Northrop Grumman Computing Systems, Inc. v. United States , 709 F.3d 1107 ( 2013 )


Menu:
  •   United States Court of Appeals
    for the Federal Circuit
    ______________________
    NORTHROP GRUMMAN COMPUTING SYSTEMS,
    INC.,
    Plaintiff-Appellant,
    v.
    UNITED STATES,
    Defendant-Appellee.
    ______________________
    2011-5124
    ______________________
    Appeal from the United States Court of Federal
    Claims in no. 07-CV-613, Judge Francis M. Allegra.
    ----------------------
    NORTHROP GRUMMAN COMPUTING SYSTEMS,
    INC.,
    Plaintiff-Appellant,
    v.
    UNITED STATES,
    Defendant-Appellee.
    ______________________
    2012-5044
    ______________________
    2                       NORTHROP GRUMMAN COMPUTING   v. US
    Appeal from the United States Court of Federal
    Claims in no. 11-CV-608, Judge Francis M. Allegra.
    ______________________
    Decided: February 19, 2013
    ______________________
    DAVID C. AISENBERG, Looney Cohen & Aisenberg,
    LLP, of Boston, Massachusetts, argued for plaintiff-
    appellant in both appeals.
    AMANDA L. TANTUM, Trial Attorney, Commercial Liti-
    gation Branch, Civil Division, United States Department
    of Justice, of Washington, DC, argued for defendant-
    appellee in both appeals. With her on the brief were
    TONY WEST, Assistant Attorney General, JEANNE E.
    DAVIDSON, Director, KIRK T. MANHARDT, Assistant Direc-
    tor, and ARMANDO A. RODRIGUEZ-FEO, Trial Attorney.
    ______________________
    Before RADER, Chief Judge, PROST and REYNA, Circuit
    Judges.
    REYNA, Circuit Judge.
    Northrop Grumman Computing Systems, Inc.
    (“Northrop”) appeals two decisions of the Court of Federal
    Claims (“Northrop I” and “Northrop II”). Both appeals
    arise from a single contract between Northrop and U.S.
    Immigrations and Customs Enforcement (“ICE”) for the
    delivery of computer-network monitoring software.
    Because we find that the first claim letter Northrop filed
    with the contracting officer was a valid claim under the
    Contract Disputes Act (“CDA”), we reverse the Court of
    Federal Claims’ decision in Northrop I and remand the
    case for further proceedings.      We dismiss as moot
    Northrop’s appeal in Northrop II.
    NORTHROP GRUMMAN COMPUTING     v. US                   3
    I. BACKGROUND
    In July 2001, ICE awarded Northrop 1 Contract No.
    NAS5-01143, which was a commercial items contract.
    Under this Contract, ICE awarded Delivery Order No.
    COW-4-D-1025 according to which Northrop would lease
    to ICE, and provide support for, network monitoring
    software produced by Oakley Networks (“Oakley”). The
    Delivery Order provided that Northrop would furnish the
    software and services via a lease for one twelve month
    base year and three twelve month option years. The base-
    year price was $900,000, and each option year was priced
    at $899,186. If the Government exercised all three option
    years, the Delivery Order would have a total value of
    $3,597,558. In the month that followed the Delivery
    Order award, ICE executed three modifications at
    Northrop’s request. These modifications added clauses
    regarding Northrop’s first-priority status, the Govern-
    ment’s best efforts to secure funding, and a prohibition on
    the Government substituting comparable software for the
    Oakley software in the Northrop contract.
    In order to obtain Oakley’s software, Northrop was
    required to pay Oakley an up-front fee of $2,899,710.
    Four days after the Delivery Order award, ICE provided
    Northrop with an “essential use statement” that described
    the intended use of the Oakley software and was designed
    to facilitate third-party funding for the Oakley software.
    Thereafter, Northrop entered a private finance agreement
    with ESCgov, Inc. for the Oakley software. Under the
    terms of the financing agreement, ESCgov would pay
    Northrop $3,296,093 in exchange for Northrop’s assign-
    1     Northrop Grumman Computing Systems, Inc.
    (“Northrop”) is a division of Northrop Grumman Corpora-
    tion’s Information Technology segment. At the time of the
    award, this division was named Logicon FDC. The con-
    tract was modified in October 2004 to reflect the name
    change.
    4                      NORTHROP GRUMMAN COMPUTING      v. US
    ment to ESCgov of all payments received under the
    Delivery Order. ESCgov subsequently assigned its rights
    under the Northrop-ESCgov agreement to Citizens Leas-
    ing Corp. Neither Northrop, ESCgov, nor Citizens Leas-
    ing Corp. notified the Government of the assignments.
    On September 30, 2005, ICE sent Northrop formal no-
    tification of its decision not to exercise the lease’s first
    option year, which was to run from September 30, 2005
    until September 29, 2006. Northrop responded on Febru-
    ary 22, 2006 with a request for information regarding the
    Government’s decision. On April 14, 2006, Northrop
    received a response from the contracting officer (“CO”),
    who emphasized that there was no “termination,” but that
    the Government simply was not in a position to fund the
    options due to lack of appropriations.
    A. NORTHROP’S FIRST CLAIM (NORTHROP I)
    On September 21, 2006, Northrop sent to the CO a
    letter with the subject line “Contract Disputes Act Claim
    for not Exercising Option Year #1 under COW-4-D-1025 –
    Oakley Leasing Agreement.” Northrop notified the CO
    that the letter was submitted “[i]n accordance with the
    Contract Disputes Act of 1978, 41 U.S.C. 601 et seq., and
    the Disputes clause of the Contract.” 2 Northrop asserted
    that the Government had breached the contract modifica-
    tions made after the Delivery Order’s award, and stated
    that the company was seeking $2,697,558.00 in damages.
    The letter did not mention the two private financing
    assignments. The letter concluded with a certification
    2   Congress revised and recodified title 41 of the
    United States Code in order to “remove ambiguities,
    contradictions, and other imperfections....” Pub. L. No.
    111–350, 
    124 Stat. 3677
     (2011). All further citations in
    this opinion are to the current version of the CDA, which
    is now codified at 
    41 U.S.C. §§ 7101
    –7109 (Supp. IV
    2006).
    NORTHROP GRUMMAN COMPUTING      v. US                   5
    and a request for a final decision. On December 29, 2006,
    the CO issued a final decision denying Northrop’s claim.
    On August 20, 2007, Northrop filed a complaint before
    the Court of Federal Claims appealing the CO’s decision.
    The Court of Federal Claims scheduled trial for June 13,
    2011. Before trial, the Government learned of Northrop’s
    private financing assignments and filed a motion to
    dismiss for lack of subject-matter jurisdiction on grounds
    that Northrop’s letter was not a valid CDA claim. Specifi-
    cally, the Government argued that Northrop’s letter was
    not a valid claim because it failed to provide adequate
    notice of the nature of the claim, and because it did not
    reveal that Northrop’s claim was for third-party losses of
    private funders. On June 15, 2011, the Court of Federal
    Claims issued its opinion in Northrop I granting the
    Government’s motion to dismiss for lack of subject-matter
    jurisdiction. Northrop Grumman Computing Sys., Inc. v.
    United States, 
    99 Fed. Cl. 651
    , 660-61 (Fed. Cl. 2011).
    The Court of Federal Claims determined that it did
    not have jurisdiction because Northrop’s September 21,
    2006 claim letter to the CO did not constitute a valid CDA
    claim. The court reasoned that Northrop had not sup-
    plied the CO with “adequate notice” of the claim because
    it failed to “alert the contracting officer to the potential
    application of the Anti-Assignment Act and Severin
    doctrine [and] also to put him on notice as to the possible
    relevancy of a host of other issues that have been associ-
    ated with sponsored or ‘pass-through’ claims.” Id. at 659.
    The court stated, “Based on that failure, the court must
    conclude that Northrop’s ‘claim’ did not meet the re-
    quirements of the CDA, thereby depriving this court of
    jurisdiction over this lawsuit.” Id. at 660.
    Northrop appealed the Court of Federal Claims’ dis-
    missal in Northrop I to our court.
    6                     NORTHROP GRUMMAN COMPUTING      v. US
    B. NORTHROP’S SECOND CLAIM (NORTHROP II)
    On July 20, 2011, while Northrop I was pending be-
    fore the Court of Federal Claims, Northrop filed a second
    claim letter with the CO. Like the Northrop I letter, this
    letter also contained the subject line “Contract Disputes
    Act Claim for not Exercising Option Year #1 under COW-
    4-D-1025 – Oakley Leasing Agreement.” The second
    claim letter contained much of the same content as the
    Northrop I claim letter, but also explained that “Northrop
    Grumman Computing financed this lease through various
    payments made by ESCGov [sic] and Citizens Leasing
    Corporation” and provided documents on the financing
    arrangements. Before the CO responded to Northrop’s
    second claim letter, Northrop filed its notice of appeal to
    our court in Northrop I.
    The CO determined that Northrop’s second claim was
    the same claim pending before this court in Northrop I,
    and that as a result, he lacked authority to resolve
    Northrop’s second claim:
    Northrop’s July 2011 claim arises from the same
    operative facts and is substantially the same
    claim as the claim it previously submitted to ICE
    dated September 21, 2006. . . . It is the Govern-
    ment’s position that because the July 2011 Con-
    tract Disputes Act Claim for not exercising option
    year #1 under COW-4-D-1025 is substantively the
    same claim as the one currently pending before
    the Federal Circuit on appeal under 
    28 U.S.C. § 516
    , only the Department of Justice possesses the
    authority to act.
    The CO consequently declined to issue a final decision on
    Northrop’s second claim.
    Northrop appealed the CO’s refusal to issue a decision
    on its second claim to the Court of Federal Claims. The
    Court of Federal Claims held that it lacked jurisdiction
    NORTHROP GRUMMAN COMPUTING     v. US                  7
    over Northrop’s second complaint (Northrop II). Northrop
    Grumman Computing Sys., Inc. v. United States, 
    101 Fed. Cl. 362
    , 365 (Fed. Cl. 2011). In its decision, the court
    noted, “[Northrop’s second] complaint asserts the same
    claim as [the Northrop I] complaint that was dismissed by
    this court for lack of jurisdiction on June 23, 2011.” The
    court found that Northrop’s pending appeal in Northrop I
    divested the CO of his authority to issue a final decision
    on Northrop’s second claim. Without a valid final decision
    from the CO, the court concluded that it lacked jurisdic-
    tion over Northrop’s second complaint.
    Northrop appealed the Court of Federal Claims’ dis-
    missal in Northrop II to our court and we consolidated
    Northrop I and II. We have jurisdiction under 
    28 U.S.C. § 1295
    (a)(3).
    II. STANDARD OF REVIEW
    We review a grant or denial of a motion to dismiss for
    lack of subject-matter jurisdiction de novo. Hewlett-
    Packard Co. v. Acceleron LLC, 
    587 F.3d 1358
    , 1361 (Fed.
    Cir. 2009). As both Northrop I and Northrop II were
    dismissed for lack of subject-matter jurisdiction, we
    review both dismissals de novo.
    III. NORTHROP I
    In Northrop I, the Court of Federal Claims concluded
    that Northrop’s “claim” did not meet the requirements of
    a valid claim under the CDA. Specifically, the court
    explained that Northrop’s failure to disclose information
    about its third-party financing arrangements deprived the
    CO of adequate notice of the basis of the claim because
    the claim failed to alert the contracting officer to the
    potential application of the Anti-Assignment Act, the
    Severin doctrine, and other issues associated with spon-
    sored or “pass-through” claims. The court thus concluded
    that Northrop had not submitted a valid CDA claim to the
    8                       NORTHROP GRUMMAN COMPUTING       v. US
    CO, and accordingly, the court lacked subject-matter
    jurisdiction over the Northrop I complaint.
    On appeal, Northrop argues that its first claim letter
    fully complied with the requirements of the CDA because,
    among other grounds, the CDA did not require Northrop
    to disclose its third-party financing arrangements. Ac-
    cordingly, Northrop asks us to reverse the Court of Feder-
    al Claims’ dismissal and remand for adjudication of its
    CDA claim.
    A prerequisite for jurisdiction of the Court of Federal
    Claims over a CDA claim is a final decision by a contract-
    ing officer on a valid claim. M. Maropakis Carpentry, Inc.
    v. United States, 
    609 F.3d 1323
    , 1327 (Fed. Cir. 2010). If
    a purported claim is found to be insufficient for any
    reason, the insufficiency is fatal to jurisdiction under the
    CDA. Sharman Co. v. United States, 
    2 F.3d 1564
    , 1568
    (Fed. Cir. 1993) (“Under the CDA, a final decision by the
    contracting officer on a claim . . . is a ‘jurisdictional pre-
    requisite’ to further legal action thereon.”), overruled on
    other grounds by Reflectone, Inc. v. Dalton, 
    60 F.3d 1572
    (Fed. Cir. 1995). Thus, if Northrop’s claim is an insuffi-
    cient CDA claim, the Court of Federal Claims lacks sub-
    ject-matter jurisdiction to review both the claim itself and
    the CO’s decision.
    The CDA establishes some prerequisites for a valid
    claim. For example, the CDA requires that a claim by a
    contractor be submitted to the contracting officer for
    decision, that the claim be in writing, and that the con-
    tractor certify claims over $100,000. 3 See 
    41 U.S.C. § 3
        For claims of more than $100,000, the CDA re-
    quires the contractor to certify that (1) the claim is made
    in good faith, (2) the supporting data are accurate and
    complete to the best of the contractor’s knowledge and
    belief, (3) the amount requested accurately reflects the
    contract adjustment for which the contractor believes the
    NORTHROP GRUMMAN COMPUTING      v. US                     9
    7103(a)–(b). In addition to the statutory requirements of
    the CDA, we assess whether a claim is valid based on the
    Federal Acquisition Regulation(s), the language of the
    contract in dispute, and the facts of the case. Reflectone,
    
    60 F.3d at 1575
    ; see also Garrett v. General Elec. Co., 
    987 F.2d 747
    , 749 (Fed. Cir. 1993).
    The Federal Acquisition Regulation (“FAR”) defines
    “claim” as follows:
    (c) Claim, as used in this clause, means a written
    demand or written assertion by one of the con-
    tracting parties seeking, as a matter of right, the
    payment of money in a sum certain, the adjust-
    ment or interpretation of contract terms, or other
    relief arising under or relating to this contract.
    However, a written demand or written assertion
    by the Contractor seeking the payment of money
    exceeding $100,000 is not a claim under the Act
    until certified. A voucher, invoice, or other routine
    request for payment that is not in dispute when
    submitted is not a claim under the Act. The sub-
    mission may be converted to a claim under the
    Act, by complying with the submission and certifi-
    cation requirements of this clause, if it is disputed
    either as to liability or amount or is not acted up-
    on in a reasonable time.
    FAR 52.233–1. In Reflectone, we held that the FAR sets
    forth only three requirements of a non-routine “claim” for
    money: that it be (1) a written demand, (2) seeking, as a
    matter of right, (3) the payment of money in a sum cer-
    tain. 
    60 F.3d at
    1575–76.
    While a valid claim under the CDA must contain “a
    clear and unequivocal statement that gives the contract-
    Federal Government is liable, and (4) the certifier is
    authorized to certify the claim on behalf of the contractor.
    
    41 U.S.C. § 7103
    (b)(1)(A)–(D).
    10                     NORTHROP GRUMMAN COMPUTING       v. US
    ing officer adequate notice of the basis and amount of the
    claim,” the claim need not take any particular form or use
    any particular wording. Contract Cleaning Maint., Inc. v.
    United States, 
    811 F.2d 586
    , 592 (Fed. Cir. 1987). “All
    that is required is that the contractor submit in writing to
    the contracting officer a clear and unequivocal statement
    that gives the contracting officer adequate notice of the
    basis and amount of the claim.” 
    Id.
    Northrop submitted a written claim letter to the CO
    in Northrop I. The letter contained clear allegations of
    the Government’s breach of specific contractual provi-
    sions, and it demanded a specific amount in damages.
    The letter was accompanied by the required certification
    statement, and it stated a clear request for a final deci-
    sion along with the relief sought. As required by the CDA
    and the FAR, Northrop’s claim letter was “a clear and
    unequivocal statement” that gave the CO adequate notice
    of the basis for the alleged breach and specified an
    amount of the claim. See Maropakis, 
    609 F.3d at 1327
    (quoting Contract Cleaning, 
    811 F.2d at 592
    ). Northrop’s
    claim letter thus satisfied all the requirements listed for a
    CDA “claim” according to the plain language of the FAR.
    The Court of Federal Claims noted concern that
    Northrop’s failure to disclose the details of its financing
    arrangements did not give the contracting officer ade-
    quate notice of the potential applicability of the Anti-
    Assignment Act, the Severin doctrine, or “a host of other
    issues that have been associated with sponsored or ‘pass-
    through’ claims.” See generally Anti-Assignment Act, 31
    U.S.C § 3727, 
    41 U.S.C. § 15
    ; Severin v. United States, 
    99 Ct. Cl. 435
    , 442–43 (1943) (holding that a prime contrac-
    tor cannot recover on behalf of subcontractor to whom
    prime contractor is not independently liable).
    The Court of Federal Claims correctly found that
    Northrop’s failure to notify the Government of its assign-
    ment rendered the assignment “null and void as against
    NORTHROP GRUMMAN COMPUTING     v. US                   11
    the United States” by operation of the Anti-Assignment
    Act. The court explained, “That does not mean, however,
    that Northrop forfeited its breach of contract claim
    against the United States.” Indeed, the court concluded
    that Northrop was the proper party to bring the claim.
    We agree. See Beaconwear Clothing Co. v. United States,
    
    355 F.2d 583
    , 591 (Ct. Cl. 1966) (holding, where Beacon-
    wear’s assignment of contractual right to receive pay-
    ments was void as against the Government, that
    “Beaconwear thus remains the only party which has a
    legal claim to the amount due under the contract”); Colo-
    nial Navigation Co. v. United States, 
    181 F. Supp. 237
    ,
    240 (Ct. Cl. 1960) (“But an attempted assignment of a
    claim against the United States does not forfeit the claim.
    It leaves the claim where it was before the purported
    assignment.”). As such, Northrop is not asserting a pass-
    through claim, and the Severin doctrine does not apply in
    this case. Beaconwear, 355 F.2d at 591; Colonial Nav.,
    
    181 F. Supp. at 240
    .
    Because Northrop was the proper party to bring the
    claim, we disagree that by omitting financing information
    Northrop failed to give the contracting officer adequate
    notice for the basis of its claim. We therefore hold that
    the claim letter Northrop submitted in Northrop I was a
    valid claim under the CDA, and the Court of Federal
    Claims had subject-matter jurisdiction over the CO’s
    decision on that claim.
    IV. CONCLUSION
    Because we find that the Court of Federal Claims had
    jurisdiction over Northrop’s claim in Northrop I, the
    Northrop II appeal is moot.
    The decision of the Court of Federal Claims in
    Northrop I (Appeal No. 2011-5124) is REVERSED AND
    REMANDED for adjudication on the merits. Northrop’s
    appeal in Northrop II (Appeal No. 2012-5044) is
    DISMISSED as moot.
    12                      NORTHROP GRUMMAN COMPUTING   v. US
    COSTS
    Each party shall bear its own costs.