Petrohawk Properties, L.P. v. Chesapeake Louisiana, L.P. , 689 F.3d 380 ( 2012 )


Menu:
  •      Case: 11-30576   Document: 00511932058   Page: 1   Date Filed: 07/24/2012
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT  United States Court of Appeals
    Fifth Circuit
    FILED
    July 24, 2012
    No. 11-30576                    Lyle W. Cayce
    Clerk
    PETROHAWK PROPERTIES, L.P.,
    Plaintiff - Appellant Cross-Appellee
    v.
    CHESAPEAKE LOUISIANA, L.P.,
    Defendant - Appellee Cross-Appellant
    LEE WELDON STOCKMAN; PATSY BISON STOCKMAN,
    Defendants - Appellees
    Appeals from the United States District Court
    for the Western District of Louisiana
    Before KING, HIGGINBOTHAM, and HIGGINSON, Circuit Judges.
    KING, Circuit Judge:
    What follows is the tale of competing mineral leases on the Louisiana
    property of Lee and Patsy Stockman during the Haynesville Shale leasing
    frenzy. In April 2008, the Stockmans entered into an extension of their mineral
    lease with Chesapeake Louisiana, L.P. and received a $240,000 bonus. In May
    2008, the Stockmans entered into a mineral lease with Petrohawk Properties,
    L.P. for a $1.45 million bonus. In July 2008, Petrohawk dishonored the $1.45
    million draft and executed a second mineral lease with the Stockmans, paying
    Case: 11-30576   Document: 00511932058      Page: 2   Date Filed: 07/24/2012
    No. 11-30576
    them a $1.7 million bonus. Chesapeake sued the Stockmans for breach of
    contract, and the parties settled at trial. The Stockmans then sued Petrohawk
    for fraud in obtaining the first mineral lease, and Chesapeake sued Petrohawk
    for intentional interference with its contract with the Stockmans. Petrohawk
    prayed for a judgment that its mineral lease was valid or, in the alternative, for
    a return of its bonus money. After a bench trial, the district court found that
    Petrohawk procured the first mineral lease by fraud and rescinded the lease.
    The district court dismissed Chesapeake’s tort claim and dismissed Petrohawk’s
    claim for a return of its bonus money. Petrohawk appealed, and Chesapeake
    cross-appealed. For the following reasons, we AFFIRM the judgment of the
    district court.
    I. BACKGROUND
    A. Statement of Facts
    Lee and Patsy Stockman (the “Stockmans”) own real property in Caddo
    Parish, Louisiana (the “Stockman property”). On July 14, 2005, the Stockmans
    entered into a mineral lease with Stellios Exploration Company (the “Stellios
    Lease”), which was later assigned to Chesapeake Louisiana, L.P. (“Chesapeake”).
    The primary term of the Stellios Lease expired on July 14, 2008, and the Stellios
    Lease did not contain an option to extend the primary term. However, the
    Stellios Lease provided that the lease could be maintained beyond the primary
    term by conducting drilling operations on the leased premises. On April 9, 2008,
    Chesapeake and the Stockmans executed an extension of the Stellios Lease (the
    “Chesapeake Extension”). Chesapeake tendered to the Stockmans a draft for the
    lease bonus of $500 per acre, which amounted to $241,430. Chesapeake did not
    immediately record the Chesapeake Extension.
    On May 8, 2008, Lisa Broomfield (“Broomfield”) approached the
    Stockmans about leasing their property to Petrohawk Properties, L.P.
    (“Petrohawk”). Broomfield was a landman working for Pangaea Land Services
    2
    Case: 11-30576   Document: 00511932058     Page: 3   Date Filed: 07/24/2012
    No. 11-30576
    (“Pangaea”) on behalf of its client, Petrohawk. Lee Stockman (“Mr. Stockman”)
    informed Broomfield that he had already signed the Chesapeake Extension.
    Broomfield responded that the Chesapeake Extension was not “legal or valid”
    because Chesapeake had not yet recorded it.         Broomfield explained that
    Louisiana was a race state and that if Petrohawk recorded its lease first, the
    Chesapeake Extension would be invalid. Broomfield did not tell Mr. Stockman
    that the Chesapeake Extension would still be valid as to the Stockmans
    regardless of recordation and that the Stockmans could be liable to Chesapeake
    for breaching the obligation of good faith if they signed a competing lease with
    Petrohawk. She offered the Stockmans a lease bonus of $3,000 per acre for a
    mineral lease with Petrohawk, which amounted to $1.45 million.
    After speaking with Broomfield, Mr. Stockman called his neighbor, who
    was a retired geologist and had experience with mineral leases. The neighbor
    gave Mr. Stockman the following language to include in the lease: “This lease is
    executed [without] warranty of title, either expressed or implied, not even as to
    the return of bonus money or any other payments.” That evening, Broomfield
    sent an email to her supervisor stating that the Stockmans had already signed
    the Chesapeake Extension. She explained that Mr. Stockman “realizes that if
    [Petrohawk does not] win the race to the courthouse he is stuck with $500 per
    acre.” Furthermore, she stated that Mr. Stockman requested a lease bonus of
    $3,500 per acre and the inclusion of both vertical and horizontal Pugh clauses
    in the lease. Broomfield also testified that Mr. Stockman had requested a three-
    year primary term with a two-year option to extend.
    On May 9, 2008, Broomfield returned to the Stockmans’ residence with a
    lease for them to sign. The lease contained different terms than those that
    Broomfield and Mr. Stockman had negotiated the day before: a $3,000 per acre
    bonus payment, no Pugh clauses, and a primary term of five years. Broomfield
    testified that the lease was intended as a “placeholder” in order for Petrohawk
    3
    Case: 11-30576   Document: 00511932058      Page: 4   Date Filed: 07/24/2012
    No. 11-30576
    to win the race to the courthouse. Mr. Stockman asked Broomfield to include his
    neighbor’s language expressly excluding any warranty of title. Broomfield called
    her supervisors, who allowed the Stockmans to strike through the warranty of
    title in the lease. Broomfield assured Mr. Stockman that striking the warranty
    would have the same effect as including his neighbor’s language.              The
    Stockmans then signed and executed the mineral lease with Petrohawk (the
    “May 9 Lease”). Petrohawk tendered to the Stockmans a draft for the lease
    bonus (the “Petrohawk draft”) in the amount of $1.45 million and payable in
    thirty days. That same day, Petrohawk recorded the May 9 Lease. Chesapeake
    did not record the Chesapeake Extension until May 19, 2008.
    On May 12, 2008, before depositing the Petrohawk draft, Mr. Stockman
    went to the clerk of court’s office to ensure that Broomfield was correct that the
    Chesapeake Extension was unrecorded.          The clerk of court showed Mr.
    Stockman that the Chesapeake Extension was unrecorded and confirmed that
    Louisiana is a race state. After this investigation, Mr. Stockman deposited the
    Petrohawk draft. Mr. Stockman wanted to return Chesapeake’s bonus money,
    and in late May or early June, he paid an attorney to write a letter to
    Chesapeake. The attorney drafted the June 2, 2008 letter, which revoked and
    withdrew the Stockmans’ consent to the Chesapeake Extension and contained
    a cashier’s check in the amount of Chesapeake’s bonus payment.
    The Petrohawk draft was due to be paid to the Stockmans on July 2, 2008,
    but the Stellios Lease was not set to expire until July 14, 2008. If Petrohawk
    honored the $1.45 million draft on July 2, and Chesapeake commenced
    operations on the Stockman property before the expiration of the Stellios Lease,
    then Chesapeake would maintain the Stellios Lease and Petrohawk would lose
    its bonus payment. Thus, Petrohawk intentionally dishonored the Petrohawk
    draft, which was returned to Mr. Stockman unpaid on July 7, 2008.
    4
    Case: 11-30576    Document: 00511932058     Page: 5   Date Filed: 07/24/2012
    No. 11-30576
    Mr. Stockman called Petrohawk to find out why the draft was dishonored.
    He spoke with Todd Bergeron (“Bergeron”), who explained that Petrohawk’s
    lawyers had advised Petrohawk not to pay the bonus until July 15, when it could
    be confirmed that Chesapeake had not extended the Stellios Lease. Bergeron led
    Mr. Stockman to believe that either party could walk away from the May 9
    Lease, but that if Mr. Stockman did so, he would not receive the $1.45 million
    bonus. Bergeron did not tell Mr. Stockman that he was legally entitled to
    payment of the Petrohawk draft. Bergeron told Mr. Stockman that if he allowed
    a delay in payment until July 15, Petrohawk would increase the bonus.
    Thereafter, the Stockmans and Petrohawk executed a new lease on July
    15, 2008 (the “July 15 Lease”). Petrohawk agreed to pay the Stockmans a lease
    bonus of $3,500 per acre, or $1.7 million. The July 15 Lease, which was entitled
    “Amendment of Oil, Gas and Mineral Lease,” contained a new description of the
    Stockman property, a primary term of three years, a two-year option to extend,
    and horizontal and vertical Pugh clauses. Apart from these provisions, the July
    15 Lease incorporated by reference the other provisions of the May 9 Lease.
    That same day, Petrohawk made a $1.7 million wire transfer to the Stockmans.
    Petrohawk recorded the July 15 Lease on August 26, 2008.
    B. Statement of Proceedings
    On September 3, 2008, Chesapeake filed a complaint against the
    Stockmans in federal district court, asserting, inter alia, a breach of contract
    claim. The Stockmans denied liability, maintaining that they had revoked their
    consent to the Chesapeake Extension through the June 2, 2008 letter and the
    return of the bonus payment. On July 1, 2009, the district court permitted
    Petrohawk to intervene in the action. However, on August 5, 2009, the district
    court severed Petrohawk’s intervenor complaint, creating the instant action. In
    the fall of 2009, the district court held a two-day bench trial in the action
    5
    Case: 11-30576       Document: 00511932058          Page: 6     Date Filed: 07/24/2012
    No. 11-30576
    between Chesapeake and the Stockmans. Before the court ruled on the merits
    of the action, Chesapeake settled with the Stockmans.
    In its intervenor complaint, Petrohawk sought a declaratory judgment that
    the May 9 Lease is valid and takes precedence over the Chesapeake Extension.
    Chesapeake filed an answer and counterclaim seeking a declaratory judgment
    that the Chesapeake Extension primes the May 9 Lease. Chesapeake also
    asserted that Petrohawk deliberately induced the Stockmans to breach the
    Chesapeake Extension. The Stockmans filed an answer and counterclaim
    against Petrohawk, alleging that the May 9 Lease is null and void because
    Petrohawk procured their consent by fraud. The Stockmans also presented two
    alternative arguments: (1) that the May 9 Lease is null and void for failure of
    consideration; and (2) that the May 9 Lease was novated by the July 15 Lease.
    Petrohawk filed an answer and alternative counterclaim against the Stockmans,
    seeking the return of its lease bonus if the May 9 Lease is rescinded or novated.
    Petrohawk filed a motion to dismiss, which was converted into a motion
    for summary judgment, seeking the dismissal of Chesapeake’s claims.
    Chesapeake and the Stockmans each filed motions for summary judgment. On
    August 4, 2010, the district court denied the Stockmans’ and Chesapeake’s
    motions for summary judgment. The court granted in part Petrohawk’s motion
    for summary judgment, holding that the May 9 Lease primes the Chesapeake
    Extension because the May 9 Lease was recorded first. The court denied the
    remainder of Petrohawk’s summary judgment motion.1
    Beginning on November 30, 2010, the district court held a three-day bench
    trial. At the start of the trial, the court clarified the issues to be tried: (1) the
    1
    The district court granted Chesapeake’s motion to realign the parties, such that
    “Chesapeake and the Stockmans [are] considered the plaintiffs and . . . Petrohawk [is] deemed
    the defendant.” The court stated, however, that “[f]or the benefit of the clerk of court and the
    parties, . . . the caption of the case will not change.”
    6
    Case: 11-30576    Document: 00511932058      Page: 7   Date Filed: 07/24/2012
    No. 11-30576
    Stockmans’ claims for fraud, failure of consideration, and novation;
    (2) Chesapeake’s claim for intentional interference with a contract;
    (3) Petrohawk’s prayer for judgment declaring the May 9 Lease to be in full force
    and effect; and (4) Petrohawk’s alternative counterclaim for a return of the lease
    bonus if the May 9 Lease is rescinded or novated. The court heard testimony
    from Mr. Stockman, Broomfield, and Bergeron, among others. On December 2,
    after hearing all of the testimony, the district court made preliminary oral
    findings on the record, including that the May 9 Lease was procured by fraud.
    The court then engaged in a colloquy with the parties’ lawyers regarding various
    issues, such as whether the Stockmans confirmed the fraud. The court found
    that Mr. Stockman did not confirm the fraud by signing the July 15 Lease. The
    court ordered post-trial briefing on the issue of the return of the lease bonus and
    stated that a written ruling would be forthcoming.
    On May 27, 2011, the district court issued its written Ruling on the Merits.
    The court first noted that it was bound by Erie R. Co. v. Tompkins, 
    304 U.S. 64
    (1938), to apply Louisiana law. Turning to the Stockmans’ claim for fraud, the
    court found that “Petrohawk (through its agents Pang[a]ea and Lisa Broomfield)
    was in a frenzy to get the [May 9 Lease] . . . [and was] willing to say or do
    anything to obtain it.” The court found that Broomfield made affirmative
    misrepresentations to Mr. Stockman: she “kept using the terms ‘valid’ and
    ‘invalid’, which led Mr. Stockman to reasonably . . . believe that, upon the filing
    of the [May 9 Lease], the Chesapeake [E]xtension would be invalid.” The court
    found that “Mr. Stockman’s reliance on Ms. Broomfield’s statements, in light of
    all the circumstances, was reasonable.” The court stated that Mr. Stockman’s
    “action in going to the clerk’s office to make sure that the Chesapeake
    [E]xtension had not been filed makes it more credible that Mr. Stockman
    believed what he had been told [by Broomfield].” The court concluded that “the
    [May 9 Lease] would [not] have been signed by Mr. and Mrs. Stockman had they
    7
    Case: 11-30576      Document: 00511932058         Page: 8     Date Filed: 07/24/2012
    No. 11-30576
    not been led to believe that the unrecorded Chesapeake [E]xtension would be
    invalid upon the recording of the [May 9 Lease].”
    The court concluded that Petrohawk obtained the May 9 Lease by fraud
    and rescinded the May 9 Lease. The court stated that it did not need to reach
    the issues of consideration or novation. The court declined to award damages to
    the Stockmans, but it did order Petrohawk to pay the Stockmans reasonable
    attorney’s fees and to “pay the costs associated in correcting the public records
    to strike the [May 9 Lease].”           Next, the court dismissed with prejudice
    Chesapeake’s claim for intentional interference with a contract. The court
    explained that, under the elements of the claim from the Restatement of Torts,
    “Petrohawk would be liable to Chesapeake,” but noted that Louisiana law does
    not follow the Restatement.
    The court then dismissed with prejudice Petrohawk’s counterclaim for the
    return of its bonus money. The court reiterated that it had rescinded the May
    9 Lease and noted that, under Article 2033 of the Louisiana Civil Code, the
    “parties must be restored to the situation that existed before the contract was
    made.” However, the court explained that the bonus money was not paid for the
    May 9 Lease, but “was a higher amount negotiated between the Stockmans and
    Petrohawk in exchange for the delay in payment [until July 15].” The court
    determined that the July 15 Lease is “sufficient to stand on its own while
    incorporating the contents of the [May 9 Lease].” The court determined that the
    July 15 Lease incorporated the May 9 Lease’s exclusion of the warranty of title.
    The district court issued its judgment on June 27, 2011. Petrohawk
    appealed the court’s judgment, and Chesapeake cross-appealed. On September
    26, 2011, the district court granted the Stockmans’ motion for attorney’s fees in
    the amount of $34,013. Petrohawk filed an amended notice of appeal.2
    2
    Petrohawk does not address on appeal the issue of the district court’s award of
    attorney’s fees, and thus we will not address this issue. See United States v. Whitfield, 590
    8
    Case: 11-30576       Document: 00511932058           Page: 9     Date Filed: 07/24/2012
    No. 11-30576
    II. DISCUSSION
    A. Applicable Law and Standard of Review
    When jurisdiction is based on diversity, we apply the substantive law of
    the forum state. Erie R. Co. v. Tompkins, 
    304 U.S. 64
     (1938); see also Holt v.
    State Farm Fire & Cas. Co., 
    627 F.3d 188
    , 191 (5th Cir. 2010). Thus, in the
    instant case, we apply Louisiana law. “To determine Louisiana law, we look to
    the final decisions of Louisiana’s highest court.” Holt, 
    627 F.3d at 191
     (citation
    omitted). “In the absence of a final decision by that court addressing the issue
    at hand, a federal court must determine, in its best judgment, how the state’s
    highest court would resolve the issue if presented with it.” 
    Id.
     (citation omitted).
    On appeal from a bench trial, we review a district court’s conclusions of
    law and mixed questions of law and fact de novo. Dickerson v. Lexington Ins.
    Co., 
    556 F.3d 290
    , 294 (5th Cir. 2009). We review a district court’s findings of
    fact for clear error. 
    Id.
     “A finding is clearly erroneous if it is without substantial
    evidence to support it, the court misinterpreted the effect of the evidence, or this
    court is convinced that the findings are against the preponderance of credible
    testimony.” French v. Allstate Indem. Co., 
    637 F.3d 571
    , 577 (5th Cir. 2011)
    (citation and internal quotation marks omitted). The clearly erroneous standard
    is met “only if we have a definite and firm conviction that a mistake has been
    committed.” 
    Id.
     (citation and internal quotation marks omitted).
    B. The Stockmans’ Fraud Claim
    1. Louisiana Law on Contractual Fraud
    Pursuant to the Louisiana Civil Code, a “contract is formed by the consent
    of the parties established through offer and acceptance.” LA. CIV. CODE ANN. art.
    1927. However, “[c]onsent may be vitiated by error, fraud, or duress.” LA. CIV.
    CODE ANN. art. 1948. “Fraud is a misrepresentation or a suppression of the
    F.3d 325, 346 (5th Cir. 2009) (“[A] party waives any argument that it fails to brief on appeal.”)
    (citations omitted).
    9
    Case: 11-30576    Document: 00511932058       Page: 10   Date Filed: 07/24/2012
    No. 11-30576
    truth made with the intention either to obtain an unjust advantage for one party
    or to cause a loss or inconvenience to the other. Fraud may also result from
    silence or inaction.” LA. CIV. CODE ANN. art. 1953. “Fraud does not vitiate
    consent when the party against whom the fraud was directed could have
    ascertained the truth without difficulty, inconvenience, or special skill.” LA. CIV.
    CODE ANN. art. 1954. “Error induced by fraud need not concern the cause of the
    obligation to vitiate consent, but it must concern a circumstance that has
    substantially influenced that consent.” LA. CIV. CODE ANN. art. 1955.
    Under Louisiana law, an action for fraud against a party to a contract
    requires: (1) “a misrepresentation, suppression, or omission of true information”;
    (2) “the intent to obtain an unjust advantage or to cause damage or
    inconvenience to another”; and (3) that the error induced by the fraudulent act
    relates to a circumstance that substantially influenced the victim’s consent to
    the contract. Shelton v. Standard/700 Assocs., 
    798 So. 2d 60
    , 64 (La. 2001).
    “Fraud need only be proved by a preponderance of the evidence and may be
    established by circumstantial evidence.” LA. CIV. CODE ANN. art. 1957.
    2. Analysis
    In the instant case, the district court concluded that Petrohawk procured
    the May 9 Lease by fraud. The court found that Broomfield misrepresented to
    Mr. Stockman that, upon the recordation of the May 9 Lease, the Chesapeake
    Extension would be invalid. The court found that the Stockmans reasonably
    relied on Broomfield’s misrepresentations and that they would not have signed
    the May 9 Lease had they known that her statements were false. On appeal,
    Petrohawk argues that the elements of fraud were not met in this case.
    Petrohawk asserts that: “(1) there was no misrepresentation of fact, only a
    statement of law or opinion; (2) there was no intent to defraud or deceive the
    Stockmans; (3) Mr. Stockman conducted his own investigation and did not rely
    on what Mrs. Broomfield said; and (4) the truth about the legal opinion on
    10
    Case: 11-30576        Document: 00511932058           Page: 11     Date Filed: 07/24/2012
    No. 11-30576
    recordation in Louisiana was easily ascertainable and Mr. Stockman is
    presumed to know the law.” We address each of Petrohawk’s arguments in turn.
    First, Petrohawk maintains that there was no misrepresentation of fact
    to support the district court’s finding of fraud.               Petrohawk contends that,
    pursuant to Louisiana law, fraud cannot be based on an opinion statement or a
    misrepresentation of law. Petrohawk asserts that Broomfield’s statements
    regarding the validity of the Chesapeake Extension were simply her own
    opinions or statements of law and therefore “cannot be fraudulent.” We reject
    Petrohawk’s argument that Broomfield’s statements were simply her opinions.
    In American Guaranty Co. v. Sunset Realty & Planting Co., 
    23 So. 2d 409
     (La.
    1945) (on rehearing), the Louisiana Supreme Court stated that “[w]henever a
    person states a matter which might otherwise be only an opinion, not as a mere
    expression of his own opinion, but as an existing fact, material to the
    transaction, the statement clearly becomes a statement of fact and not an
    expression of opinion.” 
    Id. at 449
     (citations omitted). Here, Broomfield’s
    misrepresentations to Mr. Stockman were made as statements of fact in order
    to assure Mr. Stockman that he could legally sign the May 9 Lease with
    Petrohawk. Thus, her statements could form the basis of a fraud claim.3
    Furthermore, we reject Petrohawk’s argument that a misrepresentation
    of law cannot give rise to a fraud claim. Under Louisiana law, the relevant
    inquiry is whether there was “a misrepresentation, suppression, or omission of
    true information.”        Shelton, 
    798 So. 2d at 64
     (emphasis added).                   Indeed,
    Louisiana courts have found fraud where the underlying false statement was a
    3
    Petrohawk additionally asserts that no fraud was committed because Broomfield’s
    statements were not wholly false, as she was correct that the first lease to be recorded is the
    valid lease from a third party’s perspective. We reject this argument. The Louisiana Supreme
    Court has stated that “[o]ne conveying a false impression by the disclosure of some facts and
    the concealment of others is guilty of fraud, even though his statement is true as far as it goes,
    since such concealment is in effect a false representation that what is disclosed is the whole
    truth.” Am. Guar. Co., 23 So. 2d at 456 (citation and internal quotation marks omitted).
    11
    Case: 11-30576    Document: 00511932058      Page: 12   Date Filed: 07/24/2012
    No. 11-30576
    misrepresentation of law. For example, in Lupo v. Lupo, 
    475 So. 2d 402
     (La. Ct.
    App. 1985), a lawyer had his client sign an appeal bond and assured him that,
    by signing the bond, he would not “have any [legal] problems.” 
    Id. at 404-05
    .
    The lawyer did not tell his client that the bond “would act as a mortgage on his
    property.” 
    Id. at 404
    . The court concluded that the lawyer “perpetrated fraud
    upon [the client]. [The lawyer] needed an appeal bond, of a substantial sum, and
    by making misrepresentations, and by failing to disclose pertinent information,
    he obtained one.” 
    Id. at 405
    ; see also Mack v. Evans, 
    804 So. 2d 730
    , 733 (La. Ct.
    App. 2001) (affirming the trial court’s finding of fraud based on a
    misrepresentation of law, where the defendant “had misled [the plaintiff] to
    believe it was necessary for her to donate her interest in the real estate in order
    to qualify for supplemental security income benefits”).
    Second, Petrohawk argues that there is no factual basis to support a
    finding that Petrohawk intended to defraud the Stockmans. Petrohawk asserts
    that the record is “completely devoid of any evidence that Mrs. Broomfield knew
    that what she told Mr. Stockman about the legal effect of recordation was false.”
    We reject Petrohawk’s argument, as there is evidence in the record that supports
    Petrohawk’s intent to defraud the Stockmans. Broomfield testified that she was
    an experienced landman and former paralegal who was very knowledgeable
    about Louisiana real estate and contract law. She testified that she even had to
    advise Pangaea’s attorney on Louisiana law. This testimony indicates that
    Broomfield knew that she was lying to Mr. Stockman about the validity of the
    Chesapeake Extension. Additionally, the district court found that Petrohawk
    was in a frenzy to get the May 9 Lease and was “willing to say or do anything to
    obtain it.” Documentary evidence and testimony support this finding. For
    example, emails sent between Broomfield and her supervisor in early May
    indicate that Petrohawk was frantic to get the lease signed. Also, Broomfield
    testified that the May 9 Lease was signed in a hurry “[t]o tie the acreage up.”
    12
    Case: 11-30576     Document: 00511932058       Page: 13    Date Filed: 07/24/2012
    No. 11-30576
    She conceded that Petrohawk wanted the lease as “a placeholder” and that she
    “was told to get it signed, get it to the courthouse, and that’s what [she] did.”
    Finally, during their initial meeting Broomfield encouraged Mr. Stockman to
    consult with an attorney, but when Mr. Stockman subsequently raised legal
    concerns relating to his signing of the Chesapeake Extension, Broomfield told
    him, “don’t worry about it, Petrohawk ha[s] an office full of lawyers.”
    Third, Petrohawk argues that the Stockmans’ fraud claim fails because
    Mr. Stockman relied on the results of his own investigation and not on
    Broomfield’s misrepresentations. Petrohawk points to the following facts to
    demonstrate Mr. Stockman’s investigation: (1) his consultation of his neighbor;
    (2) his investigation at the clerk of court’s office; and (3) his procurement of legal
    counsel. We reject Petrohawk’s argument. The district court’s finding that Mr.
    Stockman relied on Broomfield’s misrepresentations is not clearly erroneous.
    With regard to the consultation of his neighbor, the evidence indicates that the
    neighbor did not provide any legal advice to the Stockmans regarding the legal
    effect of recordation on the validity of leases. With respect to his investigation
    at the clerk’s office, the evidence indicates that Mr. Stockman only confirmed
    what Broomfield had told him—that the Chesapeake Extension was unrecorded.
    This fact indeed highlights Mr. Stockman’s reliance on her statements. With
    regard to the hiring of a lawyer, the evidence indicates that Mr. Stockman hired
    a lawyer to write the revocation letter to Chesapeake, which occurred only after
    the signing of the May 9 Lease. Thus, the record evidence supports the district
    court’s finding that Mr. Stockman relied on Broomfield’s statements.
    Fourth, Petrohawk asserts that the fraud claim fails because the truth was
    readily and reasonably ascertainable by the Stockmans. Petrohawk stresses
    that Mr. Stockman had access to legal advice, “but failed to exercise that
    minimum amount of diligence.” Under Article 1954 of the Louisiana Civil Code,
    fraud does not vitiate consent when the complaining party “could have
    13
    Case: 11-30576     Document: 00511932058       Page: 14    Date Filed: 07/24/2012
    No. 11-30576
    ascertained the truth without difficulty, inconvenience, or special skill.” When
    “a fraudulent misrepresentation can be easily uncovered,” the complaining party
    will be expected to exercise this minimum amount of diligence. Saul Litvinoff,
    Vices of Consent, Error, Fraud, Duress and an Epilogue on Lesion, 50 LA. L. REV.
    1, 69 (1989). However, when uncovering the truth requires “familiarity with
    peculiar technicalities, which calls for a special skill,” the complaining party
    “cannot be blamed for lack of diligence.” 
    Id.
     Furthermore, in determining the
    diligence of the complaining party, “[s]ubjective aspects such as a party’s
    business experience or professional capacity must be taken into account.” 
    Id.
    In the instant case, the fraudulent misrepresentation at issue concerned
    the legal effect of recordation on the validity of a mineral lease. Ascertaining the
    truth of the statement required special legal skill, and Mr. Stockman was a mere
    landowner who did not possess the requisite legal skills to uncover the truth.
    Mr. Stockman’s only likely avenue to uncovering the truth was by consulting a
    knowledgeable      attorney—which       would     have    entailed   difficulty   and
    inconvenience. Thus, we reject Petrohawk’s argument that Mr. Stockman could
    have easily ascertained the truth. In conclusion, we affirm the district court’s
    judgment finding that Petrohawk obtained the May 9 Lease by fraud.
    C. Confirmation of the Fraud
    1. Louisiana Law on Confirmation
    “A contract is relatively null . . . when a party . . . did not give free consent
    at the time the contract was made,” such as when there was fraud in the
    inducement of the contract. LA. CIV. CODE ANN. art. 2031. “A contract that is
    only relatively null may be confirmed.” Id.; see Litvinoff, Vices of Consent, 50 LA.
    L. REV. at 9-10 (“[S]ince vices or defects are susceptible of being cured, when a
    vice involves the consent of a party it gives rise to a nullity that is only relative,
    which means that it may be cured . . . through confirmation by the party of
    interest . . . .”). “Confirmation is a declaration whereby a person cures the
    14
    Case: 11-30576        Document: 00511932058           Page: 15      Date Filed: 07/24/2012
    No. 11-30576
    relative nullity of an obligation.” LA. CIV. CODE ANN. art. 1842. “An express act
    of confirmation must contain or identify the substance of the obligation and
    evidence the intention to cure its relative nullity.” 
    Id.
     “Tacit confirmation may
    result from voluntary performance of the obligation.” Id.
    2. Analysis
    On appeal, Petrohawk argues that district court erred in failing to find
    that the Stockmans confirmed the fraud through their subsequent actions. As
    evidence of the Stockmans’ confirmation, Petrohawk points to (1) their June 2,
    2008 revocation letter and (2) their acceptance of payment for the July 15 Lease.
    Petrohawk contends that their confirmation renders the May 9 Lease valid. The
    Stockmans respond that they did not confirm the fraud because they were not
    aware of the fraud until the trial with Chesapeake in the fall of 2009.
    In its Ruling on the Merits, the district court did not address the issue of
    confirmation. However, because the court found that Petrohawk procured the
    May 9 Lease by fraud and then rescinded the May 9 Lease, the court impliedly
    determined that the Stockmans did not confirm the fraud.4 This implied finding
    is supported not only by the court’s general disposition of the case, but also by
    the court’s statements during the colloquy at trial. See Mitchell v. Mitchell
    Truck Line, Inc., 
    286 F.2d 721
    , 724 & n.2 (5th Cir. 1961) (relying on a district
    court’s comments in colloquy because they were consistent with the court’s
    judgment and shed light on a finding of fact not explicitly made in the court’s
    written findings). Regarding the issue of confirmation, the court stated, “I do not
    believe that the Stockmans confirmed the May 9 [Lease].” The court stated that
    4
    “If a trial judge fails to make a specific finding on a particular fact, the reviewing court
    may assume that the court impliedly made a finding consistent with its general holding so
    long as the implied finding is supported by the evidence.” Century Marine Inc. v. United States,
    
    153 F.3d 225
    , 231 (5th Cir. 1998) (citations omitted); see 9C CHARLES ALAN WRIGHT & ARTHUR
    R. MILLER, FEDERAL PRACTICE AND PROCEDURE § 2579 (3d ed.) (“In some cases if the court fails
    to make a finding on a particular fact it has been assumed that . . . it impliedly made a finding
    consistent with its general disposition of the case.”) (footnotes omitted).
    15
    Case: 11-30576    Document: 00511932058      Page: 16    Date Filed: 07/24/2012
    No. 11-30576
    “I find as a matter of fact [Mr. Stockman] did not . . . give a declaration that he
    was trying to cure a relative nullity when he signed on July 15.”
    As a preliminary matter, we must decide whether actual or constructive
    knowledge is required for confirmation of a relative nullity under Louisiana law.
    Petrohawk contends that the standard should be constructive knowledge, while
    the Stockmans assert that actual knowledge of the vice is required. Under
    Louisiana law, when a party confirms a relative nullity, the party gives up the
    right to bring an action for that nullity. 5 SAUL LITVINOFF, LOUISIANA CIVIL LAW
    TREATISE: THE LAW OF OBLIGATIONS § 12.54 (2d ed.). Therefore, the Louisiana
    courts have held that an act of confirmation “must evince [the] intention [to
    confirm] clearly and unequivocally.” Rahier v. Rester, 
    11 So. 2d 87
    , 92 (La. Ct.
    App. 1942) (citation and internal quotation marks omitted). In his treatise on
    Louisiana civil law, Professor Saul Litvinoff stated that, with respect to express
    confirmation, “it is necessary that the act [of confirmation] evidence that the
    confirming party acted with knowledge of the vice or defect that invalidates the
    act to be confirmed, and with a deliberate will of curing that vice or defect.” THE
    LAW   OF   OBLIGATIONS § 12.54 (emphases added).          With respect to tacit
    confirmation, he stated that “the act of performance must be voluntary . . . which
    means . . . that it must be rendered with knowledge of the vice or defect that
    made the obligation null.” Id. § 12.56 (emphasis in original). Given that the
    confirming party relinquishes a cause of action and must intend to cure the vice,
    we conclude that confirmation under Louisiana law requires actual knowledge
    of the vice.
    Petrohawk argues that, even if actual knowledge is required, the
    Stockmans knew of and confirmed the fraud by the time they signed the July 15
    Lease. We reject Petrohawk’s argument. The record evidence indicates that the
    district court found that Mr. Stockman did not know of the fraud until the
    Chesapeake trial in 2009. At trial, the district court stated that “[Mr. Stockman]
    16
    Case: 11-30576    Document: 00511932058       Page: 17   Date Filed: 07/24/2012
    No. 11-30576
    testified that until he sat in this courtroom [for the Chesapeake trial], he did not
    know that he had been lied to.” The court concluded that Mr. Stockman “never
    really had all the evidence until he sat in this courtroom [in 2009].”
    Furthermore, during the colloquy, the court found that, at the time of the
    signing of the July 15 Lease, Mr. Stockman was “still operating under the belief
    and hope that the information he had been given [by Broomfield]
    was . . . correct.” This finding of fact is based on a credibility determination,
    which is for the district court to make. See French, 
    637 F.3d at 577
     (“[This court]
    must give due regard to the district court’s credibility evaluations.”). There is
    no reason to disturb the court’s finding, as Petrohawk has not demonstrated it
    to be clearly erroneous.
    Given the district court’s finding that Mr. Stockman did not have actual
    knowledge of the fraud until 2009, neither the Stockmans’ June 2, 2008 letter
    nor their acceptance of payment for the July 15 Lease constitutes an act of
    confirmation. Thus, the district court did not err in finding that the Stockmans
    did not confirm the fraud. We affirm the district court’s judgment rescinding the
    May 9 Lease, awarding attorney’s fees and costs to the Stockmans, and ordering
    Petrohawk to pay the costs of striking the May 9 Lease from the public records.
    D. Petrohawk’s Counterclaim for a Return of the Lease Bonus
    In its Ruling on the Merits, the district court concluded that Petrohawk
    was not entitled to a return of its lease bonus. The court determined that the
    July 15 Lease was a stand-alone lease and that it incorporated by reference the
    exclusion of the warranty of title from the May 9 Lease. The court thus
    concluded that the July 15 Lease did not contain an implied warranty of title.
    On appeal, Petrohawk maintains that the July 15 Lease is either an
    amendment to or a novation of the May 9 Lease, and under either scenario, it is
    entitled to a return of the bonus. If the July 15 Lease is an amendment,
    Petrohawk asserts that the rescission of the May 9 Lease requires the rescission
    17
    Case: 11-30576       Document: 00511932058          Page: 18     Date Filed: 07/24/2012
    No. 11-30576
    of the July 15 Lease and therefore a return of the bonus under Article 2033 of
    the Louisiana Civil Code.5 If the July 15 Lease is a novation (or a new lease that
    extinguishes the obligations of the May 9 Lease), Petrohawk contends that it is
    entitled to a return of the bonus pursuant to an implied warranty of title, as the
    July 15 Lease does not contain an exclusion of the express warranty clause.
    In order to assess Petrohawk’s arguments on appeal, we must first review
    the district court’s determination that the July 15 Lease is a stand-alone lease,
    and not merely an amendment to the May 9 Lease. If the interpretation of a
    contract is “determined solely from the language of the contract,” we review the
    district court’s interpretation de novo. Nat’l Union Fire Ins. Co. v. Circle, Inc.,
    
    915 F.2d 986
    , 989 (5th Cir. 1990) (citation omitted). If the interpretation of a
    contract turns on extrinsic evidence, we review a district court’s determination
    under the clearly erroneous standard. 
    Id.
     (citation omitted).
    Under Louisiana law, the “[i]nterpretation of a contract is the
    determination of the common intent of the parties.” LA. CIV. CODE ANN. art.
    2045. “When the words of a contract are clear and explicit and lead to no absurd
    consequences, no further interpretation may be made in search of the parties’
    intent.”    LA. CIV. CODE ANN. art. 2046.             Thus, when the contract is not
    ambiguous, the court “lacks the authority to look beyond the four corners of the
    document.” Taita Chem. Co. v. Westlake Styrene Corp., 
    246 F.3d 377
    , 386 (5th
    Cir. 2001) (citation omitted). However, if the contract is ambiguous, then the
    court may look to extrinsic evidence to determine the parties’ intent. See Am.
    Elec. Power Co. v. Affiliated FM Ins. Co., 
    556 F.3d 282
    , 286 (5th Cir. 2009) (citing
    Campbell v. Melton, 
    817 So. 2d 69
    , 75 (La. 2002)). “A contract is considered
    ambiguous on the issue of intent when it lacks a provision bearing on the issue,
    its written terms are susceptible to more than one interpretation, there is
    5
    Article 2033 provides that, when a contract is rescinded for a relative nullity, “[t]he
    parties must be restored to the situation that existed before the contract was made.”
    18
    Case: 11-30576    Document: 00511932058        Page: 19   Date Filed: 07/24/2012
    No. 11-30576
    uncertainty as to its provisions, or the parties’ intent cannot be ascertained from
    the language used.” Carmichael v. Bass P’ship, No. CA 12-10, 
    2012 WL 1525083
    ,
    at *3 (La. Ct. App. 2012) (citation and internal quotation marks omitted). “The
    determination of whether a contract is clear or ambiguous is a question of law.”
    Sims v. Mulhearn Funeral Home, Inc., 
    956 So. 2d 583
    , 590 (La. 2007).
    We conclude that the district court did not err in determining that the July
    15 Lease was a stand-alone lease. Looking at the face of the document, the July
    15 Lease is a complete contract in and of itself, and not a mere modification of
    an existing contract. The July 15 Lease contains “letting language,” which
    states: “Lessor . . . grants, leases, and lets to Lessee and Lessee’s successors and
    assigns the above-described lands for the primary term . . . .” This letting
    language is used when granting a new lease and thus indicates that the July 15
    Lease was meant to stand on its own. The July 15 Lease also contains the main
    provisions of a mineral lease: a description of the leased property, a reference to
    adequate consideration, and a primary term. Rather than simply amending the
    May 9 Lease, the July 15 Lease incorporated by reference many provisions from
    the May 9 Lease to form a complete contract. The four corners of the July 15
    Lease indicate that it is a stand-alone lease.
    We next address Petrohawk’s argument that there is an implied warranty
    of title in the July 15 Lease that requires the return of the lease bonus.
    Petrohawk concedes that the May 9 Lease contains an express exclusion of the
    warranty of title, but contends that the July 15 Lease does not contain such an
    exclusion. However, Petrohawk fails to note that the July 15 Lease contains a
    valid incorporation by reference provision. See Action Fin. Corp. v. Nichols, 
    180 So. 2d 81
    , 83 (La. Ct. App. 1965) (“[T]he jurisprudence is clear that documents
    may be incorporated in contracts by attachment or reference thereto. . . . [These
    writings] become a part of the agreement between the parties with the same
    force and effect as if the provisions had been contained in the basic
    19
    Case: 11-30576    Document: 00511932058       Page: 20   Date Filed: 07/24/2012
    No. 11-30576
    contract . . . .”). According to the July 15 Lease’s incorporation provision, all of
    the provisions contained in the May 9 Lease are incorporated into the July 15
    Lease—apart from the provisions regarding the property description, the
    primary term, the option to extend, and the Pugh clauses. Thus, based on the
    incorporation provision, the exclusion of the warranty of title in the May 9 Lease
    is incorporated into the July 15 Lease. Accordingly, there is no implied warranty
    of title in the July 15 Lease, and Petrohawk is therefore not entitled to a return
    of its lease bonus. See LA. REV. STAT. § 31:120 (“A mineral lessor impliedly
    warrants title to the interest leased unless such warranty is expressly excluded
    or limited.”). We affirm the district court’s judgment dismissing with prejudice
    Petrohawk’s counterclaim for the return of the lease bonus.
    E. Chesapeake’s Claim for Intentional Interference With a Contract
    In its cross-appeal, Chesapeake argues that the district court incorrectly
    dismissed its Louisiana state-law claim against Petrohawk for intentional
    interference with a contract. Chesapeake asserts that Louisiana caselaw allows
    an intentional interference with a contract claim where a defendant owes a duty
    to the plaintiff, and that Petrohawk owed a duty to Chesapeake here.
    Petrohawk argues that a Louisiana state-law claim for intentional interference
    with a contract can only be asserted against an officer of a private corporation
    and cannot be asserted against a corporate entity defendant. We review de novo
    the district court’s legal conclusion that Chesapeake’s claim is not a viable cause
    of action under Louisiana law. See Dickerson, 
    556 F.3d at 294
    .
    In 1989, the Louisiana Supreme Court first recognized the cause of action
    for intentional interference with a contract in 9 to 5 Fashions, Inc. v. Spurney,
    
    538 So. 2d 228
    , 232-34 (La. 1989). However, the cause of action that the state’s
    highest court recognized was extremely limited. The court expressly refused to
    adopt the broad common law doctrine of interference with a contract, because it
    is “a rather broad and undefined tort in which no specific conduct is proscribed
    20
    Case: 11-30576     Document: 00511932058      Page: 21   Date Filed: 07/24/2012
    No. 11-30576
    and in which liability turns on the purpose for which the defendant acts, with
    the indistinct notion that the purposes must be considered improper in some
    undefined way.” 
    Id. at 234
     (quoting W. PROSSER & P. KEETON, THE LAW              OF
    TORTS § 129, p. 979 (5th ed. 1984)) (internal quotation marks omitted). The
    court recognized “only a corporate officer’s duty to refrain from intentional and
    unjustified interference with the contractual relation between his employer and
    a third person.” Id. The court laid out the elements of this cause of action:
    (1) the existence of a contract or a legally protected interest between
    the plaintiff and the corporation; (2) the corporate officer’s
    knowledge of the contract; (3) the officer’s intentional inducement
    or causation of the corporation to breach the contract or his
    intentional rendition of its performance impossible or more
    burdensome; (4) absence of justification on the part of the officer; (5)
    causation of damages to the plaintiff by the breach of contract or
    difficulty of its performance brought about by the officer.
    Id. The Louisiana Supreme Court has not addressed the scope of this cause of
    action since its decision in 9 to 5.
    We have acknowledged the limited nature of Louisiana’s claim for tortious
    interference with a contract. In American Waste & Pollution Control Co. v.
    Browning-Ferris, Inc., 
    949 F.2d 1384
     (5th Cir. 1991), we noted that the 9 to 5
    court created a narrow cause of action, but “did not expressly preclude a cause
    of action . . . based on other facts.” Id. at 1387-88. We noted that the “common
    thread in [9 to 5] and its progeny is the requisite duty, or obligation, for such a
    cause of action.” Id. at 1390. “[W]hether a duty exists is a question of law,” and
    in 9 to 5, the requisite duty “arose out of a corporate officer’s narrowly defined
    duty to those with whom his corporation contracts.” Id. (emphasis added). In
    American Waste, the plaintiff alleged that the defendant had knowledge of the
    plaintiff’s contract with another party, and the defendant improperly induced
    the party to repudiate its contract with the plaintiff. Id. at 1385. However, we
    concluded that because the defendant “had no relationship” with the plaintiff,
    21
    Case: 11-30576     Document: 00511932058      Page: 22    Date Filed: 07/24/2012
    No. 11-30576
    the requisite duty was lacking. Id. at 1390. Given the absence of such a duty,
    we made the Erie-guess that the Louisiana Supreme Court would dismiss the
    plaintiff’s intentional interference with a contract claim. Id. at 1390-91.
    In Egorov, Puchinsky, Afanasiev & Juring v. Terriberry, Carroll & Yancey,
    
    183 F.3d 453
     (5th Cir. 1999), we again “recognized the narrowness of Louisiana’s
    tortious interference action,” and stated that “even the Louisiana appellate
    courts purporting to ‘expand’ the cause of action have done so within the limited
    confines of 9 to 5.” 
    Id. at 457
     (citations omitted). We concluded that the
    plaintiffs “failed to identify an individualized duty existing between themselves
    and their alleged tortfeasors that could give rise to the type of delictual liability
    established by the Louisiana Supreme Court in 9 to 5.” 
    Id.
     (emphasis added).
    The Louisiana courts of appeal have conformed to the limited cause of
    action expressed in 9 to 5. See, e.g., Brown v. Romero, 
    922 So. 2d 742
    , 747 (La.
    Ct. App. 2006); Tallo v. Stroh Brewery Co., 
    544 So. 2d 452
    , 453-55 (La. Ct. App.
    1989). In Technical Control Systems, Inc. v. Green, 
    809 So. 2d 1204
     (La. Ct. App.
    2002), the plaintiff urged the state appellate court to expand the holding of 9 to
    5 “to allow a cause of action against a corporate entity defendant.” 
    Id. at 1207
    .
    The court concluded that, because “recent attempts by this court to expand upon
    this [cause of action] have been reversed by our supreme court,” the court “must
    assume that [its] expansive take on a tortious interference with contract claim
    did not meet the approval of the supreme court.” 
    Id.
     at 1208-09 (citing Cowen
    v. Steiner, 
    689 So. 2d 516
     (La. Ct. App. 1997), rev’d 
    701 So. 2d 140
     (La. 1997)).
    Thus, the state appellate court affirmed the dismissal of the claim. Id. at 1209.
    Where the Louisiana appellate courts have found a viable cause of action
    for tortious interference with a contract, the courts have identified a narrow,
    individualized duty between the plaintiff and the alleged tortfeasor. See Neel v.
    Citrus Lands of La., Inc., 
    629 So. 2d 1299
    , 1301 (La. Ct. App. 1993) (stating that,
    “[i]f Mr. Neel can establish that Citrus Lands had a duty to allow him to go on
    22
    Case: 11-30576      Document: 00511932058         Page: 23    Date Filed: 07/24/2012
    No. 11-30576
    the land leased to EuroAmerican,” then he could bring a viable tortious
    interference with a contract claim); see also MD Care, Inc. v. Angelo, 
    672 So. 2d 969
    , 973 (La. Ct. App. 1996) (“[T]he determinative factor . . . was whether the
    defendant owed the plaintiff a duty, the breach of which might constitute
    intentional interference with a contract.”).
    Based on this caselaw, 9 to 5 requires that the defendant owe a duty to the
    plaintiff in order for the plaintiff to have a viable claim for tortious interference
    with a contract. Thus, we must address whether Petrohawk owed a duty to
    Chesapeake. Chesapeake argues that Petrohawk owed it three duties: (1) a duty
    not to engage in unfair business practices pursuant to the Louisiana Unfair
    Trade Practices Act (“LUPTA”);6 (2) a general duty under public policy not to
    induce the Stockmans to break their contract; and (3) a duty not to commit fraud
    on the public record by recording a fraudulently acquired document.
    We conclude that Chesapeake’s arguments are without merit, as
    Chesapeake has failed to identify a narrow, individualized duty that Petrohawk
    owed Chesapeake. See Egorov, 
    183 F.3d at 457
    ; Am. Waste, 949 F.2d at 1390.
    All three of the duties proposed by Chesapeake are broad, ill-defined duties. See
    Angelo, 
    672 So. 2d at 973
     (noting that the “statutory definition of an unfair
    practice [under LUPTA] is broad and subjectively stated and does not specify
    particular violations”) (citation omitted). Such broad, amorphous duties are not
    the kinds of duties encompassed by the court’s decision in 9 to 5. See Egorov, 
    183 F.3d at
    457 n.2 (concluding that the general duties of Louisiana lawyers under
    the Louisiana Rules of Professional Conduct are not duties encompassed by 9 to
    5); see also Am. Waste, 949 F.2d at 1390. Indeed, the 9 to 5 court explicitly
    refused to adopt “a rather broad and undefined tort in which no specific conduct
    6
    Under LUPTA, “[u]nfair methods of competition and unfair or deceptive acts or
    practices in the conduct of any trade or commerce” are deemed unlawful. LA. REV. STAT. ANN.
    § 51:1405(A).
    23
    Case: 11-30576     Document: 00511932058       Page: 24    Date Filed: 07/24/2012
    No. 11-30576
    is proscribed.”    
    538 So. 2d at 234
     (citation and internal quotation marks
    omitted). “[I]t is not for this diversity court to expand [the] cause of action in the
    face of Louisiana’s expressed unwillingness to do so.” Am. Waste, 949 F.2d at
    1391. In making our Erie-guess, we conclude that the Louisiana Supreme Court
    would hold that Chesapeake does not have a viable claim against Petrohawk for
    tortious interference with a contract.
    Chesapeake alternatively asks us to certify this issue to the Louisiana
    Supreme Court pursuant to Rule 12 of the Rules of the Louisiana Supreme
    Court. Rule 12 provides that an issue may be certified when “there are no clear
    controlling precedents” from the Louisiana Supreme Court. Here, the Louisiana
    Supreme Court has issued 9 to 5, a controlling opinion on the scope of the action
    for tortious interference with a contract. Thus, we decline to certify this issue.
    See Am. Waste, 949 F.2d at 1392. For the reasons stated above, we affirm the
    district court’s judgment dismissing with prejudice Chesapeake’s intentional
    interference with a contract claim.
    III. CONCLUSION
    For the foregoing reasons, we AFFIRM the judgment of the district court.
    24
    

Document Info

Docket Number: 11-30576

Citation Numbers: 689 F.3d 380, 2012 WL 3011035, 2012 U.S. App. LEXIS 15286

Judges: King, Higginbotham, Higginson

Filed Date: 7/24/2012

Precedential Status: Precedential

Modified Date: 11/5/2024

Authorities (24)

Neel v. Citrus Lands of Louisiana, Inc. , 1993 La. App. LEXIS 3910 ( 1993 )

Egorov, Puchinsky, Afanasiev & Juring v. Terriberry, ... , 183 F.3d 453 ( 1999 )

Holt v. State Farm Fire & Casualty Co. , 627 F.3d 188 ( 2010 )

Campbell v. Melton , 817 So. 2d 69 ( 2002 )

Cowen v. Steiner , 701 So. 2d 140 ( 1997 )

Erie Railroad v. Tompkins , 58 S. Ct. 817 ( 1938 )

James P. Mitchell, Secretary of Labor, United States ... , 286 F.2d 721 ( 1961 )

Taita Chemical Co. v. Westlake Styrene Corp. , 246 F.3d 377 ( 2001 )

National Union Fire Insurance Co. Of Pittsburgh, Pa. v. ... , 915 F.2d 986 ( 1990 )

Brown v. Romero , 922 So. 2d 742 ( 2006 )

Tallo v. Stroh Brewery Co. , 544 So. 2d 452 ( 1989 )

Shelton v. Standard/700 Associates , 798 So. 2d 60 ( 2001 )

Rahier v. Rester , 11 So. 2d 87 ( 1942 )

Dickerson v. Lexington Ins. Co. , 556 F.3d 290 ( 2009 )

Sims v. Mulhearn Funeral Home, Inc. , 956 So. 2d 583 ( 2007 )

Lupo v. Lupo , 475 So. 2d 402 ( 1985 )

MacK v. Evans , 804 So. 2d 730 ( 2001 )

Technical Control Systems, Inc. v. Green , 809 So. 2d 1204 ( 2002 )

Cowen v. Steiner , 689 So. 2d 516 ( 1997 )

9 to 5 Fashions, Inc. v. Spurney , 1989 La. LEXIS 97 ( 1989 )

View All Authorities »