language, section 2-201 immunizes a public employee who serves in “a
    position involving the determination of policy or the exercise of discretion” from liability for
    injuries allegedly caused by the employee’s “act or omission in determining policy when acting
    in the exercise of such discretion.” 745 ILCS 10/2-201 (West 2012). As this court has noted,
    the statutory language “is concerned with both the type of position held by the employee and
    the type of action performed or omitted by the employee.” (Emphases in original.) Harinek,
    
    181 Ill. 2d at 341
    . Thus, the test for determining whether a municipality is entitled to
    discretionary immunity is twofold. 
    Id.
     The municipal defendant must establish that (1) the
    employee held either a position involving the determination of policy or a position involving
    the exercise of discretion and (2) the employee engaged in both the determination of policy
    and the exercise of discretion when performing the act or omission from which the plaintiff’s
    injury resulted. 
    Id.
    ¶ 28        Policy determinations are defined as decisions requiring the public entity or employee to
    balance competing interests and make a judgment call as to what solutions will best serve each
    of those interests. Harrison, 
    197 Ill. 2d at
    472 (citing West v. Kirkham, 
    147 Ill. 2d 1
    , 11 (1992)).
    Such interests may include safety, convenience, and cost. West, 
    147 Ill. 2d at 11
    . Exercises of
    discretion are those that are “unique to a particular public office.” Snyder, 
    167 Ill. 2d at 474
    .
    An employee’s act or omission will be deemed discretionary where the employee has exercised
    “personal deliberation and judgment in deciding whether to perform a particular act, or how
    and in what manner that act should be performed.’ ” Monson v. City of Danville, 
    2018 IL 122486
    , ¶ 30 (quoting Wrobel v. City of Chicago, 
    318 Ill. App. 3d 390
    , 394-95 (2000)).
    Determining whether an act or omission is discretionary should be made on a case-by-case
    basis depending on the particular facts and circumstances. Snyder, 
    167 Ill. 2d at 474
    .
    ¶ 29        The only disputed issue in this appeal is whether Florek exercised discretion and made a
    policy determination in connection with the alleged acts or omissions that resulted in plaintiff’s
    injuries. If the answer is “no,” then the District has not established its affirmative defense of
    immunity under section 2-201 of the Tort Immunity Act. See Van Meter, 
    207 Ill. 2d at 379
     (to
    invoke immunity under section 2-201, a municipal defendant is required to establish both
    elements with respect to the alleged act or omission).
    ¶ 30        This court’s recent decision in Monson controls our analysis in this case. The plaintiff in
    that case sued the City of Danville for her injuries after tripping and falling on an uneven seam
    in a sidewalk. Monson, 
    2018 IL 122486
    , ¶ 1. The City moved for summary judgment, asserting
    discretionary immunity under sections 2-201 and 2-109 of the Tort Immunity Act. 
    Id.
     In
    support of this defense, the City provided evidence that its employees had completed a project
    to inspect and repair the city’s downtown sidewalks approximately one year prior to plaintiff’s
    -8-
    accident. Id. ¶ 34. It was uncontested that the sidewalk slabs involved in plaintiff’s accident
    were within the subject area and were not repaired in the course of the project. Based on this
    evidence, the City argued that its employees effectively exercised discretion and made a policy
    determination not to repair the section of sidewalk that allegedly caused plaintiff’s injuries. Id.
    We rejected this argument. Id. ¶ 32.
    ¶ 31        We held that a municipality seeking immunity under section 2-201 for the failure to repair
    a defective condition “must present sufficient evidence that it made a conscious decision not
    to perform the repair. The failure to do so is fatal to the claim.” (Emphasis added.) Id. ¶ 33.
    We held that, in the absence of a conscious decision on the part of the municipality, “nearly
    every failure to maintain public property could be described as an exercise of discretion,”
    which constitutes an “ ‘ “impermissibly expansive definition of discretionary immunity.” ’ ”
    Id. ¶ 35 (quoting Corning v. East Oakland Township, 
    283 Ill. App. 3d 765
    , 768 (1996), quoting
    Snyder, 
    167 Ill. 2d at 472
    ).
    ¶ 32        To illustrate the standard of proof required by the statute, we favorably cited two appellate
    court decisions—Gutstein v. City of Evanston, 
    402 Ill. App. 3d 610
     (2010), and Corning, 
    283 Ill. App. 3d 765
    . Monson, 
    2018 IL 122486
    , ¶ 33. In Gutstein, the city claimed it was immune
    from liability for the plaintiff’s injuries resulting from tripping and falling in an unimproved
    alley. Gutstein, 402 Ill. App. 3d at 611-12. The appellate court rejected the city’s immunity
    defense, finding there was “nothing in the record to show that any work was done in the alley,
    certainly not how it was done.” Id. at 626. In Corning, the appellate court held the defendants
    were not immune from liability for their failure to replace a missing stop sign where there was
    no evidence they were aware the sign was missing or made a conscious decision to remove it.
    Corning, 283 Ill. App. 3d at 768.
    ¶ 33        Similar to Gutstein and Corning, the record in Monson contained no documentation of the
    City’s decision not to repair the specific sidewalk slab at issue. Monson, 
    2018 IL 122486
    , ¶ 35.
    We stated:
    “While the City presented evidence that the [accident] site was included in an overall
    evaluation of its sidewalks, there are no facts regarding the City’s assessment of the
    actual site. We do not know which factors were taken into account by the City in
    deciding not to repair the sidewalk. More importantly, we do not know whether anyone
    even took note of a sidewalk deviation at that location, or whether it was simply
    overlooked.” Id. ¶ 38.
    For these reasons, we held that the City failed to establish evidence that its handling of the
    sidewalk deviation constituted an exercise of discretion. Id.
    ¶ 34        Thus, according to our precedent, a municipal defendant asserting immunity under section
    2-201 must present evidence of a conscious decision by its employee pertaining to the conduct
    alleged to have caused the plaintiff’s injuries. It follows that, if the employee was totally
    unaware of a condition prior to the plaintiff being injured, he or she could not possibly have
    exercised discretion with respect to that condition. Notably, other jurisdictions that have
    reached the issue agree that a public entity claiming immunity for its employee’s exercise of
    discretion must present evidence of a conscious decision on the part of the employee. See, e.g.,
    Goss v. City of Globe, 
    883 P.2d 466
    , 468-69 (Ariz. Ct. App. 1994); Caldwell v. Montoya, 
    897 P.2d 1320
    , 1326, 1327-28 (Cal. 1995) (en banc); Greathouse v. Armstrong, 
    616 N.E.2d 364
    ,
    367 (Ind. 1993); Schmitz v. City of Dubuque, 
    682 N.W.2d 70
    , 74 (Iowa 2004); Kolitch v.
    -9-
    Lindedahl, 
    497 A.2d 183
    , 197 (N.J. 1985); Little v. Wimmer, 
    739 P.2d 564
    , 569 (Or. 1987)
    (en banc); Foster v. South Carolina Department of Highways & Public Transportation, 
    413 S.E.2d 31
    , 35 (S.C. 1992); Little v. Utah State Division of Family Services, 
    667 P.2d 49
    , 51
    (Utah 1983); King v. City of Seattle, 
    525 P.2d 228
    , 233 (Wash. 1974) (en banc); Oyler v. State,
    
    618 P.2d 1042
    , 1048 & n.12 (Wyo. 1980); see also 63 C.J.S. Municipal Corporations § 886
    (Sept. 2019 Update) (“Before immunity attaches, there must be some form of considered
    decision, that is, one that consciously balances risks and advantages.”); 57 Am. Jur. 2d
    Municipal, County, School, and State Tort Liability § 66 (Nov. 2019 Update) (“The
    government must prove that the challenged act or omission was a policy decision made by
    consciously balancing risks and benefits.”).
    ¶ 35       In this case, defendant has presented no evidence documenting a decision by its employees
    with respect to the condition involved in the accident. As the appellate court below held, the
    record contains no documentation of “any decision or refusal to decide whether to use the
    ladder configuration that resulted in Andrews being injured—there was no decision-making
    process at all.” 
    2018 IL App (1st) 170336
    , ¶ 24. There is no evidence that Florek, defendant’s
    resident engineer, exercised judgment or skill in making decisions about ladders or access
    platforms. Nor is there evidence that he balanced competing interests and made a determination
    as to what solution would best serve each of those interests. Florek admitted in his deposition
    that he was totally unaware of the two-ladder setup that allegedly caused Andrews’s injuries.
    Therefore, he was unable to weigh the risks and benefits and make a conscious decision with
    respect to the condition involved in the accident.
    ¶ 36       Nevertheless, defendant argues that Florek’s unawareness of the ladder formation does not
    defeat its discretionary immunity defense. According to defendant, the contract between the
    District and the Joint Venture delegated safety responsibilities to the contractor and gave its
    engineer the right, but not the duty, to involve himself in these decisions. Florek subsequently
    opted not to make any decisions concerning worker safety. Defendant contends that Florek’s
    election not to weigh in on safety issues demonstrates a conscious exercise of discretion under
    section 2-201. We disagree.
    ¶ 37       Defendant appears to be characterizing its employee’s choice not to make any safety
    decisions at all as an “omission.” If so, this is a clear misreading of the statute. The plain
    statutory language states that the act or omission giving rise to the injuries must constitute both
    an exercise of discretion and a determination of policy. 745 ILCS 10/2-201 (West 2012); see
    Harinek, 
    181 Ill. 2d at 341
    . This language requires that the entity or person claiming immunity
    must have made an actual decision with respect to the acts or omissions giving rise to the
    injuries. Consequently, an “omission” must be construed as an affirmative decision to take no
    action given the circumstances. No such decision was made in this case. The most that can be
    said is that a decision was made by default, which is insufficient to invoke discretionary
    immunity. See, e.g., Corning, 283 Ill. App. 3d at 768 (holding defendants could not claim
    discretionary immunity for the removal of a stop sign where it was removed without their
    knowledge or authority); Goss, 
    883 P.2d at 468-69
     (holding defendant could not claim
    discretionary immunity where the city made no actual decision not to spend money on
    guardrails or sidewalks). Accordingly, as in Monson, we hold that defendant has failed to
    sustain its burden of proving that its employee exercised discretion and made a policy
    determination pursuant to section 2-201.
    - 10 -
    ¶ 38        Our determination that defendant has not established its entitlement to immunity is
    consistent with the purpose and goals of the statute. The general purpose of the Tort Immunity
    Act is to “protect local public entities and public employees from liability arising from the
    operation of government.” 745 ILCS 10/1-101.1(a) (West 2012). This court has held that the
    “ ‘operation of government’ necessarily encompasses the policy decisions made by a
    municipality; that is, those decisions which require the municipality to balance competing
    interests and to make a judgment call as to what solution will best serve each of those interests.”
    West, 
    147 Ill. 2d at 11
    .
    ¶ 39        The discretionary immunity now codified in section 2-201 was originally termed “quasi-
    judicial immunity.” Kennell v. Clayton Township, 
    239 Ill. App. 3d 634
    , 642 (1992) (citing
    Kelly v. Ogilvie, 
    64 Ill. App. 2d 144
    , 147 (1965), aff’d 
    35 Ill. 2d 297
     (1966)). The principle
    underlying this immunity is that public decision makers, like judges, should be free to make
    decisions and exercise their judgment based upon their best perception of public needs without
    fear of being subjected to a lawsuit. Id.; White, 285 Ill. App. 3d at 502. “The courts reason that
    any other rule would be a great hardship on public officials and would discourage citizens from
    seeking public positions.” Midamerica Trust Co. v. Moffatt, 
    158 Ill. App. 3d 372
    , 376 (1987)
    (citing McCormick v. Burt, 
    95 Ill. 263
    , 266 (1880)).
    ¶ 40        As noted in the most recent edition of Prosser and Keaton on Torts, discretionary
    governmental immunity is also premised on the principles that “the judiciary should not invade
    the province of the executive branch of government by supervising its decisions through tort
    law, and that if liability were imposed for discretionary decisions, effective executive action
    would be chilled.” Prosser and Keaton on the Law of Torts § 131, at 1046 (W. Page Keeton
    et al. eds., 5th ed. 1984). These principles “counsel use of the immunity only when there is no
    ‘predictable standard’ for decision making, where there is room for difference in official
    judgment, and where in fact some official judgment has been brought to bear on the
    governmental action that has caused the plaintiff harm.” (Emphasis added.) Id. at 1046-47. It
    follows that the policy reasons for granting immunity are furthered only when the government
    entity or its employee has engaged in actual decision making.
    ¶ 41        Defendant has failed to offer a policy rationale that justifies immunity for the making of
    no decision. Nor can we think of one. In the absence of a judgment call and a weighing of risks
    and benefits, there is nothing to protect. Any governmental entity can enter into a contract in
    which it reserves the right to make discretionary decisions. If this guarantees absolute
    immunity from liability, there is no incentive for local governments to supervise work or
    maintain their property. Rather, immunizing a nondecision would reward public officials and
    employees who ignore problems instead of addressing them. It also would broaden the scope
    of discretionary immunity well beyond what the legislature intended. As we have explained,
    defendant’s theory that merely entering into a construction contract satisfies the statute is
    directly contrary to the plain language of section 2-201. The clear legislative intent is that, for
    immunity to apply, the governmental employee must actually “exercise” discretion and
    “determine” policy. See 745 ILCS 10/2-201 (West 2012). A contract provision giving a
    municipality the right to exercise discretion and determine policy at some future time is not
    equivalent to an actual exercise of discretion.
    ¶ 42        Defendant argues that In re Chicago Flood, 
    176 Ill. 2d 179
    , compels a different result. In re
    Chicago Flood involved a class action lawsuit filed against the City of Chicago for property
    - 11 -
    damage and economic loss suffered as a result of flooding in the tunnel beneath the central
    business district of the city. 
    Id. at 183
    . Approximately one year prior to the flood, the City
    contracted with Great Lakes Dredge and Dock Company (Great Lakes) for the removal and
    replacement of wooden pilings at five bridges spanning the Chicago River. During this process,
    the tunnel wall was breached. 
    Id. at 184-85
    . Seven months later, the tunnel breach opened,
    causing extensive flooding in buildings connected to the tunnel. 
    Id. at 185
    . The class plaintiffs’
    numerous claims against the City included the failure to supervise Great Lakes’ work, the
    failure to repair the tunnel after the breach, and the failure to warn of the dangerous condition.
    
    Id. at 185-86
    .
    ¶ 43       With respect to the failure to supervise claim, this court held that the City was immune
    from liability for negligence pursuant to section 3-108(a) of the Tort Immunity Act (745 ILCS
    10/3-108(a) (West 1994)). In re Chicago Flood, 
    176 Ill. 2d at 193
    . In addition, we held that
    the City’s allegedly negligent and willful and wanton supervision of Great Lakes was
    immunized by sections 2-109 and 2-201 of the Tort Immunity Act. 
    Id. at 195-96
    . The class
    plaintiffs argued that discretionary immunity was inapplicable because, “once the City
    approved the pile driving plan, its actions ceased to be discretionary and became ministerial.”
    
    Id. at 194-95
    . We rejected this argument, reasoning that,
    “[i]n the present case, the contract between the City and Great Lakes provided that ‘the
    contractor shall not drive the pilings at any other location than that specified by the
    City,’ and authorized the City to change its specifications. Thus, the City retained the
    discretion to locate the pilings in any location it thought best. [Citation.] This was a
    matter within the City’s discretion for which there is immunity under the [Tort
    Immunity] Act.” 
    Id. at 195
    .
    ¶ 44       Relying on this language, defendant argues that a contract provision that retains a
    government entity’s discretion to make decisions is sufficient to establish section 2-201
    immunity without a further showing that discretion was consciously exercised. We disagree.
    ¶ 45       In re Chicago Flood was decided prior to Harinek, 
    181 Ill. 2d at 341
    , where this court
    addressed for the first time whether section 2-201 requires that a public entity’s act or omission
    be both an exercise of discretion and a determination of policy. We held:
    “According to the statute, an employee may be granted immunity if he holds either
    a position involving the determination of policy or a position involving the exercise of
    discretion. The statute is equally clear, however, that immunity will not attach unless
    the plaintiff’s injury results from an act performed or omitted by the employee in
    determining policy and in exercising discretion.” (Emphases in original.) 
    Id.
    ¶ 46       Twenty years later, in Monson, we articulated the standard of proof required to satisfy the
    exercise of discretion element. Monson, 
    2018 IL 122486
    , ¶ 33. This court expressly held that
    a local public entity claiming immunity under section 2-201 must present evidence that it made
    a “conscious decision” with respect to the acts or omissions alleged in the complaint. 
    Id.
     We
    further held that “[t]he failure to do so is fatal to the claim.” 
    Id.
     To the extent that In re Chicago
    Flood can be read as suggesting that a contract provision alone satisfies the exercise of
    discretion element in section 2-201, we now clarify that our most recent elucidation of the
    standard of proof is controlling. Furthermore, Cabrera v. ESI Consultants, Ltd., 
    2015 IL App (1st) 140933
    , and any other decisions applying a lesser standard of proof are hereby overruled.
    See id. ¶ 125 (holding that a construction contract granting the City of Chicago the right to
    - 12 -
    reject methods used by contractors qualified the City for discretionary immunity). In this case,
    it was defendant’s burden to support its immunity defense with evidence of conscious decision
    making, and it has failed to sustain that burden. See, e.g., Monson, 
    2018 IL 122486
    , ¶¶ 38-39;
    Gutstein, 402 Ill. App. 3d at 626.
    ¶ 47       Defendant’s final argument is based on public policy. Defendant contends that our reading
    of the statute imposes an undue hardship on local governments because it conflicts with a
    defendant’s ability to assert a defense under section 414 of the Restatement (Second) of Torts.
    Restatement (Second) of Torts § 414 (1965). It is important to note that defendant is not
    arguing it owed no duty in this case. The existence of a duty is not at issue in this appeal.
    Rather, defendant is urging this court to interpret section 2-201 of the Tort Immunity Act in a
    manner compatible with a section 414 defense.
    ¶ 48       Section 414 of the Restatement is a recognized exception to the common-law rule that one
    who employs an independent contractor is not liable for harm caused by the acts or omissions
    of the independent contractor. Carney v. Union Pacific R.R. Co., 
    2016 IL 118984
    , ¶¶ 31, 33-
    35. This provision states:
    “One who entrusts work to an independent contractor, but who retains the control
    of any part of the work, is subject to liability for physical harm to others for whose
    safety the employer owes a duty to exercise reasonable care, which is caused by his
    failure to exercise his control with reasonable care.” Restatement (Second) of Torts
    § 414 (1965).
    Thus, the existence of a duty under section 414, and liability for negligence generally, turns on
    the extent to which the hiring entity controls the work of the independent contractor. See
    Carney, 
    2016 IL 118984
    , ¶ 41.
    ¶ 49       Defendant argues that construing section 2-201 of the Tort Immunity Act to require
    evidence that a public entity involved itself in the contractor’s work would deprive public
    entities of a defense under section 414 of the Restatement. Defendant reasons that public
    entities would be required to “go above and beyond what their contracts require” to control the
    work delegated to the contractor in order to sustain a tort immunity defense under section 2-
    201. This could impact a defendant’s ability to claim it owed no duty to an injured plaintiff.
    Defendant argues, therefore, that section 2-201 should be read to allow a public entity to satisfy
    the statute through evidence that it entered into a contract reserving its right to exercise
    discretion. We reject defendant’s argument.
    ¶ 50       A defense predicated on section 414 of the Restatement (Second) of Torts is not in conflict
    with tort immunity. Whether a local governmental entity owed a duty of care and whether it is
    entitled to immunity are discrete issues, which must be analyzed separately. Coleman v. East
    Joliet Fire Protection District, 
    2016 IL 117952
    , ¶ 46; Village of Bloomingdale v. CDG
    Enterprises, Inc., 
    196 Ill. 2d 484
    , 490 (2001); Barnett, 
    171 Ill. 2d at 388
    . This court has noted
    that “ ‘[t]he distinction between an immunity and a duty is crucial, because only if a duty is
    found is the issue of whether an immunity or defense is available to the governmental entity
    considered.’ ” Coleman, 
    2016 IL 117952
    , ¶ 46 (quoting Zimmerman, 
    183 Ill. 2d at 46
    ).
    Moreover, section 2-201 of the Tort Immunity Act does not distinguish between a public entity
    who enters into a contract for construction work and one who does not. See 745 ILCS 10/2-
    201 (West 2012). All local governmental entities are held to the same standard. Accordingly,
    defendant’s argument is not a valid reason to ignore the express, unambiguous language in the
    - 13 -
    statute.
    ¶ 51                                        CONCLUSION
    ¶ 52       Construing the Tort Immunity Act strictly against defendant, as we must (Monson, 
    2018 IL 122486
    , ¶ 15), we find that defendant has not met its burden of establishing discretionary
    immunity under sections 2-109 and 2-201. We hold, therefore, that defendant is not entitled to
    summary judgment as a matter of law.
    ¶ 53       For the foregoing reasons, we affirm the judgment of the appellate court, reverse the
    judgment of the circuit court, and remand for further proceedings.
    ¶ 54       Appellate court judgment affirmed.
    ¶ 55       Circuit court judgment reversed.
    ¶ 56       Cause remanded.
    ¶ 57       JUSTICE KARMEIER, dissenting:
    ¶ 58       This case differs from Monson v. City of Danville, 
    2018 IL 122486
    —which the majority
    finds controlling, and the genesis of a “conscious decision” rule—in that Monson concerned
    the governmental entity’s endeavor to inspect its own sidewalks and effect its own repairs.
    This case, in contrast, speaks to a governmental entity’s employment of an intermediary, a
    construction contractor, to carry out the work with the contractor’s own workers under the
    direct supervision of the contractor’s personnel, but with the governmental entity’s retained
    contractual authority to “disapprove or reject” procedures it deemed “inadequate or unsafe.” 4
    Retained contractual authority, where a contractor was employed to do the work, is what In re
    Chicago Flood Litigation, 
    176 Ill. 2d 179
     (1997), and Cabrera v. ESI Consultants, Ltd., 
    2015 IL App (1st) 140933
    , specifically addressed and what the cases cited by the majority do not.
    ¶ 59       Whether one agrees or disagrees with the holding of Chicago Flood—that the City was
    entitled to absolute immunity under sections 2-109 and 2-201 because it retained contractual
    oversight and discretion with respect to the matter resulting in injury—that decision is the law
    4
    The contract provided:
    “The Contractor shall determine the procedure and methods and also design and furnish all
    temporary structures, sheeting, bracing, tools, machinery, implements and other equipment and
    plant to be employed in performing the work hereunder, and shall promptly submit layouts and
    schedules of his proposed methods of conducting the work to the Engineer for his approval. The
    use of inadequate or unsafe procedures, methods, structures or equipment will not be permitted,
    and the Engineer may disapprove and reject any of same which seem to him to be unsafe for the
    work hereunder, or for other work being carried on the vicinity or for work which has been
    completed or for the public or for any workmen, engineers and inspectors employed thereon, or
    that interferes with the work of the Water Reclamation District or other contractors, or that will not
    provide for the completion of the work within the specified time, or that is not in accordance with
    all the requirements herein specified.”
    No one disputes the terms of the contract, which was made a part of the record in this case. Although
    there are numerous other contractual provisions specifying that the contractor was solely responsible
    for safety, the foregoing paragraph unequivocally grants the defendant’s on-site engineers discretion
    and policy oversight with respect to safety.
    - 14 -
    until it is overruled, and in doing that, “[w]e may not depart from stare decisis without special
    justification.” Iseberg v. Gross, 
    227 Ill. 2d 78
    , 101 (2007); see also People v. Hernandez, 
    231 Ill. 2d 134
    , 144-45 (2008). In this context, I think a recent observation of Justice Thomas does
    apply:
    “If the majority believes this court’s cases are in error, it needs to overrule them. If
    it believes that the court made a mistake, then it should own the mistake rather than
    claiming that our cases say something other than what they clearly say. However, this
    would require a discussion of why departure from stare decisis is appropriate, which
    may be difficult. Stare decisis considerations are at their apex in matters of statutory
    construction.” (Emphasis added.) People v. Dupree, 
    2018 IL 122307
    , ¶ 69 (Thomas,
    J., specially concurring, joined by Kilbride, J.)
    The majority simply suggests that our jurisprudence has evolved past Chicago Flood—a
    suggestion voiced in no case previous to this in the course of the last 22 years—and that the
    majority is merely “clarifying” the law with “our most recent elucidation of the standard of
    proof.” Supra ¶ 46. Yet in truth, this court is effectively overruling Chicago Flood.
    ¶ 60        The court specifically overrules Cabrera, lumping it in with “any other decisions applying
    a lesser standard of proof” than that applied by the majority. Supra ¶ 46. However, Cabrera
    merely applies the clear holding of Chicago Flood, to even more compelling circumstances, 5
    and the Cabrera court does not espouse a significantly different standard of proof than that the
    majority applies (see Cabrera, 
    2015 IL App (1st) 140933
    , ¶ 122), other than omission of the
    newly recognized “conscious decision” doctrine.
    ¶ 61        So, where does the “conscious decision” rule go from here? How will it be applied to cases
    where public entities employ contractors?
    ¶ 62        My first concern is that the rule announced today may, in the future, result in the unintended
    consequence of less safety supervision on construction sites, not more. Governmental entities
    may well attempt to do in contracting what this defendant’s engineers did while testifying: 6
    5
    The contract language in Cabrera is very similar to the contract provisions in this case. However,
    the City’s engineer (Shum) in Cabrera, while emphasizing that the contractor was solely responsible
    for safety, also freely admitted—unlike the engineers here—that he had the authority to shut down the
    construction project for safety violations if he saw fit. He had the discretion; he could determine policy
    on site:
    “Shum testified that safety was not the City’s responsibility, and the City did not require a site-
    specific safety plan. Shum did not have any role on this project with respect to jobsite safety; safety
    was the contractor’s responsibility. The contractor was responsible for determining what the
    workers needed for safety. He testified that if he observed anything unsafe he would inform the
    foreman. He testified that if he observed grease and slippery surfaces at the preconstruction
    meeting, he would tell the contractor to clean it up because it was the contractor’s responsibility to
    keep the site clean. ***
    Shum testified that he had the authority to stop work if he observed something hazardous or
    dangerous at a jobsite. He had the ability to shut down the whole project.” Cabrera, 
    2015 IL App (1st) 140933
    , ¶¶ 46-47.
    6
    The engineers in this case chose to interpret—or at least claimed to have interpreted—the contract
    in a way that could negate duty by ceding all control over matters of safety to the contractor. (The
    majority takes pains to emphasize: “It is important to note that defendant is not arguing it owed no duty
    - 15 -
    lay responsibility for overseeing safety solely at the door of the contractors. In Carney v. Union
    Pacific R.R. Co., 
    2016 IL 118984
    , ¶¶ 31-39, we addressed the nuanced consequences of
    control—or divestiture thereof—in work performed by a contractor on behalf of someone else.
    This court noted: “Under the common law, one who employs an independent contractor is not
    liable for harm caused by the latter’s acts or omissions.” Id. ¶ 31. However, “ ‘[t]he test of the
    relationship is the right to control. It is not the fact of actual interference with the control, but
    the right to interfere, that makes the difference between an independent contractor and a servant
    or agent.’ ” Id. (quoting Hartley v. Red Ball Transit Co., 
    344 Ill. 534
    , 539 (1931)). Thus,
    applying that test, if the hiring entity retains any right of advisory supervision over safety
    concerns, the entity could be liable—in this instance—for willful and wanton conduct. The
    solution for one hiring a contractor is to vest the contractor with sole responsibility for safety.
    That would result in fewer eyes focused on safety, not more.
    ¶ 63       Moreover, on a pragmatic level, the “conscious decision” rule today runs counter to our
    analysis of negligence in selecting a contractor in Carney. If the “ ‘character of the work to be
    done *** can be properly done only by persons possessing special skill and training,’ ” a
    municipality will likely be less able to exercise the conscious decisions in day-to-day
    operations necessary to claim discretionary immunity. Id. ¶ 66 (quoting Restatement (Second)
    of Torts § 411 cmt. c, at 378 (1965)). Municipalities employ contractors for a multitude of
    tasks, for many of which the public entity may possess little or no expertise. This is a case in
    point: the engineers who had the authority to exercise the retained contractual right of
    supervision over safety acknowledged in their depositions that they had no training whatsoever
    in matters relating to safety. To impose the duty of rendering decisions in all of a contractor’s
    day-to-day minutiae to avoid liability not only contradicts the utility of subcontracting but, in
    highly specialized tasks, may be practically inconceivable. 7
    ¶ 64       Given these considerations, in the future, decisions might well be made to sacrifice control
    over safety measures in order to minimize potential liability.
    ¶ 65       My second concern is that this “conscious decision” rule will come to require the
    articulation of “magic words” evincing a conscious decision, a requirement that ignores what
    may be reasonably inferred from conduct and circumstance. The engineers in this case, via
    their interpretation of the contract, effectively ceded oversight over matters of safety to the
    contractor. They did not say that was their conscious decision, but that was clearly their
    in this case. The existence of a duty is not at issue in this appeal.” (supra ¶ 47)) Admittedly, the
    defendant in this case tried to have it both ways: defendant claimed discretionary immunity, via retained
    contractual control, under sections 2-109 and 2-201, and it attempted to negate any duty to the plaintiffs
    through deposition testimony of defendant’s engineer-supervisors and representatives of the contractor,
    to the effect that the contractor was solely responsible for safety on the construction project. Patrick
    Healy, the contractor’s foreman, admitted in his deposition testimony that Florek could, through the
    contractor’s superintendent, stop work if he observed an unsafe practice. Irrespective of how the
    engineers chose to interpret the contract, a conscious decision was made that impacted supervision of
    safety on the project.
    7
    Although not at issue here, I would note that the amount of care we require to avoid liability in
    selecting a contractor, when the work “can be properly done only by persons possessing special skill
    and training,” evinces a “conscious decision” that the majority would require for discretionary
    immunity.
    - 16 -
    determination of policy and responsibility on the job site. Thus, even if the contractual right to
    control is not enough alone, as it was in Chicago Flood, to accord the entity immunity, the
    engineers’ interpretation and implementation of supervisory obligations on the job site would
    nonetheless suffice to accord the entity immunity.
    ¶ 66       But what if the facts are as plaintiff alleges in her complaint? What if the engineers in fact
    witnessed all the safety concerns and silently chose to do nothing, having it in their power to
    act? Is that not a conscious decision that would entitle the defendant to immunity? Ahrens, the
    director of public works in Monson, could not recall inspecting or measuring the particular
    slab of concrete where plaintiff fell. No conscious decision. The majority here opines: “In this
    case, defendant has presented no evidence documenting a decision by its employees with
    respect to the condition involved in the accident.” 8 Supra ¶ 35. Well, what supervisory
    deficiencies has this plaintiff alleged of defendant?
    ¶ 67       Plaintiff alleged that defendant,
    “with an utter indifference and a conscious disregard for plaintiff’s safety:
    a. allowed workers to work upon effluent chambers without the use of access
    platforms, when it had actual knowledge that employees were previously not using
    them;
    b. failed to supervise their employees on site when it knew of previous occasions
    when crews were working without fall protection;
    c. wilfully failed to implement its fall protection plan by not providing
    supervision by a competent person;
    d. wilfully failed to provide an offset platform or landing between the portable
    ladder and the 43’ fiberglass extension ladder, when it had actual knowledge that
    offset platforms were previously not being used;
    e. failed to implement a mandatory fall protection plan when it had actual
    knowledge of prior occasion [sic] when employees were not utilizing fall
    protection;
    f. failed to implement a safety plan when it had actual knowledge that
    employees were transitioning from makeshift ladders to extension ladders without
    access platforms;
    g. wilfully failed to provide an adequate or suitable scaffold or ladder for Jeffrey
    Andrews to carry out his work when it knew Jeffrey Andrews was transitioning
    without an access platform;
    h. required the F.H. Paschen, S.N. Nielsen & Associates, LLC crew members
    to work around the subject settling tank when it knew it was extremely muddy and
    knew that the inside of the chamber contained excessive water;
    8
    Does an entity retaining supervisory control over a contractor even have to be aware of the
    condition involved in the accident? In an appropriate case, where discretion and policy decisions are
    made with respect to the creation and maintenance of a system of supervision and oversight, does the
    failure to find and address the condition in question necessarily preclude immunity? If it does, then the
    entity’s required degree of involvement would seem to be commensurate with that of the contractor
    itself. That would certainly entail a dramatic shift in the allocation of human resources in governmental
    construction projects.
    - 17 -
    i. knowingly allowed Jeffrey Andrews to work in a confined work site in sloppy,
    rainy, muddy, and wet weather conditions;
    j. wilfully failed to provide a wide enough opening so that the slope of the ladder
    could be adequately extended, allowing Jeffrey Andrews to work safely when it
    knew the opening was too small to allow for a proper slope of the ladder;
    k. wilfully failed to provide fall restraints to Jeffrey Andrews when it knew
    Jeffrey Andrews did not have fall restraints during the transitioning stage;
    l. [the District’s] on-site engineer wilfully failed to provide the necessary
    requirements for water site control, as per the contract;
    m. wilfully failed to provide safe, suitable site-control to Jeffrey Andrews, as
    per the contract; and
    n. knowingly failed to properly monitor the work activities of the F.H. Paschen,
    S.N. Nielsen & Associates, LLC crew members.” (Emphases added.)
    ¶ 68       So, according to plaintiff, defendant, with “conscious disregard” for Andrews’s safety,
    knowing all those things, failed to act. Is that something other than a “conscious decision?” If
    plaintiff proves the very things she professes provable in her complaint, has plaintiff not made
    the case that defendant, through its engineers on site, made a conscious decision not to act—
    the final requisite for immunity under the new analytical standard? Or are we to assume the
    engineers were devoid of any mental processes whatsoever?
    ¶ 69       “Section 2-1005 of the [Code] provides for summary judgment when the pleadings,
    depositions, and admissions on file, together with any affidavits, show that there is no genuine
    issue as to any material fact ***.” (Emphases added.) Forsythe v. Clark USA, Inc., 
    224 Ill. 2d 274
    , 280 (2007); 735 ILCS 5/2-1005 (West 2012). Plaintiff has, presumably in good faith,
    claimed in her complaint that the defendant’s engineers knew of the dangerous conditions and
    did nothing. Taking those allegations as true, the defendant would be entitled to immunity
    under sections 2-109 and 2-201.
    ¶ 70       In light of the foregoing concerns, I cannot subscribe to the majority decision.
    ¶ 71      JUSTICE GARMAN joins in this dissent.
    - 18 -