Borough v. Waverly, Sayre & Athens Traction Co. ( 1921 )


Menu:
  • Opinion by

    Mr. Justice Walling,

    In 1893 the plaintiff borough by ordinance, duly accepted by defendant, authorized the latter to occupy certain streets, including North Elmer Avenue, with its street railway. This the defendant did and constructed a single track road upon the avenue, which it has since maintained. The ordinance provides, inter alia, that, “Whenever any grade shall be changed along the street or avenue line of said tracks, the grade of street railway shall be at once altered at the expense of said company to conform to the new grade......And whenever this borough council shall decree or ordain the paving of any street or avenue upon which switches, tracks or turnouts are laid, the company shall at once pave between their rails and for eighteen inches outside them, with material as used or ordained by the borough or with vitrified brick at the company’s option.” The avenue was then an earth road at natural grade, but in the spring of 1917 the borough enacted an ordinance and let a contract for laying a concrete pavement therein. Of this defendant had due notice and was requested to lay its part of the pavement, but neglected and refused to do so. Paving the avenue necessitated slight changes of grade ranging from one to eight inches at the street intersections, being the usual levelling of the surface of an earth road when-changing it into a paved street. To this new grade, defendant failed to bring its track, although duly requested. Three years have elapsed since the borough completed its part of the improvement, but the avenue is still in a disturbed and unsafe condition by *414reason of appellant’s default. Defendant’s failure to comply with the original ordinance caused plaintiff an extra expense of $1,266.92; to recover which and compel defendant to bring its tracks to grade and complete the pavement, the borough filed this bill. The case was heard upon bill, answer, replication and testimony; the chancellor found the facts, stated his legal conclusions and, after passing upon exceptions, entered a final decree granting the relief prayed for; from which defendant brought this appeal.

    The case was well tried and rightly decided. Defendant could not enter the borough without its consent '(article NVII, section 9, state Constitution) and the franchise ordinance as accepted forms a contract between the parties, with which defendant must comply.

    Equity has jurisdiction to compel a street railway company to specifically perform its contract with the municipality for the making of street improvements (Patton Twp. v. Street Ry. Co., 226 Pa. 372; Chambers-burg Borough v. C. & G. Elec. Ry. Co., 258 Pa. 57) ; and having obtained jurisdiction for that purpose it will, to prevent a multiplicity of suits, grant complete relief by ordering such company to pay the loss its failure of performance 'caused the municipality:, see Allison and Evans’s App., 77 Pa. 221.

    Defendant’s financial embarrassment and difficulty in procuring material and labor constitute no legal excuse for failure to perform its contract. The alleged inability to procure new rails is entirely without merit, as plaintiff offered to permit defendant to use the rails then in place. Since this improvement was undertaken before our entrance into the world war, and before any request from the government to refrain from unnecessary work, the patriotic objection made to it is not well taken. Leaving the avenue torn up and unsafe for traffic did not assist in winning the war.

    As the street crossings affected were all on the ground long before the pavement was started, and there was *415no attempt at or intention of establishing, abolishing, relocating, or substantially changing the grade of any crossing, the case does not fall within the jurisdiction of the Public Service Commission. A municipality is not required to get the consent of the commission before it can make an inconsequential change of a few inches in the grade of its existing street intersections, rendered necessary by a street improvement, although there may be a railway track upon the street so improved. This is especially so where, as here, the railway company is under contract to conform the grade of its track to that of the street as the municipality may establish it.

    The decree is affirmed and appeal dismissed at the costs of appellant.

Document Info

Docket Number: Appeal, No. 272

Judges: Frazer, Kephart, Moschzisker, Sadler, Schaffer, Simpson, Walling

Filed Date: 5/2/1921

Precedential Status: Precedential

Modified Date: 10/19/2024