Wyeth Pharmaceuticals v. Borough of West Chester and Pfizer Inc. ( 2015 )


Menu:
  •          IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Wyeth Pharmaceuticals, Inc., a          :
    Delaware Corporation, successor         :
    to Wyeth Laboratories Inc., a           :
    New York Corporation,                   :
    Appellant              :
    :
    v.                       :   No. 2116 C.D. 2014
    :   Argued: October 5, 2015
    Borough of West Chester and             :
    Pfizer Inc.                             :
    BEFORE:        HONORABLE BERNARD L. McGINLEY, Judge
    HONORABLE MARY HANNAH LEAVITT, Judge
    HONORABLE ROCHELLE S. FRIEDMAN, Senior Judge
    OPINION
    BY JUDGE LEAVITT                                        FILED: November 5, 2015
    Wyeth Pharmaceuticals, Inc. appeals an order of the Court of
    Common Pleas of Chester County that denied its request for a declaratory
    judgment that its contract with the Borough of West Chester had terminated and
    denied its request for a refund of invoices it had paid after the contract’s
    termination.        Instead, the trial court granted the Borough of West Chester
    $1,719,235.27 on its counter-claim for breach of contract. For the reasons set forth
    below, we reverse and remand.
    Background
    This case concerns a contract between Wyeth and the Borough of
    West Chester relating to the reconstruction of a Borough wastewater treatment
    plant known as the Goose Creek Plant.            In the 1970’s, the Pennsylvania
    Department of Environmental Resources ordered the Borough to rebuild the Goose
    Creek Plant because it had been repeatedly cited for exceeding its discharge limits.
    At the time, Wyeth, which began operating a penicillin manufacturing facility in
    the Borough in the 1950’s, was one of the largest industrial dischargers of
    wastewater in the Borough. The Borough obtained the agreement of Wyeth and
    two other industrial dischargers to share in the costs of the upgrade to the Goose
    Creek Plant. The terms of the agreement between Wyeth and the Borough were set
    forth in a written contract (Agreement) that was executed on July 31, 1984.
    Under the Agreement, Wyeth promised to contribute both to the
    capital costs of upgrading the Goose Creek Plant and to its operational and
    maintenance expenses. The Agreement recited the following:
    Significant portions of the Costs of the Project ... are
    attributable to equipment and facilities necessary to treat the
    companies’ Sewage. Therefore, the companies should pay their
    share of the principal and interest on money borrowed to
    finance the Costs of the Project, including costs and expenses of
    financing, and the companies should also pay their share of the
    annual Operating and Maintenance Expenses attributable to
    the treatment of the companies’ waste.
    Agreement, “Background of Agreement,” at 2 (hereinafter “Background Clause”);
    Reproduced Record at 985a (R.R. ___) (emphasis added).1 A 1976 letter from
    Wyeth’s Vice President to the Borough Solicitor explained that “[t]he intended
    period of use of the treatment facilities by Wyeth Laboratories Inc. shall be for the
    life of the treatment works or as long as Wyeth Laboratories shall remain in the
    Borough of West Chester.” R.R. 1067a.
    1
    “Companies” refers to the three industrial dischargers that executed a similar agreement. At
    least one, Sartomer, which is a specialty chemical company, continues to operate in the Borough.
    2
    Under the final terms, Wyeth agreed to cover 49.2% of the capital
    costs of upgrading the Goose Creek Plant and 49.2% of the plant’s Operational and
    Maintenance Expenses.2 Agreement, ¶¶4, 8; R.R. 995a, 998a. The Agreement
    divided the Operational and Maintenance Expenses into two categories: variable
    costs and fixed costs. Variable costs were based upon Wyeth’s volume and type of
    wastewater and included such items as treatment chemicals and electricity. Fixed
    costs fell into seven categories: (1) labor (including benefits), (2) administration,
    (3) telephone, (4) electric, (5) fuel, (6) materials and supplies and (7) maintenance
    and repair. 
    Id. Wyeth discharged
    wastewater into the reconstructed Goose Creek
    Plant from 1988 until the mid-2000s. In 2004, Wyeth ceased all operations at its
    West Chester pharmaceutical facility, and, by February 2005, had completely
    decommissioned the site. It has not discharged wastewater since then. In 2006,
    Wyeth razed all structures at its West Chester facility, abandoned its sewer
    connection and has not used the property since. Attempts to sell the property have
    failed, and it remains undeveloped.
    In 1997, Wyeth completed the payment of the capital costs required
    under the Agreement. When Wyeth stopped using the Goose Creek Plant, the
    Borough stopped sending it invoices for variable costs. The Borough agrees that
    Wyeth has fully discharged its contractual obligations for the capital costs and
    variable costs. The parties disagree on Wyeth’s continuing liability for the fixed
    2
    Wyeth’s share was calculated based on projected waste flows and characteristics at the time the
    contract was executed, as set forth in Schedule A to the Agreement. The Agreement originally
    assigned a 51.1% share to Wyeth, and was amended in May 1985 to reduce the share to 49.2%.
    R.R. 1005a; R.R. 1015a.
    3
    costs portion of the Operational and Maintenance Expenses of the plant as
    provided in the Agreement.
    Although Wyeth has not used the Goose Creek Plant since 2005, the
    Borough’s invoices to Wyeth for fixed costs have steadily increased, as shown by
    the following table:
    Year                Total Charge to Wyeth
    2005                      $572,858
    2006                      $657,119
    2007                      $665,751
    2008                      $705,328
    2009                      $733,944
    2010                      $779,783
    2011                      $808,135
    2012                      $837,055
    2013 (3 quarters)               $592,319
    Wyeth Brief at 10; R.R. 1532a-1664a; R.R. 2113a-2122a.         Wyeth paid these
    invoices through 2011. On December 8, 2011, Wyeth gave notice to the Borough
    “of our intent to cease paying the fixed costs of Operating and Maintenance
    Expenses or any other expenses of the [Goose Creek Plant] and to terminate the
    Agreement.” R.R. 1109a. Wyeth did not pay the Borough’s invoices for 2012 and
    2013.
    On April 11, 2012, Wyeth filed a lawsuit against the Borough of West
    Chester. It sought a declaratory judgment that the Agreement terminated in 2006
    when it severed the sewage connection or, in the alternative, 2011, when it
    formally notified the Borough of the termination. The complaint also sought a
    refund of all fixed costs Wyeth has paid since 2006. Alternatively, it sought a
    recomputation of the fixed cost invoices to delete those charges that, in Wyeth’s
    4
    view, exceeded what was required to operate and maintain the Goose Creek Plant,
    assuming the Agreement had continued in force after 2006.
    The Borough counterclaimed, seeking a declaratory judgment that the
    Agreement remained in effect, that its charges for fixed costs were properly
    computed and that Wyeth was liable for the unpaid 2012 and 2013 invoices. The
    Borough sought monthly interest of 1½% on the unpaid invoices under authority of
    its local sewer ordinance. WEST CHESTER BOROUGH CODE (App. E) §89-12(B).3
    3
    It states, in relevant part, as follows:
    All sewer rents not paid within 21 days of the date of the bill shall be deemed to
    be delinquent and shall be subject to a penalty of 1½% per month. All delinquent
    sewer rents, together with interest, penalties, charges and costs thereof, shall
    constitute a municipal claim against the property or properties served by the sewer
    service from the date the same first became due and payable. If such sewer rents,
    penalties and charges are not timely paid, the Borough shall file a municipal lien
    against the property served pursuant to the procedure established in the
    Pennsylvania Municipal Lien Law and in §89-14 herein, and such lien shall be
    collected in the manner provided for by law for the filing and collecting of such
    municipal liens. The Borough is further authorized to collect reasonable
    attorneys’ fees that it incurs in the collection of any delinquent sewer accounts in
    the amount specified in §89-14 herein. In addition, the Borough may collect all
    delinquent sewer rents, penalties, interest and charges, including attorneys’ fees,
    by referring such delinquent claims to a collection agency, by filing an action in
    assumpsit, or in any other manner or by any proceeding otherwise provided by
    law. Any fees that the Borough incurs in exercising its legal remedies shall be
    added to the amount of the delinquent account. All of the Borough’s remedies
    shall be cumulative.
    WEST CHESTER BOROUGH CODE (App. E) §89-12(B) (emphasis added).
    When Wyeth stopped paying the fixed cost invoices, the Borough issued past-due notices
    stating that under “the sewer agreement between the Borough and [Wyeth], along with the
    Borough’s sewer ordinance, any invoice not paid within thirty days, will be subject to a penalty
    of 1.5%.” R.R. 2119a. Wyeth notes that Paragraph 10 of the Agreement provides that the
    Borough will not apply a penalty where Wyeth “makes a timely request for further information
    or clarification ....” Agreement, ¶10.
    5
    At the bench trial, Wyeth produced evidence that the Borough’s
    yearly invoices for fixed costs have been roughly equivalent to the amounts the
    Borough’s Sewer Department has transferred each year to the Borough’s General
    Fund. It also produced a 2012 document prepared by the Borough Manager stating
    that should the Borough sell its sewer system, it would need a profit of $20 million
    because the Sewer Department transfers $800,000 per annum to the General Fund.
    R.R. 1862a.     The Borough apportioned the “administration” charges equally
    between the Goose Creek Plant and the Borough’s other plant, the Taylor Run
    Plant, without regard to the actual Borough services provided to either plant.
    Wyeth’s evidence showed that included in the “administration” portion of the fixed
    cost invoices were expenses as varied as fueling vehicles in the police department
    and funding a new HVAC system for the municipal building, neither of which had
    anything to do with operating and maintaining the Goose Creek Plant. Wyeth also
    showed that the Borough’s fixed cost invoices included charges for labor
    associated with pumping stations that did not serve the Goose Creek Plant.
    Finally, Wyeth presented evidence that the Borough overstaffed the Goose Creek
    Plant.
    The Borough responded with expert testimony that the upgrade to the
    Goose Creek Plant was required in order to treat Wyeth’s waste. This included the
    purchase of equipment that must be maintained regardless of whether Wyeth
    continues to discharge waste. The Borough also presented evidence that the fixed
    cost invoices sent to Wyeth had been calculated in the same manner since the late
    1980s. Thus, for two decades Wyeth had agreed that the Borough’s methodology
    was consistent with the Agreement. The Borough explained that the transfers from
    the Sewer Department to the General Fund covered the cost of services provided to
    6
    the Sewer Department by other Borough departments and were calculated in
    accordance with generally accepted accounting principles. The Borough sought
    breach of contract damages equal to the amount of the unpaid invoices plus
    interest.
    On July 14, 2014, the trial court entered an order that found against
    Wyeth on all claims, and found in the Borough’s favor on its counterclaim for
    damages.4 The trial court awarded the Borough $1,719,235.27 in damages plus
    “interest at the legal rate.” Trial Court Order at 2. Wyeth filed a post-trial motion,
    which the trial court denied. On November 19, 2014, Wyeth appealed.
    In response to Wyeth’s Rule 1925(b) statement, the trial court filed a
    Rule 1925(a) opinion. The opinion concluded that Wyeth did not establish that the
    Agreement had terminated as of the date of trial. The trial court acknowledged
    “that some of the Borough’s charges were not support[ed] by the contract” and,
    thus, reduced the Borough’s claim for damages. Trial Court §1925(a) op. at 9.
    However, the trial court declined to specify the amount of the overcharge or to
    provide a breakdown of its damage award and basis for pre-judgment interest,
    concluding that the issue was waived by Wyeth. Nevertheless, the trial court
    explained that the evidence supported “an intelligent estimation” of the Borough’s
    damages and that the Borough “was entitled to pre-judgment interest as a matter of
    law.” Trial Court §1925(a) op. at 10.
    4
    The trial court denied the Borough’s request for damages for future unpaid invoices as “too
    speculative.” Trial Court Order at 2 n.2. However, the trial court held open the possibility of
    such an award in the future, stating:
    If it becomes clear that these payments will not be made and that quarterly
    litigation will be required, the time may come when .... the future damages as the
    Borough seeks in this litigation will become proper and appropriate.
    
    Id. 7 Issues
    on Appeal
    On appeal, Wyeth seeks a reversal of the trial court’s order and entry
    of judgment in Wyeth’s favor. It raises three issues.5
    First, Wyeth contends that the trial court erred because the
    Background Clause of the Agreement supports a termination in 2006, when Wyeth
    abandoned its sewer connection to the Goose Creek Plant.                       If not, then the
    Agreement was a contract of indefinite duration and, as such, terminable at will by
    either party. Wyeth’s notice of termination to the Borough on December 8, 2011,
    ended the Agreement.
    Second, Wyeth contends that the trial court erred because the Borough
    breached the Agreement and was unjustly enriched when it collected hundreds of
    thousands of dollars in charges from Wyeth that were not authorized by the
    Agreement or required to operate and maintain the Goose Creek Plant.
    Third, the trial court erred in awarding damages to the Borough
    because the Agreement did not authorize the Borough’s overcharges, let alone the
    interest award. Additionally, the trial court erred because the Borough’s sewer
    ordinance did not authorize an award of interest or penalty, assuming Wyeth’s
    payments of the fixed cost invoices were not timely.
    5
    The trial court’s findings of fact are entitled to deference, so long as they are supported by the
    evidence of record. In re Condemnation by Urban Redevelopment Authority of Pittsburgh, 
    913 A.2d 178
    , 183 (Pa. 2004). Construction of a contract or ordinance is a question of law subject to
    a de novo standard of review on appeal. McMullen v. Kutz, 
    985 A.2d 769
    , 773 (Pa. 2009). On
    questions of law, this Court’s scope of review is plenary. Hospital & Healthsystem Association
    of Pennsylvania v. Department of Public Welfare, 
    888 A.2d 601
    , 607 n.12 (Pa. 2005).
    8
    I. Duration of the Agreement
    In its first, and central, issue, Wyeth argues that it has satisfied all of
    its contractual obligations under the Agreement and, thus, the Agreement has
    terminated. The Agreement obligated Wyeth to pay a share of the upgrade costs as
    well as its share of “the annual Operating and Maintenance Expenses attributable
    to the treatment of [Wyeth’s] waste.” R.R. 985a (emphasis added). Once Wyeth
    paid for the capital costs and stopped producing waste, its obligations under the
    Agreement ceased. Recognizing that the Agreement does not contain an express
    termination provision or a duration clause, Wyeth argues that it is terminable at
    will by either party in accordance with common law contract principles. Finally, it
    contends that even assuming, arguendo, that there is a question about whether the
    Agreement extended beyond the point where Wyeth no longer produced waste,
    evidence contemporaneous with the execution of the Agreement clarifies that it
    would end when Wyeth closed its facility.
    The Borough responds that the Agreement obligated Wyeth to pay the
    fixed costs portion of Operating and Maintenance Expenses indefinitely.              In
    support it cites Paragraph 9, which states:
    In no event, however, shall Company be charged and pay less
    than its share of the fixed costs of the Operating and
    Maintenance expenses as described in paragraph 8.
    R.R. 998a (emphasis added). The Borough argues that Paragraph 9 carries far
    more weight than the Background Clause cited by Wyeth. The Borough also finds
    support for the perpetual nature of the Agreement in Paragraph 19, which states:
    This Agreement shall be binding upon the parties hereto and
    their respective successors and assigns.        Covenants and
    agreements contained in this Agreement on behalf of Company
    shall constitute and shall be construed as covenants which shall
    9
    attach to, run with and burden the land of Company upon which
    the Company Plant is located ....
    R.R. 1003a. Because the Agreement must be construed as running with the land, it
    has no durational limit.         Indeed, Wyeth remained liable for its contractual
    obligations notwithstanding its “conveyance of all or part of the land of Company
    upon which Company’s Plant is located ....” Agreement, ¶19; R.R. 1004a.
    We address the contract construction arguments ad seriatim.
    a. Language in Background Clause and Paragraph 9
    To begin, we reject the Borough’s argument that the preamble to the
    Agreement is irrelevant.6 A contractual preamble can be a “reliable indicator of
    intentions of the parties.” Mercy Health System of S.E. Pa. v. Metro. Partners
    Realty LLC, No. 3046 Nov. Term 2001, 
    2005 WL 957722
    , at *5 (Phila. Ct. Com.
    Pl. Mar. 6, 2005) (emphasis added) (citing Pritchard v. Wick, 
    178 A.2d 725
    (Pa.
    1962)). A background recital may not contradict a substantive provision of the
    contract, but it nevertheless “will be looked to in construing the contract.” Cain
    Rest. Corp. v. Carrols Corp., 273 F. App’x 430, 434 (6th Cir. 2008). In Pritchard,
    our Supreme Court expressly relied upon a recital clause to ascertain the
    circumstances under which one party to an option contract was permitted to
    exercise the option. 
    Pritchard, 178 A.2d at 728
    . In sum, the Background Clause is
    relevant to the meaning of the substantive provisions of the Agreement.
    We also agree with Wyeth that the recording of the Agreement is not
    dispositive of the Agreement’s duration. The purpose of the recording was to give
    constructive notice of the Agreement to prospective purchasers of Wyeth’s land
    6
    The trial court did not find the Background Clause irrelevant. Rather, it held that because the
    Agreement was recorded, it had a duration “in perpetuity.” Trial Court §1925(a) op. at 4.
    10
    and facility in the Borough. See Act of April 24, 1931, P.L. 48, 21 P.S. §357.7 As
    Wyeth points out, a 30-year mortgage lien is recorded, but it expires after 30 years.
    The recording does not extend the duration of the lien. The recording of the
    Agreement did mean that Wyeth’s sale of its penicillin plant would not terminate
    its outstanding contractual obligations under the Agreement, but the sale of the
    property never took place.
    Paragraph 8 of the Agreement sets up Wyeth’s “share of Operational
    and Maintenance Expenses,” detailing the components of variable costs and fixed
    costs. R.R. 998a. Paragraph 9 then states that “[i]n no event, however, shall
    [Wyeth] be charged and pay less than its share of the fixed costs of the Operating
    and Maintenance Expenses as described in paragraph 8.”                     Id.; Agreement, ¶9
    (emphasis added). Wyeth argues that Paragraph 9 simply emphasizes that fixed
    costs and variable costs must be calculated independently of one another. On the
    other hand, Paragraph 9 can also be read, as argued by the Borough, to mean that
    Wyeth must pay fixed costs even when it has no obligation for variable costs. The
    question is whether Paragraph 9 and the Background Clause conflict with each
    other or can be read together.
    7
    The statutory provision states:
    Constructive notice as result of recordation.
    The legal effect of the recording of such agreements shall be to give constructive
    notice to subsequent purchasers, mortgagees, and/or judgment creditors of the
    parties to said agreements of the fact of the granting of such rights or privileges
    and/or of the execution of said releases, and the rights of the subsequent
    purchasers, mortgagees, and/or judgment creditors of the parties to said
    agreements shall be limited thereby with the same force and effect as if said
    subsequent purchasers, mortgagees, and/or judgment creditors had actually joined
    in the execution of the agreement or agreements aforesaid.
    21 P.S. §357.
    11
    The Background Clause explains that the Agreement’s purpose is to
    require Wyeth to pay “its share” of Operating and Maintenance Expenses
    “attributable to the treatment of [Wyeth’s] waste.”        This clause can be read
    harmoniously with Paragraph 9’s statement that “in no event” would Wyeth pay
    less than “its share” of the fixed costs. The “share” refers to the fixed costs
    attributable to the treatment of Wyeth’s waste, as stated in the Background Clause.
    If Wyeth should shut down its plant for a month while it retrofitted the plant’s
    equipment, for example, it would not have to pay variable costs during that month
    but would continue to pay fixed cost invoices. However, once Wyeth lost the
    ability ever again to discharge waste water, its “share” of expenses ceased to exist.
    Giving the benefit of the doubt to the Borough, Wyeth could continue
    to have a “share” if the expenses of operating and maintaining the Goose Creek
    Plant could be attributed to the maintenance of specialized equipment that was
    installed solely to treat Wyeth’s wastewater. Maintenance would be necessary
    whether or not Wyeth was still using that specialized equipment. However, this
    was not proven by the Borough.
    The Borough’s solicitor at the time, Ross Unruh, testified that “there
    would be certain fixed O&M costs which would be there regardless of whether
    Wyeth Laborator[ies’] manufacturing was still there.” R.R. 481a. This states the
    obvious because the Goose Creek Plant treats waste generated by 10,000
    individuals in two municipalities, two industrial users, numerous businesses, a
    private septic hauler and West Chester University. R.R. 236a, 237a, 277a and
    1683a.    The Borough did not offer evidence that it incurred any expenses
    attributable to equipment purchased for the specific purpose of treating Wyeth’s
    waste. Indeed, Borough Manager Ernie McNeely and Borough CFO Douglas
    12
    Kapp acknowledged that the Borough does not know “how much more [the Goose
    Creek Plant] cost[s] to operate than a plant that was not designed to handle
    industrial discharges from Wyeth.” R.R. at 4061a. They also acknowledged that
    the Borough does not have “an order of magnitude on” the allegedly heightened
    costs of treating Wyeth’s waste. 
    Id. at 4062a.
    Finally, they acknowledged that the
    Borough does not “know one way or the other whether the Goose Creek plant is
    more expensive to operate today than it would have been if it had been built
    without having Wyeth in mind as a discharger.” R.R. 1937a.
    Borough Wastewater Director Kevin Oakes confirmed that whether
    the Goose Creek Plant costs more to operate as a result of Wyeth’s historical need
    for wastewater treatment “depends on who’s running it.” R.R. 1919a. He declined
    to quantify any cost differential because doing so would be “hypothetical.” R.R.
    1920a.   The Borough took the position in post-trial briefing that the “Actual
    Difference in Costs to Run the Plant Is Irrelevant.” R.R. 4190a.
    Wyeth, on the other hand, presented evidence that the Goose Creek
    Plant uses industry-standard treatment technology, R.R. 345a; that “[a]ll the unit
    processes [at the Goose Creek Plant] are conventional,” R.R. 347a; and that “the
    Fixed Costs [of the Goose Creek Plant] are the same” as the Borough’s other plant,
    the Taylor Run Plant, which has equivalent capacity as the Goose Creek Plant and
    does not serve any industrial users. R.R. 286a, 1678a.
    In sum, the Background Clause and Paragraph 9 can be read together.
    They do not conflict. They establish that Wyeth must pay its share of Operational
    and Maintenance Expenses attributable to the treatment of Wyeth’s waste. Had the
    Goose Creek Plant required larger, more or specialized equipment to treat Wyeth’s
    wastewater, the Borough theoretically would continue to incur expenses to
    13
    maintain that equipment without regard to whether Wyeth continued to generate
    wastewater. However, the evidence showed the contrary.
    b. Absence of Duration Clause
    The trial court concluded that the Agreement was perpetual. The
    Borough argues that this was correct because the Agreement does not have a stated
    duration. Further, the “in no event” clause in Paragraph 9 supports a perpetual
    duration. Borough Brief at 30. Wyeth responds that contracts without a stated
    duration will be “construed as providing for a reasonable time or some particular
    period inferred from the nature and circumstances of the undertaking.” Price v.
    Confair, 
    79 A.2d 224
    , 226 (Pa. 1951). The Borough acknowledges this principle
    but argues that it applies only to “services contracts, employment contracts,
    exclusive sales contracts,” and the like. See Borough Brief at 25.
    In general, a contract for an indefinite period will be construed to be
    for a “reasonable time or terminable at will unless the intention of the parties can
    be ascertained.”        Major v. Flock Brewing Co., 
    2 Pa. D. & C. 2d
    . 496, 500
    (Lycoming Ct. Com. Pl. 1954). Pennsylvania law disfavors perpetual contracts
    and, thus, requires a perpetual term to be expressed unequivocally. Hutchison v.
    Sunbeam Coal Co., 
    519 A.2d 385
    , 390 n.5 (Pa. 1986); 
    Leet, 531 A.2d at 21
    .
    Absent this expression, for a court “[t]o infer an intent on the part of the
    contracting parties so drastic and absolute would be unreasonable.” Moravecz v.
    Hillman Coal & Coke Co., 
    141 A.2d 570
    , 572 (Pa. 1958) (rejecting a covenant to
    supply drinking water to an adjacent parcel as creating a perpetual obligation
    because no express provision to that effect appeared in the operative documents). 8
    8
    Wyeth cites the Restatement of Property, which provides as follows:
    (Footnote continued on the next page . . . )
    14
    Price v. Confair, 
    79 A.2d 224
    , is instructive. The case involved a
    written contract between Confair and the Cloverdale Spring Company, dated
    January 17, 1941.          Confair agreed to furnish Pepsi-Cola to seven named
    distributors, one of which was Price. In return, Cloverdale gave up its distribution
    rights in Confair’s territory, making Confair the exclusive bottler and distributor of
    Pepsi-Cola in the Williamsport area. Confair agreed to sell the bottled cola to the
    seven distributors at 60 cents per case. The set retail price was 80 cents per case.
    Confair sold Price 100 cases a week at the set price from January of 1941 through
    July 13, 1945, when it informed Price that it would no longer furnish him bottled
    cola.
    Price sued, contending that because the contract did not specify a
    duration it was for his life. Presuming his life expectancy would be age 80, Price
    claimed he was owed his expected profit of 20 cents per case on 100 cases sold per
    week for 12.11 years.
    (continued . . . )
    A covenant to pay money or provide services in exchange for services or facilities
    provided to the burdened estate may be modified or terminated if the obligation
    becomes excessive in relation to the cost of providing the services or facilities or
    to the value received by the burdened estate; provided, however, that modification
    based on a decrease in value to the burdened estate should take account of any
    investment made by the covenantee in reasonable reliance on continued validity
    of the covenant obligation.
    RESTATEMENT (THIRD) OF PROPERTY (SERVITUDES) §7.12(2) (2000). The comment explains that
    such covenants can be modified where there are not “competitive pressures to keep prices
    reasonable, particularly where the obligation to pay is indefinite in duration or for a long term.”
    
    Id. cmt. a.
    The Borough incurs no costs attributable to Wyeth’s waste yet charges Wyeth over
    $800,000 annually for a service that Wyeth cannot use. That is an example of Wyeth’s costs
    “becom[ing] excessive in relation to the cost of providing the services or facilities” at issue. 
    Id. §7.12(2). 15
                  The Pennsylvania Supreme Court rejected Price’s argument. It held
    that the
    general rule is that when a contract provides that one party shall
    render service to another, or shall act as his agent, or shall have
    exclusive sales rights within certain territory, but does not
    specify a definite time or prescribe conditions which shall
    determine the duration of the relationship, the contract may be
    terminated by either party at will.
    
    Id. at 542
    (emphasis omitted). However, the Court also stated that in some cases,
    the intent of the parties may establish that the contract should be “construed as
    providing for a reasonable time[.]” 
    Id. The Borough
    argues that Price principles apply only to service
    contracts.   The Borough overlooks the fact that the Agreement relates to the
    Borough’s provision of waste treatment services to Wyeth.                       Further, the
    presumption of a reasonable duration is a rule of general applicability and not a
    narrow exception. See, e.g., Nova Chems., Inc. v. Sekisui Plastics Co., 
    579 F.3d 319
    , 326 (3d Cir. 2009) (applying presumption to an intellectual property licensing
    contract).
    The principle that a contract without an express duration clause
    endures for a reasonable period of time or is terminable at will may have been
    established in the context of commercial sales or lease agreements, but the
    principle is not limited to those specific types of contracts. The Borough has not
    identified a single case in which a court found that a contract that called for the
    payment of money from one party to another continued in perpetuity. 9 Rather, the
    9
    The Borough cites Rossmassler v. Spielberger, 
    112 A. 876
    (Pa. 1921), which involved an
    obligation to pay an annual priority dividend out of a corporation’s profits, which the Borough
    characterizes as “presumably continu[ing] in perpetuity.”         See Borough Brief at 25.
    (Footnote continued on the next page . . . )
    16
    law requires that a contract of perpetual duration be provided in an express term,
    which is nowhere to be found in the Agreement.
    c. Extrinsic Evidence
    Although both parties agree that the Agreement is not ambiguous,
    they each presented extrinsic evidence to support their respective interpretations of
    the Agreement. Wyeth argues that the contemporaneous evidence it presented
    supports a 21-year life for the Goose Creek Plant. The Borough argues that its
    extrinsic evidence showed that Wyeth would have to contribute to the operation of
    the Goose Creek Plant even if it had no wastewater that required the plant’s
    services.
    The 1975 Wastewater Treatment Facilities Plan prepared for the
    Borough stated that “the planning period [for the upgraded Goose Creek and
    Taylor Run Plants] should extend 20-years beyond the estimated date of initial
    system operation.” R.R. 1059a. The plan also stated that “[t]he Borough would
    like to upgrade their present Goose Creek [Plant] to handle existing and future
    flows to the year 2000.” R.R. 1064a. As recently as 2007, an internal sewer rate
    study commissioned by the Borough acknowledged that “[t]he largest industrial
    user’s agreement runs out in 2007.” R.R. 1136a. Wyeth is that industrial user.
    In 1976, Wyeth’s Vice President Larry Hewlett informed the Borough
    that Wyeth expected the Agreement to last “for the life of the treatment works or as
    (continued . . . )
    Rossmassler, however, expressly limited its holding to the duration of the corporation’s existence
    and acknowledged that the obligation would terminate if the corporation was 
    dissolved. 112 A. at 880
    . The Pennsylvania Supreme Court has itself described Rossmassler as endorsing the
    proposition that “contracts which do not fix a definite time for the duration of the relationship
    which they create are sometimes construed as providing for a reasonable time or some particular
    period inferred from the nature and circumstances of the undertaking.” 
    Price, 79 A.2d at 226
    .
    17
    long as Wyeth Laboratories shall remain in the Borough of West Chester.” R.R.
    1067a.    John Alivernini, who represented Wyeth in negotiations over the
    Agreement, testified that, “[a]t the outside, it was my understanding the Agreement
    would end in about 20 years, at the end of the life or the design life of the
    wastewater plant.” R.R. 192.
    Wyeth’s understanding of the life of the plant was shared by the
    Borough. In 1979, the Borough’s solicitor, Ross Unruh, wrote to Wyeth engineer
    Robert Herion requesting that Wyeth provide an estimated “maximum discharge to
    the Goose Creek wastewater facility during the design life of the facility,” which
    he represented to be “twenty-one years after start-up.” R.R. 1069a. At trial, Unruh
    acknowledged that he made that representation to Wyeth as the Borough’s official
    position of the Goose Creek Plant’s life. R.R. 491a-492a.
    The Borough rejoins that Unruh informed Wyeth that the Borough did
    not want to get saddled with the costs of operating the Goose Creek Plant, which
    was designed and constructed to accommodate Wyeth’s wastewater needs. R.R.
    477a. The protections for the Borough were memorialized in Paragraphs 8, 9, 17
    and 19 of the Agreement. The Agreement was recorded so that there would be no
    dispute as to Wyeth’s ongoing obligations.
    The Borough also argues that Unruh’s testimony is supported by
    documentary evidence. Unruh’s August 8, 1980, letter to Mr. Harold Loughhead
    of Wyeth included a provision entitled “Minimum charge for availability of
    treatment whether or not industry is using system.” R.R. 481a. At trial, Unruh
    was asked why that language was included in his letter to Wyeth:
    Q. And why is that language included in your outline, sir?
    A. Because that was a significant point with the Borough of
    West Chester. There was a concern that if this plant was
    18
    designed for Wyeth, who would be the major user, not
    only in terms of quantity but quality of waste, that there
    would be certain fixed O&M costs which would be there
    regardless of whether Wyeth Laboratory’s manufacturing
    was still there. So the concern raised by the engineers was
    to protect the Borough so they wouldn’t be holding the bag
    in terms of a monthly/yearly costs, that Wyeth would have
    to agree that they would pay certain fixed costs whether
    they were operating their facility or not.
    R.R. 481a (emphasis added). Unruh went on to explain that the Borough was
    concerned that Wyeth would seek to avoid its obligations under the Agreement by
    selling the facility.
    Wyeth responds that there was no “bag” for the Borough to hold as of
    2006.    It denies that the Agreement is ambiguous, a point agreed to by the
    Borough. Notably, the extrinsic evidence was not relied upon by the trial court.
    The Borough’s extrinsic evidence may have shown that Wyeth could not abandon
    its obligations under the Agreement by selling the property, but that did not
    happen. In any case, the Borough’s extrinsic evidence did not establish a perpetual
    duration to the Agreement.
    d. Conclusion
    The extrinsic evidence is conflicting, but it is not necessary to resolve
    that conflict. We agree with the parties that the Agreement is not ambiguous. Its
    meaning can be determined by application of common law contract principles to
    the actual language of the Agreement.
    We conclude that the trial court erred in its construction of the
    Agreement. It gave no effect to the Background Clause and erred in holding that
    the recording of the Agreement established a perpetual duration. Such a duration
    requires express language in the contract. 
    Hutchinson, 519 A.2d at 390
    n.5. No
    such expression was made in the Agreement.
    19
    We conclude that the Agreement had a reasonable, not infinite,
    duration. As such, it was terminable at will by either party once Wyeth paid for its
    share of the capital costs and for its share of the operating and maintenance
    expenses incurred at the Goose Creek Plant that were “attributable to the treatment
    of [Wyeth’s] waste.” Wyeth argues that the Agreement terminated in 2006 when it
    stopped using the Goose Creek Plant. We hold, however, that termination of the
    Agreement required notice. This is consistent with Price v. 
    Confair, 79 A.2d at 226
    , where the contract found to be terminable at will did not terminate until one
    party notified the other that the termination right was being exercised. Wyeth’s
    notice to the Borough effected a termination of the Agreement on December 31,
    2011.10
    II. Excessive Charges
    Although the trial court acknowledged that “some of the Borough’s
    charges were not support[ed] by the contract,” it did not identify those overcharges
    or address Wyeth’s evidence thereon. Trial Court 1925(a) op. at 9. Wyeth’s
    essential complaint was that the Borough used “Wyeth as the Borough’s own
    personal piggy bank” to operate other departments of the Borough. Wyeth Brief at
    35.
    The terms of the Agreement required Wyeth to “pay its share of
    Operating and Maintenance Expenses of the Sewage Treatment Facilities.”
    Agreement, ¶8. Operating and Maintenance Expenses are defined as “all expenses
    10
    This termination date of December 31, 2011, disposes of the Borough’s counter-claim for
    damages arising from Wyeth’s non-payment of the 2012 and 2013 invoices. The Agreement was
    no longer in effect when the Borough sent those invoices. Accordingly, we need not consider
    Wyeth’s challenges to the trial court’s award and calculation of damages on the counter-claim.
    20
    required in operating and maintaining the Sewer System or the Sewage Treatment
    Facilities.”11 R.R. 990a (emphasis added). “Sewage Treatment Facilities” are
    defined as “the treatment facilities to be constructed at the site of the current Goose
    Creek waste water treatment plant.” R.R. 992a.
    Instead, Wyeth was charged for providing fire protection to Borough
    residents, purchasing gasoline for police cruisers, paying the salary of the
    Borough’s information technology director, and (as of 2012) replacing the HVAC
    system in the municipal building, which is not where the Sewer Department is
    even located.
    Wyeth also showed that the labor charges portion of the fixed costs
    included four wastewater pumping stations located in the Borough that never
    served Wyeth’s waste stream and are entirely unrelated to operation of the Goose
    Creek Plant. R.R. 270a-271a. Additionally, Wyeth presented evidence that the
    Borough has overstaffed the Goose Creek Plant, and the labor charges included
    personnel costs for two employees who were not needed to operate the Plant. R.R.
    364a-365a.
    The Borough responds that Paragraph 8 states that fixed costs include
    “sums payable to any person, which sums, under generally acceptable accounting
    or engineering practice constitute expenses of operation and maintenance.” R.R.
    2057a. This necessarily includes a charge for services provided by the Borough,
    such as fire and police protection. The cost of these services are apportioned by
    11
    Although the definition of Operating and Maintenance Expenses includes expenses
    attributable to the sewer system as a whole, Paragraph 8 of the Agreement provides that the
    Borough may only bill for the Operating and Maintenance Expenses associated with the Goose
    Creek Plant. R.R. 998a, ¶8.
    21
    comparing the Sewer Department’s revenue to the General Fund to develop a ratio
    that is used to apportion overhead expenses among Borough departments.
    As noted, the Agreement defines “Operating and Maintenance
    Expenses” to mean “all expenses required in operating and maintaining” the Goose
    Creek Plant. Agreement at 7; R.R. 990a. The Borough argues that Wyeth ignores
    the list of potential types of costs in Sections B through D of this definition, which
    include labor, repair, administration, supervision, engineering and taxes. R.R.
    991a. However, these sections do not modify the limitation that any such expenses
    must be “required in operating and maintaining ... the Sewage Treatment
    Facilities.” Agreement at 7; R.R. 990a. Wyeth argues that salaries of the fire
    department, gasoline for the police department, and the $500,000 cost of upgrading
    the municipal building HVAC system were not required to operate and maintain
    the Goose Creek Plant.
    None of this evidence was addressed by the trial court.                          It
    acknowledged there were overcharges but then waved the issue aside by
    concluding that Wyeth voluntarily made payment.12 This is troublesome for two
    reasons. First, the voluntary payment issue was raised sua sponte by the trial
    court.13 Second, Wyeth asserts that its payments were made under a mistake of
    12
    The trial court also concluded that Wyeth could not make out a case for unjust enrichment
    because, inter alia, the parties had a written agreement. Wyeth’s unjust enrichment claim would
    come into play only if the trial court, or an appellate court, were to conclude that the Agreement
    terminated in 2006.
    13
    The Borough denies that the voluntary payment doctrine was raised sua sponte by the trial
    court, invoking its statement of “New Matter”:
    21. Plaintiff’s claim sounding in unjust enrichment is barred by Plaintiff’s
    previous payments, pursuant to the ongoing obligations of the Agreement,
    through the third quarter of 2011.
    (Footnote continued on the next page . . . )
    22
    fact. Wyeth did not know what expenses the Borough had loaded into the fixed
    costs invoices until it took discovery in this case. Nothing in the record shows that
    Wyeth knew that the Borough’s fixed cost invoices included the labor for the pump
    stations, plant overstaffing, the components of the administrative transfer, a portion
    of Borough Wastewater Director Kevin Oakes’ salary, or any of the other charges
    Wyeth claims to be extra-contractual.           See Liss & Marion P.C. v. Recordex
    Acquisition Corp., 
    983 A.2d 652
    , 661 (Pa. 2009) (noting that the voluntary
    payment doctrine bars recovery only if the plaintiff had “knowledge of all the
    facts” regarding the applicable charges at the time payment was made). In any
    case, the voluntary payment theory is not relevant to Wyeth’s challenge to the
    propriety of the 2012 and 2013 bills because it has not paid those invoices.
    The trial court erred in its disposition of Wyeth’s challenge to the
    fixed cost invoices sent after 2006. During the time the Agreement was still in
    effect, i.e., 1984 to 2011, Wyeth did not pay invoices voluntarily. Wyeth did not
    waive its right to pay only those fixed cost invoices required to operate and
    maintain the Goose Creek Plant. Accordingly, we will remand the matter to the
    trial court for specific findings of fact and conclusions of law on Wyeth’s
    allegations that part of the Borough’s fixed cost invoices sent to Wyeth were extra-
    contractual because they exceeded what was required to operate the Goose Creek
    Plant.
    (continued . . . )
    R.R. 59a. This vague New Matter does not refer to the doctrine and it does not respond to
    Wyeth’s breach of contract claim at all. Because the Borough contends that payments were
    made “pursuant to the ongoing obligations of the Agreement,” the payments were not
    “voluntary.” Borough Brief at 51. The Borough never briefed the issue.
    23
    Conclusion
    For all the above-stated reasons, we reverse the trial court’s judgment
    in favor of the Borough’s breach of contract claim and against Wyeth’s request for
    a declaratory judgment that the Agreement terminated on December 31, 2011. We
    remand for further proceedings on Wyeth’s claim for breach of contract arising
    from the alleged over-charges for the fixed cost invoices from 2006 to 2011.
    ______________________________
    MARY HANNAH LEAVITT, Judge
    24
    IN THE COMMONWEALTH COURT OF PENNSYLVANIA
    Wyeth Pharmaceuticals, Inc., a           :
    Delaware Corporation, successor          :
    to Wyeth Laboratories Inc., a            :
    New York Corporation,                    :
    Appellant               :
    :
    v.                           :   No. 2116 C.D. 2014
    :
    Borough of West Chester and              :
    Pfizer Inc.                              :
    ORDER
    AND NOW, this 5th day of November, 2015, the order of July 14,
    2014, of the Court of Common Pleas of Chester County is REVERSED, and the
    matter is REMANDED for further proceedings consistent with the attached
    opinion.
    Jurisdiction relinquished.
    ______________________________
    MARY HANNAH LEAVITT, Judge