In Re: Appeal of Provco Pinegood Sumneytown, LLC ( 2019 )


Menu:
  •         IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    In Re: Appeal of Provco Pinegood      :
    Sumneytown, LLC From The              :
    Decision Dated December 4, 2017       :
    of The Board of Commissioners of      :   No. 1554 C.D. 2018
    Upper Gwynedd Township                :   Argued: June 3, 2019
    :
    Appeal of: Provco Pinegood            :
    Sumneytown, LLC                       :
    BEFORE:     HONORABLE MARY HANNAH LEAVITT, President Judge
    HONORABLE ROBERT SIMPSON, Judge
    HONORABLE ELLEN CEISLER, Judge
    OPINION
    BY JUDGE SIMPSON                      FILED: July 29, 2019
    I. Introduction
    In this land use appeal, Provco Pinegood Sumneytown, LLC
    (Developer) appeals from an order of the Court of Common Pleas of Montgomery
    County (trial court) that affirmed a December 2017 decision by the Upper
    Gwynedd Township (Township) Board of Commissioners (Commissioners)
    denying Developer’s second application for preliminary land development
    approval for construction of a Wawa Food Market, which would be comprised of a
    convenience store and gasoline service station. The Commissioners’ decision
    included 31 numbered paragraphs identifying specific reasons for denying
    Developer’s application.
    Without taking additional evidence, the trial court affirmed the
    Commissioners on the grounds specified in Paragraph 31 of the Commissioners’
    decision. In Paragraph 31, the Commissioners reasoned that Developer failed or
    refused to seek special exception relief before the Township’s Zoning Hearing
    Board (ZHB) as required by the Township’s Zoning Ordinance.                          Because
    Developer’s application violated the Zoning Ordinance, it also expressly violated
    the Township’s Subdivision and Land Development Ordinance (SALDO).
    On appeal, Developer first contends the Commissioners erred in
    concluding that a zoning officer’s report, made in the context of a land
    development plan review, was an appealable determination under the Pennsylvania
    Municipalities Planning Code (MPC).1 Also, Developer asserts the Commissioners
    erred in concluding that Developer’s failure to appeal the determination was a
    valid legal basis to deny its application where it had already received a decision
    from the ZHB permitting a convenience store with a gasoline service station at the
    property.
    Relevant for current purposes, Developer also contends the
    Commissioners erred or abused their discretion in denying its application based on
    traffic standards and requirements for safe road access not contained in any
    Township Ordinance. Further, Developer argues the Commissioners violated its due
    process rights by refusing to allow it to cross-examine witnesses whose testimony
    the Commissioners relied upon to support the denial of its second application. Upon
    review, we affirm, although on a different basis.2
    1
    Act of July 31, 1968, P.L. 805, as amended, 53 P.S. §§10101-11202.
    2
    We may affirm a trial court’s order on different grounds if the reasons stated for our
    decision are clear on the record. Ness v. York Twp. Bd. of Comm’rs, 
    81 A.3d 1073
    (Pa.
    Cmwlth. 2013); Guy M. Cooper, Inc. v. E. Penn Sch. Dist., 
    903 A.2d 608
    (Pa. Cmwlth. 2006).
    2
    II. Background
    Developer owns two contiguous lots (site) located at the intersection
    of Sumneytown Pike and West Point Pike in a C-Commercial District in the
    Township. Developer proposed to build a 5,585-square-foot Wawa convenience
    store with gasoline sales from eight outdoor detached fueling stations (16 fueling
    lanes), and 56 parking spaces. The fueling stations would be located under a
    detached 7,150-square-foot A-frame canopy. A convenience store is a retail use
    permitted by right in the C-Commercial District.
    A. Related Zoning Proceedings
    In November 2016, the ZHB issued a decision determining that
    Developer’s proposed gasoline sales use was an accessory use to a by-right principal
    convenience store retail use. See ZHB Dec., 11/22/16; Reproduced Record (R.R.) at
    460a-61a. The decision was appealed to the trial court. On March 23, 2018, in an
    opinion and order by Judge Daniel J. Clifford, the trial court reversed the ZHB,
    holding that Developer failed to demonstrate that the gasoline sales use was an
    accessory use to the convenience store. The trial court remanded the case to the
    ZHB to determine whether Developer was entitled to a special exception for its
    proposed gasoline sales use. Developer appealed to this Court, which quashed the
    appeal as from an interlocutory order. See In Re: Appeal of Bd. of Comm’rs of
    Upper Gwynedd Twp. (Appeal of Provco Pinegood Sumneytown, LLC) (Provco I)
    (Pa. Cmwlth., No. 502 C.D. 2018, filed April 3, 2019), 
    2019 WL 1492781
    (unreported).
    3
    B. Planning Commission Proceeding on First Application
    Meanwhile, in January 2017, Developer submitted its first preliminary
    land development application to the Planning Commission. Merck & Co., Inc.
    (Merck) and Hartford Properties, Inc. (Hartford), two neighboring property
    owners, were permitted to intervene in opposition to the application. The Planning
    Commission held five meetings on the application. The Township and Merck
    presented engineering testimony on alleged traffic, stormwater and other
    engineering deficiencies. At the final meeting, the Planning Commission voted six
    to one to reject the application.
    C. Zoning Officer’s Determination (Special Exception)
    In addition, after reviewing the application, the Township’s specially
    appointed Conflict Zoning Officer Kenneth Amey (Zoning Officer), notified the
    Township Manager by letter (copied to Developer and others) that the gasoline
    sales use required special exception approval under the Zoning Ordinance.
    Although Developer initially appealed the Zoning Officer’s letter regarding the
    need for a special exception, Developer later withdrew its appeal. Developer took
    the position that the Zoning Officer’s letter to the Township Manager did not
    constitute either a decision on a permit application or a formal zoning opinion.
    Rather, Developer interpreted the Zoning Officer’s letter as a review letter offering
    comments on Developer’s first application.
    D. Commissioners’ Denial of First Application
    At a July 2017 Commissioners’ meeting, the parties again presented
    engineering evidence. The Township and Merck again focused on traffic and
    4
    stormwater management concerns. Due to various deficiencies in the application,
    the Commissioners voted at the meeting to deny the application.
    On August 7, 2017, the Commissioners issued its written decision.
    The Commissioners set forth 50 specific reasons for denying the application.
    Paragraphs 18, 20 and 21 addressed stormwater management deficiencies.
    Paragraphs 26-43 addressed traffic impact design and site ingress/egress
    deficiencies. Most notably, a driver exiting the site onto eastbound Sumneytown
    Pike would not be able to see the required distance to the west (or left) because of a
    blind curve and a train overpass which blocks the view of oncoming eastbound
    drivers.   Paragraph 44 addressed parking deficiencies for oversized vehicles,
    common at other Wawa locations, which lead to the obstruction of traffic.
    Paragraph 50 addressed the Zoning Officer’s letter regarding the need for a special
    exception for a gasoline sales use.
    E. Second Application
    On August 15, 2017, Developer submitted its second preliminary land
    development application, which was substantially similar to the first application.
    The Township’s engineers again issued review letters to the Township Manager
    regarding various unresolved deficiencies. Zoning Officer issued a second letter to
    the Township Manager (copied to Developer and others) again noting the need for
    a special exception for gasoline sales. Developer did not appeal Zoning Officer’s
    second letter indicating the need for a special exception.
    5
    In October 2017, in response to a review letter from the Township’s
    engineers, Developer submitted revised plans. Zoning Officer issued a third letter to
    the Township Manager (copied to Developer and others) indicating a special
    exception would be needed for gasoline sales. Developer did not appeal this letter.
    Ultimately, the Planning Commission voted 4-3 to approve the second
    application subject to two conditions. First, the exit on the western driveway on
    Sumneytown Pike must have a larger “pork chop” traffic barrier, which would
    more effectively preclude drivers from making prohibited left turns onto
    Sumneytown Pike. See R.R. at 1001a. Second, drivers must be prohibited from
    making left turns onto West Point Pike during the A.M. and P.M. peak hours. 
    Id. Following the
    Planning Commission’s conditional approval, Merck
    provided the Township Manager (copied to many others) with updated expert
    engineering reports regarding unresolved stormwater deficiencies.        Merck also
    provided the Township with an expert engineering report detailing numerous traffic
    deficiencies.
    F. Commissioners’ Denial of Second Application
    At a November 2017 public meeting, the parties again presented
    engineering evidence, including various traffic studies regarding safe stopping
    distance for egress from the site to Sumneytown Pike, anticipated U-turns and
    illegal left turns onto West Point Pike during peak hours, and insufficient parking
    6
    for trucks and oversized vehicles. The evidence included studies of these types of
    problems at similarly designed Wawa locations.3
    At the conclusion of the meeting, the Commissioners voted
    unanimously, with one abstention, to deny the second application. On December
    4, 2017, the Commissioners issued a written decision containing 31 specific
    reasons to deny the application.           Reasons 7 and 8 addressed stormwater
    management deficiencies.        Paragraphs 9-26 addressed traffic design and road
    access deficiencies. Paragraph 27 addressed the failure to provide parking for
    oversized vehicles, delivery trucks, landscaping trucks with trailers, recreation
    vehicles and larger commercial trucks.           Paragraph 28 addressed internal site
    circulation deficiencies.
    Paragraph 31 addressed Developer’s failure to obtain a special
    exception for gasoline sales use. The Commissioners noted that Developer failed
    to appeal the Zoning Officer’s determination that the Zoning Ordinance required a
    special exception for a gasoline sales use.          To that end, the Commissioners
    indicated that in a proceeding to determine whether to approve or disapprove a
    plan, a zoning officer’s interpretation constitutes a determination under the MPC
    upon which the Commissioners may rely.
    3
    Merck also presented evidence of unresolved stormwater management deficiencies. In
    particular, Gary R. Emmanuel, P.E., of O’Brien and Gere, Engineers, Inc. (Merck’s Stormwater
    Engineer), explained Developer’s failure to appropriately determine the capacity of existing
    downstream systems. In particular, Merck’s Stormwater Engineer further asserted that
    Developer relied on erroneous calculations, which resulted in the stormwater system being
    under-designed.
    7
    Addressing the facts here, the Commissioners observed that
    Developer must appeal the Zoning Officer’s determination within 30 days as
    required by Section 914.1 of the MPC, 53 P.S. §10914.1.4 The Commissioners
    further noted that Section 909.1(a)(3) of the MPC, 53 P.S. § 10909.1(a)(3),5
    provides the ZHB with exclusive jurisdiction to hear and render a final
    adjudication on appeals from a zoning officer’s determinations and that failure to
    appeal renders such determinations binding. Because Developer neither appealed
    Zoning Officer’s determination nor applied for a special exception, the
    Commissioners determined Developer’s proposed development violated Section
    195-22.A(8)(c) of the Zoning Ordinance. Developer appealed the Commissioners’
    decision to the trial court.
    G. Trial Court’s Decision and Order
    In November 2018, the trial court affirmed the Commissioners’ order
    denying Developer’s second application. In so doing, the trial court, in a decision by
    Judge Wendy G. Rothstein, observed that the rejection of a land development plan
    may stand if supported by even one of several objections, relying on Robal
    Associates, Inc. v. Board of Supervisors of Charlestown Township, 
    999 A.2d 630
    (Pa. Cmwlth. 2010). Here, the trial court relied solely on the Commissioners’
    determination in Paragraph 31. More specifically, the trial court recognized that
    Section 195-22.A(8)(c) of the Zoning Ordinance requires a special exception for a
    gasoline service station, regardless of whether it is a primary or accessory use. The
    4
    Added by the Act of December 21, 1988, P.L. 1329.
    5
    Added by the Act of July 4, 2008, P.L. 319.
    8
    trial court also noted that the Zoning Officer’s second and third determinations
    became final upon Developer’s failure to appeal them within 30 days. See Lower
    Mount Bethel Twp. v. Gacki, 
    150 A.3d 575
    (Pa. Cmwlth. 2016) (the developer’s
    failure to appeal violation notice within 30 days resulted in conclusive determination
    of ordinance violation).
    Therefore, Judge Rothstein agreed with Judge Clifford’s decision in
    the related zoning case that Developer’s proposed development is in violation of
    Section 195-22.A(8)(c) of the Zoning Ordinance and Sections 168-13.E(6) and
    168-13.H of the SALDO based on Developer’s failure to obtain a special exception
    for the gasoline sales operation.          Accordingly, the trial court determined the
    Commissioners’ rejection of Developer’s second application was validly supported
    by the Commissioners’ reasons for denial set forth in Paragraph 31. Consequently,
    the trial court affirmed the Commissioners’ denial of Developer’s second
    application. Developer appeals.6
    III. Discussion
    A. Plan Approval Generally
    Section 508(2) of the MPC provides that when a governing body
    denies an application for plan approval, it shall specify the defects in the plan
    application, describe the requirements that were not met, and in each case, cite the
    6
    Where the trial court takes no additional evidence, appellate review in a land
    development appeal is limited to determining whether the local governing body committed an
    error of law or an abuse of discretion. Whitehall Manor, Inc. v. Planning Comm’n of the City of
    Allentown, 
    79 A.3d 720
    (Pa. Cmwlth. 2013). An abuse of discretion occurs when the governing
    body’s findings are not supported by substantial evidence. Gerryville Materials, Inc. v. Planning
    Comm’n of Lower Milford Twp., Lehigh Cty., 
    74 A.3d 322
    (Pa. Cmwlth. 2013).
    9
    provisions of the ordinance or statute relied upon. 53 P.S. §10508(2). If a plan
    complies with all objective provisions of the applicable SALDO, as well as all other
    regulations, the plan must be approved. Robal. However, a single reason, if
    legitimate, may support the denial of the plan. Robal; Herr v. Lancaster Cty.
    Planning Comm’n, 
    625 A.2d 164
    (Pa. Cmwlth. 1993). We are also mindful of the
    deference courts should exercise when reviewing a governing body’s interpretation
    of the ordinances it enacts and applies. Tink-Wig Mountain Lake Forest Prop.
    Owners Ass’n v. Lackawaxen Twp. Zoning Hearing Bd., 
    986 A.2d 935
    (Pa.
    Cmwlth. 2009).
    B. Zoning Officer’s Report
    1. Argument
    Developer first contends Zoning Officer’s conclusion that a gasoline
    sales use requires the applicant to obtain a special exception under Section 195-
    22.A(8)(c) of the Zoning Ordinance, was not a determination appealable to the ZHB.
    Citing Section 107 of the MPC, 53 P.S. §10107, which defines an appealable
    determination as a final action by an officer charged with the administration of any
    land use ordinance or application thereunder, Developer argues Zoning Officer’s
    report was not a final determination. In short, it was not a final action. In fact,
    Developer asserts the report did not constitute an action of any kind. Rather, it was
    merely a comment in a review letter issued to assist the Commissioners in rendering
    their decision on the second application.
    As support, Developer cites the MPC’s definition of “report.” Section
    107 defines a “report” as “any letter, review, memorandum, compilation or similar
    10
    writing made by any body, board, officer or consultant other than a solicitor … for
    the purpose of assisting the recipient in the rendering of any decision or
    determination.” 53 P.S. §10107 (emphasis added). All reports shall be considered
    recommendatory and advisory, and shall not be binding on the recipient. 
    Id. Moreover, reports
    are not appealable.      
    Id. As such,
    Developer contends the
    Commissioners erred in concluding that Zoning Officer’s reports were binding and
    appealable.
    Also, Developer asserts the ZHB rejected Zoning Officer’s special
    exception determination in a separate decision granting Developer’s request for
    zoning relief on neighboring property. The ZHB determined Developer’s proposed
    gasoline sales at that other property qualified as an accessory use permitted by-
    right in a C-Commercial District, despite Zoning Officer’s advice to the contrary.
    Developer therefore argues it would have been nonsensical to appeal Zoning
    Officer’s report.
    Further, Developer acknowledges that the trial court, in a March 2018
    decision by Judge Clifford, reversed the ZHB’s decision regarding the current
    property. However, the Commissioners denied Developer’s second application in
    December 2017, prior to the trial court’s reversal. Stated differently, the trial
    court’s March 2018 decision could not serve as a valid basis for the
    Commissioners’ 2017 denial of the second application.
    11
    2. Analysis
    In the context of a pending land development application, a zoning
    officer’s oral interpretation of a zoning ordinance made directly to an applicant can
    be an appealable determination under the MPC. N. Codorus Twp. v. N. Codorus
    Twp. Zoning Hearing Bd., 
    873 A.2d 845
    (Pa. Cmwlth. 2005). Section 909.1(a)(3)
    of the MPC provides that a zoning hearing board shall have exclusive jurisdiction
    to hear and render final adjudications in matters including “appeals from the
    determination of the zoning officer, including, but not limited to, the granting or
    denial of any permit ….” 53 P.S. §10909.1(a)(3) (emphasis added). Failure to
    appeal a zoning officer’s determination within 30 days results in the determination
    becoming binding and unappealable. Section 914.1 of the MPC,7 53 P.S. §10914.1;
    Gacki (zoning violation notice directed to Developer).
    Here, however, Zoning Officer issued three letters addressed to the
    Township Manager, copied to other Township officials and to Developer, covering
    various points, including that Section 195-22.A(8)(c) requires a special exception
    be obtained for a gasoline sales use, whether or not it qualifies as a primary or
    accessory use. On their face, these letters appear to be reports to the Township
    regarding a pending land development application, not an immediately appealable
    final zoning determination directed to Developer. E.g., R.R. at 475a, 975a. In
    other words, the letters appear on their face to be “reports” rather than final
    “determinations,” as respectively defined in Section 107 of the MPC. 53 P.S.
    §10107.
    7
    Added by the Act of December 21, 1988, P.L. 1329.
    12
    Moreover, much of this dispute was rendered moot in subsequent
    proceedings on the related zoning case. In Provco I, the Township appealed the
    ZHB’s 2016 decision that Developer’s proposed gasoline sales use qualified as an
    accessory use to a convenience store permitted by-right.        Ultimately, Judge
    Clifford determined that, regardless of the ZHB’s decision in the other case
    involving a convenience store/gasoline sales development on neighboring property,
    the ZHB had the responsibility to conduct an evidentiary hearing in the Wawa
    zoning case to determine whether a special exception was required for this
    particular property. Consequently, in its order granting Developer an evidentiary
    hearing on the special exception issue, the trial court explicitly reinstated
    Developer’s request for a special exception as opposed to requiring a new,
    additional finding. See Upper Gwynedd Twp. Bd. of Comm’rs v. Upper Gwynedd
    Twp. Zoning Hearing Bd., (Mont. C.P., No. 2016-29426, filed March 23, 2018).
    As a result, questions about the underlying zoning for the proposed
    development have not yet been resolved. At this stage of the land development
    proceedings, it is impossible to determine whether the lack of a special exception,
    by itself, is a sufficient basis to affirm the Commissioners’ actions. Accordingly,
    we must look beyond the trial court’s reliance on the underlying zoning. In
    particular, we must examine other issues raised in Developer’s appeal from the
    Commissioners’ denial.
    C. Safe Road Access
    1. Argument
    13
    Developer contends the Commissioners erred and abused their
    discretion by denying its second application based on Pennsylvania Department of
    Transportation (PennDOT) traffic policies, standards and specifications for safe
    road access not contained in any Township ordinance. Under Pennsylvania law,
    Developer asserts, a preliminary plan must be approved if it meets all specific,
    objective requirements of the applicable SALDO. Robal; Herr.
    Developer alleges Paragraphs 9 through 30 of the Commissioners’
    decision set forth reasons for denial of the second application based on
    Developer’s failure to comply with PennDOT publications concerning various
    PennDOT policies and procedures including traffic control, signing standards, and
    road construction specifications for safe road access. However, Developer argues
    there are no requirements in the Township’s SALDO or any other Township
    ordinance that would require compliance with PennDOT specifications on non-
    state-owned roads.
    In particular, Developer argues the Commissioners erred in relying on
    Sections 168-16.B and 168-17.H of the SALDO to support their conclusion that
    Developer must comply with PennDOT specifications even though no state roads
    are involved.   Section 168-16.B provides:      “Development shall be planned,
    reviewed and carried out in conformance with all Township, [C]ounty, [S]tate and
    other applicable laws and regulations.” R.R. at 58a.
    Section 168-17.H of the SALDO provides:
    Improvement construction requirements will be
    completed under specifications of [PennDOT], [the
    14
    Pennsylvania Department of Environmental Protection or
    other appropriate state agency, the [County] Soil and
    Water Conservation District or other appropriate
    agencies, or the specifications included herein, whichever
    specifications shall be the more restrictive.
    R.R. at 59a (emphasis added).
    Developer asserts Section 168-16.B clearly states that compliance
    with State standards and specifications, including PennDOT standards and
    specifications, is only required when applicable. Developer maintains PennDOT
    standards and specifications are only applicable where access to a state highway is
    involved. Therefore, Developer argues, Section 168-16.B of the SALDO cannot
    require compliance with PennDOT access regulations for roads not under
    PennDOT jurisdiction.
    Developer also contends Section 168-17.H applies to improvement
    construction specifications detailing the materials and thickness for road
    construction, such as binder course and asphalt. However, Developer claims this is
    a far cry from requiring that all roads comply with PennDOT’s access
    requirements.
    Developer therefore argues that the Commissioners’ rejection of the
    second application based on the alleged failure to provide safe access is based only
    on generalized health and safety concerns rather than a specific provision in a
    Township ordinance. It is an abuse of discretion to deny approval of a preliminary
    land development plan based on generalized traffic concerns that are not supported
    by a specific ordinance violation. Valley Run, Inc. v. Bd. of Comm’rs of Swatara
    15
    Twp., 
    347 A.2d 517
    (Pa. Cmwlth. 1975). Developer further argues a preliminary
    plan may not be rejected upon non-specific standards such as the potential danger
    to health, safety and welfare. Scluffer v. Plymouth Twp., 
    379 A.2d 1060
    (Pa.
    Cmwlth. 1977).
    Consequently, Developer claims the Commissioners erred and abused
    their discretion by denying Developer’s second application based on a generalized
    concern that Developer failed to demonstrate safe road access.
    2. Analysis
    a. PennDOT Regulations for Driveway Access
    Paragraphs 9 through 26 of the Commissioners’ decision essentially
    identify the safety deficiencies in Developer’s planned road access to the proposed
    Wawa. Prior to addressing the traffic issues, the Board observed:
    NOTE: Developer is required to comply with the traffic
    standards of [PennDOT], and any Federal standards
    adopted thereby, except where the Township has adopted
    more restrictive standards by ordinance, pursuant to
    Township Ordinance, Chapter 168 (SALDO), Article VI
    (Design and Construction Standards), Sections 168-16B.
    and 168-17.H, [Section 6109(a) of the Vehicle Code, 75
    Pa. C.S. §6109] and other applicable authority.
    Comm’rs’ Op., 12/4/17, at 3.
    Pursuant to Section 6109(a) of the Vehicle Code, nothing in the
    Vehicle Code8 shall prevent local authorities on streets and “highways” within their
    8
    75 Pa. C.S. §§101-9805.
    16
    boundaries from the reasonable exercise of their police powers.            75 Pa. C.S.
    §6109(a). Section 102 of the Vehicle Code defines a “highway” as: “The entire
    width between the boundary lines of every way publicly maintained when any part
    thereof is open to the use of the public for purposes of vehicular travel.” 75 Pa.
    C.S. §102.
    Zoning and other land development ordinances such as the
    Township’s SALDO are valid exercises of a municipality’s police power that
    promote the public health, safety and welfare.          See Penn Street, L.P. v. E.
    Lampeter Twp. Zoning Hearing Bd., 
    84 A.3d 1114
    (Pa. Cmwlth. 2014); Main
    Street Dev. Grp., Inc. v. Tinicum Twp. Bd. of Supervisors, 
    19 A.3d 21
    (Pa.
    Cmwlth. 2011). As noted above, Section 168-16.B of the Township’s SALDO
    provides that a proposed development shall be planned, reviewed and carried out in
    conformance with all Township, County, State and other applicable laws and
    regulations.    R.R. at 58a.     Section 168-17.H of the SALDO requires that
    improvement construction requirements must meet not only the specifications in the
    SALDO, but also comply with the specifications of PennDOT or any other
    appropriate state agency if those specifications are more restrictive. 
    Id. at 59a.
    Here, the Commissioners properly interpreted Sections 168-16.B and
    168-17.H of the SALDO as requiring Developer to comply with PennDOT traffic
    standards for safe access to and from Sumneytown Pike, even though it is not a
    state highway. If authorized by a zoning or subdivision ordinance, a municipality
    may apply stricter safety standards to arterial or collector streets. See Shelbourne
    Square Assocs., L.P. v. Bd. of Supervisors of Twp. of Exeter, Berks Cty., 
    794 A.2d 17
    946 (Pa. Cmwlth. 2002) (township, as authorized by its ordinance, may demand
    more than minimum safety standards).
    b. Safe Egress to Sumneytown Pike
    As discussed above, the Commissioners’ denial of Developer’s
    second application must stand if there is one valid reason for disapproval of it.
    Kassouf v. Township of Scott, 
    883 A.2d 463
    (Pa. 2005); Robal. When a governing
    body denies an application, its decision must specify the defects found in the
    application and describe the requirements that were not met. Section 508(2) of the
    MPC, 53 P.S. §10508(2). In each case, the governing body must cite to the
    provision of the statute or ordinance upon which it relied. 
    Id. Here, we
    focus on Paragraph 11 of the Commissioners’ decision. In
    applying PennDOT’s regulations governing safe stopping sight distance (SSSD)
    for access driveways, the Commissioners determined Developer’s second
    application failed to provide for safe egress onto eastbound Sumneytown Pike from
    the site. The Township’s traffic engineer, Andreas Heinrich, P.E., P.T.O.E, 9 of
    Heinrich and Klein Associates, Inc. (Township’s Traffic Engineer), described
    SSSD as “a scientific representation that takes into account the velocity of the
    vehicle, the perception time of the motorist, the wet friction factor of the pavement,
    and the percent grade of the roadway.” See Township’s Traffic Engineer’s Traffic
    Review, 11/6/17 (Township Traffic Review), at 5; R.R. at 987a. “The equation
    accounts for the time the motorist observed an object in/entering the road, the time
    to react and depress the brake, and the time to bring the vehicle to a halt.” 
    Id. 9 Professional
    Transportation Operations Engineer.
    18
    In its entirety, Paragraph 11 states:
    11. [Developer] failed to adequately demonstrate that the
    driveways located on Sumneytown Pike will have safe
    access, for reasons including, but not limited to, failing to
    satisfy the minimum Safe Stopping Sight Distance
    (‘SSSD’).      The minimum SSSD must exceed the
    available sight distance. The SSSD shall be calculated
    with the use of the 85th percentile of the measured vehicle
    operating speed of the abutting roadway (not the posted
    speed limit). The SSSD is the absolute minimum
    acceptable sight distance for driveways and if the
    measured available sight distance for a proposed
    driveway does not exceed the minimum SSSD, such
    driveway shall not be approved. [Developer] measured
    the minimum acceptable SSSD to be 351 feet and the
    Township calculated the minimum SSSD to be 363 feet.
    However, [Developer] also proposes the use of a ‘desired
    sight distance’, which it calculated to be 300 feet, instead
    of the SSSD. The parties then measured the available
    sight distance to the western Sumneytown Pike driveway,
    as follows:
    Township Traffic Engineer: Available Sight Distance:
    265 feet
    Developer: Available Sight Distance: 305 feet
    Merck Traffic Engineer: Available Sight Distance: 281.5
    feet
    The [Commissioners do] not find [Developer’s]
    proposed use of the ‘desired stopping distance’ (300 feet)
    to be the applicable value necessary to determine
    compliance of the Development’s driveways with the
    minimum acceptable sight distance. However, even using
    [Developer’s] calculations of the ‘desired stopping
    distance’, the location of the western driveway on
    Sumneytown Pike still fails to fall within the available
    sight distances calculated by both the Township and
    Merck. Neither the minimum SSSD nor the ‘desired sight
    distance’ are available for safe egress at this location.
    19
    Furthermore, the western Sumneytown Pike
    driveway is too close to the Intersection to permit access
    therefrom, and therefore should be right-in only. This is
    because the peak-hour (both AM and PM) queue of the
    eastbound traffic in the through-lanes on Sumneytown
    Pike is in excess of 600 feet, well beyond the position of
    the western Sumneytown Pike driveway right-out egress.
    Additionally, the PM peak-hour queue of the eastbound
    traffic in the left-turn-lane is approximately 360 feet,
    which also appears to be beyond the position of the
    western Sumneytown Pike driveway right-out egress.
    This becomes of particular concern during the weekday
    PM peak-hour because the West Point Pike left-turn
    egress is proposed to be prohibited between 4:00 pm and
    6:00 pm, likely increasing the traffic attempting to use the
    Sumneytown Pike driveway egress (to go east or west on
    Sumneytown Pike). Furthermore, it is difficult to prohibit
    drivers using the proposed Sumneytown Pike egress from
    attempting to cross multiple lanes of traffic on eastbound
    Sumneytown Pike to reach the eastbound left-turn lane in
    order to turn onto northbound Church Road, which
    maneuver is accompanied by a significant probability of a
    broadside collision with traffic traveling in the center
    through-lane. There appears to be no point along
    Sumneytown Pike where there is acceptable SSSD for
    egress at a location that is also far enough removed from
    the queues of the eastbound approach of Sumneytown
    Pike’s intersection with West Point Pike, and therefore, all
    proposed points of egress from the site onto Sumneytown
    Pike must be eliminated. (See PennDOT Publication No.
    282; Highway Occupancy Permit Operations Manual,
    Section 3.4, p 122; 67 Pa. Code §441.8(h)(2)(iv);
    PennDOT Publication Access Management – Model
    Ordinances for Pennsylvania Municipalities Handbook,
    pp. 7-8, PennDOT Policies and Procedures for
    Transportation Impact Studies, Appendix G., p. 2).
    Comm’rs’ Op., ¶11 (emphasis in text added, emphasis in citations in original).
    In short, the Commissioners determined in Paragraph 11 that
    Developer’s proposed western driveway on Sumneytown Pike, which would
    20
    provide right-turn-in ingress and right-turn-out egress,10 failed to meet the
    minimum SSSD for egress to Sumneytown Pike as determined pursuant to the
    formula/equation set forth in 67 Pa. Code §441.8(h)(2)(iv). At the Commissioners’
    November 2017 meeting, Township’s Traffic Engineer commented that
    Developer’s application did not provide for safe egress from the site to
    Sumneytown Pike. See Comm’rs Meeting, 11/20/17, Tr. (C.M.T.) at 87; R.R. at
    2050a. Township’s Traffic Engineer explained the difference between SSSD,
    which is based on an analysis of several factors including the actual speed of the
    vehicles and road conditions, and the “desired stopping distance,” which is
    primarily based on the posted speed limit. C.M.T. at 92; R.R. at 2055a. Citing
    PennDOT regulations at 67 Pa. Code §441.8(h)(2)(iv), Township’s Traffic
    Engineer indicated that the SSSD calculation is the absolute minimum sight
    distance acceptable for driveways. C.M.T. at 93; R.R. at 2056a.
    Here, Developer’s traffic engineer, Matthew Hammond, P.E., of
    Traffic Planning and Design, Inc. (Developer’s Traffic Engineer), calculated the
    minimum SSSD for the western driveway on Sumneytown Pike at 351 feet.
    Comm’rs Op., ¶11. Township’s Traffic Engineer calculated the SSSD for the
    western driveway at 363 feet.11 
    Id. 10 A
    second driveway on Sumneytown Pike, located approximately 200 feet from the
    intersection with West Point Pike would be right-turn-in only. See Township’s Traffic
    Engineer’s Traffic Review, 1/6/17 (Township Traffic Review), at 1; Reproduced Record (R.R.) at
    983a.
    11
    Township’s Traffic Engineer calculated the SSSD for the western driveway on
    Sumneytown Pike for a vehicle traveling at 43 miles per hour (mph) at 351 feet. See Township
    Traffic Review at 5; R.R. at 987a. For a vehicle traveling at 44 mph, the SSSD would be 363
    feet. 
    Id. 21 However,
    Township’s Traffic Engineer calculated the available sight
    distance from the western driveway at 265 feet. Township Traffic Review at 3;
    R.R. at 985a. Merck’s Traffic Engineer calculated the available sight distance
    from the western driveway at 281.5 feet (at best 282 feet). See Century Eng’g
    Inc.’s Transp. Impact Study Review at 3; R.R. at 1020a. Moreover, Developer’s
    Traffic Engineer calculated the available sight distance from the western driveway
    at 305 feet. See C.M.T. at 92, 129; R.R. at 2055a, 2092a. Consequently, we
    discern no error in the Commissioners’ determination that Developer’s second
    application failed to meet the minimum SSSD requirements for safe egress from
    anywhere on the site to eastbound Sumneytown Pike.
    Further, although the Commissioners rejected Developer’s contention
    that the desired sight distance (based on the posted speed limit of 35 miles per
    hour) would be only 300 feet, the Commissioners nevertheless noted Township’s
    Traffic Engineer and Merck’s Traffic Engineer calculated the available sight
    distance from the western driveway at less than 300 feet. Comm’rs Op., ¶11.
    In addition to failing to meet SSSD requirements, the Commissioners
    also observed that the western driveway on Sumneytown Pike should be only
    “right-turn-in” (no right-turn-out) because peak-hour eastbound traffic, both A.M.
    and P.M., on Sumneytown Pike in the through-lanes would queue-up in excess of
    600 feet, well beyond the “right-turn-out” egress from the western driveway.
    Comm’rs Op., ¶11. This determination is also supported by the record. See
    Township Traffic Review at 6, R.R. at 988a.
    22
    For these reasons, the Commissioners concluded there appeared to be
    no point along Sumneytown Pike where there would be acceptable SSSD for
    egress at a location that is far enough removed from the queues of the eastbound
    approach of Sumneytown Pike’s intersection with West Point Pike.             The
    Commissioners thus concluded that “all proposed points of egress from the site
    onto Sumneytown Pike must be eliminated.” Comm’rs Op., ¶11 (emphasis added).
    Based on our careful review of the record, we hold that Paragraph 11
    of the Commissioners’ decision, by itself, is legally sufficient to support the
    Commissioners’ denial of Developer’s second application. Kassouf; Robal. In
    Paragraph 11, the Commissioners specified the defects in Developer’s planned
    egress onto Sumneytown Pike.
    Although Developer took the position that PennDOT’s SSSD
    requirements do not apply to Sumneytown Pike, the Commissioners properly
    interpreted Section 6109(a) of the Vehicle Code and Sections 168-16.B and 168-
    17.H of the Township’s SALDO as requiring Developer to comply with PennDOT
    SSSD specifications for driveway design. We note Sumneytown Pike and West
    Point Pike, even if not state highways, are heavily traveled roads with multiple
    lanes in each direction. As Township’s Traffic Engineer explained, in addition to
    the inadequate available sight distance, the eastbound traffic on Sumneytown Pike
    queues up in both the through-lanes and left-turn-lane during peak–hour traffic
    beyond Developer’s proposed western driveway.
    23
    Consequently, the Commissioners’ reasons for their ultimate
    determination in Paragraph 11, that Developer’s proposed points of egress from the
    site onto Sumneytown Pike must be eliminated, are supported by substantial
    evidence and are in accord with the applicable law. Thus, the Commissioners
    properly denied Developer’s second application on this basis alone. Section 508(2)
    of the MPC; Kassouf; Robal.
    D. Commissioners’ Remaining Reasons for Denying Second Application
    Developer raises several other challenges to the Commissioners’
    specified reasons for denial of Developer’s second application.12 However, having
    determined the Commissioners properly denied Developer’s second application
    because egress from any point on the site to Sumneytown Pike is unacceptable, we
    need not address Developer’s challenges to the Commissioners’ remaining reasons
    for denying the plan. Kassouf; Robal.
    12
    In addition to other traffic design deficiencies, Developer asserts the Commissioners
    erred or abused their discretion in refusing Developer’s request for a waiver or modification from
    Section 163-19.J of the Township’s Stormwater Management Ordinance for the Wissahickon
    Creek Watershed. Developer also alleges the Commissioners erred or abused their discretion in
    basing their denial on stormwater management reasons never identified in any Township review.
    Developer argues the alleged deficiencies in the design of a stormwater management system are
    minor technical defects that can be corrected by amending the plan and thus cannot serve as the
    basis for the denial of a preliminary plan. See CACO Three v. Bd. of Supervisors of Huntington
    Twp., 
    845 A.2d 991
    (Pa. Cmwlth. 2004) (minor defects such as failure to include labels,
    notations and design calculations in a preliminary plan are not objective defects justifying
    outright disapproval of the plan; rather, they are minor technical defects that could be corrected
    by amending the plan).
    Developer further contends the Commissioners erred or abused their discretion in
    denying its second application based on other minor, easily correctable items. Developer cites
    the reasons stated in Paragraphs 1-6 of the Commissioners’ decision.
    24
    E. Right of Cross-Examination
    1. Argument
    In its final argument, Developer contends the Commissioners violated
    its due process rights by refusing to allow the cross-examination of witnesses upon
    whom the Commissioners relied in denying the second application. Developer
    asserts that a fair trial in a fair tribunal is a basic requirement of due process. In re:
    Murchison, 
    349 U.S. 133
    (1925). Citing DeJohn v. Orell, 
    240 A.2d 472
    (Pa. 1968),
    Developer maintains that when credibility determinations are made, a party has a
    fundamental right to cross-examine a witness.
    Here, Developer asserts the Commissioners’ decision clearly reflects
    that the Commissioners relied on the testimony of witnesses to support a denial of
    the second application. However, the Commissioners refused to let Developer
    cross-examine those witnesses. As a result, Developer claims the Commissioners
    denied it an opportunity to cross-examine the Township’s Traffic Engineer or the
    engineers who spoke on Merck’s behalf. Developer maintains this constituted
    reversible error. Downey v. Weston, 
    301 A.2d 635
    (Pa. 1973).
    2. Analysis
    As we observed in Miravich v. Township of Exeter, 
    6 A.3d 1076
    ,
    1079 (Pa. Cmwlth. 2010), unlike proceedings before a zoning hearing board, the
    MPC places virtually no procedural requirements on a governing body’s
    consideration of subdivision and land development proposals. To that end, Section
    508(5) of the MPC, provides: “Before acting on any subdivision plat, the
    governing body or the planning agency, may hold a public hearing thereon after
    25
    public notice.” 53 P.S. §10508(5) (emphasis added). In other words, public
    hearings are not required. Whitehall Manor, Inc. v. Planning Comm’n of the City
    of Allentown, 
    79 A.3d 720
    (Pa. Cmwlth. 2013); Miravich. Because Section 508(5)
    of the MPC does not require a public hearing on land development applications,
    we cannot interpret that provision as permitting a right of cross-examination of
    witnesses at a public meeting of the Commissioners. Whitehall Manor; Miravich.
    Notably, both the terms, “public hearing” and “public meeting,” are separately
    defined and thereby distinguished in the MPC. See Section 107 of the MPC, 53
    P.S. §10107.
    Moreover, our review of the record does not indicate Developer
    requested a public hearing on its application here. As such, the Commissioners
    only considered Developer’s second application at a public meeting held on
    November 20, 2017.        Consequently, there was no sworn testimony.          At the
    November 2017 meeting, the Township’s solicitor explained to counsel that the
    meeting was not a hearing. See C.M.T. at 55; R.R. at 2018a. Developer’s counsel
    replied: “I agree.” 
    Id. Further, Developer
    cites no case law or decisional authority indicating
    there is a right of cross-examination at a public meeting on a land development
    application under the MPC. Consequently, we reject Developer’s contention that
    the Commissioners violated its due process rights based on the denial of a non-
    existent right to cross-examination. Whitehall Manor; Miravich.
    26
    IV. Conclusion
    For the above reasons, we discern no error or abuse of discretion in
    the   Commissioners’    decision     denying   Developer’s   second   application.
    Accordingly, we affirm the order of the trial court based on the alternate grounds
    stated herein.
    ROBERT SIMPSON, Judge
    27
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    In Re: Appeal of Provco Pinegood     :
    Sumneytown, LLC From The             :
    Decision Dated December 4, 2017      :
    of The Board of Commissioners of     :   No. 1554 C.D. 2018
    Upper Gwynedd Township               :
    :
    Appeal of: Provco Pinegood           :
    Sumneytown, LLC                      :
    ORDER
    AND NOW, this 29th day of July 2019, for the reasons stated in the
    foregoing opinion, the order of the Court of Common Pleas of Montgomery
    County is AFFIRMED.
    ROBERT SIMPSON, Judge